JPS6047118A - Low-pollution piling work - Google Patents

Low-pollution piling work

Info

Publication number
JPS6047118A
JPS6047118A JP15300983A JP15300983A JPS6047118A JP S6047118 A JPS6047118 A JP S6047118A JP 15300983 A JP15300983 A JP 15300983A JP 15300983 A JP15300983 A JP 15300983A JP S6047118 A JPS6047118 A JP S6047118A
Authority
JP
Japan
Prior art keywords
ground
pile
injection
bearing stratum
noise
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP15300983A
Other languages
Japanese (ja)
Inventor
Kisho Takagi
高木 希昭
Hiroto Nakagawa
中川 宏人
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Asahi Kasei Corp
Asahi Chemical Industry Co Ltd
Original Assignee
Asahi Chemical Industry Co Ltd
Asahi Kasei Kogyo KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Asahi Chemical Industry Co Ltd, Asahi Kasei Kogyo KK filed Critical Asahi Chemical Industry Co Ltd
Priority to JP15300983A priority Critical patent/JPS6047118A/en
Publication of JPS6047118A publication Critical patent/JPS6047118A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/24Placing by using fluid jets

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

PURPOSE:To reduce noise and vibration in driving a custom-made pile by a method in which the ground is loosened by an injection rod, a custom-made pile is penetrated to the vicinity of the bearing stratum by lightly striking it by a low-noise striker and then further into the bearing stratum. CONSTITUTION:Injection rods 2 are penetrated while being connected additionally by means of a machine 1 until they reach right before the bearing stratum 10. The injection rods 2 are then pulled while being turned and while injecting water or cement milk at a high pressure. The pile is vertically erected by a pile-driving tower and a noiseless hammer 8 and finally penetrated into the bearing stratum 10. Since the hard ground alone, requiring a loosening work, is loosened and also the ground requiring no loosening work is left untreated, the construction work can be speeded up, and the hardness of the ground till the bearing stratum can be made almost uniform. Sufficient frictional forces on the periphery of the pile can thus be obtained.

Description

【発明の詳細な説明】 既製杭の特徴は、製品そのものは工場製品であり厳重な
品質管理の基に安定した品質の藺品であること。力m工
も本来打撃施工で土を圧密排除しながら貫入し、支持層
への確実な根入れと共に大きな摩擦力と確実な先端支持
力とで大きな支持力が期待でき、安価な施工で手軽に使
用できるなど材工合せ優れた工法として広範に使用され
てきた。
[Detailed Description of the Invention] The characteristic of ready-made piles is that the product itself is a factory product and has stable quality based on strict quality control. The force m method is originally a hammer construction method, which penetrates the soil while compacting it and eliminates it.In addition to reliable penetration into the supporting layer, it can be expected to have a large bearing capacity due to large frictional force and reliable tip support force, and is easy to install at a low cost. It has been widely used as a construction method with excellent combination of materials.

しかし、近年低公害化の要求が強くなシ打撃施工による
振動1掻音が問題となり、打撃工法は減少すると共に各
種無振動無騒音全ねらった低公害工法が普及してきた。
However, in recent years, there has been a strong demand for low-pollution construction, and the vibrations and scratching noise caused by hammer construction have become a problem, and the hammer construction method has declined, and various low-pollution construction methods that are vibration-free, noise-free, and other construction methods have become popular.

しかしながらこのためには杭を静かに地中に挿入する必
要があり、どのような方法であれ地盤を予め相当緩めて
おかな仏と挿入は不可能であり、この結果杭周面の地盤
は戻らず十分な摩擦力を期待できないのが現実である。
However, in order to do this, it is necessary to insert the pile gently into the ground, and no matter what method you use, it is impossible to insert the pile without loosening the ground considerably in advance, and as a result, the ground around the pile will not return. The reality is that we cannot expect sufficient frictional force.

やけ9本来は杭を打撃し、強制的に地盤の中に圧入し少
しでも周辺の地盤を圧密しながら施工されるのが既製杭
の最も優れた使い方と言えよう1、所で打撃工法は一概
に大きな経世、振i1r k出すとは言えないケースが
ある。即ち地盤は支持層までの深さや、土質あるいは硬
さ等々千差万別ではあるが5例えばN値0〜5位のシル
ト質の地盤に杭を打設すると、−打撃当シで数メートル
も杭が貫入されることがしばしば有る。極端な例では杭
自重で自沈することさえもち、乙。このようなケースで
は騒音、振動は必ずしも大きく安い。しかし・硬い中間
層を打抜いて支持層に到達さぜる。ような打撃施工では
相当の騒音、振動を発生させるのは言うまでもない。こ
こで前記の極端に軟かい地盤であっても、施工後杭周面
の摩擦力は2〜3t/m位は十分に取れるものであり、
仮に杭長507n、杭径500鑓φがこの様な地盤に打
込まれたとすると実に157TON〜236TONの摩
擦力が有シ、軟弱な地盤と言えども打撃施工の威力は相
当なものが有る。
Burn 9 Originally, the best way to use ready-made piles is to hammer the pile into the ground, forcing it into the ground and compacting the surrounding ground as much as possible. There are cases in which it cannot be said that there will be a big change in the future. In other words, although the ground varies greatly in terms of depth to the supporting layer, soil quality, hardness, etc.5, for example, if a pile is driven into silty ground with an N value of 0 to 5, the impact force will be several meters. Piles are often penetrated. In extreme cases, the pile may even scuttle under its own weight. In such cases, noise and vibration are not necessarily large and cheap. However, the hard intermediate layer is punched out to reach the support layer. It goes without saying that such impact construction generates considerable noise and vibration. Even in the extremely soft ground mentioned above, the frictional force around the pile after construction is sufficient to be around 2 to 3 t/m.
If a pile with a length of 507n and a diameter of 500mm were driven into such ground, it would have a frictional force of 157TON to 236TON, and even though the ground is soft, the power of impact construction is considerable.

本発明はこの現象に着目した。即ち、打字施工を採用す
るが施工による騒音、振動を必要に応じ軽減させるため
予め地盤を緩める。ただし、緩める必要のあるような固
い地盤の所のみ緩め、元々軟かく緩める必要のない所は
そのままにして緩める族ニスピードを早めると同時に支
持地盤までの地中の固さをほぼ一様な軟かさに改質し同
かつ。
The present invention focuses on this phenomenon. In other words, stamping construction will be adopted, but the ground will be loosened in advance to reduce noise and vibration caused by construction as necessary. However, it is possible to loosen only the hard ground that needs to be loosened, and leave the areas that are already soft and do not need loosening as they are.At the same time, it is possible to speed up the loosening process and at the same time reduce the hardness of the ground up to the supporting ground to a nearly uniform level. The same cutlet that has been modified into a cap.

前述のような打撃しても軽微な騒音、振動しか発生させ
ないよう例えばN値0〜5位にまで改質する。ここで改
質の程度として相当無振動、無厨音を要求するような所
ではここで述べたようにN値0〜5位まで相当改質する
必要があるが、多少の騒音、振動は許される所では例え
ばN値5〜10位まで緩めれば十分でちる。所で従来、
基本的には同じことを目的とした工法があった。それは
所謂プレポーリング工法がその代表例で必る。プレポー
リング工法は予めアースオーガーを用い必要な長さだけ
地m+ポーリングする。場合によってはこの除土を排出
するが%あるいはノ43合によってはアースオーガーを
最後には逆転させ土を排土せず地中に緩めた形で残して
くる方法が採用されている。これも本発明と考え方は同
一フトが、基本的に異るのは必要な断金必要な程度に緩
めると言う作業ができず、アースオーガー金挿入した全
域を自動的に緩めてしまう。このことは飾ニスピードの
面でも不経剤であるし、又施工機械の大型化も1ねき、
本来緩める必要がなく、できれば元のままで使用したい
地質であっても否応なく改質してしまう欠点もあった。
The material is modified to, for example, an N value of 0 to 5 so that even when hit as described above, only slight noise and vibration are generated. In places where the degree of modification requires considerably less vibration and noise, it is necessary to modify considerably to an N value of 0 to 5 as described here, but some noise and vibration are acceptable. For example, it is sufficient to loosen the N value to around 5 to 10. Conventionally,
Basically, there were construction methods for the same purpose. A typical example of this is the so-called pre-poling method. The pre-poling method uses an earth auger to poll the ground for the required length in advance. In some cases, this removed soil is discharged, but in some cases, the earth auger is reversed at the end, and the soil is not discharged but left in a loose form underground. This also has the same idea as the present invention, but the basic difference is that the required cutting bolt cannot be loosened to the necessary extent, and the entire area into which the earth auger metal is inserted is automatically loosened. This is a nuisance in terms of decoration speed, and the construction machinery is also becoming larger.
There was also a drawback that even if the geology did not need to be loosened and would be used as it was, it would inevitably be modified.

更に、アースオーガーを無理に回転圧入を行う関係で曲
りも生じ、せっかく穴をあける所が後の施工に困るよう
な曲シを予め起させる感作用も有シ、余り長いアースオ
ーガーは実用上、使用できなかった。この欠点を多少改
良した方法に最近ではロッドにJan−付け、土中でこ
れを回転させると同時にロッド先端部付近よシ注水し地
中を一様に泥土化し緩める方法も行われるようになった
。これとてもロッドを挿入した全長が翼によって攪拌、
混合され、アースオーガーの状況と何ら変らない方法と
なるが、異るのはアースオーガーに見られるような排土
はこの段階では発生しない点にあるし、共通の欠点とし
ては杭径に応じて全サイズの道具を用意する必要があり
Furthermore, as the earth auger is forcefully rotated and press-fitted, the earth auger may be bent, and the place where the hole is drilled has a sensitizing effect that causes bending that will cause problems in later construction. Couldn't use it. Recently, a method that has somewhat improved this drawback has been a method in which a Jan- is attached to the rod, the rod is rotated in the soil, and at the same time water is injected near the tip of the rod to uniformly turn the underground into mud and loosen it. . This means that the entire length of the rod inserted is stirred by the blades,
The method is no different from the situation with the earth auger, but the difference is that the soil removal that occurs with the earth auger does not occur at this stage, and the common drawback is that You need to have tools of all sizes.

不経剤であることが言える。これら全勘案して本発明は
次のような方式を採用するに至った。即ち、予め行われ
ている地盤調査を基に深度何メートルの所にどのような
固さのどのような土質のものが有るか判明しているので
緩めるべき範囲の推定と計画を行う。次に現場で工事に
入るが、工事では旨圧に耐えられる注入ロッドを回転圧
入させる。
It can be said that it is a menopausal agent. Taking all of these into account, the present invention has adopted the following method. In other words, since it is known based on the ground survey that has been conducted in advance how many meters deep and what kind of hardness and type of soil exists, the range to be loosened is estimated and planned. Next, construction begins on site, during which an injection rod that can withstand the pressure is rotated and press-fitted.

この注入ロッドには先端部に挿入がスムーズになるよう
切削刃が付けられており、又もう一つには略〃直角にり
(射できるよう噴射口金有している。
This injection rod has a cutting edge attached to its tip to facilitate smooth insertion, and the other end has an injection nozzle that can be inserted at a substantially right angle.

これ以外特殊なものはこの注入ロッドに何も伺いていな
い。このロッドを圧入する作5°;ミに入るとまず回転
を与え圧入して行くが必要あればこの噴射口から水等ご
く少量’(i: 1fit射させ挿入全スムーズに行え
るよう補うが、この挿入時の具入抵抗f:1m測するこ
とで前記地盤調査との対比を可能にし、前記推定を現場
でも確認することができる。所定の深さまで、通常は支
持層の直前まで注入ロッドは継ぎ足され挿入されると今
度は回転引上げに入る。
Other than this, I haven't heard anything special about this injection rod. The process of press-fitting this rod is 5 degrees; when the rod is inserted, it is first rotated and press-fitted, but if necessary, a very small amount of water (i: 1 fit) is injected from this injection port to make the insertion smooth. Filling resistance f at the time of insertion: By measuring 1 m, it is possible to compare with the above-mentioned ground survey, and the above estimation can be confirmed on site. Once it is inserted, it will start rotating and pulling up.

この場合、水又はセメントミルク等を噴射口よシ50 
Kg/cr71〜500 K9/lrAの圧で噴射する
ことでロッド周辺の地盤を崩壊、掘削、攪拌等の作用で
泥土状態に改質する。この際、噴射液の当る’1lil
s分が泥土状態になるが、上昇スピードを早めるとスパ
イラル状に噴射軌跡が残ることもあるが、土質等によっ
てはこれでもかまわず、要は後に杭を打設する際に打設
しやすいように、又、打設時の条件としてほぼ無振動、
無騒音に近い要求の、1jj合とある程度の振動、騒音
がかまわない要求とで改質処理の方法が異る。即ち、余
シ改質を必要としない場合は例えば50に2/ca の
圧力で回転引上げのスピードも早く、又、逆のケースは
500にり/CIr1の圧力で引上げスピードも遅くし
つかり緩める。又、同じ程度に緩める場合でも土質が非
常に固い場合は高圧で噴射し、さらに杭径が大きいもの
用であれば全体に高めの圧力で噴射する等、噴射圧と回
転引上げスピードを調節することで任意に改質した地盤
を構成することにある。当然のことながら注入ロッドは
一種類の形式で例えば300φ〜600φ程度の既製杭
用の予備掘削は可能である3、又、はぼ無振動、無騒音
型にするため相当の緩めを実施する場合、施工後の周面
地盤の戻9は余9期待できないケースもあるので噴射液
にセメントミルク、(例えばセメント1:水1重量比の
ミルク)を用いることで改質泥土化した土砂をソイルセ
メント状にする。これで局面摩擦先金回復させる補助手
段に役立たせる。要はこれらを配慮し、途中地盤の改質
を固い土質では十分緩める作業を行うなど作業計画に従
って上方に向は緩めて行く。163、この緩め作業は上
方引上げ時を基本とするが、地盤が安定しており、何本
もこの作業を実施した後では何も上方とは限らず、下方
に挿入時に計画的に緩めを実施しても良い。
In this case, pour water or cement milk etc. into the injection port for 50 minutes.
By injecting at a pressure of Kg/cr71 to 500 K9/lrA, the ground around the rod is reformed into a muddy state by collapse, excavation, stirring, etc. At this time, the '1lil' that the injection liquid hits
The soil will become muddy for s minutes, but if the rising speed is increased, a spiral trajectory may remain, but depending on the soil quality, this may be fine, and the point is to make it easier to drive the piles later. In addition, there is almost no vibration as a condition during pouring.
The method of reforming treatment differs depending on the 1jj case, which requires near-noise, and the case where a certain amount of vibration and noise is acceptable. That is, if no residual reforming is required, for example, a pressure of 50 to 2/ca will increase the speed of rotational pulling, and in the opposite case, a pressure of 500 to 2/ca will cause the pulling speed to be slow and loosen. In addition, even if the soil is loosened to the same extent, if the soil is very hard, inject at a high pressure, and if the pile has a large diameter, inject at a higher pressure overall, etc., and adjust the injection pressure and rotational pulling speed. The goal is to construct ground that has been arbitrarily modified. Of course, the injection rod is of one type, and it is possible to perform preliminary excavation for ready-made piles of, for example, 300φ to 600φ3, or if a considerable amount of loosening is performed to make the rod vibration-free and noise-free. In some cases, the return of the surrounding ground after construction cannot be expected, so by using cement milk as the injection liquid (for example, milk with a weight ratio of 1 part cement to 1 part water), the earth and sand that has been converted into modified mud can be converted into soil cement. make it into a shape. This will serve as an auxiliary means to recover the tip due to surface friction. The key is to take these into account and gradually loosen the soil in an upward direction according to the work plan, such as loosening the soil sufficiently if the soil is hard. 163. This loosening work is basically done when pulling upwards, but since the ground is stable, and after performing this work several times, loosening will not necessarily be done upwards, but will be done systematically when inserting downwards. You may do so.

所で特許請求の範囲に示すゲージ圧の範囲であるが、本
発明が応用できるものは既製杭であり、通常の既製杭の
直径は300φ〜1000φ程度、常用では300φ〜
600φが多い。これらの杭を対象とした予備掘削工程
では、完全無振動、無騒音に近い、換言すれば杭自重で
自沈する程度まで地盤を緩めるとすればほぼ杭径に近い
範囲を予備掘削する必要がある。一般的に水噴射による
掘削に対するエネルギーとセメントミルク等微粒子を含
む液の噴射エネルギーとでは後者の方が強いが、本発明
はどちらでも応用することを考え後述する実例テストも
加味して圧力を設定した、即ち、最低の50 Kg/l
rAの圧力はほぼ挿入するロッド径にDcmの周辺地盤
を掘削した程度となり、これ以下ではロッドが単に挿入
された程度で初期の目的を達成できない。一方高圧側は
前述の如く最大1000φの施工を考えると500に9
7−の圧がちれば丁度良い。
By the way, although the gauge pressure range shown in the claims is applicable to ready-made piles, the diameter of normal ready-made piles is about 300φ to 1000φ, and in regular use it is about 300φ to 1000φ.
There are many 600φ. In the preliminary excavation process for these piles, if the ground is to be loosened to the extent that there is no vibration and almost no noise, in other words, the pile will scuttle under its own weight, it is necessary to conduct preliminary excavation in an area close to the diameter of the pile. . Generally, the latter is stronger when it comes to the energy for excavation by water injection and the injection energy of liquid containing fine particles such as cement milk, but considering that the present invention can be applied to either, the pressure is set by taking into account the actual test described later. i.e. a minimum of 50 Kg/l
The pressure rA is approximately equal to the diameter of the rod to be inserted by excavating the ground around Dcm, and if it is less than this, the rod is merely inserted and the initial purpose cannot be achieved. On the other hand, on the high pressure side, as mentioned above, considering the construction of a maximum of 1000φ, 500 to 9
If the pressure drops to 7-, it's just right.

以上の範囲の中で引上げスピード、回転数、吐出量等を
訓節し任意の掘削径を設定する。
Within the above range, set the desired excavation diameter by adjusting the pulling speed, rotation speed, discharge amount, etc.

次に杭の施工に移る。これに用いる装置としては防音装
置付の各種機械がある。即ち爆発音や排煙が発生し防音
装置の付は難いディーゼルハンマーのような形式は不向
きで、逆に油圧ハンマーや単なるモンケンを用いるが、
ある意味では細かい打撃作用とも思えるバイブレーショ
ン方式等で杭を打設する方法を取る。特に本発明によれ
ば一打撃で相当量貫入するよう配慮しであるから、支持
層イ」近までの貫入は過度の打撃が一度に杭に力えられ
ないよう打撃エネルギーを調節できるシステムでなけれ
ばならず、その意味でもディーゼルハンマー型の装置は
不向きである。この結果、支持層伺近まで改質した部分
での打撃施工はほぼ無振動無騒音で貫入できる。この後
支持層へは必要な長さだけ打撃貫入させるが、これは大
きな支持力を得るだめの最後の仕上げであり、騒音は防
音装置で、又振動は相当深い所を打設することになるの
でほとんど影響なく打設することができる。
Next, move on to the construction of the piles. As equipment used for this purpose, there are various types of machines equipped with soundproofing devices. In other words, diesel hammers, which generate explosive noise and exhaust smoke and are difficult to install soundproofing devices, are not suitable; on the other hand, hydraulic hammers or simple Monken hammers are used.
In a sense, we use a method of driving piles using a vibration method, which can be thought of as a fine impact action. In particular, according to the present invention, consideration is given to a considerable amount of penetration with one blow, so a system that can adjust the blow energy so that excessive blows are not applied to the pile at once is required in order to penetrate close to the support layer A. Of course, a diesel hammer type device is unsuitable in that sense as well. As a result, impact construction can be carried out in the modified part close to the support layer with almost no vibration or noise. After this, the supporting layer is penetrated by hammer for the required length, but this is the final finishing touch to obtain a large supporting force, and noise must be prevented by soundproofing equipment, and vibrations must be avoided at a considerable depth. Therefore, it can be poured with almost no impact.

しかし打設による振動の影響がやはり問題となろう地域
ではそれなりの対応が必要である。このため次のような
処理も場合によっては必要となる。
However, in areas where the effects of vibration caused by pouring are likely to be a problem, appropriate measures must be taken. Therefore, the following processing may be necessary depending on the case.

即ち、予備掘削は支持層直前域で実施することを基本と
していたが、支持層も必要な長さを予備掘削する。この
場合の掘削長さは通常の打設貫入でも21)〜5D(D
:杭径)位貫入されるため本方式でも同程度必要である
。このように支持層でも行えば打設は軽減されることに
なる。尚、この方式では、単に支持層内の予備掘削をそ
れより上部の予備掘削の方法と同じにしてはならない。
That is, preliminary excavation was basically carried out in the area immediately in front of the support layer, but the support layer was also preliminary excavated to the required length. In this case, the excavation length is 21) to 5D (D
: Pile diameter), this method also requires the same amount of penetration. If the support layer is also used in this way, the amount of pouring will be reduced. In addition, in this method, preliminary excavation within the support layer must not be performed simply in the same manner as preliminary excavation above it.

即ち、確実な支持力を確保する/こめ支持層内での掘削
時には例えば水1:七メン) 1.5 (Mfif比)
のような?6 FA度のミルクを注入し、さらにこのミ
ルクの中にはブリージング防止や流水等による逸散を防
ぐ添加剤も加える等配慮が必要である。この結果、打設
は軽減される代りに固結材等補助手段をもって支持力発
現を可能にならしめるものである。
In other words, ensure a reliable supporting force/When excavating within the support layer, for example, water 1:7 m) 1.5 (Mfif ratio)
like? It is necessary to inject milk with a degree of 6 FA and also add additives to this milk to prevent breathing and prevent it from escaping through running water. As a result, while the amount of pouring is reduced, it is possible to develop supporting force using auxiliary means such as consolidation material.

このようにして打設するシステムに於いて、途中軽打で
も出来る限り軽減するには杭の圧入、必要あれば回転圧
入を与えつり軒灯を行うのも一つの方式でありこの回転
は杭の挿入を楽にする作業方式でもある。以上、本発明
は既製杭利用の基本に戻り打撃施工を可能にならしめる
画期的システムである。
In this type of driving system, one method is to press in the piles and, if necessary, apply rotational press-in to create a hanging eave light, in order to reduce as much as possible the occurrence of light hammering during the process. It is also a working method that makes insertion easier. As described above, the present invention is an epoch-making system that returns to the basics of using ready-made piles and enables impact construction.

実施例 第1表に示される土質柱状の施工地盤に対し、第1図に
示すとおシの吐出圧と掘削直径との関係を調査観測し、
第2図における■〜■の予備掘削工程および■〜■の杭
の打込工程を実施した。順序に従って説明する。
Example For the columnar construction ground shown in Table 1, the relationship between the discharge pressure of the toshi and the excavation diameter shown in Figure 1 was investigated and observed,
The preliminary excavation process (■ to ■) and the pile driving process (■ to ■) in FIG. 2 were carried out. Explain in order.

■::入ロッド挿入用マシン(通常ボーリングマシン)
1を設置し、クレーン6を用いて注入ロッド2を建込み
、その後該ロッドをアヤツキングした後回転しなから圧
入する。ばロッドにはスイベル5を介して注入ホース3
と、先端には軸芯に対し略〃ぽ角方向に噴射可能な噴射
口及び切削刃を持つ先端部4とが接合されている。
■:: Input rod insertion machine (normal boring machine)
1 is installed, and the injection rod 2 is erected using the crane 6. After that, the rod is airtightened and then press-fitted while being rotated. The injection hose 3 is connected to the rod via the swivel 5.
A distal end portion 4 having an injection port and a cutting blade capable of ejecting in an approximately angle direction with respect to the axis is joined to the distal end.

使用機器:注入ポンプ PG−50 噴射口径 2.2− 注入ロッド 85閉φ ■::入ロッドを継ぎ足しながら圧入を継続する。Equipment used: Infusion pump PG-50 Injection diameter 2.2- Injection rod 85 closed φ ■: Continue press-fitting while adding the inlet rod.

■:支支持層l型直前到達した注入ロッドは挿入を完了
する。
(2): The injection rod that has arrived just before the support layer l-type completes its insertion.

■二次に掘削工程に移るが注入ロッド2は同じく回転さ
せながら高圧で水又はセメントミルク等を噴射しつつ引
上げる。
(2) Next, the process moves to the excavation process, where the injection rod 2 is similarly rotated and pulled up while injecting water, cement milk, etc. at high pressure.

■:噴射による掘削は土質、固さ等に応じ処理方法が異
るが、第2図で示した例で行けば(イ)〜0今まで5種
類の緩め方を実施している。即ちこの例の中ではr−t
の場合が最大に緩められ、丁度この部分は中間層と言え
る部分と考えて良い。一方(→の部分はほとんど緩めて
おらず、この部分は例えば軟弱なシルト地帯であり元元
はとんど緩める必要がないので緩め方も少ない。この様
に計画的に実施し地表面近くまで実施して工程を終了す
る。
■: Excavation by injection differs depending on soil quality, hardness, etc., but in the example shown in Figure 2, (a) - 0 Up to now, five types of loosening methods have been implemented. That is, in this example, r-t
The case is the most relaxed, and this part can be considered to be the middle layer. On the other hand, the part marked (→) has hardly been loosened. This part is, for example, a soft silt area and there is little need to loosen the original, so there are few loosening methods. Execute and complete the process.

■二次に杭の打設工程に入る。杭打やぐら7及び騒音対
策を施したハンマー8を用意し杭9を建込む。
■Secondly, the pile driving process begins. A pile driving tower 7 and a hammer 8 with noise countermeasures are prepared and piles 9 are erected.

■:垂直に立てた後打設に入る0 ■:jM工は支持層重0まで杭9を継ぎだして継続され
る。
■: Start driving after vertically standing 0 ■: The jM construction continues by splicing piles 9 until the bearing layer weight is 0.

■::終的には支持層10に打設貫入させて全工程が終
了する。
(2): Finally, the support layer 10 is cast and penetrated, and the entire process is completed.

以下余白 −8ζMargin below −8ζ

【図面の簡単な説明】[Brief explanation of drawings]

第1図■〜■は注入ロッドの吐出圧と掘削直径との関係
線図、第2図は本発明の工程を順次説明する断面図でお
る。 1:注入ロッド挿入用マシン、2:注入ロッド、3:注
入ホース、4:注入ロッド先端部、5:スイベル、6:
クレーン、7:杭打やぐら、8:低騒音打撃装置(ハン
マー)、9:杭、10:支持層 掘1 棧 ((4rl 第1図 [) 0 100 200 300 400 500□水口貢
111こよ30士出/′i、(ケージ圧%・)手続補正
書彷式) 昭和58年12月2日 特許庁長官 若杉 和 夫 殿 1、事件の表示 ロ訃058’閂を許1頭負貝5300
9 号2、発明の名称 低公害杭施工法 3、補正をする者 事件との関係 特許出願人 4、ネili正命令の日付 6、補正の内容 ゛ ゛ (1)、明細書に添付の図面の第1図。 第2図を別紙のとおり補正する。 以上 手続補正書(自発) 1 事件の表示 昭和58年特許願第 153009 
号2 発明の名称 低公害杭施工法 a 補正をする者 事件との関係 特許出願人 大阪府大阪市北区堂島浜1丁目2番6号4、補正の対象 明細書の「発明の詳細な説明」 及び「図面の簡単な説明」〜の栖 5、補正の内容 (1)明細書、第11 頁第8行、「第1図」を1第2
図」と補正する。 (2)同、第11頁第9行、「第2図」を・「第1図」
と補正する。 (3)同、第12頁第11行、「第2図」を「第1図」
と補正する。 (4)明細書、第15頁第2〜4行、[第1図■〜■は
・・・・・・・・・・・・・・・断面図である。」をつ
ぎの文章に補正する。 「第1図■〜■は予備掘削工程を順次説明する側断面図
、同■〜■は杭の打込工程を順次説明する側断面図、第
2図は注入ロッドの吐出圧と掘削直径との関係線図であ
る。」 以上
FIGS. 1-1 are diagrams showing the relationship between the discharge pressure of the injection rod and the excavation diameter, and FIG. 2 is a sectional view sequentially explaining the steps of the present invention. 1: Injection rod insertion machine, 2: Injection rod, 3: Injection hose, 4: Injection rod tip, 5: Swivel, 6:
Crane, 7: Pile driving tower, 8: Low-noise impact device (hammer), 9: Pile, 10: Supporting layer 1 棧((4rl Figure 1 [) 0 100 200 300 400 500 □ Mitsugu Mizuguchi 111 Koyo 30 (Cage Pressure %/) Procedural Amendment Form) December 2, 1981 Kazuo Wakasugi, Commissioner of the Japan Patent Office 1, Incident Indication RO 058' 1 head and shellfish 5300
9 No. 2, Name of the invention Low-pollution pile construction method 3, Relationship with the case of the person making the amendment Patent applicant 4, Date of Neili official order 6, Contents of the amendment ゛ ゛(1), Drawings attached to the description Figure 1. Figure 2 is corrected as shown in the attached sheet. Written amendment to the above procedures (voluntary) 1 Indication of the case 1982 Patent Application No. 153009
No. 2 Name of the invention Low-pollution pile construction method a Relationship with the case of the person making the amendment Patent applicant 1-2-6-4 Dojimahama, Kita-ku, Osaka-shi, Osaka Prefecture, "Detailed description of the invention" in the specification to be amended and ``Brief Description of the Drawings'', Section 5, Contents of Amendment (1) Specification, page 11, line 8, ``Figure 1'' has been replaced with 1, 2.
Correct it to "Fig." (2) Same, page 11, line 9, "Figure 2" and "Figure 1"
and correct it. (3) Same, page 12, line 11, "Figure 2" was replaced with "Figure 1"
and correct it. (4) Specification, page 15, lines 2 to 4, [Figure 1 ■ to ■ are sectional views. ” to the following sentence. "Figures 1 - 2 are side sectional views sequentially explaining the preliminary excavation process, 2 - 2 side sectional views sequentially explaining the pile driving process, and Figure 2 shows the relationship between injection rod discharge pressure and excavation diameter. This is a relationship diagram of

Claims (1)

【特許請求の範囲】[Claims] 注入ロッドを地中に挿入しこの注入ロッドを回転引上げ
あるいは回転降下を行いつつ、軸芯に対し略に直角方向
に水又はセメントミルク等全50胸/−〜500Kq/
cII!の高圧で1射して地盤を緩める予備工程と、こ
の俵に既製杭を低騒音の打水装置を用い支持層付近まで
軽打で挿入させた後、同装置で支持層へ杭を貫入させる
工程とからなる低公害杭施工法
Insert the injection rod into the ground, and while rotating the injection rod up or down, pour a total of 50 volumes of water or cement milk, etc./- to 500Kq/ in a direction approximately perpendicular to the axis.
cII! A preliminary process involves loosening the ground by applying one shot of high-pressure water to the bales, and then inserting ready-made piles into the bales using a low-noise water-driving device to the vicinity of the support layer, and then penetrating the piles into the support layer using the same device. Low pollution pile construction method consisting of process
JP15300983A 1983-08-24 1983-08-24 Low-pollution piling work Pending JPS6047118A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15300983A JPS6047118A (en) 1983-08-24 1983-08-24 Low-pollution piling work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15300983A JPS6047118A (en) 1983-08-24 1983-08-24 Low-pollution piling work

Publications (1)

Publication Number Publication Date
JPS6047118A true JPS6047118A (en) 1985-03-14

Family

ID=15552958

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15300983A Pending JPS6047118A (en) 1983-08-24 1983-08-24 Low-pollution piling work

Country Status (1)

Country Link
JP (1) JPS6047118A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04169618A (en) * 1990-11-01 1992-06-17 Hokukon:Kk Forming process for foot-fixing section used in pile fixation
JP2003082658A (en) * 2001-09-12 2003-03-19 Asahi Kasei Corp Partially constructed soil cement composite pile

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04169618A (en) * 1990-11-01 1992-06-17 Hokukon:Kk Forming process for foot-fixing section used in pile fixation
JP2003082658A (en) * 2001-09-12 2003-03-19 Asahi Kasei Corp Partially constructed soil cement composite pile
JP4641369B2 (en) * 2001-09-12 2011-03-02 旭化成建材株式会社 Partially built soil cement composite pile

Similar Documents

Publication Publication Date Title
JP2006169942A (en) Vibrating-rotating pile driver and vibrating-rotating pile driving method
JPS6047118A (en) Low-pollution piling work
KR101812463B1 (en) Rrotating-press type pile construction method by using tip-enlarged pile
JP2952324B2 (en) Dynamic injection method of ground improvement
JP6798845B2 (en) Displacement-reducing compaction sand pile construction hollow pipe and compaction sand pile construction method
JPH06287943A (en) Foot protection method for tip of foundation pile and cylindrical foundation pile
JP4884276B2 (en) Rotating press pile construction method and slope construction equipment
JP2016156150A (en) Construction method of reinforcing body with freely widening diameter that uses partial cylindrical body, and aseismic reinforcement method for existing earth structure using reinforcing body
KR100975409B1 (en) System for double-drilling
JP2000154532A (en) Ground improving construction method and excavating device therefor
JP2941590B2 (en) Rotary impact drilling tools and drilling methods
JPS594029B2 (en) Penetration piping method and equipment that simultaneously strengthens the consolidation of the ground
JP2002038469A (en) Execution method of precast pile
JPS5819836B2 (en) Large-diameter vertical hole drilling method
JPS6112053B2 (en)
JPS6012492B2 (en) Root hardening method using ready-made piles
JPS55155823A (en) Burying method for pile
JP2582724B2 (en) Drilling equipment for foundation ground
JPS5944421A (en) Method and apparatus for construction of foundation pile
JPS61165414A (en) Stabilization work for ground
JPS6140817B2 (en)
JPS6140816B2 (en)
JP2023105455A (en) Ground improvement method by compaction
JP2789370B2 (en) Piling method
JPS57146833A (en) Pressure-driving work of knotted pile