JPS60169797A - Method of construction of housing for nuclear power plant - Google Patents

Method of construction of housing for nuclear power plant

Info

Publication number
JPS60169797A
JPS60169797A JP59025765A JP2576584A JPS60169797A JP S60169797 A JPS60169797 A JP S60169797A JP 59025765 A JP59025765 A JP 59025765A JP 2576584 A JP2576584 A JP 2576584A JP S60169797 A JPS60169797 A JP S60169797A
Authority
JP
Japan
Prior art keywords
construction
building
factory
power plant
nuclear power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP59025765A
Other languages
Japanese (ja)
Inventor
清 清水
大内 太郎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Service Engineering Co Ltd
Hitachi Ltd
Original Assignee
Hitachi Service Engineering Co Ltd
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Service Engineering Co Ltd, Hitachi Ltd filed Critical Hitachi Service Engineering Co Ltd
Priority to JP59025765A priority Critical patent/JPS60169797A/en
Publication of JPS60169797A publication Critical patent/JPS60169797A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Silver Salt Photography Or Processing Solution Therefor (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔発明の利用分野〕 本発明線、原子炉建屋、制御建屋、タービン建〔発明の
背景〕 原子力発電プラント建屋を建設する場合、従来は、機器
の据付工事に先行して、土木、建築工事がおこなわれ、
その後、一定の建屋強度に達した部屋ごとに各種機器の
据付をおζなうようにしており、その工事期間は、着工
から運転開始までに約5年もの長年月を必要としている
[Detailed Description of the Invention] [Fields of Application of the Invention] Invention line, nuclear reactor building, control building, turbine building [Background of the Invention] When constructing a nuclear power plant building, conventionally, construction work was carried out prior to equipment installation work. Civil engineering and construction work was carried out,
After that, various equipment is installed in each room once the building has reached a certain level of strength, and the construction period takes approximately five years from the start of construction to the start of operation.

このように、従来にあっては、原子力発電プラント建屋
の工事期間に長年月を必要とし、その分だけプラントの
運転開始が遅れるばかシか、工事に際し、コンクリート
型枠や足場の搬入、組立、解体、撤去作業に非常に多く
の時間と労力とを費やす必要がアシ、上記した従来工法
に部分的改善策を採シ入れても、工期の大幅短縮化をは
かることは非常に困難であシ、もはや限界に達している
というのが実情である。
In this way, in the past, it took many years to construct a nuclear power plant building, which delayed the plant's start of operation. It is necessary to spend a great deal of time and effort on demolition and removal work, and even if partial improvements are made to the conventional construction methods mentioned above, it is extremely difficult to significantly shorten the construction period. The reality is that we have already reached our limits.

〔発明の目的〕[Purpose of the invention]

本発明は、以上の点にかんがみ、この種建屋の建設工法
を抜本的に見直し、種々検討を重ねた結果なされたもの
であって、その目的とするところは、従来とは全く異な
る工法の採用により、工期の大幅短縮化をはかシ、プラ
ント運転開始の早期化を実現できるばかシか、建設現地
で取シ扱う各種付帯設備の大幅節減化をはかった、経済
性にすぐれた原子力発電プラント部屋の建設工法を提供
しようとするものである。
In view of the above points, the present invention was made as a result of a fundamental review of the construction method for this type of building and repeated various studies. As a result, the construction period can be significantly shortened and plant operations can be started earlier, and the number of ancillary equipment handled at the construction site can be significantly reduced, making it an extremely economical nuclear power plant. It attempts to provide a construction method for rooms.

〔発明の概要〕[Summary of the invention]

上記目的を達成するため、本発明は、原子力発電プラン
ト建屋を複数の建屋ブロックに分割してあらかじめ工場
製作するとともに、各建屋ブロックに必要とする設備も
あらかじめ工場において装備し、他方、建設現地におい
ては、上記建屋ブロックの工場製作と併行して、これら
複数の建屋ブロック間を補強する鉄筋をあらかじめ所定
の位置間を、あらかじめ現地打ちした鉄筋とともにコン
クリート打ちして連結することを特徴とするものである
In order to achieve the above object, the present invention divides a nuclear power plant building into a plurality of building blocks and manufactures them in advance in a factory, equips each building block with the necessary equipment in advance in the factory, and then is characterized in that, in parallel with the manufacturing of the building blocks at a factory, reinforcing bars for reinforcing the plurality of building blocks are connected in advance by pouring concrete between predetermined positions together with reinforcing bars cast on-site in advance. be.

〔発明の実施例〕[Embodiments of the invention]

以下、本発明を、図面にもとづいて説明すると、第1図
は原子力発電プラント建屋の内部構造を示す縦断面図、
第2図は本発明工法を進める上で一つのユニット構築物
を構成する原子炉建屋ブロックの内部構造を示す一部破
断斜視図、第3図は本発明工法によって構築された原子
炉建屋ブロック相互間の連結状態を示す縦断面図である
Hereinafter, the present invention will be explained based on the drawings. FIG. 1 is a longitudinal sectional view showing the internal structure of a nuclear power plant building;
Fig. 2 is a partially cutaway perspective view showing the internal structure of a reactor building block that constitutes one unit structure when proceeding with the construction method of the present invention, and Fig. 3 shows the relationship between the reactor building blocks constructed by the construction method of the present invention. FIG. 3 is a longitudinal sectional view showing a connected state.

原子力発電プラント建屋の内部構造を示す第1図におい
て、建屋内は、鉄筋コンクリートによシ、多数の部屋(
コンパートメント)に仕切られておム各部屋には、それ
ぞれ所定の機器1が1機械据付基礎2を介して据え付け
られている。t′/c1各部屋には、内部にケーブル4
を収容したケーブルトレー3や空調ダクト5なども取シ
付けられている。
In Figure 1, which shows the internal structure of a nuclear power plant building, the building is made of reinforced concrete and has many rooms (
Predetermined equipment 1 is installed in each room via a machine installation foundation 2. t'/c1 Each room has cable 4 inside.
A cable tray 3 containing a cable, an air conditioning duct 5, etc. are also attached.

本発明工法を進める上で一つのユニット構築物を構成す
る原子炉建屋ブロックの内部構造を示す第2図において
、第1図と同一符号は同一部分、6は系の途中に弁やフ
ィッティングを有する配管であって 機器工ないし配管
6などの必要設備を内部に装備した建屋ブロックの外側
は、補強リプ8を有する鋼製容器7によシ製作されてい
る。しかして、本発明において、上記したごとき鋼製容
器7からなる複数の建屋ブロックは、あらかじめ工場製
作されるものであって、機器工ないし配管6などの必要
設備も、あらかじめ工場において装備される。一方、原
子力発電プラントの建設現地の においては、上記した建屋ブロック、工場製作と併行し
て、これら建屋ブロック間を補強する鉄筋があらかじめ
所定の位置に配筋される。以上のようにして、鉄筋の現
地打ちが完了したならば、当該鉄筋の現地打ち作業と併
行して工場製作された建屋ブロックを建設現地に搬入し
、各ブロック間を鉄筋とともにコンクリート打ちするも
のであって、その状態を第3図に示す。第3図において
、第1図および第2図と同一符号は同一部分、9は鉄筋
を示している。なお、各建屋ブロック内に装備されてい
るケーブルトレー3、ケーブル4、空調ダクト5、配管
6などの各基を接続するには、建屋ブロックの工場製作
と併行しておこなわれる鉄筋9の現地打ちに際し、第3
図に符号10で示すスリーブをあらかじめ所定の位置に
据付固定しておき、コンクリート打設後、上記スリーブ
内の空間を利用して、各建屋ブロック相互間の配線系、
配管系を接続すればよい。また、建設現地に搬入された
複数の建屋ブロック相互間にコンクリートを打設するに
際しては、各建屋ブロックの開口部扉にバッキングを装
着するとともに、その扉をキーロックしておけばよく、
上記した簡単なシーリング作業によシ、コンクリート液
が建屋ブロック内に浸入するのを未然に防止することが
できる。
In Figure 2, which shows the internal structure of a reactor building block that constitutes one unit structure for carrying out the construction method of the present invention, the same reference numerals as in Figure 1 refer to the same parts, and 6 denotes piping with valves and fittings in the middle of the system. The outside of the building block, which is internally equipped with necessary equipment such as mechanics or piping 6, is made of a steel container 7 with a reinforcing lip 8. Therefore, in the present invention, the plurality of building blocks made of the above-mentioned steel containers 7 are manufactured in advance at a factory, and necessary equipment such as mechanics or piping 6 is also installed in advance at the factory. On the other hand, at the construction site of a nuclear power plant, reinforcing bars for reinforcing between these building blocks are arranged in advance at predetermined positions in parallel with the above-mentioned building blocks and factory fabrication. Once the on-site casting of reinforcing bars has been completed as described above, the factory-fabricated building blocks are delivered to the construction site and concrete is poured between each block along with the reinforcing bars. The state is shown in FIG. In FIG. 3, the same reference numerals as in FIGS. 1 and 2 indicate the same parts, and 9 indicates reinforcing bars. In addition, in order to connect the cable trays 3, cables 4, air conditioning ducts 5, piping 6, etc. installed in each building block, reinforcing bars 9 are cast on-site at the same time as the building block is manufactured at the factory. On the occasion of the third
A sleeve indicated by reference numeral 10 in the figure is installed and fixed in a predetermined position in advance, and after concrete is poured, the space inside the sleeve is used to connect the wiring system between each building block.
Just connect the piping system. Additionally, when pouring concrete between multiple building blocks that have been delivered to the construction site, it is sufficient to attach a backing to the opening door of each building block and to lock the door with a key.
By performing the simple sealing work described above, it is possible to prevent concrete liquid from penetrating into the building blocks.

〔発明の効果〕〔Effect of the invention〕

本発明は以上のごときであり、本発明によれば、以下に
列挙するような種々の効果を奏する。ことができる。
The present invention is as described above, and according to the present invention, various effects as listed below are achieved. be able to.

(1)原子力発電プラント建屋を複数の建屋ブロックに
分割してあらかじめ工場製作するようにしたから、建屋
内の耐蝕塗装は、各建屋ブロックを工場において製作し
た段階で実施することができ、従来のごとき建設現地で
の塗装作業を省略することができる。
(1) Since the nuclear power plant building is divided into multiple building blocks and prefabricated at the factory, corrosion-resistant coating inside the building can be done at the stage when each building block is manufactured at the factory, compared to the conventional method. Painting work at the construction site can be omitted.

(2)コンクリート型枠兼用の大型建屋ブロックを採用
したことによシ、コンクリート打設前後における型枠の
搬入、組立、解体、撤去作業が不要とな夛、さらにこれ
に付随する型枠の整備作業も不要となる。
(2) By adopting large building blocks that can also be used as concrete formwork, there is no need to transport, assemble, dismantle, or remove the formwork before or after concrete pouring, and there is no need to maintain the accompanying formwork. No work is required.

(3)建屋ブロックの工場製作と同時に、各建屋ブロッ
クに必要とする設備もあらかじめ工場において装備され
るため、建設現地で取り扱う部品点数が大幅に減少され
る。1100MWeクラスの原子力発電所を建設する場
合、従来にあっては、マット打設開始から燃料装荷まで
に約52ケ月程度(ただし、総合試運転期間を除く)を
必要としていたが、本発明によれば、その期間を30数
ケ月程度〔クリティカル−パス法(crilicll 
path method)にもとづいてなされた計画立
案による〕に短縮することができる。
(3) At the same time as the building blocks are manufactured at the factory, the necessary equipment for each building block is also pre-equipped at the factory, which greatly reduces the number of parts handled at the construction site. When constructing a 1,100 MWe class nuclear power plant, conventionally it took about 52 months from the start of mat laying to the time of fuel loading (excluding the total test run period), but according to the present invention, , the period was about 30 months [critical path method (crilicll method)]
(by planning based on the path method).

(4) 建設現地における足場の搬入、組立、解体、撤
去作業がほとんど不要となる。
(4) Transporting, assembling, dismantling, and removing scaffolding at the construction site is almost unnecessary.

(5)プラント建屋の建設工期短縮化にともない、建設
現地における各種付帯設備のヤード保管も短縮化される
ため、上記した付帯設備の防錆対策が容易となる。
(5) As the construction period for plant buildings is shortened, storage of various auxiliary equipment at the construction site in yards is also shortened, making it easier to take anti-rust measures for the auxiliary equipment mentioned above.

(6)上記した(3)の理由により、配管系のフラッシ
ングや耐圧テスト、さらには配線系のベルチェツクやシ
ーケンステストを工場側の作業とすることができる。
(6) Due to the above-mentioned reason (3), the flushing and pressure test of the piping system, as well as the bell check and sequence test of the wiring system, can be performed by the factory.

(7)同じく、上記した(3)の理由によシ、ヤード保
管される伺帯設備の部品点数が大幅に減少するため、膨
大な面積の付帯設備保管ヤードを確保する必要がない。
(7) Similarly, for the reason mentioned in (3) above, the number of parts of the belt-holding equipment stored in the yard is significantly reduced, so there is no need to secure a huge area of ancillary equipment storage yard.

以上詳述したごとく、本発明によれば、従来とは全く異
なる工法の採用によシ、工期の大幅短縮化をはかシ、プ
ラント運転開始の早期化を実現できるはかシか 建設現
地で取シ扱う各種付帯設備の大幅節減化をはかった、経
済性にすぐれた原子力発電プラント建屋の建設工法を得
ることができる。
As detailed above, according to the present invention, by adopting a construction method that is completely different from the conventional method, it is possible to significantly shorten the construction period and realize an earlier start of plant operation. It is possible to obtain an economically efficient construction method for a nuclear power plant building that significantly reduces the amount of various auxiliary equipment that must be handled.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は原子力発電プラント建屋の内部構造を示す縦断
面図、第2図は本発明工法を進める上で一つのユニット
構築物を構成する原子炉建屋ブロックの内部構造を示す
一部破断斜視図、第3図は本発明工法によって構築され
た原子炉建屋ブロック相互間の連結状態を示す縦断面図
である。 1・・・機器、2・・・機械据付基礎、3・・・ケーブ
ルトレー、4・・・ケーブル、5・・・空調ダクト、6
・・・配管、7・・・鋼製容器、8・・・補強リプ、9
・・・鉄筋、10・・・スリーブ。 代理人 弁理士 長崎博男1゜ (ほか1名) 第 ! 口 夢 21!]
FIG. 1 is a vertical sectional view showing the internal structure of a nuclear power plant building, and FIG. 2 is a partially cutaway perspective view showing the internal structure of a reactor building block that constitutes one unit structure in proceeding with the construction method of the present invention. FIG. 3 is a longitudinal sectional view showing the state of connection between reactor building blocks constructed by the construction method of the present invention. 1... Equipment, 2... Machine installation foundation, 3... Cable tray, 4... Cable, 5... Air conditioning duct, 6
... Piping, 7... Steel container, 8... Reinforcement lip, 9
...Reinforcing bar, 10...Sleeve. Agent Patent Attorney Hiroo Nagasaki 1゜ (and 1 other person) No. ! Mouth dream 21! ]

Claims (1)

【特許請求の範囲】[Claims] 1、原子力発電プラント部屋を複数の建屋ブロックに分
割してあらかじめ工場製作するとともに、各建屋ブロッ
クに必要とする設備もあらかじめ工場において装備し、
他方、建設現地においては、上記建屋ブロックの工場製
作と併行して、これら複数の建屋ブロック間を補強する
鉄筋をあらかじめ所定の位置に配筋しておき、工場製作
された上記建屋ブロックを建設現地に搬入した後、各建
屋ブロック相互間を、あらかじめ現地打ちした鉄筋とと
もにコンクリート打ちして連結することを特徴とする原
子力発電プラント建屋の建設工法。
1. The nuclear power plant room is divided into multiple building blocks and fabricated in advance at the factory, and the necessary equipment for each building block is also equipped in advance at the factory.
On the other hand, at the construction site, in parallel with the factory fabrication of the building blocks mentioned above, reinforcing bars for reinforcing between these multiple building blocks are placed in advance at predetermined positions, and the factory-fabricated building blocks are transported to the construction site. A construction method for nuclear power plant buildings, which is characterized by connecting each building block by pouring concrete together with reinforcing bars cast on-site in advance after the building blocks have been delivered to the site.
JP59025765A 1984-02-14 1984-02-14 Method of construction of housing for nuclear power plant Pending JPS60169797A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP59025765A JPS60169797A (en) 1984-02-14 1984-02-14 Method of construction of housing for nuclear power plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP59025765A JPS60169797A (en) 1984-02-14 1984-02-14 Method of construction of housing for nuclear power plant

Publications (1)

Publication Number Publication Date
JPS60169797A true JPS60169797A (en) 1985-09-03

Family

ID=12174930

Family Applications (1)

Application Number Title Priority Date Filing Date
JP59025765A Pending JPS60169797A (en) 1984-02-14 1984-02-14 Method of construction of housing for nuclear power plant

Country Status (1)

Country Link
JP (1) JPS60169797A (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5786785A (en) * 1980-11-20 1982-05-29 Hitachi Ltd Method of constructing atomic power plant building
JPS57205651A (en) * 1981-06-12 1982-12-16 Tokyo Shibaura Electric Co Method of executing house building

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5786785A (en) * 1980-11-20 1982-05-29 Hitachi Ltd Method of constructing atomic power plant building
JPS57205651A (en) * 1981-06-12 1982-12-16 Tokyo Shibaura Electric Co Method of executing house building

Similar Documents

Publication Publication Date Title
JPH07506643A (en) Modular reinforcing cage for ductile concrete frame members and method of manufacturing and erection thereof
Tatum What prompts construction innovation?
CN114411945A (en) Bin jump construction method based on BIM technology
KR19980080404A (en) Method of construction of plant buildings and modular structures used in the construction thereof
JPS60169797A (en) Method of construction of housing for nuclear power plant
JP3015415B2 (en) Nuclear power plant construction method
JPH09287157A (en) Steel shell structure of composite immersed tunnel and construction method thereof
Tatum Innovations in nuclear concrete construction
Burgan et al. An innovative form of steel-concrete (sc) structures for nuclear power plant
Rahman et al. Considerations in construction of nuclear cements: Materials, technologies, and management systems
JPH0862370A (en) Reactor container and reactor building
JP3273668B2 (en) How to construct a containment vessel
WO2022168109A1 (en) An improved method for manufacturing / constructing single cast concrete construction modular buildings
HUH3533A (en) Reinforced concrete lamellated supporting structure, method for producing same as well as reinforced concrete panel, cradling tray and method for producing reinforced concrete casket panel of twin plate
JPS62170640A (en) Outer wall structure of building
JPS60175647A (en) Construction of reinforced concrete
JPS5926095A (en) Method of constructing reactor building
JP2531045B2 (en) Construction method for reinforced concrete structure
JPH0649897A (en) Joining method for beam and pillar and precast concrete pillar applied to above method
JPS58204247A (en) Construction of reinforced concrete structure
JPS61102592A (en) Package control chamber and method of installing said control chamber
Hulshizer et al. Scale Models for Complex Reinforcement
JPS61175596A (en) Lining storage tank
Yotsuya et al. Design concept of composite module for nuclear power plant construction
JPS62273347A (en) Construction of building of atomic power plant