JPS6010014A - On-site piling work - Google Patents
On-site piling workInfo
- Publication number
- JPS6010014A JPS6010014A JP11767883A JP11767883A JPS6010014A JP S6010014 A JPS6010014 A JP S6010014A JP 11767883 A JP11767883 A JP 11767883A JP 11767883 A JP11767883 A JP 11767883A JP S6010014 A JPS6010014 A JP S6010014A
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- tremie
- tube
- pit
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
- E02D15/04—Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Piles And Underground Anchors (AREA)
- Underground Or Underwater Handling Of Building Materials (AREA)
Abstract
Description
【発明の詳細な説明】
本発明は、ベントナイト溶液等の存在下で杭打設用孔を
掘削するステップ、該掘削孔内に鉄筋籠を挿入設置する
ステップ、および、トレミー管を該掘削孔内に挿入設置
しこれを介してコンクリートを打設するステップを含む
場所打ち杭の打設工法lこ関する。DETAILED DESCRIPTION OF THE INVENTION The present invention provides the following steps: drilling a pile driving hole in the presence of a bentonite solution, inserting a reinforcing bar cage into the drilling hole, and inserting a tremie pipe into the drilling hole. It relates to a method for driving cast-in-place piles, which includes the step of inserting and installing concrete into a pile and pouring concrete therethrough.
この種の工法においては、従来、次のような問題があっ
た。Conventionally, this type of construction method has had the following problems.
即ち、ベントナイト溶液等の安定液を多量に注入しなが
ら杭打設用孔を掘削するために、該掘削孔の底部lこは
スライムと呼d:れる相当な厚さの沈饅層が生成される
。そこで、鉄i11/i節の設置あるいはコンクリート
の打設置こ先立って、底サラえパケット工法、エアリフ
ト工法、ジェット工法あるいはジェットリフト工法等に
ょシ前記スライムをあらかた除去するのであるが、この
スライム除去から実際にコンクリートを打設するまでに
、一般に3θ分〜グθ分の時間を要するので、この間に
掘削孔の底部には再びスライムが沈澱してしまい、結局
3θan−グQtynのヌライム層がどうしても残って
しまう。That is, because a pile driving hole is excavated while injecting a large amount of a stabilizing liquid such as bentonite solution, a considerably thick layer of sediment, called slime, is formed at the bottom of the excavated hole. Ru. Therefore, before installing iron I11/I joints or pouring concrete, most of the slime is removed using the bottom cleaning packet method, air lift method, jet method, or jet lift method. Generally, it takes 3θ minutes to 3θ minutes to actually place concrete, so during this time slime will settle again at the bottom of the excavation hole, and in the end, a layer of slime of 3θan-gQtyn will remain. It ends up.
加えて、孔の掘削は通常オーガ等による機械掘削で行な
うので、掘削孔の底部はオーガ先端によってかなシ1欧
弱化されることとなる。In addition, since the hole is usually excavated mechanically using an auger or the like, the bottom of the hole is weakened by the tip of the auger.
このように、掘削孔の底部はスライムの沈I11と機械
1々i(削による軟弱化とが相俟って、極めて軟弱な状
態となる。従って、所定のスライム処理を行なっている
にも拘らず、コンクリートを打設して杭を築造した後、
杭の沈下を招くことがちシ、特に不同沈下する場合は、
1部構造体に悪影響を及ばず可能性が大であった。In this way, the bottom of the excavation hole becomes extremely soft due to the combination of slime sedimentation I11 and softening caused by machine scraping. First, after pouring concrete and building piles,
This tends to cause the pile to settle, especially if it settles unevenly.
There was a high possibility that there would be no adverse effect on the structure.
本発明は、上記従来実情に歌みてなされたものであって
、その目的は、掘削孔底部の軟弱な層を強化して、杭の
沈下を防止することができる、全く新規な場所打ち杭の
打設工法を提供せんとすることにある。The present invention has been made in consideration of the above-mentioned conventional situation, and its purpose is to provide a completely new cast-in-place pile that can strengthen the soft layer at the bottom of an excavation hole and prevent the pile from sinking. The purpose is to provide a pouring method.
以下、先ず本発明の一実施例を図面に基いて説明する。First, one embodiment of the present invention will be described below with reference to the drawings.
即ち、本発明工法による場所打ち杭の打設は次の手順で
行なわれる。That is, the driving of cast-in-place piles according to the construction method of the present invention is performed in the following steps.
(1)先ず、第1図(イ)に示すように、所定の位置に
ベントナイト溶液等の安定液(孔壁保護液)を注入しな
がら、オーガ(図示せず)等によって杭打設用孔1を機
械掘削し、その掘削孔1の底部にスライム2が沈敞する
まである程度の時間放置する。(1) First, as shown in Figure 1 (a), while injecting a stabilizing liquid (hole wall protection liquid) such as bentonite solution into a predetermined position, use an auger (not shown) etc. to drill into the pile driving hole. 1 is mechanically excavated and left for a certain period of time until the slime 2 settles at the bottom of the excavated hole 1.
(II)次に第1図(ロ)に示すように、例えばパケッ
ト工法によって、ni1記沈沫スライム2の除去を行な
う。(II) Next, as shown in FIG. 1(B), the ni1 precipitate slime 2 is removed by, for example, the packet construction method.
011) そして、第1図(ハ)に示すように、鉄筋前
6を挿入設置する。011) Then, as shown in FIG. 1(C), the front reinforcing bar 6 is inserted and installed.
怜 次に、第2図に示すような逆円雑犬の金属I!l!
!蓋体4をトレミー管5の先端に装盾し、第1図に)に
示すように、との蓋体4 (−Jきトレミー管5を、蓋
体4の先端が再び沈澱したスライム2を貫通して掘削孔
1の底部に達するまで挿入する。Rei Next, the metal I of the inverted circular mongrel as shown in Figure 2! l!
! The lid 4 is attached to the tip of the tremie tube 5, and as shown in Fig. 1, the lid 4 (-J) is attached to the tremie tube 5. Insert until it penetrates and reaches the bottom of the borehole 1.
位)そして、その状態において、第1図(ホ)に示すよ
うに、トレミー’+#5内にコンクリートCを充満させ
て、そのトレミー管5およびコンク!J−)Cの全重量
を前記円錐状萱体4に作用させ、その蓋体4を掘削孔1
の底部中央軟弱部にしっかりと喰い込ませる。) In that state, as shown in Figure 1 (e), the tremie '+ #5 is filled with concrete C, and the tremie pipe 5 and the concrete C! J-) The entire weight of C is applied to the conical shell 4, and the cover 4 is inserted into the excavation hole 1.
Press it firmly into the soft center center of the bottom.
(イ)次いで、第1図(へ)に示すように、トレミー管
5を若干引き揚げて、逆円雑犬蓋体4の内部およびその
付近にコンクリ、、−トcを流し込みながら、そのコン
クリートCの重量によってトレミー管5と蓋体4とを分
離させる。(a) Next, as shown in FIG. The tremie tube 5 and the lid body 4 are separated by the weight of the tremie tube 5 and the lid body 4.
&i) その後第1図(ト)に示すように、トレミー管
5の下部先端が打設コンクリートCの上面よりも常に下
方に位置する状態を維持するように、該トレミー管5を
徐々に引き揚け゛ながら連続的にコンクリートCを流し
込む。&i) Thereafter, as shown in FIG. Pour concrete C continuously.
(An そして最後に、第1図(イ)に示すように、余
盛コンクリートC′の除去ならびに地面Gの整地を行な
うのである。(An) Finally, as shown in FIG. 1(a), the excess concrete C' is removed and the ground G is leveled.
なお、L記の実施例においては、トレミー管5の先端に
装着する蓋体4として、金属製の逆円雑犬のものを用い
たが、1舅磁器製とか硬質デヲヌチツク製とか他の比較
的硬質の材料から構成されたものを用いてもよく、また
、逆円錐状に限らず逆角錐法のものとか、あるいは、第
3図0)、(ロ)に示すように外表面に多数の鋭い突起
4a・・・を付設して、全体として逆雑犬をなすものを
用いてもよい。In addition, in the embodiment described in L, a metal inverted round mongrel was used as the lid 4 attached to the tip of the tremie tube 5, but other comparative materials such as one made of porcelain or hard porcelain were used. It may be made of a hard material, and it is not limited to an inverted conical shape, but may also be an inverted pyramid shape, or one with many sharp edges on the outer surface as shown in Figure 3 0) and (b). The protrusions 4a... may be added to form a reverse mongrel as a whole.
円
また、第4図3こ示ず如く、逆余錐吠の蓋体4の上面に
固着された筒軸4bの外面に、直径方向に突出した突片
4C・・・を設ける一方、トレミー管5の開口端縁には
前記突片4C・・・と上下方向に嵌合する切欠部5aを
設けて、トレミー管5をその軸芯rsbに回転させるこ
と1こより、蓋体4を回転駆動し得るように槽成し、蓋
体4の逆円雑犬下面には、螺旋PK4d・・・を設け、
トレミー管5を回転させつつ下降させて、蓋体4を掘削
孔底部にねじ込むようにしてもよい。Further, as shown in FIG. 4, a protrusion 4C projecting in the diametrical direction is provided on the outer surface of the cylindrical shaft 4b fixed to the upper surface of the lid 4 of the inverted cone tube. A notch 5a is provided at the opening edge of 5 to fit in the vertical direction with the protrusion 4C, and by rotating the tremie tube 5 about its axis rsb, the lid 4 is rotationally driven. A spiral PK4d... is provided on the lower surface of the lid body 4 in a reverse circular shape.
The lid 4 may be screwed into the bottom of the excavation hole by lowering the tremie tube 5 while rotating it.
以上要するに、本発明による場所打ち杭の打設工法は、
泥水の存在下で杭打設用孔を掘削するステップ、該掘削
孔内に鉄→?i1由を挿入設置するステップ、および、
トレミー管を該掘削孔内に挿入設置しこれを介してコン
クリートを打設するステップを含む工法において、+’
+iJ記トレミー管を掘削孔内に設置してコンクリート
をすJ設するに、該トレミー管の下部先端に逆錐法蓋体
を装着し、この逆錐法蓋体が掘削孔の底に達する法典に
該トレミー管を掘削孔内に挿入設置し、その状態におい
て核トレミー管内にコンクリートを充満させて、そのト
レミー管およびコンクリートの全重量を前記先端逆錐法
蓋体に作用させ、しかる後、該トレミー管を若干引き揚
げてコンクリート重量によシ該トレミー管と逆錐法蓋体
とを分離させ、以後、該トレミー管を徐々に引き揚げな
がら連続的にコンクリートを打設することを特徴とする
。In summary, the method for driving cast-in-place piles according to the present invention is as follows:
The step of drilling a pile driving hole in the presence of muddy water, iron in the drilling hole →? a step of inserting and installing i1 Yu, and
In a construction method including a step of inserting and installing a tremie pipe into the excavation hole and pouring concrete through it, +'
When a tremie pipe is installed in an excavation hole and concrete is poured, an inverted conical cap is attached to the lower tip of the tremie pipe, and this inverted conical cap reaches the bottom of the excavation hole. The tremie pipe is inserted into the excavation hole, and in this state, the core tremie pipe is filled with concrete, and the entire weight of the tremie pipe and concrete is applied to the tip inverted conical lid. The method is characterized in that the tremie tube is lifted up a little to separate the tremie tube and the inverted conical lid due to the weight of the concrete, and then concrete is poured continuously while the tremie tube is gradually lifted up.
上記特徴構成により奏される作用および効果は下記の涌
シである。The functions and effects achieved by the above characteristic configuration are as follows.
即ち、トレミー管の先端に装着した逆惟吠の蓋体を、前
記第1図←)、(へ)に示したよう憂こ、トレミー管お
よびその内部のコンクリートの全重量によって、掘削孔
の底部に強力に喰い込ませ得ると共lこ、その蓋体の内
部およびその付近にコンクリートを確実に打設できるの
で、これが割栗石と同様の機能を発揮して掘削孔底部軟
弱層を十分に強化することとなp1前述のように掘削孔
底部に確実にコンクリートを打設できるので、従来のよ
うに孔底部と打設コンクリート杭下端との間にスライム
層が残存してしまうことが無く、従って、事後の杭沈下
や杭の不同沈下による上部構造体への恕影臂を確実に防
止できるに至ったのである。That is, as shown in Fig. 1 (←) and (f) above, the bottom of the excavation hole is covered by the reverse cover attached to the tip of the tremie pipe, due to the total weight of the tremie pipe and the concrete inside it. It is possible to forcefully dig into the hole, and also to ensure that concrete is placed inside and around the lid, which functions similarly to cracked stone and sufficiently strengthens the soft layer at the bottom of the borehole. P1 As mentioned above, concrete can be reliably placed at the bottom of the excavation hole, so there is no slime layer remaining between the bottom of the hole and the lower end of the poured concrete pile, as in the conventional case. This has made it possible to reliably prevent damage to the superstructure due to subsequent pile settlement or uneven pile settlement.
第1図ないし第8図は本発明工法に係る実施例の説明図
を示し、第1図(イ)〜伊)は工法の手順を示す概略断
面図、第2図は要部の斜視図、第3図(イ)、(ロ)は
夫々側実施例の要部断面図である。
第4図は別の実施例を示す要部の斜視図である。
1・・・杭打設用孔、2・・・スライム、3・・・鉄務
籠、 4・・・逆錐法蓋体、 5・・・トレミー管、C
・・・コンクリート。
−二
第1図
(’= ) (O) (ノー) (=)第2図
j ” ”−’L、、−5
し−J
第3図
(イ) (ロ)
第4図
0Figures 1 to 8 show explanatory diagrams of embodiments of the construction method of the present invention, Figures 1 (a) to 1) are schematic sectional views showing the steps of the construction method, and Figure 2 is a perspective view of the main parts. FIGS. 3(A) and 3(B) are sectional views of the main parts of the respective embodiments. FIG. 4 is a perspective view of main parts showing another embodiment. 1... Pile driving hole, 2... Slime, 3... Steel cage, 4... Inverted conical lid, 5... Tremie pipe, C
···concrete. -2 Fig. 1 ('= ) (O) (No) (=) Fig. 2 j ” ” -'L,, -5 -J Fig. 3 (A) (B) Fig. 4 0
Claims (1)
孔内に鉄117i籠を挿入設置するステップ、および、
トレミー管を該掘削孔内に挿入設置しこれを介してコン
クリートを打設するステップを含む場所打ち杭の打設工
法において、前記トレミー管を掘削孔内に設置してコン
クリートを打設するに、該トレミー管の下部先端に逆錐
状蓋体を装着し、との逆錐状蓋体が掘削孔の底に達する
法典に該トレミー管を掘削孔内に挿入設置し、その法典
において該トレミー管内にコンクリートを充満させて、
そのトレミー管およびコンクリートの全重量を前記先端
逆錐状蓋体に作用させ、しかる後、トレミー管を若干引
き揚げてコンクリート重量により該トレミー管と逆錐伏
蓋俸とを分離させ、以後、該トレミー管を徐々に引き拗
けながら升続的にコンクリートを打設することを特徴と
する場所J″Jち杭の打設工法。drilling a pile driving hole in the presence of muddy water; inserting and installing an iron 117i cage into the drilling hole; and
In a cast-in-place pile driving method that includes the step of inserting and installing a tremie pipe into the excavation hole and pouring concrete through it, installing the tremie tube into the excavation hole and pouring concrete, An inverted cone-shaped lid is attached to the lower tip of the tremie tube, and the tremie tube is inserted into the borehole until the inverted cone-shaped lid reaches the bottom of the borehole. filled with concrete,
The entire weight of the tremie pipe and concrete is applied to the tip of the inverted conical cap, and then the tremie pipe is pulled up slightly to separate the tremie pipe and the inverted conical cap by the weight of the concrete. A method of driving piles in places where concrete is poured in succession while gradually tightening the pipe.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP11767883A JPS6010014A (en) | 1983-06-29 | 1983-06-29 | On-site piling work |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP11767883A JPS6010014A (en) | 1983-06-29 | 1983-06-29 | On-site piling work |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS6010014A true JPS6010014A (en) | 1985-01-19 |
JPS6147929B2 JPS6147929B2 (en) | 1986-10-22 |
Family
ID=14717578
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP11767883A Granted JPS6010014A (en) | 1983-06-29 | 1983-06-29 | On-site piling work |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS6010014A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06272243A (en) * | 1993-03-19 | 1994-09-27 | Kajima Corp | End ground processing method for concrete pile and jig therefor |
JPH06280258A (en) * | 1993-03-25 | 1994-10-04 | Kumagai Gumi Co Ltd | Construction method of pile |
CN102392451A (en) * | 2011-09-30 | 2012-03-28 | 广州市市政工程机械施工有限公司 | Method for carrying out densely buckled concrete piling construction by drilling holes through flexible cutter |
JP2017089234A (en) * | 2015-11-10 | 2017-05-25 | 五洋建設株式会社 | Tremie pipe |
-
1983
- 1983-06-29 JP JP11767883A patent/JPS6010014A/en active Granted
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06272243A (en) * | 1993-03-19 | 1994-09-27 | Kajima Corp | End ground processing method for concrete pile and jig therefor |
JPH06280258A (en) * | 1993-03-25 | 1994-10-04 | Kumagai Gumi Co Ltd | Construction method of pile |
CN102392451A (en) * | 2011-09-30 | 2012-03-28 | 广州市市政工程机械施工有限公司 | Method for carrying out densely buckled concrete piling construction by drilling holes through flexible cutter |
JP2017089234A (en) * | 2015-11-10 | 2017-05-25 | 五洋建設株式会社 | Tremie pipe |
Also Published As
Publication number | Publication date |
---|---|
JPS6147929B2 (en) | 1986-10-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
GB2133068A (en) | Method of forming cast-in-place concrete pile | |
JPS6010014A (en) | On-site piling work | |
JPH05222729A (en) | Execution method for cast-in-place concrete pile, etc. | |
US3736757A (en) | Cast-in-situ concrete piles | |
US3410095A (en) | Method of making water-sealing pile barrier around an excavation cutoff area | |
JPS6146610B2 (en) | ||
JP3077747B2 (en) | Method and apparatus for removing concrete at pile head extra | |
JPS6119771B2 (en) | ||
US3358458A (en) | Methods for installing nondisplacement sand drains | |
JPS6136571Y2 (en) | ||
JPH05106222A (en) | Embedding method for wooden pile | |
GB2132667A (en) | Method of installing precast concrete piles | |
JPS59195925A (en) | Construction of on-site concrete pile | |
JPS582294B2 (en) | Continuous basement wall construction method | |
JPH01182410A (en) | Method of building cast-in-place concrete pile | |
JP3103286B2 (en) | Construction method of cast-in-place concrete pile | |
JP2000352053A (en) | Existing pile dismantling construction method | |
JPH042134B2 (en) | ||
JPS6149452B2 (en) | ||
SU881254A1 (en) | Method of erecting cast-in-place pile in bulging soil | |
JPH0121288B2 (en) | ||
JPS626023A (en) | Construction work for foundation pile | |
JPS58153895A (en) | Hole inserting steel pipe and construction of steel pipe inserting hole | |
JPS5842336B2 (en) | Construction method of underwater foundation using reverse piles | |
JPH06280258A (en) | Construction method of pile |