JPH1181305A - Removing method of concrete in underground concrete structure - Google Patents

Removing method of concrete in underground concrete structure

Info

Publication number
JPH1181305A
JPH1181305A JP23601097A JP23601097A JPH1181305A JP H1181305 A JPH1181305 A JP H1181305A JP 23601097 A JP23601097 A JP 23601097A JP 23601097 A JP23601097 A JP 23601097A JP H1181305 A JPH1181305 A JP H1181305A
Authority
JP
Japan
Prior art keywords
concrete
hole
underground
top end
pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP23601097A
Other languages
Japanese (ja)
Inventor
Tetsuji Sato
哲司 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP23601097A priority Critical patent/JPH1181305A/en
Publication of JPH1181305A publication Critical patent/JPH1181305A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PROBLEM TO BE SOLVED: To securely and rapidly crush concrete of an inferior part near the top end without noise and vibration and reduce the construction period. SOLUTION: In the removing method of a defective finish part D formed near a concrete C top end after the concrete C has been placed in a hole or a ditch excavated in the ground E and cured, one or more bar-shaped bodies 14 having a length corresponding to the thickness of the inferior part expected before the concrete C is placed or cured are driven from the top end of the concrete C. After it has been cured, the bar-shaped bodies 14 are drawn to form a hole 16. An expansive agent 18 us poured in the hole to give a static pressure toward the outside to the inner wall of the hole. In this way, the concrete C at the periphery of the hole 16 is crushed and removed.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、地中連続壁や場所
打杭など、泥水などの薬液と置換して得られる地中コン
クリート構造物において、特に水中置換におけるコンク
リート構造物の頂部近傍の不良部位を効率よく除去する
方法に関する。
BACKGROUND OF THE INVENTION The present invention relates to an underground concrete structure obtained by substituting a chemical solution such as muddy water, such as an underground continuous wall or a cast-in-place pile. The present invention relates to a method for efficiently removing a site.

【0002】[0002]

【従来の技術】例えば、地中連続壁、場所打杭などの地
中コンクリート構造物の構築工事では、地表より泥水な
どの薬液を満たして孔壁の崩壊を防止しながら掘削を行
い、次いで鉄筋籠の建て込みと、コンクリートの打設作
業を行って地中に壁体あるいは杭などの地中コンクリー
ト構造物を構築する。この構築工事におけるコンクリー
ト打設にあたっては、トレミー管を用いて孔(溝)底部
から順次泥水と置換しつつ地表面近くまで打設する。
2. Description of the Related Art For example, in the construction of an underground concrete structure such as an underground continuous wall or a cast-in-place pile, excavation is performed while filling a chemical solution such as muddy water from the surface of the ground to prevent collapse of a hole wall, and then rebar. Construction of baskets and casting of concrete are performed to construct underground concrete structures such as walls and piles in the ground. In this construction work, concrete is poured from the bottom of the hole (groove) to near the ground surface using a tremy pipe while replacing it with muddy water.

【0003】一般に、コンクリートは、打設後に余剰水
の一部が表面に浮上し、打設表面にはスライムと称され
る固結しない、あるいは固結してもコンクリート強度と
してはきわめて脆弱な仕上がり不良部位が生ずる。
[0003] In general, after casting, a part of surplus water floats on the surface after casting, and the finished surface, which is called slime, does not solidify on the casting surface, or has extremely weak concrete strength even if solidified. Defective parts occur.

【0004】そして、特にこの種の工法では、コンクリ
ートの打設深度がきわめて大きいものもあるし、加えて
泥水との置換により泥水中の微粉末も引連れてくるた
め、特に表面における不良部位の厚みが厚くなる傾向に
ある。
[0004] In particular, in this type of construction method, there is a case where the concrete placement depth is extremely large, and in addition, fine powder in the muddy water is attracted by replacement with the muddy water. The thickness tends to be large.

【0005】このため、この種の地中コンクリート構造
物の構築後は、上部構造物の構築に先立ち、天端部分を
はつって不良部位を除去するのが通常である。
For this reason, after the construction of this kind of underground concrete structure, it is usual to remove the defective portion by removing the top end portion before constructing the upper structure.

【0006】[0006]

【発明が解決しようとする課題】しかしながら、従来の
はつり作業による除去方法では、次に述べる技術的な課
題があった。特に、地中連続壁の構築工事では、一般に
地表面に埋設された一対のガイドウオール(ガイドトレ
ンチとも言う)によって掘削箇所を仕切り、このガイド
ウオールをガイドとしてその内部を鉛直に掘削し、その
後、掘削孔内にコンクリートを打設するが、工事後はこ
のガイドウオールをそのまま残しておく場合が多い。
However, the conventional removing method by the hanging operation has the following technical problems. In particular, in the construction work of the underground diaphragm wall, the excavation site is generally partitioned by a pair of guide walls (also referred to as guide trenches) buried in the ground surface, and the inside is excavated vertically using the guide wall as a guide, Concrete is poured into the borehole, but the guide wall is often left as it is after construction.

【0007】従って、ガイドウオールを撤去できない状
態で、はつり工事を行うときは、大型機械が使用不可能
であり、人力作業が主体となるため、特に鉄筋が輻輳し
ている箇所でのはつり作業などは効率が低く、多大な手
間を要するのみならず、騒音や振動及び粉塵の発生原因
となるため、周囲環境や作業員の健康に留意しながら作
業を実施しなければならず、工期が長引く原因となって
いた。
[0007] Therefore, when performing hanging work in a state in which the guide wall cannot be removed, large machines cannot be used and manual work is mainly performed. Is not efficient and requires a great deal of trouble, and also causes noise, vibration and dust, so it is necessary to carry out the work while paying attention to the surrounding environment and the health of workers. Had become.

【0008】本発明方法は、以上の課題を解決するため
になされたものであり、その目的は、天端近傍における
不良部位のコンクリートを確実、かつ騒音や振動の発生
を伴うことなく迅速に破砕でき、工期の短縮を図るよう
にした地中コンクリート構造物におけるコンクリートの
除去方法を提供するものである。
The method of the present invention has been made in order to solve the above-mentioned problems, and an object thereof is to crush concrete in a defective portion near the top end quickly and without generating noise or vibration. It is an object of the present invention to provide a method for removing concrete from an underground concrete structure capable of shortening the construction period.

【0009】[0009]

【課題を解決するための手段】以上の目的を達成するた
め、本発明のうち請求項1に記載の発明は、地盤中に掘
削された孔ないし溝にコンクリートを打設し、該コンク
リートの固化後、コンクリートの天端近傍に形成される
仕上り不良部位を除去する方法であって、コンクリート
打設前ないしはコンクリートの固化以前に、予測される
不良発生部位の厚みに応じた長さの棒状体をコンクリー
トの天端から一ないし複数本打込み、該コンクリートの
固化後に、前記棒状体を引抜いて孔を形成し、次いで該
孔の内壁に外方に向けて圧力を加えることで、孔周囲の
コンクリートを破砕してからこれを撤去することを特徴
とするものである。この発明方法によれば、大型機械が
不要で、孔数に応じてその周囲コンクリートを効率よく
破砕できる。
Means for Solving the Problems In order to achieve the above object, according to the first aspect of the present invention, concrete is poured into a hole or a groove excavated in the ground, and the concrete is solidified. After that, a method of removing the defective portion formed near the top end of the concrete is a method of removing a rod-shaped body having a length corresponding to the expected thickness of the defective portion before the concrete is poured or before the concrete is solidified. One or more pieces are poured from the top of the concrete, and after solidification of the concrete, the rod is pulled out to form a hole, and then pressure is applied outward on the inner wall of the hole to reduce the concrete around the hole. It is characterized in that it is crushed and then removed. According to the method of the present invention, a large-sized machine is not required, and the surrounding concrete can be efficiently crushed according to the number of holes.

【0010】請求項2に記載の発明は、前記圧力が、前
記孔内に充填された膨張性薬剤の膨張により加えられる
ことを特徴とするものであり、この発明によれば、各孔
に薬剤を注入するだけの簡単な作業により破砕作用を行
うことができるほか、従来のはつり作業に比べて、騒
音、振動の発生や粉塵の発生がない。
[0010] The invention according to claim 2 is characterized in that the pressure is applied by expansion of the expansive drug filled in the holes, and according to the present invention, the drug is applied to each hole. The crushing action can be performed by a simple operation of merely injecting water, and there is no generation of noise, vibration or dust as compared with the conventional hanging operation.

【0011】請求項3に記載の発明は、前記圧力が、前
記孔内に挿通された爆発物の爆発により加えられること
を特徴とするものであり、この発明によれば、比較的短
期に破砕作業を行うことができる。
According to a third aspect of the present invention, the pressure is applied by the explosion of an explosive inserted into the hole, and according to the present invention, the crushing is performed in a relatively short time. Work can be done.

【0012】請求項4に記載の発明は、前記圧力が、前
記孔内に挿通されて径方向に伸長可能なジャッキにより
加えられることを特徴とするものであり、この発明によ
れば、騒音、振動の発生や粉塵の発生がないし、かつ比
較的短期に破砕作業を行うことができる。
According to a fourth aspect of the present invention, the pressure is applied by a jack which is inserted into the hole and can be extended in a radial direction. There is no generation of vibration or dust, and the crushing operation can be performed in a relatively short time.

【0013】[0013]

【発明の実施の形態】以下、本発明の好ましい実施の形
態につき、添付図面を参照して詳細に説明する。
Preferred embodiments of the present invention will be described below in detail with reference to the accompanying drawings.

【0014】図1(a)〜(d)は本発明の除去方法
を、地中連続壁に適用した場合の作業手順を示すもので
ある。同図において、地盤Eの地表部には逆L字型断面
の左右一対のガイドウオール10が埋設され、このガイ
ドウオール10によって仕切られた内部には掘削溝12
が形成され、この掘削溝12内にはコンクリートCが打
設充填され、地中連続壁が構築されている。
FIGS. 1 (a) to 1 (d) show an operation procedure when the removal method of the present invention is applied to an underground continuous wall. In the figure, a pair of left and right guide walls 10 having an inverted L-shaped cross section are buried in the surface of the ground E, and an excavation groove 12 is provided inside the guide wall 10.
Is formed, and concrete C is poured and filled into the excavation groove 12 to construct an underground continuous wall.

【0015】以上において、コンクリートCの打設深
度、コンクリート材料、使用泥水などに応じて、コンク
リート天端近傍における不良部位の厚みDは、経験値か
らおおよそ特定される。これに基づき、予め打設前、あ
るいは打設直後であって、コンクリートCの固化以前に
(a)に示すように、その不良部位Dの厚みに応じた長
さであって、所定の径の丸棒14が配置され、その不良
部位Dのほぼ全厚みをカバーした状態に埋設される。
In the above description, the thickness D of the defective portion near the top of the concrete is roughly specified from empirical values according to the concrete casting depth, concrete material, used muddy water, and the like. Based on this, before casting or immediately after casting, and before solidification of the concrete C, as shown in (a), the length corresponding to the thickness of the defective portion D and having a predetermined diameter A round bar 14 is arranged and buried in a state of covering almost the entire thickness of the defective portion D.

【0016】なお、丸棒14は打設以前に配置した場合
には、ガイドウオール10などに固定する手段や、他の
設備機械類と輻輳するので、コンクリートの打設が終了
し、固化する以前の間に埋設することが好ましい。ま
た、その後の抜取り作業性を考慮して丸棒14の表面は
なめらかな平滑面とするのがよい。
If the round bar 14 is placed before the casting, the round bar 14 is congested with the means for fixing to the guide wall 10 and other equipment and machinery. It is preferable to be buried between them. The surface of the round bar 14 is preferably a smooth and smooth surface in consideration of the subsequent workability.

【0017】そして、この実施形態では丸棒14が幅方
向に二本埋設してあるが、図の紙面と直交する方向にも
等間隔で配列されている。また、丸棒14の径や、配置
間隔は、次に述べるコンクリート破砕用の膨張性薬剤の
体膨張率などの破砕性能を考慮して選定される。
Although two round bars 14 are buried in the width direction in this embodiment, they are also arranged at equal intervals in a direction perpendicular to the plane of the drawing. In addition, the diameter and the arrangement interval of the round bar 14 are selected in consideration of crushing performance such as the body expansion rate of the expansive agent for concrete crushing described below.

【0018】次に、コンクリートの固化後に丸棒14を
抜取り、(b)に示すように、その抜孔16に静圧付加
体としての膨張性薬剤18を順次注入充填する。膨脹性
薬剤18としては、たとえば株式会社小野田製の「スー
パーブライスター(商品名)」ないしは同社製の「ブラ
イスター(商品名)」等の固化時における体膨張率の高
い石灰系の薬剤が好ましい。
Next, after the concrete is solidified, the round bar 14 is removed, and as shown in (b), an expanding agent 18 as a static pressure additive is sequentially injected and filled into the hole 16 thereof. As the intumescent agent 18, for example, a lime-based agent having a high body expansion rate at the time of solidification such as "Super Blister (trade name)" manufactured by Onoda Co., Ltd. or "Blyster (trade name)" manufactured by Onoda is preferable. .

【0019】そして、薬剤18の固化反応が進行するに
つれて、薬剤18は径方向に膨張する結果、抜孔16の
周囲ですでに固結しているコンクリートCを圧し、ま
た、この部位ではコンクリート強度が低下している部位
でもあるため、抜穴16の周囲は図に示すごとく、ひび
割れが進行する。
Then, as the solidification reaction of the chemical 18 progresses, the chemical 18 expands in the radial direction, and as a result, presses the concrete C already solidified around the hole 16, and the concrete strength is reduced at this portion. As shown in the figure, cracking progresses as shown in the figure because it is a lowered portion.

【0020】そして、薬剤18の最終反応終了後は、
(c)に示すごとく、個々の細片20に破砕される。薬
剤18も同様に破砕され、細片20に混在する。なお、
ほぼ3時間〜10時間経過後には膨張反応が終了し、抜
穴16への充填後は人手を煩わすことなく膨張に起因し
た静圧のみによって自動的にコンクリートCの破砕が行
われることになる。
After completion of the final reaction of the drug 18,
As shown in (c), the individual pieces 20 are crushed. The drug 18 is similarly crushed and mixed in the strip 20. In addition,
After about 3 hours to 10 hours, the expansion reaction is completed, and after filling the hole 16, the concrete C is automatically crushed only by the static pressure resulting from the expansion without any trouble.

【0021】従って、その後は人力、あるいは不良部位
Dに鉄筋などが輻輳していない場合には、溝幅に応じた
幅のショベルを備えたパワーショベルなどの重機を用い
て細片20を順次除去することにより、(d)に示すよ
うに、コンクリート強度の高い部位のみが地中連続壁の
天端となる。
Therefore, after that, when the reinforcing bar or the like is not congested at the defective portion D, the strips 20 are sequentially removed using a heavy machine such as a power shovel having a shovel having a width corresponding to the groove width. By doing so, as shown in (d), only the portion with high concrete strength becomes the top end of the underground continuous wall.

【0022】この後は必要に応じて新たな天端位置にフ
レッシュコンクリートを打設すれば、仕上げ工事が完了
する。
After that, if necessary, fresh concrete is poured into a new top position to complete the finishing work.

【0023】なお、前記実施の形態では静圧付加体とし
て膨張性薬剤を用いたが、これに代えて、前記抜穴16
内にこれより小さな径であって、径方向に拡張可能なジ
ャッキを挿入し、その拡張操作により不良部位の破砕を
行ってもよく、いずれの作業形態であっても、静圧によ
りコンクリートが破砕されるため、作業に伴い粉塵や騒
音が発生することがなく、周囲環境や作業員に対する配
慮も不要となるし、特にジャッキの場合には比較的短時
間で破砕作業を完了することができる。また、比較的小
さな爆発力を呈する爆発物を抜穴16に装填して破砕作
業を行ってもよく、この場合には、さらに短時間で破砕
作業を完了することができる。
In the above embodiment, the expansive drug is used as the static pressure applying body.
A jack with a smaller diameter than this and which can be expanded in the radial direction may be inserted, and the defective portion may be crushed by the expansion operation. Therefore, no dust or noise is generated during the operation, no consideration is required for the surrounding environment and workers, and especially in the case of a jack, the crushing operation can be completed in a relatively short time. Further, an explosive having a relatively small explosive power may be loaded into the hole 16 to perform the crushing operation. In this case, the crushing operation can be completed in a shorter time.

【0024】[0024]

【発明の効果】以上の説明より明らかなように、本発明
によるコンクリートの除去方法にあっては、破砕作業に
対して大型機械が不要で、孔数に応じてその周囲コンク
リートを効率よく破砕でき、工期短縮に有効である。
As is apparent from the above description, the concrete removing method according to the present invention does not require a large machine for the crushing operation, and can efficiently crush the surrounding concrete according to the number of holes. It is effective for shortening the construction period.

【0025】膨脹性薬剤やジャッキの静圧により破砕作
業を行う場合には、従来のはつり作業に比べ、騒音、振
動、粉塵の発生もないため、周囲環境への悪影響がな
く、作業員の健康管理の点からも好ましい。また、爆発
物を採用する場合には、短時間で破砕作業を完了するこ
とができ、不良部位の除去を短期で行える。
When crushing work is performed by the static pressure of an inflatable chemical or a jack, there is no generation of noise, vibration and dust as compared with the conventional hanging work, so there is no adverse effect on the surrounding environment and the worker's health is reduced. It is also preferable from the viewpoint of management. Also, when explosives are used, the crushing operation can be completed in a short time, and the defective portion can be removed in a short time.

【図面の簡単な説明】[Brief description of the drawings]

【図1】(a)〜(d)は本発明のコンクリート除去手
順を示す説明用断面図である。
1 (a) to 1 (d) are explanatory sectional views showing a concrete removing procedure of the present invention.

【符号の説明】[Explanation of symbols]

12 掘削溝 14 棒状体 16 抜孔 18 膨張性薬剤 E 地盤 D 不良部位 C コンクリート Reference Signs List 12 excavation groove 14 rod-like body 16 drilling hole 18 expansive medicine E ground D defective part C concrete

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 地盤中に掘削された孔ないし溝にコンク
リートを打設し、該コンクリートの固化後、コンクリー
トの天端近傍に形成される仕上り不良部位を除去する方
法であって、 コンクリート打設前ないしはコンクリートの固化以前
に、予測される不良発生部位の厚みに応じた長さの棒状
体をコンクリートの天端から一ないし複数本打込み、該
コンクリートの固化後に、前記棒状体を引抜いて孔を形
成し、次いで該孔の内壁に外方に向けて圧力を加えるこ
とで、孔周囲のコンクリートを破砕してからこれを撤去
することを特徴とする地中コンクリート構造物における
コンクリートの除去方法。
1. A method for casting concrete in a hole or a groove excavated in the ground, and after solidifying the concrete, removing a poor finish portion formed near a top end of the concrete, comprising: Before or before solidification of the concrete, one or more rods having a length corresponding to the thickness of the predicted failure site are driven in from the top of the concrete, and after the concrete is solidified, the rods are pulled out to form holes. A method for removing concrete in an underground concrete structure, comprising forming and then applying pressure outwardly on the inner wall of the hole to crush and remove the concrete around the hole.
【請求項2】 前記圧力が、前記孔内に充填された膨張
性薬剤の膨張により加えられることを特徴とする請求項
1に記載の地中コンクリート構造物におけるコンクリー
トの除去方法。
2. The method for removing concrete in an underground concrete structure according to claim 1, wherein the pressure is applied by expansion of an expandable agent filled in the hole.
【請求項3】 前記圧力が、前記孔内に挿通された爆発
物の爆発により加えられることを特徴とする請求項1に
記載の地中コンクリート構造物におけるコンクリートの
除去方法。
3. The method for removing concrete from an underground concrete structure according to claim 1, wherein the pressure is applied by an explosion of an explosive inserted into the hole.
【請求項4】 前記圧力が、前記孔内に挿通されて径方
向に伸長可能なジャッキにより加えられることを特徴と
する請求項1に記載の地中コンクリート構造物における
コンクリートの除去方法。
4. The method according to claim 1, wherein the pressure is applied by a radially extending jack inserted into the hole.
JP23601097A 1997-09-01 1997-09-01 Removing method of concrete in underground concrete structure Pending JPH1181305A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP23601097A JPH1181305A (en) 1997-09-01 1997-09-01 Removing method of concrete in underground concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP23601097A JPH1181305A (en) 1997-09-01 1997-09-01 Removing method of concrete in underground concrete structure

Publications (1)

Publication Number Publication Date
JPH1181305A true JPH1181305A (en) 1999-03-26

Family

ID=16994453

Family Applications (1)

Application Number Title Priority Date Filing Date
JP23601097A Pending JPH1181305A (en) 1997-09-01 1997-09-01 Removing method of concrete in underground concrete structure

Country Status (1)

Country Link
JP (1) JPH1181305A (en)

Similar Documents

Publication Publication Date Title
JPS5850219A (en) Treatment of head of pile
JPH1181305A (en) Removing method of concrete in underground concrete structure
JP3648664B2 (en) Building renovation method and building
JP2009013660A (en) Method of reinforcing outside of underground structure
KR100446586B1 (en) Soil-Nail able to Withdraw Itself by Blasting
JPS58189414A (en) Construction of sheathing wall
JP2006161450A (en) Pile foundation method
JPH0711232B2 (en) Non-removing earth construction device for foundation piles and non-removing earth construction method for foundation piles
JP2604622B2 (en) Tunnel construction method
JP2561968B2 (en) Construction method of deep underground space
JP2000120066A (en) Execution method for steel pipe pile
JP2741095B2 (en) Pile head treatment method for cast-in-place concrete pile
JPH10325141A (en) Crusher for pile head of cast-in-plate concrete pile and crushing method thereof
JP2001090060A (en) Driving method for pile and constructing method for cut- off wall using the method
JP2000130070A (en) Construction method for vertical shaft for shield
JPH02140323A (en) Formation of soil cement synthetic pile
JP2675858B2 (en) Vertical shaft excavation method
JPH07331666A (en) Slope cutting method
JP2004250897A (en) Earth retaining wall construction method
JPH1037180A (en) Construction method of continuous underground wall
JPH04231593A (en) Method of constructing base of deeper depth vertical shaft constructed with vertical type shield machine
JPS6128046B2 (en)
JPH0317314A (en) Execution of underground continuous wall
JPS62206198A (en) Method of constructing tunnel lining
JP2005194837A (en) Widening method for tunnel