JPS6036546Y2 - Marine civil engineering vessel - Google Patents

Marine civil engineering vessel

Info

Publication number
JPS6036546Y2
JPS6036546Y2 JP6998878U JP6998878U JPS6036546Y2 JP S6036546 Y2 JPS6036546 Y2 JP S6036546Y2 JP 6998878 U JP6998878 U JP 6998878U JP 6998878 U JP6998878 U JP 6998878U JP S6036546 Y2 JPS6036546 Y2 JP S6036546Y2
Authority
JP
Japan
Prior art keywords
work
air chamber
vessel
conveyor
stones
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP6998878U
Other languages
Japanese (ja)
Other versions
JPS54172495U (en
Inventor
定夫 三上
久 加納
Original Assignee
三菱重工業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 三菱重工業株式会社 filed Critical 三菱重工業株式会社
Priority to JP6998878U priority Critical patent/JPS6036546Y2/en
Publication of JPS54172495U publication Critical patent/JPS54172495U/ja
Application granted granted Critical
Publication of JPS6036546Y2 publication Critical patent/JPS6036546Y2/en
Expired legal-status Critical Current

Links

Landscapes

  • Underground Or Underwater Handling Of Building Materials (AREA)
  • Framework For Endless Conveyors (AREA)

Description

【考案の詳細な説明】 従来の工法で海洋等に護岸を築造する場合、最も困難な
作業は、護岸の基礎捨て石堤の構築である。
[Detailed description of the invention] When constructing a seawall in the ocean using conventional construction methods, the most difficult task is to construct a stone embankment as the foundation for the seawall.

その理由は、基礎用捨石は護岸に影響する波浪の力、特
に例えば台風の如く、非常に強力な水圧がくり返しかか
る場合に、基礎用捨て石が安定して海底に静止する場合
の安定力は互いの摩擦力と自重に依る事は衆知であり、
そのため、基礎堤を構成する各種の石材即ち、大小のサ
イズのものを、うまく取並べる事と、その基礎石の上に
設置するコンクリートケーソンの接触レベルを整え難い
ことにある。
The reason for this is that when foundation rubble is repeatedly subjected to wave forces that affect the seawall, especially extremely strong water pressure such as in typhoons, the stability of the foundation rubble when it rests stably on the seabed is mutually unstable. It is common knowledge that it depends on the frictional force and own weight of
Therefore, it is difficult to properly arrange the various stones that make up the foundation embankment, that is, those of various sizes, and to adjust the contact level of the concrete caissons that are installed on the foundation stones.

波浪力に耐えるためこれらの基礎石は、しかも一般に、
数十に9から数百kg場合によれば、1〜2TOHに及
ぶものが使用される。
In order to withstand wave forces, these foundation stones are generally
Depending on the case, 1 to 2 TOH is used.

しかも、これらは例えば陸上の石垣の如く構築されると
考えてさしつかえない。
Moreover, it is safe to assume that these structures will be constructed like, for example, stone walls on land.

したがって今までに種々な形態の大型均し機等も考案さ
れているがいづれも実用化されているとは云えない。
Therefore, although various types of large leveling machines have been devised up to now, it cannot be said that any of them have been put into practical use.

したがって相変らず、潜水夫に依る手作業と、クレーン
船を利用して、海底での基礎捨て石堤を構築していると
云う現況にある。
Therefore, the current situation is that the foundation stone embankment is still being constructed on the seabed using manual labor by divers and the use of crane ships.

従来の工法により海洋等に護岸を築造する一実施例を詳
しく説明すると、まずクレーン船に土運船を横づけし、
パケットをもって、土運船より構築用石材をつかみ上げ
、海底の堤上面の水深を計りながら水面上から適当な所
に、石材を投入する。
To explain in detail one example of constructing a seawall in the ocean using the conventional construction method, first, an earth carrier is placed next to a crane ship,
Grab the construction stones from the earth carrier with a packet, and while measuring the depth of the water on the surface of the embankment on the seabed, place the stones at an appropriate location from above the water surface.

この作業をくり返しつつ、基礎捨て石堤の荒投入を行な
う。
While repeating this work, the foundation stone embankment was roughly laid.

その次に潜水夫は、水中で遺り方と称する作業を水中で
レベル出しの水平木材を荒仕上げの上に設け、スタンド
用立木を組み上げ潜水夫の手作業で上均し作業を行う。
Next, the diver performs a process called ``remaining'' underwater, setting up leveled horizontal timbers on top of the rough finish, assembling the standing timber for the stand, and leveling the top by hand by the diver.

これら作業を海面中、10〜30mの中で行なう事は、
海水の汚れによる視認の不良を招来し非常に困難な作業
を強いるという不具合があった。
Carrying out these operations at a depth of 10 to 30 meters below sea level means that
There was a problem in that the seawater contamination caused poor visibility, making the work extremely difficult.

本考案はかかる不具合を解消した海洋土木工事船を提案
しようとするもので、その構成とするところは、昇降可
能な着底脚を有し、その着底によって一定海域に帯留可
能な工事船と、同工事船に基端を俯仰及び旋回可能に枢
支される作業コンベヤと、同作業コンベヤの先端に設け
られ、下方が外部に開放され上部及び周囲が気密状に囲
われ、かつ、水中にて充気可能な気室と、同気室内に設
けられた作業機と、上記気室の近傍に水中にても作業員
が入室のまま同気室内を目視しつつ上記作業機を操作し
得る如く設けられた操作室とを備えてなることを特徴と
する海洋土木工事船であって本考案は、海底での捨て石
作業を常に目視出きる状態にするために、水圧とバラン
スさせた空気室を海底に設け、その中に作業機本体を修
納させると共に、これらの諸装置を、台船から海底中に
達したコンベヤ先端に設置し更に該諸装置に接近した位
置に耐圧の操作室を設け、その内部に作業機、コンベヤ
装置等の操作卓を設置し、操作員がその中に入って操作
する。
The present invention aims to propose a marine civil engineering construction vessel that eliminates such problems.The structure is such that it has bottom landing legs that can be raised and lowered, and can be anchored in a certain sea area by landing on the bottom. , a work conveyor whose base end is pivotably supported on the construction ship so that it can be elevated and rotated; an air chamber that can be filled with air, a working machine installed in the same air chamber, and a worker who can remain in the room and operate the working machine while visually observing the interior of the same air chamber, even if the worker is underwater near the air chamber. The present invention is a marine civil engineering vessel characterized by having an operation room equipped with an air chamber, which is equipped with an air chamber balanced with the water pressure, in order to always be able to visually see the disposal work on the seabed. In addition to installing the equipment on the seabed and repairing the work equipment therein, these devices will be installed at the tip of the conveyor that reaches the bottom of the sea from the barge, and a pressure-resistant operation room will be located close to the various devices. A control console for work equipment, conveyor equipment, etc. is installed inside the machine, and an operator enters and operates the machine.

云う迄もなくこの操作室には、常圧の空気を送入し、操
作員は地上と同様な状態で捨て石の積上げ作業、均し作
業を空気室を通して目視しながら非常に能率良く、安全
に、しかも良視界のもとに、行う事が出来る。
Needless to say, normal-pressure air is fed into this control room, and the operators work on stacking and leveling the stones in the same conditions as on the ground, while visually observing through the air chamber, very efficiently and safely. , and can be done under good visibility.

しかも、大型耐圧の重量の大きいシェルを必要とせず、
極めて、コンパクトで安価な海底作業機の性能を有する
、海洋土木工事船を提供する。
Moreover, there is no need for a large pressure-resistant and heavy shell,
To provide a marine civil engineering vessel having the performance of an extremely compact and inexpensive submarine working machine.

本考案の更に他の一つの特徴は本海洋土木工事船は、巨
大な体積の捨て石類を、能率良く施工する必要上、クレ
ーン船でバッチ的にグラブを用いて、土運船上の石材等
をハンドリングする事を連続的に、パケットバージ船の
パケットから該船のコンベヤで本海洋土木工事船に移載
させるシステムを有し、このシステムにより、海洋土木
工事船の上下、左右の旋回自在なコンベヤを海中、ある
いは陸上、あるいはケーソン等の砂、砂利詰めの多機能
を有し同時に、該海洋土木工事船の強力な係留能力を利
用しての他船の係留にも利用可能な面で多くの利点を持
つものである。
Another feature of the present invention is that this offshore civil engineering vessel uses a crane ship to grab stones in batches to remove stones, etc. from the earth-carrying vessel, in order to efficiently carry out the construction of huge volumes of waste stones. We have a system that continuously transfers the handling from the packets of the packet barge to the marine civil engineering vessel using the ship's conveyor. It has many functions in the sea, on land, and for filling sand and gravel in caissons, etc., and at the same time, it can be used for mooring other ships by utilizing the strong mooring capacity of the marine civil engineering vessel. It has advantages.

次に本考案の一実施例について図面により説明する。Next, one embodiment of the present invention will be described with reference to the drawings.

1図及び第2図は、海洋土木工事船(以后本船と称す)
4と、これに砂、砂利、石材等を供給する、パケットバ
ージ(以后バージと称す)1の組合せを示す。
Figures 1 and 2 show a marine civil engineering vessel (hereinafter referred to as the main vessel).
4 and a packet barge (hereinafter referred to as "barge") 1 that supplies sand, gravel, stones, etc.

バージ1には、パケット2を多数甲板上の両側に設置し
、甲板上中央部に、排出コンベヤ3を設けている。
A barge 1 has a large number of packets 2 installed on both sides of the deck, and a discharge conveyor 3 provided at the center of the deck.

パケット2の舷側を、油圧シリンダ2′で持ち上げ中央
部の排出コンベヤ3にパケット2内の積載物を移送し、
本船側に排出する。
The side of the packet 2 is lifted up by the hydraulic cylinder 2', and the load inside the packet 2 is transferred to the discharge conveyor 3 in the center.
Discharge to the ship side.

本船4には、受入れコンベヤ5を設は本船4の后方に接
舷されたバージ1より排出コンベア3によって排出され
る積載物を受けとる。
The ship 4 is provided with a receiving conveyor 5 for receiving cargo discharged by a discharge conveyor 3 from a barge 1 attached to the back of the ship 4.

受入コンベヤ5の下側には作業コンベヤ7の一端と水平
方向にスイング自在にしている旋回部6を固着する前后
動する台車18を設置する。
A truck 18 that moves forward and backward is installed below the receiving conveyor 5 to which a rotating part 6 that can freely swing in the horizontal direction is fixed to one end of the work conveyor 7.

したがって作業コンベヤ7は台車18上で前厄移動が可
能でしかもスイングする事が出きる。
Therefore, the work conveyor 7 can be moved on the cart 18 and can also swing.

又台車18には、作業コンベヤ7の中央部をワイヤ9で
吊り巻上げ機8で、上下に取付角度を移動させる事が出
きる。
Further, the central part of the work conveyor 7 is suspended on the trolley 18 by a wire 9, and the mounting angle can be moved up and down using a hoisting machine 8.

作業コンベヤ7の一端には平行4辺形を形成するリンク
機構を設は該リンク機構の他端には作業コンベヤ7の俯
仰角の如何にかかわらず水平に近い状態を保持する支え
台枠10を設け、その上部に操作室11を設ける。
A link mechanism forming a parallelogram is provided at one end of the work conveyor 7, and a supporting frame 10 is provided at the other end of the link mechanism to maintain a nearly horizontal state regardless of the elevation angle of the work conveyor 7. and an operation chamber 11 is provided above it.

該操作室11は水圧に耐える構造とし、操作具の必要と
する空気や、操作に必要な操作卓を設ける等する。
The operation room 11 has a structure that can withstand water pressure, and is provided with air required by the operation tools and an operation console necessary for operation.

その前方には、その前方に操作窓11′を設ける。An operation window 11' is provided in front of it.

更に支え台枠10の下方には、陸上等の建設機械の一種
である、油圧式掘削機を設ける。
Further, below the support frame 10, a hydraulic excavator, which is a type of land-based construction machine, is provided.

しかしながらこの掘削機のフォーク13.14は同時に
作動さす場合岩石もつかむ事が出来る事は図の構成にお
いて明白である。
However, it is clear in the configuration of the diagram that the forks 13, 14 of this excavator can also grip rocks when activated at the same time.

又フォーク13た゛けで作動させれば掘削機のシャベル
同様にも使用出きる。
Also, if operated with the fork 13, it can be used like a shovel on an excavator.

この作業機12、フォーク13.14は遠隔操作可能で
あり、フレキシブルな気密布で構成される空気室カバー
15と、ワイヤネット17は支台枠にその一端と回転自
在にした可動アーム16にその下端を固着される。
The working machine 12 and forks 13 and 14 can be remotely controlled, and an air chamber cover 15 made of flexible airtight cloth and a wire net 17 are attached to one end of the support frame and a movable arm 16 that is rotatable. The bottom end is fixed.

又その他端は、操作室11前に固定した壁体19に固着
する。
The other end is fixed to a wall 19 fixed in front of the operation room 11.

又その壁体19の上部は空気管20に接続し、作業時は
空気カバー15の中に空気を送り込んで水を排除し、作
業局部の目視を可能にする。
The upper part of the wall 19 is connected to an air pipe 20, and during work, air is sent into the air cover 15 to remove water and enable visual inspection of the working area.

その付近には図示しない照明灯を設ける。An illumination light (not shown) is installed in the vicinity.

更に操作窓11′に通ずるフード11″をも設ける。Furthermore, a hood 11'' communicating with the operation window 11' is also provided.

かかる構成において、操作室11からは作業機12およ
び海底の上面は、海水の流れや水深外光の状態の如何を
問わず常に操作室11からよく観る事が出きる。
With this configuration, the operating machine 12 and the upper surface of the seabed can always be clearly seen from the operating room 11, regardless of the state of the seawater flow or water depth and external light.

したがって、作業コンベヤ7から供給される石材、海底
の基礎捨て石の均し状態を常に、観測し得るものである
Therefore, it is possible to constantly observe the leveling condition of the stones supplied from the work conveyor 7 and the foundation stones on the seabed.

本船4には又2本のスパッド20′を設は操業中の安定
を保つものである。
The vessel 4 is also provided with two spuds 20' to maintain stability during operation.

このスパッド20′は操業域の海象により4本に増す事
も可能に配置させうる。
The number of spuds 20' can be increased to four depending on the sea conditions in the operating area.

又本船4には、更に公知の4ケのアンカを配置させ、ウ
ィンドラスで作動させ得る。
Additionally, the ship 4 may further be provided with four known anchors, which can be operated by a windlass.

次に海底の基礎捨て石堤の構築の要領を説明する。Next, we will explain the procedure for constructing a foundation stone embankment on the seabed.

第3図、第4図は捨て石の要領である。Figures 3 and 4 show the outline of throwing stones.

作業コンベヤ7を左右に第3図の矢印A、同A′のよう
にスイングすると同時に、順次后退させる。
The work conveyor 7 is swung left and right as shown by arrows A and A' in FIG. 3, and at the same time is sequentially retreated.

この場合必要に応じて空気カバー15のアームは上昇さ
せておく場合もある。
In this case, the arm of the air cover 15 may be raised if necessary.

それは石材の一部が下部アームに当り、損傷させる危険
があるからである。
This is because there is a risk that some of the stones will hit the lower arm and cause damage.

次に第5図、第6図に示す様に下部アーム16を降し、
そのアーム16の下端が作る水平を基準にセットするが
基準ボール100の頂部を基準とし、hを本船から測定
しhをもって規定する、水面の高さは潮の干満を考慮す
ればいい。
Next, lower the lower arm 16 as shown in FIGS. 5 and 6,
The level created by the lower end of the arm 16 is set as a reference, and the top of the reference ball 100 is used as a reference, and h is measured from the ship and defined as h.The height of the water surface can be determined by taking into account the ebb and flow of the tide.

これらの方法は公知である。These methods are known.

したがって、水深Hとhと作業コンベヤの角度θから海
底の基準を作る事は明白である。
Therefore, it is obvious that the seabed standard is created from the water depths H and h and the angle θ of the work conveyor.

作業中のθの修正は本船上から水中の操作員に連絡する
事は容易である。
Corrections to θ during work can be easily communicated to the underwater operator from onboard the ship.

かかる関係において作業機12を操作しフォーク13で
均しながら場合によりフォーク14との共同操作により
大石の一部を取去る等の操作も行う。
In such a relationship, the operator operates the working machine 12 and performs operations such as leveling with the fork 13 and, in some cases, removing part of the large stone in conjunction with the fork 14.

又ある場合には小型の石を均しつつ平担にする作業も可
能である。
In some cases, it is also possible to level small stones and make them flat.

これらの作業は空気カバーの内部で作業状態を操作員が
目視しつつ行なえる事は構造の説明通りである。
As explained in the structure, these operations can be performed while the operator visually observes the operating conditions inside the air cover.

これらの一連の作業範囲は作業コンベヤ7の台車18の
ストローク円で定まる。
These series of work ranges are determined by the stroke circle of the cart 18 of the work conveyor 7.

その範囲の作業が完了すればスパッド20′を抜き上げ
本船をアンカの支持力を利用し台車18のストローク分
だけパージ側に移動させる、と再びスパッド20′を打
ち込み再び前記の作業をくり返す。
When the work in that range is completed, the spud 20' is pulled out and the vessel is moved to the purge side by the stroke of the truck 18 using the supporting force of the anchor, and the spud 20' is driven in again and the above-mentioned work is repeated.

次にかくの如く構築した基礎捨て石の上に公知の方法で
ケーソンを設置するがそのケーソン内部には砂、砂利等
の中詰めをパケットパージ1から本船を介して急速に行
う事が出きる。
Next, a caisson is installed by a known method on top of the foundation stones constructed as described above, and the inside of the caisson can be rapidly filled with sand, gravel, etc. from the packet purge 1 via the ship.

ケーソンの設置が完了すれば海洋の外海に対する基礎捨
て石堤の斜面の上に(法面と称する)は大形の捨て石を
設置する必要がある。
Once the caissons have been installed, it is necessary to install large stones on the slope of the basic stone embankment facing the open sea (referred to as the slope).

この場合の作動をケーソン25に土砂を充たし、その基
部を捨て石で固める例として第7図及び第8図に示す。
The operation in this case is shown in FIGS. 7 and 8 as an example in which the caisson 25 is filled with earth and sand and its base is hardened with throw stones.

特に第8図ではフォーク13.14で作業コンベヤ7を
介して搬送した大形石材を順次取ならべる様子を示して
いる。
In particular, FIG. 8 shows how large stones conveyed via the work conveyor 7 are successively arranged by forks 13 and 14.

これらの作業が完了すれば護岸の上塗コンクリートを施
工し護岸工事は完了したと考えていい。
Once these works are completed, the top coat of concrete for the revetment will be applied and the revetment work can be considered complete.

しかる后は、本船を護岸近くに係留腰パージ用の係留装
置と護岸内側への埋立用の産業廃棄物投棄のために使用
されるコンベヤとしても、利用できる事は第9図に示す
After that, the vessel can be moored near the seawall and used as a mooring device for purge and as a conveyor for dumping industrial waste for landfill inside the seawall, as shown in Figure 9.

産業廃棄物の最終処理は海面を利用して埋立てる事で処
理されるが海面埋立用利用のために護岸は完全にしめ切
られた中に投棄する事が望ましく、そのため完全に仕切
られた護岸内部への投棄は外海側からのみ行う事が必要
であり、かかる必要性からも本船とパージの組合せは、
その意味で非常に望ましい作動を行う事は以上の説明で
明白である。
The final treatment of industrial waste is by landfilling using the sea surface, but it is desirable to dump it in a completely closed seawall for use as a sea surface landfill, so a completely partitioned seawall is used. Dumping into the interior must be done only from the open sea side, and due to this necessity, the combination of the main vessel and purge is
In this sense, it is clear from the above explanation that a very desirable operation is performed.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本考案の一実施例の平面図、第2図はその側面
図、第3図ないし第8図は上記実施例の使用情況の説明
図で第3図は捨て石の要領図の平面図、第4図はその側
面図、第5図は捨て石を均らす場合の要領図の平面図、
第6図はその側面図、第7図及び第8図はケーソンに土
砂を充たしてそれを護岸体とし、かつ、その基部を捨て
石で固める要領図を段階的に示した側断面図、第9図は
産業廃棄物の投棄でもって埋立に役立てる一例の側断面
図である。 4・・・・・・本船、6・・・・・・旋回部、7・・・
・・・作業コンベヤ、8・・・・・・巻上げ機、9・・
・・・・ワイヤ、10・・・・・・支え台、11・・・
・・・操作室、12・・・・・・作業機、13゜14・
・・・・・フォーク、15・・・・・・空気室カバー、
16・・・・・・可動アーム、17・・・・・・ワイヤ
ネット、19・・・・・・壁体、20・・・・・・空気
管、20′・・・・・・スパッド。
Fig. 1 is a plan view of one embodiment of the present invention, Fig. 2 is a side view thereof, Figs. 3 to 8 are explanatory diagrams of the usage situation of the above embodiment, and Fig. 3 is a plan view of the outline of the sacrificial stone. Fig. 4 is a side view, Fig. 5 is a plan view of the procedure for leveling discarded stones,
Figure 6 is a side view of the same, Figures 7 and 8 are side sectional views showing step-by-step how to fill the caisson with earth and sand and use it as a seawall, and solidify its base with rubble. The figure is a side sectional view of an example of dumping industrial waste that is useful for landfill. 4... Main ship, 6... Turning section, 7...
...Work conveyor, 8...Hoisting machine, 9...
...Wire, 10...Support stand, 11...
...Operation room, 12... Work equipment, 13゜14.
...Fork, 15...Air chamber cover,
16...Movable arm, 17...Wire net, 19...Wall body, 20...Air tube, 20'...Spud.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 昇降可能な着底脚を有し、その着底によって一定海域に
帯留可能な工事船と、同士事船に基端を俯仰及び旋回可
能に枢支される作業コンベヤと、同作業コンベヤの先端
に設けられ、下方が外部に開放され上部及び周囲が気密
状に囲われ、かつ、水中にて充気可能な気室と、同気室
内に設けられた作業機と、上記気室の近傍に水中にても
作業員が入室のまま同気室内を目視しつつ、上記作業機
を操作し得る如く設けられた操作室とを備えてなること
を特徴とする海洋土木工事船。
A construction ship has a bottom landing leg that can be raised and lowered and can be anchored in a certain sea area by landing on the bottom, a work conveyor whose base end is pivoted to the ship to be able to lift and turn, and a work conveyor that is attached to the tip of the work conveyor. An air chamber is provided, the lower part of which is open to the outside, the upper part and surroundings are enclosed in an airtight manner, and which can be filled with water, a working machine installed in the same air chamber, and an underwater chamber near the air chamber. 1. A marine civil engineering work vessel, characterized in that it is provided with an operation room provided so that a worker can operate the working equipment while visually observing the interior of the same air chamber while entering the vessel.
JP6998878U 1978-05-24 1978-05-24 Marine civil engineering vessel Expired JPS6036546Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6998878U JPS6036546Y2 (en) 1978-05-24 1978-05-24 Marine civil engineering vessel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6998878U JPS6036546Y2 (en) 1978-05-24 1978-05-24 Marine civil engineering vessel

Publications (2)

Publication Number Publication Date
JPS54172495U JPS54172495U (en) 1979-12-05
JPS6036546Y2 true JPS6036546Y2 (en) 1985-10-30

Family

ID=28979352

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6998878U Expired JPS6036546Y2 (en) 1978-05-24 1978-05-24 Marine civil engineering vessel

Country Status (1)

Country Link
JP (1) JPS6036546Y2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS648086A (en) * 1987-07-01 1989-01-12 Canon Kk Recording material and recording method

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60212519A (en) * 1984-04-09 1985-10-24 Kajima Corp Rubble-mound levelling device
WO2009112596A1 (en) * 2008-03-14 2009-09-17 Sanchez Gonzales Jesus Underwater leveller

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS648086A (en) * 1987-07-01 1989-01-12 Canon Kk Recording material and recording method

Also Published As

Publication number Publication date
JPS54172495U (en) 1979-12-05

Similar Documents

Publication Publication Date Title
US2895301A (en) Stabilization of submarine raft foundations
CN109780325B (en) Installation method of underwater pipeline of water taking tunnel of water plant
KR100729864B1 (en) Dredger
CA1050493A (en) Apparatus for excavating and transporting excavated quantities
CN111893944B (en) Environment-friendly submarine reef cleaning construction process
CN111038652A (en) Multifunctional engineering ship
US4150503A (en) Apparatus for excavation and earth removal from aquatic bottoms
JPS6036546Y2 (en) Marine civil engineering vessel
CN1308001A (en) Deep-sea pile driver
EP0205341A1 (en) Underwater ground working apparatus
JP2002070013A (en) Underwater riprap leveler and underwater riprap leveling method
US4360291A (en) Subsea foundation
US4276846A (en) Recovery apparatus
CN211642530U (en) Multifunctional engineering ship
JP4260448B2 (en) Connection method and structure of submerged shaft and horizontal shaft
CN209703599U (en) A kind of underwater hammering constructing device
JPS6073921A (en) Underwater excavator
JP2585195B2 (en) Underwater work machine
JPH0619642Y2 (en) Sea garden building equipment
JPH04363417A (en) Rubble throw-in and levelling device
JPS6233822Y2 (en)
JP2633445B2 (en) Earth removal equipment in cast-in-place pile method
KR20170070794A (en) Shipping equipment for soil and rock underwater and Loading method by using it
EP0145713A1 (en) Apparatus and method for performing work at sea
JPH0841896A (en) Excavating device for caisson