JPS60105715A - Consolidating and levelling weight for underwater rubble-mound foundation - Google Patents
Consolidating and levelling weight for underwater rubble-mound foundationInfo
- Publication number
- JPS60105715A JPS60105715A JP18267384A JP18267384A JPS60105715A JP S60105715 A JPS60105715 A JP S60105715A JP 18267384 A JP18267384 A JP 18267384A JP 18267384 A JP18267384 A JP 18267384A JP S60105715 A JPS60105715 A JP S60105715A
- Authority
- JP
- Japan
- Prior art keywords
- weight
- weight plate
- height
- top end
- vibrator
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 16
- 239000010959 steel Substances 0.000 claims abstract description 16
- 238000005056 compaction Methods 0.000 claims abstract description 6
- 238000010276 construction Methods 0.000 claims description 3
- 239000004575 stone Substances 0.000 claims description 2
- 239000004744 fabric Substances 0.000 claims 1
- 238000007596 consolidation process Methods 0.000 abstract description 9
- 230000005484 gravity Effects 0.000 abstract description 2
- 239000000463 material Substances 0.000 abstract description 2
- 238000001514 detection method Methods 0.000 abstract 1
- 238000005259 measurement Methods 0.000 abstract 1
- 238000000034 method Methods 0.000 abstract 1
- 230000001105 regulatory effect Effects 0.000 abstract 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 8
- 239000011150 reinforced concrete Substances 0.000 description 4
- 238000004519 manufacturing process Methods 0.000 description 2
- 239000004567 concrete Substances 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 210000003205 muscle Anatomy 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 238000009423 ventilation Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/10—Placing gravel or light material under water inasmuch as not provided for elsewhere
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Underground Or Underwater Handling Of Building Materials (AREA)
Abstract
Description
【発明の詳細な説明】
〔産業−1−の利用分野〕
本発明しJ、防波堤等の横築にあたり、ケーソン等の構
造体を設置固定するため築造Jる水中捨石7J rl;
aを圧密均しするのに使用する重錘に関する。[Detailed Description of the Invention] [Field of Application of Industry-1-] The present invention provides underwater rubble 7J rl, which is used for installing and fixing structures such as caissons in horizontal construction of breakwaters, etc.;
This relates to a weight used to consolidate and level a.
この種の重錘として、従来、ill、筋mlノンクリ1
・Hp、11あるいL;i′4171製の中空ゲージン
グの頭部に振動くい打機を固定−4′ろとともに、下端
に鉄筋τノンクリ−,1−沓を剛結合した振動締固め装
置が知られている(ソ連運輸建設省発行rTPAIIC
nOPTHOE c、 T p OM T EΔb′C
′rBO」1973年12月号)。Conventionally, as this kind of weight, ill, muscle ml non-critic 1
・Hp, 11 or L; A vibrating pile driver is fixed to the head of a hollow gauging made of i'4171, and a vibratory compaction device is rigidly connected to the lower end of the reinforcing bar τ non-crete, 1-shoe. known (rTPAIIC published by the Ministry of Transport and Construction of the USSR)
nOPTHOE c, T p OM T EΔb′C
'rBO' December 1973 issue).
〔発明が扮′決し、l;うとする問題点〕−1−記振動
締固め装置は、中空ケーシングの下端の沓が1失筋コン
クリ−1・製であり鋼1反にくらべI最弱であるため、
振動締固め能力が必ずしも充分でなく、特に長期間繰り
返し使用しているうちに、その沓自体に亀裂を生じるも
ので、このことは、中空ゲージングについても、それが
鉄筋コンクリ−1・製であるかぎり同様のことがいえる
。[Problems to be solved and attempted by the invention] -1- In the vibration compaction device described above, the shoe at the lower end of the hollow casing is made of unreinforced concrete and is the weakest compared to steel. Because there is
The vibration compaction capacity is not necessarily sufficient, and cracks occur in the shoe itself, especially after repeated use over a long period of time.This also applies to hollow gauging, even if it is made of reinforced concrete. The same thing can be said.
また、−J−記振動締固め装置は、中空ケーシングも
のI′if1部に振動くい打機を固定してしまってしΣ
ので、下、+6:Hに鉄筋コンクリ−1製沓を剛結合さ
せた全体、ずなわら、中空ろ一一シング、振動くい打機
及び鉄筋コンクリ−1・製置から成る装置全体をもって
、単体扱いしなジノればならず、その運世に不便である
ばかりでなく、振動くい打機を各中空ケーシングに個別
に設置する不経済を強いられると認められる。In addition, the vibratory compaction device described in -J- has a vibrating pile driver fixed to the I'if1 part of the hollow casing.
Therefore, the entire equipment consisting of the reinforced concrete shoe 1 rigidly connected to the bottom +6:H, the hollow filter shing, the vibrating pile driver, and the reinforced concrete 1/setting is assembled as a single unit. It is recognized that if the piles are not handled properly, it is not only inconvenient for the company's fortunes, but also that it is uneconomical to install a vibrating pile machine in each hollow casing individually.
本発明は、鋼材組立製の支枠の下端Gこ極厚鋼板製の錘
板を固定するとともに、この錘板に振動を与える振動機
を着脱自在にして設り、かつ、上記支枠δこは錘板の底
面を起点とする「1盛尺を設けたものである。The present invention fixes a weight plate made of an extremely thick steel plate to the lower end G of the support frame made of steel assembly, and also provides a removable vibrator that vibrates the weight plate, and is a 1-segment scale starting from the bottom of the weight plate.
したがって、 本発明によれば、極厚鋼板製の鍾仮に振
動を与えて所期の圧密均しを、効果的に、しかも長期に
わたって能力を減じることなく行うごとができ、必要に
応じ振動機を取り外した状態で、ずなわち錘板つき支枠
より成る重錘として自由落下させて使用できるとともに
、この重錘と振動機とを各別に運1駁できる。Therefore, according to the present invention, it is possible to perform the desired consolidation and leveling effectively and over a long period of time without reducing the capacity by applying vibrations to the pile made of extra-thick steel plate, and the vibrator can be used as needed. In the detached state, it can be used as a free-falling weight consisting of a support frame with a weight plate, and the weight and the vibrator can be used separately.
〔実施例〕
本発明圧密均し用重錘は、当該水中捨石基礎の大端の均
し幅、据付けるケーソン等の構造物の形状ないしは寸法
、水深、クレーン船の能力等に対応して、型鋼材及び極
厚鋼板等により、予めケーソンヤー]°゛等で製作する
ものである。[Example] The consolidation and leveling weight of the present invention can be used in accordance with the leveling width of the large end of the underwater rubble foundation, the shape or size of the structure such as a caisson to be installed, the water depth, the capacity of the crane ship, etc. It is manufactured in advance using a caisson wheel, etc. using shaped steel materials and extra-thick steel plates.
すなわち、本発明、圧密均し用重鍾aは、高さ方向の目
盛尺3を設けた支枠1を、4本の支柱4に梁5及び筋交
い6を適宜の間隔で配置して型鋼材により角柱形の櫓状
に組み、その下端に錘板2を固定している。That is, in the present invention, the consolidation and leveling hammer a is constructed by forming a support frame 1 provided with a scale scale 3 in the height direction, and placing beams 5 and braces 6 on four supports 4 at appropriate intervals. They are assembled into a prismatic tower shape, and a weight plate 2 is fixed to the lower end.
上記錘板2は、極厚鋼板により方形に形成し、下面に突
き固め用の鋼製の突起7を所要の間隔で列設するととも
に、各突起7の間の部分に、上下に貫通する水抜孔8を
列設し、吊り降ろし時の抵抗を軽減し、かつ水圧で小さ
な捨石が飛ばされないようにしている。The weight plate 2 is formed into a rectangular shape using an extra-thick steel plate, and has steel protrusions 7 for tamping arranged in rows at required intervals on the lower surface, and water that penetrates vertically between the protrusions 7. A series of holes 8 are provided to reduce resistance during lifting and lowering, and to prevent small rubble from being blown away by water pressure.
上記目盛尺3は、上記支枠lとは別体に製作し錘板2の
下面を起点とした1 cm単位の目盛を表示してあり、
当該水中捨石基礎の天端に吊り降ろしたとき、少なくと
も上側部が水面から突出するように前記各支柱4の外側
面に取り付けている。The scale 3 is manufactured separately from the support frame 1 and has a scale of 1 cm starting from the bottom surface of the weight plate 2.
It is attached to the outer surface of each of the pillars 4 so that at least the upper part protrudes from the water surface when it is suspended from the top of the underwater rubble foundation.
9は上記錘板2の一ヒ面中央に下端を固定して設立した
鋼管で、上端の天板1oに設けた1対の掛吊具11,1
1を前記支枠1の上側開口に臨ませるとともに、−上端
部に通気孔13を、下端部に通水孔14をそれぞれ開設
して、この鋼管9により浮力が発生しないようにしてい
る。Reference numeral 9 denotes a steel pipe whose lower end is fixed to the center of one side of the weight plate 2, and a pair of hanging tools 11, 1 are provided on the top plate 1o at the upper end.
1 faces the upper opening of the support frame 1, and has a ventilation hole 13 at the upper end and a water passage hole 14 at the lower end to prevent the steel pipe 9 from generating buoyancy.
15、15は1対の電動式の振動機で、それぞれ油圧式
のチャック16.16を備え、そのチャック16゜16
で前記掛吊具比11を咬持し、かつ振動機15゜15に
接続したワイヤーローブ17をクレーンのフ、7り18
にJJIけることにより、この圧密均し用徂錘aを吊り
上げたり吊り降ろしたりできるとともに、振動機15.
15により鋼管9を介して錘板2に振動、を与えること
ができるものである。Reference numerals 15 and 15 denote a pair of electric vibrators, each equipped with a hydraulic chuck 16.16.
The wire lobe 17, which is connected to the vibrator 15 and 15, is held on the hanging device 11 by the crane.
By placing JJI on the machine, this consolidation and leveling weight a can be lifted and lowered, and the vibrator 15.
15, it is possible to apply vibration to the weight plate 2 via the steel pipe 9.
19は振動機用の電源ゲーブル及びチャック16゜]6
用の送油パイプである。19 is the power cable and chuck for the vibrator 16°]6
This is an oil pipe for use.
上記構成の重錘aによる水中捨石基礎の圧密均しはつぎ
のようにして行う。Consolidation and leveling of the underwater rubble foundation using the weight a having the above configuration is carried out as follows.
まず、所要の捨石投入を行うことにより、天端を51画
高さより少し高くした水中捨石基礎を形成する。そのの
ら、天端両側位置を旗竿20により計画幅より少し余裕
をもたせて表示し、所要の検測をしながら捨石の過不足
を調整して天端が計画高さより少し高いことを確認する
。First, by putting in the required amount of rubble, an underwater rubble foundation with the top slightly higher than 51 steps is formed. Then, use the flagpole 20 to display the positions on both sides of the crown with a little more margin than the planned width, and make sure that the crown is a little higher than the planned height by adjusting the excess or deficiency of rubble while making the necessary inspections. .
そのうえ、クレーン船のクレーンのフック18にワイヤ
ーローブ17で吊下した重錘aを、その水中捨石基礎上
に吊り降ろし、支枠lの水1−突出具合及び1すIき具
合で、天端の輯圧ずべき量(計画高さより高い分)及び
凹凸方向を検知し、重錘aを上下動ずなわぢ所要の高さ
に吊り上げて自由落下することを所要回数繰り返し、起
立させたときその重錘aが極端にぐらつかない程度に荒
均しする。In addition, a weight a suspended by a wire lobe 17 from a hook 18 of a crane of a crane ship is lowered onto the underwater rubble foundation, and the top is adjusted to the extent that the supporting frame l protrudes from water and The amount of strain (higher than the planned height) and the direction of the unevenness are detected, and the weight a is lifted up and down to the required height and allowed to fall freely for the required number of times, and when it is stood up, Roughly level the surface to the extent that the weight a does not wobble excessively.
つぎに、測量者23が、固定点たとえば既設ケーソン2
1に設置しである測量器22により、天端」二に吊り降
ろし起立させた重1iaの支柱4に表示した目盛尺3を
読んで天端高ざを測量し、輯圧すべき正確な数値をトラ
ンシーバ−等でクレーン船のオペレーターに知らせる。Next, the surveyor 23 checks a fixed point, for example, the existing caisson 2.
Using the surveying instrument 22 installed at 1, the height of the crest was measured by reading the scale 3 displayed on the 1ia pillar 4 suspended and erected at the crest, and the exact value to be pressed was determined. Notify the crane ship operator using a transceiver, etc.
その数値により、オペレーターは、重錘aの吊り降ろし
高さを調節しながら吊り降ろし錘板2に振動を付与して
天端を輪圧し、この輪圧した天端高さを再度測定して計
画高さになるまでさらに輯圧して締め固め、以後上記操
作を継続して行うことにより当該水中捨石基礎の天端面
を計画高さに圧密均しすることができる。Based on the numerical value, the operator applies vibration to the hanging weight plate 2 while adjusting the lifting height of the weight a to apply ring pressure to the top, and then measures the top height with this ring pressure again and plans. By further compressing and compacting until the height is reached, and then continuing the above operations, the top surface of the underwater rubble foundation can be consolidated and leveled to the planned height.
なお、本実施例においては、支枠を角柱状に、錘板を方
形に形成した場合を示したが、支枠及び錘板は上記形状
に限らず、たとえば支枠を円柱状に、錘板を円形にそれ
ぞれ形成してもよいものである。In addition, in this embodiment, a case is shown in which the support frame is formed into a prismatic shape and the weight plate is formed into a rectangular shape, but the support frame and the weight plate are not limited to the above shapes. may each be formed into a circular shape.
また、目盛尺は支枠と別体でなく、支柱の所要部分に目
盛を直接表示するようにしてもよい。Further, the scale scale may not be separate from the support frame, but the scale may be directly displayed on a required portion of the support.
さらにまた、振動機は支枠の所要部位に設置するか、錘
板I−に水密構造にして直接載置してもよい。Furthermore, the vibrator may be installed at a required part of the support frame, or may be placed directly on the weight plate I- in a watertight structure.
本発明圧密均し用重錘によれば、支枠が当該水1118
石基礎に設置するゲーソン等の構造体に対応する高さを
¥Jするので、−上記基礎1農こ起立させたときの水上
突出共合及び傾き具合で、天☆1j、1の幅圧ずへb
L及び凹凸方向を検知でき、かつこの支枠の所要部位に
錘板の底面を起点として設けた目盛尺によって人品)の
旨さを/1llJ定でき、そのうえ、支枠εよ、lrl
4A組立製でその下端に極厚鋼板製の錘板を固定して
なるにより、重心が低く安定度が高いため、大端−にに
起立して行う(ibf圧を円lX化しその圧密作業を効
果的に実施できる。According to the consolidation and leveling weight of the present invention, the supporting frame is the water 1118
Since the height corresponding to the structure such as a geison installed on the stone foundation is ¥J, - the width pressure of the top ☆ 1j, 1 depending on the above water protrusion and inclination when the foundation 1 is erected. Heb
L and the uneven direction can be detected, and the quality of the workpiece can be determined by the scale scale provided at the required part of this support frame with the bottom of the weight plate as the starting point.
Since it is made of 4A assembly and has a weight plate made of extra-thick steel plate fixed to the lower end, the center of gravity is low and stability is high. Can be implemented effectively.
特に、上記のように、錘板は、極厚鋼板製であるからi
!:iJ久惺に富み、鉄筋コンクリ−1・製のものの如
き)1f6さがないので長期にわたり繰り返し使用する
のに浮部であり、製作も容易なものである。In particular, as mentioned above, the weight plate is made of extremely thick steel plate.
! It has a long life and does not have 1f6 (like those made of reinforced concrete), so it is a floating part that can be used repeatedly over a long period of time, and it is easy to manufacture.
また、振動機は、着脱自在であるから、錘板つきの支枠
と別に運IMでき、また、振動1浅を取り外し、ずなわ
ちfQなる錘板つき支枠を重錘とし、これを自由落下さ
ゼて実施例で述べたよ・うに荒均しするのに使用するこ
ともでき至便である。In addition, since the vibrator is removable, it can be operated separately from the support frame with a weight plate, and it is also possible to remove the vibration 1 shallow and use the support frame with a weight plate called fQ as a weight, and use it as a free fall. It can also be conveniently used for rough leveling as described in the embodiment.
図面第1,2図は本発明圧密均し用重錘の斜視図及び正
面図で、第1図は振動機を取り外した状態で、また第2
図は錘板のみを切断した状態で示し、第3図は上記単錘
にょる圧密均しの実施状況の説明図である。
■・・・支枠、2・・・錘板、15・・・振動機、3・
り目盛尺。
矛1図Figures 1 and 2 are a perspective view and a front view of the consolidation and leveling weight of the present invention.
The figure shows only the weight plate cut away, and FIG. 3 is an explanatory view of the state of implementation of consolidation leveling using the single weight. ■... Support frame, 2... Weight plate, 15... Vibrator, 3...
ri scale scale. Spear 1
Claims (1)
阜の構造物に対症、する高さを有する鋼)7(組立製の
支枠と、その支枠の下端に固定された極厚′5141反
製の錘板と、その錘板に振動を与える着JI4Th自在
な1辰動機と、上記支枠の所要部(☆に、−1−記錘板
のた「1盛尺とからなることを般徴とする水中捨石2、
(陥圧密均し用重錘。[Scope of Claims] 1. Not installed on the underwater 13 stone foundation 1- [Steel having a height that is compatible with the structure of the construction site] 7 (Assembled support frame and the lower end of the support frame) A fixed weight plate made of extra-thick '5141 cloth, a rotatable screwdriver that vibrates the weight plate, and the necessary parts of the above-mentioned support frame (☆, -1-marked on the weight plate) Underwater rubble 2, whose general characteristic is that it consists of a large scale.
(A weight for compaction and leveling.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18267384A JPS60105715A (en) | 1984-09-03 | 1984-09-03 | Consolidating and levelling weight for underwater rubble-mound foundation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18267384A JPS60105715A (en) | 1984-09-03 | 1984-09-03 | Consolidating and levelling weight for underwater rubble-mound foundation |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP12183277A Division JPS5456229A (en) | 1977-10-13 | 1977-10-13 | Method of construction of levelling underwater riprap foundation and heavy weight for levelling |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS60105715A true JPS60105715A (en) | 1985-06-11 |
JPH0326734B2 JPH0326734B2 (en) | 1991-04-11 |
Family
ID=16122431
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP18267384A Granted JPS60105715A (en) | 1984-09-03 | 1984-09-03 | Consolidating and levelling weight for underwater rubble-mound foundation |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS60105715A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105937242A (en) * | 2016-06-29 | 2016-09-14 | 江苏中海昇物联科技有限公司 | Filling control device for concrete filling pile and using method of filling control device |
CN106013160A (en) * | 2016-06-29 | 2016-10-12 | 江苏中海昇物联科技有限公司 | Cast-in-place concrete pile grouting height control device and using method thereof |
-
1984
- 1984-09-03 JP JP18267384A patent/JPS60105715A/en active Granted
Non-Patent Citations (2)
Title |
---|
TRANSPORTNOYE STROITYELBSTVO=1967SU * |
TRANSPORTNOYE STROITYELBSTVO=1973SU * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105937242A (en) * | 2016-06-29 | 2016-09-14 | 江苏中海昇物联科技有限公司 | Filling control device for concrete filling pile and using method of filling control device |
CN106013160A (en) * | 2016-06-29 | 2016-10-12 | 江苏中海昇物联科技有限公司 | Cast-in-place concrete pile grouting height control device and using method thereof |
Also Published As
Publication number | Publication date |
---|---|
JPH0326734B2 (en) | 1991-04-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110206493B (en) | Construction process of full-sleeve full-rotation bored pile | |
CN104074199B (en) | Underwater bearing platform construction method | |
CN109505229A (en) | Highway high gradient slope stress equilibrium and vibration damping are taken precautions against natural calamities high bridge pier structure and construction method | |
CN108487339A (en) | A kind of single pile bearing capacity method | |
CN112878332A (en) | Basement elevator shaft sump construction structure and method thereof | |
CN106284311B (en) | A kind of dry efficient construction technology of pore-forming cast-in-place concrete pile of rotary drilling rig | |
CN104264682A (en) | Anchor traction wall protection pile base layer concrete beam support pouring technology | |
CN114086567A (en) | Larsen steel sheet pile reinforcement construction method for side slope of foundation pit | |
JP2688560B2 (en) | Construction method of underground structure | |
CN109853635A (en) | A kind of flexibility vibration isolation plate board-plugging device and its application method | |
CN110725163B (en) | Composite roadbed device based on existing rail transit roadbed and pile construction method | |
JPS60105715A (en) | Consolidating and levelling weight for underwater rubble-mound foundation | |
JP2663021B2 (en) | Ground improvement method by sand pile formation ship | |
KR101159193B1 (en) | Fundation gravel sinking apparatus of sea-bottom for harbor fabric construction | |
JP5060579B2 (en) | Ground improvement direct foundation method | |
JP4363597B2 (en) | Solid foundation method | |
JPH0326733B2 (en) | ||
CN218116532U (en) | Full-rotation drilling machine foundation for protecting underground structures | |
CN211006679U (en) | Anti uplift soil pressure balancing device for foundation pit | |
CN116856408B (en) | Sinking method of steel casing suitable for deepwater bare rock area | |
CN115198797B (en) | Underground communication channel construction method combining three-side surrounding pipe curtain method and open cut | |
CN114182723A (en) | Karst tunnel foundation pile raft structure construction method | |
JPS6210329A (en) | Method and apparatus for tamping and leveling underwater rubble mound by hammer striking method | |
CN207048350U (en) | No-welding type steel kind design positioner based on contrary sequence method | |
JPS5828008Y2 (en) | Seabed rubble reinforcement leveling device |