JPS58164939A - Ventilating equipment for nuclear power plant - Google Patents

Ventilating equipment for nuclear power plant

Info

Publication number
JPS58164939A
JPS58164939A JP57046305A JP4630582A JPS58164939A JP S58164939 A JPS58164939 A JP S58164939A JP 57046305 A JP57046305 A JP 57046305A JP 4630582 A JP4630582 A JP 4630582A JP S58164939 A JPS58164939 A JP S58164939A
Authority
JP
Japan
Prior art keywords
air
housing
supply
fans
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP57046305A
Other languages
Japanese (ja)
Inventor
Shigeru Hirono
広野 茂
Hideo Hara
日出夫 原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Plant Construction Co Ltd
Hitachi Plant Technologies Ltd
Original Assignee
Hitachi Plant Construction Co Ltd
Hitachi Plant Technologies Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Plant Construction Co Ltd, Hitachi Plant Technologies Ltd filed Critical Hitachi Plant Construction Co Ltd
Priority to JP57046305A priority Critical patent/JPS58164939A/en
Publication of JPS58164939A publication Critical patent/JPS58164939A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F7/00Ventilation
    • F24F7/04Ventilation with ducting systems, e.g. by double walls; with natural circulation
    • F24F7/06Ventilation with ducting systems, e.g. by double walls; with natural circulation with forced air circulation, e.g. by fan positioning of a ventilator in or against a conduit

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Ventilation (AREA)

Abstract

PURPOSE:To reduce the capacity of air-supply fan facilities, and to improve maintenance capability by installing air-supply fans concentrated at each housing at one position and making them even to the same kind. CONSTITUTION:Air supplied to a nuclear reactor housing 4, an auxiliary housing 8, a turbine housing 12 and a waste treating housing 16 is treated by treating- device units 18 installed into a centralized outside-air treating device 17, and forwarded into each housing through air-supply ducts 3, 7, 11, 15 by centralized air-supply fans 19. Fixed air-quantity devices are each set up to these air-supply ducts, and each quantity of air designed can be blasted to several housing by air actuating dampers. According to such constitution, one air-supply fan 19 is used as a spare, other three ones can supply air to all of each housing 4, 8, 12, 16, installation of only four in total air-supply fans 19 of one kind is necessary instead of eight if each two fans of four kinds are installed for each houses 4, 8, 12, 16, and the intercangeability and maintenance capability of the parts of the air-supply fans are improved remarkably.

Description

【発明の詳細な説明】 設備に関する。[Detailed description of the invention] Regarding equipment.

従来の原子力発電所の換気設備は,各建屋毎に設置され
,外気処理装置及び給気ファンを含む。
Ventilation equipment in conventional nuclear power plants is installed in each building and includes outside air processing equipment and air supply fans.

この゛換気設備においては,外気はまず外気処理装置で
フィルター処理,加熱冷却処理された後,給気ファンに
より各建屋内に送風される。各建屋の給気ファンには,
換気設備を停止すること々く。
In this ventilation system, outside air is first filtered and heated and cooled by an outside air processing device, and then is blown into each building by an air supply fan. The air supply fans in each building are
Ventilation equipment was often shut down.

保守点検等が出来るよう予備機が必要であり,各建屋毎
に50%或いは100%容量の予備機が設けられている
Spare machines are required to enable maintenance and inspection, and each building has a spare machine with a capacity of 50% or 100%.

このような従来の換気設備を第1図に示す。原子炉建屋
4,補助建屋8,タービン建屋12,廃棄物処理建屋l
6の換気設備の給気は,外気処理装置1,5.9及び1
3で外気を取入れ,フィル第1図に示した設備では,原
子炉建屋給気ファン2,補助建屋給気ファン6,タービ
ン建屋給気ファン10,廃棄物処理建屋給気ファンl4
が各々100%容量の予備機をもっているため,その設
備容量は運転容量の2倍となっている。また。
Such conventional ventilation equipment is shown in FIG. Reactor building 4, auxiliary building 8, turbine building 12, waste treatment building l
The air supply for ventilation equipment No. 6 is provided by outside air processing equipment No. 1, No. 5.9 and No. 1.
In the equipment shown in Figure 1, the reactor building air supply fan 2, the auxiliary building air supply fan 6, the turbine building air supply fan 10, and the waste treatment building air supply fan 14 are used.
Since each of these has 100% capacity spare equipment, their installed capacity is twice the operating capacity. Also.

容量の異なる4種類の給気ファンが各建屋に設置されて
いる。
Four types of air supply fans with different capacities are installed in each building.

本発明の目的は,給気ファンの設備容量を低減し、かつ
保守性を向上することのできる原子力発電所の換気設備
を提供することにある。
An object of the present invention is to provide ventilation equipment for a nuclear power plant that can reduce the installed capacity of air supply fans and improve maintainability.

この目的は9本発明によれば各建屋の給気ファンを1ケ
所に集中設置し、複数台の各給気ファンとして同一機種
のものを使用することによって達成される。
According to the present invention, this object is achieved by centrally installing the air supply fans of each building in one place and using the same model as each of the plurality of air supply fans.

次に、第2図に示した本発明の一実施態様に基づいて2
本発明を詳述する。原子炉建屋4.補助建屋8.タービ
ン建屋12及び廃棄物処理建屋16への給気は、集中外
気処理装置17の中に設置1及び15を通じて各建屋に
送風される。これらの給気ダクトには、各々定風量装置
を設け、空気作動ダンパにより、各々の設計空気量を各
建屋に送風できるようにする。
Next, based on one embodiment of the present invention shown in FIG.
The invention will now be described in detail. Reactor building 4. Auxiliary building 8. Air supply to the turbine building 12 and waste treatment building 16 is blown to each building through installations 1 and 15 in a central outside air treatment system 17. Each of these air supply ducts is equipped with a constant air volume device, and an air-operated damper allows each designed air volume to be blown to each building.

このように構成すること−より設計容量を著しく減少す
ることができる。原子炉建屋4の給気量をAm”/’H
,補助建屋8の給気量をBm3/H,タービン建屋12
の給気量1c771.3/H,廃棄物処理建屋の給気量
’!i=Dm”/Hとしたとき、第1図に示した従来例
では、各々の建屋の給気ファンが100%容量の予備機
を有しているため、全給気ファンの全運転容量に対する
設備容量の比率は下式により2倍となる。
With this arrangement, the design capacity can be significantly reduced. The supply air amount of reactor building 4 is Am”/’H
, the air supply amount of auxiliary building 8 is Bm3/H, turbine building 12
Air supply amount of 1c771.3/H, air supply amount of waste treatment building'! When i = Dm''/H, in the conventional example shown in Fig. 1, the supply air fan in each building has a spare unit with 100% capacity, so the total operating capacity of all supply air fans is The ratio of installed capacity will be doubled using the following formula.

2A+2B+2C+2D=2(A十B+C+D)一方、
第2図に示す実施態様では、給気ファンの予備を1台と
し、他の3台で各建屋の全給気を行うものとすれば、1
台当りの容量は。
2A + 2B + 2C + 2D = 2 (A + B + C + D) On the other hand,
In the embodiment shown in Fig. 2, if one spare air supply fan is used and the other three are used to supply all the air to each building, then 1
What is the capacity per unit?

となる。従って全給気ファンの全運転容量に対する設備
容量の比率は下式により約1.3倍となり。
becomes. Therefore, the ratio of the installed capacity to the total operating capacity of all air supply fans is approximately 1.3 times according to the formula below.

従来設備に比べて大きく低減する。Significant reduction compared to conventional equipment.

: 。:.

、千1.3 (A+B+C+D ) L。, 1,000 1.3 (A+B+C+D) L.

更に、従来設備で、各建屋に各々Am3/H。Furthermore, with conventional equipment, each building has a capacity of Am3/H.

B m”/H,Cm3/H及びDm”/H04種の給気
ファンが合計8台必要であったが9本発明によれ4台設
置すれば良く、捷た。全ての給気ファンが一ケ所に設置
されているので、給気ファンの部品の互換性及び保守性
が従来設備に比べて著しく有利である。
A total of 8 air supply fans of B m''/H, Cm3/H, and Dm''/H04 types were required, but according to the present invention, only 4 need to be installed. Since all the air supply fans are installed in one place, the interchangeability and maintainability of the air supply fan parts is significantly advantageous compared to conventional equipment.

また、給気ファンを集中設置すると共に、第2図に示し
たように外気処理装置も集中設置することにより、製作
、輸送を考慮した1種類のユニットタイプの処理装置と
することができ、給気ファンと同様に保守性の向上及び
設計の省力化を図ることができる。
In addition, by centrally installing the air supply fans and also centrally installing the outside air processing equipment as shown in Figure 2, it is possible to create one type of unit type processing equipment that takes manufacturing and transportation into consideration. As with fans, it is possible to improve maintainability and save labor in design.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は従来の換気設備を示す系統構成図、第2図は本
発明の一実施態様を示す系統構成図である。 符号の説明 1.5,9.13・・・外気処理装置 2.6,10.14・・・給気ファン 3、’7,11.15・・・給気ダクト4・・・原子炉
建屋    8・・・補助建屋■2・・・タービン建屋
  16・・廃棄物処理建屋。 17・・・集中外気処理装置 18・・・処理装置ユニ
ット19・・・集中給気ファン。 第1図 4 第2図 ビー16.−
FIG. 1 is a system configuration diagram showing a conventional ventilation equipment, and FIG. 2 is a system configuration diagram showing an embodiment of the present invention. Explanation of symbols 1.5, 9.13... Outside air processing device 2.6, 10.14... Air supply fan 3, '7, 11.15... Air supply duct 4... Reactor building 8...Auxiliary building ■2...Turbine building 16...Waste treatment building. 17... Centralized outside air processing device 18... Processing device unit 19... Centralized air supply fan. Figure 1 4 Figure 2 Bee 16. −

Claims (2)

【特許請求の範囲】[Claims] (1)外気処理装置と複数個の給気ファンを含む原子力
発電所の換気設備において、各建屋ごとに付設する外気
を移送する前記給気ファンを1ケ所に集中設置し、同一
機種としたことを特徴とする原子力発電所の換気設備。
(1) In the ventilation equipment of a nuclear power plant, which includes an outside air processing device and multiple air supply fans, the air supply fans that are attached to each building to transfer outside air are centrally installed in one place and are of the same model. Ventilation equipment for a nuclear power plant featuring:
(2)外気処理装置も集中設置した特許請求の範囲第1
項記載の換気設備。
(2) Claim 1 in which outside air processing equipment is also centrally installed
Ventilation equipment as described in section.
JP57046305A 1982-03-25 1982-03-25 Ventilating equipment for nuclear power plant Pending JPS58164939A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP57046305A JPS58164939A (en) 1982-03-25 1982-03-25 Ventilating equipment for nuclear power plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP57046305A JPS58164939A (en) 1982-03-25 1982-03-25 Ventilating equipment for nuclear power plant

Publications (1)

Publication Number Publication Date
JPS58164939A true JPS58164939A (en) 1983-09-29

Family

ID=12743476

Family Applications (1)

Application Number Title Priority Date Filing Date
JP57046305A Pending JPS58164939A (en) 1982-03-25 1982-03-25 Ventilating equipment for nuclear power plant

Country Status (1)

Country Link
JP (1) JPS58164939A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61105489A (en) * 1984-10-29 1986-05-23 株式会社日立製作所 Ventilating facility for nuclear power plant

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61105489A (en) * 1984-10-29 1986-05-23 株式会社日立製作所 Ventilating facility for nuclear power plant
JPH0140316B2 (en) * 1984-10-29 1989-08-28 Hitachi Ltd

Similar Documents

Publication Publication Date Title
CN106678966A (en) Low-noise modular air purification system
GB821805A (en) Improvements in or relating to air conditioning units and methods of air conditioning
JPS56117027A (en) Air conditioning method for dome-shaped building
JPS58164939A (en) Ventilating equipment for nuclear power plant
CN206637723U (en) The box electronic purifier component of return air and fan and coil air conditioner group
CN112747406A (en) Fresh air system
JPS5680644A (en) Controller for air conditioner
CN212063042U (en) Electrical engineering is with quick heat dissipation regulator cubicle
JPS6124933A (en) Air-conditioning system
WO2019024454A1 (en) Air handling module and air conditioner
JPS6488300A (en) Ventilating air-conditioning equipment of nuclear power plant
CN210801515U (en) Variable air volume air treatment system for laboratory
CN209165684U (en) A kind of fluorescence detection ventilating system
CN216204034U (en) New fan of split type central authorities
JPH0330060B2 (en)
WO2019024457A1 (en) Air treatment module and air conditioner
JPH02293554A (en) Clean room system
CN212746806U (en) Circulating air system for air conditioner welding room
CN214665013U (en) Fresh air system
JPH0631828B2 (en) Ventilation and air conditioning equipment for nuclear power plants
CN216011124U (en) Sterilizing device for direct-discharge type dust-free room workshop
CN211060317U (en) Fully-decoupled multi-working-condition stable-control purification air conditioning equipment
CN208779589U (en) A kind of medicine toilet clean system
CN208332605U (en) Air conditioner fresh air integrated pipeline
CN117212943A (en) Ventilation device for clean room