JPS582309B2 - Multilayer PC plate advance method - Google Patents

Multilayer PC plate advance method

Info

Publication number
JPS582309B2
JPS582309B2 JP10919279A JP10919279A JPS582309B2 JP S582309 B2 JPS582309 B2 JP S582309B2 JP 10919279 A JP10919279 A JP 10919279A JP 10919279 A JP10919279 A JP 10919279A JP S582309 B2 JPS582309 B2 JP S582309B2
Authority
JP
Japan
Prior art keywords
plate
concrete
floor
layer
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP10919279A
Other languages
Japanese (ja)
Other versions
JPS5634859A (en
Inventor
菊三 小川
万佐雄 大下
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyu Construction Co Ltd
Original Assignee
Tokyu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyu Construction Co Ltd filed Critical Tokyu Construction Co Ltd
Priority to JP10919279A priority Critical patent/JPS582309B2/en
Publication of JPS5634859A publication Critical patent/JPS5634859A/en
Publication of JPS582309B2 publication Critical patent/JPS582309B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Load-Bearing And Curtain Walls (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 本発明は多層PC版の先付け工法に関するものである。[Detailed description of the invention] The present invention relates to a pre-installation method for multilayer PC plates.

鉄骨躯体を組み立てたら床コンクリートなどを打設する
以前にPC版の壁面を取り付けておくPC版先付工法は
既に実施されている。
The PC version pre-installation method is already in use, in which PC version walls are attached after the steel frame is assembled and before concrete floors are poured.

また床梁などのコンクリートを打設する階よりも複数階
上方までPC壁板を先行して取り付けてしまう多層PC
版先付け工法も一部で実施されている。
Also, in multi-layer PC, PC wall boards are installed in advance several floors above the floor where concrete such as floor beams will be poured.
The plate tip method is also used in some areas.

この工法は各層ごとに鉄骨躯体にPC版を固定し、各階
のPC版の重量はすべて各階の鉄骨床梁で支持しておく
ものであり、いわば各層独立支持方式である。
In this construction method, the PC boards are fixed to the steel frame for each floor, and the weight of the PC boards on each floor is all supported by the steel floor beams on each floor, so to speak, each floor is supported independently.

このように各層ごとにその層のPC版重量を独立して支
持する方式は鉄骨造の躯体に限れば可能であるが、他の
構造の躯体、すなわち鉄骨鉄筋コンクリート、あるいは
鉄筋コンクリートの場合には不可能である。
This method of independently supporting the weight of the PC board for each layer is possible only for steel frame structures, but is not possible for other structures, such as steel reinforced concrete or reinforced concrete. It is.

すなわちSRC造では鉄骨が小さく少ないため、そのま
までは1層分のPC版重量を支持するのは困難である。
In other words, since the steel frame is small and scarce in SRC construction, it is difficult to support the weight of one layer of PC board as it is.

またRC造ではPC版を支持する鉄骨自体存在しないか
ら、PC版先付けという考えはなり立たない。
Also, in RC construction, there is no steel frame to support the PC version, so the idea of installing the PC version first is not viable.

本発明はこのような点を改善するためになされたもので
、鉄骨造の躯体では勿論、鉄骨鉄筋コンクリ−ト造の躯
体も補強することなく、更に鉄筋コンクリート造の躯体
でもそのまま使用できる多層PC版先付け工法を提供す
ることを目的とする。
The present invention has been made to improve these points, and is a multilayer PC board that can be used as is, not only in steel frame structures, but also in steel-framed reinforced concrete structures without any reinforcement, and even in reinforced concrete structures. The purpose is to provide a pre-installation method.

次に実施例について説明する。Next, an example will be described.

本発明の先付け工法に使用するPC版は次のような連結
材などを埋込んである。
The PC plate used in the pre-installation method of the present invention has the following connecting materials embedded therein.

〈1〉仮受材 PC版1を壁面に取付ける状態で垂直に吊ったときの上
縁11または下縁12に仮受材2を突設する。
<1> Temporary receiving material A temporary receiving material 2 is provided protruding from the upper edge 11 or lower edge 12 when the PC plate 1 is attached to a wall and hung vertically.

図の実施例ではPC版1の上縁11に2個所にボルトの
頭を仮受材2として突設し、この仮受材2の位置に応ず
る下縁12には受板21を固定してある。
In the illustrated embodiment, bolt heads are protruded from two locations on the upper edge 11 of the PC plate 1 as temporary support material 2, and a receiving plate 21 is fixed to the lower edge 12 corresponding to the position of the temporary support material 2. be.

しかし仮受材2を下縁12に突設することも、また特別
な部材を突設せずPC版1の上縁11また下縁12自体
を曲線状に盛り上げておいてもPC版1の簡易な角度調
整という目的は達成できる。
However, it is also possible to protrude the temporary support material 2 from the lower edge 12, or to raise the upper edge 11 or lower edge 12 of the PC plate 1 into a curved shape without protruding any special member. The purpose of simple angle adjustment can be achieved.

要するに上下のPC版1は実質的に点接触、または線接
触していればよい。
In short, it is sufficient that the upper and lower PC plates 1 are substantially in point contact or in line contact.

〈2〉上部連結材 PC版1の内側(壁面として取り付けた場合の建物内面
)の上方には上部連結材3を設ける。
<2> Upper connecting material The upper connecting material 3 is provided above the inside of the PC version 1 (inner surface of the building when installed as a wall surface).

これはPC版1の上方を躯体に取り付け、外側へ倒れる
のを防止する連結材である。
This is a connecting member that attaches the upper part of the PC plate 1 to the frame and prevents it from falling outward.

実施例ではPC版1内側に箱抜き31を行ない、この箱
抜31内に水平に固定した水平軸32に回転自在に舌板
33を取り付け、この舌板33にねじ孔34を貫通した
構成を示す。
In the embodiment, a box cutout 31 is made inside the PC plate 1, a tongue plate 33 is rotatably attached to a horizontal shaft 32 fixed horizontally inside the box cutout 31, and a screw hole 34 is passed through the tongue plate 33. show.

この連結材3を躯体の水平梁Hに取り付けるには、梁H
から調整用の水平ボルト35を介して突設した有孔板3
6のボルト孔と、舌板33のねじ孔34とをボルト37
で貫通して締め付けて行う。
To attach this connecting member 3 to the horizontal beam H of the building frame, the beam H
A perforated plate 3 protrudes from the horizontal bolt 35 for adjustment.
6 bolt hole and the screw hole 34 of the tongue plate 33 with the bolt 37.
Penetrate and tighten.

この上部連結材3を必要とする機能は、2種の物体を容
易に結合でき、かつ両者間の距離の調整が出来ることで
あるから公知の部材を広く利用できる。
The function that requires this upper connecting member 3 is that two types of objects can be easily connected and the distance between them can be adjusted, so that a wide variety of known members can be used.

〈3〉盛替具 PC版1の下縁12には盛替具4を設ける。<3> Refilling tool A replacement tool 4 is provided on the lower edge 12 of the PC plate 1.

この盛替具4は、水平梁Hにコンクリートが打設された
後に始めてPC版の荷重を受け、コンクリート打設後の
水平梁H、すなわち躯体に荷重を伝達するための連結具
である。
This replacement tool 4 is a connecting tool that receives the load of the PC plate only after concrete is placed on the horizontal beam H, and transmits the load to the horizontal beam H after concrete placement, that is, to the frame.

実施例ではPC版1下縁12よりも下方に鋼製の箱41
を穿設してある。
In the embodiment, a steel box 41 is placed below the lower edge 12 of the PC plate 1.
has been drilled.

そしてこの箱41の底42には垂直ボルト43用のねじ
孔を、また箱41の躯体側の面には水平ボルト44用の
ねし孔を、各々開設してある。
A screw hole for a vertical bolt 43 is provided in the bottom 42 of the box 41, and a tapped hole for a horizontal bolt 44 is provided in the surface of the box 41 on the body side.

垂直ボルト43はPC版1の上下方向の再調整(後述す
るようにコンクリート打設後の調整)用に、水平ボルト
44はPC版1の下部の出入りの調整に用いるが、コン
クリート打設前に仮受材2で正確な高さを出してあれば
垂直ボルト43を必要としない場合もある。
The vertical bolts 43 are used to readjust the vertical direction of the PC plate 1 (adjustment after concrete placement as described later), and the horizontal bolts 44 are used to adjust the entrance and exit of the lower part of the PC plate 1. If the temporary support material 2 has an accurate height, the vertical bolt 43 may not be necessary.

PC版1の上縁11部には、盛替具4に応ずる位置に受
溝45を凹設してあるが、盛替具4を下縁12から突設
せずにPC版1下部の内面に突設する構造を採用すれば
受溝45は不要になる。
A receiving groove 45 is recessed in the upper edge 11 of the PC plate 1 at a position corresponding to the reloading tool 4. If a structure in which the receiving groove 45 protrudes is adopted, the receiving groove 45 becomes unnecessary.

次に上記の構造のPC版を使用した多層先付け工法につ
いて説明する。
Next, a multilayer advance construction method using a PC plate with the above structure will be explained.

〈1〉梁の取付け 柱に梁Hを取り付ける。<1> Installing the beam Attach beam H to the pillar.

梁Hは鉄骨造、鉄骨鉄筋造、あるいは鉄骨造のいずれで
あってもよく、既にコンクリートの打設が終った階(N
階より上方の複数階の梁Hを取り付ける。
Beam H may be of steel frame construction, steel reinforced steel construction, or steel frame construction, and can be used on floors where concrete has already been poured (N
Attach beams H for multiple floors above the floor.

〈2〉N階のPC版の状態 N階のPC版1は既に建込まれており、梁H床のコンク
リート打設時に盛替具4の箱41部分はコンクリ−トで
まかれて躯体と一体になっている。
<2> Condition of PC version on the N floor It's all one.

従ってN階のPC版1の重量は、充分な強度を持つ躯体
に支持されていて安定な状態を保っている。
Therefore, the weight of the PC version 1 on the Nth floor is supported by a frame with sufficient strength and remains stable.

<3>PC版の先付け 梁Hを取り付けた後にPC版1をN+1、N+2、N+
3階程度まで取り付けてゆく。
<3> After installing the pre-attached beam H of the PC version, set the PC version 1 to N+1, N+2, N+
It will be installed up to about the third floor.

このとき従来の工法と根本的に異なる点は上層階のPC
版1の重量を順次下層階のPC版1で受け、コンクリ−
トでまいていない梁Hにはまったく垂直方向の重量を伝
達しないことである。
At this time, the fundamental difference from the conventional construction method is that the PC on the upper floor
The weight of Plate 1 is sequentially received by PC Plate 1 on the lower floor, and the concrete is
No weight in the vertical direction is transmitted to the beam H that is not wrapped around the beam.

そしてN+3階までのPC版の重量は、既に強度の充分
に出たコンクリ−ト打設済みの梁Hで受けることになる
The weight of the PC plates up to the N+3 floor will be supported by beams H, which have already been poured with sufficiently strong concrete.

従って各PC版1の上下方向の重量の伝達は順次仮受材
2を介して行なわれる。
Therefore, the weight of each PC plate 1 in the vertical direction is transmitted sequentially via the temporary support material 2.

更に各PC版1の上方は上部連結材3を介して未打設の
梁Hに連結する。
Further, the upper part of each PC plate 1 is connected to an uncast beam H via an upper connecting member 3.

この場合に未打設の梁Hに加わる荷重は転倒開始を引き
止めるだけの荷重であるからコンクリートは打設してい
す補強もしていない鉄骨鉄筋や鉄筋の梁によっても充分
に支持できる。
In this case, the load applied to the unconcrete beam H is just enough to prevent it from falling over, so the concrete can be sufficiently supported by steel reinforcing bars or rebar beams that have not been poured and reinforced with chairs.

PC版1を下層のPC版1の仮受材2上に載置したとき
に上層下縁12の盛替具4は下層PC版1上縁11に凹
設した受溝45内におさまる。
When the PC plate 1 is placed on the temporary receiving material 2 of the lower PC plate 1, the replacement tool 4 on the lower edge 12 of the upper layer fits into the receiving groove 45 recessed in the upper edge 11 of the lower PC plate 1.

その状態で垂直ボルト43の下端が梁Hの上面または梁
Hから張り出した受板46の上面に接してかつ荷重は伝
達しない状態に調整する。
In this state, the lower end of the vertical bolt 43 is adjusted to be in contact with the upper surface of the beam H or the upper surface of the receiving plate 46 extending from the beam H, and no load is transmitted.

更に水平ボルト44でPC版下端の出入りを調整して固
定する。
Furthermore, the horizontal bolt 44 is used to adjust and fix the lower end of the PC plate.

<4>N+1階のコンクリート打設 N+1階の梁Hや床にコンクリ−トを打設ずると盛替具
4の箱42も受板46もコンクリートでまかれる。
<4> Concrete pouring on the N+1st floor When concrete is poured on the beam H and floor on the N+1st floor, the box 42 of the replacement tool 4 and the receiving plate 46 are also poured with concrete.

その結果N+1階以上の先付けしたPC版の重量はコン
クリート打設が終り充分な強度を有丈るようになったN
+1階の梁Hで支持されることになる。
As a result, the weight of the pre-attached PC slabs on the N+1st floor and above has reached a point where it has sufficient strength after the concrete is poured.
It will be supported by the beam H on the +1st floor.

従って更に上層階のPC版1を搭載することができる。Therefore, the PC version 1 on the upper floor can be installed.

本発明は上記したように下縁をコンクリート打設後の梁
に取り付けたPC版の上縁の上に、上層のPC版を垂直
に搭載しておき、下層から順次梁にコンクリートを打設
した後にその層のPC版の荷重を梁に盛替える工法であ
る。
As described above, in the present invention, the upper layer of PC plate is vertically mounted on the upper edge of the PC plate whose lower edge is attached to the beam after concrete pouring, and concrete is poured onto the beam sequentially from the lower layer. This is a construction method in which the load of the PC plate of that layer is then transferred to the beam.

従って下記のような効果を期待できる。Therefore, the following effects can be expected.

〈1〉先付けするPC版の垂直方向の荷重をコンクリー
ト未打設の梁には一切負担させず、すべて下方のPC版
を通してコンクリ−ト打設済みの梁や床に負荷させるも
のである。
<1> The vertical load of the pre-attached PC plate is not applied to the unconcrete beam at all, but is entirely applied to the concrete-concrete beam and floor through the lower PC plate.

従って鉄骨の断面、強度の小さい鉄骨鉄筋造の骨組みの
場合でも、更に鉄骨の存在しない、従ってそれ自体では
まったくPC版重量を支持できない鉄筋造の骨組みの場
合でも、コンクリート未打設時の強度には関係な<PC
版の先付けを、しかも多数階にわたって一時に行うこと
ができる。
Therefore, even in the case of a steel-reinforced frame with a low steel cross-section and strength, and even in the case of a steel-reinforced frame with no steel frame and therefore unable to support the weight of the PC board at all, the strength when concrete is not poured is the same. It doesn't matter <PC
It is possible to pre-apply plates on multiple levels at the same time.

<2>PC版の上縁と下縁の接触部を点または線接触で
仮受けしておけば多数枚のPC版を先付けして搭載した
状態でも、上部連結材の調整によって容易に垂直性の修
正を行うことができる。
<2> If the contact parts of the upper and lower edges of the PC plates are temporarily supported by point or line contact, even when a large number of PC plates are loaded in advance, vertical alignment can be easily achieved by adjusting the upper connecting material. corrections can be made.

【図面の簡単な説明】[Brief explanation of drawings]

第1図二本発明に係る多層PC版先付け工法の一実施例
の斜視図、第2〜4図:その要部断面図、第5図:その
側面図。 i:pc版、2:仮受材、3:連結材、4:盛替具。
FIG. 12 is a perspective view of an embodiment of the multilayer PC board pre-attaching method according to the present invention, FIGS. 2 to 4 are sectional views of essential parts thereof, and FIG. 5 is a side view thereof. i: PC version, 2: Temporary receiving material, 3: Connecting material, 4: Replacement tool.

Claims (1)

【特許請求の範囲】 1 下縁をコンクリート打設後の梁や床に取り付けたP
C版の上縁の上に、 上層のPC版を順次ほぼ垂直に搭載し、 下層から梁や床にコンクリートを打設した後、その層の
PC版の荷重をコンクリート打設部に盛替えて行う多層
PC版先付け工法。 2 コンクリート打設部に盛替える以前のPC版の上下
層の接触部が実質的に点または線接触である、特許請求
の範囲第1項記載の工法。
[Claims] 1. P whose lower edge is attached to a beam or floor after concrete pouring
The upper layer of PC plates is mounted almost vertically on top of the upper edge of the C plate, concrete is poured into the beams and floor from the lower layer, and then the load of the PC plates of that layer is transferred to the concrete pouring area. Multi-layer PC plate pre-installation method. 2. The construction method according to claim 1, wherein the contact area between the upper and lower layers of the PC plate before being replaced in the concrete placement area is substantially point or line contact.
JP10919279A 1979-08-29 1979-08-29 Multilayer PC plate advance method Expired JPS582309B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10919279A JPS582309B2 (en) 1979-08-29 1979-08-29 Multilayer PC plate advance method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10919279A JPS582309B2 (en) 1979-08-29 1979-08-29 Multilayer PC plate advance method

Publications (2)

Publication Number Publication Date
JPS5634859A JPS5634859A (en) 1981-04-07
JPS582309B2 true JPS582309B2 (en) 1983-01-14

Family

ID=14503959

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10919279A Expired JPS582309B2 (en) 1979-08-29 1979-08-29 Multilayer PC plate advance method

Country Status (1)

Country Link
JP (1) JPS582309B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58159337U (en) * 1982-04-19 1983-10-24 鹿島建設株式会社 tile pasting equipment
FR2546555B1 (en) * 1983-05-25 1986-04-18 Freyssinet Int Stup IMPROVEMENTS ON CURTAIN WALLS AND THEIR COMPONENTS
JPS6259210U (en) * 1985-09-30 1987-04-13
JPS6396115U (en) * 1986-12-15 1988-06-21
JPH0626650Y2 (en) * 1987-01-23 1994-07-20 日建工業株式会社 Precast outer wall version with adjusting bracket
JPH0765361B2 (en) * 1987-09-01 1995-07-19 旭化成工業株式会社 Wall panel mounting structure

Also Published As

Publication number Publication date
JPS5634859A (en) 1981-04-07

Similar Documents

Publication Publication Date Title
US9085901B2 (en) Pre-assembled internal shear panel
CA2358747C (en) Ring beam/lintel system
US4074487A (en) Multi-story wall framing system and method
US5906076A (en) Removable support for concrete slab construction and method
US4619090A (en) Truss assembly for brick wall or masonry support
CA2208401C (en) Building panels
AU657120B2 (en) Supporting element for use in casting concrete floors
US4802316A (en) Eave truss and method for supporting and reinforcing a concrete or masonry wall and metal roof structure
US3927518A (en) Site assembled multi-story stair
US6390438B1 (en) End latch for removable support for concrete slab construction and method
JPS582309B2 (en) Multilayer PC plate advance method
JPH08189042A (en) Structure of h-section continuous footing beam for tying in building member
RU2094574C1 (en) Supporting beam for use in pouring concrete flooring
JPH0432182B2 (en)
JP2001164684A (en) Method of mounting precast concrete curtain wall
JPH1046706A (en) Panel anchoring structure and anchoring method therefor regarding building structure made of concrete wall panel
JP3138981B2 (en) Construction method of reinforced concrete building
JPS5931627B2 (en) Extension construction method
JP2545095B2 (en) Structure of the foundation of the building
JP2002364139A (en) Steel stair mounting hardware, mounting device and mounting method
JPS6134468Y2 (en)
JPH0220779B2 (en)
JPS6133141Y2 (en)
JP2001064980A (en) Foundation of building and its construction
JP3143659B2 (en) Structure of reinforced concrete building