JPS5924029A - Removal of earth anchor - Google Patents

Removal of earth anchor

Info

Publication number
JPS5924029A
JPS5924029A JP13375782A JP13375782A JPS5924029A JP S5924029 A JPS5924029 A JP S5924029A JP 13375782 A JP13375782 A JP 13375782A JP 13375782 A JP13375782 A JP 13375782A JP S5924029 A JPS5924029 A JP S5924029A
Authority
JP
Japan
Prior art keywords
earth anchor
flat tube
mortar
concrete
core
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP13375782A
Other languages
Japanese (ja)
Inventor
Kensuke Asakura
健介 朝倉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP13375782A priority Critical patent/JPS5924029A/en
Publication of JPS5924029A publication Critical patent/JPS5924029A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
    • E02D5/765Anchorings for bulkheads or sections thereof in as much as specially adapted therefor removable

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

PURPOSE:To remove an earth anchor from cement mortar by a method in which an inner space surrounded by steel wires is provided at the tip of an earth anchor, an expandible flat tube surroudning the steel wires is set, and the flat tube is expanded when removing the earth anchor. CONSTITUTION:A hole 15 is provided at the center of the center part 13 of the core 12 of an earth anchor and plural piano wires 16 and porous rubber 24 are provided around the center part 13. They are then covered witn a flat tube 21 to make up the tip portion of the core 12 of the earth anchor. The earth anchor is penetrated into a hole 11 drilled in the ground and fixed with cement mortar. When removing the earth anchor, pressure water is supplied through a pipe 22 leading to the flat tube 21, whereupon the flat tube is expanded, the center part 13 of the core 12 is crushed, and the core 12 is separated from cement mortar 18.

Description

【発明の詳細な説明】 この発明はアースアンカーの除去方法に関するものであ
る。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for removing an earth anchor.

従来アースアンカーを除去する場合ピアノ線等により構
成しだしん部材が地下の深い位置でモルタル等に強固に
結合しているため実質的な除去が困難であった。したが
って、しん部材を完全に除去することなく除去可能な部
分で切断してそれより深い部分を放置することが行われ
そおり、通常アースアンカーを設置するのに隣接した他
人の土地に延びるようにする場合が多くあって種々の問
題が発生する可能性がある。
Conventionally, when removing an earth anchor, it has been difficult to remove it because the ground anchor is made of piano wire or the like and is firmly connected to mortar or the like at a deep underground location. Therefore, it is common practice to cut off the removable part and leave the deeper part without completely removing the shingle member, and it is common practice to install the earth anchor by cutting it at the removable part and leaving it alone. In many cases, various problems may occur.

この発明はこのような点を解消してしん部材が完全に除
去されるようにしたアースアンカーの除去方法を提供す
るものである。
The present invention solves the above-mentioned problems and provides a method for removing an earth anchor in which the shin member is completely removed.

以下図面を参照しながらこの発明の実施例について説明
する。
Embodiments of the present invention will be described below with reference to the drawings.

第1〜5図に示すこの発明の一実施例において、10は
矢板、1jはアースアンカーを構成するため地中に掘っ
た穴である。12はこの穴の中央に延びたアースアンカ
ーのしん部材で、中央に大きい孔15を有する合成樹脂
製の中心部材13を有している。この中心部材13は従
来のものより十分大きい直径に形成しである。24は中
心部材13に沿って延びるように適当個数必要に応じて
設け/こ合成樹脂又はゴム等よりなる多孔質材である。
In one embodiment of the present invention shown in FIGS. 1 to 5, 10 is a sheet pile, and 1j is a hole dug in the ground to constitute an earth anchor. Reference numeral 12 denotes a base member of the earth anchor extending in the center of this hole, and has a central member 13 made of synthetic resin and having a large hole 15 in the center. This central member 13 is formed to have a sufficiently larger diameter than the conventional one. Reference numeral 24 is a porous material made of synthetic resin, rubber, etc., which is provided in an appropriate number as required so as to extend along the central member 13.

16は中心部拐13を囲んで配置したそれぞれピアノ線
等の鋼線をより合わした複数個の鋼線部材である。中心
部材13及び鋼線部材16等は図示してない適当間隔の
ライナーにより所定の配置形状を保持するようになって
いる。17は穴1.1内において所定長さ壕で延びる合
成樹脂製パイプで、シ、ん部材12が貫通している。1
8は穴11内でパイプ17の外側から供給して硬化させ
たモルタル又はコンクリート(以下モルタル等と記載す
る)で、パイプ17の先端部より先ではしん部材12と
強固に結合するようになっている。
Reference numeral 16 denotes a plurality of steel wire members arranged around the central section 13, each made of twisted steel wires such as piano wire. The central member 13, steel wire member 16, etc. are maintained in a predetermined arrangement shape by liners (not shown) at appropriate intervals. Reference numeral 17 denotes a synthetic resin pipe extending a predetermined length in the hole 1.1, through which the sealing member 12 passes. 1
Reference numeral 8 denotes mortar or concrete (hereinafter referred to as mortar, etc.) supplied from the outside of the pipe 17 in the hole 11 and hardened, so that it is firmly connected to the insulation member 12 beyond the tip of the pipe 17. There is.

20はパイプ17の先端を覆う仕切板である。20 is a partition plate that covers the tip of the pipe 17.

21は例えば銅、銅合金、鉄等の金属により構成した金
属製偏平管で、螺旋状になっていてしん部材12と直交
する方向に薄くなった断面形状を有し、しん部材12が
モルタル等18に埋設されることになる部分の外側をほ
ぼ囲むように配置しておきしん部材12とともにモルタ
ル等18に埋設されるようになっており、両端は円形断
面の金属製パイプ22がそれぞれ一体として連通して外
部へ導出され仕り板20を貫通した後パイプ17内を通
って穴11の入日付近に達している。通常偏平管21は
パイプ22と一体となったパイプから加工して偏平に形
成できるものである。
Reference numeral 21 denotes a metal flat tube made of metal such as copper, copper alloy, iron, etc., and has a spiral cross-sectional shape that becomes thinner in a direction perpendicular to the shin member 12, and the shin member 12 is made of mortar or the like. It is arranged so as to almost surround the outside of the part to be buried in 18, and is buried in mortar etc. 18 together with insulation member 12, and metal pipes 22 with a circular cross section are integrally attached to both ends. It communicates and is led out to the outside, passes through the partition plate 20, and then passes through the inside of the pipe 17 to reach the vicinity of the sunrise of the hole 11. Normally, the flat tube 21 can be formed into a flat shape by processing a pipe integrated with the pipe 22.

以上のように構成したアースアンカーを使用した後除去
する場合には矢板10を除去する。次に一方のパイプ2
2から加圧した水等の液体を供給して他方のパイプ22
の端部に達した場合この端部を閉塞する。引続き加圧液
体を供給すると第4図と第5図に示すように偏平管21
が膨出してしん部材12の中心部材13を押しつぶして
しん部材12をモルタル等18から分離するようになる
When the earth anchor configured as described above is to be removed after use, the sheet pile 10 is removed. Next, one pipe 2
2 to the other pipe 22 by supplying pressurized liquid such as water.
When the end of is reached, this end is closed. When pressurized liquid is continuously supplied, the flat tube 21 as shown in FIGS. 4 and 5
bulges out and crushes the center member 13 of the shin member 12, separating the shin member 12 from the mortar or the like 18.

この押しつぶし作用は多孔質材24が用いであるとこの
部分から始するのが普通である。この状態でしん部イA
12を引張れば容易に除去できるものである。
This squeezing action usually starts from this part when a porous material 24 is used. In this state, the shin part A
It can be easily removed by pulling 12.

この発明は前述したようKしてしん部材12を引抜くよ
うになっているから、モルタル等18からしん部材12
が容易に分離されて完全に除去できるという効果を有し
ている。
In this invention, as described above, the sill member 12 is pulled out from the mortar 18.
This has the effect that it can be easily separated and completely removed.

なお、この発明においては第6図に示すようにしん部材
12を囲んでとのしん部材の方向に延びる複数個の偏平
管21を円形断面の部分25で連結したものを用いても
よい。又、第7図に示すようにしん部材12として中心
部材13が中空ではないが全体として合成樹脂又はゴム
の多孔質のものよりなり大きい外圧を受けると収縮可能
なものを用いてもよいことはもちろんである。
In addition, in this invention, as shown in FIG. 6, a plurality of flat tubes 21 surrounding the herring member 12 and extending in the direction of the herring member 12 may be connected by a portion 25 having a circular cross section. Furthermore, as shown in FIG. 7, a material may be used as the herring member 12 in which the center member 13 is not hollow, but is made of synthetic resin or rubber and is porous, and is capable of contracting when subjected to a large external pressure. Of course.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はこの発明の一実施例によるアースアンカーを示
す縦断面図、第2図は第1図におけるA−A断面拡大図
、第3図は偏平管を示す斜視図、第4図は動作状態を示
す横断面図、第5図はその縦断面図、第6図はこの発明
の他の実施例において用いる偏平管を示す斜視図、第7
図はこの発明の他の実施例において用いるしん部材を設
置した状態を示す横断面図である。 11は穴、12はしん部材、13は中心部材、16は鋼
線部材、18はモルタル等、21は偏平管、22はパイ
プ。 代理人 弁理士 勝 部 明 長 事ぢρ 〉t 7
Fig. 1 is a longitudinal sectional view showing an earth anchor according to an embodiment of the present invention, Fig. 2 is an enlarged cross-sectional view taken along line A-A in Fig. 1, Fig. 3 is a perspective view showing a flat tube, and Fig. 4 is an operation. FIG. 5 is a longitudinal sectional view of the state, FIG. 6 is a perspective view of a flat tube used in another embodiment of the present invention, and FIG.
The figure is a cross-sectional view showing a state in which a shin member used in another embodiment of the present invention is installed. 11 is a hole, 12 is a shin member, 13 is a center member, 16 is a steel wire member, 18 is mortar, etc., 21 is a flat tube, and 22 is a pipe. Agent Patent Attorney Akira Katsube Chojiぢρ〉t7

Claims (1)

【特許請求の範囲】[Claims] 中央に延びる中心部材及びこの中心部材を囲んで延びる
それぞれ鋼線をより合わした複数個の鋼線部材を有する
しん部材の一端をモルタル又はコンクリートに埋設した
アースアンカーの除去方法であって、前記しん部材のモ
ルタル又はコンクリートに埋設される部分は少くとも前
記中心部材は所定以上の大きい外圧を受けると内方へつ
ぶされるように構成しておく段階と、前記しん部材のモ
ルタル又はコンクリートに埋設される部分の周囲をほぼ
囲んでしん部材の延びる方向とほぼ直交する方向を薄く
した金属製偏平管を配置してしん部材とともにモルタル
又はコンクリートに埋設する段階と、アースアンカーを
除去する場合前記偏平管内へ加圧液体を供給してしん部
材を内方へ圧縮して中心部材をつぶすことによりモルタ
ル又はコンクリートからしん部材を分離させる段階と、
しん部材を引抜く段階とを包含することを特徴とするア
ースアンカーの除去方法。
A method for removing an earth anchor in which one end of a shingle member is embedded in mortar or concrete and has a central member extending in the center and a plurality of steel wire members each having twisted steel wires extending around the central member, the method comprising: The part of the member to be buried in the mortar or concrete is configured such that at least the central member is crushed inward when subjected to external pressure greater than a predetermined value, and the part of the core member to be buried in the mortar or concrete is configured. A step of arranging a metal flat tube that is thinned in a direction substantially perpendicular to the extending direction of the shin member so as to almost surround the periphery of the part and embedding it in mortar or concrete together with the shin member, and when removing the earth anchor, inserting it into the flat tube. separating the shingle member from the mortar or concrete by supplying a pressurized liquid to compress the shingle member inwardly and crushing the center member;
A method for removing an earth anchor, comprising the step of pulling out a support member.
JP13375782A 1982-08-02 1982-08-02 Removal of earth anchor Pending JPS5924029A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13375782A JPS5924029A (en) 1982-08-02 1982-08-02 Removal of earth anchor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13375782A JPS5924029A (en) 1982-08-02 1982-08-02 Removal of earth anchor

Publications (1)

Publication Number Publication Date
JPS5924029A true JPS5924029A (en) 1984-02-07

Family

ID=15112230

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13375782A Pending JPS5924029A (en) 1982-08-02 1982-08-02 Removal of earth anchor

Country Status (1)

Country Link
JP (1) JPS5924029A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63103123A (en) * 1986-10-20 1988-05-07 Taisei Corp Removing type anchoring work
FR2704574A1 (en) * 1993-04-28 1994-11-04 Sol Cie Method for extracting a ground anchor and devices which can be used to implement this method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63103123A (en) * 1986-10-20 1988-05-07 Taisei Corp Removing type anchoring work
FR2704574A1 (en) * 1993-04-28 1994-11-04 Sol Cie Method for extracting a ground anchor and devices which can be used to implement this method

Similar Documents

Publication Publication Date Title
US6216403B1 (en) Method, member, and tendon for constructing an anchoring device
CA1050233A (en) Removable press anchor with destructible anchor body
US4132498A (en) Earth anchor and method of setting and removing same
JP4901593B2 (en) Underground bite type anchor and its anchor method
EP0750710A1 (en) A foundation tube for use as a foundation for masts, posts, pillars, etc., together with a method for formation of the foundation
JPS5924029A (en) Removal of earth anchor
JPS60244315A (en) Cylindrical screen and preparation thereof
WO2004070121A1 (en) Techniques for pile breaking
AU639355B2 (en) A method of producing a tension part anchorable in the earth
JPH10183638A (en) Drainage structure of slope
KR100930541B1 (en) Slope reinforcement device and method
KR100729661B1 (en) Construction method for soil improvement anchor system
JPH0730562B2 (en) Reinforced earth method with tubular reinforcement
KR100717252B1 (en) Grouting apparatus and Method of construction work using Earth anchor
JP6179020B2 (en) Housing separation method
JP2562041B2 (en) End fixing method for PC steel wire in anchor and fixing tool
KR101988301B1 (en) Anchor construction method
JPH0412768B2 (en)
JP2009121218A (en) Pile head separating method
JP2775609B2 (en) Water collection method and water collection structure
JPH0340913Y2 (en)
JPS59170323A (en) Head cutting of concrete pile
KR100597117B1 (en) Nail device for method of slope reinforcement
JPH0960471A (en) Wall body for shield tunneling method
JP2700634B2 (en) Removable anchor