JPS61130596A - Construction method of tunnel wall surface - Google Patents

Construction method of tunnel wall surface

Info

Publication number
JPS61130596A
JPS61130596A JP59248599A JP24859984A JPS61130596A JP S61130596 A JPS61130596 A JP S61130596A JP 59248599 A JP59248599 A JP 59248599A JP 24859984 A JP24859984 A JP 24859984A JP S61130596 A JPS61130596 A JP S61130596A
Authority
JP
Japan
Prior art keywords
concrete
formwork
tunnel
guide rail
wall surface
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP59248599A
Other languages
Japanese (ja)
Other versions
JPH042758B2 (en
Inventor
星野 彰
鷹巣 征行
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyu Construction Co Ltd
Original Assignee
Tokyu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyu Construction Co Ltd filed Critical Tokyu Construction Co Ltd
Priority to JP59248599A priority Critical patent/JPS61130596A/en
Publication of JPS61130596A publication Critical patent/JPS61130596A/en
Publication of JPH042758B2 publication Critical patent/JPH042758B2/ja
Granted legal-status Critical Current

Links

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〈産業上の利用分野〉 本発明は、トンネル内の壁面コンクリートを施工するト
ンネル壁面の施工方法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION <Industrial Application Field> The present invention relates to a tunnel wall construction method for constructing wall concrete in a tunnel.

〈従来の技術〉 トンネル内のコンクリート壁等を施工するにあたり、各
種の吹付は工法が存在する。
<Conventional technology> There are various spraying methods for constructing concrete walls in tunnels, etc.

例えば、頻繁に行なわれるものとしては、セメントと骨
材を練りまぜて吹付はノズル先端まで送り、ここで水と
合流させて圧搾空気で吹付ける乾式1法がある。
For example, one method that is frequently used is the dry method, in which cement and aggregate are mixed and sprayed to the tip of a nozzle, where they are mixed with water and sprayed with compressed air.

く本発明が解決しようとする問題点〉 上記のような従来の工法には、次のような問題点が存在
する。
Problems to be Solved by the Present Invention> The conventional construction methods described above have the following problems.

(イ)コンクリートの跳返り量が多(経済的でない。(b) The amount of concrete rebound is large (not economical).

(ロ)吹付は面とノズルとの間に一定の間隔を必要とす
るので、トンネル内等では作業面積を占有してしまう。
(b) Since spraying requires a certain distance between the surface and the nozzle, it occupies the working area in tunnels and the like.

(ハ)他の作業と並行して行うことが難しく、全体の工
期が長くなる。
(c) It is difficult to carry out in parallel with other work, and the overall construction period becomes longer.

(ニ)空練り材料と水をノズル部分で混合するため、作
業員の熟練度により品質が左右される。
(d) Since the dry kneading material and water are mixed at the nozzle, the quality depends on the skill level of the worker.

(ホ)吹付は作業中に粉塵の発生が多く、作業環境を悪
化させ、労働安全衛生上問題が多い。
(e) Spraying generates a lot of dust during work, worsens the working environment, and poses many problems in terms of occupational safety and health.

く本発明の目的ン 本発明は上記のような問題点を解決するために成された
もので、粉塵の発生をおさえて作業環境の悪化を防止す
るとともに、作業面積を占有せず、他の作業と並行する
ことができるので作業の能率が上がり、なおかつ跳ね返
りが少なく経済的であり、更に高品質なコンクリート壁
の施工を行うことのできる、トンネル壁面の施工方法を
提供す−るを目的とする。
OBJECT OF THE INVENTION The present invention has been made to solve the above-mentioned problems.It suppresses the generation of dust to prevent deterioration of the working environment, does not occupy the working area, and does not require the use of other objects. The purpose of the present invention is to provide a method for constructing tunnel walls that can be performed in parallel with the work, increasing work efficiency, reducing bounce back, and being economical, as well as enabling construction of high-quality concrete walls. do.

〈問題点を解決するための手段〉 本発明では上記のような問題点を解決するために次のよ
うな手段を採用した。
<Means for Solving the Problems> In order to solve the above problems, the present invention employs the following means.

すなわち、トンネルの軸方向に移動可能でトンネルの断
面形状とほぼ相似形の支持枠の外周にガイドレールを取
り付け、細かく振動しつつ、充填したコンクリートに圧
迫を加える型枠板を有した型枠移動装置をガイドレール
に沿って移動させながらスランプの小さいコンクリート
を充填し、コンクリートに振動を与えつつ圧迫を加えて
良質のコンクリート壁を施工する。
In other words, a guide rail is attached to the outer periphery of a support frame that is movable in the axial direction of the tunnel and has a cross-sectional shape that is almost similar to the cross-sectional shape of the tunnel, and the formwork is moved using formwork plates that apply pressure to the filled concrete while vibrating finely. The device moves along guide rails to fill concrete with low slump, and applies pressure while vibrating the concrete to construct a high-quality concrete wall.

〈実施例ン 次に本発明の一実施例を図面にもとづいて説明するが、
まず本発明に使用する壁面コンクリート打設装置につい
て説明する。
<Example> Next, an example of the present invention will be described based on the drawings.
First, the wall concrete placing apparatus used in the present invention will be explained.

本発明に使用する壁面コンクリート打設装置は、トンネ
ルの軸方向に移動可能でトンネルの断面形状とほぼ相似
形の支持枠Sに取り付けたガイドレール1と、ガイドレ
ール1上をトンネルの内壁に沿って移動する型枠移動装
置2とで構成する。
The wall concrete placing device used in the present invention includes a guide rail 1 that is movable in the axial direction of the tunnel and is attached to a support frame S that has a cross-sectional shape that is almost similar to the cross-sectional shape of the tunnel. It consists of a formwork moving device 2 that moves by moving the formwork.

(イ)支持枠とガイドレール 支持枠Sは前枠と後枠とからなり対象のトンネルの断面
形状にほぼ相似形の構造体である。
(a) Support frame and guide rail The support frame S is a structure consisting of a front frame and a rear frame, and has a cross-sectional shape that is almost similar to the cross-sectional shape of the target tunnel.

そして、支持枠Sの進行方向側の前枠の外周にカイトレ
ール1を取り付ける。
Then, the kite rail 1 is attached to the outer periphery of the front frame of the support frame S on the advancing direction side.

ガイドレール1は、例えば断面形状がH形の鋼材等を支
持枠Sの外周に沿った形状に形成して前枠に取り付ける
The guide rail 1 is formed, for example, from a steel material having an H-shaped cross section into a shape along the outer periphery of the support frame S, and is attached to the front frame.

そしてガイドレール1には、その全長に亘つて、トンネ
ル内壁とほぼ平行に案内ラック1】を設ける。
A guide rack 1 is provided on the guide rail 1 almost parallel to the inner wall of the tunnel over its entire length.

案内ラック11は後述する型枠移動装置2のギヤ21が
噛合する歯板である。
The guide rack 11 is a toothed plate with which a gear 21 of a formwork moving device 2 to be described later meshes.

また、トンネルの床面の壁面付近に軸方向にレールを敷
設するなどして、支持枠Sがトンネルの軸方向に移動で
きるように構成する。
Further, the support frame S is configured to be movable in the axial direction of the tunnel by, for example, laying rails in the axial direction near the wall surface of the floor surface of the tunnel.

更に支持枠Sが進行する方向に対して後方に位置する後
枠の天端部分には圧入シリンダS1を設置して後述する
鋼矢板Yをガイドレール1と打設したコンクリート間に
圧入するよう構成する。
Furthermore, a press-fitting cylinder S1 is installed at the top end of the rear frame located at the rear with respect to the direction in which the support frame S moves, and a steel sheet pile Y, which will be described later, is press-fitted between the guide rail 1 and the poured concrete. do.

(ロ)型枠移動装置(第2図) 型枠移動装置2は側面にギヤ21を有する矩形の板体で
ある。
(b) Formwork moving device (FIG. 2) The formwork moving device 2 is a rectangular plate body having a gear 21 on the side.

そして内蔵する走行装置等によりガイドレール1の案内
ラック11と吻合したギヤ21に回転を与えて、ガイド
レール1に沿ってトンネル内周を移動する部材である。
It is a member that moves along the guide rail 1 on the inner periphery of the tunnel by applying rotation to the gear 21 anastomosed with the guide rack 11 of the guide rail 1 using a built-in traveling device or the like.

ギヤ21を案内ラック11に係止させて型枠移動装置2
をガイトレール1に設置した状態で型枠移動装置2のト
ンネル内壁側に型枠板22を設置する。
The formwork moving device 2 is moved by locking the gear 21 to the guide rack 11.
A formwork plate 22 is installed on the tunnel inner wall side of the formwork moving device 2 while the formwork plate 22 is installed on the guide rail 1.

型枠板22はトンネル壁面に平行な矩形の板体で、ガイ
ドレール1例の一辺に壁面側に向けてフランジ23を設
け、トンネル壁面と型枠板22間にコンクリートを充填
する空間を設けるよう構成する。
The form plate 22 is a rectangular plate parallel to the tunnel wall surface, and a flange 23 is provided on one side of the guide rail toward the wall surface to provide a space between the tunnel wall surface and the form plate 22 to be filled with concrete. Configure.

また型枠板22には、コンクリートを型枠板22とトン
ネル壁面間に充填するための吐出口24を開設し、そこ
にコンクリートポンプからのコンクリートバイブPを接
続する。
Further, a discharge port 24 for filling concrete between the form board 22 and the tunnel wall surface is provided in the form board 22, and a concrete vibe P from a concrete pump is connected thereto.

(ハ)型枠板の運動 型枠板22の型枠移動装置2例の面に、型枠板22に小
刻みな振動を与えるバイブレータ−25を付設してお(
(C) Motion of the formwork plate A vibrator 25 that gives small vibrations to the formwork plate 22 is attached to the surface of the two examples of the formwork moving device of the formwork plate 22.
.

また、型枠板22の型枠移動装置2側の面の上下部分に
は型枠移動装置2からのジヤツキ26を接続する。
Further, jacks 26 from the formwork moving device 2 are connected to the upper and lower portions of the formwork moving device 2 side surface of the formwork plate 22.

そして両者をゆっくり伸縮させることによって、型枠板
22がストロークの大きい往復動をするよう構成する。
By slowly expanding and contracting both, the form plate 22 is configured to reciprocate with a large stroke.

次に以上の各装置を使用してのトンネル壁面の施工方法
を説明する。
Next, a method of constructing a tunnel wall surface using each of the above devices will be explained.

(イ)支持枠の設置 まず対象のトンネル内に支持枠Sを設置する。(b) Installation of support frame First, a support frame S is installed inside the target tunnel.

すなわち、トンネルの床面の壁面付近に支持枠Sの移動
用のレールを敷設して、その前枠にガイドレール1を取
り付けた支持枠Sを載置する。
That is, a rail for moving the support frame S is laid near the wall surface of the floor surface of the tunnel, and the support frame S to which the guide rail 1 is attached is placed on the front frame of the rail.

(ロ)型枠移動装置の設置 支持枠Sのガイドレール1の一端の最下部に型枠移動装
置2を設置する。
(b) Installation of a formwork moving device The formwork moving device 2 is installed at the bottom of one end of the guide rail 1 of the support frame S.

すなわち、トンネル壁面の掘削方向側に型枠板22のフ
ランジ23を位置させて型枠移動装置2のギヤ21をガ
イドレール1のラック11に係止させる。
That is, the flange 23 of the form plate 22 is positioned on the excavation direction side of the tunnel wall surface, and the gear 21 of the form moving device 2 is locked to the rack 11 of the guide rail 1.

くハ)コンクリートの充填および型枠板の移動コンクリ
ートパイプPを通じて型枠板22の吐出口24からコン
クリートを吐出し他山と型枠板22間にスランプの小さ
いコンクリートを充填する。
(c) Filling concrete and moving the form plate Concrete is discharged from the outlet 24 of the form plate 22 through the concrete pipe P, and concrete with a small slump is filled between the other pile and the form plate 22.

そしてコンクリートの整型と並行して型枠移動装置2を
ゆっくりガイドレール1に沿って移動させ、、トンネル
壁面の内周に帯状のコンクリート壁を打設する。
Then, in parallel with the shaping of the concrete, the formwork moving device 2 is slowly moved along the guide rail 1 to cast a band-shaped concrete wall around the inner periphery of the tunnel wall surface.

なお型枠板22が降下する工程ではコンクリートが落下
しないように型枠板22の下に受は枠を突設しておく。
In addition, in the process of lowering the formwork plate 22, a frame is provided protrudingly below the formwork plate 22 to prevent concrete from falling.

このとき、予めコンクリート打設予定部分にコンクリー
ト壁の補強材等の鉄筋や鉄板等を設置しておくことも可
能である。
At this time, it is also possible to install reinforcing bars, iron plates, etc., such as reinforcing materials for concrete walls, in advance in the area where concrete is to be poured.

(ニ)型枠板の作動 型枠板22は、型枠移動装置2の移動と共に、バイブレ
ータ−25およびジヤツキ26によって一定の運動を開
始する。
(d) Operation of the formwork plate The formwork plate 22 starts a certain movement by the vibrator 25 and the jack 26 as the formwork moving device 2 moves.

すなわち、型枠板22はバイブレータ−25によって小
さく振動しつつ、上下のジヤツキ26をゆっ(り伸縮さ
せることによってストロークの大きい往復動を繰返す。
That is, the form plate 22 repeats a large stroke reciprocating motion by slowly expanding and contracting the upper and lower jacks 26 while being slightly vibrated by the vibrator 25.

(第3図) ストロークの大きい往復動は充填したコンクリートをお
しかため、一方バイブレータ−25による小さい振動は
コンクリートを密の状態にする。
(Fig. 3) The reciprocating motion with a large stroke compacts the filled concrete, while the small vibration by the vibrator 25 makes the concrete dense.

ジヤツキ26による波状の動きはストロークが極めて大
きく、バイブレータ−25にょる撮動は極めて小さいた
め、型枠板22は型枠としての機能を失うことはない。
The wave-like movement by the jack 26 has an extremely large stroke, and the movement by the vibrator 25 is extremely small, so the formwork plate 22 does not lose its function as a formwork.

(ホ)鋼矢板の圧入 スランプの小さいコンクリートを使用するので型枠移動
装置の移動速度を調整することによってコンクリートの
剥落を防止することができる。
(E) Since concrete with a small slump for press-fitting the steel sheet pile is used, spalling of the concrete can be prevented by adjusting the moving speed of the formwork moving device.

ただしトンネルの天端部分などでは、必要に応じて圧入
シリンダS1によって鋼矢板Yをガイドレール1と打設
したコンクリート間に圧入しておくことによってコンク
リートの剥離脱落を防止するよう構成する。
However, at the top end of the tunnel, etc., the steel sheet pile Y is press-fitted between the guide rail 1 and the poured concrete using a press-fitting cylinder S1 as necessary to prevent the concrete from peeling off and falling off.

(へ)ガイドレールの移動(第4図) ガイドレール1に沿ったトンネル内周に帯状にコンクリ
ートを打設したら、ガイドレール1を軸方向に型枠板2
2の幅だけ移動して隣接するトンネル壁面にコンクリー
ト壁を同じ要領で打設していく。
(v) Movement of the guide rail (Fig. 4) After pouring concrete in a band shape around the inner circumference of the tunnel along the guide rail 1, move the guide rail 1 in the axial direction to form plate 2.
Move by a width of 2 and pour a concrete wall on the adjacent tunnel wall in the same manner.

なお型枠移動装置2を二台用意してガイドレール1の両
端から互いに接近するように移動させながら行うことに
よって施工時間の半減をはがるこ 。
The construction time can be halved by preparing two formwork moving devices 2 and moving them toward each other from both ends of the guide rail 1.

ともできる。Can also be done.

(ト)その他の実施例 上記実施例では型枠移動装置の移動は型枠移動装置2の
ギヤ22とガイドレール1の案内ラック11の噛合わせ
によって行ったが、ワイヤの巻上げやローラーの噛合い
等の公知の機構を使用することも考えられる。
(G) Other Examples In the above embodiments, the formwork moving device was moved by the meshing of the gear 22 of the formwork moving device 2 and the guide rack 11 of the guide rail 1. It is also conceivable to use a known mechanism such as.

〈発明の効果〉 本発明は以上説明したようになるので次のような効果を
期待することができる。
<Effects of the Invention> Since the present invention has been described above, the following effects can be expected.

(イ)コンクリートの跳返りがなく、材料ロスをおさえ
ることができるので経済的である。
(a) It is economical because there is no rebound of concrete and material loss can be suppressed.

(ロ)型枠移動装置等はトンネル内周に沿ったガイドレ
ールと壁面間に位置するので、トンネルの内空部分を占
有することがなく、トンネルの内空部分を掘削やズリ出
し等の作業空間として使用できる。
(b) Formwork moving devices, etc. are located between the guide rail along the inner circumference of the tunnel and the wall surface, so they do not occupy the inner space of the tunnel, and can be used for excavation, scraping, etc. It can be used as a space.

したがってこれらの作業と並行して行うことができ工期
が短縮できる。
Therefore, it can be done in parallel with these works, shortening the construction period.

(ハ)型枠移動装置の移動中に、型枠板が大きな波状の
前後動と小さな振動をしているので密な品質の良いコン
クリート壁を打設することができる。
(c) While the formwork moving device is moving, the formwork plate makes large wave-like back and forth movements and small vibrations, so it is possible to cast a dense concrete wall of good quality.

(二〉作業中に粉塵の発生が少なく作業環境が良好であ
る。
(2) The work environment is good with little dust generated during work.

(ホ)コンクリートは湿式によるポンプ圧送によって行
うことができるので打設量を確実に把握でき打設時間の
短縮が可能である。
(e) Concrete can be poured by wet pumping, so the amount of concrete to be poured can be accurately determined and the time required for pouring can be shortened.

【図面の簡単な説明】[Brief explanation of drawings]

第1図:本発明の施工方法の説明同 第2因二本発明に使用するガイドレールおよび型枠移動
装置の説明図 第3図:型枠板の作動状態の説明図 第4図:装置の移動の説明図
Figure 1: Explanation of the construction method of the present invention Second factor: Explanation of the guide rail and formwork moving device used in the present invention Figure 3: Explanation of the operating state of the formwork plate Figure 4: Explanation of the device Illustration of movement

Claims (1)

【特許請求の範囲】 トンネルの軸方向に移動可能な支持枠の外周にガイドレ
ールを取り付け、 振動しつつ打設面に向かって大きな周期で前後動する型
枠を、 ガイドレールに沿って移動させながらコンクリートを打
設して行うことを特徴とする、 トンネル壁面の施工方法。
[Claims] A guide rail is attached to the outer periphery of a support frame that is movable in the axial direction of the tunnel, and the formwork, which vibrates and moves back and forth at large cycles toward the pouring surface, is moved along the guide rail. A construction method for tunnel walls, characterized by pouring concrete at the same time.
JP59248599A 1984-11-27 1984-11-27 Construction method of tunnel wall surface Granted JPS61130596A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP59248599A JPS61130596A (en) 1984-11-27 1984-11-27 Construction method of tunnel wall surface

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP59248599A JPS61130596A (en) 1984-11-27 1984-11-27 Construction method of tunnel wall surface

Publications (2)

Publication Number Publication Date
JPS61130596A true JPS61130596A (en) 1986-06-18
JPH042758B2 JPH042758B2 (en) 1992-01-20

Family

ID=17180514

Family Applications (1)

Application Number Title Priority Date Filing Date
JP59248599A Granted JPS61130596A (en) 1984-11-27 1984-11-27 Construction method of tunnel wall surface

Country Status (1)

Country Link
JP (1) JPS61130596A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01121499A (en) * 1987-11-05 1989-05-15 Toda Constr Co Ltd Method and device for executing tunnel
JPH0224495A (en) * 1988-07-14 1990-01-26 Teruo Shinohara Tunnel covering work using spraying concrete
JPH04128496A (en) * 1990-09-20 1992-04-28 Toda Constr Co Ltd Mold device
JP2012046891A (en) * 2010-08-24 2012-03-08 Ohbayashi Corp Tunnel lining concrete compaction apparatus

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01121499A (en) * 1987-11-05 1989-05-15 Toda Constr Co Ltd Method and device for executing tunnel
JPH0224495A (en) * 1988-07-14 1990-01-26 Teruo Shinohara Tunnel covering work using spraying concrete
JPH04128496A (en) * 1990-09-20 1992-04-28 Toda Constr Co Ltd Mold device
JP2012046891A (en) * 2010-08-24 2012-03-08 Ohbayashi Corp Tunnel lining concrete compaction apparatus

Also Published As

Publication number Publication date
JPH042758B2 (en) 1992-01-20

Similar Documents

Publication Publication Date Title
JPS61130596A (en) Construction method of tunnel wall surface
CN105818251B (en) The method and apparatus of cast concrete product
JPH0224495A (en) Tunnel covering work using spraying concrete
JPS61130558A (en) Movable mold frame apparatus
JPH024760B2 (en)
JP2003176697A (en) Tunnel lining method and lining device for mountain tunneling method
JP4798542B2 (en) Method and apparatus for removing bubbles in concrete
KR200202341Y1 (en) A tunnel steel materials mold concrete operation equipment
JPH05179894A (en) Sliding formwork
KR100380286B1 (en) A tunnel steel materials mold concrete operation equipment
CN220699946U (en) Bottom plate structure of cement prefabricated plate processing equipment
CN109162461A (en) A kind of lower boom plate placing installation of arch bar concrete pouring construction
US4751033A (en) Method of compacting concrete by mutually synchronized reciprocating movements
CN113107541B (en) Mold spraying concrete construction method and wet spraying trolley
CN220013284U (en) Concrete compaction device
FI60517C (en) REFERENCE TO A FRAME ORDER FRAMSTAELLNING AV IHAOLIGA ELEMENT AV BETONG
JPS62185962A (en) Solidifying casting construction method of concrete
JP2810749B2 (en) Lining equipment for tunnels, etc.
JPH08300340A (en) Method and apparatus for smoothing inner surface of centrifually molded hollow concrete product
SU1693175A1 (en) Concrete spreader
SU718580A1 (en) Form for erecting monolithic walls with simultaneous lining
CN117386123A (en) Method and device for reinforcing molding template of super-long platform wall structure
RU1813646C (en) Apparatus for molding pipes from concrete mix
JP2002038209A (en) Blast furnace trough construction device and construction method using the same
SU1740521A1 (en) Method of forming deformation seam in fresh-laid road bed concrete