JPS60238518A - Ground penetrator - Google Patents

Ground penetrator

Info

Publication number
JPS60238518A
JPS60238518A JP9528184A JP9528184A JPS60238518A JP S60238518 A JPS60238518 A JP S60238518A JP 9528184 A JP9528184 A JP 9528184A JP 9528184 A JP9528184 A JP 9528184A JP S60238518 A JPS60238518 A JP S60238518A
Authority
JP
Japan
Prior art keywords
pile
press
ground
machine
chuck
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP9528184A
Other languages
Japanese (ja)
Other versions
JPH0368968B2 (en
Inventor
Morio Kitamura
精男 北村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Giken Seisakusho Co Ltd
Original Assignee
Giken Seisakusho Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Giken Seisakusho Co Ltd filed Critical Giken Seisakusho Co Ltd
Priority to JP9528184A priority Critical patent/JPS60238518A/en
Publication of JPS60238518A publication Critical patent/JPS60238518A/en
Publication of JPH0368968B2 publication Critical patent/JPH0368968B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/20Placing by pressure or pulling power

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

PURPOSE:To exactly penetrate a pile into the ground by providing a vertically movable penetrating blade to be positioned for its tip downwards from the lower end of a pile when a body is grasped by a chuck along the pile and the pile is penetrated into the body. CONSTITUTION:Existing piles (a) are grasped by clamps 10, and a penetrator 5 together with a pile 4 to be penetrated is grasped by the chuck 3 of a static load type pile constructor 2. In this case, the tip of a penetrating blad 7 is positioned downwards from the lower end of the pile 4. A static pushing load is applied to the chuck 3, the pile 4 is penetrated into the ground, and the blade 7 is pushed down in relation to the pile 4 by an oil-pressure cylinder plunger device 8. The pile 4 can thus be exactly penetrated with the aid of the preceding penetration of the blade 7 into the ground.

Description

【発明の詳細な説明】 発明の技術分野 本発明は地盤貫入機、特にパイル圧入機、詳しくはチャ
ックで被圧入パイルを掴み、これを静押下げ荷重の負荷
により地盤に圧入するようにされたパイル圧入機(以下
、これを静荷重式パイ/1/施工機という)と併用され
る地盤貫入機に関する。
[Detailed Description of the Invention] Technical Field of the Invention The present invention relates to a ground penetrating machine, particularly a pile press-in machine, and more specifically, a chuck grips a pile to be press-fitted and press-fits the pile into the ground by applying a static push-down load. The present invention relates to a ground penetrating machine that is used in combination with a pile press-in machine (hereinafter referred to as a static load type pie/1/construction machine).

発明の技術的背景とその問題点 静荷重式バイ)L7施工機は無騒音、無振動でパイJV
を施工できるし、まだパイル頭部の破損や変形がない。
Technical background of the invention and its problems Static load type Bi) L7 construction machine is noiseless and vibrationless
can be constructed, and there is no damage or deformation of the pile head yet.

しかしパイルにはこれを地上部位で掴むチャックを通じ
押下げ荷重が負荷される、換言すればパイルに(は地上
部位で圧入荷重が加えられる点に問題があった。即ち、
パイ/I/全圧入する場合その圧入抵抗はパイルの先端
抵抗、周表面抵抗、及びセクション抵抗が加ったもので
あり、この点、パイルの地上部位で圧入荷重を負荷する
ことは、これ等の抵抗による力の損失が大きく、パイル
先イ/L/施工機では、地盤中に転石や礫層等の障害物
層があると、パイルの圧入が困難或いは不能となつてい
る。無理にパイルの圧入を強制すればパイル先端の変形
、破損を招いたり、バイμの方向性が悪くなったりし、
バイル倒れ、セクション抵抗の増大等を生じ、パイルの
後続施工ができないに至る。
However, there was a problem in that a push-down load was applied to the pile through a chuck that gripped it at an above-ground location, or in other words, a press-fit load was applied to the pile at an above-ground location.
Pi / I / When performing a full press-in, the press-fit resistance is the addition of the pile tip resistance, circumferential surface resistance, and section resistance. The loss of force due to the resistance is large, and it is difficult or impossible for the pile tip A/L/constructing machine to press in the pile if there is an obstacle layer such as boulders or gravel in the ground. If the pile is forced into the pile, it may cause deformation or damage to the tip of the pile, or the directionality of the biμ may deteriorate.
The pile collapses, the section resistance increases, etc., and subsequent pile construction becomes impossible.

然るに従来、静荷屯式パイ/L/施工機の前足問題点を
簡潔に解消し得る有効な対策が未だ確立されていないの
が実情である。
However, the reality is that no effective countermeasure has yet been established to simply solve the problem with the front legs of static load-tun type pie/L/construction machines.

従来、静荷重式パイル施工機によるパイル施工において
、パイルの圧入を補助するにはジェット水の噴射による
掘削、或いはアーヌオーガーでの掘削を併用する方法に
依存している。これによれば、パイルの圧入に併せてパ
イル先端部位で地盤を掘削する、即ちパイルの先端に掘
削手段が補設されることになるからパイルの圧入それ自
体の効果は向上するが、前者では水の浸透による地盤の
緩みを伴い、後者ではオーガーによる掘削穴が大き過ぎ
、何れもこのような附加的補助手段を併用しないパイル
圧入の単独的施工の場合に比較し、パイルをしつかシと
圧入することが困難であるし、また両者共に上記掘削に
よる附加的圧入補助手段の併用で静荷重式パイル施工機
全体の規模が相当大きくなることを免れない。斯くして
従来公知の工法では静荷重式パイル施工機の前述した問
題を簡潔には解消し得ない。
Conventionally, in pile construction using a static load type pile construction machine, the method of assisting the press-in of the pile has relied on excavation using jet water or excavation using an Arnu auger. According to this, the ground is excavated at the tip of the pile at the same time as the pile is press-fitted, that is, the digging means is additionally installed at the tip of the pile, so the effect of the pile press-in itself is improved, but the former In the latter case, the hole drilled by the auger is too large, and it is difficult to keep the pile firmly in place compared to the case of independent pile press-in construction without such additional auxiliary means. It is difficult to press-fit, and in both cases, the use of the additional press-fitting auxiliary means by excavation inevitably increases the size of the entire static load type pile construction machine considerably. Thus, the above-mentioned problems of static load type pile construction machines cannot be easily solved by conventionally known construction methods.

発明の目的 そこで本発明はこれを簡潔に解消し得るようにしようと
いうものである。
OBJECT OF THE INVENTION Therefore, the present invention aims to solve this problem in a simple manner.

更にまだ本発明はパイル施工中、これに作動を併行させ
る仕様でのパイル施工だけでなしに、バイ/1/施工中
必要なときだけ、即ち地盤中の転石や礫等の障害物層の
個所をパイル先端が突破する間、稼働させ、それ以外の
ときは地上に引抜いて待機させるという仕様でのパイル
施工も可能で、しかもその稼働の再開を圧入途次のバイ
pを一旦引抜いて再び挿入することなく簡潔に遂行し得
る地盤貫入機を提供することを目的としている。
Furthermore, the present invention is applicable not only to pile construction with specifications that allow the operation to occur concurrently with pile construction, but also only when necessary during bi/1/construction, i.e., at locations where there are obstruction layers such as boulders or gravel in the ground. It is also possible to construct piles in such a way that the pipe is operated while the pile tip breaks through, and is pulled out to the ground and left on standby at other times.Moreover, the next pipe must be pulled out and reinserted during press-in to restart its operation. The purpose of the present invention is to provide a ground penetrating machine that can be easily and easily operated.

発明の構成 本発明の地盤貫入機は、静荷重穴パイル施工機(即ちチ
ャックで被圧入パイルを掴み、これを静押下げ荷重の負
荷により地盤に圧入するようにされたパイル圧入機)と
併用され、被圧入パイルに先行して地盤に貫入される地
盤貫入機であって、前記パイル圧入機におけるチャック
に被圧入パイルに沿わせてこれと共に掴まれる本体を構
成要素として包含し、該本体にパイル圧入時に圧入パイ
ルの下端より下方に先端が位置される上下動が可能な地
盤貫入ブレード、及び該ブレードを駆動する駆動機を装
備したことを特徴としている。
Structure of the Invention The ground penetrating machine of the present invention can be used in combination with a static load hole pile construction machine (i.e., a pile press-in machine that grips the pile to be press-fitted with a chuck and press-fits it into the ground by applying a static push-down load). A ground penetrating machine that penetrates into the ground prior to the pile to be press-fitted, which includes as a component a main body that is gripped by the chuck of the pile press-fit machine along with the pile to be press-fitted, It is characterized by being equipped with a ground penetrating blade that can move up and down and whose tip is positioned below the lower end of the press-in pile during pile press-fitting, and a drive machine that drives the blade.

発明の作用 本発明においては被圧入パイルに沿わせてこれと共に上
記貫入機の本体を静荷重式パイル施工機のチャックで掴
むと、該本体は被圧入パイルと一体化される。従ってこ
の一体化を上記地盤貫入ブレードの先端が被圧入パイル
の下端より下方に位置するようにして行い、その一体化
の状態下でチャックに靜押下げ荷重を負荷して、被圧入
パイルを圧入しつ\、地盤貫入グレードの駆動機により
該圧入パイルに対し該ブレードを押下げることにより、
該ブレードをパイルの圧入に先行して地盤に貫入させる
ことができる。このブレードの地盤への先行貫入は、そ
れが圧入パイルに対して押下げ限度になれば、駆動機で
元に戻し再び押下げるという操作の繰返しで進め得る。
Effect of the Invention In the present invention, when the main body of the penetrating machine is gripped by the chuck of the static load type pile construction machine along with the pile to be press-fitted, the main body is integrated with the pile to be press-fitted. Therefore, this integration is performed so that the tip of the ground penetrating blade is located below the lower end of the pile to be press-fitted, and in this state of integration, a silent pressing load is applied to the chuck to press-fit the pile to be press-fitted. By pressing down the blade against the press-fit pile using a ground-penetrating grade drive machine,
The blade can be penetrated into the ground prior to the pile being press-fitted. The preliminary penetration of the blade into the ground can be advanced by repeating the operation of returning the blade to its original position with a drive machine and pushing it down again when it reaches its limit of pushing down against the press-fit pile.

ブレードの地盤先行貫入はパイル圧入を補助する。The advance penetration of the blade into the ground assists in the pile press-in.

上記グレードの地盤先行貫入は、チャックによる貫入機
本体の掴持を維持したま\にするとバイル施工中、これ
に併行して施され、チャックを開放して貫入機を地上へ
引抜けば、パイルのみの圧入施工、即ち本発明貫入機の
稼働休止となる。
Pre-penetration of the above grade of ground is performed concurrently with the pile construction by keeping the grip of the penetrating machine body with the chuck, and when the chuck is released and the penetrating machine is pulled out to the ground, the pile In other words, the operation of the inventive penetration machine will be suspended.

ブレードの地盤先行貫入は、施工途次のパイルをそのま
\とし貫入機を地中に戻して再セットすると再開可能で
ある。
Preliminary penetration of the ground by the blade can be resumed by leaving the pile in the middle of construction and returning the penetrating machine to the ground and resetting it.

発明の効果 上記のように本発明によれば、バイi圧入の補助が前足
ブレードの地盤先行貫入でなされるから、パイルはそれ
単独での圧入と変らないしつかりした圧入施工状態が得
られ、またこの本発明の施工によればパイル圧入補助に
必要な設備は従来に比較し規模が小さくてすむ。従って
本発明では静荷重式バイtvlA工機の上述した問題を
簡潔に解消することができる。
Effects of the Invention As described above, according to the present invention, since the support for bi-i press-in is performed by the preliminary penetration of the ground by the front blade, the pile can be press-fitted in the same firm state as when it is press-fitted alone, and According to the construction of the present invention, the equipment required for assisting pile press-in can be smaller in scale than in the past. Therefore, in the present invention, the above-mentioned problems of the static load type bit tvlA machine can be easily solved.

本発明においては質入機の本体がチャックに掴まれるよ
うになっているのでパイルの施工中、これに地盤貫入ブ
レードの先行貫入を併行させる仕様でのパイル施工だけ
でなしに、パイル施工中、必要なときだけ、即ち地盤中
の転石や礫等の障害物層の個所をパイル先端が突破する
間、地盤貫入ブレードを地中で稼働させ、それ以外のと
きは地上に貫入機を引抜いて待機させるという仕様での
パイ/l/施工も可能で、しかもその稼働の再開には施
工途次のパイルを一旦引抜いて再挿入する必要がないか
ら、これを簡潔に遂行することが保証される。
In the present invention, the main body of the pawning machine is gripped by a chuck, so that it can be used not only for pile construction with a specification that allows the ground penetration blade to advance in parallel with this during pile construction, but also for pile construction during pile construction. The ground penetrating blade is operated underground only when necessary, that is, while the pile tip breaks through an obstacle layer such as boulders or gravel in the ground, and at other times, the penetrating machine is pulled out and stands by on the ground. It is also possible to construct piles with specifications such that the piles are installed, and since there is no need to pull out and reinsert the piles that are currently under construction in order to resume operation, it is guaranteed that this process can be carried out simply.

実 施 例 以下、本発明の実施例を図面について説明する。Example Embodiments of the present invention will be described below with reference to the drawings.

第1図乃至第8図に本発明の一実施例が示され、第1.
2.8図で(1)がそれ自体公知の静荷重式パイ/l/
施工機(2)[第8図]と併用される地盤貫入機で、こ
れは静荷重式パイル施工機(2)におけるチャック(3
)に被圧入パイμ(4)に沿わせてこれと共に掴まれる
本体(5)を具備する。本例の場合、該本体(5)はパ
イ/l/ +41の断面形状に合致する断面形状になっ
ているが他の適当な形でもよい。
One embodiment of the present invention is shown in FIGS. 1 to 8, and 1.
In Figure 2.8, (1) is the static load type pi/l/ which is known per se.
This is a ground penetrating machine used together with the construction machine (2) [Figure 8], and this is the chuck (3) in the static load type pile construction machine (2).
) is provided with a main body (5) that is gripped together with the press-fitted pie μ (4). In this example, the body (5) has a cross-sectional shape that corresponds to a pi/l/+41 cross-sectional shape, but it may have any other suitable shape.

上記本体(5)には先端にチゼル付き、より好ましくは
取外し可能にチゼ/I/(6)を取付けた地盤貫入グレ
ード(7)を備えると共に、該ブレード(7)を駆動す
る駆動機、例えば油圧シリンダー・プランジャー装置(
8)等の流体圧駆動機や電動型スクリュージヤツキのよ
うな駆動機を装備する。上記修モ番疹番φ0−ψ 油圧シリンダー・プランジャー装置(8)は、一端側が
本体(5)に結合され、他端側か地盤貫入ブレード(7
)に枢着結合される。+91 +9+は上記本体(5)
の下端部の左右両側に形成したガイドレールで、該ガイ
トレー yL/f91 +91に上記地盤貫入グレード
(7)の上半側部(7a)の左右耳部を上下動自在に嵌
合する。(ltl・・・は静荷重式パイル施工機(2)
のクランプである。
The main body (5) is equipped with a ground penetration grade (7) with a chisel attached to the tip, more preferably a chisel/I/(6) removably attached, and a drive machine that drives the blade (7); For example, hydraulic cylinder plunger device (
8) Equipped with a drive machine such as a fluid pressure drive machine or an electric screw jack. The hydraulic cylinder plunger device (8) has one end connected to the main body (5), and the other end connected to the ground penetrating blade (7).
). +91 +9+ is the above body (5)
The left and right ear portions of the upper half side portion (7a) of the ground penetration grade (7) are fitted into the guide rail yL/f91 +91 with guide rails formed on both left and right sides of the lower end portion of the guide rail yL/f91 +91 so as to be vertically movable. (ltl... is a static load type pile construction machine (2)
It is a clamp.

第4図及び第5図に本発明の他の実施例が示され、第4
,5図において第1図乃至第8図と同符号は同部分を指
示している。第4,5図のものは油圧シリンダー・プラ
ンジャー装置(8)を左右二基併設とし、第1図乃至第
3図におけるガイトレー/Iz +91 +91による
地盤貫入グレードロ0)の上下動案内を廃した点を除き
、第1図乃至第8図の実施例のもの3−Nド−漕爾でふ
六− 地盤貫入ブレード(7)は第1図乃至第5図に示す形式
の他に、第6,7図に示す形式のものでもよい。
Other embodiments of the present invention are shown in FIGS. 4 and 5.
, 5, the same reference numerals as in FIGS. 1 to 8 indicate the same parts. The one in Figures 4 and 5 has two hydraulic cylinder plunger devices (8) on the left and right, eliminating the vertical movement guide of the ground penetration grade Ro0) by the guide tray / Iz +91 +91 in Figures 1 to 3. Except for this point, the ground penetrating blade (7) of the embodiment shown in Figs. 1 to 8 is of the type shown in Figs. , 7 may be used.

上側の本発明地盤貫入機によるパイル圧入の補助は下記
のようにしてなされる、 既圧入パイ/L/(a)・・・をクランプ(1■・・で
掴んで該パイA/(a)上に自立させた静荷重式パイル
施工機(2)のチャック(3)に、被圧入バイ/l’ 
+41に重ね沿わせてこれと共に貫入機本体(5)を掴
ませる。との際、地盤貫入ブレード(7)の先端が被圧
入バイ1V(41の下端より下方位置を占めるようにす
る。
The pile press-in is assisted by the ground penetrating machine of the present invention on the upper side as follows: Grasp the already press-fit pie /L/(a)... with the clamps (1■...) and hold the pie A/(a). The chuck (3) of the static load type pile construction machine (2) that is freestanding on the
+41 and grab the penetrating machine main body (5) along with it. At this time, the tip of the ground penetrating blade (7) should be positioned below the lower end of the press-fitted bye 1V (41).

この状態下で、チャック(3)に静押下げ荷重を負荷(
7てパイ/I/141を地盤に圧入し、そのパイル施工
と併行して或いは必要なときに油圧シリンダー・プラン
ジャー装置(8)により地盤貫入ブレード(7)をパイ
ル(4)に対し押下げれば、それによる該グレード(7
)の地盤に対する先行貫入により、パイル(4)の圧入
が補助される。
Under this condition, a static push-down load is applied to the chuck (3) (
7, press-fit the Pi/I/141 into the ground, and press the ground-penetrating blade (7) down against the pile (4) using the hydraulic cylinder plunger device (8) at the same time as the pile construction or when necessary. If so, the corresponding grade (7
) into the ground assists in the press-in of the pile (4).

上記パイ#(4)の施工途次チャック(3)を開放して
貫入機(1)を地上に引抜けば貫入機(1)は非稼働状
態におかれ、パイ/l/ 141の圧入のみの施工仕様
が可能となる。地盤貫入ブレード(8)の先行貫入によ
るパイIV+41の圧入補助を再開するには、貫入機(
1)を地中に戻して再セットすればよい。
If the chuck (3) is opened during construction of the pie # (4) and the penetrating machine (1) is pulled out to the ground, the penetrating machine (1) will be in a non-operating state and only the pie/l/141 will be press-fitted. construction specifications are possible. To resume the press-in assistance of Pi IV+41 by the advance penetration of the ground penetration blade (8), use the penetration machine (
All you have to do is put 1) back into the ground and reset it.

なお、上記静荷重式バイμ施工機(2)としては、下記
構成のものを使用することができる。
Note that as the static load type biμ construction machine (2), one having the following configuration can be used.

低圧入パイル(a)・・・を掴むクランプαυに被圧入
パイIvf41を掴むチャック(3)が隣接して配置さ
れると共に、該チャック(3)がクランプqO1・・・
との間に、適当な手段により相対的上下駆動ならびに上
記パイ/I/(a)・・並列方向へのパイル並列ピッチ
以上の相対的前後駆動が可能であり、更に適宜の手段に
よシフランデ(](ト)・・・に対しパイ/L/(a)
・・・並列方向を横断する方向へ直進的に横送り或いは
旋回できるようにされている。この構成に加えてチャッ
ク(3)はその垂直軸線の周りの方向へ180°以上回
動変位可能になっていることがより好しい。チャック(
3)のそのような所要の駆動或いは回動変位はそれ自体
公知の油圧シリンダー・プランジャー装置や油圧モータ
ーにより行えばよい。
A chuck (3) that grips the press-fitted pie Ivf41 is arranged adjacent to a clamp αυ that grips the low-pressure-fit pile (a), and the chuck (3) also holds the clamp qO1...
It is possible to perform relative up-and-down movement and relative back-and-forth movement at a pitch greater than the pile parallel pitch in the above-mentioned pie/I/(a) parallel direction using appropriate means. ] (g) For...pi/L/(a)
. . . It is designed to be able to horizontally move or turn in a direction that crosses the parallel direction. More preferably, in addition to this configuration, the chuck (3) is rotatably displaceable by more than 180° in directions around its vertical axis. Chuck(
Such required driving or rotational displacement in 3) may be performed by a hydraulic cylinder/plunger device or a hydraulic motor, which are known per se.

第8図に示した静荷重式バイ/l/施工機(2)におい
て、(111がクランプ面・・・との間にチャック(3
)を相対的に上下駆動させる油圧シリンダー・プランジ
ャー装置で、その一端側がチャック(3)の本体に結合
され、他端側か水平方向に旋回し得るマスh azに結
合、より好ましくは枢着結合される。マストα2はパイ
ル(a)・・・並列方向にパイIV(a)・・・の並列
ピッチ以上、クランプ+1[Il・・・に対し油圧シリ
ンダー・プランジャー装置により前後駆動可能なスライ
ドベース(131上に立設され、スライドベース(I3
1がクランプαGを備えたサド/V (141に搭載さ
れる。
In the static load type bi/l/execution machine (2) shown in Fig. 8, (111 is the clamping surface...
) is a hydraulic cylinder/plunger device that drives the chuck (3) up and down relatively, one end of which is connected to the main body of the chuck (3), and the other end is connected to a mass h az that can be rotated horizontally, more preferably pivoted. be combined. The mast α2 is a slide base (131 The slide base (I3
1 is equipped with SAD/V (141) equipped with clamp αG.

静荷重式パイル施工機としては上述したようなものの他
に、パイルの圧入反力を静荷重式バイμ施工機の自重や
、地盤中にアースオーガー或いはそれに類するスクリュ
ーアンカーを運込んで該アンカーでとるようにしたもの
でもよいし、パイルに静押下げ荷重を負荷するのに、ウ
ィンチによる形式を採用した静荷重式パイ/L’M工機
も使用できる。
In addition to the above-mentioned static load type pile construction machines, there are also static load type pile construction machines that use the dead weight of a static load type biμ construction machine or carry earth augers or similar screw anchors into the ground and use the anchors to absorb the press-in reaction force of the pile. Alternatively, a static load type pie/L'M machine using a winch may be used to apply a static downward load to the pile.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の一実施例を示す正面図、第2図は第1
図の平面図、第3図は第1図■〜■絆断面図、第4図は
本発明の実施の他側を示す正面図、第5図はその側面図
、第6図は地盤貫入ブレードの変更例を示す正面図、第
7図はその部分縦断側面図、第8図は本発明貫入機の使
用態様を本発明で適用する静荷重式パイ#施工機の一例
と共に示す正面図である。 (1)は地盤貫入機、 (2)は静荷重式パイル施工機
、(3)はチャック、(4)は被圧入パイル、(5)は
本体、 (6)はチゼμ、 (7)は地盤貫入ブレード、 (8)は油圧シリンダー・プランジャー装置(駆動機) (101はクランプ。 (以上) (−ゝ・ 代理人 弁理士 三 枝 英 二 1.゛−1・ 第2図 第4図 第5図
FIG. 1 is a front view showing one embodiment of the present invention, and FIG. 2 is a front view showing one embodiment of the present invention.
Fig. 3 is a cross-sectional view of the bonds shown in Figs. FIG. 7 is a front view showing a modified example of the same, FIG. 7 is a partial vertical side view thereof, and FIG. 8 is a front view showing the manner of use of the penetrating machine of the present invention together with an example of a static load type pipe construction machine to which the present invention is applied. . (1) is a ground penetrating machine, (2) is a static load type pile construction machine, (3) is a chuck, (4) is a press-fit pile, (5) is a main body, (6) is a chize μ, (7) (8) is the hydraulic cylinder/plunger device (driver) (101 is the clamp. Figure 5

Claims (1)

【特許請求の範囲】[Claims] ■ チャックで被圧入パイルを掴み、これを静押下げ荷
重の負荷により地盤に圧入するようにされたパイル圧入
機と併用され、被圧入パイルに先行して地盤に貫入され
る地盤貫入機であって、前記パイル圧入機におけるチャ
ックに被圧入パイルに沿わせてこれと共に掴マれる本体
を構成要素として包含し、該本体にパイル圧入時に圧入
パイルの下端より下方に先端が位置される上下動が可能
な地盤貫入ブレード、及び該ブレードを駆動する駆動機
を装備したことを特徴とする地盤貫入機。
■ It is a ground penetrating machine that is used in conjunction with a pile press-in machine that grips the pile to be press-fitted with a chuck and press-fits it into the ground by applying a static downward load, and penetrates into the ground before the pile to be press-fitted. The pile press-fitting machine includes a main body as a component that is gripped along with the pile to be press-fitted by the chuck, and the main body has a vertical movement that positions the tip below the lower end of the press-fit pile when the pile is press-fitted. A ground penetrating machine characterized by being equipped with a ground penetrating blade and a drive machine for driving the blade.
JP9528184A 1984-05-11 1984-05-11 Ground penetrator Granted JPS60238518A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9528184A JPS60238518A (en) 1984-05-11 1984-05-11 Ground penetrator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9528184A JPS60238518A (en) 1984-05-11 1984-05-11 Ground penetrator

Publications (2)

Publication Number Publication Date
JPS60238518A true JPS60238518A (en) 1985-11-27
JPH0368968B2 JPH0368968B2 (en) 1991-10-30

Family

ID=14133387

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9528184A Granted JPS60238518A (en) 1984-05-11 1984-05-11 Ground penetrator

Country Status (1)

Country Link
JP (1) JPS60238518A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0673457A4 (en) * 1991-04-29 1995-05-26 Subterranean Systems Pte Ltd Improvements to building construction methods and materials.

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS543522A (en) * 1977-06-09 1979-01-11 Sony Corp Production of diaphragms for speakers
JPS58150626A (en) * 1982-02-26 1983-09-07 Tosa Kikai Kogyo Kk Pile driving and drawing machine

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS543522A (en) * 1977-06-09 1979-01-11 Sony Corp Production of diaphragms for speakers
JPS58150626A (en) * 1982-02-26 1983-09-07 Tosa Kikai Kogyo Kk Pile driving and drawing machine

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0673457A4 (en) * 1991-04-29 1995-05-26 Subterranean Systems Pte Ltd Improvements to building construction methods and materials.
EP0673457A1 (en) * 1991-04-29 1995-09-27 Subterranean Systems Pte. Ltd. Improvements to building construction methods and materials

Also Published As

Publication number Publication date
JPH0368968B2 (en) 1991-10-30

Similar Documents

Publication Publication Date Title
CN102704481A (en) Construction method combining static pressure pile sinking with middle-digging hole guiding for buildings or bridges
JP6085484B2 (en) Pile driver
CN106948346B (en) A kind of pilot hole formula static-pressure pile planting device suitable for hard geological province
JP4986799B2 (en) Embedded pile method using both earth drill and pile driver
CN207727581U (en) A kind of full-sleeve obstacle cleaning machine
CN109594563A (en) A kind of full-sleeve obstacle cleaning machine and its construction method
US4100972A (en) Displacement hammer apparatus for sinking and lining boreholes
JPS60238518A (en) Ground penetrator
CN108266122A (en) One kind can the multi-functional middle pick agitation driller of tuning and its construction method
JP3533981B2 (en) Construction method of screwed pile
JP2005120622A (en) Construction method of underground structure
JPS6330451B2 (en)
JPS61250229A (en) Method and apparatus for penetration of steel sheet pile
CN108952568B (en) Drilling machine
JPH0368967B2 (en)
JP2017025530A (en) Ground bearing force increasing injection method
US3696874A (en) Operably aligned and clamped earth boring machine
JP3921299B2 (en) Pile press-fitting device
KR0123886B1 (en) Working machine and working method for underground foundation pile
KR20150124728A (en) Sheet Pile Construction Apparatus For Perforating and Pile Driver Work
JP3012064B2 (en) Steel pipe pile intrusion method and pile driving device
CN108894750B (en) Cable sleeve device and method for assisting directional drill to penetrate through drill bit to raise head
JP2897870B2 (en) Drilling equipment and medium digging method
JP2612497B2 (en) Drilling method for large diameter underground holes
JP4104340B2 (en) Pipe line propulsion device

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees