JPS59190590A - Spiral duct - Google Patents

Spiral duct

Info

Publication number
JPS59190590A
JPS59190590A JP6607383A JP6607383A JPS59190590A JP S59190590 A JPS59190590 A JP S59190590A JP 6607383 A JP6607383 A JP 6607383A JP 6607383 A JP6607383 A JP 6607383A JP S59190590 A JPS59190590 A JP S59190590A
Authority
JP
Japan
Prior art keywords
spiral
duct
connecting bolt
joint surface
spiral duct
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP6607383A
Other languages
Japanese (ja)
Inventor
豊島 習之
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
KIYUUSHIYUU SUPAIRARU KOUKAN K
KIYUUSHIYUU SUPAIRARU KOUKAN KK
Original Assignee
KIYUUSHIYUU SUPAIRARU KOUKAN K
KIYUUSHIYUU SUPAIRARU KOUKAN KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KIYUUSHIYUU SUPAIRARU KOUKAN K, KIYUUSHIYUU SUPAIRARU KOUKAN KK filed Critical KIYUUSHIYUU SUPAIRARU KOUKAN K
Priority to JP6607383A priority Critical patent/JPS59190590A/en
Publication of JPS59190590A publication Critical patent/JPS59190590A/en
Pending legal-status Critical Current

Links

Landscapes

  • Supports For Pipes And Cables (AREA)
  • Duct Arrangements (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔発明の技術分野〕 本発明は、随道工事等の土木工事や建設工事に当って、
工事現場に設置される送気用、仮設排水用等に使用され
るスパイラル・ダクトの構造に関する。
[Detailed Description of the Invention] [Technical Field of the Invention] The present invention relates to civil engineering work and construction work such as road work, etc.
Related to the structure of spiral ducts used for air supply, temporary drainage, etc. installed at construction sites.

従来、スパイラル・ダクトの組立連結に当っては、比較
的幅の狭いブリキ板をスパイラル状に巻回してスパイラ
ル管を作り、各スパイラル管の間をニソツ°ル、フラン
ジを用いて連結してスパイラルダクトとし、そして各ス
パイラル管を複数の支持環によって天井等から懸吊支持
していた。
Conventionally, when assembling and connecting spiral ducts, a spiral pipe was created by winding a relatively narrow tin plate in a spiral shape, and the spiral pipes were connected using Nisoturu and flanges between each spiral pipe. A duct was used, and each spiral pipe was suspended and supported from the ceiling or the like by a plurality of support rings.

また、昨今、熱軟化性樹脂を用いた収縮性のある連結緊
締用のテープが開発され、このテープを巻回して締め付
けて連結部に空気洩れや水洩れのないものが現場作業に
用いられるようになった。
In addition, recently, shrinkable connection tightening tapes made of heat-softening resin have been developed, and these tapes can be wound and tightened to prevent air or water leaks in the connection areas and can be used in field work. Became.

しかしながら、かかる構造のダクトにあっても、支持環
が各スパイラル管(2)の中途を吊下するので、各スパ
イラル管を直線的に支持することが難しく、連結部が屈
曲し、芯ズレを生じて連結テープが切断して空気洩れや
水洩れを起したり、また、その組立設置も、現場作業と
して手間がかかるという問題がある。
However, even in a duct with such a structure, since the support ring suspends the middle of each spiral pipe (2), it is difficult to support each spiral pipe in a straight line, and the connecting part is bent, causing misalignment. There are problems in that the connecting tape is cut, resulting in air leakage or water leakage, and that assembly and installation thereof is time-consuming and labor-intensive on-site work.

〔発明の目的〕[Purpose of the invention]

本発明の目的は、かかる従来のスパイラル・ダクトの問
題点に鑑み考案されたもので、結合部分の芯ズレをなく
しかつ気密性を高めることによって接合面の接合強度を
向上して洩れを防止し、しかも、現場で簡単にかつ短期
間に組立てることができる強固な結合部を有するスパイ
ラル・ダクトを提供することにある。
The purpose of the present invention was devised in view of the problems of the conventional spiral duct, and it is intended to improve the joint strength of the joint surface and prevent leakage by eliminating misalignment of the joint part and increasing airtightness. Moreover, it is an object of the present invention to provide a spiral duct having a strong joint that can be easily assembled on-site in a short period of time.

〔発明の構成〕[Structure of the invention]

上記目的を達成するため、本発明ではスパイラル管の接
合面に伸縮性のある防食熱収縮テープを巻着するととも
に、同接合面の面倒位置に対のボルト固定金具を取付け
、両固定金具に連結ボルトを緊締状態に取付け、接合部
における接合強度及び直線度を増大するとともに、吊支
時曲げモーメンI・や剪断応力を接合面に生じず、耐震
性があり、かつ芯ズレを発生しない構成にしている。
In order to achieve the above object, the present invention wraps an elastic anti-corrosion heat-shrinkable tape around the joint surface of the spiral pipe, and attaches a pair of bolt fixing fittings at awkward positions on the joint surface, and connects them to both fixing fittings. The bolts are tightened to increase the joint strength and straightness at the joint, and the structure is earthquake resistant and does not cause misalignment, without causing bending moment I or shear stress on the joint surface during suspension. ing.

〔実施例〕〔Example〕

以下添付図に示す実施例に基いて本発明を具体的に説明
する。なお、図示の実施例は間道における送風管として
用いた場合を示す。
The present invention will be specifically described below based on embodiments shown in the accompanying drawings. Note that the illustrated embodiment shows a case where it is used as a blow pipe in a driveway.

なお第1図は本発明のスパイラル管クI・の斜視図を示
し、第2図は同スパイラルダクトの取付状態説明図、第
3図は第2図1−1線による断面図である。
1 is a perspective view of the spiral duct I of the present invention, FIG. 2 is an explanatory view of the spiral duct in an attached state, and FIG. 3 is a sectional view taken along line 1-1 in FIG.

スパイラルダクト(1)はブリキ板を巻回して組立てた
スパイラル管(2)から構成されている。(3)はスパ
イラル管(2)の対応する端面を接合する接合面であり
、同接合面(3目皿には防食熱収縮テープ(4)が一部
重合状態に巻付けられている。さらに(5)と(6)は
、スパイラル管(21,(2+の接合面(3)から対称
に離隔した位置に、カス溶接あるいばりベントかしめさ
れた一対の連結ボルト固定金具であって、両固定金具(
5)、 (61に連結ボルト(7)の両端が緊締状態に
係合される。
The spiral duct (1) is composed of a spiral tube (2) assembled by winding tin plates. (3) is a joint surface that joins the corresponding end surfaces of the spiral tube (2), and the joint surface (the third plate is wrapped with anticorrosive heat shrink tape (4) in a partially polymerized state. (5) and (6) are a pair of connecting bolt fixing fittings that are slender welded or burr bent caulked at positions symmetrically apart from the joint surface (3) of the spiral pipe (21, (2+), and both fixing Metal fittings (
5), (Both ends of the connecting bolt (7) are engaged in a tightened state at 61.

各添付図には連結ボルト固定金具(5L (61として
平板状の一対のみのものが図示されているが、ダクトの
径とその環境によって、平板状のものを単にアングルに
したり、複数の対にすることも勿論可能である。
Each attached figure shows only one pair of connecting bolt fixing fittings (5L (61) in the form of a flat plate, but depending on the diameter of the duct and its environment, the flat plate may be simply made into an angle, or it may be made into multiple pairs. Of course, it is also possible to do so.

また、連結ボルト(7)としては、両端をナンド(8)
によって締め付ける代りに、図示のように一端を曲げて
、他端のみをボルト締めするようにしたものを利用する
と作業も簡単でしかも、確実な芯出しを行うことができ
る。
In addition, as a connecting bolt (7), both ends are connected to a NAND (8).
Instead of tightening with a bolt, use one in which one end is bent and only the other end is tightened with a bolt, as shown in the figure, which makes the work easier and allows for reliable centering.

かかる構造を持つスパイラル管(2)の組み立ては以下
のようにして行う。
The spiral tube (2) having such a structure is assembled as follows.

ます、スパイラル管(2+、 (2)の連結ボルト固定
金具(5)と(6)に連結ボルト(7)を通してす・ノ
ド(8)によって、スパイラル管(2+、 (2+の接
合面(3)を作る。その後、連結ボルト(7)に、なま
じ線或いはフラノトノ\−によって作成された吊具(9
)を介して、鈴道内を伸延する吊支用メンセンジャワイ
ヤ00)に吊支する。
First, pass the connecting bolt (7) through the connecting bolt fixing fittings (5) and (6) of the spiral tube (2+, (2)). Using the throat (8), connect the joint surface (3) of the spiral tube (2+, (2)). After that, connect the connecting bolt (7) with a hanging tool (9) made from a straight line or a furano tono\-.
), it is suspended from the mensenger wire 00) extending inside the bell path.

そして、その接合面(3)を、例えば、架橋ポリエチレ
ンフィルムの基材の片面にブチルゴム系粘着剤を塗布し
た引張り強さ 100kg / ctAツ上の伸縮性の
防食熱収縮テープ(4)を一部を重合状態にして巻き付
ける。そしてテープ(4)の巻き付は部分を、通常の場
合粘着剤の軟化温度である120度に加熱して、緊締を
強くする。
Then, the joint surface (3) is partially covered with a stretchable anti-corrosion heat shrinkable tape (4) with a tensile strength of 100 kg/ctA, which is made by applying a butyl rubber adhesive to one side of the base material of a cross-linked polyethylene film. into a polymerized state and wrap it around. When wrapping the tape (4), the part is heated to 120 degrees, which is the softening temperature of the adhesive in normal cases, to strengthen the tightening.

さらに第2図及び第3図に見られるように、フレーム0
.0)に吊支されるスパイラルダクト(1)は、連結ボ
ルト(7)がつねに頂部に来るようになるので、各スパ
イラル管(2)、 (21の芯は、ずれることがなく連
結テープ(4)に剪断応力が発生せず、はぼ永久的に連
結接合面の空気洩れや水洩れの発生を防止することがで
きる。
Furthermore, as seen in FIGS. 2 and 3, frame 0
.. Since the connecting bolt (7) of the spiral duct (1) suspended from the spiral duct (1) is always at the top, the cores of the spiral pipes (2) and (21) can be attached to the connecting tape (4) without shifting. ), no shear stress is generated on the joint surface, and air leakage and water leakage from the connecting joint surfaces can be almost permanently prevented.

なお、上記実施例では隘道工事における送風管として用
いたが、仮設排水管として用いることもでき、この場合
は、地面上に設置することができる。さらに地面に設置
する場合は、前述の連結ボルトを地上の固定物と連結し
て、排水管の固定化を図ることができる。
In addition, in the above embodiment, it was used as a blower pipe in tunnel construction, but it can also be used as a temporary drainage pipe, and in this case, it can be installed on the ground. Furthermore, when installing on the ground, the drain pipe can be fixed by connecting the above-mentioned connecting bolt to a fixed object on the ground.

〔発明の効果〕〔Effect of the invention〕

以上述べてきた如く、本発明は下記の効果を奏する。 As described above, the present invention has the following effects.

(1)  スパイラル管の接合作業を容易に行うことが
でき、作業時間を短縮でき、工事費を著しく低減するこ
とができる。
(1) Spiral pipe joining work can be easily performed, work time can be shortened, and construction costs can be significantly reduced.

(2)接合面の気密性を著しく高めることができ、洩れ
を完全に防止することができる。
(2) The airtightness of the joint surfaces can be significantly improved, and leakage can be completely prevented.

(3)  フランジ接合法に比べて材料費が廉価である
(3) Material costs are lower than the flange joining method.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明にかかるスパイラルダクトの斜視図、第
2図は同スパイラルダクトの取付状!3説明図、第3図
は第2図1−I線による断面図である。 図中、 (1)  スパイラルダクト (2)  スパイラル管 (3)接合面 (4)防食熱収縮テープ (5)連結ボルト固定金具 (6)連結ホル(・固定金具 (7)連結ボルト (8)  ナソ1− (9)吊具 00)  吊支用メソセンジャワイヤ 特許出願人     九州スパイラル鋼管株式会社代理
人  小堀 益(ほか2名)
Fig. 1 is a perspective view of the spiral duct according to the present invention, and Fig. 2 is the installation state of the spiral duct! 3 is a sectional view taken along line 1-I in FIG. 2. In the figure: (1) Spiral duct (2) Spiral pipe (3) Joint surface (4) Anti-corrosion heat shrink tape (5) Connection bolt fixing fitting (6) Connection hole (fixing fitting (7) Connection bolt (8) Naso 1- (9) Hanging tool 00) Mesosenja wire for hanging support Patent applicant: Kyushu Spiral Steel Tube Co., Ltd. Agent Masu Kobori (and 2 others)

Claims (1)

【特許請求の範囲】[Claims] 1、 スパイラル管を防食熱収縮テープによって接合し
てなるスパイラルダクトにおいて、同ダクトを構成する
各スパイラル管の各接合面の近傍の外周面上であってか
つ同接合面に相対する位置に対をなす連結ボルト固定金
具を固設し、両連結ボルト固定金具間に連結ボルトを差
し渡すことを特徴とするスパイラルダクト。
1. In a spiral duct formed by joining spiral pipes with anti-corrosion heat shrinkable tape, a pair is placed on the outer circumferential surface of each spiral pipe constituting the duct near each joint surface and at a position opposite to the joint surface. A spiral duct characterized in that a connecting bolt fixing fitting is fixedly installed, and the connecting bolt is passed between both connecting bolt fixing fittings.
JP6607383A 1983-04-14 1983-04-14 Spiral duct Pending JPS59190590A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6607383A JPS59190590A (en) 1983-04-14 1983-04-14 Spiral duct

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6607383A JPS59190590A (en) 1983-04-14 1983-04-14 Spiral duct

Publications (1)

Publication Number Publication Date
JPS59190590A true JPS59190590A (en) 1984-10-29

Family

ID=13305297

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6607383A Pending JPS59190590A (en) 1983-04-14 1983-04-14 Spiral duct

Country Status (1)

Country Link
JP (1) JPS59190590A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2021128099A (en) * 2020-02-14 2021-09-02 日本製鉄株式会社 Accessory attachment position inspection method and attachment position inspection device

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59170588A (en) * 1983-03-18 1984-09-26 昭和電工株式会社 Method and device for hanging composite pipe

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59170588A (en) * 1983-03-18 1984-09-26 昭和電工株式会社 Method and device for hanging composite pipe

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2021128099A (en) * 2020-02-14 2021-09-02 日本製鉄株式会社 Accessory attachment position inspection method and attachment position inspection device

Similar Documents

Publication Publication Date Title
US2896669A (en) Pipe casement
US3642308A (en) Conduit system
JPS59190590A (en) Spiral duct
KR20110075788A (en) Duct for clamp
JPH05322080A (en) Pipe with flange made of reinforced synthetic resin
CN214425441U (en) Assembled built on stilts insulating tube
JP3510162B2 (en) How to install fittings
CN215634715U (en) Inhaul cable with high-temperature-resistant protection structure
JP7379412B2 (en) Sheet metal exterior materials and construction methods for sheet metal exterior materials
US20240117914A1 (en) Connector for subsea pipelines and risers, and repair of a pipeline or riser utilizing the connector
JPH0228318Y2 (en)
JPS6123096Y2 (en)
SU1397670A1 (en) Arrangement for butt joint of pressure reinforced-concrete pipe
CN112253897A (en) Assembled built on stilts insulating tube
KR0136170Y1 (en) Duct connecting device
JPH02262814A (en) Protection of rising section of burried cable
JPS59170588A (en) Method and device for hanging composite pipe
RU31427U1 (en) Support ring for piping
JP2001099390A (en) Pipe joint part corrosion preventing structure
JPS5918211B2 (en) 114/1. Corrosion prevention method for elbows
RU2407941C1 (en) Clamp-brace for securing rubber collar on pipeline of crossing
JPS6215327Y2 (en)
JP3098160B2 (en) Flexible structure pipeline
JPH0340923Y2 (en)
JPH08285146A (en) Joining structure of sheath pipe inserting prefabricated porous pipe