JPS5910267Y2 - temporary scaffolding structure - Google Patents

temporary scaffolding structure

Info

Publication number
JPS5910267Y2
JPS5910267Y2 JP2740780U JP2740780U JPS5910267Y2 JP S5910267 Y2 JPS5910267 Y2 JP S5910267Y2 JP 2740780 U JP2740780 U JP 2740780U JP 2740780 U JP2740780 U JP 2740780U JP S5910267 Y2 JPS5910267 Y2 JP S5910267Y2
Authority
JP
Japan
Prior art keywords
pipe
scaffold
building
frame
bracket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP2740780U
Other languages
Japanese (ja)
Other versions
JPS56129462U (en
Inventor
徳夫 米谷
俊昭 河野
Original Assignee
株式会社国元商会
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社国元商会 filed Critical 株式会社国元商会
Priority to JP2740780U priority Critical patent/JPS5910267Y2/en
Publication of JPS56129462U publication Critical patent/JPS56129462U/ja
Application granted granted Critical
Publication of JPS5910267Y2 publication Critical patent/JPS5910267Y2/en
Expired legal-status Critical Current

Links

Landscapes

  • Movable Scaffolding (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

【考案の詳細な説明】 本考案は、建築中の建物外壁にそって仮設する外装工事
等のための仮設足場構造に関するものであって、隣接建
造物との間の空間が狭い場合に使用する単管利用の足場
上に幅の広い枠組足場を連設した仮設足場を提供するも
のである。
[Detailed description of the invention] This invention relates to a temporary scaffold structure for exterior work, etc. that is temporarily installed along the outer wall of a building under construction, and is used when the space between it and an adjacent building is narrow. This provides temporary scaffolding, which consists of a wide framework scaffolding connected to a single-pipe scaffolding.

以下本考案の一実施例を添付の例示図に基づいて説明す
ると、第1図は使用する建枠支持ブラケット1を示し、
このブラケット1は、上端が同一レベルに位置するよう
に水平材2と斜材3とで互に連結した長尺縦パイプ4と
短尺縦パイプ5とから或り、略直角三角形の棚受け形状
のものである。
An embodiment of the present invention will be described below based on the attached illustrative drawings. FIG. 1 shows a building frame support bracket 1 to be used;
This bracket 1 consists of a long vertical pipe 4 and a short vertical pipe 5, which are connected to each other by a horizontal member 2 and a diagonal member 3 so that their upper ends are located at the same level. It is something.

6はねじジャッキであり、単管7の上端に内挿される軸
杆部8と、単管7の上端に当接する受座9と、この受座
9から突出し且つブラケット1の長尺縦パイプ4の下端
に内挿されるねじ軸部10と、このねじ軸部10に螺嵌
され且つ前記長尺縦パイプ4の下端を支持するハンドル
付き雌ねじ体11とから構戊されている。
Reference numeral 6 designates a screw jack, which has a shaft portion 8 inserted into the upper end of the single pipe 7, a catch 9 that abuts the upper end of the single pipe 7, and a long vertical pipe 4 that protrudes from the catch 9 and is attached to the bracket 1. It consists of a threaded shaft portion 10 inserted into the lower end of the pipe, and a female threaded body 11 with a handle that is screwed into the threaded shaft portion 10 and supports the lower end of the long vertical pipe 4.

12.13は、ブラケット1の長尺縦パイプ4及び短尺
縦パイプ5と、第2図に示す枠組足場用建枠14の前後
両支柱パイプ15.16とを接続するための連結ピンで
あり、中央にストッパー用フランジ17.18を備えて
いる。
12.13 is a connecting pin for connecting the long vertical pipe 4 and short vertical pipe 5 of the bracket 1 to both the front and rear support pipes 15.16 of the scaffolding frame 14 shown in FIG. A stopper flange 17, 18 is provided in the center.

通常、単管7よりも建枠14の前後両支柱パイプ15.
16は若干小径のものが使用されている。
Normally, both the front and rear support pipes 15 of the building frame 14 are used rather than the single pipe 7.
16 is used with a slightly smaller diameter.

従って、ブラケット1の長尺縦パイプ4には単管7と同
一径のものを使用し、短尺縦パイプ5には建枠支柱パイ
プ15,16と同一径のものを使用して構或すると共に
、建枠支柱パイプ15.16の外面間の間隔とブラケッ
ト1の前後の縦パイプ4,5の外面間の間隔とが等しく
なるように構或し、さらに長尺縦パイプ4に使用する連
結ピン12のピン下部12aのみを長尺縦パイプ4に丁
度内挿し得るように大径とし、且つこの大径のピン下部
12 aに対し、建枠支柱パイプ15に内拝する小径の
ピン上部12bを若干偏心させて、長尺縦パイプ4に接
続された建枠支柱パイプ15の外面が長尺縦パイプ4の
外面と面一になるように構或してある。
Therefore, the long vertical pipe 4 of the bracket 1 is constructed with the same diameter as the single pipe 7, and the short vertical pipe 5 is constructed with the same diameter as the frame support pipes 15, 16. , the spacing between the outer surfaces of the frame support pipes 15 and 16 is made equal to the spacing between the outer surfaces of the vertical pipes 4 and 5 at the front and rear of the bracket 1, and the connecting pins used for the long vertical pipes 4 are Only the lower part 12a of the pin 12 has a large diameter so that it can be inserted into the long vertical pipe 4, and in contrast to the lower part 12a of the large diameter pin, the upper part 12b of the small diameter pin is inserted into the frame support pipe 15. The outer surface of the building frame support pipe 15 connected to the long vertical pipe 4 is slightly eccentric so that it is flush with the outer surface of the long vertical pipe 4.

勿論、連結ピン13によってブラケット1の短尺縦パイ
プ5と建枠支柱パイプ16とが同心状に接続されるので
、連結ピン12として、上下のピン部が同心小径の連結
ピン13と同一のものを使用しても、長尺縦パイプ4と
建枠支柱パイプ15とを外面が面一となるように接続し
得る。
Of course, since the short vertical pipe 5 of the bracket 1 and the frame support pipe 16 are concentrically connected by the connecting pin 13, the connecting pin 12 should be the same as the connecting pin 13 whose upper and lower pin parts are concentric and small diameter. Even when used, the long vertical pipe 4 and the building frame support pipe 15 can be connected so that their outer surfaces are flush.

第2図及び第3図は上記のブラケット1、ねじジャッキ
6、及び連結ピン12.13とによって互に接続された
単管足場19と枠組足場28とを示し、単管足場19は
、横方向に一定間隔おきに並列された垂直な単管7が水
平方向の単管20とパイプクランプ21とにより互に連
結され、さらに必要に応じて筋違によって補強され、垂
直な単管7には足場板22を支持するブラケット23が
パイプクランク24を介して取付けられたものであって
、建物外加25に一端を結合した壁つなぎ26の外端が
垂直な単管7にパイプクランプ27で連結される事によ
り、単管足場19は建物外壁25にそって垂直に仮設さ
れている。
2 and 3 show a monotube scaffold 19 and a framework scaffold 28 connected to each other by the above-mentioned bracket 1, screw jack 6 and connecting pin 12.13, the monotube scaffold 19 being Vertical single pipes 7 arranged in parallel at regular intervals are connected to each other by horizontal single pipes 20 and pipe clamps 21, and are further reinforced with braces as necessary. A bracket 23 supporting the board 22 is attached via a pipe crank 24, and the outer end of a wall connector 26, one end of which is connected to a building exterior addition 25, is connected to a vertical single pipe 7 with a pipe clamp 27. Due to this, the single pipe scaffolding 19 is temporarily installed vertically along the outer wall 25 of the building.

枠組足場28は、前記建枠14が上下方向に連結ピンに
より接続されると共に横方向に隣り合う建枠14の横地
パイプ29間には布板(足場板)30が架設され、さら
に横方向に隣り合う建枠14の前後各支柱パイプ15間
及び16間には筋違31が介装されているものであり、
この枠組足場28はブラケット1により単管足場19上
に支持されている。
In the frame scaffolding 28, the building frames 14 are vertically connected by connecting pins, and cloth boards (scaffolding boards) 30 are constructed between horizontal pipes 29 of horizontally adjacent building frames 14, and further horizontally. Braces 31 are interposed between the front and rear support pipes 15 and 16 of adjacent building frames 14,
This framework scaffold 28 is supported on the monotube scaffold 19 by brackets 1.

即ち、単管足場19の各単管7上にねしジャッキ6の軸
杆部8を内挿し、このねじジャッキ6のねじ軸部10に
ブラケット1の長尺縦パイプ4の下端を嵌合して雌ねじ
体11上に載置し、このブラケット1の長尺縦パイプ4
上と短尺縦パイプ5上とに夫々所定の連結ピン12.1
3を介して枠組足場28の各最下端建枠14の前後両支
柱パイプ15.16を接続している。
That is, the shaft part 8 of the screw jack 6 is inserted onto each single pipe 7 of the single pipe scaffold 19, and the lower end of the long vertical pipe 4 of the bracket 1 is fitted into the threaded shaft part 10 of this screw jack 6. the long vertical pipe 4 of this bracket 1.
Predetermined connecting pins 12.1 are provided on the top and on the short vertical pipe 5, respectively.
3, both the front and rear support pipes 15 and 16 of each lowermost building frame 14 of the framework scaffolding 28 are connected.

そしてこの枠組足場28も、建物外壁25に一端を結合
した壁つなぎ32の外端が建枠14の支柱パイプ15に
パイプクランプ33で連結される事により、建物外壁2
5にそって垂直に仮設され、垂直荷重が単管足場19の
各単管7に確実に伝達されるように、各ねじジャッキ6
の雌ねじ体11を昇降調節してブラケット1の前後の縦
パイプ4,5と建枠14の前後両支柱15.16とで連
結ピン12.13のフランジ17.18を挾着させてい
る。
This frame scaffolding 28 is also connected to the building outer wall 25 by connecting the outer end of the wall joint 32, which has one end connected to the building outer wall 25, to the support pipe 15 of the building frame 14 with a pipe clamp 33.
5, each screw jack 6 is temporarily installed vertically along
The flange 17.18 of the connecting pin 12.13 is clamped between the front and rear vertical pipes 4, 5 of the bracket 1 and the front and rear supports 15,16 of the building frame 14 by adjusting the internal threaded body 11 up and down.

又、各ブラケット1間には、その水平材2間において布
板(足場板)34を架設している。
Further, between each bracket 1, a cloth board (scaffolding board) 34 is installed between the horizontal members 2.

さらに上記実施例では、ブラケット1の長尺縦パイプ4
を挾む単管7と建枠14の支柱パイプ15とにわたって
別の補助単管35を並列配置すると共に、これら単管7
,35、長尺縦パイプ4と単管35、及び建枠支柱パイ
プ15と単管35をパイプクランプ36,37.38に
て互に連結して補強している。
Furthermore, in the above embodiment, the long vertical pipe 4 of the bracket 1
Another auxiliary single pipe 35 is arranged in parallel across the single pipe 7 sandwiching the pipe 7 and the support pipe 15 of the building frame 14, and these single pipes 7
, 35, the long vertical pipe 4 and the single pipe 35, and the building frame support pipe 15 and the single pipe 35 are connected and reinforced with pipe clamps 36, 37, and 38.

以上の如く実施し得る本考案の仮設足場構造によれば、
隣接建造物との関係で作業足場全体を枠組足場とする事
ができないで、下部を幅が狭くて済む単管利用の足場と
しなければならないような場合に、上方の枠組足場を建
物外壁に大形特殊なブラケットを介して支持させなくと
も、この上方の枠組足場を下方の単管足場の垂直な単管
に支持させる事ができ、仮設足場全体のコスI・やその
組立て作業に要するコストを低減し得るのである。
According to the temporary scaffolding structure of the present invention that can be implemented as described above,
When it is not possible to use the entire work scaffold as a frame scaffold due to the relationship with an adjacent building, and the lower part must be a single-tube scaffold that is narrow, it is possible to attach the upper frame scaffold to the outer wall of the building. This upper framework scaffold can be supported by the vertical single pipe of the lower single pipe scaffold without having to support it through a special shaped bracket, reducing the cost of the entire temporary scaffold and the cost required for its assembly work. It can be reduced.

しかも介装したねしジャッキにより、上方の枠組足場の
垂直荷重を確実に下方の単管足場に伝達せしめて、枠組
足場を安全確実に支持する事ができ、従来通り適当個所
を壁つなぎで建物外壁に連結するだけで、下方単管足場
、上方枠組足場から或る安全性の高い特殊形仮設作業足
場を得る事ができるのである。
Moreover, the interposed jack jacks ensure that the vertical load of the upper frame scaffold is transferred to the lower single-pipe scaffold, allowing the frame scaffold to be safely and reliably supported. By simply connecting it to the outer wall, a special type of highly safe temporary work scaffold can be obtained from the lower single pipe scaffold and the upper frame scaffold.

尚、連結ピン12.13の代わりにねしジャッキを使用
し、ねじジャッキ6に代えて連結ピンを用いる事もでき
る。
Incidentally, a screw jack can be used instead of the connecting pins 12 and 13, and a connecting pin can be used instead of the screw jack 6.

又、単管足場19や枠組足場28の構造は図示のものに
限定されない。
Furthermore, the structures of the single tube scaffold 19 and the framework scaffold 28 are not limited to those shown in the drawings.

例えば、枠組足場28の建枠14として鳥居形のものを
示したが、矩形材状のもの、H形桟橋状のもの等、互に
水平材で連結された前後一対の支柱を有するものであれ
ば如何なるものでも良い。
For example, although a torii-shaped frame 14 is shown as the frame 14 of the framework scaffold 28, it may also be a rectangular frame, an H-shaped pier-shaped frame, or any other frame having a pair of front and rear supports connected to each other by horizontal members. Anything is fine.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本考案一実施例の要部分解側面図、第2図は本
考案一実施例の側面図、第3図は同縦断正面図である。 1・・・・・・建枠支持ブラケット、6・・・・・・ね
じジャッキ、7・・・・・・単管、12.13・・・・
・・連結ピン、14・・・・・・建枠、15,16・・
・・・・建枠前後支柱パイプ、19・・・・・・単管足
場、22・・・・・・足場板、23・・・・・・足場板
支持ブラケット、26,32・・・・・・壁つなぎ、2
8・・・・・・枠組足場、30 .34・・・・・・布
板(足場板)、35・・・・・・補助単管、21 ,2
7,33.36〜38・・・・・・パイプクランプ。
FIG. 1 is an exploded side view of a main part of an embodiment of the present invention, FIG. 2 is a side view of an embodiment of the present invention, and FIG. 3 is a longitudinal sectional front view of the same. 1... Building frame support bracket, 6... Screw jack, 7... Single pipe, 12.13...
...Connecting pin, 14... Building frame, 15, 16...
...Front and rear support pipes for building frame, 19...Single tube scaffolding, 22...Scaffolding board, 23...Scaffolding board support bracket, 26,32...・Wall connection, 2
8...Framework scaffolding, 30. 34...Cloth board (scaffolding board), 35...Auxiliary single pipe, 21,2
7, 33. 36-38...Pipe clamp.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 足場板支持ブラケットを取付けた垂直な単管を並列連結
して構或した足場の前記単管上に建枠支持ブラケットを
接続し、この建枠支持ブラケットの上端に枠組足場用建
粋の前後両支柱下端を接続すると共に、並列する建枠ど
うじを互に連結して枠組足場を組立て、前記建枠支持ブ
ラケットとこれを支持する単管との間又はこの建枠支持
ブラケットとこれに支持された建粋の前後両支柱との間
にねしジャッキを介装して戊る仮設足場構造。
A building frame support bracket is connected to the single pipe of the scaffold constructed by connecting vertical single pipes with scaffold board support brackets attached in parallel, and both the front and rear of the frame scaffolding structure are attached to the upper end of this building frame support bracket. The lower ends of the columns are connected, and the parallel building frames are connected to each other to assemble a framework scaffold, and between the building frame support bracket and the single pipe supporting it, or between the building frame support bracket and the pipe supported by this. A temporary scaffolding structure with jacks interposed between the front and rear pillars of the building.
JP2740780U 1980-03-03 1980-03-03 temporary scaffolding structure Expired JPS5910267Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2740780U JPS5910267Y2 (en) 1980-03-03 1980-03-03 temporary scaffolding structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2740780U JPS5910267Y2 (en) 1980-03-03 1980-03-03 temporary scaffolding structure

Publications (2)

Publication Number Publication Date
JPS56129462U JPS56129462U (en) 1981-10-01
JPS5910267Y2 true JPS5910267Y2 (en) 1984-03-31

Family

ID=29623371

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2740780U Expired JPS5910267Y2 (en) 1980-03-03 1980-03-03 temporary scaffolding structure

Country Status (1)

Country Link
JP (1) JPS5910267Y2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60108642U (en) * 1983-12-28 1985-07-24 株式会社竹中工務店 mobile scaffolding
JP3733303B2 (en) * 2001-08-01 2006-01-11 信和株式会社 Bracket for temporary scaffold
JP5172525B2 (en) * 2008-08-04 2013-03-27 株式会社東芝 Construction scaffold

Also Published As

Publication number Publication date
JPS56129462U (en) 1981-10-01

Similar Documents

Publication Publication Date Title
US4937989A (en) Locking brace for uniting mobile home sections through their undercarriage I-beams
JPS5910267Y2 (en) temporary scaffolding structure
CN217949318U (en) Multi-layer steel structure plant supporting frame
CN106337529A (en) Spliced herringbone beam
KR200491378Y1 (en) Supporter for safety foot plate and scaffolding
CN210423968U (en) Assembled support and hanger and building using same
JP2519196B2 (en) One-sided scaffold
JPS6013113B2 (en) Support framework for slab construction
JPH05214806A (en) Frame unit for scaffolding plate
CN214996308U (en) Support frame for construction convenient to height-adjusting
CN218541407U (en) Multifunctional scaffold
JPH0536907Y2 (en)
CN219060740U (en) Raised floor module and supporting structure thereof
CN208184198U (en) A kind of attachment device of attachment type raise scaffold upright bar
CN210316144U (en) Curtain wall keel framework
JPS588828Y2 (en) scaffolding support
CN107476200A (en) A kind of full framing dislocation set takes structure and method
CN219118693U (en) Support frame for building decoration
CN211548280U (en) Light and stable mounting structure for curtain wall
JPH0332675Y2 (en)
JPH051547Y2 (en)
JP2982858B2 (en) Scaffolding bracket
JPH0545692Y2 (en)
JP3013456U (en) Building equipment for scaffolding for construction
JPH0211549Y2 (en)