Intermediate anchoring method and tool of unbond steel material

Info

Publication number
JPS59179965A
JPS59179965A JP5555883A JP5555883A JPS59179965A JP S59179965 A JPS59179965 A JP S59179965A JP 5555883 A JP5555883 A JP 5555883A JP 5555883 A JP5555883 A JP 5555883A JP S59179965 A JPS59179965 A JP S59179965A
Authority
JP
Japan
Prior art keywords
steel material
slab
unbonded steel
unbonded
formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP5555883A
Other languages
Japanese (ja)
Inventor
土居 健二
博史 竹山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fudo Kenken Kk
Fudou Kenken Kk
Original Assignee
Fudo Kenken Kk
Fudou Kenken Kk
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fudo Kenken Kk, Fudou Kenken Kk filed Critical Fudo Kenken Kk
Priority to JP5555883A priority Critical patent/JPS59179965A/en
Publication of JPS59179965A publication Critical patent/JPS59179965A/en
Pending legal-status Critical Current

Links

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 本発明はスラブにおけるアンボンド鋼材の中間定着の技
術に関するものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a technique for intermediate fixing of unbonded steel materials in slabs.

アンボンド工法はスラブの大型化、スラブ自軍の低減、
たわみ、ひび割の制御等を目的としてスラブに用いられ
ているが、アンボンド工法の鋼材はコンクリートとの付
着がなく、定着点間の距離も作業性のため60〜50m
と長くしているため、設計条件下では前記目的は一応達
成畑れるが、予想外の、集中荷重や大荷重によるたわみ
の増加、それの隣接スパンへの影響、部分的にスラブが
破壊して鋼材が切断した場合の鋼材のすべり等の問題点
がある。
The unbonded construction method increases the size of the slab, reduces the size of the slab,
It is used in slabs for the purpose of controlling deflection and cracking, but the unbonded method steel does not adhere to concrete, and the distance between anchoring points is 60 to 50 m for workability.
Although the above objectives can be achieved under the design conditions, there are unexpected increases in deflection due to concentrated loads and large loads, its impact on adjacent spans, and partial slab failure. There are problems such as slipping of the steel material when it is cut.

本発明は、アンボンド工法の特長を生かし、かつ、前記
問題点に対して安全性を高めることができるアンボンド
鋼材の中間定着方法と該方法用の中間定着具を提供する
ことを目的としているものであって、方法発明の構成ト
の特徴は、スラブ型枠内の所望位置に設置した箱状型枠
の内部を除いてスラブコンクリートを打設するとともに
、前記箱状型枠を貫通しているアンボンド鋼材に中間定
着具を取付け、スラブコンクリートの硬化後、アンボン
ド鋼材を緊張してその端部を定着し、それから前記箱状
型枠の内部にコンクリートを充填する点にあり、1だ用
具発明の構成上の特徴は、上縁に開口するU形のアンボ
ンド鋼材挿入溝を設けたスペーサ兼用のアンカープレー
トと、該アンカープレートの両側において相対向してア
ンボンド鋼材に取付けられる各1対のコーンとチャック
から成る点である。
The present invention aims to provide an intermediate fixing method for unbonded steel materials that takes advantage of the features of the unbonded method and can improve safety against the above-mentioned problems, and an intermediate fixing tool for the method. A feature of the method invention is that slab concrete is poured except for the inside of a box-shaped form installed at a desired position within the slab form, and unbonded concrete is poured through the box-shaped form. An intermediate fixing device is attached to the steel material, and after the slab concrete hardens, the unbonded steel material is tensioned to fix the ends thereof, and then the inside of the box-shaped formwork is filled with concrete. The above feature consists of an anchor plate that also serves as a spacer with a U-shaped unbonded steel material insertion groove that opens on the upper edge, and a pair of cones and chucks that are attached to the unbonded steel material facing each other on both sides of the anchor plate. This is the point.

以下、図面に基いて本発明を具体的に説明する。Hereinafter, the present invention will be specifically explained based on the drawings.

第1図において、1は柱、2はスラブ、3iI′iアン
ポンド鋼材であって、このアンボンド鋼材3は図示され
ていないスラブ2の両端で定着きれている。
In FIG. 1, 1 is a column, 2 is a slab, and 3iI'i is an unbonded steel material, and the unbonded steel material 3 is fixed at both ends of the slab 2 (not shown).

この図の場合、本発明によるアンボンド鋼材3の中間定
着点は4で示されており、この所ではアンボンド鋼材3
は負の曲げモーメントに対抗するためにスラブ2の上側
部を通っている。
In this figure, the intermediate anchorage point of the unbonded steel 3 according to the invention is indicated at 4, where the unbonded steel 3
passes through the upper side of the slab 2 to counter negative bending moments.

第2図、第3図は中間定着点4の施工時における断面図
であり、図中、5はスラブ型枠、6は箱状型枠、7はス
ラブコンクリ−1・、8は中間定着具である。
Figures 2 and 3 are cross-sectional views of the intermediate fixing point 4 during construction, and in the figures, 5 is a slab formwork, 6 is a box-shaped formwork, 7 is a slab concrete 1, and 8 is an intermediate fixing tool. It is.

本発明によりアンボンド鋼材3の中間定着を行う場合は
、先ず、スラブ型枠5内の所望位置(中間定着点4)に
、アンボンド鋼材3が貫通した状態で箱状型枠6を投首
し、スラブ型枠5内に箱状型枠6の内部を除いてスラブ
コンクリート7を打設するとともに、箱状型枠6内に露
出しているアンボンド鋼材3に中間定着具8を取付ける
。この際、中間定着具8を取付ける近辺では、アンボン
ド鋼材30周面のすベシ材(例えば、グリース)は除去
する。
When performing intermediate fixation of the unbonded steel material 3 according to the present invention, first, the box-shaped formwork 6 is placed at a desired position (intermediate fixation point 4) in the slab formwork 5 with the unbonded steel material 3 penetrated, Slab concrete 7 is cast inside the slab formwork 5 except for the inside of the box-like formwork 6, and an intermediate fixing tool 8 is attached to the unbonded steel material 3 exposed inside the box-like formwork 6. At this time, the surrounding material (eg, grease) on the circumferential surface of the unbonded steel material 30 is removed in the vicinity where the intermediate fixing device 8 is attached.

中間定着具8は、スペーサ兼用のアンカープレート9と
各1対のコーン10 、10およびチャック11゜Ll
から成り、この中、コーン10 、10はチャック11
の挿入口を反対向きにして、予めアンボンド鋼材3に嵌
挿しておく。
The intermediate fixing device 8 includes an anchor plate 9 that also serves as a spacer, a pair of cones 10, 10, and a chuck 11°Ll.
It consists of a cone 10, 10 is a chuck 11
Insert it into the unbonded steel material 3 in advance with the insertion opening facing in the opposite direction.

アンカープレート9には上縁に開口するU形のアンボン
ド鋼材挿入溝L2が設けられておシ、このアンカープレ
ート9を図示のように直立状態でアンボンド鋼材3に取
付けてから、その両側にコーン10 、10を当てがい
、チャック11 、11を仮に挿入しておく。
The anchor plate 9 is provided with a U-shaped unbonded steel material insertion groove L2 that opens at its upper edge.After the anchor plate 9 is attached to the unbonded steel material 3 in an upright state as shown in the figure, cones 10 are inserted on both sides of the anchor plate 9. , 10, and temporarily insert the chucks 11 and 11.

スラブコンクリート7が硬化したら、アンボンド鋼材3
を緊張するが、箱状型枠6の内法tは緊張時のアンボン
ド鋼材3の伸びを拘束しない長さにすべきである。
Once the slab concrete 7 has hardened, unbond steel 3
However, the inner diameter t of the box-like formwork 6 should be set to a length that does not restrict the elongation of the unbonded steel material 3 during tensioning.

緊張したアンボンド鋼材3の端部をスラブコンクリート
に定着し、チャック11 、11を打込むとともに、箱
状型枠6の内部にコンクリートを充填すれば、作業終了
である。
The end of the tensed unbonded steel material 3 is fixed to the slab concrete, the chucks 11 are driven in, and the inside of the box-shaped formwork 6 is filled with concrete, and the work is completed.

本発明によれば、前述のようにしてアンボンド鋼材の中
間定着を行うので、アンボンド工法の特長を生かしつつ
、不慮の事故に対して安全性の高いスラブを施工するこ
とができる。そして、使用する中間定着具等も比較的簡
単なものであり、全体の作業性も良好であるから、経済
的である。
According to the present invention, since the unbonded steel material is intermediately fixed as described above, it is possible to construct a slab that is highly safe against unexpected accidents while taking advantage of the features of the unbonded construction method. Further, the intermediate fixing device and the like used are relatively simple, and the overall workability is good, so it is economical.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の対象であるスラブの説明図、第2図は
本発明による中間定着点の施工時における断面図、第3
囚は第2図のX−X線断面図である。 図中、2・・・スラブ、3・・・アンボンド鋼材、5・
・・スラブ型枠、6・・・箱状型枠、7・・・スラブコ
ンクリート、8・・・中間定着具、9・・・アンカーグ
レート、10・・・コーン、11・・・チャック、12
・・・アンボンド鋼材挿入溝。 特許出願人  フドウ建研株式会社 代理人弁理士  染 谷  廣 司
Figure 1 is an explanatory diagram of the slab that is the object of the present invention, Figure 2 is a sectional view of the intermediate fixing point according to the present invention during construction, and Figure 3
The figure is a sectional view taken along the line X--X in FIG. 2. In the figure, 2... slab, 3... unbonded steel, 5...
... Slab formwork, 6... Box-shaped formwork, 7... Slab concrete, 8... Intermediate fixing tool, 9... Anchor grate, 10... Cone, 11... Chuck, 12
...Unbonded steel material insertion groove. Patent applicant: Fudo Kenken Co., Ltd. Representative patent attorney: Hiroshi Sometani

Claims (1)

【特許請求の範囲】 1)スラブ型枠内の所望位置に設置した箱状型枠の内部
を除いてスラブコンク’J −トを打設するとともに、
前記箱状型枠を貫通しているアンボンド鋼材に中間定着
具を取付け、スラブコンクリートの硬化後、アンボンド
鋼材を緊張してその端部を定着し、それから前記箱状型
枠の内部にコンクリートを充填することを特徴とするア
ンボンド鋼材の中間定着方法。 2)上縁に開口するU形のアンボンド鋼材挿入溝を設け
たスペーサ兼用のアンカープレートと、該アンカープレ
ートの両側において相対向してアンボンド鋼材に取付け
られる各1対のコーンとチャックから成ることを特徴と
するアンボンド鋼材の中間定着具。
[Claims] 1) Placing slab concrete except for the inside of the box-shaped formwork installed at a desired position within the slab formwork,
An intermediate fixing device is attached to the unbonded steel material penetrating the box-shaped formwork, and after the concrete slab has hardened, the unbonded steel material is tensed to fix its ends, and then concrete is filled into the inside of the box-like formwork. An intermediate fixing method for unbonded steel material, characterized by: 2) It consists of an anchor plate that also serves as a spacer with a U-shaped unbonded steel material insertion groove opened at the upper edge, and a pair of cones and chucks that are attached to the unbonded steel material facing each other on both sides of the anchor plate. An intermediate fixing tool made of unbonded steel.
JP5555883A 1983-03-31 1983-03-31 Intermediate anchoring method and tool of unbond steel material Pending JPS59179965A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5555883A JPS59179965A (en) 1983-03-31 1983-03-31 Intermediate anchoring method and tool of unbond steel material

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5555883A JPS59179965A (en) 1983-03-31 1983-03-31 Intermediate anchoring method and tool of unbond steel material

Publications (1)

Publication Number Publication Date
JPS59179965A true JPS59179965A (en) 1984-10-12

Family

ID=13002026

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5555883A Pending JPS59179965A (en) 1983-03-31 1983-03-31 Intermediate anchoring method and tool of unbond steel material

Country Status (1)

Country Link
JP (1) JPS59179965A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5781560A (en) * 1980-11-05 1982-05-21 Taisei Corp Unbond prestressed concrete method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5781560A (en) * 1980-11-05 1982-05-21 Taisei Corp Unbond prestressed concrete method

Similar Documents

Publication Publication Date Title
US4182092A (en) Building panel chord tie and method of tieing together precast concrete building panels
US5423362A (en) Apparatus for forming an access pocket at the terminal end of a post-tensioned tendon
JPS59179965A (en) Intermediate anchoring method and tool of unbond steel material
JP2831934B2 (en) How to build substructure
JPS59192145A (en) Fixing of iron pillar
JP2649205B2 (en) Anchor bolt burying method
JPS6033159Y2 (en) Ready-made concrete pile
JPS605968A (en) Prestress introduction of pc slab in existing structure
JP3187343B2 (en) Legal structure and its construction method
JPS6058351B2 (en) Shear reinforcement method for openings in reinforced concrete members
JPH076252Y2 (en) Joint structure of PC beam and beam
JPS5944469B2 (en) Beam joining method using post-tension method
JPS58123907A (en) Erective construction of precast pillar-like body
JPH0786270B2 (en) Arrangement method of PC steel material of tubular structure
JP3078195U (en) Prestressed concrete structure
JPS61169522A (en) Head metal of soil cement pile for improving ground
JPH0124288Y2 (en)
JPS62228543A (en) Post-casting wall structure of wall body opening black body in atomic reactor building
JPS5944464A (en) Anchoring of building to concrete foundation
JPS63289145A (en) Method for fixing anchor bolt
JPS5980851A (en) Assembling type iron skeletal support tool
JPS59224755A (en) Crack prevention of opening part corner
JPS6314936A (en) Construction of prestessed concrete structure
JPS5898599A (en) Construction of tunnel structure
JPS6037346A (en) Connection of precast concrete beam and pillar