JPS5942160B2 - Tunnel primary winding method using bend panels - Google Patents

Tunnel primary winding method using bend panels

Info

Publication number
JPS5942160B2
JPS5942160B2 JP55037291A JP3729180A JPS5942160B2 JP S5942160 B2 JPS5942160 B2 JP S5942160B2 JP 55037291 A JP55037291 A JP 55037291A JP 3729180 A JP3729180 A JP 3729180A JP S5942160 B2 JPS5942160 B2 JP S5942160B2
Authority
JP
Japan
Prior art keywords
shoring
tunnel
panel
panels
square
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP55037291A
Other languages
Japanese (ja)
Other versions
JPS56135698A (en
Inventor
宏武 花方
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP55037291A priority Critical patent/JPS5942160B2/en
Publication of JPS56135698A publication Critical patent/JPS56135698A/en
Publication of JPS5942160B2 publication Critical patent/JPS5942160B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

【発明の詳細な説明】 本発明は、掘削されたトンネルの一次巻に当って、トン
ネル内に建込まれた支保工に、ペンドパネルを一時的に
固定してこれを型枠となし、支保工矢板とこのベンドパ
ネル間にコンクリートを充填してゆ(ペンドパネルによ
るトンネル−FIJ工法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention provides for the primary winding of an excavated tunnel by temporarily fixing pend panels to the shoring built in the tunnel and using this as a formwork. Concrete is filled between the sheet pile and this bent panel (tunnel using a bent panel - this relates to the FIJ construction method).

従来のトンネル−次巻工法には下記の工法がある。The conventional tunnel-subtraction construction method includes the following construction methods.

(1)バラセントルおよびセントルフオームによる工法 (2)埋殺し型枠による工法 (1)の方法は、鉄製骨組の外側にメタルフオームを当
てたセントルを使ってこれを型枠とする方法であシ、こ
れは本巻に使用される型枠と同様なものである。
(1) Construction method using loose center and center form (2) Construction method using buried formwork (1) Method uses a center with metal foam applied to the outside of the steel frame and uses this as the formwork. This is similar to the formwork used in this volume.

そしてこのセントルをもってトンネル全断面を逐次移動
させながらその一次巻を施工するのであるが、これによ
ると、その仕上カリが平滑で奇麗であるが、トンネル施
工延長が短い場合は非常に高価になる。
Then, the primary winding is constructed by moving the center one after another over the entire tunnel cross section, but this method produces a smooth and beautiful finish, but is very expensive if the length of the tunnel construction is short.

(2)の方法は、(1)とは反対に施工延長が短い場合
に、これが簡易に使用できるので広(用いられてきたも
のである。
Contrary to method (1), method (2) has been widely used because it can be easily used when the construction length is short.

そして、埋殺し型枠としてキーストンプレート又はエキ
スバンドメタルが通常使われている。
A keystone plate or expanded metal is usually used as the filling formwork.

このキーストンプレートを使つfc場合ハ、コンクリー
トの充填の様子が、コンクリート面が外部:(露出しな
いため、外部からこれを確認することが困難であるので
、その品質管理上問題がある。
In the case of fc using this keystone plate, the state of concrete filling is difficult to check from the outside because the concrete surface is not exposed, which poses a quality control problem.

エキスバンドメタルは、金網と二枚重ねにして使用され
るが、コンクリートのモルタル分が漏れ易く、これも品
質管理上好ましくないし、さらに作業環境上も好ましく
ない。
Extended metal is used as a double layer with a wire mesh, but the mortar in the concrete tends to leak, which is not desirable in terms of quality control and is also not desirable in terms of the working environment.

また、その施工時に、キーストンメタル又はエキスバン
ドメタルは、支保工に6接しながらコンクリートを打設
するのでこれに手間を喰い、施工性がよくなかった。
Furthermore, during construction, keystone metal or expanded metal has to be placed in concrete while contacting the shoring, which is time consuming and has poor workability.

本発明方法はこの両者の長所を生かした工法である。The method of the present invention takes advantage of the advantages of both.

これを図示のものに基いて説明する。This will be explained based on what is shown in the drawings.

1は掘削されたトンネルの地山であって、3はその内面
に建込まれたH型の支保工であシ、2は支保工3と地山
1との間に挿入された矢板である。
1 is the ground for the excavated tunnel, 3 is the H-shaped shoring built on its inner surface, and 2 is the sheet pile inserted between the shoring 3 and the ground 1. .

4は支保工3に容接されたナツトで、このナツト4にフ
オームタイ5を螺し込み、フオームタイ5を支保工3面
に立設する。
Reference numeral 4 denotes a nut which is fitted onto the shoring 3, and a form tie 5 is screwed into this nut 4, so that the form tie 5 is erected on the three sides of the shoring.

このフオームタイ5には約3tという大きな張力が加わ
るため、前記ナツト4は、容接部の歪みを考え、そして
十分なねじ山長を確保するために、高さ20m、mのロ
ングナットヒ使用する。
Since a large tension of about 3 tons is applied to the form tie 5, a long nut 4 with a height of 20 m is used to prevent distortion of the connecting part and to ensure a sufficient thread length.

6は角パイプで、フオームタイ5を中心として2本甚設
する。
6 is a square pipe, and two of them are installed around the form tie 5.

この角パイプは支保工3の曲率と同じとなるようベンダ
ーでベンド加工される。
This square pipe is bent using a bender so that it has the same curvature as the shoring 3.

角バイブロは一本の長さは2080m−mとし、これを
継足して使用できるようにしてその建込みに便ならしめ
る。
The length of one square vibro is 2080 m, and it can be used by adding more to make the construction easier.

そのために、その端部にこれよシ稍小ロ径のソケット状
管7を挿入6着し、このソケット状管7に次位の角バイ
ブロを挿入してこれを継足して行く。
For this purpose, a socket-shaped tube 7 with a slightly smaller diameter is inserted into the end of the tube, and the next square vibro is inserted into this socket-shaped tube 7 to add on.

角バイブロの断面の大きさは60X60X2.3m−m
位が適当であシ、ソケット状管Tは50×50 X 2
.3m−mとする。
The cross-sectional size of the square vibro is 60 x 60 x 2.3 m-m.
If the position is appropriate, the socket-shaped tube T is 50 x 50 x 2.
.. 3m-m.

8はペンドパネルであって、支保工3面と角バイブロ面
との間で挾持される。
Reference numeral 8 denotes a pend panel, which is held between the three supporting surfaces and the square vibro surface.

ペンドパネル8は従来の丸ピアーやマンホールの型枠材
として使用されてきた合板ベニア型枠材を使用する。
The pend panel 8 uses a plywood veneer formwork material that has been used as a formwork material for conventional round piers and manholes.

ペンドパネル8は厚さ28m、m巾700m−m長さ1
050m、mでその曲率は支保工3面に密着するよう予
めベンドされる。
The pendo panel 8 has a thickness of 28 m, a width of 700 m, and a length of 1 m.
At 050m, the curvature is bent in advance so that it comes into close contact with the three sides of the shoring.

前記厚さ28m−mはコンクリート打設時の最大側圧4
、8 t 、/m2 として決定したものである。
The thickness of 28mm is the maximum lateral pressure of 4 when concrete is placed.
, 8 t ,/m2.

9は座金であって両側に折曲状の耳部9’、 9’w設
け、この座金9で両角バイブロ、6を挾持した時、この
耳部S/、 S/で両パイプが外れないようにこれt抱
持する。
Reference numeral 9 is a washer with bent ears 9' and 9'w on both sides, and when the washer 9 holds the double-sided vibro and 6, the ears S/ and S/ prevent both pipes from coming off. I'll hold onto this.

10は座金9を両パイプに対して締付ける締付はナツト
である。
Numeral 10 is a nut that tightens the washer 9 against both pipes.

12は天端の迫め部施工の際に使用する遺構鉄板で、1
3は天板の両隣のペンドパネル8,8端間に亘ってこれ
を止着するための止着具(図示していない)の挿入穴で
ある。
12 is the iron plate of the remains used when constructing the apson part of the crown;
Reference numeral 3 denotes an insertion hole for a fastener (not shown) for fastening the pend panels 8 on both sides of the top plate between the ends thereof.

その施工の順序を説明すると、 トンネル状に掘削された地山1に支保工3が建込まれた
後、この支保工3にナツト4を所定ピッチ、すなわち1
050m−m毎に直接する。
To explain the construction order, after the shoring 3 is erected on the ground 1 excavated in the shape of a tunnel, nuts 4 are placed on the shoring 3 at a predetermined pitch, that is, 1
Directly every 050 m-m.

次いで、これにフオームタイ5を螺着して立設し、座金
9と締付はナツト10を嵌合しておく。
Next, the form tie 5 is screwed onto this and set upright, and the washer 9 and tightening nut 10 are fitted.

そして、施工は下部より始め、所定のコンクリート打設
置区劃においてその最下部より、2本の角バイブロ、6
0対を並設する。
Construction begins from the bottom, and two square vibrators, 6
0 pairs are installed in parallel.

そして隣接する角バイブロ、6間において2枚のペンド
パネル8,8を上から順欠落し込み、角座金9を締付は
ナツト10をもって締付け、ペンドパネル8,8ビ支保
工3に密着せしめる。
Then, the two pend panels 8, 8 are sequentially inserted from above between the adjacent square vibrators 6, and the square washers 9 are tightened with the nuts 10 to bring the pend panels 8, 8 into close contact with the support 3.

角バイブロの長さは2080m、mであり、ペンドパネ
ル8の長さは1050m、mであるので、一本の角バイ
ブロで、前記のように2枚のペンドパネル8,8を支持
する。
Since the length of the square vibro is 2080 m, and the length of the pendo panel 8 is 1050 m, m, one square vibro supports the two pendo panels 8, 8 as described above.

なお、実際には、ペンドパネル8を角バイブロに2枚落
し込んだ時、次回のペンドパネル8の取付けを容易にす
るため、ペンドパネル8が角バイブロよシ約10cm、
上に出るように適宜割り付けがしである。
In fact, when two pendo panels 8 are dropped into the square vibro, in order to make it easier to install the next pendo panel 8, the pendo panel 8 is placed about 10 cm from the square vibro.
It is arranged appropriately so that it appears at the top.

またこのためもあって下端および天端のペンドパネル8
角バイブロの長さは前記標準長のものより適宜短いもの
を使用する。
Also for this reason, the bottom and top pend panels 8
The length of the square vibro is appropriately shorter than the standard length.

ペンドパネル8の取付けが終れば、コンクリート11を
上方開口からペンドパネル8の上端附近まで流し込む。
When the installation of the pendo panel 8 is completed, concrete 11 is poured from the upper opening to the vicinity of the upper end of the pendo panel 8.

次に同様の方法で、次の2枚のペンドパネル8を取付け
これにコンク’)−NHc−流し込む。
Next, in the same manner, the next two pend panels 8 are attached and filled with Conc')-NHc-.

なおこの操作はトンネルの左右対称に、同じ高さを保ち
ながらその両側において同時に施工して行(。
This operation is carried out symmetrically on both sides of the tunnel, maintaining the same height.

そしてこれを順次天端附近まで行う。Then, do this sequentially until you reach the top.

天端における迫めは、左右のペンドパネル8゜8端間上
においてその間隙に遺構鉄板12を掛は渡してその挿入
穴13に図示のない止着具を挿入してこれを締付ける。
For tightening at the top, the remains iron plate 12 is hung in the gap between the ends of the left and right pend panels 8°, and a fastener (not shown) is inserted into the insertion hole 13 to tighten it.

そして支保工3の最上端の上に打設ホースが入るだけの
孔を掘削しておき、ここからコンクリートを流し込みコ
ンクリートの打設を完了する。
Then, a hole large enough for the pouring hose to be inserted is excavated above the top end of the shoring 3, and concrete is poured through the hole to complete concrete pouring.

適当な養生時間を経て解体するが、その解体の順序は、
これと全(逆の手順で行う。
It is dismantled after a suitable curing time, but the order of dismantling is as follows:
This and all (do in reverse order).

解体したペンドパネル8角バイブロ角座金9迫猫鉄板1
2などの型枠材は移動式足場(図示していない)に乗せ
矢の打設個所に移動し、再びこのコンクリート1区劃毎
の打設を繰返えして行く。
Disassembled pendo panel 8 angle vibro square washer 9 Sako cat iron plate 1
Formwork materials such as No. 2 are placed on a movable scaffold (not shown) and moved to the location where the arrows will be placed, and this concrete placement for each section is repeated again.

なお本発明工法における前記角バイブロは同様の目的を
達し得るものならばその断面形状はこれに限るものでは
ない。
Note that the cross-sectional shape of the square vibro in the construction method of the present invention is not limited to this, as long as it can achieve the same purpose.

また場合によっては断面が横に長い矩形状の一本のパイ
プを使いその中心線においてフオームタイ5が挿入し得
る透孔を穿設しておいて、同角パイフロの建込みに当っ
て同透孔にフオームタイ5を挿入してその施工をするよ
うにすることもできる。
In some cases, a rectangular pipe with a horizontally long cross section is used, and a through hole is drilled along its center line into which the form tie 5 can be inserted. It is also possible to install the form tie 5 by inserting the form tie 5 therein.

本工法は、以上の説明で判るように、冒頭に記載した、
従来の埋殺し型枠工法と同様に、支保工に直接型枠を固
定するものであり、そしてセントル工法と同様に型枠を
転用して反覆使用できるものである。
As you can see from the above explanation, this construction method is based on the
Like the conventional fill-in formwork method, the formwork is fixed directly to the shoring, and like the center method, the formwork can be repurposed and used repeatedly.

したがってセントル工法と同様に、施工後はコンクリー
ト面がそのまま露出するので、打設コンクリートの充填
状況を確認することができる。
Therefore, similar to the Center method, the concrete surface is exposed after construction, making it possible to check the filling status of the poured concrete.

また、埋殺し型枠工法に比べると型枠の表面が平滑であ
るので、打設コンクリートの流れが非常によく、またエ
キスバンドメタルのようにモルタルの漏れなど全くなく
品質管理の面でも非常に有利である。
In addition, since the surface of the formwork is smooth compared to the buried formwork method, the poured concrete flows very well, and unlike expanded metal, there is no mortar leakage, making it very easy to control quality. It's advantageous.

そして下より上方に向は順次ペンドパネルを組立て、順
次コンクリートを打設して行けるので、セントル工法と
は異なシ埋殺し型枠工法と同様に広い内空断面の施工を
することができるし、また埋殺し型枠工法と違い、支保
工に予めナラトラ6接しておくだけで後は型枠の組立て
が簡単であるので、その施工性が非常によい。
From the bottom to the top, pend panels can be assembled one after another and concrete can be poured one after the other, so it is possible to construct a wide internal cross-section, similar to the fill-in formwork method, which is different from the center construction method. Unlike the fill-in formwork method, the formwork can be easily assembled by simply contacting the Naratra 6 with the shoring in advance, so the workability is very good.

しかも反覆使用の転用可能回数が多いので埋殺し型枠工
法よりも安く施工できることは勿論セントル工法よりも
安価である。
Moreover, since it can be reused many times, it can be constructed at a lower cost than the fill-in formwork method, and of course, it is also cheaper than the center method.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明工法によるトンネルの左半部を示す側面
図、第2図はその左下部の型枠材の取付状態を示すその
拡大側面図、第3図はその天端の拡大側面図、第4図は
第1図の一部を横断して拡大して示した横断面図、第5
図は角パイプの胴視図、第6図は遺構鉄板の斜視図であ
る。 2・・・・・・矢板、3・・・・・・支保工、5・・・
・・・フオームタイ、6・・・・・・角パイプ、9・・
・・・・座金。
Fig. 1 is a side view showing the left half of the tunnel constructed by the construction method of the present invention, Fig. 2 is an enlarged side view showing the installation state of the formwork material in the lower left part of the tunnel, and Fig. 3 is an enlarged side view of the top of the tunnel. , FIG. 4 is an enlarged cross-sectional view of a part of FIG. 1, and FIG.
The figure is a perspective view of the square pipe, and Figure 6 is a perspective view of the remains of the steel plate. 2... Sheet pile, 3... Shoring, 5...
...Form tie, 6...Square pipe, 9...
...Washer.

Claims (1)

【特許請求の範囲】[Claims] 1 掘削されたトンネル地山に建込まれた支保工に、適
宜間隔をもってフオームタイを植設し、トンネル下方よ
り、フオームタイを中心として、支保工に、2本の角パ
イプを沿い付け、そして隣設の支保工間において各支保
工と各角パイプとの間にペンドパネル2落し込み、これ
をフオームタイに装着した座金で締め付け、そしてペン
ドパネルの上開口よシ矢板とベンドパネル間にコンクリ
ートを流し込み、これを順次天端まで行うペンドパネル
によるトンネル−次巻工法。
1. Plant the form ties at appropriate intervals on the shoring constructed in the excavated tunnel ground, and from the bottom of the tunnel, install two square pipes along the shoring, centering on the form ties, and then install them next to each other. Insert pend panel 2 between each shoring and each square pipe between the supports, tighten it with washers attached to form ties, and pour concrete between the sheet pile and bend panel through the upper opening of the pend panel. Tunnel-sequential construction method using pendo panels that are carried out sequentially to the top.
JP55037291A 1980-03-24 1980-03-24 Tunnel primary winding method using bend panels Expired JPS5942160B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP55037291A JPS5942160B2 (en) 1980-03-24 1980-03-24 Tunnel primary winding method using bend panels

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP55037291A JPS5942160B2 (en) 1980-03-24 1980-03-24 Tunnel primary winding method using bend panels

Publications (2)

Publication Number Publication Date
JPS56135698A JPS56135698A (en) 1981-10-23
JPS5942160B2 true JPS5942160B2 (en) 1984-10-12

Family

ID=12493599

Family Applications (1)

Application Number Title Priority Date Filing Date
JP55037291A Expired JPS5942160B2 (en) 1980-03-24 1980-03-24 Tunnel primary winding method using bend panels

Country Status (1)

Country Link
JP (1) JPS5942160B2 (en)

Also Published As

Publication number Publication date
JPS56135698A (en) 1981-10-23

Similar Documents

Publication Publication Date Title
JP2001098514A (en) Method for constructing arch rib of concrete arch bridge
JPS5942160B2 (en) Tunnel primary winding method using bend panels
JPS5916621B2 (en) How to build side walls of underground tanks
JP2730705B2 (en) Improvement method for soft ground
JPS6181979A (en) Precast prestressed concrete tank and execution method thereof
CN211898553U (en) Fixing template of underground pipe gallery band steel edge rubber waterstop
JPH04108916A (en) Construction method for reinforced banking body
CN113789949B (en) Construction method for splicing templates without horizontal construction joints
JPH0332586Y2 (en)
JP2651550B2 (en) Concrete tank side wall construction method
JP2764252B2 (en) Underground concrete structure repair material and repair method
CN111502077B (en) Construction method for joint of steel column and shear wall under uneven settlement
CN211872648U (en) Plugging structure for prestressed bent cap tensioning end notch
TW201700842A (en) Bar connecting method
JPS6192265A (en) Root winding method of iron pillar leg
AU2017100986A4 (en) Concrete / masonry hollow core clean out block cavity plug
JP2001207409A (en) Pier structure and its constructing method
JP2001317070A (en) Permanent form framing method for cellular concrete
JPH10311046A (en) Temporary post fixing method and device for erecting plug-in type post
JP3006239U (en) Stacking block with separator
JPS5862223A (en) Slope protection work
JPH06505787A (en) Elongated housing with large cross section and method for manufacturing the same
CN117738452A (en) Construction method for constructional engineering frame structure constructional column top concrete
JPS58218555A (en) Casting joint method of concrete
JPH05287761A (en) Building construction member and construction method of structure using the same