JPS61130518A - Improvement of underwater ground - Google Patents

Improvement of underwater ground

Info

Publication number
JPS61130518A
JPS61130518A JP25054684A JP25054684A JPS61130518A JP S61130518 A JPS61130518 A JP S61130518A JP 25054684 A JP25054684 A JP 25054684A JP 25054684 A JP25054684 A JP 25054684A JP S61130518 A JPS61130518 A JP S61130518A
Authority
JP
Japan
Prior art keywords
leader
ground
ship
improvement
hull
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP25054684A
Other languages
Japanese (ja)
Other versions
JPH0378889B2 (en
Inventor
Keizo Kikui
菊井 敬三
Hideo Aiko
愛甲 秀夫
Minoru Aoi
青井 実
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP25054684A priority Critical patent/JPS61130518A/en
Publication of JPS61130518A publication Critical patent/JPS61130518A/en
Publication of JPH0378889B2 publication Critical patent/JPH0378889B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

PURPOSE:To exactly and accurately improve the ground under water by a method in which a leader is kept in the fallen form on the hull during the period when an improvement ship is transported to an improving area, and when improving work is made, the leader is raised and the shaft is slidably lowered. CONSTITUTION:An improving ship 2' is towed under a condition that a leader 4' is kept in the horizontal state to the hull 3' and an arm 25 on one end is fixed to the bracket 27 of the hull 3' by a pin 28. When an aimed improving area is reached, the ship 2' is anchored by a wire 48, the leader 4' in erected attitude is kept in a fixed and stable attitude, and preplanned improving work is made. The shaft 9 is penetrated with stirring into the ground 10 for improving the ground, and then drawn out of the ground 10. The anchoring of the ship 2' is released and the ship 2' is advanced by a given distance. The ship 2' can thus be towed smoothly to the desired improving area, and the leader can be easily erected on site.

Description

【発明の詳細な説明】 く産業上の利用分野〉 開示技術は、海中や川や湖等の水面下の地盤中に対し、
地盤改良船により粉体セメント等の改良材を気体輸送で
供給する等して地盤改良を行う技術分野に属する。
[Detailed description of the invention] Industrial application field> The disclosed technology can be applied to the ground beneath the water surface of the sea, rivers, lakes, etc.
It belongs to the field of technology that improves the ground by supplying improvement materials such as powdered cement by gas transport using a soil improvement ship.

而して、この発明は、該海中や河川や湖沼等の水面下の
地盤に対し、水面上から粉体セメント等の改良材を気体
輸送で送給する等のシャフトをスライドさせるリーダー
を搭載し、該リーダーに対1る改良工事のシャフトをス
ライドさせて水面下地盤に挿設した改良域を送給する地
盤改良方法に関する発明であり、特に、船体が口の字型
や双胴型等にされてその中央に水面に対する開放部を有
し、又、該開放部の左右に一対の軸受を有しており、該
軸受に対して方形枠型のリーダーを垂立面に沿って旋回
動自在に枢支し、該リーダーの先端の地盤貫入部を該開
放部を介して水面に出入り自在であるようにされ、リー
ダーと船体との間にはウィンチ等の起伏装置が設けられ
て所望改良域までの水上航行に際しては、該リーダーを
船体に対して水平に倒伏させて装置高さを充分に低くし
、重心を低くするようにし、又、目的改良域に於ける地
盤改良施工に際してはリーダーを起立させて水中を介し
、水面下の地盤に対しシャフトを貫入させて船体に設け
られた改良材プラントから改良材を所定にシャフトを介
して地盤中に空気輸送を介する等して送給し、地盤改良
を行うようにし、更には、船体とリーダーとの間に傾斜
姿勢装置を介装させてシャフトをして所定傾斜状態に雑
書して地盤に対し設定角度の斜め方向の改良工事を行う
ことが出来るようにした水中地盤改良方法に係る発明で
ある。
Therefore, this invention is equipped with a leader that slides a shaft to feed improvement materials such as powdered cement from above the water surface to the ground under the water surface such as the sea, rivers, lakes, etc. This invention relates to a ground improvement method in which a shaft for improvement work for the leader is slid to feed an improvement area inserted into the ground below the water surface. It has an open part to the water surface in the center, and a pair of bearings on the left and right sides of the open part, and a square frame-shaped leader can be freely pivoted along the vertical surface with respect to the bearings. The ground-penetrating part at the tip of the leader can be freely moved in and out of the water surface through the open part, and a luffing device such as a winch is installed between the leader and the hull to move the desired improvement area. When navigating on water up to The improved material is conveyed from the improved material plant installed in the ship's hull through pneumatic transport through the shaft into the ground through a shaft that is erected upright and penetrated into the ground below the water surface. The ground should be improved, and furthermore, a tilting position device should be interposed between the hull and the leader, the shaft should be placed in a predetermined tilted state, and the improvement work should be carried out diagonally at a set angle with respect to the ground. This invention relates to an underwater ground improvement method that allows for.

〈従来技術〉 周知の如く、軟弱地盤に対する改良工事は広く行われて
いるが、広い面積を有する湖沼や海岸での埋立てを行っ
て大規模な地盤改良を行うような場合には、陸上に於け
る地盤改良と異なり様々な制約や条件がある。
<Prior art> As is well known, improvement work on soft ground is widely carried out, but when large-scale ground improvement is carried out by reclamation in lakes and coastal areas with large areas, it is necessary to Unlike ground improvement, there are various restrictions and conditions.

而して、近時、陸上の地盤改良可能区域が少くなり、し
たがって、国土計画等による水中地盤改良域が拡大され
、上述制約や条件が払拭されて円滑な地盤改良が“正確
、且つ、迅速に行われることが求められるようになって
きた。
Recently, the area where ground improvement is possible on land has become smaller, and the area for underwater ground improvement has been expanded based on national land planning, etc., and the above-mentioned constraints and conditions have been eliminated, making it possible to carry out smooth ground improvement "accurately and quickly." There is a growing demand for this to be done.

例えば、陸上での地盤改良では、公害問題等の観点から
水ガラス系の薬液を用いる注入工法が広く行われている
が、地盤中の地下水等の問題があり、液系としての薬液
注入よりもセメント等の親水性の粉体の改良材を空気輸
送して地盤中に送給し、土壌と混合攪拌して地下水どの
反応を促進して凝結するような所謂噴射攪拌工法等が目
覚ましく開発されてきている。
For example, in ground improvement on land, injection methods that use water glass-based chemicals are widely used from the perspective of pollution problems, but there are problems with groundwater in the ground, so it is more effective than injection of liquid chemicals. There has been remarkable development of so-called injection agitation methods, in which hydrophilic powder improvers such as cement are pneumatically transported into the ground, mixed with the soil, and agitated to promote reactions in groundwater and coagulate. ing.

特に、粉体改良材輸送上の種々の技術的課題や輸送気体
の浮上後の処理についての数々のネックも解決ざれつつ
ある。
In particular, various technical issues in transporting powder improvers and numerous bottlenecks in post-floating treatment of transport gas are being resolved.

このように陸上に於ける地盤改良技術は、液系の薬液住
人工法から噴射攪拌工法へと移行しつつあるが、上述海
中や河川や湖沼に対する水中の地盤改良では猶のこと地
盤に対する水環境の点から液系の注入地盤改良よりも粉
体セメント等の改良材を送給する地盤改良技術が潜在的
にもマツチングすることになり、そのため、この導入が
強く求められるようになってきている。
In this way, ground improvement technology on land is transitioning from the liquid-based chemical-based construction method to the injection stirring method, but the above-mentioned underwater ground improvement for underwater, rivers, and lakes has not yet improved the water environment of the ground. From this point of view, ground improvement technology that feeds improvement materials such as powder cement is potentially more compatible than liquid-based injection ground improvement technology, and for this reason, there is a strong demand for its introduction.

したがって、上述の如く拡大するニーズに応える水中地
盤改良技術がより一層開発拡充ざれることが望まれるよ
うになってきた。
Therefore, it has become desirable to further develop and expand underwater ground improvement technology to meet the expanding needs as described above.

そして、当然のことではあるが、該種水中地型改良にお
いては工事用の台船等の船を改良域まで曳航したり、或
は、自走したりしてアンカーをとり、船体からシャフト
を水中に降下し、水面下の地盤に貫入して船上より改良
材を空気輸送して所定に供給するような態様で原則的に
とられる。
As a matter of course, in this type of underwater soil improvement, a construction barge or other ship is towed to the improvement area, or is self-propelled, takes the anchor, and removes the shaft from the hull. In principle, it descends into the water, penetrates the ground below the surface of the water, and pneumatically transports the improvement material from the ship to supply it to a specified location.

そこで、これまで一般にとられてきた地盤改良船による
地盤改良の態様を、第23、24図によって略説すると
、所定の改良域の水面1に対し、地盤改良船2を曳航、
或は、自走により位置させ、その船体3をアンカーして
セットさせ、該船体3上に予め固設されているやぐらタ
イプのリーダー4に対し、ガイドケーシング5を併設さ
せ、該リーダー 4から水中にサブリーダー6をくしざ
し式に下延させ、これに沿ってヘドロ等の軟弱層7に対
し貫入装置8を有するシャフト9をして挿入し、地盤中
に貫入させて改良材プラント11により改良材タンク1
2かう所定の改良材を上記ガイドシ、フト 5を介して
シャフト 9により地盤10中に送給して所定の地盤改
良を行うようにしている。
Therefore, the mode of soil improvement using a soil improvement boat that has been generally adopted up to now will be briefly explained with reference to Figures 23 and 24.
Alternatively, it can be positioned by self-propulsion, anchored and set with the hull 3, a guide casing 5 attached to a tower-type leader 4 fixed in advance on the hull 3, and a guide casing 5 placed in the water from the leader 4. The sub-leader 6 is extended downward in a comb-like manner, and the shaft 9 having the penetration device 8 is inserted into the soft layer 7 such as sludge along this, and the shaft 9 is penetrated into the ground and improved by the improvement material plant 11. material tank 1
Two predetermined improvement materials are fed into the ground 10 by a shaft 9 via the guide shaft and foot 5 to perform predetermined ground improvement.

〈発明が解決しようとする問題点〉 しかるに、船体3上に設けられたリーダー4等の施設は
充分な剛性を有して付設されているものの、水中に下延
されているサブリーダー6は上述の如く、くしざし式の
所謂カンチレバ一方式であるために充分な剛性がとれず
、したがって、理論的にはリーダー4から鉛直に下延し
、シャフト9や貫入装置8をして静的に貫入させ、改良
材送給作業が行われ得るようにされてはいるが、地盤改
良方法自体が相当な重囲を有し、慣性力が大きくアンカ
ーをとられてはいても、作業中の波浪の影響による揺動
や施工中の諸装置の撮動等により、サブリーダー6と改
良船2との相対位置が揺動撮動して変化し、その結果、
正確な改良杭等が出来ない欠点があり、特に、水中に於
ける施工状態の確認行為が出来ないこと等から施工精度
が粗くなるという不具合があった。
<Problems to be Solved by the Invention> However, although the facilities such as the leader 4 provided on the hull 3 are attached with sufficient rigidity, the sub-leader 6 extending downward into the water has the above-mentioned problems. Since it is a so-called cantilever one-way type of comb type, it cannot have sufficient rigidity, so theoretically it extends vertically from the leader 4 and penetrates statically using the shaft 9 or the penetrating device 8. However, the ground improvement method itself has a considerable heavy enclosure, and the inertia force is large. The relative position of the sub-leader 6 and the improved ship 2 changes due to the shaking due to the impact and the photography of various equipment during construction, etc., and as a result,
There was a drawback that accurate improved piles etc. could not be made, and in particular, construction accuracy was poor because it was not possible to confirm the construction status underwater.

一方、船体3上に組立固定されるリーダー4については
、相当程度その高さがあり、特に、大規模工事用の改良
船2では、その高さが極めて大きく、改良材プラント1
1や操作部13等に比べると、比較にならぬほど大きい
ために重心が相当高く、極めて不安定である難点があり
、曳航や走1行に際しての動揺が大きく、そのため、船
体を更に広くするためにコスト高になる不利点があり、
更には、ドックや船体組付は岸壁から所定の目的改良域
に曳航や自走するプロセスにて河口や入り江に設置され
ている吊り橋等の橋に該リーダーが干渉したり、港湾施
設に干渉してしまう虞があるために、その高さが制限さ
れるというマイナス点があった。
On the other hand, the leader 4 that is assembled and fixed on the hull 3 has a considerable height, and especially in the improved ship 2 for large-scale construction, the height is extremely large, and the improved material plant 1
Since it is incomparably larger than 1 and the operation part 13, the center of gravity is quite high and it is extremely unstable, causing a lot of sway when being towed or traveling, so the hull must be made wider. This has the disadvantage of high costs,
Furthermore, during docking and hull assembly, the process of towing or self-propelling from the quay to the designated target improvement area may cause the leader to interfere with bridges such as suspension bridges installed at river mouths or inlets, or interfere with port facilities. There was a negative point in that the height was limited because there was a risk that the

そのため、本来的な目的の水中地盤改良工事の規模が制
限をされるという拘束状態が生じることになり、陸上施
工に対比するに、大幅な立ち遅れを生じるという好まし
くない制約があった。
As a result, the scale of underwater ground improvement work, which was originally intended to be carried out, was restricted, which was an undesirable constraint that caused a significant delay compared to land-based construction.

特に、粉体噴射攪拌工法等のセメントを空気輸送する等
の工法では陸上施工では著しい成果が得られるだけにそ
の施工中の精度が高く求められ、したがって、施工の上
)本不具合が良好な施工を阻害するという不具合がある
In particular, construction methods such as the powder injection stirring method in which cement is transported pneumatically require high accuracy during construction, as remarkable results can be obtained in land construction. There is a problem that it obstructs the

又、これらの制約や悪条件に耐えて所望サイズの改良船
2を建造するに際しても、該リーダーは相当に高いため
に、建造は勿論のこと、保守点検整備等の際に所謂高所
作業が避けられず、危険性を伴い、又、高所での支持の
作業精度も完全さが期し難くなるというデメリットもあ
った。
In addition, even when building an improved ship 2 of a desired size that can withstand these restrictions and adverse conditions, the leader is quite expensive, so not only construction but also so-called high-altitude work is required during maintenance, inspection, etc. This is unavoidable and involves danger, and it also has the disadvantage that it is difficult to ensure perfect accuracy in supporting work at high places.

又、これらの作業において高所作業という制約がある他
に、多くの部位での同時併行的な作業が行われず、作業
能率が悪いという能率低下のマイナス点もあった。
Furthermore, in addition to the constraints of working at heights, there was also the negative point of reduced efficiency in that many parts of the work could not be performed simultaneously, resulting in poor work efficiency.

この発明の目的は上述従来技術に基づく極めて需要が高
く、又、本来的な地盤に対する粉体噴射攪拌地盤改良工
事の施工技術が数々の優れて点を伴って開発されている
にもかかわらず、単に船体に対するリーダーの阻害条件
があるために、これらを拘束している地盤改良船による
水中地盤改良の問題点を解決すべき技術的課題とし、施
工時には、リーダーが船体上は勿論、水中に下延する部
分についても充分な剛性を有して本来的な地盤改良が確
実に、且つ、正確に行うことが出来るようにし、就中、
高精度好効果の粉体、噴射改良等の工事が成され、しか
も、目的改良域までの曳航や自走に際しては充分に低く
、安定した姿勢がとれるリーダーとし、該曳航や走行が
橋や沿岸施設に何等支障を与えないようにし、又、船の
建造や保守点検がし易く、又、岸壁での付帯工事等もし
易く出来るようにして建設産業における水中地盤改良技
術利用分野に益する優れた地盤改良方法を提供せんとす
るものである。
The purpose of this invention is based on the above-mentioned prior art and is in extremely high demand, and even though the construction technology of powder injection agitation ground improvement work on the original ground has been developed with many excellent points, The problem of underwater ground improvement using a soil improvement ship, which is simply due to the obstruction of the leader to the ship's hull, is a technical issue that must be solved, and during construction, the leader must not only be placed on the ship's hull, but also be lowered into the water. The extending parts should also have sufficient rigidity so that essential ground improvement can be carried out reliably and accurately, and above all,
Work has been carried out to improve high precision and effective powder injection, and the leader is low enough to maintain a stable attitude when towing or self-propelling to the target improvement area, and the leader is designed to be able to maintain a stable attitude when towing or traveling to the target improvement area. It is an excellent method that benefits the field of underwater ground improvement technology application in the construction industry by not causing any hindrance to facilities, making it easier to construct ships, maintain and inspect them, and make it easier to carry out incidental work on quays. The purpose is to provide a ground improvement method.

〈問題点を解決するための手段・作用〉上jボ目的に沿
い先述特許請求の範囲を要旨とするこの発明の構成は、
前述問題点を解決するために、最も高い姿勢をとるリー
ダーを船体に対し倒伏状態で定位買作業を、且つ、諸作
業を同時併行的に行うようにし、安全で高能率に行い、
而して、水中での地盤改良を行うに際し、改良船を目的
改良域までの曳航や自走に際しては、その長いリーダー
を船体に平行に倒伏させた状態のまま、即ち、低い姿勢
で重心が低く安定した姿勢で風や波浪の影響を受けず、
したがって、揺動が少く、又、河口や入り江等に設けら
れている吊り橋や港湾施設等にも回答干渉することなく
スムースに移動出来、而して、目的改良域に到達後、船
体にアンカーをとり、該リーダーをその船体に設けられ
た一対の軸受を介して垂立面に平行に上下方向旋回させ
て、該軸受より下側のリーダーについては船体の略中火
に設けられた開口等の開放部より水中に臨ませ船体から
所定に下延するようにして船体の上下部に於いても充分
な剛性を有するようにし、そこで、該リーダーに沿って
シャフトをスライド降下させて水面下の地盤に貫入させ
、船体上の改良材プラントより改良材を気体輸送等を介
し所定に地盤中に送給して杭造成等の地盤改良を行い、
このプロセスにても該船体上下のリーダーが充分な剛性
を有して延設されるために、シャフトが所望通りに地盤
に貫入状態を保ち、したがって、正確な地盤改良工事が
高精度に行われるようにし、粉体、噴射攪拌工事による
水中地盤改良が設計通りに行われ、更に、船体とリーダ
ーとの間に介装された傾斜姿勢装置が設計に従ってリー
ダーを船体に対し所望角度に傾斜した姿勢を維持固定す
るようにし、それによって水面下の地盤に対する斜め杭
等の傾斜地盤改良も回答支障なくスムースに行えるよう
にし、この間、工事の態様によって軸受を船体に対し水
平方向、或は、上下方向、更には、旋回裡に移動し、又
、交換するようにして船体に対するリーダーの姿勢位置
を最適状態に保つことが出来るようにした技術的手段を
講じたものである。
<Means/effects for solving the problems> In accordance with the above object, the structure of the present invention, which is summarized in the above-mentioned claims, is as follows:
In order to solve the above-mentioned problems, the leader, who takes the highest position, is placed in a reclined position with respect to the ship's hull, and various tasks are carried out simultaneously, allowing safe and highly efficient work.
Therefore, when performing underwater ground improvement, when towing or self-propelling the improved ship to the target improvement area, the long leader is laid down parallel to the ship's hull, that is, the center of gravity is in a low position. With a low and stable posture, it is unaffected by wind and waves,
Therefore, there is little rocking, and it is possible to move smoothly without interfering with suspension bridges and port facilities installed at river mouths and inlets. The leader is rotated vertically parallel to the vertical plane via a pair of bearings provided on the hull, and the leader below the bearings is placed in an opening or the like provided at approximately the middle of the hull. The open part faces into the water and extends downward from the hull at a predetermined distance so that the upper and lower parts of the hull have sufficient rigidity.Then, the shaft is slid down along the leader to connect the ground beneath the water surface. The improvement material is penetrated into the ground and delivered from the improvement material plant on the ship's hull into the ground via gas transport, etc., to perform ground improvement such as building piles.
In this process, the leaders above and below the hull are extended with sufficient rigidity, so the shaft maintains its penetration into the ground as desired, allowing accurate ground improvement work to be carried out with high precision. Underwater ground improvement using powder and injection agitation work was carried out as designed, and furthermore, the tilting position device installed between the ship's hull and the leader tilted the leader at the desired angle relative to the ship's hull in accordance with the design. As a result, improvements to the sloped ground such as diagonal piles on the ground below the water surface can be carried out smoothly without any problems. Furthermore, technical measures have been taken to enable the leader to be moved and replaced while turning, thereby maintaining the leader's attitude and position relative to the ship's hull in an optimal state.

〈実施例〉 次に、この発明の実施例を第1〜22図に基づいて説明
すれば以下の通りである。尚、第23.24図と同一態
様部分は同一符号を用いて説明するものとする。
<Example> Next, an example of the present invention will be described below based on FIGS. 1 to 22. 23 and 24 will be described using the same reference numerals.

第1.2図に示す態様において、2′は地盤改良船であ
り、当該実施例においては海水中の地盤10に対する改
良材としての粉体セメントを空気輸送してこれまでに開
発されてきた最新技術の粉体噴fJJ1g!拌工法によ
る高精度の水中地盤改良を行うための工事に供せられる
ものであって、その船体3′は口の字型(後述する如く
双胴船タイプでも含まれる。)に形成され、その略中央
部には開放部としての開口14が開設されており、その
周囲には粉体セメントの改良材の輸送用のコンプレッサ
等を装備した改良材プラント11、これらにパイプ接続
されているセメントタンク12.12・・・、及び、操
作部13、エンジン等の機器等のハウジング15が設け
られている。
In the embodiment shown in Fig. 1.2, 2' is a soil improvement ship, and in this embodiment, it pneumatically transports powdered cement as an improvement material for the ground 10 in seawater. Technical powder injection fJJ1g! It is used for construction work to perform high-precision underwater ground improvement using the mixing method, and its hull 3' is formed in the shape of a mouth (also included in the catamaran type, as described later). An opening 14 as an open part is opened approximately in the center, and around the opening 14 there is an improved material plant 11 equipped with a compressor, etc. for transporting improved material for powdered cement, and a cement tank connected to these by pipes. 12, 12..., an operating section 13, and a housing 15 for equipment such as an engine.

而して、該船体3′の間口14の両側には各々一対のレ
ール16.16・・・が長手方向に沿って敷設されてお
り、該両側に於いては、レール16.16にローラ17
.17・・・を介して交換自在の軸受18.18が長手
方向移動可能に設けられている。
A pair of rails 16, 16... are laid along the longitudinal direction on both sides of the frontage 14 of the hull 3'.
.. 17... are provided with exchangeable bearings 18, 18 which are movable in the longitudinal direction.

又、各軸受18に対しては、第2.8図に示す様に、油
圧シリンダ19がそのロンドの先端をビン20を介して
枢支され、又、その後端は各々レール16.16間に長
手方向に沿って設定ピッチで有段的に穿設されたネジ孔
21.21・・・に対して選択的に図示しないネジビン
を介して連結解離されるようにされており、したがって
、各軸受18は該油圧シリンダ19の尺取り史的反復動
作により各レール16に沿って長手方向進退調節自在に
されている。
Further, as shown in FIG. 2.8, for each bearing 18, a hydraulic cylinder 19 is pivotally supported at its rond end via a pin 20, and its rear end is connected between each rail 16 and 16. Screw holes 21, 21, etc., which are bored stepwise at set pitches along the longitudinal direction, are selectively connected and disconnected via screw pins (not shown), so that each bearing 18 can be adjusted to move forward and backward in the longitudinal direction along each rail 16 by the repetitive movement of the hydraulic cylinder 19.

そして、該軸受18.18に対し、軸22.22を一体
的に外延固定された方形枠型の平面視口の字型のリーダ
ー4′が垂立面に対して旋回動自在、即ち、倒伏起立自
在に枢支支承されて設けられている。
A leader 4' having a rectangular frame shape and having an opening in plan view has a shaft 22.22 integrally fixed to the bearing 18.18, and is rotatable with respect to a vertical plane, that is, can be laid down. It is pivotably supported so that it can stand up freely.

而して、当該実施例においては、第1.2図に示す様に
、横方の補強桁23.23を介して一対の断面円形の所
定長さの短パイプ24.24が1ユニツト、にされてフ
ランジ25.25・・・を介して設定長さのリーダー4
′に組付けされて、該リーダー4′の両端にはアーム2
6.26を渡設して全体的には方形に枠組み形成される
ようにされている。
In this embodiment, as shown in Fig. 1.2, a pair of short pipes 24, 24 with a circular cross section and a predetermined length are connected to one unit via horizontal reinforcing girders 23, 23. Set length leader 4 through flange 25.25...
', and arms 2 are attached to both ends of the leader 4'.
6.26 are installed across the building to form a rectangular framework overall.

したがって、各ユニットのフランジ25.25・・・を
介しての継足し、或は、取外しにより、改良船2′の建
造、或は、組替え時にリーダー4′の所定長さに形成さ
せることが出来るようにされている。
Therefore, by adding or removing each unit via the flanges 25, 25, etc., it is possible to form the leader 4' to a predetermined length when building an improved ship 2' or rearranging the unit. It is like that.

そして、当該実施例においては、第1.2図に示す様に
、リーダー4′の一方側が前記開口14の基端側に臨ま
されるようにされ、他方側のアーム26は水平に倒伏状
態にある姿勢では、船体3′に設けられたブラケット2
7に対して取外し可能なビン28で固定されて旋回不能
にされている。
In this embodiment, as shown in FIG. 1.2, one side of the leader 4' faces the proximal end of the opening 14, and the arm 26 on the other side lies horizontally. In one position, the bracket 2 provided on the hull 3'
7 with a removable pin 28 and is prevented from rotating.

而して、船体3′の開口14の一方側中央寄りに設けら
れたスタンド29の上部にブラケット36に対してビン
枢支され、起立、及び、倒伏自在にされると共に図示し
ないストッパにより当該起立、及び、倒伏姿勢を維持さ
れるサブスタンド31の上端に設けられたプーリ32を
介して該スタンド29の後部に設けられたウィンチ33
からのワイヤ34が、該リーダー4′の他端側のアーム
26に係止されて起伏装置35を形成しており、該ウィ
ンチ33を起動することにより、該リーダー4′をして
軸22.22、及び、軸受18.18を介してこれを中
心として船体3′上に旋回起立するようにさせることが
出来るようにされている。
A stand 29 provided near the center on one side of the opening 14 of the hull 3' is pivotally supported to a bracket 36 at the top of the stand 29, and can be raised and lowered freely, and can be raised or lowered by a stopper (not shown). , and a winch 33 provided at the rear of the stand 29 via a pulley 32 provided at the upper end of the sub-stand 31 that is maintained in a collapsed position.
A wire 34 from the leader 4' is engaged with the arm 26 at the other end of the leader 4' to form a hoisting device 35, and by activating the winch 33, the leader 4' is raised to the shaft 22. 22 and bearings 18, 18, it is possible to pivot and stand up on the hull 3' about this.

そして、該リーダー4′の補強桁23に沿って設けられ
ると共に該リーダー4′に沿ってスライド可能な横設ブ
ラケット36に固定された軸受37.37・・・とこれ
に対向する側の他端側のアーム26に設けられた油圧モ
ータ等のロータリ一式の駆@機構38.38・・−との
間には前記粉体セメントの改良材を空気輸送して水中地
盤粉体噴射攪拌工事を行うシャフト9.9・・・が回動
可能に支承されている。
Bearings 37, 37, etc. are provided along the reinforcing beam 23 of the leader 4' and are fixed to a horizontal bracket 36 that is slidable along the leader 4', and the other end of the bearing 37, 37 on the side opposite thereto. The powder cement improvement material is pneumatically transported between the drive mechanism 38, 38, etc. of a rotary set such as a hydraulic motor installed on the side arm 26, and underwater ground powder injection agitation work is carried out. Shafts 9.9... are rotatably supported.

そして、該各シャフト9の先端には上記空気輸送粉体セ
メントを地盤10中に噴出して土壌と粉体セメントを攪
拌混合する攪拌羽根39が所定段数に一体固定されて側
方延設されており、又、基端側には上記改良材プラント
11に対して図示しない空気輸送パイプで接続される周
知のスイーベルジョイント40が設けられている。
Further, at the tip of each shaft 9, stirring blades 39 are integrally fixed at a predetermined number of stages and extend laterally, for spouting the pneumatically transported powder cement into the ground 10 and stirring and mixing the soil and powder cement. Further, a well-known swivel joint 40 is provided on the base end side, which is connected to the improvement material plant 11 by an air transport pipe (not shown).

尚、上記リーダー4′の先端両側には遠隔操作により適
宜手段によりリモートコントロール式に伸縮自在にされ
た油圧式のスパッド41.41が設けられており、第2
図に示す様に、船体3′に対して水平に倒伏させた状態
では縮退されており、起立されて地盤改良施工に際して
は突出されて地盤10に突き刺さって該リーダー4′を
水中に於いて、第13図に示す様に、地g!110に対
しリーダー4′の安定起立姿勢を維持するようにされて
いる。
Furthermore, on both sides of the tip of the leader 4', there are provided hydraulic spuds 41, 41 which are telescopically telescopic and retractable by appropriate means by remote control.
As shown in the figure, when the leader 4' is laid down horizontally with respect to the hull 3', it is retracted, and when it is erected and used for ground improvement work, it is protruded and pierced into the ground 10, and the leader 4' is placed in the water. As shown in Figure 13, the ground g! 110 to maintain a stable standing posture of the leader 4'.

又、上記リーダー4′の他方端のアーム26に設けられ
たウィンチ42は、該リーダー4′に対してスライド自
在に設けられた前記ブラケット36に設けられたブー9
43との間にワイヤ44を張設して、第13図に示すリ
ーダー4′の起立状態において、シャフト9.9・・・
に対する引き上げ機構を形成している。
A winch 42 provided on the arm 26 at the other end of the leader 4' is attached to a boot 9 provided on the bracket 36 slidably provided with respect to the leader 4'.
43, and in the upright state of the leader 4' shown in FIG. 13, the shafts 9.9...
It forms a pulling mechanism for the

そして、該ブラケット3Bの他端に設けられた他のウィ
ンチ45と、上記リーダー4′の基端側のアーム26に
設けられたプーリ46との間にはワイヤ41が張設され
て、同じく第13図に示す様に、リーダー4′が起立姿
勢にされている状態で、シャフト9.9・・・の地盤1
0に対する強制貫入機構とされている。
A wire 41 is stretched between another winch 45 provided at the other end of the bracket 3B and a pulley 46 provided on the arm 26 on the base end side of the leader 4'. As shown in Figure 13, with the leader 4' in the upright position, the ground 1 of the shaft 9.9...
It is said to be a forced penetration mechanism for zero.

而して、上記改良船2′の建造に際しては、第3.4図
に示す様に、造船所の岸壁にて予め完成された船体3′
に対しリーダー4′を岸壁に設けられた小型のクレーン
等によって類バイブ24.24、及び、補強桁23.2
3等を介してフランジ25.25・・・等により水平姿
勢のままで船体3′の上に横組付は状態で同時併行的に
所定段数、即ち、所定長さのリーダー4′を建造する。
Therefore, when constructing the improved ship 2', as shown in Figure 3.4, the hull 3' was completed in advance at the quay of the shipyard.
Meanwhile, the leader 4' is attached to the similar vibrator 24.24 and the reinforcing girder 23.2 by a small crane or the like installed on the quay.
A leader 4' of a predetermined number of stages, that is, a predetermined length, is constructed simultaneously and horizontally on the hull 3' in a horizontal position through flanges 25, 25, etc. .

勿論、この間、該リーダー4′の軸22.22の軸受1
8.18に対する組付けやそのローラ17.17・・・
のレール16.16・・・に対1゛るセット等も同様に
して同時併行的に行う。
Of course, during this time, the bearing 1 of the shaft 22, 22 of the leader 4'
8. Assembly to 18 and its roller 17.17...
Similarly, the sets for the rails 16, 16, etc. are performed concurrently.

したがって、これらのリーダー4′の組付は建造作業は
全て低姿勢で行われるために、高所作業はなく、作業能
率が向上し、しかも、安全な状態で出来、そのうえ、各
組付けや溶接等の作業もし易いために精度が上り、検査
等も正確に行える。
Therefore, since all construction work for assembling these leaders 4' is done in a low position, there is no need for work at heights, work efficiency is improved, and it can be done safely. Because it is easy to perform such operations, accuracy is increased, and inspections can be performed accurately.

そして、各作業は同時併行的に効率良く行える。Each task can be performed simultaneously and efficiently.

勿論、他の改良材プラント11や操作部13、改良材タ
ンク12等の建造作業とも同時併行的に行うことも出来
る。
Of course, the construction work of other improvement material plants 11, operation section 13, improvement material tank 12, etc. can also be carried out simultaneously.

このようにして、建造された改良船2′は、第3.4図
に示す様に、リーダー4′を船体3′に対して水平状態
にされ、その、−万端のアーム26を船体・3′のブラ
ケット27に対し、ビン28で固定して曳航、或は、走
行等により適宜水上輸送に供し、目的改良域まで行く。
The improved ship 2' constructed in this way has the leader 4' horizontal to the hull 3', as shown in FIG. It is fixed to the bracket 27 with a bin 28 and transported by water, such as towing or traveling, to the target improvement area.

而して、その間、第3.4図、即ち、第1.2図に示す
様に、リーダー4′は建造時の姿勢の状態のままで船体
3′に対して水平状態にあり、又、スタンド29のサブ
スタンド31も倒伏姿勢にされて図示しないストッパに
より固定されているために、操作部13の高さ以上には
ならず、したがって、河口や入り江等の吊り橋等の相当
に低い橋等とも干渉せず、或は、港湾のデツキやクレー
ン等の突出する他の1M設にも干渉することなく航行出
来、しかも、リーダー4′が倒伏水平姿勢にあるため、
中心は極めて低く、波浪や風の影響も受けず、動揺や傾
動はなく、安全に歩行出来、したがって、そのスピード
を相当に上げてもほとんど支障はなく、そのため、目的
改良域まで速やかに安定して海上輸送することが出来る
During this time, as shown in Figure 3.4, that is, Figure 1.2, the leader 4' remains in the attitude at the time of construction and remains horizontal with respect to the hull 3'; Since the sub-stand 31 of the stand 29 is also in a collapsed position and fixed by a stopper (not shown), the height does not exceed the height of the operating part 13, and therefore, it cannot be used on a considerably low bridge such as a suspension bridge at an estuary or an inlet. It is possible to navigate without interfering with other protruding 1M facilities such as port decks and cranes, and since the leader 4' is in a horizontal position,
The center is extremely low, it is not affected by waves or wind, it does not sway or tilt, and it can be walked safely.Therefore, there is almost no problem even if the speed is increased considerably, and as a result, it quickly stabilizes to the target improvement area. It can be transported by sea.

そして、目的改良域に到達すると、詳しくは後述するが
、第5図に示す様に、ワイヤ48で適宜アンカーし、垂
立姿勢のリーダー4′によって地盤改良を行うに際して
は、後述詳説するようにスパッド41.41を遠隔操作
により地盤10に対して突き刺し、リーダー4′を固定
姿勢に、即ち、改良船2′をも固定するようにして風や
波浪によってほとんど影響されず、又、安定した姿勢を
維持して所定の地盤改良を行う。
When the target improvement area is reached, as shown in Fig. 5, the ground is improved by properly anchoring it with a wire 48 and using the leader 4' in a vertical position, as will be described in detail later. The spuds 41 and 41 are pierced into the ground 10 by remote control, and the leader 4' is fixed in a fixed position, that is, the improved ship 2' is also fixed, so that it is almost unaffected by wind and waves and has a stable position. and perform the prescribed ground improvement.

又、該地盤改良工事は上下方向垂立姿勢で行われるとは
限らず、設計によっては施工を第6図に示す様に、斜め
姿勢で斜杭打設等を行う場合があるが、この場合には次
述詳説するように、リーダー4′を起立しながら所定姿
勢に傾斜したところでスパッド41を地盤10に対して
突き刺し、ワイヤ48を介してのアンカーとの協働によ
り当該所定角度の姿勢をリーダー4′にとらせて斜め施
工による地盤改良を行う。
In addition, the ground improvement work is not necessarily carried out in a vertical position; depending on the design, the construction may be performed by driving diagonal piles in an oblique position, as shown in Figure 6. As detailed below, the spud 41 is stuck into the ground 10 when the leader 4' is erected and tilted to a predetermined posture, and the posture at the predetermined angle is maintained by cooperating with the anchor via the wire 48. Ground improvement is carried out by diagonal construction using leader 4'.

而して、上述施工の原理態様を詳述すると、まず、改良
域に到達して、第5図に示す様に、ワイヤ48により改
良船2′をアンカーした後、リーダー4′ のアーム2
6とブラケット27のビン28を除去してリーダー4′
に対する拘束を解き、船体3′の接部に設けられたスタ
ンド29のサブスタンド31を、第1図実線に示す様に
4、垂立状態にして図示しないストッパにより固定し、
各軸受18に設けた油圧シリンダ19の基端側の孔を、
第8図に示す様に、船体3′に設けられたネジ孔との間
に交互に抜き刺しし、即ち、油圧シリンダ19を伸縮さ
せてその都度ネジビンを抜刺し離脱固定することにより
、所謂尺取り史的動作を介して各軸受18を船体3′の
長手方向に沿って移動させ、各シャフト9の先端の潰痒
羽根39が充分に船体3′の開口14に臨まされて侵入
し易い位置姿勢にし、そこで、船体3′の後端に設けら
れたウィンチ33を起動することにより、ワイヤ34が
リーダー4′の一方端のアーム26を引き、したがって
、リーダー4′は各軸受18に対しその軸22を介して
これを中心に旋回動して起立姿勢に移り、ウィンチ33
の連続動作によりリーダー4′は起立し、所定角度にな
ったところで、先述第6図に示す傾斜施工が必要な場合
には当該所定傾斜角度でウィンチ33を停止し、スパッ
ド41を地!1l1110に適宜遠隔操作により貫入さ
せ、リーダー4′の当該設定角度の傾斜姿勢を固定する
To explain in detail the principle of the above-mentioned construction, first, after reaching the improved area and anchoring the improved ship 2' with the wire 48, as shown in Fig. 5, the arm 2 of the leader 4' is
6 and the bin 28 of the bracket 27 and remove the leader 4'
The sub-stand 31 of the stand 29 provided at the contact portion of the hull 3' is brought into a vertical position 4 as shown by the solid line in FIG. 1, and fixed by a stopper (not shown).
The hole on the base end side of the hydraulic cylinder 19 provided in each bearing 18 is
As shown in FIG. 8, by alternately inserting and inserting the screw holes between the screw holes provided in the hull 3', that is, by expanding and contracting the hydraulic cylinder 19 and extracting and detaching the screw bottles each time, the so-called length is fixed. Each bearing 18 is moved along the longitudinal direction of the hull 3' through a sliding movement, and the itching blade 39 at the tip of each shaft 9 is placed in a position where it fully faces the opening 14 of the hull 3' and can easily enter. attitude and thereupon, by activating the winch 33 provided at the aft end of the hull 3', the wire 34 pulls the arm 26 at one end of the leader 4', so that the leader 4' has its position relative to each bearing 18. The winch 33 pivots around the shaft 22 and assumes a standing position.
The leader 4' stands up as a result of the continuous operation, and when it reaches a predetermined angle, if the slope construction shown in FIG. 1l1110 by remote control as appropriate to fix the inclined posture of the leader 4' at the set angle.

又、第5図に示す垂立状態での施工を行う場合には、更
に、上述傾斜姿勢を越えてウィンチ33を連続動作させ
てリーダー4′を船体3′、即ち、地盤10に対して垂
立姿勢にしてスパッド41を地盤10に対して貫入させ
る。
In addition, when performing construction in the vertical state shown in FIG. The spud 41 is made to penetrate into the ground 10 in an upright position.

そして、リーダー4′の下端側のアーム26に設けられ
たウィンチ46を動作して上部に設けられたブラケット
36をリーダー4に沿ってプーリ45、ワイヤ47を介
し強制的に引っ張り下降させて各シャフト9の先端を地
盤10に貫入させると共に、地盤の下端側のアーム26
に設けた油圧モータ等のロータリ一式回転機構38を介
して各シャフト9を、即ら、攪拌羽根39を回転させて
地盤10に貫入攪拌させ、所定深度に達すると、改良材
プラント11によりタンク12からの粉体セメントをコ
ンプレッサからの空気により気体輸送して各シャフト内
を通過させ、所定深度で回転する攪拌羽根39から地盤
中に噴出させ、併せてそれまで動作させていたウィンチ
45を停止すると共に、リーダー4′の上端アーム26
に設けた他のウィンチ42を動作してワイヤ44、及び
、プーリ43を介してブラケット36を、即ち、各シャ
フト9を上昇引き抜きさせ、回転R構38の継続回転に
より各攪拌羽根39は地盤10中で旋回しながら土壌と
噴出セメントを混合攪拌する。
Then, by operating the winch 46 provided on the arm 26 on the lower end side of the leader 4', the bracket 36 provided on the upper part is forcibly pulled down along the leader 4 via the pulley 45 and the wire 47, and each shaft is moved down. 9 into the ground 10, and the arm 26 on the lower end side of the ground.
Each shaft 9, that is, the stirring blade 39, is rotated through a rotary complete rotation mechanism 38 such as a hydraulic motor installed in the ground 10 to penetrate into the ground 10 and stir it. The powdered cement is transported by air from the compressor and passed through each shaft, and is ejected into the ground from the stirring blade 39 rotating at a predetermined depth, and at the same time, the winch 45 that had been operating until then is stopped. together with the upper arm 26 of the leader 4'.
The other winch 42 provided in The soil and spouted cement are mixed and stirred while swirling inside.

尚、この間、粉体セメントを輸送した空気は各シャフト
9の図示しないスピル等を介してこれに沿って上昇逸散
する。
During this time, the air that transported the powder cement ascends and dissipates along the shafts 9 via spills (not shown).

尚、当該施工は前記第6図に示す傾斜施工においても全
く同様にして行うことが出来る。
Incidentally, the construction can be carried out in exactly the same manner in the inclined construction shown in FIG. 6.

そして、各シャフト9が地盤10より引き汰かれた後に
は、アンカーを解き、改良船2′を所定距離だけ進行さ
せて再びアンカーをとり、上述施工を反復して地盤10
に対する地盤改良を行っていく。
After each shaft 9 has been pulled out of the ground 10, the anchors are released, the improved ship 2' is advanced a predetermined distance, the anchors are removed again, and the above-mentioned construction is repeated to remove the anchors from the ground 10.
We will carry out ground improvement for this area.

そして、この間、施工中での船体3′から地盤10に対
するスパッド41を介してのリーダー 4′ は船体3
′の上部空中部分と下部水中部分とに於いて同じ剛性を
有しているために、先述従来態様のカンチレバ一式の弱
い補助リーダーと異なり、多少の波浪による改良船2′
の揺動をも受けつけず、充分にリーダー4′の垂立、或
は、傾斜姿勢を堅持して各シャフト9の確実な貫入、粉
体セメント噴射、及び、Illの各施工を行うことが出
来るものである。
During this period, the leader 4' is connected to the ground 10 from the hull 3' during construction through the spud 41.
Because the upper aerial part and the lower underwater part of the ship 2' have the same rigidity, unlike the weak auxiliary leader of the conventional cantilever set described above, the modified ship 2'
It is possible to securely penetrate each shaft 9, perform powder cement injection, and perform Ill construction by sufficiently maintaining the vertical or inclined position of the leader 4' without accepting any shaking. It is something.

而して、上述実施例においては、船体3′と・地盤10
との施工域での深度が一定の場合であり、当該態様の場
合は予め造船所においてリーダー4′を測量に従った上
記深度と同一長さに各短パイプ24と補強桁23とによ
るフランジ25を介してのユニットの組付けによって軸
22から下側アーム26、即ち、スパッド41までの長
さを予め決めておいても行える態様であるが、船体3′
と地盤10の深度が変化したり、或は、バラツキがあっ
たりする場合には、施工現場にて軸22とスパッド41
の長さを深度に応じて調整しなければならない場合があ
る。
Therefore, in the above embodiment, the hull 3' and the ground 10
This is a case where the depth in the construction area is constant, and in this case, the flange 25 formed by each short pipe 24 and reinforcing girder 23 is installed at the shipyard to the same length as the above depth according to the survey of the leader 4'. Although this mode can be carried out by predetermining the length from the shaft 22 to the lower arm 26, that is, the spud 41, by assembling the unit through the hull 3'
If the depth of the ground 10 changes or varies, the shaft 22 and spud 41 should be removed at the construction site.
The length may have to be adjusted depending on the depth.

このような場合には、例えば、第14図に示す様な深度
が浅かったり、或は、第15図に示す様な深度が深い場
合には、予め造船所にてリーダー4′の各類バイブ24
と補強桁23の組付けを調整して軸22の位置が軸受1
8に対して当該対応深度に対応する長さであるように組
付けを行うことによって対処することが出来る。
In such cases, for example, if the depth is shallow as shown in Figure 14, or deep as shown in Figure 15, each type of vibrator of the leader 4' should be installed at the shipyard in advance. 24
By adjusting the installation of the reinforcing girder 23, the position of the shaft 22 is adjusted to the bearing 1.
This can be solved by assembling 8 to a length corresponding to the corresponding depth.

勿論、当該類バイブ24、及び、補強桁23の組付けは
前述同様に水平状態で岸壁の低いクレーンにより行うこ
とが出来、又、その組付は精度調整精度の管理は前述の
如く極めて正確に水平姿勢で行うことが出来るものであ
る。
Of course, the similar vibrator 24 and the reinforcing girder 23 can be assembled in a horizontal state using a low crane on the quay, as described above, and the accuracy of the assembly can be controlled extremely accurately as described above. This can be done in a horizontal position.

当該態様において、例えば、第15図に示す様に、軸2
2とスパッド41との距離が長く船体3′の開口14に
対する干渉がある場合には、前述の如く各軸受18の油
圧シリンダ19の動作により該各軸受18をして船体3
′の各ネジ孔21に対する尺取り史的移動によりリーダ
ー4′を船体3′に対して最適姿勢にして曳航走行を行
うように出来、又、該油圧シリンダ19の伸縮操作によ
りスパッド41、及び、各シャフト 9の攪拌羽根39
が間口に臨み易く水中に侵入し易いようにすることが出
来る。
In this aspect, for example, as shown in FIG.
If the distance between the spud 2 and the spud 41 is long and there is interference with the opening 14 of the hull 3', the hydraulic cylinder 19 of each bearing 18 operates to close each bearing 18 to the hull 3'.
The leader 4' can be towed in an optimal position relative to the hull 3' by adjusting the length of each screw hole 21, and by expanding and contracting the hydraulic cylinder 19, the spud 41 and Stirring blades 39 on each shaft 9
It is possible to make it easy for people to face the frontage and enter the water easily.

勿論、当該態様において、軸22をしてリーダー4′の
所定位置に入替え貫入取付けするようにする態様も設計
によってはとり得ることは勿論である。
Of course, in this embodiment, it is possible to adopt a mode in which the shaft 22 is replaced and inserted into a predetermined position of the leader 4' depending on the design.

さりながら、軸22とスパッド41との距離を改良域現
場にて、深度に応じて調整して無段的に調整する必要が
ある場合があるが、これに対処するに、第16.17図
に示す様に、各軸受18のスリット49にスライダ50
を上下摺動可能に介装し、その下側に設けた減速機付モ
ータ51の該スライダ50に遊挿される軸52の上端に
設けられたウオーム53を該スリット49に形成された
ラック54に係合させて、該モータ51を動作すること
により、該スライダ5゜は所定に微少距離上下動し、し
たがって、該スライダ50に軸装されている軸22を介
してリーダー4′は上下動することが出来、そのため、
施工現場の深度に即応して軸22とスパッド41間の距
離を調整し、更には、スパッド41が地盤10に当接し
た後に強制的に地盤に貫入させるようにすることが出来
る。
However, there are cases where it is necessary to adjust the distance between the shaft 22 and the spud 41 steplessly depending on the depth at the site of the improvement area. As shown in the figure, a slider 50 is inserted into the slit 49 of each bearing 18.
A worm 53 provided at the upper end of a shaft 52 that is loosely inserted into the slider 50 of a motor 51 with a reducer provided below the worm 53 is inserted into a rack 54 formed in the slit 49 so as to be slidable up and down. By engaging and operating the motor 51, the slider 5° moves up and down a predetermined minute distance, and therefore, the leader 4' moves up and down via the shaft 22 mounted on the slider 50. Therefore,
The distance between the shaft 22 and the spud 41 can be adjusted in response to the depth of the construction site, and furthermore, the spud 41 can be forcibly penetrated into the ground after coming into contact with the ground 10.

尚、当該実施例はリーダー4′の垂立、及び、゛傾斜姿
勢のいづれの場合にも適用可能である。
Incidentally, this embodiment can be applied to both cases where the leader 4' is in an upright position and an inclined position.

このようにして、船体3′に対するリーダー4′の軸4
4の位置を変更調整することにより、第10図に示す様
に、リーダー4′の空中部分と水中部分が略等しくする
ように出来、又、第11図に示す様に、空中部分が長く
、水中部分が短く、又、第12図に示す峰に、これらに
中間姿勢をとるようにすることも出来、これらによって
現場での船体3′と地110との深度に対してリーダー
4′の長さを無段的に対応調整することが出来る。
In this way, the axis 4 of the leader 4' relative to the hull 3'
By changing and adjusting the position of the leader 4, the aerial part and the underwater part of the leader 4' can be made almost equal, as shown in FIG. 10, and the aerial part is longer, as shown in FIG. The underwater portions are short, and the ridges shown in Figure 12 can be arranged to take an intermediate position, thereby reducing the length of the leader 4' relative to the depth between the hull 3' and the ground 110 at the site. The height can be adjusted steplessly.

又、第18〜20図に示す実施例は傾斜姿勢装置の付設
の態様であり、リーダー4′の両側に各々油圧シリンダ
55を配設し、そのロンド56の先端をして該リーダー
4′の側面に固設したブラケット57に揺動自在にビン
枢支すると共に、船体3′の開口14の両側に設けられ
た所定ピッチのネジ孔58に対し、各々油圧シリンダ5
5の基端側のブラケット59のピン孔60を合致させて
ネジ化めすることにより、第19図に示す様に、起立状
態のリーダー4′をサポートして前述第5.6図に示す
ウィンチ33、ワイヤ34を介してのリーダー4′の所
定起立姿勢を助勢維持することが出来るようにし、特に
、該リーダー4′の垂立姿勢の船体3′の空中部分での
高さが高い場合の姿勢維持を確実にしてスパッド41.
41による姿勢固定状態をより確実にするものである。
The embodiment shown in FIGS. 18 to 20 is a mode in which a tilting position device is attached, and hydraulic cylinders 55 are provided on both sides of the leader 4', and the tip of the iron 56 is connected to the leader 4'. The cylinders are pivotally supported on a bracket 57 fixed to the side surface, and each hydraulic cylinder 5 is connected to a screw hole 58 with a predetermined pitch provided on both sides of the opening 14 of the hull 3'.
By aligning the pin holes 60 of the bracket 59 on the base end side of the bracket 5 and screwing them together, as shown in FIG. 19, the leader 4' in the upright state is supported and the winch shown in FIG. 33, it is possible to support and maintain the predetermined standing posture of the leader 4' via the wire 34, especially when the height of the aerial part of the hull 3' of the vertical posture of the leader 4' is high. Make sure to maintain your posture and spud 41.
This makes the posture fixed state by 41 more reliable.

而して、当該実施例において、リーダー4′の船体3′
に対する水平倒伏状態では、第18図に示す様に、該油
圧シリンダ55とリーダー4′ との間に固定チェーン
61等によって縮退状態の油圧シリンダ55をリーダー
4′に平行状態にして側位固定することが出来る。
Therefore, in this embodiment, the hull 3' of the leader 4'
In the horizontally collapsed state, as shown in FIG. 18, the retracted hydraulic cylinder 55 is parallel to the leader 4' and fixed at the side using a fixed chain 61 or the like between the hydraulic cylinder 55 and the leader 4'. I can do it.

尚、該油圧シリンダ55とリーダー4′との間にエアシ
リンダ等設けて平行側位させたり、或は、ハの字型に開
いて船体3′との間に固定させるようにする等の手段も
充分採用出来るものである。
In addition, an air cylinder or the like may be provided between the hydraulic cylinder 55 and the leader 4' so that they are positioned parallel to each other, or the leader 4' may be opened in a V-shape and fixed between the leader 4' and the hull 3'. can also be fully adopted.

このようにすることにより、第21図に示す様に、垂立
姿勢のリーダー4′に対して確実にその姿勢を固定する
ことが出来、又、第22図に示す様に、リーダ〒4′の
傾斜姿勢での傾斜施工が安定した状態で常に終始維持す
ることが出来る。
By doing this, as shown in FIG. 21, the posture of the leader 4' can be reliably fixed in the upright position, and as shown in FIG. It is possible to maintain a stable condition from start to finish during slope construction in an inclined position.

尚、この発明の実施態様は上述実施例に限るものでない
ことは勿論であり、例えば、第18.19図に示す実施
例に前述第16.17図に示すリーダー4′の軸22の
垂立移動機構等を設けたり、軸受18.18を船体3′
の開口14の回りに設けた円形レールに沿って旋回させ
たり、船体を双胴船タイプにしたりして施工する等径々
の態様が採用可能である。
It goes without saying that the embodiment of the present invention is not limited to the above-mentioned embodiment. For example, the embodiment shown in FIG. If a moving mechanism etc. is provided, the bearing 18.18 is mounted on the hull 3'.
It is possible to adopt an aspect in which the vessel is constructed with equal diameters, such as by turning the vessel along a circular rail provided around the opening 14, or by making the hull into a catamaran type.

又、適用対象は先述粉体噴射攪拌による地盤改良ばかり
でなく、サンドドレーンやペーパードレン、或は、生石
灰等による地盤改良も勿論可能であり、適用水域は2N
中のみならず、河川や湖沼においても適用可能である。
In addition, it is applicable not only to the ground improvement using powder injection and agitation mentioned above, but also to ground improvement using sand drains, paper drains, quicklime, etc., and the applicable water area is 2N.
It can be applied not only inside, but also in rivers and lakes.

〈発明の効果〉 以上、この発明によれば基本的、近時、極めて需要に高
い河川水中湖沼等における水中での粉体噴射攪拌工事等
の地盤改良に用いるリーダーを有する地盤改良船による
水中地盤改良工法において、リーダーが水上輸送中は船
体に平行に水平姿勢で倒伏され、改良域現場では船体に
対し傾斜、或は、垂立状態で垂立させることが出来るた
めに、造船所等にて組付は建造、改造する際には水平姿
勢で岸壁の低いクレーン等により施工が容易に安全に行
われ、しかも、他の作業と共に同時併行的に行われるこ
とが出来、作業能率を向上させることが出来るという優
れた効果が奏される。
<Effects of the Invention> As described above, according to the present invention, it is basically possible to improve the underwater ground using a soil improvement vessel equipped with a leader, which is used for ground improvement such as underwater powder injection stirring work in rivers, underwater lakes, etc., which is in extremely high demand these days. In the improved construction method, the leader is laid down in a horizontal position parallel to the ship's hull during transportation on water, and at the site of the improvement area it can be tilted or vertically placed against the ship's hull. When building or remodeling, construction can be easily and safely carried out using a crane or the like with a low quay in a horizontal position, and can be carried out simultaneously with other work, improving work efficiency. The excellent effect of being able to do this is achieved.

又、水上輸送では、河口や入り江等に設けられた吊り橋
等や他の港湾配設等と干渉することがなく、スムースに
所定改良域まで航行することが出来るという優れた効果
が奏される。
In addition, water transportation has the excellent effect of being able to smoothly navigate to a designated improvement area without interfering with suspension bridges or other port facilities installed at river mouths, inlets, etc.

又、高さが低く重心が低位にあって安定姿勢であるため
に、風や波浪の影響を、受けず、揺動が少く、極めて安
全であるという効果があるうえに、抵抗が少いために相
当なスピードで輸送することが出来、したがって、工期
短縮等のうえでも極めて効果的である利点がある。
In addition, because the height is low and the center of gravity is low and the posture is stable, it is not affected by wind or waves, and there is little swaying, making it extremely safe. It can be transported at a considerable speed and therefore has the advantage of being extremely effective in shortening the construction period.

そして、リーダー4の長さは航行中の吊り橋等に対する
障害や施工中の安全性等の束縛を受けないために、高さ
、即ち、長さの設計の自由度が得られる効果があり、し
かも、施工がし易い点からコストダウンが図られるとい
う優れた効果が奏される。
Furthermore, since the length of the leader 4 is not restricted by obstructions to suspension bridges during navigation or safety during construction, it has the effect of providing freedom in designing the height, that is, the length. , the excellent effect of reducing costs is achieved due to ease of construction.

そして、リーダーの長さが自由にとれるために、施工規
模の大小を問わず、無段長に長さが出来るために、水中
での地盤改良工事の発展にも寄与することが出来るとい
う優れた効果が奏される。
In addition, since the length of the leader can be adjusted freely, the length can be infinitely extended regardless of the size of the construction project, making it an excellent product that can also contribute to the development of underwater ground improvement work. The effect is produced.

又、船体とリーダーとの間に該リーダーに対する起伏装
置が設けられていることにより、上述の航行中のリーダ
ーの倒伏姿勢が保証され、更に、現場に容易にリーダー
を起立させることが出来る効果が奏される。
In addition, by providing a lifting device for the leader between the hull and the leader, the above-mentioned lying position of the leader during navigation is guaranteed, and furthermore, the leader can be easily erected at the site. It is played.

又、船体には改良材プラントが設ることにより、前述の
薬液注入工法を用いない粉体空気輸送によるセメント等
の空気輸送による粉体噴射攪拌工法や深層混合工法が適
用出来るという優れた効果が秦される。
In addition, by installing an improved material plant in the hull, it has the excellent effect of being able to apply the powder injection stirring method and deep mixing method, which uses powder pneumatic transport to transport cement, etc., without using the chemical injection method mentioned above. Qin will be conquered.

而して、リーダーは単にその耳部が船体に対して倒伏起
立自在にされているものとは異なり、軸を介しての旋回
起立により水中の下側の部分も一つのリーダーの躯体で
あるために、船体の空中部分にある上部が剛性があるば
かりでなく、水中にある部分も同じく剛性があり、した
がって、従来のカンチレバ一式のような剛性がなく、不
安定であるものとは異なり、地盤に対する改良材輸送シ
ャフトの姿勢を確実に維持させることが出来、そのため
、地盤改良工事が設計通りに精度高く行え、例えば、地
盤中の杭等も正確に形成出来るという優れた効果があり
、更には、施工中多少の波浪や風があっても該水中での
リーダーの剛性が充分であるために、逆に改良的自体を
も水面に低姿勢に維持することが出来るという優れた効
果が奏される。
Therefore, the leader is different from the case where the ears are simply able to lie down and stand up with respect to the hull, but because the lower part of the leader underwater is also one body of the leader because it rotates and stands up through the shaft. Not only is the upper portion of the hull in the air rigid, but the underwater portion is equally rigid, and therefore, unlike traditional cantilever sets, which are not rigid and unstable, It is possible to reliably maintain the posture of the improvement material transport shaft against the ground, and as a result, ground improvement work can be carried out with high precision as designed, and, for example, piles in the ground can be formed accurately, which is an excellent effect. Even if there are some waves or wind during construction, the rigidity of the leader in the water is sufficient, and on the other hand, it has the excellent effect of being able to maintain the improved structure itself in a low position on the water surface. Ru.

このため、多少の気象変動があっても従来は施工を中止
する等していた不具合が一挙に解消され、はとんど天候
が激変しない限り、これに左右されずに施工を続行する
ことが出来るという優れた効果が奏される。
As a result, problems that would previously have required construction to be stopped even if there was a slight change in the weather have been resolved all at once, and construction can now continue without being affected by weather changes, unless the weather changes drastically. Excellent effects can be achieved.

そして、船体とリーダーとの少くとも一方に傾斜装置が
設けられていることにより、単にリーダーの垂立姿勢の
みならず、設定傾斜角度での傾斜姿勢を安定に維持出来
、これにより斜杭等の傾斜施工が出来、本来的に施工の
自由度が拘束される水中での地盤改良が飛曜的に向上さ
れる優れた効果が奏される。
By providing a tilting device on at least one side of the hull and the leader, it is possible to stably maintain not only the vertical position of the leader but also the tilted position at the set tilt angle. It is possible to perform slope construction, and has the excellent effect of dramatically improving ground improvement underwater, where freedom of construction is originally restricted.

したがって、近時、粉体セメント等の優れた改良材を水
中環境の水中地盤に対しても正確に設計通りに噴出して
土壌と攪拌し、所定の地盤改良を精度良く行うことが出
来る優れた効果が奏される。
Therefore, in recent years, excellent improvement materials such as powdered cement have been developed that can accurately perform predetermined ground improvement by ejecting excellent improvement materials such as powder cement into the underwater ground as designed and mixing it with the soil. The effect is produced.

【図面の簡単な説明】[Brief explanation of drawings]

第1〜22図はこの発明の詳細な説明図であり、第1図
は1実施例の船体の部分透視側面図、第2図は同平面図
、第3図は改良的の水上輸送姿勢概略側面図、第4図は
同概略平面図、第5図は施工領域におけるリーダーの垂
立姿勢概略側面図、第6図は同傾斜姿勢概略側面図、第
7図は改良船舶体の概略透視正面図、第8図は軸受の水
平移動機構平面図、第9図は軸受の部分断面正面図、第
10.11.12図はリーダーの船体に対する垂立姿勢
の各態様図、第13図はリニダーの垂立姿勢での地盤に
対する姿勢固定部分断面正面図、第14.15図は水深
の撮動変化に対応するリーダーの組何は調整正面図、第
16図はリーダーの軸受に対する昇降機構概略部分断面
正面図、第17図は第16図部分断面拡大図、第18図
は第2図相当他の実施例の平面図、第19図は同リーダ
ーの垂立姿勢固定機構概略正面図、第20図は同油圧シ
リンダの斜視図、第21図は同リーダーの垂立姿勢固定
透視側面図、第22図は同リーダーの傾斜姿勢固定透視
側面図、第23図は従来技術に基づく地盤改良的による
水中地盤改良の概略側面図、第24図は同概略平面図で
ある。 1・・・水面、  10・・・地盤、   9・・・シ
ャフト、4′・・・リーダー、  33・・・作動装置
、2′・・・地盤改良船 第10図   第13図 1u            39 手続補正書(1釦 昭和59年12月20日 特許庁長官  志 賀   学  殿 1、$件の表示 昭和59年 特許願 第250546号2、発明の名称 水中地盤改良方法 3、補正をする者 事件との関係   特許出願人 住  所  静岡県富士市冨士見台3丁目3番地の30
氏 名 三谷 健
1 to 22 are detailed explanatory diagrams of the present invention, in which FIG. 1 is a partially transparent side view of the hull of one embodiment, FIG. 2 is a plan view of the same, and FIG. 3 is a schematic diagram of an improved water transportation posture. 4 is a schematic plan view of the same, FIG. 5 is a schematic side view of the leader in the vertical position in the construction area, Fig. 6 is a schematic side view of the leader in the same inclined position, and Fig. 7 is a schematic perspective front view of the improved hull. Fig. 8 is a plan view of the horizontal movement mechanism of the bearing, Fig. 9 is a partially sectional front view of the bearing, Figs. Figures 14 and 15 are front views of a part of the reader with its posture fixed relative to the ground in a vertical position; Figures 14 and 15 are front views of the adjustment of the leader set corresponding to changes in water depth; Figure 16 is a schematic part of the lifting mechanism for the reader's bearings. 17 is an enlarged partial sectional view of FIG. 16, FIG. 18 is a plan view of another embodiment equivalent to FIG. 2, FIG. 19 is a schematic front view of the vertical position fixing mechanism of the reader, and FIG. Figure 21 is a perspective view of the hydraulic cylinder, Figure 21 is a transparent side view of the leader fixed in an upright position, Figure 22 is a transparent side view of the leader fixed in an inclined position, and Figure 23 is a ground improvement method based on conventional technology. A schematic side view of the underwater ground improvement, and FIG. 24 is a schematic plan view thereof. 1... Water surface, 10... Ground, 9... Shaft, 4'... Leader, 33... Operating device, 2'... Ground improvement ship Figure 10 Figure 13 Figure 1u 39 Procedure amendment (1 button December 20, 1980 Manabu Shiga, Commissioner of the Patent Office 1, Display of $ 1980 Patent Application No. 250546 2, Title of invention Underwater ground improvement method 3, Amendment with the person making the amendment) Related Patent Applicant Address: 3-30 Fujimidai, Fuji City, Shizuoka Prefecture
Name Ken Mitani

Claims (10)

【特許請求の範囲】[Claims] (1)水面上に浮設する改良船より該改良船に設けたリ
ーダーを介し改良材シャフトを延出させて水面下地盤に
対し挿設し改良材を送給する地盤改良方法において、上
記改良船の改良域までの輸送では上記リーダーを船体に
倒伏させておき改良施工に際しては該リーダーを起立さ
せ、次いでシャフトを該リーダーに沿ってスライド降下
させて地盤に挿設固定して改良材を地盤中に送給するよ
うにしたことを特徴とする水中地盤改良方法。
(1) In a ground improvement method in which an improved material shaft is extended from an improved ship floating on the water surface through a leader provided on the improved ship, and inserted into the ground below the water surface to feed the improved material, the improvement described above is carried out. When transporting the ship to the improvement area, the leader is laid down on the ship's hull, and when carrying out the improvement work, the leader is erected, and the shaft is then slid down along the leader and inserted and fixed into the ground, allowing the improvement material to be placed in the ground. An underwater ground improvement method characterized by feeding water into the water.
(2)上記リーダーの倒伏から起立までの間に該リーダ
ーが船体に対して移動されていることを特徴とする上記
特許請求の範囲第1項記載の水中地盤改良方法。
(2) The underwater ground improvement method according to claim 1, wherein the leader is moved relative to the ship's hull during the period from when the leader is lowered to when it is raised.
(3)上記移動が水平、旋回、上下移動のいづれかであ
ることを特徴とする上記特許請求の範囲第2項記載の水
中地盤改良方法。
(3) The underwater ground improvement method according to claim 2, wherein the movement is one of horizontal, turning, and vertical movement.
(4)上記リーダーの起立姿勢が垂立姿勢であることを
特徴とする上記特許請求の範囲第1項記載の水中地盤改
良方法。
(4) The underwater ground improvement method according to claim 1, wherein the standing position of the leader is a vertical position.
(5)上記リーダーの起立姿勢が傾斜姿勢であることを
特徴とする上記特許請求の範囲第1項記載の水中地盤改
良方法。
(5) The underwater ground improvement method according to claim 1, wherein the standing position of the leader is an inclined position.
(6)上記リーダーが起立した後船体に対し固定姿勢を
維持するようにされていることを特徴とする上記特許請
求の範囲第4、5項のいづれか記載の水中地盤改良方法
(6) The underwater ground improvement method according to any one of claims 4 and 5, wherein the leader maintains a fixed posture with respect to the ship's body after standing up.
(7)上記改良材が粉体であってその地盤中への送給が
気体輸送により行われ、地盤中で噴射されて地盤土壌と
攪拌されることを特徴とする上記特許請求の範囲第1項
記載の水中地盤改良方法。
(7) Claim 1, characterized in that the improvement material is a powder, and is fed into the ground by gas transport, and is injected into the ground and mixed with the ground soil. Underwater ground improvement method described in section.
(8)上記地盤改良がサンドドレーンによるものである
ことを特徴とする上記特許請求の範囲第1項記載の水中
地盤改良方法。
(8) The underwater ground improvement method according to claim 1, wherein the ground improvement is performed by using a sand drain.
(9)上記地盤改良が生石灰によるものであることを特
徴とする上記特許請求の範囲第1項記載の水中地盤改良
方法。
(9) The underwater ground improvement method according to claim 1, wherein the ground improvement is performed using quicklime.
(10)上記地盤改良がペーパードレーンによるもので
あることを特徴とする上記特許請求の範囲第1項記載の
水中地盤改良方法。
(10) The underwater ground improvement method according to claim 1, wherein the ground improvement is performed using a paper drain.
JP25054684A 1984-11-29 1984-11-29 Improvement of underwater ground Granted JPS61130518A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP25054684A JPS61130518A (en) 1984-11-29 1984-11-29 Improvement of underwater ground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP25054684A JPS61130518A (en) 1984-11-29 1984-11-29 Improvement of underwater ground

Publications (2)

Publication Number Publication Date
JPS61130518A true JPS61130518A (en) 1986-06-18
JPH0378889B2 JPH0378889B2 (en) 1991-12-17

Family

ID=17209516

Family Applications (1)

Application Number Title Priority Date Filing Date
JP25054684A Granted JPS61130518A (en) 1984-11-29 1984-11-29 Improvement of underwater ground

Country Status (1)

Country Link
JP (1) JPS61130518A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5249612A (en) * 1975-10-16 1977-04-20 Takenaka Komuten Co Treating apparatus for solidifying surface sludge
JPS58178719A (en) * 1982-04-14 1983-10-19 Aoki Kensetsu:Kk Method and apparatus for driving board-like drain material
JPS59170319A (en) * 1983-03-16 1984-09-26 Tokyu Constr Co Ltd Road-bed improver with movable excavation rod frame

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5249612A (en) * 1975-10-16 1977-04-20 Takenaka Komuten Co Treating apparatus for solidifying surface sludge
JPS58178719A (en) * 1982-04-14 1983-10-19 Aoki Kensetsu:Kk Method and apparatus for driving board-like drain material
JPS59170319A (en) * 1983-03-16 1984-09-26 Tokyu Constr Co Ltd Road-bed improver with movable excavation rod frame

Also Published As

Publication number Publication date
JPH0378889B2 (en) 1991-12-17

Similar Documents

Publication Publication Date Title
JPS6315381Y2 (en)
CN104652394B (en) A kind of Multifunction shallow sea job platform
CN201245235Y (en) Deep water jackstone leveling ship
US20080240863A1 (en) Elevating support vessel and methods thereof
US20080247827A1 (en) Work-over rig assembly and methods thereof
CN202148526U (en) Multi-functional piling system,
CN206859209U (en) A kind of inland river deep water rock quality base steel tube pile embeded in rock construction system
JP2543405B2 (en) Super buoy type boring turret and mooring device
US3763580A (en) Apparatus for dredging in deep ocean
CN103119222A (en) Surface-breaking re-usable submergeable template for installing one or more submerged columns/piles
JPS61143291A (en) Foundation improving ship
JPS61130518A (en) Improvement of underwater ground
CN212582685U (en) High-pile wharf steel pipe pile construction positioning device
JP4038393B2 (en) Ground improvement ship and ground improvement method
JPS5820660Y2 (en) Soft ground improvement equipment
CN115492105B (en) Photovoltaic pile driver and water operation platform
CN215926122U (en) Platform equipment for cofferdam foundation cleaning
JP4520907B2 (en) Solidification processing equipment
JP2772562B2 (en) Premix seabed casting method and premix casting boat
CN108978759B (en) Workboat is dredged suitable for the environment-friendly type in the confined space
JP2023073733A (en) Elevating-type working ship and installing method of cylindrical body using it
JP4925092B2 (en) Temporary scaffolding for coastal construction
CN116104093A (en) Mixing and pumping pouring device and method for underwater foundation scour protection fluid solidified soil
CN116378145A (en) Full-automatic sand pumping method for sand sedimentation tank
JP2000240054A (en) Pile driving work barge and pile driving device