JPH11324345A - Construction method for structure - Google Patents

Construction method for structure

Info

Publication number
JPH11324345A
JPH11324345A JP13085398A JP13085398A JPH11324345A JP H11324345 A JPH11324345 A JP H11324345A JP 13085398 A JP13085398 A JP 13085398A JP 13085398 A JP13085398 A JP 13085398A JP H11324345 A JPH11324345 A JP H11324345A
Authority
JP
Japan
Prior art keywords
formwork
gantry
installation position
temporary girder
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP13085398A
Other languages
Japanese (ja)
Other versions
JP3690463B2 (en
Inventor
Yoji Tate
洋史 舘
Masayoshi Karasawa
正芳 柄澤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP13085398A priority Critical patent/JP3690463B2/en
Publication of JPH11324345A publication Critical patent/JPH11324345A/en
Application granted granted Critical
Publication of JP3690463B2 publication Critical patent/JP3690463B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

PROBLEM TO BE SOLVED: To easily assemble a form and a reinforcement in constructing a new structure of reinforced concrete construction just under an existing structure in a close state. SOLUTION: An elevatable frame 9 is installed below a temporary girder 3 as an existing structure, and with the frame 9 lowered, a form 10 for forming a floor plate 5 as a new structure is supported thereon by a timbering 11 to be arranged in a lower position than the original installation position. After a reinforcement 12 for forming the floor plate 5 on the form 10 is assembled, the frame 9 is raised by a jack 13 or the like to guide the form 10 and the reinforcement 12 to the original installation position, and concrete is placed.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は構造物の構築方法、
特に既設物の直下に近接せしめて鉄筋コンクリート造の
新設構造物を構築するに際して適用して好適な方法に関
する。
The present invention relates to a method for constructing a structure,
In particular, the present invention relates to a method suitable for application when a new reinforced concrete structure is constructed by being brought close to immediately below an existing structure.

【0002】[0002]

【従来の技術】建築工事や土木工事の分野においては、
既設物の直下に近接せしめて新設構造物を設ける場合が
多々ある。たとえば図5に示すような鉄道用の高架橋1
を構築するに際しては、(a)に示すように既存の軌道を
仮設支柱2および仮設桁3により仮支持して車両を運行
しながら、その下方空間に高架橋1を構築する場合があ
る。そのような場合にはまず高架橋1の柱4を立設し、
次いでその上部に床版5を設けることになるが、新設す
るべき床版5を既設物である仮設桁3に対して十分に近
接させて設けることが一般的であり、したがってそれら
床版5と仮設桁3との間にはごくわずかな間隙しか確保
し得ないことが通常である。
2. Description of the Related Art In the field of construction and civil engineering,
In many cases, a new structure is provided close to immediately below an existing structure. For example, a railway viaduct 1 as shown in FIG.
When the vehicle is operated while the existing track is temporarily supported by the temporary columns 2 and the temporary girders 3 as shown in (a), the viaduct 1 may be constructed in the space below the existing track. In such a case, first, pillar 4 of viaduct 1 is erected,
Next, the floor slab 5 is to be provided on the upper part thereof. Generally, the floor slab 5 to be newly installed is provided sufficiently close to the temporary girder 3 which is an existing object. Usually, only a very small gap can be secured between the temporary girder 3 and the temporary girder 3.

【0003】[0003]

【発明が解決しようとする課題】ところで、上記のよう
に既設物の直下に近接せしめて新設構造物を設ける場合
において、新設構造物が鉄筋コンクリート造である場合
には、既設物が新設構造物の施工の障害となることがあ
る。たとえば図5に示した場合において新設すべき高架
橋1が鉄筋コンクリート造であるときには、床版5を施
工するに際してコンクリート打設用の型枠を仮設桁3の
直下に設け、その型枠上に鉄筋を組み立てることになる
のであるが、床版5を仮設桁3に対して十分に近接させ
て設ける必要があることから仮設桁3の下方に型枠工事
や鉄筋工事を行うためのスペースが殆ど確保し得ず、そ
の作業が極めて困難なものとなる。
In the case where a new structure is provided immediately below the existing structure as described above, if the new structure is a reinforced concrete structure, the existing structure is replaced with the new structure. It may hinder construction. For example, in the case shown in FIG. 5, when the viaduct 1 to be newly constructed is a reinforced concrete structure, a concrete casting formwork is provided immediately below the temporary girder 3 when the floor slab 5 is constructed, and the reinforcing steel is placed on the formwork. It is necessary to provide the floor slab 5 close enough to the temporary girder 3, so that there is almost enough space below the temporary girder 3 for formwork and rebar work. And the operation becomes extremely difficult.

【0004】このため、従来においては型枠工事や鉄筋
工事が可能な程度に床版5と仮設桁3との間の間隙を必
要以上に大きく確保するか、もしくは型枠工事や鉄筋工
事が不要な構造や工法を採用するしかないが、そのよう
なことは不都合であるので有効な改善策が要望されてい
た。
For this reason, in the related art, a gap between the floor slab 5 and the temporary girder 3 is made larger than necessary so that formwork and reinforcing work can be performed, or formwork and reinforcing work are not required. There is no other choice but to adopt a simple structure and construction method, but such an inconvenience is inconvenient.

【0005】[0005]

【課題を解決するための手段】上記事情に鑑み、本発明
は、既設物の直下に近接せしめて鉄筋コンクリート造の
新設構造物を構築するに際して適用する構造物の構築方
法であって、前記既設物の下方において昇降可能な架台
を設置し、該架台を降下せしめた状態で該架台上に前記
新設構造物を形成するための型枠を支保工により支持し
て本来の設置位置よりも低い位置に配置するとともに、
該型枠上に前記新設構造物を形成するための鉄筋を組み
立て、しかる後に、前記架台を上昇せしめて前記型枠お
よび前記鉄筋を本来の設置位置に導いてコンクリートを
打設することを特徴とする。
SUMMARY OF THE INVENTION In view of the above circumstances, the present invention relates to a method of constructing a structure to be applied when a new reinforced concrete structure is constructed by being brought close to immediately below an existing structure. A frame that can be raised and lowered is installed below the frame, and a frame for forming the new structure is supported on the frame with the support lowered by the shoring while the frame is lowered to a position lower than the original installation position. Place it,
Assembling rebar for forming the new structure on the formwork, and then raising the gantry to guide the formwork and the rebar to the original installation position and cast concrete. I do.

【0006】[0006]

【発明の実施の形態】以下、本発明の実施形態を図1〜
図4を参照して説明する。以下で説明する実施形態は、
図5に示したように既存の軌道を仮設支柱2および仮設
桁3により仮支持しながらその下方空間にラーメン構造
の鉄筋コンクリート造の高架橋1を新設する場合に適用
したものである。この場合、新設するべき高架橋1の床
版5は可及的に仮設桁3に対して近接して設けることが
要求され、したがってその床版5と仮設桁3との間には
50〜150mm程度の間隙しか確保し得ない状況にあ
る。なお、図1〜図4においていずれも(a)は横断面
図、(b)は縦断面図であって、(b)に示されるよう
に本実施形態では高架橋1の施工をその長さ方向に一定
長ずつ(図示例のものは3スパンずつ)行うものとして
いる。また、図1〜図4においては新設すべき高架橋1
および既設物である仮設支柱2と仮設桁3はいずれも鎖
線で示してある(ただし(b)においては仮設支柱2お
よび仮設桁3の図示は省略している)。
BRIEF DESCRIPTION OF THE DRAWINGS FIG.
This will be described with reference to FIG. The embodiments described below are:
As shown in FIG. 5, the present invention is applied to a case in which an existing track is temporarily supported by a temporary support 2 and a temporary girder 3 and a reinforced concrete viaduct 1 having a rigid frame structure is newly installed in a space below the temporary support 2 and the temporary girder 3. In this case, the floor slab 5 of the viaduct 1 to be newly installed is required to be provided as close to the temporary girder 3 as possible, and therefore, the space between the floor slab 5 and the temporary girder 3 is about 50 to 150 mm. It is in a situation where only the gap can be secured. 1 to 4, (a) is a cross-sectional view and (b) is a longitudinal cross-sectional view. In this embodiment, as shown in (b), the construction of the viaduct 1 is performed in the length direction. At a fixed length (3 spans in the illustrated example). In addition, in FIGS.
In addition, both the temporary support 2 and the temporary girder 3, which are existing objects, are indicated by chain lines (however, the illustration of the temporary support 2 and the temporary girder 3 is omitted in (b)).

【0007】本実施形態の構築方法では、まず、図1に
示すように高架橋1を支持するための杭6、基礎7を施
工するとともに、柱4の下端部すなわち柱脚部4aのみ
を先行施工し、柱脚部4aの上部には柱筋8を突出せし
めておく。これらの施工は仮設桁3と地表との間に十分
なスペースが確保されるので通常の工法により支障なく
行い得る。
In the construction method according to the present embodiment, first, as shown in FIG. 1, a pile 6 and a foundation 7 for supporting the viaduct 1 are constructed, and only the lower end of the column 4, that is, only the column base 4a is constructed in advance. Then, the column bar 8 is made to protrude above the column base 4a. Since a sufficient space is secured between the temporary girder 3 and the ground surface, these constructions can be performed without any trouble by a normal construction method.

【0008】次いで、図2に示すように、仮設桁3の下
方において昇降可能な架台9を地表部に設置し、その上
部に床版5を形成するための型枠10を支保工11によ
り支持して設置する。この際、架台9は地表部に降下さ
せておき、型枠10は本来の設置位置(すなわち実際に
床版5を形成するべき位置)よりも低い位置となるよう
に支保工11の高さを設定する。これにより、支保工1
1および型枠10の組立作業は実質的に地表部で行い得
て高所作業とはならず、また、仮設桁3の下方に作業ス
ペースを確保し得るから型枠10の組立作業を容易に行
い得る。
Next, as shown in FIG. 2, a pedestal 9 which can be raised and lowered is provided below the temporary girder 3 on the surface of the ground, and a formwork 10 for forming the floor slab 5 is supported by the support 11 above the gantry 9. And install it. At this time, the gantry 9 is lowered to the surface of the ground, and the height of the shoring 11 is set so that the formwork 10 is at a position lower than the original installation position (that is, the position where the floor slab 5 is to be actually formed). Set. As a result, Shoring 1
The work for assembling the formwork 1 and the formwork 10 can be performed substantially at the surface of the ground and is not a work at a high place, and a work space can be secured below the temporary girder 3 so that the work for assembling the formwork 10 can be easily performed. Can do.

【0009】次に、図3に示すように、上記で組み立て
た型枠10の上部に床版5中に埋設するべき鉄筋12を
組み立てる。これらの鉄筋12を組み立てる作業も、型
枠10が本来の設置位置よりも低い位置に配置されてい
ることから、仮設桁3との間に作業スペースが確保さ
れ、支障なく実施することができる。
Next, as shown in FIG. 3, a reinforcing bar 12 to be embedded in the floor slab 5 is assembled on the upper part of the formwork 10 assembled above. The work for assembling these reinforcing bars 12 can be carried out without any trouble because a work space is secured between the formwork 10 and the temporary girder 3 because the formwork 10 is located at a position lower than the original installation position.

【0010】上記の鉄筋12の組立作業が完了したら、
図4に示すようにジャッキ13を用いて架台9を徐々に
上昇せしめ、鉄筋12および型枠10を本来の設置位置
すなわち床版5を形成するべき位置まで上昇させる。そ
して、鉄筋12および型枠10をその位置に保持したま
まで、すでに施工が完了している柱脚部4aの上部に継
ぎ足す形で柱筋14を組み立て、その周囲に柱型枠(図
示せず)を組み立てる。しかる後に、コンクリートを打
設して床版5と柱4を一体に形成すれば図5(b)に示
したような高架橋1が完成する。なお、ジャッキ13と
しては汎用の油圧ジャッキやセンターホールジャッキ等
を任意に採用可能であるし、架台9を地表より押し上げ
る形式のもののみならず架台9を上方より吊り上げる形
式のものも採用可能である。また、コンクリート打設荷
重は型枠10、支保工11、架台9を介してジャッキ1
3により受けることが可能であるが、必要に応じて架台
9と地表との間にコンクリート打設荷重を受けるための
他の支保工を適宜設ければ良い。
[0010] When the assembling work of the reinforcing bar 12 is completed,
As shown in FIG. 4, the gantry 9 is gradually raised by using the jack 13, and the reinforcing bar 12 and the formwork 10 are raised to the original installation position, that is, the position where the floor slab 5 is to be formed. Then, while holding the reinforcing bar 12 and the formwork 10 in that position, the column reinforcing bar 14 is assembled in such a manner as to be added to the upper portion of the column base 4a which has already been constructed, and a column formwork (see FIG. Assemble). After that, if the concrete is cast and the floor slab 5 and the pillar 4 are integrally formed, the viaduct 1 as shown in FIG. 5B is completed. In addition, as the jack 13, a general-purpose hydraulic jack, a center hole jack, or the like can be arbitrarily used, and not only a type in which the gantry 9 is pushed up from the surface of the ground but also a type in which the gantry 9 is hung from above. . In addition, the concrete placing load is applied to the jack 1 via the formwork 10, the support 11, and the gantry 9.
3, it is possible to appropriately provide another support between the gantry 9 and the ground surface to receive the concrete placing load.

【0011】以上のように、型枠10および鉄筋12を
架台9上において本来の設置位置よりも下げて低い位置
として組み立ててから、架台9を上昇させて本来の位置
に配置することにより、型枠10および鉄筋12の組立
作業に際して仮設桁3が障害になることがなく、またそ
れらの作業を高所ではなく地表部において容易に行うこ
とができ、しかも架台9をジャッキ13によりジャッキ
アップすることのみで鉄筋12および型枠10を本来の
設置位置まで速やかにかつ容易に上昇させることが可能
であり、仮設桁3により仮支持している鉄道の運行に支
障を来すこともない。
As described above, by assembling the mold 10 and the reinforcing bar 12 on the gantry 9 at a lower position than the original installation position, and then raising the gantry 9 and disposing it in the original position, The temporary girder 3 does not hinder the work of assembling the frame 10 and the reinforcing bar 12, and the work can be easily performed not on a high place but on the ground surface, and the gantry 9 is jacked up by the jack 13. It is possible to quickly and easily raise the reinforcing bar 12 and the formwork 10 to the original installation position only by using only the temporary girder 3, and there is no hindrance to the operation of the railway temporarily supported by the temporary girder 3.

【0012】以上のことから、上記方法によれば、型枠
10や鉄筋12を最初から本来の位置に設置する場合に
比較すると作業性を格段に改善することができるし、従
来のように施工性を考慮して仮設桁3と床版5との間の
間隙を必要以上に大きく確保するような必要がなく、ま
た従来においては作業スペースが確保できないために採
用することができなかった構造や工法も採用可能とな
る。
From the above, according to the above method, the workability can be remarkably improved as compared with the case where the formwork 10 and the reinforcing bar 12 are installed in their original positions from the beginning, It is not necessary to secure an excessively large gap between the temporary girder 3 and the floor slab 5 in consideration of the performance, and a structure which could not be adopted because a work space could not be secured conventionally. The construction method can also be adopted.

【0013】なお、本発明は上記実施形態のように鉄道
用の高架橋を仮設桁の下方に構築する場合に限らず、種
々の既設の構造物の下方に近接せしめて鉄筋コンクリー
ト造の構造物を新設する場合全般に広く適用できるもの
であって、既設物および新設構造物の形態や規模、用途
は何ら限定されるものではない。
The present invention is not limited to the case where the railway viaduct is constructed below the temporary girder as in the above-described embodiment, but is constructed in such a manner that a new reinforced concrete structure is constructed by being brought close to below various existing structures. In this case, the present invention can be widely applied in general, and the form, scale, and use of existing and new structures are not limited at all.

【0014】[0014]

【発明の効果】以上で説明したように、本発明は、既設
物の下方に昇降可能な架台を設置し、その架台上におい
て型枠および鉄筋を本来の設置位置よりも低い位置に下
げた状態で組み立てた後、架台を上昇せしめてそれら型
枠および鉄筋を本来の設置位置に導いてコンクリートを
打設するようにしたから、型枠および鉄筋の組立作業に
際して既設物が障害になることがなく、したがって型枠
や鉄筋を最初から本来の位置に設置する場合に比較する
と作業性を格段に改善することができ、その結果、従来
のように施工性を考慮して既設物と新設構造物との間隙
を必要以上に大きく確保するような必要がなく、従来に
おいては作業スペースが確保できないために採用するこ
とができなかった構造や工法も採用可能となる。
As described above, according to the present invention, a frame that can be moved up and down is installed below an existing object, and the formwork and reinforcing bars are lowered to a position lower than the original installation position on the frame. After assembling, the gantry was raised to guide the formwork and rebar to the original installation position and cast concrete, so that the existing work did not become an obstacle when assembling the formwork and rebar. Therefore, workability can be remarkably improved as compared with the case where the formwork and rebar are installed in the original position from the beginning, and as a result, the existing structure and the new structure can be It is not necessary to secure an unnecessarily large gap, and a structure or a construction method that could not be adopted because a work space could not be conventionally secured can be adopted.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明の構築方法により既設物の直下に高架
橋を構築する場合の実施形態を示すもので、基礎および
柱脚部を先行施工した状態を示す図である。
FIG. 1 is a view showing an embodiment in which a viaduct is constructed immediately below an existing object by a construction method of the present invention, and is a view showing a state in which a foundation and a column base have been pre-constructed.

【図2】 同、架台上に型枠を設置した状態を示す図で
ある。
FIG. 2 is a diagram showing a state where a formwork is installed on a gantry.

【図3】 同、型枠上に鉄筋を組み立てた状態を示す図
である。
FIG. 3 is a diagram showing a state where a reinforcing bar is assembled on a formwork.

【図4】 同、架台を昇降させて型枠および鉄筋を本来
の位置に配置した状態を示す図である。
FIG. 4 is a view showing a state where the gantry is moved up and down to dispose a formwork and a reinforcing bar at their original positions.

【図5】 既設物である仮設桁の直下に新設構造物であ
る高架橋を設置する場合の例を示す図である。
FIG. 5 is a diagram showing an example of a case where a viaduct as a new structure is installed immediately below a temporary girder as an existing object.

【符号の説明】[Explanation of symbols]

1 高架橋(新設構造物) 3 仮設桁(既設物) 4 柱 5 床版 9 架台 10 型枠 11 支保工 12 鉄筋 13 ジャッキ DESCRIPTION OF SYMBOLS 1 Viaduct (new construction) 3 Temporary girder (existing thing) 4 Pillar 5 Floor slab 9 Girder 10 Formwork 11 Shoring 12 Steel bar 13 Jack

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 既設物の直下に近接せしめて鉄筋コンク
リート造の新設構造物を構築するに際し、前記既設物の
下方において昇降可能な架台を設置し、該架台を降下せ
しめた状態で該架台上に前記新設構造物を形成するため
の型枠を支保工により支持して本来の設置位置よりも低
い位置に配置するとともに、該型枠上に前記新設構造物
を形成するための鉄筋を組み立て、しかる後に、前記架
台を上昇せしめて前記型枠および前記鉄筋を本来の設置
位置に導いてコンクリートを打設することを特徴とする
構造物の構築方法。
When a new reinforced concrete structure is constructed by being brought close to immediately below an existing object, a pedestal that can be raised and lowered is installed below the existing object, and the gantry is lowered onto the pedestal in a state where the pedestal is lowered. A formwork for forming the new structure is supported by a shoring and placed at a position lower than the original installation position, and a reinforcing bar for forming the new structure is assembled on the formwork. A method of constructing a structure, comprising raising the gantry, guiding the formwork and the rebar to the original installation position, and placing concrete.
JP13085398A 1998-05-13 1998-05-13 Construction method of viaduct Expired - Fee Related JP3690463B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13085398A JP3690463B2 (en) 1998-05-13 1998-05-13 Construction method of viaduct

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13085398A JP3690463B2 (en) 1998-05-13 1998-05-13 Construction method of viaduct

Publications (2)

Publication Number Publication Date
JPH11324345A true JPH11324345A (en) 1999-11-26
JP3690463B2 JP3690463B2 (en) 2005-08-31

Family

ID=15044232

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13085398A Expired - Fee Related JP3690463B2 (en) 1998-05-13 1998-05-13 Construction method of viaduct

Country Status (1)

Country Link
JP (1) JP3690463B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106555379A (en) * 2015-09-30 2017-04-05 中铁十八局集团第四工程有限公司 Pass through both wired elevated formation level Combined temporary bridge construction methods

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106555379A (en) * 2015-09-30 2017-04-05 中铁十八局集团第四工程有限公司 Pass through both wired elevated formation level Combined temporary bridge construction methods

Also Published As

Publication number Publication date
JP3690463B2 (en) 2005-08-31

Similar Documents

Publication Publication Date Title
JP2007077630A (en) Continuous girder using precast main-girder segment, and its erection method
KR20090098180A (en) Method for broadening width of existing bridge without temporary road
JP4406879B2 (en) Bridge girder construction method
JPH11324345A (en) Construction method for structure
JP2980567B2 (en) How to replace the bearing device
JP2009097197A (en) Method of constructing pillar head
JP5003253B2 (en) RC beam construction method
KR101194866B1 (en) Rahmen bridge construction method using longitudinal and lateral steel member
JPH05179647A (en) Supporting structure for earth retaining wall
JP7012486B2 (en) Bridge construction method
JP2020186516A (en) Method of constructing bridge railing
JP3407168B2 (en) Foundation of new building using existing pile foundation
JP3905021B2 (en) Construction method of viaduct pier
KR20120124129A (en) Non-supporting rc top down construction method using hybrid formwork beam
KR102280901B1 (en) Combined structure for half section slab and girder
JPH0336362B2 (en)
JP3338240B2 (en) Construction method for reinforced concrete structures
CN218373897U (en) Assembly type reinforced concrete inner supporting structure capable of adjusting axial force
JP3660657B2 (en) Construction method of viaduct
JPH1088522A (en) High level bridge supportless construction method
JPH1113306A (en) Building supporting method at installation of vibration isolation device
JP2534009B2 (en) Form support for overhang
JPH05148817A (en) Construction of pc bridge
JP2000356041A (en) Method for placing concrete
JPH1143955A (en) Basement constructing method in existing building

Legal Events

Date Code Title Description
A977 Report on retrieval

Effective date: 20040729

Free format text: JAPANESE INTERMEDIATE CODE: A971007

A131 Notification of reasons for refusal

Effective date: 20050104

Free format text: JAPANESE INTERMEDIATE CODE: A131

A521 Written amendment

Effective date: 20050228

Free format text: JAPANESE INTERMEDIATE CODE: A523

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050524

A61 First payment of annual fees (during grant procedure)

Effective date: 20050607

Free format text: JAPANESE INTERMEDIATE CODE: A61

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees