JPS5910622A - Manufacture of concrete foundation structure - Google Patents

Manufacture of concrete foundation structure

Info

Publication number
JPS5910622A
JPS5910622A JP11766782A JP11766782A JPS5910622A JP S5910622 A JPS5910622 A JP S5910622A JP 11766782 A JP11766782 A JP 11766782A JP 11766782 A JP11766782 A JP 11766782A JP S5910622 A JPS5910622 A JP S5910622A
Authority
JP
Japan
Prior art keywords
concrete
frame
rope
manufacturing
legs
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP11766782A
Other languages
Japanese (ja)
Inventor
Keiichi Tanimura
谷村 圭一
Taizo Sugimoto
杉本 泰三
Yasuhiro Mizuno
水野 保浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Carbide Industries Co Inc
Original Assignee
Nippon Carbide Industries Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Carbide Industries Co Inc filed Critical Nippon Carbide Industries Co Inc
Priority to JP11766782A priority Critical patent/JPS5910622A/en
Publication of JPS5910622A publication Critical patent/JPS5910622A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys

Abstract

PURPOSE:To simplify operation processes on site by a method in which a caged frame is produced, the periphery of the caged frame is covered with a net, and concrete is placed into the caged frame. CONSTITUTION:In the manufacture of a concrete foundation structure for fixing the legs of a high-tension power transmission line tower, for example, a hole 2 is drilled, a supporting beam 3 for the steel tower is set at a given height by using cobble stones 4 or concrete blocks 5, the legs 1 of the steel tower are attached to the beam 3 and fixed with a temporary strut 6. A leveling concrete 7 is placed to a depth at which the beam 3 is buried adn hardened, and four one-split rings 8 are fixed to the periphery of the legs 1 of the steel tower through the temporary strut 6. Furthermore, 12 steel pipes 9 are fixed at equal intervals along the periphery of four rings 8 to complete a caged frame, as shown by Fig. The whole side of the caged frame is covered with a net 11 to form a tight net covering, and concrete is placed into the upper opening of the caged frame.

Description

【発明の詳細な説明】 本発明は商用送電鉄塔の脚部固定用構造物等のコンクリ
ート基礎構造物の製法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for manufacturing concrete foundation structures such as structures for fixing the legs of commercial power transmission towers.

従来より一般に用いられているコンクリート構造物の製
造法としては、コンクリート用型枠として木材パネル、
鉄拳あるいは合成樹脂等のユニット型枠を用い所望の形
状に組立てたのち、該型枠中にコンクリートを打設する
方法がとられているが、欠点として施工現場におけるこ
れらの型枠の組立て、取外しには非常な手間が必要で、
該型枠の作成には多l力資拐を施工現場へ輸゛送する必
要があって、輸送費が大きく友る問題や、更に複雑な形
状の型枠の作成および組立て等には熟練者を必要とする
問題等があった。
Conventionally, methods for manufacturing concrete structures that have been commonly used include wood panels as formwork for concrete;
The method used is to assemble unit formwork of iron fist or synthetic resin into the desired shape and then pour concrete into the formwork, but the drawback is that it is difficult to assemble and remove these formworks at the construction site. requires a great deal of effort,
In order to create the formwork, it is necessary to transport a large amount of material to the construction site, which increases transportation costs, and requires skilled workers to create and assemble formwork with more complex shapes. There were problems that required .

特に、電力を輸送する送電線用鉄塔のや1設あるいは改
修等の工事では、平地よりも山岳部の施工が多く、なか
でも高圧送電線用鉄塔の工事では山間僻地の施工が極め
て多い。従って該工事においては、必要な資材を輸送す
るのが極めて困難で、通常地上からの運搬が困難なため
に資材輸送はヘリコプタ−等の壁中輸送に頼っているの
が現状である。また、これら鉄塔工事の施工は平地のそ
れと同じで、資材運搬から始まり地盤の掘削、捨てコン
クリート打ち、複雑な形状の型枠組み、コンクリート打
設、型枠の取外し、埋戻し1回収した型枠の手入れ1次
の工事地区への輸送等の多大な労力と時間も必要である
In particular, construction work for installing or renovating power transmission line towers that transport electricity is more often carried out in mountainous areas than in flat areas, and in particular, construction work for high-voltage power transmission line towers is extremely common in remote mountainous areas. Therefore, in the construction work, it is extremely difficult to transport the necessary materials, and since transport from the ground is usually difficult, the current situation is that material transport relies on intra-wall transport such as helicopters. In addition, the construction of these steel towers is the same as that on flat land, starting with material transportation, excavating the ground, pouring concrete, forming formwork with complex shapes, pouring concrete, removing formwork, backfilling, and removing the recovered formwork. A great deal of labor and time is also required for transportation to the construction area for the first stage of maintenance.

本発明者等は2等従来法の間四点を解決するため種々研
究を重ねた結果、筆状枠を作り5次いで枠の外周にフィ
ルムを幾重(一般には約10重)にも巻きつけて、その
中にコンクリ−)1打設する等という簡便な方法を発明
した(特開昭55−521429号、特開昭56−39
266号及び特之等の方法は一部実用化に移されつつあ
るが。
The inventors of the present invention conducted various studies to solve the four problems of the second conventional method, and as a result, they created a brush-shaped frame and then wrapped the film around the outer circumference of the frame many times (generally about 10 times). , invented a simple method of pouring concrete (1980-521429, 1982-39).
Some of the methods of No. 266 and Tokuyuki are being put into practical use.

その段1偕で箔状枠にフィルムを幾重にも巻きつける作
業性、一般に作業の足場がよくない事が多いことから困
難な作業を長時間続けるどとを余畔なくさり、、tな、
巻きつけられたフイ、′ルムもメクレ易く目、つコンク
リート打設時その重#による側圧で下方のフィルム程上
方へズリ上る(滑り上る)傾向があり、この様な欠陥を
防止するため現場作業の工程は、当初期待された程軽減
されないのが実情であった。
In the first step, the workability of wrapping the film around the foil frame several times, which is difficult to do for a long time because the footing for work is often not good, is avoided.
Wrapped films and lumes are also prone to tearing, and when concrete is poured, the lower the film tends to slide upward due to the lateral pressure due to its weight, so to prevent such defects, on-site work must be carried out. The reality is that the process has not been reduced as much as initially expected.

%に巻きつけられたフィルムのメクレの問題や。The problem of messing up the film wrapped around the %.

またコンクリート打設時のコンクリート重址圧による下
方フィルムの上方へのズリ上りの問題は。
There is also the problem of upward shearing of the lower film due to the heavy concrete bearing pressure during concrete pouring.

打設コンクリートの漏洩を招くので避けられねばならな
い。この様な問題は、高圧送電線用鉄塔の脚部固定用の
構造物等の場合、その構造物は数頭円錐形又は数頭多角
錐形であって、フィルムのメクレとズリ上りが起き易く
、更に構造物は水平線に対(2て約10度傾斜している
ので、打設コンクリートの爪量圧が一部に集中するため
に下方フィルムの上方へのズリ上りが起き易いので1%
llIc重要な問題であった。
This must be avoided as it may lead to leakage of poured concrete. Such problems arise in the case of structures for fixing the legs of high-voltage transmission line towers, etc., where the structure is in the shape of a cone with several heads or a polygonal pyramid with several heads, making it easy for the film to bend and slip. Furthermore, since the structure is inclined at an angle of about 10 degrees with respect to the horizontal line, the pressure of the nails of the poured concrete is concentrated in one part, making it easy for the lower film to slide upward.
This was an important issue.

本発明のコンクリート基礎構造物の製法は、従来法の上
記のような問題点ト解決するものである。
The method of manufacturing a concrete foundation structure of the present invention solves the above-mentioned problems of the conventional method.

本発明の製法は、筆状枠を作り、載枠の外岑を綱で被覆
して、その中にコンクリート金打設すること¥特徴とす
るコンクリート基?#栴造物の製法である。
The manufacturing method of the present invention is to make a brush-shaped frame, cover the outer shell of the frame with a rope, and pour concrete into the frame. #This is the manufacturing method of Senzomono.

本発明の筆状枠とは、目的とするコンクリート基礎構造
物の外形′f:棒状、線状、雀状、板状等の任意適宜な
形状の材料を用いて筆状に形成させたもので、その−同
として高圧送11L線鉄塔の脚部固定用基礎構造物に用
いる賭状枠を図−3に示した。
The brush-shaped frame of the present invention is formed into a brush-like shape by using a material having an arbitrary shape such as a rod, a line, a sparrow, or a plate. Similarly, Figure 3 shows a stake-shaped frame used for the foundation structure for fixing the legs of a high-pressure transmission 11L line steel tower.

即ち、筆状枠(よ、その外周全綱で被覆後、その中にコ
ンクリートを打設した場合、コンクリートの硬化迄、 
Ff+定の形状を保つのに十分な強度を有すれば、どの
ような材料を用いてもよい。簸状枠の材料としては強度
及び価格の点より一般に鉄製が好ましいが、鉄製に限定
されるものではない。
In other words, if concrete is placed inside the brush-shaped frame after its entire circumference is covered with rope, until the concrete hardens,
Any material may be used as long as it has sufficient strength to maintain the constant Ff+ shape. In terms of strength and cost, it is generally preferable to use iron as the material for the elongated frame, but the material is not limited to iron.

本発明で用いる綱は、筆状粋の外周を被覆し、その中に
コンフリートラ打設した場合、実質的々コンクリートの
漏洩がなく、マたコンクリート重量の側圧によって膨張
乃至破損しないような綱であれば、どのような綱であっ
ても制限なく使用することが出来る。このような綱とし
ては、目開きが約0.5〜25朋、好ましくは約1〜1
0m+c、最も好ましくは約2〜5 m+mの絹が使用
される。目開きが0.5朋未満と小さ過ぎては、綱目全
通して水   ・が排出されにくいので好ましくなく、
一方25mmを超えて大き過ぎてtよ打設時コンクリー
トの漏洩が多くなるので好ましくない。
The rope used in the present invention is a rope that covers the outer periphery of the brush-like shape and, when a comfleet track is placed inside, there is virtually no leakage of concrete, and the rope does not expand or break due to the lateral pressure of the weight of the concrete. If so, any type of rope can be used without restriction. Such a rope has a mesh opening of about 0.5 to 25 mm, preferably about 1 to 1 mm.
0 m+c, most preferably about 2-5 m+m silk is used. If the opening is too small (less than 0.5 mm), water will be difficult to drain through the entire rope, which is undesirable.
On the other hand, if it is too large, exceeding 25 mm, concrete will leak more frequently during pouring, which is not preferable.

また本発明で用いられる綱は、綱を形成している絹糸の
坤び率が50%以下好ましくf″i、40%以FであI
7.呻び率が50%を超えて大きすぎては。
In addition, in the rope used in the present invention, the elasticity of the silk thread forming the rope is preferably 50% or less, f″i, 40% or more, and I
7. If the groaning rate exceeds 50%, it's too loud.

打設時に側圧により変形し易く構造物の寸法精度が出に
くいので好ましくない。このよう々絹糸の@質としては
、ポリエステル系、ナイロン系、アクリル系、ビニロン
系、ポリプロピレン系、ポリエチレン系等の合成樹脂或
いは麻や木綿等の天然繊維材料のものが使用され5更に
或いは芯にポリエステル等の合成繊維に塩ビ等の熱可塑
性樹脂被覆層を有する複合系の絹糸が好適に用いられる
This is undesirable because it is easily deformed by lateral pressure during pouring, making it difficult to achieve dimensional accuracy of the structure. As for the quality of silk thread, synthetic resins such as polyester, nylon, acrylic, vinylon, polypropylene, and polyethylene, or natural fibers such as hemp and cotton are used. A composite silk thread having a synthetic fiber such as polyester and a thermoplastic resin coating layer such as vinyl chloride is preferably used.

また金網板も好適に用いることができる。Moreover, a wire mesh plate can also be suitably used.

本明細書に絹糸の坤び率とは、JIS  z、t。In this specification, the elasticity of silk thread refers to JIS z, t.

69に準じ、下記のように測定した値をいう。巾5龍長
さ30鮎の紙片に、9間距離20龍に絹糸をゆるく張っ
た状態で、両端を接着剤で固定し。
69, the value measured as follows. A piece of paper with a width of 5 long and a length of 30 long is loosely stretched with silk thread at a distance of 9 and 20 long, and both ends are fixed with adhesive.

試験片を作成し、定速緊張形の単繊維引張試験機を使用
し引張速度20土1龍/分で引つり長り切断時の伸び(
闘)全測定し1次式により叶び率を求めた。
A test piece was prepared, and the elongation at length and cutting was measured using a constant speed tension type single fiber tensile tester at a tensile speed of 20 mm/min.
) All measurements were taken and the success rate was calculated using the linear equation.

但しこ\でE、:ゆるみ(朋) E2 :切断時の伸び(龍) 本発明で「絹糸」なる語は、モノフィラメント(繊維)
、ヤーン(糸)や紐、針金等の綱を形成する種々の太さ
の線状材料全総称する意味で用いられるものである。こ
れ等締1糸の太さは好ましくは05〜2w1I11.最
も好ましく f′i0.5〜1 龍のものが用いられる
However, E: Looseness (tomo) E2: Elongation upon cutting (dragon) In the present invention, the term "silk thread" refers to monofilament (fiber).
, is used to collectively refer to all linear materials of various thicknesses that form ropes such as yarns, strings, and wires. The thickness of each tightening thread is preferably 05 to 2w1I11. Most preferably, those having an f'i of 0.5 to 1 are used.

怜状枠を綱で被挿する方法は、筒状枠の側部全面を絹で
タイトに一重被情する方法であればどの様な方法でも採
用されるが、好ましくは2〜5m(13の綱1に@状粋
の側面の展開図形に若干の重ね代ケ加えた形に予め切断
し、これを筒状枠に巻きつけ、irね代部分を1層の綱
と針金等で結びつけて固定することによって行なわれる
。必要な場合には、被覆した綱の全面全豹20〜40c
m間隔でポリプロバンド等で更に緊縛してもよい。
Any method can be used to insert the cylindrical frame with a rope, as long as the entire side surface of the cylindrical frame is wrapped tightly with silk, but it is preferably 2 to 5 m (13 mm). Cut the rope 1 in advance into a shape with a slight overlap added to the developed figure on the side of the @ shape, wrap it around a cylindrical frame, and tie the irradiation allowance to the first layer of rope with wire etc. to fix it. If necessary, the whole surface of the covered rope should be 20 to 40 cm long.
It may be further bound with polypropylene bands or the like at intervals of m.

以下に実施例に従って本発明の詳細を第1〜5図を参照
に説明する。本発明によって高圧送電線鉄塔の脚部固定
用コンクリート基礎構造物(高さ3、6 m 、上部径
0.7 mφ、下部径1.28 mφ)を製造する場合
、第1図のように先づ5.5 m長さの鉄塔脚部1を埋
めるための4.1 m深さの穴2を掘る。次いで十字形
の鉄塔支持材ネコ3を所定の高さになるよう栗石4及び
コンクリートブロック5で刺節し、次いでネコ3の上に
鉄塔脚部l全敗りつけて脚部が水平に対し所定の傾斜角
lO°になるよう正確に仮止支柱6で鉄塔脚部を固定す
る。
The details of the present invention will be explained below according to examples with reference to FIGS. 1 to 5. When manufacturing a concrete foundation structure for fixing the legs of a high-voltage power transmission line tower (height 3.6 m, upper diameter 0.7 mφ, lower diameter 1.28 mφ) according to the present invention, the first step is as shown in Fig. 1. Dig a hole 2 4.1 m deep to bury the 5.5 m long tower leg 1. Next, the cross-shaped steel tower supporting material cat 3 is pierced with chestnut stones 4 and concrete blocks 5 to a predetermined height, and then the steel tower legs l are completely laid down on top of the cat 3 so that the legs are horizontal to the predetermined height. The legs of the steel tower are accurately fixed with temporary support columns 6 so that the inclination angle is 10°.

次いでネコ3が埋まる深さに捨てコンクリート7を拐ち
一日以上故一して硬化させる。
Next, the concrete 7 is dumped to a depth where the cat 3 is buried, and the concrete 7 is allowed to stand for more than a day to harden.

次いで鉄塔脚部1の周りに第2図(斜視図)のように4
箇の1つ割りリング8(ljJ3cm厚さ2.5龍のス
チル−・ぐンド)を仮止支柱6ゲ〈マらせて鉄柱脚部l
に固定する。それが終ったならば、4分の鉄ノやイブ9
の12本を上記4ケのリング外周に沿って等間隔に固定
し、紀3図(模式図)のような咽状枠f:完成する。な
お、この際、各鉄/Pイブ9の最下端近くには綱のズリ
上り防11−の為の滑り市め機h1ヒケ持たせるため第
4図のように2ケの鍔10を設けた。
Next, as shown in Figure 2 (perspective view), 4
Attach the split ring 8 (ljJ3cm thickness 2.5 dragon steel gundo) to the temporary support post 6 and attach it to the steel column leg l.
Fixed to. Once that is finished, 4 minutes of Tetsunoya Eve 9
Twelve rings are fixed at equal intervals along the outer periphery of the four rings, and the throat-shaped frame f as shown in Figure 3 (schematic diagram) is completed. At this time, two tsuba 10 were installed near the bottom end of each iron/pipe 9 as shown in Fig. 4 in order to have a slippery machine h1 sink to prevent the rope from slipping 11-. .

このように出来上った筒状枠の側面に、予め奄状伜11
1!l而の展開図にmね代を加えた形に切謔1してあっ
た綱11を巻きつけ5重ね代部分で−「の綱と針金で適
宜結びつけることにより、触状伜の側部全面に第5図の
ようにタイトな綱被覆を形成させた。使用した系間は塩
ビ被援ポリエステルの融着ネットで絹糸の太さ岐約1m
、沖び率30%、目開き約2m、重量0、tskg/ゴ
、空間率47%のものであった。
On the side of the cylindrical frame completed in this way, a mark of 11
1! Wrap the cut rope 11 in the shape of the expanded view of 1 and add m lenght, and connect the 5 rope and wire appropriately at the 5 overlap part to make the entire side of the tactile part. A tight rope covering was formed as shown in Figure 5.The system used was a fusion net of PVC-covered polyester, and the thickness of the silk thread was approximately 1 m.
, an openness ratio of 30%, an opening of about 2 m, a weight of 0, tskg/go, and a void ratio of 47%.

このようにして出来上った亀状粋にはこのま\」一部間
口部よりコンクリート’tri股してもよいが。
The turtle-like appearance created in this way may be covered with concrete from part of the frontage.

本実施例では地上部に出る構造物の外形をより整えるた
め、地上部に出る枠の上部にだけ、型枠と同一傾斜を有
するPEP型枠12を綱級覆の上に更にかぶせ、その後
早硬化性コンクリートを打設した。コンクリ−ト打設時
は、先日来の降雨のため穴2の中には約50σの水が溜
まっていたが。
In this example, in order to improve the external shape of the structure that appears above the ground, a PEP formwork 12 having the same slope as the formwork is further covered over the rope cover only on the upper part of the frame that appears above the ground, and then quickly Hardening concrete was poured. At the time of concrete pouring, approximately 50σ of water had accumulated in hole 2 due to recent rainfall.

コンクリートは綱目より漏洩することは殆んど無かった
。またコンクリート打設時充填状況を網目ケ通じ肉眼或
いは触手によって直接判断することが可能であった。
There was almost no leakage from the concrete through the rope. In addition, it was possible to directly judge the filling status during concrete placement with the naked eye or feel through the mesh.

コンクリートが十分硬化後、上部のFRP型枠金取り除
き穴2を埋め戻して、コンクリート基礎構造物を児成し
た。得られた構造物は、従来工法から得られた構造物に
較べ何等の遜色の無いものであった。
After the concrete had sufficiently hardened, the upper FRP form metal removal hole 2 was backfilled to form a concrete foundation structure. The obtained structure was in no way inferior to structures obtained using conventional construction methods.

上記実施例よりも明らかなように1本発明のコンクリー
ト基礎構造物の製法は、運搬容易な材料のみを用い、足
場の悪い施工埃場でも型枠組立作業が容易であり、更に
特開昭55−52429号のようにフィルムを多重巻き
する必観もないので、それに曹する作業時間は全く要せ
ず、晶価なフィルムの使用も無いので拐科費1−1.節
減される等の長ハrTh有するものである。また1本発
明でtまコンクリート打設時に綱L」をフ1旦じてt]
設状況が直接点検出来ることや、卸i目ケ)市じ−C水
1友さが容易に行なわれる利益を有する。更に本発明の
大きい長r9rは水中打設が有利に行なえることで、綱
目を進じてのコンクリート中の水分の有効な拡11ダに
基づくものと推定される。
As is clear from the above examples, the method for manufacturing concrete foundation structures of the present invention uses only materials that are easy to transport, and forms can be easily assembled even in dusty construction sites with poor footing. There is no need to wind the film multiple times as in No. 52429, so there is no additional work time required, and there is no need to use expensive film, so the cost is 1-1. It has a long h rTh such as saving. In addition, with the present invention, the rope L is suspended once when concrete is poured.
It has the benefit of being able to directly inspect the installation status and making wholesale inspections easier. Furthermore, it is presumed that the large length r9r of the present invention is based on the fact that underwater casting can be advantageously carried out, and the water content in the concrete can be effectively spread as the concrete progresses through the wire.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図〜第5図は高圧送電線鉄塔の脚部固定用コンクリ
ート構造物を作る本発明の製法の1例を示すものであり
、第1図は鉄塔脚部lを穴2に10°の傾斜角度で固定
している状況を示す断面図である。第2図は鉄塔脚部l
を中心にリング8ケとりつけ筆状枠紮作りつ\ある状況
透水ず斜視図である。第3図は出来上った艙状粋の斜視
模式図である。第4図は輛状枠の下部Vこズリ上り止め
用のため6けた鍔10を示ず拡太斜祝図である。 第5図Vi龜状粋に絹11を被俺し更に上部にFRP型
枠12を設けたコンクリート打設面MiJの型枠の11
而図である。 (ほか3名) 手続補正書(自発) 昭和57年8 月17日 特許庁長官  若 杉和 夫 殿 11iVPlノit 小 昭和57年時、n顕第117667号 2発明の名ゼ■・ コ/りIJ −ト基礎構造物の#遣方法3 紬11をす
る名 事(1−の関係  特許出願人 111すi  r−京都千代田区丸の白玉丁目3番1号
4代 理 人〒10フ イ1  所   東京都港区赤坂1丁目9番15号別紙 (1)明細僅の特許請求の範囲の欄の記載を以下のとお
り訂正する。 r〔(P♀rF請求の範囲〕 1、筆状枠金作り、載枠の外周ケ網で被覆し、その中に
コンクリートケ打設することを的徴とするコンクIJ 
−ト基礎F4造物の製法。 2 網の目開きが約05〜25mである特許jf!求の
哩1用弔1項記載の製法。 3イjak形成する絹糸の伸び率が50%以)−である
特許請求の範囲第1項又は第2項記載専の製法。 4、絹糸が合成樹脂製網糸である特許請求の範囲第1項
〜第3項の何れかに言「シ載の製法。 5 水中打設で行なわれる車f訂請求の幀囲第1項〜編
4項の何れかに口[°、載の製法。 6、 基礎構造物が高圧送電線鉄塔の脚部固疋月]コノ
クリート基1涜rrlti青物jである時ff(’呂ず
1求の範囲第1項〜・A5瑣、)中域の縛法。」(2)
  明・l111書の・10貞・π9竹、FJ”、 6
頁第1行、第7行、第10有、I臂へ11行、第12行
及び第14行、第7自第12行、第8日第9111第1
4行及第15イゴ、 第 9 自記 l 7テ、 第 
3行及び4) 5イ丁、 第10頁第1Oイ■及び単1
5行、小11自第1何及び第13自第12行にり、g」
とあイ)?i−1「 網 」 にnl’、+E−f石つ (31同第7頁第3行、第6行、第12有、第14イ■
及第16何1.、f48自記8行及第1I行、l君11
自・菖2イ■vc、J綱糸]とあるを、「 網糸 」 にlltヒする。 (4)  同第6自ドから3行、第11頁第13付及第
14何、l貼12自第13行、第14何及び第16行に
「綱目」とある會 「64目 」 に訂正する。 (5)同第7自第13イIに[全綱$21とあるを、「
 金網板 」 に@J’ 、iEする。 (6)第10頁末行及第11向第9行に「綱破情」とあ
る?、 「 網被援 」 に訂正する。
Figures 1 to 5 show an example of the manufacturing method of the present invention for making a concrete structure for fixing the legs of a high-voltage power transmission tower. FIG. 3 is a cross-sectional view showing a situation in which it is fixed at an inclination angle. Figure 2 shows the tower leg l.
This is a perspective view of a situation in which a brush-shaped frame ligature is being made with eight rings attached to the center without water permeability. Figure 3 is a schematic perspective view of the completed boat. FIG. 4 is an enlarged perspective view that does not show the six-digit collar 10, which is used to prevent the lower V of the frame from rising. Fig. 5 Vi The formwork 11 of the concrete pouring surface MiJ, which is covered with silk 11 and further provided with the FRP formwork 12 on the top.
This is a diagram. (3 others) Procedural amendment (voluntary) August 17, 1980 Commissioner of the Japan Patent Office Kazuo Wakasugi 11iVPlnoit 1980, nken No. 117667 2 Name of the invention IJ - How to use #3 for basic structures 3 Famous events of playing Tsumugi 11 (Relation to 1) Patent applicant 111Sir - 4th generation, 3-1, Shiratama-chome, Maruno, Chiyoda-ku, Kyoto, 10th floor, 1st place 1-9-15 Akasaka, Minato-ku, Tokyo Attachment (1) The statement in the scope of claims column with a small specification is corrected as follows: r [(P♀rF Claims)] 1. Brush-shaped frame metal making , concrete IJ, which is characterized by covering the outer periphery of the mounting frame with a net and pouring concrete into it.
- Method for manufacturing basic F4 structures. 2 Patent jf where the mesh opening is approximately 05 to 25 m! The manufacturing method described in Paragraph 1 of the ``Soul of Hope''. 3. The manufacturing method according to claim 1 or 2, wherein the elongation rate of the silk thread to be formed is 50% or more. 4. The manufacturing method described in any one of claims 1 to 3, in which the silk thread is a synthetic resin net thread. 6. When the foundation structure is made of conocrete based on the legs of a high-voltage power transmission tower, Range 1st term ~・A5 D,) Middle range binding method.'' (2)
Ming 111 book 10 Tei π9 Bamboo, FJ”, 6
Page 1st line, 7th line, 10th line, 11th line to I arm, 12th line and 14th line, 7th page 12th line, 8th day, 9111, 1st
4th line and 15th Igo, 9th autobiography l 7th, 1st
3rd line and 4) 5th I, page 10, 1st Oi ■ and single 1
5th row, the 1st row of the 11th grade student and the 12th row of the 13th student, g.
Toai)? i-1 "net", nl', +E-f stone (31, page 7, line 3, line 6, 12th, 14th i)
16th and 1st. , f48 self-written line 8 and line 1I, l-kun 11
Self・Iris 2i ■vc, J rope thread] is llt into ``net thread''. (4) 3 lines from the 6th C, page 11, appendix 13, 14th, 1st page, 12th line, 13th, 14th, and 16th line, "64" correct. (5) In the same 7th car, 13th I, [all ropes $21] was changed to ``
@J', iE on the wire mesh board. (6) Does it say "Tsunahajo" on the last line of page 10 and the 9th line of the 11th direction? , corrected to ``net assistance''.

Claims (1)

【特許請求の範囲】 1、南状枠を作り、載枠の外周を綱で被覆し。 その中にコンクリ−)1打設することを特徴とするコン
クIJ −ト基礎構造物の製法。 2 綱の目開きが約0.5〜25宵諷である特許請求の
範囲第1項記載の製法。 3、綱を形成する絹糸の呻び率が50%以下である特許
請求の範囲第1項又は第2項記載の製法。 4、絹糸が合成樹脂製絹糸である特許請求の範囲第1項
〜第3項の倒れかに記載の製法。 5 水中打設で行なわれる特許請求の範囲第1項〜第4
項の何れかに記載の製法。 6、基礎構造物が高圧送電線鉄塔の脚部固定用コンクI
J −ト基礎構造物である特許請求の範囲第1項〜第5
項記載の製法。
[Claims] 1. Make a southern frame and cover the outer periphery of the frame with rope. A method for manufacturing a concrete IJ-contact foundation structure, characterized by pouring concrete (1) therein. 2. The manufacturing method according to claim 1, wherein the rope has a mesh opening of about 0.5 to 25 mm. 3. The manufacturing method according to claim 1 or 2, wherein the silk thread forming the rope has a writhing ratio of 50% or less. 4. The manufacturing method according to claims 1 to 3, wherein the silk thread is a synthetic resin silk thread. 5 Claims 1 to 4 that are performed by underwater casting
The manufacturing method described in any of the paragraphs. 6. The foundation structure is concrete I for fixing the legs of high-voltage transmission line towers.
J-Claims 1 to 5 which are foundation structures
Manufacturing method described in section.
JP11766782A 1982-07-08 1982-07-08 Manufacture of concrete foundation structure Pending JPS5910622A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11766782A JPS5910622A (en) 1982-07-08 1982-07-08 Manufacture of concrete foundation structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11766782A JPS5910622A (en) 1982-07-08 1982-07-08 Manufacture of concrete foundation structure

Publications (1)

Publication Number Publication Date
JPS5910622A true JPS5910622A (en) 1984-01-20

Family

ID=14717298

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11766782A Pending JPS5910622A (en) 1982-07-08 1982-07-08 Manufacture of concrete foundation structure

Country Status (1)

Country Link
JP (1) JPS5910622A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104514225A (en) * 2015-01-09 2015-04-15 国家电网公司 Power transmission line tower footing anti-distortion energy absorbing structure in mining area and anti-distortion energy absorbing method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104514225A (en) * 2015-01-09 2015-04-15 国家电网公司 Power transmission line tower footing anti-distortion energy absorbing structure in mining area and anti-distortion energy absorbing method

Similar Documents

Publication Publication Date Title
US3650112A (en) Method of shoring and apparatus therefor
US3934422A (en) Pile splicing apparatus and method
JP2022135486A (en) Support erection structure
CN106400783B (en) The construction method of bored concrete pile is made of expansion steel reinforcement cage
JP3954414B2 (en) Protective body using net
JPS5910622A (en) Manufacture of concrete foundation structure
CN204876609U (en) Foundation ditch sleet system of shielding
US4126001A (en) Method for constructing a soil structure
US3256694A (en) Structural piles and methods of preparing pipe foundations
JPH07292675A (en) Slope protection structure
KR101140876B1 (en) Installation device of stake type wood pole and method using the same
JP2010255229A (en) Slope protection method and slope protection structure
JPH02219527A (en) Method for supporting and planting tree
JPH0813502A (en) Cut slope face stabilizing construction method
JP3096424B2 (en) Vegetation infrastructure construction method
CH621174A5 (en) Method of constructing a retaining wall and set of structural parts for carrying out this method
JP4071664B2 (en) Slope protection method
JPS58123924A (en) Protecting method for slope
JPS58156631A (en) Slope protection work
US7618216B1 (en) Faultline fearless nanotube homes
JP3508875B2 (en) Continuous wall method
JPS5931610B2 (en) Reinforced slope protection method
JPH04213605A (en) Construction of diagonal member of stay panel bridge
SU912896A1 (en) Rope fence for protecting power transmission line mast from ice
JPH05260862A (en) Construction for supporting tree