JPS59224770A - Wire arranging and assembling method of underground beam - Google Patents

Wire arranging and assembling method of underground beam

Info

Publication number
JPS59224770A
JPS59224770A JP9773583A JP9773583A JPS59224770A JP S59224770 A JPS59224770 A JP S59224770A JP 9773583 A JP9773583 A JP 9773583A JP 9773583 A JP9773583 A JP 9773583A JP S59224770 A JPS59224770 A JP S59224770A
Authority
JP
Japan
Prior art keywords
assembled
bodies
assembled bodies
column steel
steel frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP9773583A
Other languages
Japanese (ja)
Inventor
入谷 五郎
松山 禎憲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Haseko Corp
Original Assignee
Hasegawa Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hasegawa Komuten Co Ltd filed Critical Hasegawa Komuten Co Ltd
Priority to JP9773583A priority Critical patent/JPS59224770A/en
Publication of JPS59224770A publication Critical patent/JPS59224770A/en
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 本発明は地中梁の配筋組立方法に関する。[Detailed description of the invention] The present invention relates to a reinforcing assembly method for underground beams.

従来、地中梁の配筋は、梁主筋とスターラップを立体的
に先組みしてなる先組み体を柱鉄骨間に配置する一方、
柱梁仕口部においては柱鉄骨と交差する梁主筋を1本ず
つ配置し、それらと前記先組体の梁主筋を接合した後、
仕口部のスターラップを巻回固定していくという方法又
は現場で主筋の1本1本を配筋し、スターラップを巻回
固定し的であるため、高張シ、輸送、運搬が不便である
Conventionally, reinforcing for underground beams is done by placing a pre-assembled body between the column steel frames, which is made up of three-dimensional pre-assembled beam main reinforcements and stirrups.
At the column and beam joints, the main beam reinforcements that intersect with the column steel are placed one by one, and after connecting them to the main beam reinforcements of the pre-assembled body,
The method of winding and fixing the stirrup at the joint, or arranging each main reinforcing bar one by one at the site and winding and fixing the stirrup, is inconvenient due to high tension and transportation. be.

また、各スパン間で先組み体の両端をジヨイントしなけ
ればならず、ジヨイント数が多いという欠点があるし、
先組み体を捨コンクリ1−ト上面から一定高さに持ち上
げた状態で支持するだめの仮設材が必要である。一方、
後者の方法はこのような輸送等の面での欠点はないもの
の、現場で主筋を1本1本配筋せねばならないため、能
率が悪く、しかも、上端主筋を一定の高さに渫つための
犬がかりな足場を組まねばならず、作業性の点で問題が
ある。
Also, it is necessary to joint both ends of the pre-assembled body between each span, which has the disadvantage of requiring a large number of joints.
A temporary material is required to support the pre-assembled body at a certain height above the top of the waste concrete. on the other hand,
Although the latter method does not have such disadvantages in terms of transportation, etc., it is inefficient because the main reinforcing bars must be arranged one by one on site, and moreover, the upper main reinforcing bars must be raised to a fixed height. This poses a problem in terms of workability, as scaffolding must be erected with the help of several dogs.

そこで本発明は、現場での作業性が良く、かつ輸送、運
搬が便利であると共に、足場やその他の仮設材を大幅に
省略できる等、上nCシた従来方法の各欠点を一掃し得
る新規方法を提供するものである。
Therefore, the present invention is a novel method that can wipe out the drawbacks of the above-mentioned conventional methods, such as being easy to work with on-site, convenient to transport and transport, and greatly eliminating the need for scaffolding and other temporary construction materials. The present invention provides a method.

即ち、本発明に係る地中梁の配筋組立方法は、地中梁の
主筋を、梁幅方向で2分割された如き一対の平面的な形
状の先組み体に組立てておく一方、柱鉄骨には、柱鉄骨
の両面から突出した腕杆を固着しておき、前記先組み体
を柱鉄骨に両面から抱き合わせだ状態に配置して先組み
体の各々を前記腕杆で吊下げ支持させ、これら両先組み
体の主筋と、梁長さ方向に隣接する先組み体の主筋とを
スパン中間部において接合した後、これらの先組み体の
周囲にスターラップを巻回固定することを要旨としてい
る。
That is, in the underground beam reinforcement assembly method according to the present invention, the main reinforcement of the underground beam is assembled into a pair of planar pre-assembled bodies that are divided into two in the beam width direction, while the column steel In this step, arm rods protruding from both sides of the column steel frame are fixed, and the pre-assembled bodies are arranged to be hugged from both sides of the column steel frame, and each of the pre-assembled bodies is suspended and supported by the arm rod, The gist of this method is to connect the main reinforcements of both pre-assembled bodies and the main reinforcements of the pre-assembled bodies adjacent in the length direction of the beam at the mid-span section, and then wrap and fix stirrups around these pre-assembled bodies. There is.

次に本発明方法の実施例を図面に基づき説明する。先ず
第1図に示すように梁主筋の左右側面に相当する部分A
、Bを平面的に先組みする。この先組みに際しては各主
筋ta、tb・・・1fを所定の間隔に保った状態で継
ぐ治具2を用いる。この治具2は第2図に示すように上
端主筋1a、lbを挿入すZ孔3,3と、2段筋及び下
端主筋ld、Ifを載せる受部4,4と、各孔及び受部
を所定の間隔に保つ継ぎ腕5とから成っている。
Next, embodiments of the method of the present invention will be described based on the drawings. First, as shown in Figure 1, part A corresponds to the left and right sides of the main beam reinforcement.
, B are preassembled in a plane. In this pre-assembly, a jig 2 is used to connect the main reinforcements ta, tb, . . . 1f while keeping them at predetermined intervals. As shown in Fig. 2, this jig 2 has Z holes 3, 3 into which the upper end main reinforcements 1a, lb are inserted, receivers 4, 4 into which the two-step reinforcements and lower end main reinforcements ld, If are placed, and each hole and receiver. It consists of a joint arm 5 that maintains a predetermined spacing.

次いで、このように先組みした左右側面体A。Next, the left and right side bodies A were assembled in this way.

B(以下、先組み体という。)を第3図(a)(H)に
示すように柱鉄骨60両側から抱き合わせるように設け
る。この場合、柱鉄骨6に予じめ適当な高さに柱鉄骨6
の梁幅方向両面から突出した腕杆7゜7を取付けておき
、との腕杆7,7に先組み体A。
B (hereinafter referred to as a pre-assembled body) are provided so as to hug each other from both sides of the column steel frame 60, as shown in FIGS. 3(a) and 3(H). In this case, the column steel frame 6 should be placed at an appropriate height on the column steel frame 6 in advance.
Attach the arm rods 7゜7 that protrude from both sides in the width direction of the beam, and attach the pre-assembled body A to the arm rods 7, 7.

Bの上端主筋1aを引掛けて、吊下げ支持させるものと
する。
It is assumed that the upper end main reinforcement 1a of B is hooked and suspended for support.

そして、両先組み体A、Bの主筋と、梁長さ方向に隣接
する同様な形状を有し且つ同様な方法により配設された
先組み体A’ 、 B’の主筋とをスパン中間部におい
て圧接1重ね継手等pcよシ接合する。
Then, the main reinforcements of the double-end assembled bodies A and B and the main reinforcements of the front assembled bodies A' and B', which have the same shape and are arranged in the same manner and are adjacent to each other in the beam length direction, are connected to the middle part of the span. At this step, PC joints such as pressure welding single lap joints are made.

しかる後、これら先組み体A 、 B 、 A 、 1
3’の周囲にスターラップ8を巻回固定し、地中梁の配
筋を完了するのである。尚、スターラップ8として、角
形のスパイラルフープ筋を用いる場合には、先組み体A
、Bを腕杆7,7に吊rげ支持させた時点で、収縮状態
にあるスパイラルフープ筋を先組み体A、Bに套嵌係止
させておき、隣接する先組み体N、B′との接合後に、
スパイラルフープ筋を引き伸ばし、番線等により主筋に
固定すればよい。
After that, these pre-assembled bodies A, B, A, 1
Stirrup 8 is wound and fixed around 3', and reinforcement of the underground beam is completed. In addition, when using a rectangular spiral hoop muscle as the stirrup 8, the pre-assembled body A
, B are suspended and supported by the arm rods 7, 7, the spiral hoop muscles in the contracted state are fitted and locked in the pre-assembled bodies A, B, and the adjacent pre-assembled bodies N, B' After joining with
Just stretch the spiral hoop reinforcement and fix it to the main reinforcement with wire, etc.

以上説明したように本発明に係る地中梁の配筋組立方法
によれば次の如き効果がある。
As explained above, the underground beam reinforcement assembly method according to the present invention has the following effects.

■ 先組み体は梁主筋の左右各側面に相当する平面的な
ものであるから、嵩張らず、輸送、運搬が至極便利であ
る。
■ Since the pre-assembled body is flat, corresponding to the left and right sides of the main beam reinforcement, it is not bulky and is extremely convenient to transport and transport.

■ 2つの先組み体を柱鉄骨に抱き合せて配置し、柱鉄
骨に固着された腕杆で吊下げ支持させるので、現場に足
場を組む必要がなく、現場での作業が頗る簡単になる。
■ Since the two pre-assembled bodies are placed together on the steel column and suspended and supported by arm rods fixed to the steel column, there is no need to set up scaffolding on site, making on-site work extremely easy.

■ 先組み体を柱鉄骨と交差する状態に設けて配筋する
ので、各スパン間で先組み体の主筋同士を接合すればよ
く、接合数が減少する。
■ Since the pre-assembled body is installed and reinforced so that it intersects with the column steel frame, the main reinforcements of the pre-assembled body only need to be connected between each span, reducing the number of connections.

【図面の簡単な説明】[Brief explanation of the drawing]

図面本発明方法の一実施例を示し、第1図は先組み体の
斜視図、第2図は治具斜視図、第3図(a)(1))は
先組み体を柱鉄骨に設ける状態を示す正面図及び側面図
、第4図は第f図の如く配筋された先組み体にスターラ
ップを巻き、また隣の先組み体とジヨイントした状態を
示す図である。 A、B・・・先組み体、ia、ib・・・主筋、6・・
・柱鉄骨、7・・・腕杆。 1f 第2図 第3図 第4図
The drawings show one embodiment of the method of the present invention, in which Fig. 1 is a perspective view of a pre-assembled body, Fig. 2 is a perspective view of a jig, and Fig. 3 (a) (1)) shows a pre-assembled body installed on a column steel frame. A front view and a side view showing the state, and FIG. 4 is a diagram showing a state in which a stirrup is wound around the pre-assembled body having reinforcement as shown in FIG. A, B... pre-assembled body, ia, ib... main reinforcement, 6...
・Column steel frame, 7...arm rod. 1f Figure 2 Figure 3 Figure 4

Claims (1)

【特許請求の範囲】[Claims] 地中梁の主筋を、梁幅方向で2分割された如き一対の平
面的な形状の先組み体に組立てておく一方、柱鉄骨には
、柱鉄骨の両面から突出した腕杆を固着しておき、前記
先組み体を柱鉄骨に両面から抱き合わせた状態に配置し
て、先組み体の各々を前記腕杆で吊下は支持させ、これ
ら両先組み体の主筋と、梁長さ方向に隣接する先組み体
の主筋とをスパン中間部において接合した後、これらの
先組み体の周囲にスターラップを巻回固定することを特
徴とする地中梁の配筋組立方法。
The main reinforcement of the underground beam is assembled into a pair of planar pre-assembled bodies that are divided into two parts in the width direction of the beam, while arm rods protruding from both sides of the column steel frame are fixed to the column steel frame. The pre-assembled bodies are placed in a state where they are hugged from both sides by the column steel frame, each of the pre-assembled bodies is suspended and supported by the arm rod, and the main reinforcement of both of these pre-assembled bodies and the beam length direction are arranged. A method for assembling reinforcing for underground beams, which comprises joining the main reinforcements of adjacent pre-assembled bodies at mid-spans, and then winding and fixing stirrups around these pre-assembled bodies.
JP9773583A 1983-05-31 1983-05-31 Wire arranging and assembling method of underground beam Pending JPS59224770A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9773583A JPS59224770A (en) 1983-05-31 1983-05-31 Wire arranging and assembling method of underground beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9773583A JPS59224770A (en) 1983-05-31 1983-05-31 Wire arranging and assembling method of underground beam

Publications (1)

Publication Number Publication Date
JPS59224770A true JPS59224770A (en) 1984-12-17

Family

ID=14200149

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9773583A Pending JPS59224770A (en) 1983-05-31 1983-05-31 Wire arranging and assembling method of underground beam

Country Status (1)

Country Link
JP (1) JPS59224770A (en)

Similar Documents

Publication Publication Date Title
JP2005194878A (en) Reinforcing bar connecting structure and method for producing reinforced unit
JP2003293521A (en) Double reinforcement structure of reinforced concrete foundation
JPS59224770A (en) Wire arranging and assembling method of underground beam
TWI644006B (en) Seismic reinforcing structure of composite spiral reinforcement and method for producing thereof
CN218437471U (en) H-shaped steel column haunch beam link node structure
JP2926120B2 (en) Reinforcing method using semi prefabricated reinforcing bars for column hoops
JP2538528B2 (en) Slope stabilization method
JP2542283B2 (en) Joining Method of Beam Reinforcement in Wall-type Ramen Column
JPH06146301A (en) Reinforcement unit for concrete foundation and connection method thereof
JPS60129350A (en) Construction of reinforced concrete pillar
JPS62146332A (en) Connection structure of pillar and beam and construction method thereof
JP3002704B2 (en) Rebar joint structure
JPH019843Y2 (en)
JPS58204246A (en) Construction of reinforced concrete structure
JPH07109788A (en) Foundation construction reinforcements and foundation construction reinforcement frame assembling method
JPH0439954Y2 (en)
JPS61250240A (en) Connection of pc pillar and beam
JPS62260967A (en) Method for assembling reinforcement for reinforced concrete structure
JP2582190Y2 (en) Pre-bar arrangement of total foundation
JPS5830987B2 (en) Rebar assembly method
JPS60212552A (en) Assembling of iron skeletal of pillar and beam
JP2001214511A (en) Light-weight driven column form with column hoop
JPH0426380B2 (en)
JP2001241101A (en) Structure for erecting beam-shaped members in prefabricated building
JP2000282624A (en) Reinforcing bar structure and reinforcing bar unit using it