JPS6030797A - Enlarging shield construction method - Google Patents
Enlarging shield construction methodInfo
- Publication number
- JPS6030797A JPS6030797A JP13910083A JP13910083A JPS6030797A JP S6030797 A JPS6030797 A JP S6030797A JP 13910083 A JP13910083 A JP 13910083A JP 13910083 A JP13910083 A JP 13910083A JP S6030797 A JPS6030797 A JP S6030797A
- Authority
- JP
- Japan
- Prior art keywords
- tunnel
- enlarged
- shield
- shield excavator
- expansion
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
(発明の技術分野)
本発明は、通常径トンネルの一部を拡大トンネルとする
拡大/ールド工法に関し、特に、通常径トンネルの拡大
予定区域では、通常径トンネルの施工の手間を省き、直
ちに拡大トンネルの掘削を行在うことができるようにし
た拡大シ・−ルド工法に関する。DETAILED DESCRIPTION OF THE INVENTION (Technical Field of the Invention) The present invention relates to an expansion/fold construction method in which a part of a normal diameter tunnel is expanded into an enlarged tunnel. This invention relates to an expansion shield construction method that allows for immediate excavation of an expansion tunnel without the hassle of.
(従来技術)
従来、通常径トンネルの一部を拡大トンネルとするには
、拡大予定区域の地上より縦穴を掘削し、該縦穴から各
種の掘削機械を導入して、轟該通常径トンネルを拡幅す
るのが一般的であった。(Prior art) Conventionally, in order to enlarge a part of a normal diameter tunnel, a vertical hole is excavated from the ground in the area planned for expansion, and various excavating machines are introduced through the vertical hole to widen the normal diameter tunnel. It was common to do so.
しかし、この方法では、地上の建造物等が近年過密化し
ているので縦穴の掘削場所を確保するのが困難であり、
丑た拡幅工事終了後に縦穴を埋め戻す手間かかかる等の
問題があった。However, with this method, it is difficult to secure a place to excavate a vertical hole as above-ground structures have become overcrowded in recent years.
There were problems such as the time-consuming work required to backfill the vertical hole after the Ushita widening work was completed.
そこで、本件出願人は縦穴の掘削を不要にする拡大トン
ネルの掘削工法を先の出願において提案した。この工法
は、−次シールド掘進機で通常径トンネルを掘削したの
ち、当該トンネルの拡大予定区域の一方端部を部分的に
拡大掘削して、拡大シールド掘進機の発進基地を設け、
−この発進基地で拡大シールド掘進機を組立設置し、拡
大予定区域の全域ですでに張設されている通常径トンネ
ルのセグメントを順次取外しながら拡大シールド掘進機
を推進させて拡大掘削を行々うとともに、拡幅部の内面
に新たにセグメントを施して拡大トンネルを築造するこ
とを特徴とする。Therefore, in a previous application, the present applicant proposed a method for excavating an enlarged tunnel that eliminates the need to excavate a vertical hole. This construction method involves excavating a normal-diameter tunnel with a secondary shield excavator, then partially enlarging and excavating one end of the area scheduled for expansion of the tunnel to provide a starting base for the enlarged shield excavator.
- The expansion shield excavator will be assembled and installed at this starting base, and the expansion excavation will be carried out by propelling the expansion shield excavator while sequentially removing segments of the normal diameter tunnel that have already been installed throughout the area scheduled for expansion. At the same time, a new segment is added to the inner surface of the widened portion to construct an enlarged tunnel.
この既提案の工法によれば施工性および経済性が改善さ
れ、工期の短縮と費用の低減を図ることができる。According to this previously proposed construction method, the workability and economic efficiency are improved, and it is possible to shorten the construction period and reduce costs.
しかし、拡大部が長距離に亘る場合は、通常径トンネル
の施工手間と拡大トンネルの施工手間の重複を回避する
ことが望まれる。However, when the enlarged section extends over a long distance, it is desirable to avoid duplication of the time and effort required to construct a normal-diameter tunnel and the time and effort required to construct an enlarged tunnel.
(発明の目的)
したがって本発明は、通常径トンイ・ルのうち、拡大予
定区域では通常径トンネルの施工の手間を省き、直ちに
拡大トンネルの掘削を行なうことができる拡大シールド
工法を提供することを特徴とする
特に本発明は、カッターを併用して通常径トンネルおよ
び拡大トンネルを掘削することができる拡大シールド工
法を提供することを目的とする。(Objective of the Invention) Therefore, the present invention aims to provide an expansion shield construction method that can eliminate the trouble of constructing a normal diameter tunnel in areas scheduled for expansion among normal diameter tunnels and can immediately excavate an expanded tunnel. Particularly, an object of the present invention is to provide an enlarged shield construction method that can excavate a normal diameter tunnel and an enlarged tunnel by using a cutter in combination.
(発明の主要構成)
本発明の要旨は、通常径トンネルの内径に対応する外径
を持ったカッターを前面に備えた一部シールド据進機で
通常径トンネルを掘削し、同トンイ・ルの拡大予定区域
に到達したところで前記−次シールド掘進機の後方に、
拡大シールド掘進機の発進基地となる拡大部を設け、該
拡大部で拡大シールド掘進機を組立てて前記−次シール
ド掘進機と連結させるとともに、前記カッターの外径が
前記拡大シールド掘進機の外径にほぼ一致するよう、前
記カッターに延長部を継ぎ足し、前記−次7−ルド掘進
機および拡大シール)パ掘進機を一体に同時推進させて
拡大トンネルを掘削することにある。(Main Components of the Invention) The gist of the present invention is to excavate a normal diameter tunnel using a partially shielded stationary machine equipped with a cutter on the front surface having an outer diameter corresponding to the inner diameter of the normal diameter tunnel. After reaching the planned expansion area, behind the above-mentioned next shield excavator,
An enlarged part is provided as a starting base for the enlarged shield excavator, and the enlarged shield excavator is assembled in the enlarged part and connected to the next shield excavator, and the outer diameter of the cutter is the outer diameter of the enlarged shield excavator. The present invention is to add an extension to the cutter so as to substantially match the cutter, and to excavate the enlarged tunnel by simultaneously propelling the 7-rd tunnel excavator and the enlarged seal tunnel excavator.
(発明の実施例) 以下、図面に示す実施例に基づいて本発明を説明する。(Example of the invention) The present invention will be described below based on embodiments shown in the drawings.
本発明工法によると、まず第1〜2図に示すように、従
来と同様構造の一部シールド掘進機1で通常径トンネル
2を拡大予定区域3の一方端部捷で掘削し、通常径トン
ネル2の内面には既存のエレクタ−(図示せず)で−次
セグメント4を施す。According to the construction method of the present invention, first, as shown in Figs. 1 and 2, a normal diameter tunnel 2 is excavated with a partial shield excavator 1 having the same structure as the conventional one at one end of the area 3 to be expanded. On the inner surface of 2, a second segment 4 is applied using an existing erector (not shown).
この場合本発明によると、−次シールド掘進機1−通常
径トンネル2の内径に対応する外径を持ったカッター5
を前面に備えており、また従来と同様カッター5側に掘
削泥水を供給するノズル6と、使用済みの泥水を回収す
るノズル7と、前記−次セグメント4より反力を得て一
部ノールド掘進機1を推進させるジヤツキ8とを備えて
いる。In this case, according to the invention, - the next shield excavator 1 - the cutter 5 with an outer diameter corresponding to the inner diameter of the normal diameter tunnel 2;
In addition, as in the conventional case, there is a nozzle 6 that supplies drilling mud to the cutter 5 side, a nozzle 7 that collects used mud water, and a nozzle 7 that receives a reaction force from the above-mentioned next segment 4 to partially excavate the nord. It is equipped with a jack 8 that propels the aircraft 1.
次に、上記−次シールド掘進機」が前記拡大予定区域3
に到達したところで、通常径トンネル2のそれ以上の掘
削を停止し、−次シールド掘進機1の後方の通常径トン
ネル2において、拡大シールド掘進機9の発進基地とな
る拡大部2aを設ける。この拡大部2aを形成するには
種々な方法が用いられ、例えば手掘り作業や、本件出願
人の既提案に係る円周拡大シールド工法等が用いられ、
拡大部2aの内面には一般((適宜の被覆10が施され
る。Next, the above-mentioned “next shield tunneling machine” is installed in the expansion planned area 3.
When this point is reached, further excavation of the normal diameter tunnel 2 is stopped, and an enlarged portion 2a is provided in the normal diameter tunnel 2 behind the -next shield excavator 1, which serves as a starting base for the enlarged shield excavator 9. Various methods are used to form this enlarged portion 2a, such as manual digging, the circumferential enlargement shield method proposed by the applicant, etc.
Generally, an appropriate coating 10 is applied to the inner surface of the enlarged portion 2a.
次に、上記拡大部2a内で拡大シールド掘進機9の刃口
部9aを組立てる。拡大シールド掘進機9の後方では、
例えば通常径トンネル2の一部セグメント4間に反力受
けJlを設けるとともに、この反力受け11から反力を
得て拡大シールド掘進機9を成る程度推進させる所望数
のジヤツキ]2を設置する。この後、第3〜4図に示す
ように、被覆10の前部を外し、ジヤツキJ2を用いて
拡大シールド掘進機9の刃口部9aを推進させて拡大部
2aから押し出したのち、拡大部2aて中間胴部9bを
組立て、これを刃口部9aの後部に接続する。同様にし
てテール部9c(第5図)も組立てる。Next, the blade mouth portion 9a of the enlarged shield excavator 9 is assembled within the enlarged portion 2a. Behind the expansion shield excavator 9,
For example, a reaction force receiver Jl is provided between some segments 4 of the normal diameter tunnel 2, and a desired number of jacks 2 are installed to obtain reaction force from the reaction force receiver 11 and propel the expanding shield excavator 9 to a certain extent. . After that, as shown in FIGS. 3 and 4, the front part of the covering 10 is removed, and the blade part 9a of the enlarged shield tunneling machine 9 is pushed out from the enlarged part 2a by using the jack J2, and then the enlarged part 2a, assemble the intermediate body portion 9b, and connect this to the rear part of the blade mouth portion 9a. The tail portion 9c (FIG. 5) is also assembled in the same manner.
このように拡大シールド掘進機9を完全に組立てたのち
、拡大シールド掘進機9を進めて一部シールド」朋進機
]の外側に位置させ、両者を一体に結合する。After the expanding shield tunneling machine 9 is completely assembled in this manner, the expanding shield tunneling machine 9 is advanced to a position partially outside the shield "Hoshin Machine" and the two are joined together.
寸だ、上記−次シールド掘進機1が停止してぃる間に、
第7〜8図に示すように、カッター5の周縁に延長部5
aを継ぎ足し、カッター5の外径を拡大シールド掘進機
9の外径とほぼ一致させる。While the above-mentioned shield tunneling machine 1 was stopped,
As shown in FIGS. 7 and 8, an extension 5 is attached to the periphery of the cutter 5.
a is added to make the outer diameter of the cutter 5 almost match the outer diameter of the enlarged shield excavator 9.
な:1)−1拡大シ一ルド掘進機9が一部シールド掘進
機]に到達する捷でに掘削した拡大トンネル3aの壁面
には、新たに二次セグメント】3を装着する。1)-1 A new secondary segment 3 is attached to the wall of the previously excavated expansion tunnel 3a where the expanded shield excavator 9 reaches the shield excavator.
1だ、本実施例では一次シールド掘進機1のジヤツキ8
が前記被覆10外いし二次セグメント1:3から)y−
力を得て、−次および拡大シールド掘進機1.9を同時
に推進させるよう、−次シールドにtii進機1のテー
ル部を取外し、ジヤツキ8の後部に延長部8aを設け、
該延長部8aが二次セグメント】3に当接するようにし
である。1, in this example, the jack 8 of the primary shield excavator 1
is from the outer coating 10 and the secondary segment 1:3) y-
In order to obtain power and simultaneously propel the -next and expanded shield excavator 1.9, remove the tail part of the tii advance machine 1 from the -next shield, provide an extension part 8a at the rear of the jack 8,
The extension portion 8a is adapted to abut against the secondary segment ]3.
しかし、第9図に示すように、拡大シールド、磯9側の
推進ジヤツキ1/Iが両方の7一ルド掘仏機1.9を推
進させる構造としてもよい。However, as shown in FIG. 9, a structure may be adopted in which the expansion shield and the propulsion jack 1/I on the rocky shore 9 side propel both the 71-rudo digging machines 1.9.
上記したように、−次シールド掘進機1と一体になった
拡大シールド掘進機9で拡大予定区域;3に拡大トンイ
、ルを掘削する。したがって、拡大予定区域3では予め
一次シールド掘進機1で掘削した後で、−次セグメント
を取外しながら再度拡大掘削を行なうという手間が省け
る。As described above, the expansion tunnel is excavated in the area to be expanded using the expansion shield excavation machine 9 integrated with the next shield excavation machine 1. Therefore, it is not necessary to excavate the planned expansion area 3 in advance with the primary shield excavator 1 and then carry out the expansion excavation again while removing the -next segment.
丑だ、所定長さの拡大トンネルの掘削が終了した後は、
−次シールド掘進機1より継き足したカッターおよび拡
大シールド掘進機9を分離し、−次7−ルド掘進機1で
再度通常径トンネルを掘削する0
(発明の効果)
以」″説明してきたように本発明によると、トニネルの
拡@工事の際地上から縦穴を掘る必要がなく、丑だ拡大
予定区域では予め通常径トンネルを掘削することなく、
直接拡大トンネルを掘削することができ、施工性が向上
するとともに経済的になる利点が得られる。After completing the excavation of the enlarged tunnel of the specified length,
- Separate the cutter added from the next shield excavator 1 and the enlarged shield excavator 9, and excavate a normal diameter tunnel again with the next 7-rd shield excavator 1. According to the present invention, there is no need to dig a vertical hole from the ground during tunnel expansion work, and there is no need to excavate a normal diameter tunnel in advance in the area where the expansion is planned.
It is possible to directly excavate an enlarged tunnel, which has the advantage of improving construction efficiency and being economical.
第1図〜第8図は/本発明の一実施例に在る拡大シール
ド工法の各工程を示す概略縦断面側面図であって、第1
図は主として通常径トンネルを掘削した状態を示す説明
図、第2図は第1図のn−Lr線に沿う半断面ン1、第
3図は主として拡大シールド掘進機の組立て状態を示す
説明図、第4図は第3図のI\r −+v純に沿う半断
面図、第5図は一部ノールド掘進機と拡大シールド掘進
機の結合状態を示す説明図、第6図は第5図のVl −
VIl線に沿う半断面図、第71シ1は拡大トンネルの
掘削状態を示す説明図、第8図は第7図のvm −vm
線に沼・う半断面図、第9図は本発明の他の実MQ例に
より拡大トンネルを掘削する様子を示す概略縦断面側面
図である。
1・・−次シールド掘進機 2・・通常径トンネル3・
・拡大予定区域 3a・・・拡大トンイ、ル4・−一次
セグメント 5・・カッター5a−延長部 8・推進ジ
ヤツキFIGS. 1 to 8 are schematic vertical cross-sectional side views showing each step of the expanding shield construction method in one embodiment of the present invention;
The figure is an explanatory diagram mainly showing a state in which a normal diameter tunnel has been excavated, Fig. 2 is a half cross section taken along the n-Lr line in Fig. 1, and Fig. 3 is an explanatory diagram mainly showing an assembled state of the expansion shield excavator. , FIG. 4 is a half cross-sectional view taken along the I\r −+v line in FIG. Vl −
A half-sectional view taken along the line VII, No. 71 C1 is an explanatory diagram showing the state of excavation of the enlarged tunnel, and FIG. 8 is the vm-vm of FIG. 7.
FIG. 9 is a schematic longitudinal cross-sectional side view showing how an enlarged tunnel is excavated by another actual MQ example of the present invention. 1.-Next shield tunneling machine 2..Normal diameter tunnel 3.
・Planned expansion area 3a... Expansion gear, 4.-Primary segment 5..Cutter 5a-extension part 8.Propulsion jack
Claims (1)
を前面に備えだ一部シールド掘進機で通常径トンネルを
掘削し、同l・ンネルの拡大予定区域に到達したところ
で前記−次シールド掘進機の後方に、拡大シールド掘進
機の発進基地となる拡大部を設け、該拡大部で拡大シー
ルド掘進機を組立てて前記−次ノールド掘進機と連結さ
せるとともに、前記カッターの外径が前記拡大・ンール
)゛tJ:!進機の外径にほぼ一致するよう、前記カッ
ターに延長部を絆ぎ足し、前記−次シールド掘進機およ
び拡大シールド掘進機の推進ジヤツキのうち、少なくと
も一方を用いて前記拡大部の被覆ないし拡大トンネルに
施したセグメントから反力を得ることにより、前記−次
シールド掘進機および拡大シールド掘進機を同時に推進
させて拡大トンネル掘削することを特徴とする拡大シー
ルド工法。The normal diameter tunnel is excavated using a partial shield excavator equipped with a cutter on the front side having an outer diameter corresponding to the inner diameter of the normal diameter tunnel, and when the area where the tunnel is planned to be expanded is reached, the above-mentioned next shield excavator An enlarged part is provided at the rear of the cutter to serve as a starting base for the enlarged shield excavator, and the enlarged shield excavator is assembled in the enlarged part and connected to the next Nord excavator, and the outer diameter of the cutter is set to the enlarged part. )゛tJ:! Add an extension part to the cutter so that it almost matches the outer diameter of the advancing machine, and cover or enlarge the enlarged part using at least one of the propulsion jacks of the secondary shield excavator and the expansion shield excavator. An expansion shield construction method characterized in that the secondary shield excavation machine and the expansion shield excavation machine are simultaneously propelled to excavate an enlarged tunnel by obtaining a reaction force from the segments applied to the tunnel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP13910083A JPS6030797A (en) | 1983-07-29 | 1983-07-29 | Enlarging shield construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP13910083A JPS6030797A (en) | 1983-07-29 | 1983-07-29 | Enlarging shield construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS6030797A true JPS6030797A (en) | 1985-02-16 |
JPS6346235B2 JPS6346235B2 (en) | 1988-09-14 |
Family
ID=15237484
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP13910083A Granted JPS6030797A (en) | 1983-07-29 | 1983-07-29 | Enlarging shield construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS6030797A (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4854523B2 (en) * | 2007-01-12 | 2012-01-18 | 鹿島建設株式会社 | Tunnel construction method |
-
1983
- 1983-07-29 JP JP13910083A patent/JPS6030797A/en active Granted
Also Published As
Publication number | Publication date |
---|---|
JPS6346235B2 (en) | 1988-09-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPS59106695A (en) | Enlargement shield drilling method | |
JPS6030797A (en) | Enlarging shield construction method | |
JP2742026B2 (en) | Underground tunnel joining method and segment | |
JPS59102088A (en) | Method and apparatus for drilling enlarged tunnel | |
JP3093437B2 (en) | Shield machine | |
JPS6216310B2 (en) | ||
JPH0538093U (en) | Shield excavator capable of underground docking | |
JPS6362637B2 (en) | ||
JPS6217068B2 (en) | ||
JP4257263B2 (en) | How to build a linked wide shield tunnel | |
JP3787807B2 (en) | Tunnel construction method using shield excavator | |
JP4142828B2 (en) | Shield machine | |
JPH0349192Y2 (en) | ||
JPS61146996A (en) | Enlargement shield excavation method | |
JPS6217077B2 (en) | ||
JPS59177497A (en) | Method of construction of expansion and propulsion | |
JPS6088793A (en) | Curve shield construction method | |
JPS59102089A (en) | Enlarging tunnel drilling method | |
JPS6346236B2 (en) | ||
JPS6216312B2 (en) | ||
JPS6088788A (en) | Circumferential shield drilling machine | |
JPS60238599A (en) | Enlarging shield drilling machine | |
JPS59102087A (en) | Tunnel enlarging and drilling apparatus | |
JPS59102094A (en) | Tunnel enlarging and drilling apparatus | |
JPS59102085A (en) | Enlarging shield machine |