JPS59173420A - On-site driving reinforced concrete pile and its construction - Google Patents
On-site driving reinforced concrete pile and its constructionInfo
- Publication number
- JPS59173420A JPS59173420A JP4528183A JP4528183A JPS59173420A JP S59173420 A JPS59173420 A JP S59173420A JP 4528183 A JP4528183 A JP 4528183A JP 4528183 A JP4528183 A JP 4528183A JP S59173420 A JPS59173420 A JP S59173420A
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- pile
- cylinder
- unsuitable
- reinforced concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000011150 reinforced concrete Substances 0.000 title claims abstract description 14
- 238000010276 construction Methods 0.000 title description 3
- 239000004567 concrete Substances 0.000 claims abstract description 28
- 239000012535 impurity Substances 0.000 claims abstract description 11
- 239000011178 precast concrete Substances 0.000 claims abstract description 10
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 4
- 239000010959 steel Substances 0.000 claims abstract description 4
- 230000003014 reinforcing effect Effects 0.000 claims description 9
- 238000000034 method Methods 0.000 claims description 5
- 238000005266 casting Methods 0.000 claims 1
- 239000000440 bentonite Substances 0.000 abstract description 3
- 229910000278 bentonite Inorganic materials 0.000 abstract description 3
- SVPXDRXYRYOSEX-UHFFFAOYSA-N bentoquatam Chemical compound O.O=[Si]=O.O=[Al]O[Al]=O SVPXDRXYRYOSEX-UHFFFAOYSA-N 0.000 abstract description 3
- 239000000428 dust Substances 0.000 abstract 1
- 239000000843 powder Substances 0.000 abstract 1
- 230000002787 reinforcement Effects 0.000 description 12
- 201000010099 disease Diseases 0.000 description 2
- 208000037265 diseases, disorders, signs and symptoms Diseases 0.000 description 2
- 239000010419 fine particle Substances 0.000 description 2
- RYGMFSIKBFXOCR-UHFFFAOYSA-N Copper Chemical compound [Cu] RYGMFSIKBFXOCR-UHFFFAOYSA-N 0.000 description 1
- 229910052802 copper Inorganic materials 0.000 description 1
- 239000010949 copper Substances 0.000 description 1
- 230000001066 destructive effect Effects 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D9/00—Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
- E02D9/005—Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof removing the top of placed piles of sheet piles
Abstract
Description
【発明の詳細な説明】
本発明は場所打ち鉄筋コンクリート杭とその構築方法に
関する。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to cast-in-place reinforced concrete piles and methods of construction thereof.
従来、上記場所打ち熱動コンクIJ −ト杭は、一般に
所定位置に掘削し走杭孔内にかご型鉄筋を配設しコンク
リートをトレミー管により杭孔底部から徐々に打ち上げ
て構築するが、杭上端部分(約005〜1m位)には削
孔残層(スライム)、ベントナイトの微粉粒等の不純物
が混入した所定の強度以下の不適格なコンクリートが集
中する0
そこで杭上端部分を所定の杭頭面よりも約0.5〜1m
位高く余盛部分として形成し、硬化後にこの余盛部分の
コンクリートを削岩様、コンクリートブレーカ−等で破
壊し撤去するいわゆる杭頭処理を行っているが、その杭
頭処理に多くの時間と労力を敬し作業能率の低下、コス
トの高騰、破壊作業に伴う騒音振動公害の発生並びに労
働路疾病の発生等多くの欠点があった。Conventionally, the above-mentioned cast-in-place thermal concrete IJ-to piles are generally constructed by excavating at a predetermined location, placing cage-shaped reinforcing bars in the running pile hole, and gradually pushing up concrete from the bottom of the pile hole using a tremie tube. At the upper end (approximately 0.05 to 1 m), unsuitable concrete with a strength below the specified level and containing impurities such as the remaining layer of the drilling (slime) and fine particles of bentonite is concentrated. Approximately 0.5-1m above the head
Pile cap treatment is performed in which the concrete is formed as a high reinforcement area, and after hardening, the concrete in this reinforcement area is destroyed and removed using a rock drill or a concrete breaker. There were many disadvantages, such as a decrease in work efficiency due to labor, a rise in costs, the occurrence of noise and vibration pollution due to destructive work, and the occurrence of work-related diseases.
本発明場所打ち鉄筋コンクリート杭は、杭頭部に固着し
たプレキャストコンクリート環あるいは鋼製の筒体の内
側に不純物の混入した不適格な上層部のコンクリートを
収容し、杭頭部の性能をこの筒体が負担することにより
、上層部を撤去しないで収容したままでも杭の性能に支
障がないようにしたものである。The cast-in-place reinforced concrete pile of the present invention accommodates an unsuitable upper layer of concrete containing impurities inside a precast concrete ring or steel cylinder fixed to the pile head, and improves the performance of the pile head using this cylinder. By paying for this, the performance of the pile will not be affected even if the upper layer is left in the pile without being removed.
本発明場所打ちコンクリート杭の構築方法は、プレキャ
ストコンクリート環あるいはflA製の筒体をかご型鉄
筋の上側部に固着し、この鉄筋を杭孔内に゛その筒体の
上端が所定の杭頭面に一致するように配置−しておいて
、杭孔底よりコンクリートを徐々に打ち上げていき・ス
ライム・ゝントナイト等Q不純物が混入した不適格な上
層部を上記筒体の内側に全て収容することにより、従来
の杭頭処理を手製とし、該処蝉に伴う前記各欠点を一挙
に解消しようとするものである。The method for constructing cast-in-place concrete piles of the present invention involves fixing a precast concrete ring or a cylindrical body made of flA to the upper part of a cage-shaped reinforcing bar, and inserting this reinforcing bar into a pile hole so that the upper end of the cylindrical body is aligned with a predetermined pile cap surface. Concrete is gradually pushed up from the bottom of the pile hole, and all of the unsuitable upper layer mixed with Q impurities such as slime and atonite is contained inside the cylinder. Therefore, the conventional pile cap treatment is made by hand, and the above-mentioned drawbacks associated with the pile head treatment are all solved in one fell swoop.
以下には図示の実施例について、まず場所打ち鉄筋コン
クリート杭Aを説明し、次にその構築方法について説明
する。In the following, regarding the illustrated embodiment, first a cast-in-place reinforced concrete pile A will be explained, and then a method for constructing the same will be explained.
場所打ち鉄筋コンクリート杭Aは第1図に示すように所
定位置に掘削した杭孔1内に構築されたもので、杭頭部
に筒体2を固着している。The cast-in-place reinforced concrete pile A is constructed in a pile hole 1 excavated at a predetermined position, as shown in FIG. 1, and has a cylindrical body 2 fixed to the pile head.
筒体2は円形に配置した複数本の縦筋3を輪形の横筋4
により連結したかご型鉄筋5を設けたプレキャストコン
クリート環の円筒形をなし、下側部分に内側斜め上方に
傾斜した案内面6を形成し、上下端面から各縦筋3が所
蚤長さ突出している。The cylindrical body 2 has a plurality of vertical bars 3 arranged in a circular shape and a ring-shaped horizontal bar 4.
It has a cylindrical shape of a precast concrete ring with cage-shaped reinforcing bars 5 connected to each other, and a guide surface 6 that is inclined inwardly and upwardly is formed in the lower part, and each vertical bar 3 protrudes from the upper and lower end surfaces by a certain length. There is.
そして、筒体2tI′i杭孔1内に打設したコンクリー
ト7に埋設したかご型鉄筋8の縦筋9aと横筋9bに上
記縦筋3の下側突出部3aを重ね継手にして連結し、か
つ略下側半部をコンクリート7に固着させているととも
に、そのコンクリート7の削孔残層(スライム)、ベン
トナイトの微粉粒等の不純物が混入した所定の強度以下
の不適格な上層部7′をこの筒体2の内側中央部に収容
している。Then, the lower protruding portion 3a of the vertical reinforcement 3 is connected to the vertical reinforcement 9a and the horizontal reinforcement 9b of the cage-shaped reinforcement 8 buried in the concrete 7 cast in the pile hole 1 of the cylindrical body 2tI'i in a lap joint, In addition, approximately the lower half part is fixed to the concrete 7, and the upper layer part 7' is unsuitable because it has a strength below a predetermined strength and is contaminated with impurities such as the remaining layer of the concrete 7 (slime) and fine particles of bentonite. is housed in the inner center of this cylinder 2.
しかして、場所打ち鉄筋コンクリート杭Aは、杭頭部の
性能を筒体2が負担することによシ、コンクリート7の
上層部7′を収容したままでも杭の所要の性能に支障が
ないとともに、筒体2の縦筋3の上側突出部3bを上部
構造物(図示していない)との連結に使用できるもので
ある。Therefore, in the cast-in-place reinforced concrete pile A, since the performance of the pile head is borne by the cylinder body 2, there is no problem with the required performance of the pile even if the upper layer 7' of the concrete 7 is accommodated. The upper protruding portion 3b of the vertical reinforcement 3 of the cylinder body 2 can be used for connection with an upper structure (not shown).
次に、上記場所打ち鉄筋コンクリート杭Aの構築方法に
ついて説明するに、かご型鉄筋8の縦筋9aの上側部及
び横筋9bに筒体2の縦筋3の下側突出部3aを重ね継
手に結束して連結し、そのかご型鉄筋8を杭孔1内に筒
体2の上端が所定の杭頭面に一致するように配置する。Next, to explain the construction method of the cast-in-place reinforced concrete pile A, the lower protrusion 3a of the vertical reinforcement 3 of the cylinder body 2 is tied to the upper part of the vertical reinforcement 9a and the horizontal reinforcement 9b of the cage type reinforcement 8 in a lap joint. The cage-shaped reinforcing bars 8 are placed in the pile hole 1 so that the upper end of the cylinder body 2 coincides with a predetermined pile cap surface.
しかるのち、トレミー管(図示していない)を杭孔1の
底部まで挿入してコンクリート7を注出し、トレミー管
の先端が既に打設したコンクリート内に埋没した状態を
保持しながら徐々に打ち上げてい東、正常なコンクリー
ト7が筒体2の下端から略下半部内面にわたって固着し
、かつ不純物が混入した不適格な上層部7′が筒体2の
上側内部に収容されるところまで打設する。After that, a tremie pipe (not shown) is inserted to the bottom of the pile hole 1, concrete 7 is poured out, and the tip of the tremie pipe is gradually poured while keeping it buried in the concrete that has already been poured. East, the normal concrete 7 is poured from the lower end of the cylinder 2 to the inner surface of approximately the lower half, and the unsuitable upper layer 7' containing impurities is accommodated inside the upper side of the cylinder 2. .
この場合、上層部7′は案内面6によって筒体2の内側
に容易に案内されて上昇していくとともに、上層部7′
を筒体2内に収容したまま撒去しないので従来の杭頭処
理を全く行う必要がない0
上記実施例ではプレキャスト鉄筋コンクリート杭の筒体
を使用した場合について説〜〔たが、これに限らず、#
灸の筒体を使用してもよしとともに、筒体の形状寸法は
、構築しようとする杭に応じて正常なコンクリートに固
着し、かつ想定される不適格な上層部を全て収容できる
ものであればよいこと明らかである。In this case, the upper layer 7' is easily guided inside the cylinder 2 by the guide surface 6 and rises, and the upper layer 7'
Since the piles are not scattered while being housed in the cylinder 2, there is no need to perform conventional pile head treatment at all. ,#
A moxibustion cylinder may be used, and the shape and dimensions of the cylinder must be such that it can adhere to normal concrete according to the pile to be constructed, and accommodate all possible unsuitable upper layers. It is clear that this is a good thing.
以上述べたところから明らかなように本発明゛場所打ち
鉄筋コンクリート杭によれば、杭頭部にプレキャストコ
ンクリート環あるいは銅製の筒体を固着しているので、
杭頭部の性能をこの筒体が負担することにより、その内
側にコンクリートの不純物が混入した不適格な上層部を
収容したままでも、杭の所要の性能に支障を来たすこと
がない。As is clear from the above description, according to the cast-in-place reinforced concrete pile of the present invention, a precast concrete ring or a copper cylinder is fixed to the pile head.
Since this cylindrical body takes over the performance of the pile head, even if an unsuitable upper layer containing concrete impurities is housed inside the cylindrical body, the required performance of the pile will not be affected.
また、本発明場所打ち鉄筋コンクリート杭の構築方法に
よれば、鉄筋の上側部に固着した筒体の上端が所定の杭
頭面に一致するように配置しておいてコンクリートを打
設しその不純物の混入した不適格な上層部のコンクリー
トを、筒体の内側に収容してしまうことにより、従来の
杭頭処理を行うことなく、所定の杭頭面高式に合致した
場所打ち鉄筋コンクリート杭を正確かつ簡単に構築でき
るとともに、その上層部を撤去しないことにより従来の
杭頭処理を全く行う必要がなく、当然のことながら該処
理に伴う作業能率の低下、コストの高騰、騒音振動公害
の発生並びに労働諸疾病の発生等の欠点を一挙に解消で
きる。Further, according to the method for constructing cast-in-place reinforced concrete piles of the present invention, the upper end of the cylinder fixed to the upper side of the reinforcing bars is placed so that it coincides with the predetermined pile cap surface, and the concrete is poured and the impurities are removed. By storing the mixed and unsuitable upper layer concrete inside the cylinder, it is possible to accurately and accurately form cast-in-place reinforced concrete piles that meet the specified pile cap height formula without performing conventional pile cap treatment. It is easy to construct, and since the upper layer is not removed, there is no need for conventional pile cap treatment, which naturally reduces work efficiency, increases costs, causes noise and vibration pollution, and reduces labor costs. Disadvantages such as the occurrence of various diseases can be eliminated all at once.
図面は本発明の実施例を示し、第1図はプレキャストコ
ンクリート製の筒体を杭頭部に固着した場所打・ち鉄筋
コンクリート杭の要部の縦断面図、第2図は上記筒体を
かご型鉄筋に固着した状態を一部を切欠して示した斜視
図である。
2・・・プレキャストコンクリート製の筒体、7・・・
コンクリート、7′・・・上層部、8・・・かご型鉄筋
、−1・・・杭孔。
第2図The drawings show an embodiment of the present invention; Figure 1 is a longitudinal cross-sectional view of the main part of a cast-in-place reinforced concrete pile with a precast concrete cylinder fixed to the pile head; It is a partially cutaway perspective view showing a state in which it is fixed to a type reinforcing bar. 2... Cylindrical body made of precast concrete, 7...
Concrete, 7'... Upper layer, 8... Cage type reinforcement, -1... Pile hole. Figure 2
Claims (1)
るいt′i鋼製の筒体の内側に場所打ちコンクリート杭
のコンクリート打設に伴う不純物の混入した不適格な上
層部のコンクリートを収容しニド杭。 2、プレキャストコンク1ノート製あるいはfJi製の
筒体をかご型鉄筋の上側部に固着し、その力1ど型鉄筋
を杭孔内に上記筒体の上端力(所定の杭頭■]に一致す
るように配置しておいて、コンク1ノートを杭孔底より
徐々に打ち上げてこの不純物の混入した不適格な上層部
のコンク1ノート力玉、上記筒体の内側に収容されると
ころまで打設することを特徴とする場所打ち鉄筋コンク
1ノート杭の構築方法。[Scope of Claims] 1. An unsuitable upper layer contaminated with impurities due to concrete casting of cast-in-place concrete piles inside a cylinder made of precast concrete or T'i steel fixed to the head of the pile. Contains concrete and piles. 2. Fix a cylindrical body made of precast concrete 1 Note or fJi to the upper part of the cage-shaped reinforcing bar, and force the 1-shaped reinforcing bar into the pile hole to match the upper end force of the cylindrical body (predetermined pile cap ■). Gradually push up the Conch 1 Note from the bottom of the pile hole until the unsuitable Conk 1 Note in the upper layer containing impurities is accommodated inside the cylinder. A method for constructing a cast-in-place reinforced concrete pile, characterized by:
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4528183A JPS59173420A (en) | 1983-03-19 | 1983-03-19 | On-site driving reinforced concrete pile and its construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4528183A JPS59173420A (en) | 1983-03-19 | 1983-03-19 | On-site driving reinforced concrete pile and its construction |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS59173420A true JPS59173420A (en) | 1984-10-01 |
JPS6254931B2 JPS6254931B2 (en) | 1987-11-17 |
Family
ID=12714920
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP4528183A Granted JPS59173420A (en) | 1983-03-19 | 1983-03-19 | On-site driving reinforced concrete pile and its construction |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS59173420A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2011038266A (en) * | 2009-08-07 | 2011-02-24 | Hisahiro Hiraishi | Precast pile head joint and method for constructing pile head section |
US10316469B2 (en) | 2014-12-16 | 2019-06-11 | Ecolab Usa Inc. | On-line control and reaction process for pH adjustment |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS57119838U (en) * | 1981-01-20 | 1982-07-26 |
-
1983
- 1983-03-19 JP JP4528183A patent/JPS59173420A/en active Granted
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS57119838U (en) * | 1981-01-20 | 1982-07-26 |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2011038266A (en) * | 2009-08-07 | 2011-02-24 | Hisahiro Hiraishi | Precast pile head joint and method for constructing pile head section |
US10316469B2 (en) | 2014-12-16 | 2019-06-11 | Ecolab Usa Inc. | On-line control and reaction process for pH adjustment |
Also Published As
Publication number | Publication date |
---|---|
JPS6254931B2 (en) | 1987-11-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPS6327488B2 (en) | ||
JP4502444B2 (en) | Pile head processing method in the construction method of cast-in-place concrete pile and formwork for pile head processing of cast-in-place concrete pile | |
JPS59173420A (en) | On-site driving reinforced concrete pile and its construction | |
JP2001348866A (en) | Work execution method for cast-in-place steel pipe concrete pile by all-casing construction method | |
JPH09324422A (en) | Cast-in-place compound pile and building method therefor | |
JPS6250516A (en) | Formation work of composite pile | |
JPH0721196B2 (en) | Reverse construction method of underground structure | |
JP2693027B2 (en) | Pile head treatment method for cast-in-place concrete pile | |
JPS60141919A (en) | Method of building continuous pillar-shaped landslide protection wall | |
JPS5920822B2 (en) | Seismic reinforcement method for embankments | |
JP2558414B2 (en) | Construction method of the main retaining wall and the retaining wall | |
JP3637945B2 (en) | Construction method of base-isolated building by reverse driving method | |
JPS6059223A (en) | Treatment of head of cast-in-place pile | |
JPH042134B2 (en) | ||
JPS5996393A (en) | Construction of hollow cavity | |
JPH0632983Y2 (en) | Concrete pile | |
JPH073781A (en) | Method for constructing foundation footing on cast-in-place concrete pile head | |
JPS62236916A (en) | Treater for extra-banking portion of in-situ concrete pile | |
JP2675858B2 (en) | Vertical shaft excavation method | |
JPS6220512Y2 (en) | ||
JPH04238913A (en) | Non-reinforced in-situ concrete pile and its manufacture | |
JPH09291531A (en) | Method and tool for disposing of extra-banking concrete of driven-in-place pile | |
JPS5948519A (en) | Treatment for end part of reinforced concrete structure | |
JP2551976Y2 (en) | A recess forming tool for fitting a reinforcing bar into the top of a cast-in-place concrete pile | |
JPS6161000A (en) | Building of garage |