Preventing method for liquefaction of sandy groundInfo
- Publication number
- JPS56100919A JPS56100919A JP415080A JP415080A JPS56100919A JP S56100919 A JPS56100919 A JP S56100919A JP 415080 A JP415080 A JP 415080A JP 415080 A JP415080 A JP 415080A JP S56100919 A JPS56100919 A JP S56100919A
- Authority
- JP
- Japan
- Prior art keywords
- piles
- casing
- liquefaction
- sandy ground
- ground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
PURPOSE: To prevent effectively the liquefaction of the sandy ground apt to occur at the time of earthquake, by forming drain piles making use of such space forming materials as crushed stones by means of nonvibration and nonpressure works.
CONSTITUTION: In order to prevent the sandy ground from liquefaction, the drain piles 2 making use of such space forming materials as crushed stones 1 are arranged in the ground 3 with proper dispositions, and the excessive water pressures apt to occur at the time of earthquake are absorbed through the piles 2. These piles 2 are formed by means of nonvibration and nonpressure works, using for instance the Benoto-machine A. That is to say, the boring hole 4 is dug vertically while digging out the sands in the cylindrical casing a1 with hammer-grab a2 and lowering gradually the casing a1. When the casing hole 4 reaches the desired depth, it is filled with the materials 1. By puling up the casing a1, the pile 2 is formed.
COPYRIGHT: (C)1981,JPO&Japio
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP415080A JPS56100919A (en) | 1980-01-18 | 1980-01-18 | Preventing method for liquefaction of sandy ground |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP415080A JPS56100919A (en) | 1980-01-18 | 1980-01-18 | Preventing method for liquefaction of sandy ground |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS56100919A true JPS56100919A (en) | 1981-08-13 |
Family
ID=11576730
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP415080A Pending JPS56100919A (en) | 1980-01-18 | 1980-01-18 | Preventing method for liquefaction of sandy ground |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS56100919A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0366836A (en) * | 1989-08-04 | 1991-03-22 | Kubota Corp | Design process for piping at structure |
-
1980
- 1980-01-18 JP JP415080A patent/JPS56100919A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0366836A (en) * | 1989-08-04 | 1991-03-22 | Kubota Corp | Design process for piping at structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110359497A (en) | A kind of existing construction of structures ground base high-performance broken stone pile anti-liquefying treatment method | |
Milanovic | Prevention and remediation in karst engineering | |
JPS56100919A (en) | Preventing method for liquefaction of sandy ground | |
US4981399A (en) | Method and apparatus for increasing bearing capacity of soft soil and constructing cutoff wall | |
US3436921A (en) | Apparatus and method of producing shafts and caissons | |
JPS5631928A (en) | Constructing method for soil pile | |
JPS57108328A (en) | Formation of basement | |
JPS55116920A (en) | Compound grouting method | |
JPS5768415A (en) | Ground improving method | |
SU881254A1 (en) | Method of erecting cast-in-place pile in bulging soil | |
JPS55165308A (en) | Constructing method for underground dam | |
JPH11140881A (en) | Penetration method for caisson foundation | |
JPS62233326A (en) | Column line-type water-permeable wall construction work | |
Chastanet et al. | Wanaque filtration plant subgrade stabilization. A case history | |
JPS5631925A (en) | Constructing method for pit | |
JPH02140318A (en) | Settlement adjustment construction with water storage tank and water stop wall | |
JPS5631941A (en) | Building of underground storage tank | |
RU1812277C (en) | Method of protecting foundation against frost heaving | |
SU1395742A1 (en) | Method of constructing earth dam | |
JPS559905A (en) | Piling foundation structure for structure | |
JPS55155809A (en) | Reclaiming method for farm land or green district | |
JPS57205626A (en) | Prevention work for soil run-off | |
JPS56105017A (en) | Method of construction of foundation pile | |
JPS5585731A (en) | Method and apparatus for burying pile | |
JPS62101718A (en) | Caisson settlement work suitable for hard ground or the like |