JPS5942127B2 - Construction method of steel plate cell embankment body - Google Patents

Construction method of steel plate cell embankment body

Info

Publication number
JPS5942127B2
JPS5942127B2 JP3689180A JP3689180A JPS5942127B2 JP S5942127 B2 JPS5942127 B2 JP S5942127B2 JP 3689180 A JP3689180 A JP 3689180A JP 3689180 A JP3689180 A JP 3689180A JP S5942127 B2 JPS5942127 B2 JP S5942127B2
Authority
JP
Japan
Prior art keywords
cell
steel plate
male
leader
jig
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP3689180A
Other languages
Japanese (ja)
Other versions
JPS56135607A (en
Inventor
博通 山下
正明 平田
徹 葛原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GOYO KENSETSU
Original Assignee
GOYO KENSETSU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GOYO KENSETSU filed Critical GOYO KENSETSU
Priority to JP3689180A priority Critical patent/JPS5942127B2/en
Publication of JPS56135607A publication Critical patent/JPS56135607A/en
Publication of JPS5942127B2 publication Critical patent/JPS5942127B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Revetment (AREA)

Description

【発明の詳細な説明】 本発明1は岸壁、防波堤、大水深護岸等港湾工事に使用
する鋼板セル堤体の築造方法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention 1 relates to a method for constructing a steel plate cell embankment body used in harbor construction such as a quay wall, a breakwater, and a deep water revetment.

同期バイブロハンマーを使用する大型鋼板セルは従来の
フラット鋼矢板を使用するセルに比較して多くの利点を
有するものであるから、その据付或いは打設作業におい
ては、バイブロハンマーにより海底砂地盤が振動し液状
化することによりセルがその打込中傾斜する場合が多く
、正確な施工は仲々困難である。
Large steel plate cells that use a synchronous vibrohammer have many advantages over cells that use conventional flat steel sheet piles, so during installation or driving work, the vibrohammer is used to vibrate the seabed sandy ground. Due to liquefaction, the cell often tilts during driving, making accurate construction difficult.

従って、セルの傾斜と回転を規制する外装治具を使用す
るのが望ましい。
Therefore, it is desirable to use an exterior jig that restricts the tilt and rotation of the cell.

然しセルは巨大なものであるから治具の重量軽減には努
力せねばならない。
However, since the cell is huge, efforts must be made to reduce the weight of the jig.

本発明の目的は、アーク部取付用の鋼板セル継手構造を
、外装治具に協同し利用することにある。
An object of the present invention is to utilize a steel plate cell joint structure for attaching an arc portion in conjunction with an exterior jig.

本発明の他の目的は、アーク部継手構造を鞘型スライド
リーダーとして利用して、現地海上での鋼板セルの据付
、打設作業に際してセル相互間隔を正しく保ち、傾斜を
防止し、又、アーク部取付位置をその円周上の予定点に
正しく設定するためにセルの回転を抑止するにある。
Another object of the present invention is to use the arc joint structure as a sheath-type slide leader to maintain correct cell spacing and prevent tilting during installation and pouring work of steel plate cells at sea, and to prevent arc The purpose is to prevent rotation of the cell in order to correctly set the mounting position at a predetermined point on its circumference.

又、これら堤体の築造方法においては最初の第1セルを
正確な位置、方向に据付けするのが仲々困難である。
Furthermore, in these methods of constructing embankments, it is difficult to install the first cell in the correct position and direction.

従って本発明の更に他の目的は仮設測量台としての杭、
徂仮設構造物を設置し、これに外装治具を取り付け、位
置決定上の問題を解決するにある。
Therefore, a further object of the present invention is to provide piles as temporary surveying platforms.
This involves installing a temporary structure, attaching an exterior jig to it, and solving the problem of positioning.

本発明方法は、杭組仮設構造物を第1セル据付予定点近
くに建設する工程と、この杭組尺設構造物に雄リーダー
を有する外装治具を着脱自在に取り付ける工程と、この
外装治具の雄リーダーに第1セルのアーク部取付用雌金
物を係合せしめながら第1セルを設置する工程と、前記
外装治具を前記杭組仮設構造物から取り外し前記第1セ
ルに取り付ける工程と、この第1セルに取付けた外装治
具の雄リーダーに第2セルのアーク部取付用雌金物を係
合せしめながら第2セルを設置する工程とより成ること
を特徴とする。
The method of the present invention comprises a step of constructing a temporary pile structure near the planned first cell installation point, a step of detachably attaching an exterior jig having a male leader to the pile structure, and a step of detachably attaching an exterior jig having a male leader to the pile construction. a step of installing the first cell while engaging a female metal fitting for attaching the arc portion of the first cell to a male leader of the tool; and a step of removing the exterior jig from the pile assembly temporary structure and attaching it to the first cell. The second cell is installed while engaging the female metal fitting for attaching the arc portion of the second cell to the male leader of the exterior jig attached to the first cell.

以下図面によって本発明の詳細な説明する。The present invention will be explained in detail below with reference to the drawings.

第1図に示される如く、鋼板セル1には一般にアーク部
2が施工後段で取り付けられる様に、アーク部継手構造
3が予めヤード組立ての際取り付けられている。
As shown in FIG. 1, an arc joint structure 3 is attached to the steel plate cell 1 in advance during yard assembly so that the arc section 2 is generally attached at a later stage of construction.

これは主として鞘型ケースプレート11及び水平板状ス
チフナ−12より成る雌金物であって、その詳細な平面
形状は第2図に示されている。
This is a female metal fitting mainly consisting of a sheath-shaped case plate 11 and a horizontal plate-shaped stiffener 12, and its detailed planar shape is shown in FIG.

本発明においてはこのケースプレート11を含む雌金物
としての強固な鞘型構造物をスライドリーダーとして利
用して、次期据付セル1cを正確に吊降するために、既
に設置、中詰された既設セル1bに平面的に見て三角形
に配置され、ピン構造で結合された鋼枠としてのパイプ
フレーム14の上方基部を鋼板セル頂部にノ・ンガーバ
イス15で取9付げ、フレーム14の下方基部はセル外
周に合致する曲面を有する曲面プレート16でセル1b
の外周に取り付ける。
In the present invention, in order to accurately suspend the next installation cell 1c by using a strong sheath-shaped structure as a female metal fitting including this case plate 11, an existing cell that has already been installed and filled is used as a slide leader. The upper base of the pipe frame 14, which is a steel frame arranged in a triangular shape when viewed from above in plan view and connected by a pin structure, is attached to the top of the steel plate cell with a screw vice 15, and the lower base of the frame 14 is attached to the cell. The cell 1b is formed by a curved plate 16 having a curved surface that matches the outer periphery.
Attach to the outer periphery of the

パイプフレーム140枠組の頂点はピンヒンジ20によ
って可変角度構造にする。
The apex of the pipe frame 140 has a variable angle structure with the pin hinge 20.

又、各辺長はその中間に介挿した逆ねじソケット17即
ち対向運動回転機構によって調節可能にする。
Further, the length of each side can be adjusted by a reverse screw socket 17 inserted between them, that is, a counter-movement rotation mechanism.

これらパイプフレーム14を主体とする外装治具の型状
を第3図で示す。
FIG. 3 shows the shape of the exterior jig mainly consisting of these pipe frames 14.

図中7は木材を曲面加工して作った摺動曲面構造材で、
ボルト、ナツトにより軽量鋼構造たるプレートブロック
6を介してH型鋼ビーム5に取り付けられる。
7 in the figure is a sliding curved structure material made by processing wood into a curved surface.
It is attached to the H-shaped steel beam 5 via a plate block 6, which is a lightweight steel structure, with bolts and nuts.

このH型鋼ビーム5は外装治具の主要材であり、ピンヒ
ンジ20によってパイプフレーム14に連結される。
This H-shaped steel beam 5 is the main material of the exterior jig and is connected to the pipe frame 14 by a pin hinge 20.

H型鋼ビーム5には雄リーダー厚鋼板9が溶接により取
り付けられ、その補強材としての雄リーダ一台座8が取
り付けられる。
A male leader thick steel plate 9 is attached to the H-shaped steel beam 5 by welding, and a male leader pedestal 8 is attached as a reinforcing material.

雄リーダ一台座8は作業中雌金物としてのスチフナ−1
2と時として接触する場合があるので木製とするのが好
ましい。
The male leader pedestal 8 is a stiffener 1 as a female hardware during work.
It is preferable to use wood as it may occasionally come into contact with 2.

又、10は重要な摺動材である雄摺動頭で、雄リーダー
厚鋼板9の先端にボルト、ナツトで取り付ける。
Further, 10 is a male sliding head which is an important sliding member, and is attached to the tip of the male leader thick steel plate 9 with bolts and nuts.

これは消耗品であるので、木材を曲面加工して作る。Since this is a consumable item, it is made by processing wood into a curved surface.

雄摺動頭10は、第2図に見られる通り、据付打設作業
中、常に鞘型のケースプレート11内部にあって、摺動
する。
As can be seen in FIG. 2, the male sliding head 10 always slides inside the sheath-shaped case plate 11 during the installation and pouring operation.

以上の雄、雌構造をかみ合わせるだめには、新だに吊込
まれるセル1cを既設セル1bに固定された外装治具、
就中、雄摺動頭10の上方から降下する。
To engage the above male and female structures, an exterior jig is used to fix the newly suspended cell 1c to the existing cell 1b.
In particular, it descends from above the male sliding head 10.

逆ねじソケット17による対向回転運動機構は第4図に
示すようにパイプフレーム140辺長調節のために使用
されるものであり、逆ねじソケット17はバンドツール
18によって手動回転せしめられ、所定の位置でロッキ
ングボールド19によって固定することができる様にパ
イプフレーム14に形成したねじの一部にロッキング溝
32を軸方向に設け、この溝32に逆ねじソケット17
ヲ介してロッキングボールド19を係合し、振動によっ
てソケットが回転するのを防止する。
The opposing rotation movement mechanism by the reverse screw socket 17 is used to adjust the side length of the pipe frame 140, as shown in FIG. A locking groove 32 is provided in the axial direction in a part of the thread formed in the pipe frame 14 so that it can be fixed with a locking bolt 19, and a reverse threaded socket 17 is provided in this groove 32.
The locking bolt 19 is engaged through the socket to prevent the socket from rotating due to vibration.

一般に鋼板セルの運搬、据付、打設に従事する起重機船
30はセルの直径に応じたリーチが求められ、大型起重
機船を選定せざるを得ない。
Generally, the hoist ship 30 that is engaged in transporting, installing, and pouring steel plate cells is required to have a reach that corresponds to the diameter of the cell, and a large hoist ship must be selected.

第5図において鋼板セル1の上端は油圧チャック25に
挾まれ、その直上には同期バイブロハンマー29が位置
を占める。
In FIG. 5, the upper end of the steel plate cell 1 is clamped by a hydraulic chuck 25, and a synchronous vibrohammer 29 is positioned directly above it.

更にその上方には鋼桁により作られる吊上支架23が、
バイブロハンマー使用台数と同数の枝を伸して連結され
ていて、アイピース等吊止金物を介して、支架台付ワイ
ヤロープ31により起重機船の主催ブロック21のフッ
クにより吊上げられるのが普通である。
Furthermore, above it is a suspension support 23 made of steel girders.
They are connected by extending the same number of branches as the number of vibrohammers used, and are usually hoisted by a hook on the host block 21 of a hoist ship using a wire rope 31 with a supporting stand via a hanging hardware such as an eyepiece.

従って、支架台付ワイヤローブは同じ長さのものが使用
されるのが常識であるが、本発明の場合は異なる。
Therefore, it is common knowledge that wire robes with supporting stands are of the same length, but this is different in the case of the present invention.

本発明では、主催ブロック21の吊上点は意図的に円形
鋼板セルの中心を外すようにし、セル自重は主催ブロッ
ク21と、吊上支架23の1本にワイヤロープとアイピ
ースにより連結した補助捲ブロック22との両方に負担
せしめる。
In the present invention, the lifting point of the organizer block 21 is intentionally set off the center of the circular steel plate cell, and the weight of the cell is transferred to the support block 21 and an auxiliary hoist connected to one of the lifting supports 23 by a wire rope and an eyepiece. The burden is placed on both the block 22 and the block 22.

荷重分担率は、現場の実情に応じて設定され、これによ
って各台付ワイヤーロープの長さは計算され、調製され
る。
The load sharing ratio is set according to the actual situation at the site, and the length of each attached wire rope is calculated and adjusted accordingly.

このように2点吊とすることにより吊上げられた鋼板セ
ルの回転は抑止できほぼ全工程にわたって円滑な作業が
可能になる。
By suspending the cell at two points in this manner, rotation of the lifted steel plate cell can be suppressed and smooth work can be carried out throughout almost the entire process.

又、別の作業上の問題として、最初に据付けられる第1
セル1aの海上での位置の決定が困難でありその解決方
策が求められている。
Another work problem is that the first
It is difficult to determine the location of the cell 1a on the sea, and a solution is needed.

港湾工事施工の常識として、セル群の据付作業は、まず
隅角部から開始される。
As is common sense in port construction, the installation of cell groups begins at the corners.

即ち、第6図において第1セル1aが最初に据付けられ
るものであるが、他の第2セル1 b、 第3セル1c
に比較すれば正確な据付作業は極めて困難である。
That is, in FIG. 6, the first cell 1a is installed first, but the other second cell 1b, third cell 1c
Accurate installation work is extremely difficult compared to

本発明方法では、第7図に示すH型鋼杭26と型鋼仮設
構造部材27と、木造床板28より成る測量台兼用の杭
組仮設構造物に予めパイプフレーム14、雄す−ダー摺
動頭9、及び摺動木材7等より成る前記外装治具主要部
分を取り付けておきこれを利用して第1セルを正確に吊
降し、打設する。
In the method of the present invention, a pipe frame 14 and a male slide head 9 are pre-assembled into a pile-assembled temporary structure that also serves as a surveying platform, which is made up of an H-shaped steel pile 26, a shaped steel temporary structure member 27, and a wooden floor plate 28, as shown in FIG. The main parts of the exterior jig consisting of , sliding wood 7, etc. are attached and used to accurately suspend and cast the first cell.

次に本発明の鋼板セル堤体の築造方法をその施工の順序
に従って述べる。
Next, the method for constructing the steel plate cell embankment body of the present invention will be described in accordance with the order of construction.

まず、鋼板セル溶接組立ヤードは、通常太造船所内の海
に面した構内に設けられ、溶接組立作業は、内装治具と
しての内挿リング枠4を数段取り付けながら行われる。
First, a steel plate cell welding assembly yard is usually installed in a sea-facing premises within the Taiyo Shipyard, and the welding assembly work is carried out while attaching several stages of inner ring frames 4 as interior jigs.

鋼板セルはその直径に比較して使用鋼板厚さが至って薄
いものであるから内挿リング枠4がなければ、組立、運
搬、据付、打設等の全工程にわたってその真円を保つこ
とができない。
Since the thickness of the steel plate used in the steel plate cell is extremely thin compared to its diameter, without the inner ring frame 4, it would be impossible to maintain its perfect circle throughout the entire process of assembly, transportation, installation, pouring, etc. .

本発明方法に用いる外装治具もこの内装治具と相まって
、初めて、効果を生ずるものである。
The exterior jig used in the method of the present invention is effective only when combined with this interior jig.

鋼板セルの海上運搬は通常大型台船を使用して行われる
Sea transportation of steel plate cells is usually carried out using large barges.

据付現場海上では、並行作業として必要な地盤改良工事
が実施され、要所にはH型鋼等の鋼材を使用した測量台
が杭組仮設構造物として設けられる。
At the installation site offshore, necessary ground improvement work will be carried out in parallel, and survey stands made of steel such as H-shaped steel will be installed as temporary structures with piles at key points.

通常とれは、第6図に示すセル中心線延長上のB点、或
いは前面接線延長上の0点に作られるが本発明の場合は
その何れでもない他の地点A点とする。
Normally, the break is made at point B on the extension of the cell center line shown in FIG. 6, or at point 0 on the extension of the front surface line, but in the case of the present invention, it is set at point A, which is neither of these points.

A点は、測量台の位置として測量技術上簡単に座標軸を
ずらせて換算できる。
Point A can be easily converted from the viewpoint of surveying technology by shifting the coordinate axes as the position of the surveying platform.

外装治具の取り付けに際しては、パイプフレー14の鋼
枠を逆ねじソケット17の位置で分解しソケットには新
たに現場合わせ用鋼管をねじ込む。
When installing the exterior jig, the steel frame of the pipe frame 14 is disassembled at the position of the reverse threaded socket 17, and a new steel pipe for field fitting is screwed into the socket.

正確な雄リーダー摺動部の位置は再度の精密測量結果に
よって、逆ねじソケット17によって調整される。
The exact position of the male leader sliding portion is adjusted using the reverse screw socket 17 based on the results of another precision survey.

起重機船によって吊上げられた鋼板セル1には第5図に
示すようにケースプレート11、スチフナ−12により
成るアーク部継手構造、雌金物が取り付けられていてそ
の下端に二分割形状の尖帽24で保護されている。
As shown in FIG. 5, the steel plate cell 1 hoisted by a hoist ship is fitted with a case plate 11, an arc joint structure consisting of a stiffener 12, and a female metal fitting, with a two-part shaped cap 24 attached to its lower end. protected.

アンカーワイヤーによる起重機船の慎重なシフト動作に
より尖帽24は雄リーダーの直上に到達し、以後鋼板セ
ルはその雌金物と雄リーダーが摺動しながら吊降される
By careful shifting of the hoist using the anchor wire, the pointed cap 24 reaches directly above the male leader, and thereafter the steel plate cell is suspended while its female hardware and male leader slide.

即ち、起重機船の捲ワイヤーを緩めスライドガイドが有
効に働くのを確認しつつ、低速で降下せしめるが、実際
上、主権ブロックと補助捲ブロックの降下レベルは、必
らずしも同一を良しとしない。
In other words, loosen the hoisting wire of the hoist and make sure that the slide guide is working effectively and lower the hoist at low speed, but in reality, the lowering level of the sovereign block and the auxiliary hoisting block do not necessarily have to be the same. do not.

例えば風圧などの要因に依り思わぬ傾斜が起きる場合が
あり、調整を要する。
For example, unexpected tilting may occur due to factors such as wind pressure, and adjustment is required.

本発明の2点吊方法では、これに有効に対処できる。The two-point hanging method of the present invention can effectively deal with this problem.

セル先端が海底に若干貫入して降下が停止したならば、
次には同期バイブロハンマー29を起動して所定の深度
まで鋼板セルを打設する。
If the tip of the cell slightly penetrates the sea floor and the descent stops,
Next, the synchronous vibrohammer 29 is activated to drive the steel plate cells to a predetermined depth.

以上で第1セル1aの据付、打設工程は終了したことに
なる。
With the above steps, the installation and pouring process of the first cell 1a has been completed.

次に油圧チャック25を開き、吊上支架を捲き上げて起
重機船を離脱せしめ内挿リング枠4を除去し、直ちに中
詰砂13を堤内に投入する。
Next, the hydraulic chuck 25 is opened, the lifting support is hoisted up, the hoist is removed, the inner ring frame 4 is removed, and the filling sand 13 is immediately thrown into the embankment.

又、第5図に示す杭組仮設構造物もすみやかに撤去し、
外装治具としてのパイプフレーム14は回収の上、逆ね
じソケットには正規部品としてハンガーバイス15、曲
面プレート16を含む端部パイプフレームが取り付けら
れ、第3図に示すような正規外装治具に復帰する。
In addition, the temporary structure made of piles shown in Figure 5 will be promptly removed.
After recovering the pipe frame 14 as an exterior jig, the end pipe frame including a hanger vise 15 and a curved plate 16 as regular parts is attached to the reverse threaded socket as a regular exterior jig as shown in Fig. 3. Return.

第2セル1b以降のセル据付、打設作業はこの外装治具
の摺動作業によりほぼ同様の手順によって、より簡単に
施工される。
The cell installation and pouring work for the second cell 1b and subsequent cells can be carried out more easily by substantially the same procedure by sliding the exterior jig.

外装治具を使用せず傾斜規制を一切性わない実験工事に
よれば、同期バイブロハンマーによる鋼板セルの地盤内
貫入速度は驚くほど速やかにあり吊ワイヤーを充分にゆ
るめるとセルはたちまち傾斜し、吊ワイヤーを引締める
と、再び容易に直立状態にもどることが知られていて、
この時の傾斜角は30度にも及ぶのである。
According to experimental work that did not use external jigs and did not impose any slope restrictions, the penetration speed of steel plate cells into the ground using a synchronous vibrohammer was surprisingly fast, and when the hanging wire was loosened sufficiently, the cells immediately sloped. It is known that if the hanging wire is tightened, it will easily return to its upright position.
The angle of inclination at this time is as much as 30 degrees.

これはバイブロハンマーの振動により海底砂地盤が液状
化するためであって、貫入が容易である反面、セルは極
めて傾斜し易く、ガイド用の治具を備えるととは施工上
極めて有利であることが明らかになった。
This is because the vibrations of the vibrohammer liquefy the seabed sandy ground, and while penetration is easy, the cell is extremely prone to tilting, and providing a guide jig is extremely advantageous in construction. has become clear.

又、実験によってこの外装治具にはさして大きな外力が
作用しないことも知られている。
It has also been known through experiments that no significant external force acts on this exterior jig.

従って第1図に示すような三角形を2個合わせたように
平面形状で見られるパイプフレームは、より軽量化して
三角形1個のフレームにすることも可能である。
Therefore, the pipe frame, which has a planar shape like two triangles combined as shown in FIG. 1, can be made lighter and made into a single triangle frame.

又、ハンガーバイス15を油圧チャックに換装するのも
良いし、下部の曲面プレート16は、セルに啓接したア
イピースにピン接合する構造にしても良い。
Further, the hanger vise 15 may be replaced with a hydraulic chuck, and the lower curved plate 16 may be connected with a pin to an eyepiece that is in contact with the cell.

種々の変型が、用途に応じて考えられる。Various modifications are possible depending on the application.

何れにしても本発明の方法によれば、直径30mを越え
る巨大な鋼板セルであっても、規定のセル間隔を正確に
保ち、かつ、アーク取付位置が狂わぬようにセルの円周
方向の回転を防ぎ、急速施工の要望を満たす築造方法を
、アーク部分セル継手構造としての鞘型鋼構造を利用し
て正確に実行することができる。
In any case, according to the method of the present invention, even if the cell is a huge steel plate exceeding 30 m in diameter, the prescribed cell spacing can be maintained accurately and the arc installation position can be maintained in the circumferential direction of the cell. A construction method that prevents rotation and meets the demands of rapid construction can be accurately implemented using the sheath type steel structure as an arc partial cell joint structure.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の外装治具取付状況を示す平面図、第2
図は本発明の外装治具摺動部分を詳細に示す平面図、第
3図は本発明外装治具パイプフレームの全体構造物を説
明する斜視図、第4図はパイプフレーム辺長アジャスト
装置を説明する斜視図、第5図は起動機船による吊上支
架2嵩吊方法を示す一部切欠斜視図、第6図は第1セル
据付作業方法を示す平面図、第7図は第1セル据付作業
の際利用される杭組飯設構造物の斜視図である。 1・・・鋼板セル、2・・・アーク部、3・・・アーク
部継手構造物、4・・・内挿リング枠、5・・・H型鋼
ビーム6・・・プレートブロック、7・・・摺動曲面構
造材、8・・・雄リーダ一台座、9・・・雄リーダー厚
鋼板、10・・・雄摺動頭、11・・・ケースプレート
、12・・・スチフナー、13・・・中詰砂、14・・
・パイプフレーム、15・・・バンカーバイス、16・
・・曲面フレート、17・・・逆ねじソケット、18・
・・バンドツール、19・・・ロッキングボールド、2
0・・・ピンヒンジ、21・・・主催ブロック、22・
・・補助捲ブロック、23・・・吊上支架、24・・・
尖帽、25・・・油圧チャック、26・・・H型鋼杭、
27・・・型鋼仮設構造部材、28・・・木造床板、2
9・・・同期バイブロハンマー、30・・・起重機船、
31・・・支架台付ワイヤロープ、32・・・ロッキン
グ溝、 ]5 了
Figure 1 is a plan view showing how the exterior jig of the present invention is installed;
The figure is a plan view showing details of the sliding part of the exterior jig of the present invention, Figure 3 is a perspective view illustrating the overall structure of the pipe frame of the exterior jig of the present invention, and Figure 4 is a side length adjustment device for the pipe frame. FIG. 5 is a partially cutaway perspective view showing a method for lifting two lifting supports using a starter boat, FIG. 6 is a plan view showing a method for installing the first cell, and FIG. 7 is a perspective view of the first cell. FIG. 2 is a perspective view of a pile-set structure used during installation work. DESCRIPTION OF SYMBOLS 1... Steel plate cell, 2... Arc part, 3... Arc part joint structure, 4... Insertion ring frame, 5... H-shaped steel beam 6... Plate block, 7...・Sliding curved surface structural material, 8... Male leader single pedestal, 9... Male leader thick steel plate, 10... Male sliding head, 11... Case plate, 12... Stiffener, 13...・Filled sand, 14...
・Pipe frame, 15...Bunker vice, 16・
...Curved surface plate, 17... Reverse screw socket, 18.
...Band Tool, 19...Rocking Bold, 2
0...Pin hinge, 21...Organizer block, 22.
... Auxiliary winding block, 23 ... Lifting support, 24 ...
Pointed cap, 25...Hydraulic chuck, 26...H-shaped steel pile,
27... Temporary steel structure member, 28... Wooden floor board, 2
9... Synchronous vibrohammer, 30... Hoist ship,
31... Wire rope with support stand, 32... Locking groove, ]5 Completed

Claims (1)

【特許請求の範囲】 1 杭組仮設構造物を第1セル据付予定点近くに建設す
る工程と、この杭組仮設構造物に雄リーダーを有する外
装治具を着脱自在に取り付ける工程と、この外装治具の
雄リーダーに第1セルのアーク部取付用雌金物を係合せ
しめながら第1セルを設置する工程と、前記外装治具を
前記杭組仮設構造物から取り外し前記第1セルに取り付
ける工程と、この第1セルに取り付けた外装治具の雄リ
ーダーに第2セルのアーク部取付用雌金物を係合せしめ
ながら第2セルを設置する工程とより成ることを特徴と
する鋼板セル堤体の築造方法。 2 前記雄リーダーが雄リーダー厚鋼板と、この雄リー
ダー厚鋼板の端面に形成した雄摺動頭とより成り、前記
外装治具が三角形状に連結された伸縮自在のパイプフレ
ームと、セルの上端に係合可能なバンガーバイスと、セ
ルの外周面に合致する曲面プレートとより成る特許請求
の範囲第1項に記載の築造方法。
[Claims] 1. A step of constructing a temporary pile structure near the planned installation point of the first cell, a step of detachably attaching an exterior jig having a male leader to the temporary structure, and a step of installing the first cell while engaging the male leader of the jig with a female metal fitting for attaching the arc portion of the first cell; and a step of removing the exterior jig from the pile-assembly temporary structure and attaching it to the first cell. and a step of installing the second cell while engaging the female metal fitting for attaching the arc portion of the second cell to the male leader of the exterior jig attached to the first cell. construction method. 2. The male leader consists of a male leader thick steel plate and a male sliding head formed on the end face of the male leader thick steel plate, and the exterior jig includes a telescopic pipe frame connected in a triangular shape, and an upper end of the cell. The construction method according to claim 1, comprising a banger vice that can be engaged with the cell and a curved plate that matches the outer peripheral surface of the cell.
JP3689180A 1980-03-25 1980-03-25 Construction method of steel plate cell embankment body Expired JPS5942127B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3689180A JPS5942127B2 (en) 1980-03-25 1980-03-25 Construction method of steel plate cell embankment body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3689180A JPS5942127B2 (en) 1980-03-25 1980-03-25 Construction method of steel plate cell embankment body

Publications (2)

Publication Number Publication Date
JPS56135607A JPS56135607A (en) 1981-10-23
JPS5942127B2 true JPS5942127B2 (en) 1984-10-12

Family

ID=12482393

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3689180A Expired JPS5942127B2 (en) 1980-03-25 1980-03-25 Construction method of steel plate cell embankment body

Country Status (1)

Country Link
JP (1) JPS5942127B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0313146Y2 (en) * 1982-10-05 1991-03-27

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109853581B (en) * 2019-01-18 2021-08-03 苏州交通工程集团有限公司 Mechanism for improving verticality qualification rate of open-cut tunnel foundation pit steel latticed column and using method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0313146Y2 (en) * 1982-10-05 1991-03-27

Also Published As

Publication number Publication date
JPS56135607A (en) 1981-10-23

Similar Documents

Publication Publication Date Title
EP3517479B1 (en) Device and method for providing a sizeable, slender object with a longitudinal direction into an underwater bottom
US6113315A (en) Recoverable system for mooring mobile offshore drilling units
CN206826891U (en) A kind of offshore wind turbine single pile pile sinking operation based on barge with deck transformation is refuted
CN109853567B (en) Pile sinking method for offshore wind power rock-socketed steel pipe pile
CN109629568A (en) The process for sinking of the steady stake platform of offshore wind farm jacket foundation steel pipe pile floating
JPH09508186A (en) High tension leg platform and its installation method
CN211713979U (en) Foundation pit excavation slope supporting device
WO2021052174A1 (en) Negative-pressure barrel type single pile gripper construction mechanism and construction method thereof
JP2543405B2 (en) Super buoy type boring turret and mooring device
AU771609B2 (en) Method for removing a jacket of a drilling or production rig and vessel provided with a device therefor
JPS5942127B2 (en) Construction method of steel plate cell embankment body
CN111962552A (en) Offshore wind power foundation driving-in type rock-socketed single pile construction process
JP2541897B2 (en) Installation method of shallow water bowling turret and its turret device
CN111962543A (en) Rapid connection and separation process of pile stabilizing platform and mother ship
JPS59199914A (en) Connectional erection of pc pile
KR101358216B1 (en) Pin-type lifting frame and derrick installation method using the pin-type lifting frame
JPH06299551A (en) Steel pipe pile erected in water
CN109914411A (en) A kind of non-embedding lithotype construction technology of marine four pile leaders frame
JP2002021097A (en) Installation method for leg member of tower type structure and device used therefor
JPS5822785A (en) Working steel tube containing structure in marine working ship
CN111794225B (en) Automatic pile hoisting method
JPH0742182A (en) Leg type underwater tunnel and construction method for leg type underwater tunnel
CA1194856A (en) Method of installing subsea templates
CN212506363U (en) Equipment suitable for rock-socketed construction of offshore wind power high-rise pile cap foundation
JP2759428B2 (en) Underwater steel pipe pile driving method and equipment