JPS5926746B2 - Steel tower raising method and equipment - Google Patents

Steel tower raising method and equipment

Info

Publication number
JPS5926746B2
JPS5926746B2 JP4389079A JP4389079A JPS5926746B2 JP S5926746 B2 JPS5926746 B2 JP S5926746B2 JP 4389079 A JP4389079 A JP 4389079A JP 4389079 A JP4389079 A JP 4389079A JP S5926746 B2 JPS5926746 B2 JP S5926746B2
Authority
JP
Japan
Prior art keywords
elevating
steel tower
pedestal
height
pillars
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP4389079A
Other languages
Japanese (ja)
Other versions
JPS55136374A (en
Inventor
貞夫 阪部
進 関屋
晴彦 永見
勝美 川畑
正雄 市原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kansai Electric Power Co Inc
Original Assignee
Kansai Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kansai Electric Power Co Inc filed Critical Kansai Electric Power Co Inc
Priority to JP4389079A priority Critical patent/JPS5926746B2/en
Publication of JPS55136374A publication Critical patent/JPS55136374A/en
Publication of JPS5926746B2 publication Critical patent/JPS5926746B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 本発明は、送電線、放送アンテナ、貯水槽、広告等用の
鉄塔構築物の嵩上げ工法およびその装置に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method and apparatus for raising the height of steel tower structures for power transmission lines, broadcasting antennas, water tanks, advertisements, etc.

例えば送電線鉄塔において、近年都市近郊の過密化に伴
ない、既設の送電線に接近して建造物が建設されて送電
線の高さを高くする必要が生じ、鉄塔の嵩上げが必要と
なる場合が多く見られる。
For example, in the case of power transmission line towers, in recent years, as urban areas have become overcrowded, buildings have been constructed close to existing power lines, making it necessary to raise the height of the power lines. are often seen.

従来、このような鉄塔の嵩上げを行うには、種々の方法
が試みられている。
Conventionally, various methods have been tried to raise the height of such steel towers.

例えば鉄塔の中心に高い棒状鉄柱を設け、鉄塔の下端を
取りはずした鉄塔全体、又は鉄塔の中間部を取りはずし
た鉄塔の上部を支えるワイヤ又はロープを取り付け、前
記鉄柱の頂部のローラを介してウィンナで引張って前記
鉄塔の全体又は上部を吊り上げた後、新設の鉄塔脚部又
は中間構成部を取付けることにエリ、鉄塔の嵩上げを行
なう方法がある。
For example, a high bar-shaped steel pole is installed at the center of the steel tower, and a wire or rope is attached to support the entire steel tower with the lower end removed, or the top of the steel tower with the middle section removed, and a wire or rope is attached to the steel tower through a roller at the top of the steel tower. There is a method of raising the height of the steel tower by lifting the entire or upper part of the steel tower by tensioning and then attaching a new tower leg or intermediate component.

この方法では、鉄柱の高さが高いため、風荷重又は鉄柱
の撓み等による鉄塔上部の横振れが生じ易く、又鉄塔の
支持吊り上げをワイヤ又はロープによるため、安定性に
欠け、又鉄柱およびワイヤ又はロープに強度の限度があ
るため、鉄塔の大きさ、嵩上げ高さに制限がある欠点が
あった。
In this method, since the height of the steel column is high, the upper part of the steel tower tends to sway due to wind loads or deflection of the steel column, etc. Also, since the steel tower is supported and lifted using wires or ropes, it lacks stability. Another disadvantage is that there is a limit to the strength of the rope, which limits the size and height of the tower.

又中間構成部全取付ける方法では、取付箇所以下の構成
部の強度が旧設計の強度しか有しないため、嵩上げ高さ
にその設計裕度内の制限がある欠点があった。
Further, in the method of attaching all the intermediate components, the strength of the components below the attachment point is only that of the old design, so there is a drawback that the raised height is limited within the design tolerance.

又他の方法として、鉄塔の外側に枠組構成体を設け、上
部鉄塔を支承する上部梁ケシリンダ−によりせり上げる
か(特公昭50−32526号)、又枠組構成体の内部
に設けた昇降台上にのせた鉄塔上部を下方より上方にせ
り上げて(%公昭48−26614号)、その下方に鉄
塔脚部全取付ける方法がある。
Another method is to install a frame structure on the outside of the steel tower and raise it up using an upper beam cylinder that supports the upper steel tower (Special Publication No. 32526/1983), or to install a frame structure on the inside of the frame structure. There is a method in which the upper part of the steel tower placed on the steel tower is raised upward from the bottom (% Publication No. 48-26614), and all the legs of the steel tower are attached below that.

これらの方法では、強面的には優れた枠組構成体を作成
し得、鉄塔の高さ、嵩上げ高さに制限はないものの、特
に枠組構成体を鉄塔の外側に設けるため、大きな作業用
敷地を必要とし、このような空地のない狭い場所や、用
地確保のむつかしい場所では不可能である欠点があった
These methods make it possible to create a frame structure that is superior in terms of strength, and there are no restrictions on the height or raised height of the steel tower. However, it has the disadvantage that it is not possible in such narrow spaces with no open space or where it is difficult to secure land.

又いずれの方法も、工事中の鉄塔の横振れ、鉄塔のせり
上げ時の不安定性などによる安定性の欠如、作業者の安
全性に問題があること、構成体の組立てに時間がかかる
ことなどから鉄塔を使用状態で嵩上げすること、例えば
送電線鉄塔を活線架線のまま嵩上げすることは不可能で
あり、嵩上げのため長期間停電するか、バイパス送電の
ための仮工事を必要とする欠点があった。
In addition, with either method, there are problems such as a lack of stability due to lateral vibration of the steel tower during construction, instability when raising the tower, problems with worker safety, and the time it takes to assemble the structure. For example, it is impossible to raise the height of a transmission line tower while it is in use, for example, it is impossible to raise the height of a transmission line tower with live overhead wires, and the disadvantage is that raising the height requires a long-term power outage or temporary construction for bypass power transmission. was there.

本発明は、上述の問題点を解消するもので、鉄塔の内側
に特殊な構造の嵩上げ装置を設け、特殊な工法をとるこ
とにより、作業用敷地が小さくてすみ、かつ仮工事が不
要なため、きわめて経済1.hであり、施工性が良く、
安全性が高いため使用状態で、例えば送電線鉄塔では活
線架線のまま、嵩上げができ、さらに大型鉄塔への適用
が可能な鉄塔の嵩上げ工法およびその装置v提供せんと
するものである。
The present invention solves the above-mentioned problems.By installing a specially constructed raising device inside the steel tower and using a special construction method, the work site can be kept small and temporary construction is not required. , very economical 1. h, good workability,
It is an object of the present invention to provide a method and device for raising the height of a steel tower, which is highly safe and can be raised while in use, for example, in a power transmission tower while the overhead wire is still live, and which can be applied to large steel towers.

本発明は、鉄塔の下端脚部を継ぎ足して鉄塔を嵩上げす
る方法において、 (a) 前記鉄塔の内側に、隅に少くとも3本の支柱
を有し、箱状枠組体より成る地上に固定された固定架台
と、その上方に、前記固定架台の支柱に夫々摺動可能に
形成された少くとも3本の支柱を有し、かつ上部に既設
鉄塔の脚部を固着支持する接続具を有する箱状枠組体よ
り成る所定高さの昇降架台と、前記昇降架台の前記支柱
の外側又は内側に該昇降架台を上下させるためのジヤツ
キとを設け、 (b) 前記昇降架台上部の前記接続具を前記鉄塔の
脚部に接続固着し、 (c) 前記鉄塔の脚部の下端全地上より取りはずし
て前記鉄塔を前記固定架台と前記昇降架台に支持させ、 (d) 前記ジヤツキを上昇させて前記昇降架台を前
記鉄塔とともに1ストローク上昇させ、前記昇降架台を
前記固定架台に仮固定するか、又は前記昇降架台の1ス
トローク上昇および前記仮固定の操作後引続き前記ジヤ
ツキの上端を下降させて前記昇降架台の下方に接続替し
て前記昇降架台の1ストローク上昇および前記仮固定の
操作を、前記固定架台に対する前記昇降架台の重なり高
さく以下、ラップ代と称す)に余裕がある間−回以上行
ない、 (e) 前記(a)の前記昇降架台の上昇および前記
仮固定の1回以上の操作により前記ラップ代に余裕が無
くなる毎に、前記昇降架台の下方に所定高さの前記支柱
を含む下方構成体を順次継ぎ足して前記昇降架台の高さ
を順次太きくし、 (f) 前記(d)および(e)の操作により前記鉄
塔の地上高さが所定の高さに達した後、該鉄塔の脚部の
下端と予め組立てられた新設の下脚部と全接続すること
を特徴とする鉄塔の嵩上げ工法、およびそれに使用され
る鉄塔の嵩上げ装置である。
The present invention provides a method for raising the height of a steel tower by adding the lower end legs of the steel tower. A box having a fixed pedestal and at least three pillars above the fixed pedestal, each of which is slidably formed on each of the pillars of the fixed pedestal, and having a connecting device on the top for firmly supporting the legs of an existing steel tower. an elevating pedestal of a predetermined height consisting of a shaped frame body, and a jack for raising and lowering the elevating pedestal on the outside or inside of the support of the elevating pedestal; (c) the lower ends of the legs of the steel tower are entirely removed from the ground to support the steel tower on the fixed pedestal and the elevating pedestal; (d) the jack is raised to the elevating pedestal; be raised by one stroke along with the steel tower, and temporarily fix the elevating pedestal to the fixed pedestal, or, after raising the elevating pedestal by one stroke and temporarily fixing the elevating pedestal, continue to lower the upper end of the jack to fix the elevating pedestal to the fixed pedestal. Reconnecting downward, lifting the elevating pedestal by one stroke and temporarily fixing the elevating pedestal at least one time while there is margin for the overlapping height of the elevating pedestal with respect to the fixed pedestal (hereinafter referred to as the wrap distance); e) Every time there is no margin in the wrap allowance due to one or more operations of raising and temporarily fixing the elevating pedestal in (a), a lower structure including the support of a predetermined height below the elevating pedestal (f) After the height above the ground of the steel tower reaches a predetermined height by the operations in (d) and (e), the legs of the tower are This is a steel tower raising method characterized by completely connecting the lower end of the steel tower with a newly constructed lower leg part assembled in advance, and a steel tower raising device used therein.

本発明において、鉄塔とは、送電線、放送アンテナ、貯
水槽、広告等用の鉄塔で、使用又は不使用状態を問わず
嵩上げするもの、又例えば鉄塔建設時予め鉄塔の上部の
み組立てられたものをせり上げて下部を継ぎ足すものも
含まれる。
In the present invention, a steel tower refers to a steel tower for power transmission lines, broadcasting antennas, water storage tanks, advertising, etc., which is raised regardless of whether it is in use or not, or a tower in which only the upper part of the tower is assembled in advance at the time of construction. This also includes raising the top and adding the bottom part.

以下、本発明を図面ケ用いて実施例により説明する。Hereinafter, the present invention will be explained by examples using the drawings.

ここでは主として送電線鉄塔に例をとって説明するが、
本発明はこれに限定されるものではなく、上述の他の鉄
塔にも広く適用しうろものである。
Here, we will mainly explain power transmission line towers as an example.
The present invention is not limited to this, but can be widely applied to other steel towers mentioned above.

第1図イ〜ホは、本発明の実施例により鉄塔を嵩上げす
る工法を説明するため、作業工程順に示した構成図であ
り、第2図はその工法に使用する嵩上げ装置の一例を示
す側面図である。
Figures 1A to 1E are block diagrams shown in the order of work steps to explain a construction method for raising a steel tower according to an embodiment of the present invention, and Figure 2 is a side view showing an example of a raising device used in the construction method. It is a diagram.

図において、1は既設鉄塔で、図は山形鋼四角鉄塔會示
す。
In the figure, 1 is the existing steel tower, and the figure shows the angle iron square steel tower.

2は鉄塔1の嵩上げ後、新しく脚部の下部となる新設の
下脚部で、鉄塔の外側の強固な新設基礎上に組立てられ
る。
2 is a newly installed lower leg section that will become the lower part of the new leg section after raising the height of the steel tower 1, and will be assembled on a strong new foundation outside the steel tower.

この新設の下脚部2の組立ては、イ図に示すように最初
の工程で行っても良く、又ニスに示す、c5な既設鉄塔
1の脚部の下端3とこの新設の下脚部2を接続するまで
の適当な段階で行っても良く、或いは既設鉄塔1のせり
上げ途中、鉄塔の下方に順次継ぎ足しても良い。
The assembly of the new lower leg 2 may be done in the first step as shown in Figure A, or the lower end 3 of the leg of the existing steel tower 1 of c5 is connected to the lower leg 2 of the new construction as shown in Figure A. It may be done at an appropriate stage until the existing steel tower 1 is raised, or it may be added to the lower part of the existing steel tower 1 one after another.

4は嵩上げ装置で、イ図に示すように鉄塔1の内側に設
けられる。
Reference numeral 4 denotes a raising device, which is installed inside the steel tower 1 as shown in Figure A.

嵩上げ装置4は第2図に詳細ゲ示す、C5に、固定架台
5、昇降架台6およびジヤツキ7、例えば電動式ジヤツ
キより成る。
The elevating device 4 is shown in detail in FIG. 2 and is comprised of a fixed pedestal 5, an elevating pedestal 6, and a jack 7, for example, an electric jack.

固定架台5は四角形平面の四隅に4本の支柱9を有する
箱状枠組体より成り、その内側に作業用の踊り場10,
10が設けられている。
The fixed frame 5 consists of a box-shaped frame body having four supports 9 at the four corners of a rectangular plane.
10 are provided.

固定架台5は、予め設けられた固定架台基礎8の上にボ
ルトにて強固に固定される。
The fixed pedestal 5 is firmly fixed with bolts onto a fixed pedestal foundation 8 provided in advance.

この基礎8は、例えば大型のH形鋼を交叉して鉄塔1の
脚部11を対角に結ぶ桁を鉄筋コンクリートのベース上
に設置し、その両端をボルトにて脚部11と結合したも
のであり、鉄塔1および嵩上げ装置4の重量は勿論、設
計上の風が吹いても装置が安全に耐えるものであり、上
昇作業中風が吹いても鉄塔の水平変位が所定値以内に押
えられるよう設計されたものである。
This foundation 8 is constructed by installing, for example, a girder made of large H-beams that diagonally connects the legs 11 of the steel tower 1 on a reinforced concrete base, and both ends of which are connected to the legs 11 with bolts. The equipment is designed to safely withstand not only the weight of the steel tower 1 and the raising device 4 but also the designed wind, and the horizontal displacement of the steel tower can be held within a predetermined value even if the wind blows during the lifting operation. It is what was done.

昇降架台6は四角形平面の四隅に4本の支柱12を有す
る箱状枠組体より成り、その4本の支柱12は固定架台
の4本の支柱9の外側に夫々上下方向に摺動可能に構成
されている。
The elevating pedestal 6 consists of a box-shaped frame body having four pillars 12 at the four corners of a rectangular plane, and the four pillars 12 are configured to be able to slide vertically on the outside of the four pillars 9 of the fixed pedestal. has been done.

第3図はこの支柱の摺動部の構成の一例を示す図で、イ
図は画架台の支柱が摺動する部分を示す側面図、0図は
イ図のA−A′ 断面を示す図で、ハ図はイ図の固定架
台の支柱に取付けたコロを示す正面図である。
Figure 3 is a diagram showing an example of the configuration of the sliding part of this support, where Figure A is a side view showing the part on which the support of the picture mount slides, and Figure 0 is a cross-sectional view taken along A-A' in Figure A. Figure C is a front view showing the roller attached to the support of the fixed frame in Figure A.

図において、第2図と同一の符号は同一の部分ケ示す。In the figure, the same reference numerals as in FIG. 2 indicate the same parts.

図に示すように、支柱9の外側と支柱12の内側は所定
の隙間、例えば30mmの隙間を空けて配置され、固定
架台の支柱9の上方の外側には、ハ図に示すような複数
個のコロ13が取付けられ、支柱9の外側と支柱12の
内側の摺動をスムーズにする役目をする。
As shown in the figure, the outside of the support 9 and the inside of the support 12 are arranged with a predetermined gap, for example, 30 mm, and on the outside above the support 9 of the fixed frame, there are a plurality of A roller 13 is attached to the pillar 9 and serves to smooth the sliding movement between the outside of the pillar 9 and the inside of the pillar 12.

この摺動をスムーズにする装置は、コロ以外のものであ
っても良く、他の形状のローラー等であっても良い。
The device for smoothing this sliding may be other than rollers, or may be rollers of other shapes.

なお、昇降架台6の支柱12が固定架台5の支柱9の内
側になり、摺動可能に構成されても良い。
Note that the pillars 12 of the elevating frame 6 may be arranged inside the pillars 9 of the fixed frame 5 so as to be slidable.

昇降架台6の上面には、第2図に示すよつに、つなぎ梁
14が設けられ、この両側に延長された端部が鉄塔1の
脚部の支柱15に強固に固着接続されることにより、画
架台5お工び6が鉄塔1を支持する。
As shown in FIG. 2, a connecting beam 14 is provided on the upper surface of the elevating frame 6, and the ends extending on both sides are firmly connected to the supports 15 of the legs of the steel tower 1. , a picture mount 5 and a frame 6 support the steel tower 1.

なお昇降架台6の上部と鉄塔1の支柱15の接続具は必
ずしも図のようなつなぎ梁でなくても良く、要は鉄塔1
を強固に支持するものであれば良い。
Note that the connection between the upper part of the elevating frame 6 and the support column 15 of the steel tower 1 does not necessarily have to be a connecting beam as shown in the figure;
It is fine as long as it strongly supports the

か、c5な昇降架台6を固定架台5の上方に設け、互い
に一部を重ねて固定架台5の支柱9に昇降架台6の支柱
12を摺動することにより、昇降架台6は固定架台5に
対して昇降自在となる。
Alternatively, by installing a c5 elevating frame 6 above the fixed frame 5 and sliding the support 12 of the elevating frame 6 onto the column 9 of the fixed frame 5 with their parts overlapping each other, the elevating frame 6 can be attached to the fixed frame 5. On the other hand, it can be raised and lowered freely.

この画架台の伸縮の高さを作業の段階に応じて変え、か
つ一時その所定位置で仮固定して鉄塔1を支持するため
、画架台の各支柱9お工び12には、上下方向の所定間
隔毎にボルト孔16(第3図、イ)が設けられている。
In order to change the height of expansion and contraction of this picture trestle depending on the stage of work and temporarily fix it in a predetermined position to support the steel tower 1, each support 9 and 12 of the picture trestle has a vertical direction. Bolt holes 16 (FIG. 3, A) are provided at predetermined intervals.

このボルト孔16は高さの微量調節のため、通常1個所
に適当な間隔で複数個設けられる。
A plurality of bolt holes 16 are usually provided at one location at appropriate intervals for minute adjustment of the height.

昇降架台6の上昇に伴ない、固定架台7との摺動長さが
短かくなり、不足してくるので、昇降架台6の下方は、
本体と同様な支柱を含む下方構成体17(第1図、ハ、
二)を継ぎ足して接続するように構成されており、例え
ば第2図ではフランジ18が設けられ、下方構成体17
とボルトに工り接続するようになっている。
As the elevating pedestal 6 rises, the sliding length with respect to the fixed pedestal 7 becomes shorter and becomes insufficient, so the lower part of the elevating pedestal 6 is
Lower structure 17 (FIG. 1, c,
2), for example, in FIG. 2, a flange 18 is provided, and the lower structure 17
It is designed to be connected to the bolt by machining.

又画架台5お工び6の四隅の支柱9お工び12の夫々外
側にはジヤツキ7が配置されており(第1図、第2図)
、その上端は、昇降架台6の支柱12の上下方向の所定
間隔毎に設けられた接続部19に接続され(第2図)、
下端は地上の固定架台基礎8に固着されて支持されてい
る。
In addition, jacks 7 are placed on the outside of each of the four corner supports 9 and 12 of the picture mount 5 and 6 (Figures 1 and 2).
, its upper end is connected to connection portions 19 provided at predetermined intervals in the vertical direction of the support 12 of the elevating frame 6 (FIG. 2),
The lower end is fixed and supported by a fixed frame foundation 8 on the ground.

力鬼うに構成されることにより、昇降架台6はジヤツキ
7にエリ上昇され、ジヤツキ7の上端を順次昇降架台6
の下方の接続部19に接続替することにより、順次昇降
架台6の高さが増加できる。
Due to the structure, the elevating frame 6 is lifted up by the jack 7, and the upper end of the jack 7 is sequentially moved to the elevating frame 6.
By changing the connection to the lower connecting part 19, the height of the elevating frame 6 can be increased sequentially.

ジヤツキ7は、4台同期させて上昇させる必要があるた
め、この調節が容易な電動式ジヤツキが適当であり、好
ましくはポールネジジヤツキを使用すれば、停止中の荷
重保持が確実で安全である。
Since the four jacks 7 need to be raised in synchronization, an easily adjustable electric jack is appropriate. Preferably, a pole screw jack is used to ensure that the load is held securely and safely while the machine is stopped. be.

なお、ジヤツキ7は図では画架台の支柱9,120外側
に配置されているが、又これらを支柱9,12の内側に
配置しても良い。
Note that although the jacks 7 are arranged outside the columns 9 and 120 of the picture mount in the figure, they may also be arranged inside the columns 9 and 12.

又、固定架台5お工び昇降架台6の形状は、図では平面
形状が四角形の場合を示したが、既設鉄塔の平面形状に
対応して決定されるものであり、例えば三角鉄塔に対し
ては3本支柱を有する3角形平面の、又他の多角形鉄塔
に対しては多本支柱を有する多角形平面のものが適当で
ある。
In addition, the shape of the fixed pedestal 5 and the elevating pedestal 6 is shown as having a rectangular planar shape in the figure, but it is determined in accordance with the planar shape of the existing steel tower, for example, for a triangular steel tower. For other polygonal steel towers, a polygonal planar structure with multiple supports is suitable.

要は鉄塔の内側で鉄塔を安定して支持しうる構造のもの
であれば如何なる形状のものでも差支えない。
In short, any shape can be used as long as it has a structure that can stably support the steel tower inside the steel tower.

次に、上述のヨウに構成された嵩上げ装置4により、既
設鉄塔1を嵩上げする工法について第1図を用いて説明
する。
Next, a construction method for raising the height of the existing steel tower 1 using the height-raising device 4 configured as described above will be explained using FIG. 1.

先ずイ図に示すヨウに、鉄塔1の内側に嵩上げ装置4を
固定架台5、昇降架台6又はジヤツキ7の順序で設置す
る。
First, as shown in Figure A, the raising device 4 is installed inside the steel tower 1 in the order of the fixed pedestal 5, the elevating pedestal 6, or the jack 7.

又昇降架台6の上面のつなぎ梁lCa−鉄塔1の脚部の
支柱15に接続固着する。
Also, the connecting beam lCa on the upper surface of the elevating frame 6 is connected and fixed to the support column 15 of the leg of the steel tower 1.

次にロスに示す工うに、鉄塔1の脚部の下端3全地上よ
り取りはずして鉄塔1全体を固定架台5と昇降架台6で
支持させるようにする。
Next, as shown in Ross, the entire lower end 3 of the leg of the steel tower 1 is removed from the ground, and the entire steel tower 1 is supported by a fixed frame 5 and an elevating frame 6.

次いで4台のジヤツキ7を同期させ、上昇させると、昇
降架台6は鉄塔1と共に上昇する。
Next, when the four jacks 7 are synchronized and raised, the elevating frame 6 rises together with the steel tower 1.

上昇高さがジヤツキ701ストローク、例えば1.5
mに達すると、上昇?止め、昇降架台6を固定架台5に
仮固定するため、固定装置、例えばボルト孔16(第3
図イ)を用いてボルト締めする。
The rising height is 701 strokes, for example 1.5
Does it rise when it reaches m? In order to temporarily fix the elevating pedestal 6 to the fixed pedestal 5, a fixing device, for example, a bolt hole 16 (the third
Tighten the bolts using Figure A).

ここで、固定架台5に対する昇降架台6の必要な重なり
高さくラップ代)、例えば1.5m以上が次のジヤツキ
701ストローク上昇により無くなる見込みであれば、
ハスに示すと同様に、昇降架台6の下方に所定高さの下
方構成体17を継ぎ足す。
Here, if the necessary overlap height (lap height) of the elevating pedestal 6 with respect to the fixed pedestal 5, for example 1.5 m or more, is expected to disappear due to the next stroke rise of the jack 701,
As shown in the figure, a lower structure 17 of a predetermined height is added below the elevating frame 6.

上述のラップ代が充分な場合又は下方構成体17を継ぎ
足した場合は、ジヤツキ7の上端を昇降架台6の接続部
19(八図)J、り取りはずし、ジヤツキ7を下降させ
て元に戻し、その上端を下方の接続部19に接続替した
後、画架台の前記仮固定ボルトヲ取外し、八図に示すよ
うに再びジヤツキ7により昇降架台6を1ストローク上
昇させた後、前述と同様にして画架台を仮固定する。
If the above-mentioned wrap allowance is sufficient or if the lower structure 17 is added, remove the upper end of the jack 7 from the connection part 19 (Fig. 8) J of the lifting frame 6, lower the jack 7, and return it to its original position. After reconnecting the upper end to the lower connection part 19, remove the temporary fixing bolt of the picture mount, raise the elevating pedestal 6 by one stroke again with the jack 7 as shown in Figure 8, and then remove the picture in the same manner as described above. Temporarily fix the stand.

ここでラップ代が次の上昇で無くなる見込みであれば、
前述と同様にして昇降架台6の下方に下方構成体17の
継ぎ足しを行なう。
If the wrap fee is expected to disappear with the next increase,
The lower structure 17 is added below the elevating frame 6 in the same manner as described above.

即ち、昇降架台6のラップ代に余裕がある間はジヤツキ
7による昇降架台601ストローク上昇および前記仮固
定を1回以上(1回又は2回以上繰返し)行ない、昇降
架台6のラップ代に余裕が無くなる毎に、昇降架台6の
下方に所定の高さの下方構成体17を順次継ぎ足す。
That is, while there is margin for the lap of the lifting pedestal 6, the lifting pedestal 601 stroke by the jack 7 and the above-mentioned temporary fixing are performed at least once (repeated once or twice or more), and the lifting pedestal 601 is stroked upward by the jack 7 (repeated once or twice or more). Each time it runs out, a lower structure 17 of a predetermined height is sequentially added below the elevating frame 6.

なお、昇降架台6の本体の上昇のみで嵩上げ高さを満足
する場合は、下方構成体17は必ずしも必要ではない。
Note that if the raised height is satisfied only by raising the main body of the elevating frame 6, the lower structure 17 is not necessarily required.

上述の、J、プなジヤツキ7による上昇、仮固定および
昇降架台6の継ぎ足し會夫々必要頻度繰返すことにより
、鉄塔1の高さが高くなる(ニス)。
The height of the steel tower 1 is increased by repeating the above-mentioned lifting, temporary fixing, and addition of the elevating frame 6 by the jacks 7 as often as necessary (varnish).

例えばジヤツキ7の1ストロークが1.5 mで、昇降
架台の1回の継ぎ足し高さが3mであれば、ジヤツキに
よる上昇全2回する毎に5.1回昇降架台の継ぎ足しを
すれば良い。
For example, if one stroke of the jack 7 is 1.5 m and the height of the elevating pedestal is 3 m each time, the height of the elevating pedestal may be added 5.1 times for every two lifts by the jack.

なお以上のような操作は、すべて固定架台5に設けられ
た踊り場10(第2図)および地上で行われ、高さはせ
いぜい6m以内の比較的低い場所で行われるので、作業
上安全である。
All of the above-mentioned operations are performed on the landing 10 (Fig. 2) provided on the fixed frame 5 and on the ground, and are performed in relatively low places with a height of no more than 6 m, so that the work is safe. .

上述の操作により鉄塔1の地上高さが所定の高さに達し
た後、鉄塔の脚部の下端3(ニス)と予め組立てられた
新設の下脚部2が接続固着される。
After the height of the steel tower 1 above ground reaches a predetermined height by the above-described operation, the lower end 3 (varnish) of the leg of the steel tower and the newly installed lower leg 2 assembled in advance are connected and fixed.

しかる後、既設鉄塔1の脚部の支柱15と昇降架台6の
つなぎ梁14の固着(第2図)を取りはずした後、嵩上
げ装置4を、主として組立と反対の順序で撤去し、鉄塔
の嵩上げ工事が完了する(ホ図)。
Thereafter, after removing the fixings (Fig. 2) between the support columns 15 of the legs of the existing steel tower 1 and the connecting beams 14 of the lifting frame 6, the raising device 4 is removed mainly in the reverse order of assembly, and the height of the steel tower is raised. Construction is completed (Figure E).

以上述べたように、本発明は、鉄塔の下端脚部を継ぎ足
して鉄塔を嵩上げする場合、次のような効果を有する。
As described above, the present invention has the following effects when the steel tower is raised by adding the lower end legs of the steel tower.

■ 鉄塔の内側に嵩上げ装置上設けるため、塔体内で作
業が可能であり、作業用敷地が小さくてすみ、特に送電
線鉄塔のように用地確保がむつかしい場合、工事を可能
にすると共に、経済的である。
■ Since it is installed on the raising device inside the tower, work can be done inside the tower body, and the work site is small, making it possible to perform construction work and economically It is.

■ 鉄塔全体が、隅に夫々強固な支柱を有する箱状枠組
体よりなる固定架合お工び昇降架台によって支持され、
固定架台の支柱に昇降架台の支柱が摺動可能に形成され
、昇降架台の支柱毎に昇降架台を上下するジヤツキが設
けられているため、昇降架台の四方の上昇の同期が容易
であり、鉄塔上昇時鉄塔上部の横振れ、鉄塔の振動が防
止されろ。
■ The entire steel tower is supported by a fixed frame elevating frame consisting of a box-shaped frame with strong supports at each corner.
The columns of the elevating pedestal are slidably formed on the columns of the fixed pedestal, and a jack for raising and lowering the elevating pedestal is provided for each column of the elevating pedestal, making it easy to synchronize the rise of the elevating pedestal on all four sides. Prevent sideways shaking of the top of the tower and vibration of the tower when ascending.

特に例えばボールネジジヤツキの工5な電動式ジャッキ
ケ採用することに、l:す、上昇の同期が確実に行われ
、微調整も可能であると共に、荷重保持が確実で安全に
行われるので、作業上極めて安定であり、安全性が高い
In particular, for example, when using an electric jack for ball screw jacking, the synchronization of the rise is ensured, fine adjustments are possible, and the load is held securely and safely, making the work easier. Moreover, it is extremely stable and highly safe.

又、昇降架台の停止時にはそれを固定架台に仮固定する
ので、安全である。
Furthermore, when the elevating frame is stopped, it is temporarily fixed to the fixed frame, so it is safe.

■ 嵩上げ作業が嵩上げ装置の高さの範囲内の比較的低
い場所で行ない得るため、高所作業がなく、又活線など
との接近がないので、作業員の安全上極めて好ましい。
(2) Since the raising work can be carried out at a relatively low place within the height range of the raising device, there is no need to work at heights, and there is no need to come close to live wires, which is extremely favorable in terms of worker safety.

■ ■および■の効果より、例えば活線架線のままのヨ
ウな鉄塔の使用状態での嵩上げ工事が可能であり、又他
の仮工事が不要であるから、例えば無停電で、かつ工期
短縮が可能であるので、工事費を大巾に低減しうる利点
がある。
■ Due to the effects of ■ and ■, it is possible, for example, to carry out work to raise the height of a steel tower with live overhead lines still in use, and other temporary work is not required, so for example, there is no power outage and the construction period can be shortened. This has the advantage of significantly reducing construction costs.

なお、無停電で鉄塔の嵩上げができることは、従来、常
時系統として不可欠な系統や、事故時、作業時或いは系
統バランスのため使用頻度の多い系統においては、仮工
事なしで嵩上げ不可能であったが、この仮工事を不要と
し左利点は太きい。
It should be noted that the ability to raise the height of a steel tower without power outage has previously been impossible without temporary construction in systems that are essential as a constant system, or systems that are frequently used during accidents, work, or for system balance. However, the advantage of eliminating the need for this temporary construction is significant.

■ 固定架台、昇降架台およびジヤツキは、構造又は容
量を任意に選択しうるため、負荷荷重の増大が可能であ
るので、大型鉄塔への適用が可能である。
(2) The structure or capacity of the fixed frame, elevating frame, and jack can be selected arbitrarily, so it is possible to increase the load, so it can be applied to large steel towers.

■ 昇降架台の下方に下方構成体を継ぎ足すことと、ジ
ヤツキによる上昇および固定架台と昇降架台の仮固定を
適宜繰返すことにより、任意の高さの嵩上げが可能であ
る。
(2) It is possible to raise the height to any desired height by adding a lower structure below the elevating pedestal, and by appropriately repeating raising by jacking and temporarily fixing the fixed pedestal and the elevating pedestal.

なお上述の実施例では主として山形鋼四角鉄塔の場合に
ついて説明したが、本発明はパイプ鉄塔にも同様に適用
できろものであり、又送電線鉄塔以外の他の用途の鉄塔
、或いは鉄塔建設時予め組立てられた鉄塔上部に対して
も適用できることは明らかである。
Although the above-mentioned embodiments mainly describe the case of angle iron square steel towers, the present invention can be applied to pipe towers as well, and can also be applied to towers for other purposes other than power transmission towers, or when constructing towers. It is clear that the present invention can also be applied to the upper part of a steel tower that has been assembled in advance.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図イ〜ホは本発明の実施例により鉄塔を嵩上げする
工法を説明するため、作業工程順に示した構成図である
。 第2図は本発明高上げ装置の実施例を示す側面図である
。 第3図は本発明装置の実施例における支柱の摺動部の構
成の一例を示す図で、イ図は側面図、ロスはイ図のA−
A’ 断面を示す図、へ図はイ図の固定架台の支柱に取
付けたコロを示す正面図である。 1・・・・・・既設鉄塔、2・・・・・・新設の下脚部
、3・・・・・・脚部の下端、4・・・・・・嵩上げ装
置、5・・・・・・固定架台、6・・・・・・昇降架台
、7・・・・・・ジヤツキ、8・・・・・・固定架台基
礎、9,12・・・・・・支柱、10・・・・・・踊り
場、11・・・・・・脚部、13・・・・・・コロ、1
4・・・・・・つなぎ梁、15・・・・・・鉄塔1の脚
部の支柱、16・・・・・・ボルト孔、17・・・・・
・下方構成体、18・・・・・・フランジ、19・・・
・・接続点。
FIGS. 1A to 1E are configuration diagrams shown in the order of work steps to explain a construction method for raising a steel tower according to an embodiment of the present invention. FIG. 2 is a side view showing an embodiment of the height raising device of the present invention. Fig. 3 is a diagram showing an example of the structure of the sliding part of the column in the embodiment of the device of the present invention, in which Fig. A is a side view and loss is shown at A-A in Fig. A.
Figure A' is a cross-sectional view, and Figure A is a front view showing a roller attached to the support of the fixed frame in Figure A. 1...Existing steel tower, 2...Lower leg of new construction, 3...Lower end of leg, 4...Elevating device, 5...・Fixed frame, 6... Lifting frame, 7... Jacket, 8... Fixed frame foundation, 9, 12... Pillar, 10... ...Landing, 11...Leg, 13...Colo, 1
4... Connecting beam, 15... Leg support of steel tower 1, 16... Bolt hole, 17...
・Lower structure, 18...flange, 19...
...Connection point.

Claims (1)

【特許請求の範囲】 1 鉄塔の下端脚部を継ぎ足して鉄塔を嵩上げする方法
において、 (a) 前記鉄塔の内側に、隅に少くとも3本の支柱
を有し、箱状枠組体より成る地上に固定された固定架台
と、その上方に、前記固定架台の支柱に夫々摺動可能に
形成された少くとも3本の支柱を有し、かつ上部に鉄塔
の脚部ケ固着支持する接続具を有する箱状枠組体より成
る所定高さの昇降架台と、前記昇降架台の前記支柱の外
側又は内側に該昇降架台を上下させるためのジヤツキと
?設け、 (b) 前記昇降架台上部の前記接続具を前記鉄塔の
脚部に接続固着し、 (c) 前記鉄塔の脚部の下端を地上より取りはずし
て前記鉄塔を前記固定架台と前記昇降架台に支持させ、 (d)前記ジヤツキを上昇させて前記昇降架台全前記鉄
塔とともに1ストローク上昇させ、前記昇降架台全前記
固定架台に仮固定するか、又は前記昇降架台の1ストロ
ーク上昇および前記仮固定の操作後引続き前記ジヤツキ
の上端を下降させて前記昇降架台の下方に接続替して前
記昇降架台の1スI・ローフ上昇および前記仮固定の操
作を、前記固定架台に対する前記昇降架台の重なり高さ
く以下、ラップ代と称す)に余裕がある間−回以上行な
い、 (e) 前記(d)の前記昇降架台の上昇および前記
仮固定の1回以上の操作により前記ラップ代に余裕が無
くなる毎に、前記昇降架台の下方に所定高さの前記支柱
を含む下方構成体を順次継ぎ足して前記昇降架台の高さ
を順次大きくし、 (f) 前記(d)および(e)の操作により前記鉄
塔の地上高さが所定の高さに達した後、該鉄塔の脚部の
下端と予め組立てられた新設の下脚部とを接続すること
、全特徴とする鉄塔の嵩上げ工法。 2 隅に支柱を有する箱状枠組体より成る地」二に固定
された固定架台と、その上方に配置され、前記固定架台
の支柱の外側に夫々上下方向に摺動可能に構成された支
柱を有する箱状枠組体より成り、かつ上面に鉄塔の脚部
を固着支持するためのつなぎ梁を設けた昇降架台と、上
記画架台の隅の前記支柱の夫々外側に垂直に配置され、
上端が前記昇降架台の支柱の上下方向の所定間隔毎に設
けられた接続部に接続され、下端が地上に固着支持され
た、前記昇降架台を上下させるためのジヤツキとより成
り、前記昇降架台の下方は所定高さの前記支柱を含む下
方構成体を継ぎ足しするよう構成され、前記固定架台お
よび前記昇降架台の前記支柱には、夫々画架台間全所定
の間隔位置毎に固定するための固定装置を有すると共に
、前記装置全体が鉄塔の内側に設置されることを特徴と
する鉄塔の嵩上げ装置。 3 固定架台の隅の支柱が、該支柱の上方の外側に、昇
降架台の隅の支柱の内側との夫々の摺動全スムーズにす
るためのコロを有する特許請求の範囲第2項記載の鉄塔
の嵩上げ装置。 4 ジヤツキが電動式ジヤツキより成る特許請求の範囲
第2項又は第3項記載の鉄塔の嵩上げ装置。
[Scope of Claims] 1. A method for raising the height of a steel tower by adding the lower end legs of the steel tower, comprising: (a) an above-ground structure comprising a box-shaped frame body having at least three pillars at the corners on the inside of the steel tower; A fixed pedestal fixed to the pedestal, and above the fixed pedestal, at least three pillars are formed so as to be able to slide on the pillars of the fixed pedestal, respectively, and a connecting device for fixing and supporting the legs of the steel tower is provided on the upper part. an elevating pedestal of a predetermined height consisting of a box-like frame body, and a jack for raising and lowering the elevating pedestal on the outside or inside of the support of the elevating pedestal; (b) connecting and fixing the connector on the upper part of the elevating frame to the leg of the steel tower; (c) removing the lower end of the leg of the steel tower from the ground to connect the steel tower to the fixed frame and the elevating frame; (d) Raise the jack to raise all of the elevating gantry together with the steel tower by one stroke, and temporarily fix all of the elevating gantry to the fixed pedestal, or raise the elevating gantry by one stroke and temporarily fix it. After the operation, the upper end of the jack is lowered and reconnected to the lower part of the elevating pedestal, and the elevating trestle is raised by 1 loaf and the temporary fixing operation is performed by increasing the overlapping height of the elevating pedestal with respect to the fixed pedestal. (e) Each time there is no margin in the wrap allowance due to one or more operations of raising and temporarily fixing the elevating platform in (d) above, , the height of the elevating pedestal is increased one after another by sequentially adding lower structures including the pillars of a predetermined height below the elevating pedestal; (f) by the operations (d) and (e) above, A method for raising the height of a steel tower, which is characterized in that the lower end of the leg of the steel tower is connected to a pre-assembled new lower leg after the ground height reaches a predetermined height. 2. A fixed pedestal fixed to a base consisting of a box-shaped frame body with pillars at the corners, and pillars arranged above the fixed pedestal and configured to be slidable in the vertical direction on the outside of the pillars of the fixed pedestal, respectively. an elevating pedestal consisting of a box-shaped frame body having a box-like frame body and having a connecting beam on the upper surface for firmly supporting the legs of the steel tower; and an elevating pedestal arranged perpendicularly to the outside of each of the pillars at the corner of the picture pedestal;
a jack for raising and lowering the elevating frame, the upper end of which is connected to a connection part provided at a predetermined interval in the vertical direction of the support of the elevating frame, and the lower end of which is fixedly supported on the ground; The lower part is configured to add a lower structure including the pillars of a predetermined height, and the pillars of the fixed pedestal and the elevating pedestal are each provided with fixing devices for fixing them at every predetermined interval position between the picture pedestals. A steel tower raising device characterized in that the entire device is installed inside the steel tower. 3. The steel tower according to claim 2, wherein the corner posts of the fixed pedestal have rollers on the outside above the top thereof to ensure smooth sliding with the inside of the corner posts of the elevating pedestal. Raising device. 4. The steel tower raising device according to claim 2 or 3, wherein the jack is an electric jack.
JP4389079A 1979-04-10 1979-04-10 Steel tower raising method and equipment Expired JPS5926746B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4389079A JPS5926746B2 (en) 1979-04-10 1979-04-10 Steel tower raising method and equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4389079A JPS5926746B2 (en) 1979-04-10 1979-04-10 Steel tower raising method and equipment

Publications (2)

Publication Number Publication Date
JPS55136374A JPS55136374A (en) 1980-10-24
JPS5926746B2 true JPS5926746B2 (en) 1984-06-30

Family

ID=12676290

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4389079A Expired JPS5926746B2 (en) 1979-04-10 1979-04-10 Steel tower raising method and equipment

Country Status (1)

Country Link
JP (1) JPS5926746B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6467202B2 (en) * 2014-11-21 2019-02-06 株式会社九建 Steel tower main column replacement method

Also Published As

Publication number Publication date
JPS55136374A (en) 1980-10-24

Similar Documents

Publication Publication Date Title
CN106760529A (en) Roof system steel truss slipping and assembling operation platform and installation method
CN206736864U (en) Hydraulic self-lifting cantilever heavy type arch dam shuttering work platform
CA2998120A1 (en) Ladder installation for equipment tower
CN206319610U (en) Roof system steel truss slipping and assembling construction platform structure
US6430892B1 (en) Apparatus and method for building a domed structure
CN210459267U (en) Steel construction column foot with adjustable elevation
CN210597630U (en) Net rack integral lifting structure
JP2018044318A (en) Construction method of silo roof section, and silo roof structure
CN217439544U (en) Building top outer vertical surface overhanging structure template supporting system
JPS5926746B2 (en) Steel tower raising method and equipment
CN216787874U (en) Large-scale ring type truss hoisting structure in large-span high altitude
CN212562551U (en) Pull rod type rear support section steel overhanging discharging platform
CN109440942A (en) A kind of factory building roof rack mounting structure and construction technology
JP3453181B2 (en) Working steel stand and method of assembling tower-like structure using the working steel stand
JP2780571B2 (en) Reinforcing cage construction equipment
JP3066460B2 (en) How to build a tower
CN219990997U (en) Tower crane adheres to fixed connection base
CN217128516U (en) Temporary mounting structure for roof layer large-span steel beam
CN210947711U (en) Warehouse top steel beam supporting belt support device of silo sliding formwork
CN219587206U (en) Assembly structure supporting system
CN216429078U (en) Jacking and discharging device for temporary steel support supporting system
CN216074809U (en) Bridge rail guard template installation platform truck
CN210368652U (en) Bracket structure capable of adjusting transverse displacement
JPS597974Y2 (en) Raising equipment for steel pipe towers
JP7436341B2 (en) Structure lift-up method and its equipment configuration