JPS60208514A - Construction work of underground wall - Google Patents
Construction work of underground wallInfo
- Publication number
- JPS60208514A JPS60208514A JP6509884A JP6509884A JPS60208514A JP S60208514 A JPS60208514 A JP S60208514A JP 6509884 A JP6509884 A JP 6509884A JP 6509884 A JP6509884 A JP 6509884A JP S60208514 A JPS60208514 A JP S60208514A
- Authority
- JP
- Japan
- Prior art keywords
- wall
- earth retaining
- permanent
- temporary earth
- retaining wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/03—Prefabricated parts, e.g. composite sheet piles
- E02D5/10—Prefabricated parts, e.g. composite sheet piles made of concrete or reinforced concrete
- E02D5/105—Prefabricated parts, e.g. composite sheet piles made of concrete or reinforced concrete of prestressed concrete
Abstract
Description
【発明の詳細な説明】
周知のように地下構造物を構築する際や、シールド工事
の立坑を構築する際などに、本設壁の形成に先立って仮
設の土留壁の構築が行なわれる。DETAILED DESCRIPTION OF THE INVENTION As is well known, when constructing an underground structure or a shaft for shield construction, a temporary retaining wall is constructed prior to the formation of a permanent wall.
この仮設土留壁は、本設壁を形成するための掘削作業時
に、周囲の土、水圧に対抗して地山の崩壊を防ぐために
は必要なものである。This temporary earth retaining wall is necessary to prevent the collapse of the ground against the surrounding soil and water pressure during excavation work to form the permanent wall.
しかし、あくまで本設壁が形成されるまでの仮設である
。However, this is only a temporary structure until the permanent wall is constructed.
従って、仮設土留壁はできる限り薄いもので土。Therefore, the temporary earth retaining wall should be as thin as possible.
水圧に対抗できることが、経済性の上で望ましい。Being able to withstand water pressure is desirable from an economic standpoint.
このため、例えば特公昭45−5225号公報に見られ
るように土留壁内にプレストレス鋼材を埋設して、壁体
にプレストレスを導入することで、壁厚の低減を可能に
する工法も提供されている。For this reason, for example, as seen in Japanese Patent Publication No. 45-5225, we also provide a construction method that makes it possible to reduce the wall thickness by burying prestressed steel materials in the earth retaining wall and introducing prestress into the wall. has been done.
しかしながら、同公報に開示された工法では、仮設土留
壁の壁厚は薄くできても、本設壁の壁厚は低減できない
。However, with the construction method disclosed in the publication, although the wall thickness of the temporary earth retaining wall can be reduced, the wall thickness of the permanent wall cannot be reduced.
一方、地下構造物、例えば都市に建設される地下鉄は、
地下埋設物の錯綜によって、次第に深い場所に構築され
る傾向がある。このため地山の土。On the other hand, underground structures, such as subways built in cities,
Due to the complexity of underground structures, they tend to be built in progressively deeper locations. For this reason, the soil of the earth.
水圧に耐え得るには、仮設土留壁および本設壁は、その
壁厚が肥大化する傾向にある。In order to withstand water pressure, temporary earth retaining walls and permanent walls tend to have thicker walls.
そこで、仮設土留壁を本設壁の一部として利用すること
で、経済性を確保することが考えられる。Therefore, it may be possible to ensure economic efficiency by using a temporary earth retaining wall as part of the permanent wall.
しかし、仮設土留壁の内側面に本設壁を単に形成したの
では、両者間の一体性が弱く、期待した程の経済的効果
が得られない。However, if a permanent wall is simply formed on the inner surface of a temporary earth retaining wall, the integrity between the two will be weak, and the expected economic effect will not be obtained.
この発明は上述した背景に鑑みてなされたものであって
、その目的とするところは、緊張材を仮設土留壁と本設
壁の両方に跨がらせることにより、偏心距離を人さくす
ることができるため、両者壁間に共通に導入されるプレ
ストレスの効果をより一層増大でき、双方の壁厚を低減
できる地中壁の構築工法を提供するところにある。This invention was made in view of the above-mentioned background, and its purpose is to reduce the eccentric distance by making the tension material span both the temporary earth retaining wall and the permanent wall. Therefore, it is an object of the present invention to provide a construction method for an underground wall that can further increase the effect of prestress commonly introduced between both walls and reduce the wall thickness of both walls.
上記目的を達成するため、この発明は、地中に仮設土留
壁を形成してその内側を掘削し、この仮設土留壁の内側
面に沿って本設壁を形成する工法に−おいて、前記仮設
土留壁の内部には予めプレストレス導入用の緊張材を前
記本設壁内に配設できるように余長部分を設け、且つこ
の余長部分が前記仮設土留壁の内側縁に位置するように
埋設し、前記本設壁を形成する際に前記余長部分を露出
させ、前記緊張材が前記仮設土留壁と前記本設壁との双
方に跨がるようにして本設壁形成し、本殿壁の硬化後に
前記緊張材を緊張して仮設土留壁および本設壁にプレス
トレスを導入してなることを特徴とする。In order to achieve the above object, the present invention provides a construction method in which a temporary earth retaining wall is formed underground, the inside of the wall is excavated, and a permanent wall is formed along the inner surface of the temporary earth retaining wall. An extra length is provided in advance inside the temporary earth retaining wall so that tension material for introducing prestress can be placed inside the permanent wall, and this extra length is located at the inner edge of the temporary earth retaining wall. , and when forming the permanent wall, expose the extra length, and form the permanent wall so that the tension material straddles both the temporary earth retaining wall and the permanent wall, The structure is characterized in that after the main hall wall has hardened, the tension material is tensioned to introduce prestress into the temporary earth retaining wall and the permanent wall.
以下、この発明の好適な実施例について添附図面を参照
して詳細に説明する。Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.
第1図は、この発明に係る地中壁の構築工法の第1実施
例を示すものである。FIG. 1 shows a first embodiment of the underground wall construction method according to the present invention.
同図に示す工法においては、地表から細幅な縦溝を掘削
し、この縦溝内に°コンクリートを打設して仮設土留1
10を形成し、このコンクリートが硬化した後に、仮設
土留壁10の内側を掘削して本設置!12を形成する。In the construction method shown in the figure, a narrow vertical trench is excavated from the ground surface, and concrete is poured into this vertical trench to create a temporary earth retaining structure.
10 is formed, and after this concrete has hardened, the inside of the temporary earth retaining wall 10 is excavated and the actual installation is done! form 12.
ここで、上記仮設土留壁10の内部には、第1図<a
>に示すように、緊張材14が予め鉄筋籠等に取り付け
られて埋設されている。Here, inside the temporary earth retaining wall 10, as shown in FIG.
As shown in >, the tension material 14 is attached to a reinforcing bar cage or the like in advance and buried therein.
この緊張材14は、可撓性のシースと、その内部に挿通
された鋼材とで栴成され、適宜個所に渦巻状に形成され
た余長部分14aが設けられ、この余長部分14aは第
1図(C)に示ずように本設壁12内に配設される。The tension member 14 is made of a flexible sheath and a steel material inserted into the sheath, and is provided with spirally formed extra length portions 14a at appropriate locations. As shown in FIG. 1(C), it is disposed within the main wall 12.
また、上記余長部分14aは、上記仮設土留壁10の内
側縁、つまり本設壁12が形成される側に位置している
。。Further, the extra length portion 14a is located at the inner edge of the temporary earth retaining wall 10, that is, on the side where the permanent wall 12 is formed. .
そして、仮設土留壁10を形成し、その内側の掘削が所
定深度まで行なわれると、本設壁12を形成する際に、
上記余長部分14aが埋設されている個所を、第1図(
b)に示すように取り除き、これを露出させ、余長部分
14aを引き出ジ。Then, when the temporary earth retaining wall 10 is formed and the inside thereof is excavated to a predetermined depth, when forming the permanent wall 12,
The location where the extra length portion 14a is buried is shown in Figure 1 (
b), remove it to expose it, and pull out the extra length 14a.
この場合、余長部分14aは、仮設土留壁10の内側縁
に位置しているため、これが容易に引き出せる。 ゛
しかる後に、第1図(C)に承りように余長部分14a
を、本設壁12内に位置させてこれを形成すると、緊張
材14は仮設土留rJ!1oど本設壁12との双方に跨
がるようになる。In this case, since the extra length portion 14a is located at the inner edge of the temporary earth retaining wall 10, it can be easily pulled out.゛After that, as shown in Fig. 1(C), the extra length portion 14a is
is positioned within the permanent wall 12 to form this, the tension material 14 becomes the temporary earth retaining rJ! 1o, it comes to straddle both sides of the main wall 12.
次いで、本設壁12の硬化後に緊張材14を緊張すると
、仮設土留壁10および本設壁12内に共通するプレス
トレスが導入される。Next, when the tendons 14 are tensioned after the permanent wall 12 has hardened, a common prestress is introduced into the temporary earth retaining wall 10 and the permanent wall 12.
さて、上述した工法で地中壁を構築すると、緊張材14
が仮設土留壁10と本設壁12の両方に跨がるようにし
C配置され、偏心距離20を大きくすることができるた
め、両者壁間に共通に導入されるプレストレスの効果を
より一層増大でき、これらの壁厚を低減化できる。Now, when constructing an underground wall using the construction method described above, the tension material 14
is arranged so as to straddle both the temporary earth retaining wall 10 and the permanent wall 12, and the eccentric distance 20 can be increased, further increasing the effect of the prestress commonly introduced between both walls. It is possible to reduce the thickness of these walls.
第2図は、この“発明の第2実施例を示しており、その
特徴点についてのみ以下に説明する。FIG. 2 shows a second embodiment of this invention, and only its features will be described below.
すなわち、上記本設壁12内に埋設される緊張材14は
、筒状のシース’I4bとその内部に挿通された鋼材1
4cとで構成C1シース14bは上記実施例と同様に一
般的には可撓性である。That is, the tension material 14 buried in the main wall 12 is made up of a cylindrical sheath 'I4b and the steel material 1 inserted into the inside thereof.
4c and C1 sheath 14b is generally flexible as in the above embodiment.
そして、緊張材14・の余長部分14aは、上記仮設土
留壁10内に略台形状に設置されており(第2図(a
)参照)、その上辺が土留壁]0の内側縁に位置してい
る。The extra length portion 14a of the tendon 14 is installed in the temporary earth retaining wall 10 in a substantially trapezoidal shape (see Fig. 2(a).
), the upper side of which is located at the inner edge of the retaining wall]0.
上記余長部分14aは、本設壁12を形成リ−るに際し
て、第2図(b)に示すように露出させた後、上記シー
ス14bを所定間隔でもって切断して、その内部の鋼材
14cを所定の長さだ1ノ引き出し、この部分に被覆材
16装着して、第2図(C)に示すように、本設壁12
内に埋設する。When forming and reeling the main wall 12, the extra length portion 14a is exposed as shown in FIG. is pulled out to a predetermined length, the covering material 16 is attached to this part, and the permanent wall 12 is attached as shown in FIG. 2(C).
buried within.
このような工法においても、上記第1実施例と同様な作
用効果が得られるとともに、本設壁12の壁厚が大ぎく
なっても、仮設土留壁10内に埋設する余長部分14a
を調節することで、仮設土留壁10と本設壁12との壁
厚を低減できる。Even in such a construction method, the same effects as in the first embodiment can be obtained, and even if the wall thickness of the permanent wall 12 becomes large, the extra length 14a buried in the temporary earth retaining wall 10 can be
By adjusting , the wall thicknesses of the temporary earth retaining wall 10 and the permanent wall 12 can be reduced.
第3図は、この発明の第3実施例を示すもので、以下に
その特徴点についてのみ説明する。FIG. 3 shows a third embodiment of the present invention, and only its features will be described below.
この実施例では、緊張材14を鋼材で形成するとともに
、本設壁12内に埋設する余長部分14aは、緊張材1
4を分断してその端部が重なるようにして略台形状にし
、且つそれぞれの端部は台形の上辺であって、仮設土留
壁10の内側縁に位置するようにしである(第3図(a
)参照)。そして、余長部分14aは、第3図(b )
に示すように露出させた後、端部近傍を交差させ、本設
壁12内に埋設させるとともに、それぞれの端部は本設
壁12の内側面より突出さゼ、第3図(C)に示すよう
に、定着具18を取り付けて緊張する。In this embodiment, the tendons 14 are made of steel, and the extra length 14a buried in the main wall 12 is
4 is divided into approximately trapezoidal shapes so that their ends overlap, and each end is the upper side of the trapezoid and is positioned at the inner edge of the temporary earth retaining wall 10 (see Fig. 3). a
)reference). The extra length portion 14a is shown in FIG. 3(b).
After exposing as shown in FIG. 3(C), the vicinity of the ends are crossed and buried in the main wall 12, and each end protrudes from the inner surface of the main wall 12, as shown in FIG. 3(C). As shown, the anchor 18 is attached and tensioned.
このような方法で地中壁を構築した場合でも、上記実施
例と同様な作用効果が得られるとともに次の如き効果も
奏し得る。Even when an underground wall is constructed using such a method, the same effects as those of the above embodiment can be obtained, and the following effects can also be achieved.
すなわち、地中壁に加わる土水圧は、深度方向に増加す
るため、通常深くなる程その壁厚を増大しなければなら
ない。That is, since the soil water pressure applied to underground walls increases in the depth direction, the wall thickness must generally be increased as the depth increases.
この際に、この実施例では、緊張材14が深度方向に対
して分断されており、緊張材14の緊張力を下方になる
に従って大きくできる。At this time, in this embodiment, the tension material 14 is divided in the depth direction, so that the tension force of the tension material 14 can be increased as it goes downward.
従って、プレストレスの大きさを適宜選択して緊張し、
壁厚をさ程大きくヂることなく、地中壁を形成しても土
水圧に耐えられることになる。Therefore, by appropriately selecting the magnitude of prestress and applying tension,
Even if an underground wall is formed, it can withstand earth water pressure without increasing the wall thickness very much.
以上、実施例で詳細に説明したように、この発明に係る
地中壁の構築工法によれば、緊張材を仮設土留壁と本設
壁の両方に跨がらせることにより、偏心距離を大きくす
ることができるため、両者壁間に共通に導入されるプレ
ストレスの効果をより一層増大でき、これらの壁厚を低
減でき、極めて大きな経済的効果が得られるとともに、
両方の壁に別々に緊張材を配置するよりも、緊張材およ
び手間を節減できる。As described above in detail in the embodiments, according to the underground wall construction method according to the present invention, the eccentric distance is increased by making the tendons straddle both the temporary earth retaining wall and the permanent wall. As a result, the effect of the prestress commonly introduced between both walls can be further increased, the thickness of these walls can be reduced, and extremely large economic effects can be obtained.
Saves on strands and labor compared to placing strands on both walls separately.
第1図はこの発明の第1実施例の工程順を示す要部断面
図、第2図はこの発明の第2実施例の工程順を示ず要部
断面図、第3図はこの発明の第3実施例の工程順を示す
要部断面図である。
10・・・・・・仮設土留壁 12・・・・・・本設壁
14・・・・・・緊張材 14a・・・余長部分14b
・・・シース 14c・・・鋼 材16・・・・・・被
覆材 18・・・・・・定着具20・・・・・・偏心距
離
特許出願人 株式会社 大 林 引
代 理 人 弁理士 −色健輔
(Q)
第1図FIG. 1 is a sectional view of a main part showing the process order of a first embodiment of the present invention, FIG. 2 is a sectional view of a main part of a second embodiment of the invention without showing the process order, and FIG. FIG. 7 is a cross-sectional view of main parts showing the process order of the third embodiment. 10...Temporary earth retaining wall 12...Permanent wall 14...Tension material 14a...Extra length portion 14b
... Sheath 14c ... Steel material 16 ... Covering material 18 ... Fixture 20 ... Eccentric distance Patent applicant Obayashi Co., Ltd. Agent Patent attorney -Kensuke Shiro (Q) Figure 1
Claims (4)
該仮設土留壁の内側面に沿って本設壁を形成する工法に
おいて、該仮設土留壁の内部には予めプレストレス導入
用の緊張材を該本設壁内に配設できるように余長部分を
設け、且つ該余長部分が該仮設土留壁の内側縁に位置す
るように埋設し、該本設壁を形成マる際に該余長部分を
露出させ、該緊張材が該仮設土留壁と咳本設壁との双方
に跨がるようにして該本設壁形成し、該本設壁の硬化後
に該緊張材を緊張して該仮設土留壁および該本設壁にプ
レストレスを導入してなることを特徴とする地中壁の構
築工法。(1) Form a temporary earth retaining wall underground and excavate the inside of the child.
In a construction method in which a permanent wall is formed along the inner surface of the temporary earth retaining wall, an extra length is provided inside the temporary earth retaining wall so that tension material for introducing prestress can be placed in the permanent wall in advance. and the extra length is buried so that it is located at the inner edge of the temporary earth retaining wall, and when the permanent wall is formed, the extra length is exposed, and the tension material is placed on the inner edge of the temporary earth retaining wall. The permanent wall is formed so as to straddle both the temporary earth retaining wall and the permanent wall, and after the permanent wall has hardened, the tension material is tensioned to introduce prestress into the temporary earth retaining wall and the permanent wall. A construction method for underground walls that is characterized by the following:
れた鋼材とからなり、上記余長部分は渦巻状に形成され
、この部分を引き出して上記本設壁内に埋設してなるこ
とを特徴とする特許請求の範囲第1項記載の地中壁の構
築工法。(2) The above-mentioned tension material is composed of a visible sheath and a steel material inserted inside the sheath, and the above-mentioned extra length part is formed in a spiral shape, and this part is pulled out and buried in the above-mentioned permanent wall. An underground wall construction method according to claim 1, characterized in that:
た鋼材とからなり、上記余長部分は上記仮設土留壁内に
略台形状に埋設されるとともに、該余長部分を露出した
後、該シースを切断して該鋼線を引き出した優、この部
分を被覆して上記本設壁内に埋設しCなることを特徴と
する特許請求の範囲第1項記載の地中壁の構築工法。(3) The tension member consists of a cylindrical sheath and a steel material inserted into the sheath, and the extra length is buried in the temporary earth retaining wall in a substantially trapezoidal shape, and the extra length is exposed. After that, the sheath is cut and the steel wire is pulled out, and this part is covered and buried in the main wall. Construction method.
れた鋼材とからなり、上記余長部分は該緊張材を分断し
て端部が重なるようにして埋゛設するとともに、該緊張
材の端部は上記本設壁の内側面より突出させ該緊張材の
定着部とすることを特徴とする特許請求の範囲第1項記
載の地中壁の構築この発明は地中壁の構築工法に関し、
特に仮設土留壁と本設壁の双方にプレストレスを導入す
る地中壁の構築工法に関する。(4) The tension material is composed of a visible sheath and a steel material inserted into the sheath. The present invention relates to construction of an underground wall according to claim 1, characterized in that the end portion of the material projects from the inner surface of the main wall and serves as a fixing portion for the tension material. Regarding the construction method,
In particular, it relates to construction methods for underground walls that introduce prestress into both temporary earth retaining walls and permanent walls.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP6509884A JPS60208514A (en) | 1984-04-03 | 1984-04-03 | Construction work of underground wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP6509884A JPS60208514A (en) | 1984-04-03 | 1984-04-03 | Construction work of underground wall |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS60208514A true JPS60208514A (en) | 1985-10-21 |
JPH0375689B2 JPH0375689B2 (en) | 1991-12-03 |
Family
ID=13277095
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP6509884A Granted JPS60208514A (en) | 1984-04-03 | 1984-04-03 | Construction work of underground wall |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS60208514A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5423637A (en) * | 1993-08-11 | 1995-06-13 | Taki; Osamu | Liner joining system and method |
-
1984
- 1984-04-03 JP JP6509884A patent/JPS60208514A/en active Granted
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5423637A (en) * | 1993-08-11 | 1995-06-13 | Taki; Osamu | Liner joining system and method |
Also Published As
Publication number | Publication date |
---|---|
JPH0375689B2 (en) | 1991-12-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPS6114322A (en) | Method for decorating and supporting natural or artificial inclined surface | |
KR20060058756A (en) | Stabilized soil structure and facing elements for its construction | |
JPS60208514A (en) | Construction work of underground wall | |
KR20190137432A (en) | Soil retaining wall for phc pile | |
JPH09111758A (en) | Cast-in-place concrete pile and construction method thereof | |
JPS61122320A (en) | Method of coupling continuous underground wall with underground structure | |
JPH10102487A (en) | Method of introducing prestress into diaphragam wall | |
KR20190052391A (en) | Method for reinforcing column using V-shaped ties | |
JP3609657B2 (en) | Structural underground wall and its construction method | |
JP7211779B2 (en) | Shield start-side shaft wall and shield start-side shaft wall construction method | |
JPH0525821A (en) | Continuous underground wall and construction method thereof | |
JP3052106B2 (en) | Construction method of prestressed underground continuous wall | |
JPH073777A (en) | Method for constructing self-supporting land slide protection wall | |
JP3625750B2 (en) | Structure of the basement of the building | |
JP2984728B2 (en) | Construction method of cast-in-place concrete pile | |
JPH0447021A (en) | Construction method for sheathing guide pile | |
JP2941172B2 (en) | Manufacturing method of PC segment | |
KR102171787B1 (en) | Soil retaining wall using phc pile | |
JP3678463B2 (en) | Starting and reaching shaft for shield machine | |
JP2010144469A (en) | Construction method of intended underground outer wall, underground outer wall and earth retaining wall | |
JP2002138415A (en) | Cross girder member for girder member in pc bridge and girder member | |
JPS63261012A (en) | Construction of joint of underground continuous wall | |
JP2719991B2 (en) | Construction method of slope protection structure | |
JPS61117321A (en) | Method of building pc underground continuous wall | |
JP2629142B2 (en) | Retaining wall construction method |