JPH11289662A - Load interchange method in power distribution system - Google Patents

Load interchange method in power distribution system

Info

Publication number
JPH11289662A
JPH11289662A JP10093310A JP9331098A JPH11289662A JP H11289662 A JPH11289662 A JP H11289662A JP 10093310 A JP10093310 A JP 10093310A JP 9331098 A JP9331098 A JP 9331098A JP H11289662 A JPH11289662 A JP H11289662A
Authority
JP
Japan
Prior art keywords
power supply
power
adjacent
load
supply
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP10093310A
Other languages
Japanese (ja)
Inventor
Hiroyuki Fudo
弘幸 不動
Takashi Ganji
崇 元治
Chiyoutetsu Fujita
超徹 藤田
Yoshikazu Fukuyama
良和 福山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kansai Electric Power Co Inc
Fuji Electric Co Ltd
Original Assignee
Kansai Electric Power Co Inc
Fuji Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kansai Electric Power Co Inc, Fuji Electric Co Ltd filed Critical Kansai Electric Power Co Inc
Priority to JP10093310A priority Critical patent/JPH11289662A/en
Publication of JPH11289662A publication Critical patent/JPH11289662A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

PROBLEM TO BE SOLVED: To secure a power for to interchanging and supply reserves, by using object knowledge expression or the like due to an expart system for determining cascade interchange when the capacity of the adjacent power supply of a section to be interchanged is insufficient. SOLUTION: When an accident occurs at a point F on the feeder of a power supply G1 , a total amount of lead L1 of a section to be interchanged being detected by performing search in all directions from one node in the section to be interchanged is compared with sum ΣRG2 of the supply reserves of the group of adjacent power supples G2 . As a result, when cascade interchange is required, the adjacent power supply G2 is set to a cascade target power supply. Then, a power supply that is adjacent to the power supply G2 and has large supply reserves is set to a cascade power supply G3 , the sum of the sum ΣRG2 of the supply reserves of the group of adjacent power supplys G2 and supply reserves RG3 of the cascade power supply G3 is compared with the total amount of load L1 of the section to be interchanged. As a result, when cascade interchange can be made, switching means CB, CB1 , and CB2 for coordinating the adjacent power supplies G1 -G3 and the switching state of a switching means S1 on the feeder are determined.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、例えば配電営業所
における制御用コンピュータ等に付加される機能であっ
て、配電系統の構成、被融通区間、各負荷容量及び各電
源とその容量が与えられた時に、負荷融通の第1段階と
して、被融通区間の隣接電源の容量が不足する場合に、
エキスパートシステム(以下、必要に応じてESと略称
する)によりオブジェクト知識表現及びこれを利用した
探索手法を用いていわゆる玉突融通方法を作成する方
法、並びに、これに続く第2段階として、遺伝的アルゴ
リズム(以下、必要に応じてGAと略称する)を用いて
被融通区間を最適に隣接電源にて分担させるようにした
配電系統における負荷融通方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a function added to a control computer or the like in a distribution office, for example, in which a configuration of a distribution system, a section to be interchanged, each load capacity, each power supply and its capacity are given. When the capacity of the adjacent power supply in the section to be accommodated becomes insufficient as the first stage of load accommodation,
An expert system (hereinafter abbreviated as ES if necessary) is a method for creating a so-called ball-swap method using an object knowledge expression and a search method using the object knowledge expression. The present invention relates to a load accommodating method in a distribution system in which a section to be accommodated is optimally shared by adjacent power sources using an algorithm (hereinafter, abbreviated as GA as necessary).

【0002】[0002]

【従来の技術及び発明が解決しようとする課題】いわゆ
る玉突融通は既に自動化されているが、従来では、電力
用データベースから展開された配列を利用した発見的な
探索手法を用いて玉突融通電源を求めていた。また、被
融通区間については、最適な分割を行うことなく最も容
量が大きい電源に被融通区間を一括分担させていた。
2. Description of the Related Art The so-called ball-swapping has already been automated, but conventionally, the ball-swapping has been performed using a heuristic search method using an array developed from a power database. I was looking for power. Further, in the section to be interchanged, the section to be interchanged is collectively shared by the power source having the largest capacity without performing the optimal division.

【0003】しかるに、この従来の手法では、データの
表現が煩雑であり、負荷融通プログラムを作成するメー
カ及びこれを使用するユーザの両者にとって、プログラ
ムの作成や修正が困難であった。また、被融通区間を最
も容量が大きい電源に一括分担させていたため、電源容
量が不十分な場合には融通が不可能になる場合もあっ
た。更に、従来ではより大規模な被融通区間に対応する
ことが困難であった。
However, in this conventional method, the expression of data is complicated, and it is difficult for both a maker who creates a load accommodation program and a user who uses the program to create or modify the program. In addition, since the section to be accommodated is shared by the power supply having the largest capacity, the accommodating section may not be able to be provided if the power supply capacity is insufficient. Furthermore, it has been difficult in the past to cope with a larger-scale flexible section.

【0004】一方、配電自動化が推進されている現状に
おいて、負荷融通の第1段階である電源フィーダの決定
にあたっては、放射状負荷や電源容量制約等の配電ネッ
トワークの制約下でどの電源から電力を供給するかを決
定することが必要であり、これはグラフの分割問題とい
う一種の組合せ最適化問題と考えることができる。
On the other hand, in the current situation where power distribution automation is promoted, when determining the power supply feeder, which is the first stage of load accommodation, which power source supplies power under the restrictions of the power distribution network such as the radial load and power supply capacity restrictions. It is necessary to determine whether to do this, and this can be considered as a kind of combinatorial optimization problem called a graph partitioning problem.

【0005】この問題に対してはこれまで様々な手法が
提案されているが、GAは組合せ最適化問題に有効な手
法として注目されており、発明者等は、負荷融通におけ
る各負荷の電源フィーダの決定問題に対するGAの適用
について既に提案している(福山ほか「負荷融通問題へ
の遺伝的アルゴリズムの適用」電気学会論文誌B,11
4巻4号,平成6年4月)。また、GAを用いた負荷融
通の決定方法を、特開平7−203630号(特願平6
−12098号)として提案している。
Although various methods have been proposed to solve this problem, GA has been noted as an effective method for the combinatorial optimization problem, and the inventors have proposed a power supply feeder for each load in load interchange. Have already proposed the application of GA to the decision problem of Fukuyama (Fukuyama et al., "Application of Genetic Algorithm to Load Interchange Problem", IEICE Transactions B, 11).
Vol. 4, No. 4, April 1994). A method of determining load accommodation using a GA is disclosed in Japanese Patent Application Laid-Open No. 7-203630 (Japanese Patent Application No.
No. 12098).

【0006】ここで、GAは、自然界における淘汰や遺
伝情報の伝達に着目して生物の増殖メカニズムを模擬す
る最適化手法の一種であり、世代を構成する個体の集合
の中で環境に対する適応度の低いものは自然淘汰され、
適応度の高いものが次世代に多く生き残ると共に、遺伝
子操作としての交差や突然変異等を経て次世代を形成し
ていく過程を模擬したものである。このGAは、最適化
において評価関数の勾配を用いる必要がなく、並列処理
による高速化等のメリットにより組合せ最適化問題に有
効なものとして注目され、電力分野においても電源計画
問題や系統電圧の適正化等、様々な分野に応用され始め
ている。
[0006] Here, GA is a kind of optimization technique that simulates the growth mechanism of organisms by focusing on selection and transmission of genetic information in the natural world. Those with low are selected naturally,
This model simulates a process in which highly adaptable ones survive to the next generation and form the next generation through crossover and mutation as genetic manipulation. This GA does not need to use the gradient of the evaluation function in the optimization, and it is attracting attention as an effective one for the combination optimization problem due to the advantage of speeding up by parallel processing, etc. It has begun to be applied to various fields, such as chemical engineering.

【0007】そこで、第1の発明は、負荷融通の第1段
階として、被融通区間の隣接電源の容量が不足する場合
に、ESにより、オブジェクト知識表現及びこれを利用
した探索手法を用いて玉突融通方法を作成する方法を提
案し、また、第2の発明は、これに続く第2段階とし
て、GAを用いて実際の融通計算を行い、被融通区間を
最適に隣接電源にて分担させるようにした配電系統にお
ける負荷融通方法を提案し、前述した従来技術が有する
種々の問題を解決することを課題としている。
Therefore, the first aspect of the present invention provides, as the first stage of load accommodation, when the capacity of the adjacent power source in the section to be accommodated is insufficient, the ES uses an object knowledge expression and a search method using the object knowledge expression. The second invention proposes a method of creating an abrupt accommodation method, and the second invention performs an actual accommodation calculation using a GA as a subsequent second step, and optimally shares the accommodated section with an adjacent power supply. It is an object of the present invention to propose a load accommodating method in a distribution system as described above and to solve various problems of the above-described conventional technology.

【0008】[0008]

【課題を解決するための手段】上記課題を解決するた
め、請求項1記載の発明は、配電系統の構成、供給電力
の被融通区間、各負荷容量及び各電源並びに電源容量が
与えられたときに、被融通区間への再送電を行うために
開閉手段の入切により各負荷に対する電源フィーダを決
定し、被融通区間以外から被融通区間へ電力を融通する
負荷融通方法であって、被融通区間の負荷量総和が隣接
電源群の供給予備力総和を上回る場合に、前記隣接電源
群に隣接する別の隣接電源群から順次、電力を供給する
玉突融通方法において、配電系統を構成するノードをオ
ブジェクト知識を用いて表現し、被融通区間内の1つの
ノードから全方向に探索を行って被融通区間の負荷量総
和及び第1隣接電源群を検出し、被融通区間の負荷量総
和と第1隣接電源群の供給予備力総和とを比較して玉突
融通の要否を判定し、玉突融通が必要と判定された場合
は第1隣接電源群のうち供給予備力が最も小さい電源か
ら玉突対象電源とし、この玉突対象電源に隣接する第2
隣接電源の中で供給予備力が最も大きい電源を第1の玉
突電源として探索し、前記第1隣接電源群の供給予備力
総和と第1の玉突電源の供給予備力との和と、被融通区
間の負荷量総和とを比較して一段玉突融通の可否を判定
し、一段玉突融通が可能と判定された場合に、各隣接電
源を連系する開閉手段及びフィーダ上の開閉手段の開閉
状態を決定し、前記一段玉突融通が不可能と判定された
場合に、前記第1の玉突電源に隣接する第3隣接電源の
中で供給予備力が最も大きい電源を第2の玉突電源とし
て探索し、前記第1隣接電源群の供給予備力総和と第1
及び第2の玉突電源の供給予備力との和と、被融通区間
の負荷量総和とを比較して二段玉突融通の可否を判定
し、二段玉突融通が可能と判定された場合に、各隣接電
源を連系する開閉手段及びフィーダ上の開閉手段の開閉
状態を決定するものである。
In order to solve the above-mentioned problems, the invention according to claim 1 provides a configuration of a power distribution system, a section where power is supplied, a load capacity, a power supply, and a power supply capacity. A load accommodating method for deciding a power feeder for each load by turning on / off the switching means for performing power transmission to the accommodating section, and accommodating power from the section other than the accommodating section to the accommodating section. When the total load amount of the section exceeds the total supply reserve capacity of the adjacent power supply group, the nodes constituting the power distribution system in the ball-adjusting method for sequentially supplying power from another adjacent power supply group adjacent to the adjacent power supply group Is expressed using object knowledge, a search is performed in all directions from one node in the flexible section to detect the total load amount of the flexible section and the first adjacent power supply group, and the total load amount of the flexible section and First adjacent power supply group A comparison is made with the total supply reserve to determine the necessity of ballistic accommodation. If it is determined that ballistic accommodation is necessary, the power supply with the smallest supply reserve in the first adjacent power supply group is determined as the power supply targeted for collision. , A second power supply adjacent to this
The power supply having the largest supply reserve among the adjacent power supplies is searched for as the first ballistic power supply, and the sum of the supply reserve power of the first adjacent power supply group and the supply reserve of the first ballistic power supply is calculated; Comparing the sum of the load amounts of the sections to be interchanged with each other to determine whether or not the one-stage ball collision can be accommodated, and when it is determined that the one-stage ball collision can be accommodated, the opening / closing means for interconnecting each adjacent power supply and the opening / closing means on the feeder Is determined, and when it is determined that the one-stage collision is impossible, the power supply having the largest supply reserve among the third adjacent power sources adjacent to the first collision power source is set to the second power source. A search is made for a collision power source, and the sum of the reserve reserve of the first adjacent power source group and the first
And the sum of the reserve power of the second ball-shaped power supply and the sum of the load amounts of the sections to be interchanged to determine whether or not the two-stage ball-throwing is possible, and it is determined that the two-stage ball-throwing is possible. In this case, the open / close state of the open / close means for interconnecting the adjacent power sources and the open / close means on the feeder is determined.

【0009】請求項2記載の発明は、請求項1記載の発
明により決定された一段または二段の玉突融通方法に基
づいて、隣接電源の供給予備力を考慮しながら各隣接電
源により電力を供給する負荷を放射状かつ確率的に徐々
に決定していき、すべての負荷について電源が決定した
状態での負荷融通状態をストリング表現に変換して初期
ストリングを生成し、その後、これらの初期ストリング
に対し、電源の供給予備力に基づき適応度を評価して適
応度の高いストリングを選択し、しかる後、ストリング
表現における隣接負荷の境を交差位置として交差を行
い、その結果、配電系統に存在する制約条件に違反する
死滅ストリングが生成された場合にストリングを修正す
ると共に、ストリング表現におけるストリング位置の1
ビットを変換して前記制約条件を満たすように唯一の負
荷の供給電源方向を変更して突然変異操作を行う遺伝的
アルゴリズムにより、被融通区間を各電源に対し最適に
分担させるものである。
According to a second aspect of the present invention, based on the one-stage or two-stage ball-swapping method determined according to the first aspect of the present invention, power is supplied from each of the adjacent power sources while considering the supply reserve of the adjacent power source. The loads to be supplied are gradually and radially determined stochastically, and the load accommodating state with the power supply determined for all loads is converted into a string representation to generate initial strings. On the other hand, the fitness is evaluated based on the supply reserve of the power supply, and a string having a high fitness is selected, and then the intersection is performed with the boundary of the adjacent load in the string representation as an intersection position. As a result, the string exists in the distribution system. Modify the string if a dead string is generated that violates a constraint, as well as one of the string positions in the string representation.
The flexible section is optimally assigned to each power supply by a genetic algorithm that performs a mutation operation by changing the direction of the power supply of the only load so as to satisfy the constraint condition by converting bits.

【0010】[0010]

【発明の実施の形態】以下、図に沿って本発明の実施形
態を説明する。まず、請求項1記載の発明の実施形態を
説明するが、始めに、玉突融通の概念について述べる。
負荷融通は、フィーダ事故等により被融通区間が発生し
た場合、連系遮断器により被融通区間に隣接するフィー
ダから電源の供給を受けるものである。ここで、隣接電
源の供給予備力の総和が被融通区間の負荷量総和を上回
っていれば、通常の融通方法で再送電が可能である。し
かし、隣接電源の供給予備力の総和が被融通区間の負荷
量総和を下回っている場合には、電源容量が不足してお
り、通常の融通方法では送電が不可能となる。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to the drawings. First, an embodiment of the invention described in claim 1 will be described. First, the concept of a ball-and-shoot interchange will be described.
In the load accommodation, when a section to be accommodated occurs due to a feeder accident or the like, power is supplied from a feeder adjacent to the section to be accommodated by an interconnection breaker. Here, if the sum of the reserve powers of the adjacent power supplies exceeds the sum of the load amounts of the sections to be interchanged, the power can be retransmitted by a normal interchange method. However, when the sum of the reserve reserves of the adjacent power supplies is less than the total load amount of the section to be interchanged, the power supply capacity is insufficient, and power cannot be transmitted by a normal interchange method.

【0011】玉突融通とは、上述の如く被融通区間の隣
接電源のみからの融通では不十分な場合(隣接電源の供
給予備力総和<被融通区間の負荷量総和)に、隣接電源
に隣接する別の隣接電源から電力を融通する方法であ
り、通常、大事故が発生した場合の融通手法と考えるこ
とができる。ここで、「どの電源からどの程度融通して
もらえば良いか」は最適化問題であり、玉突融通は大規
模な組合せ最適化問題となる。そこで請求項1記載の発
明では、公知の実用化負荷融通システムで採用している
発見的手法を用い、これをES(オブジェクト知識表現
を用いた探索処理システム)により実現することとし
た。
[0011] As described above, when the accommodation from only the adjacent power supply in the section to be interchanged is insufficient (the sum of the reserve power of the adjacent power supply <the total amount of the load in the section to be interchanged) as described above, the collision of the adjacent power supply is considered. This is a method in which power is exchanged from another adjacent power supply, and can be generally considered as an accommodation method in the event of a major accident. Here, “how much power should be exchanged from which power source” is an optimization problem, and ball collision is a large-scale combination optimization problem. Therefore, in the first aspect of the present invention, a heuristic method employed in a known practical load interchange system is used, and this is realized by an ES (search processing system using an object knowledge expression).

【0012】図1は一段の玉突融通の概念を説明するた
めの図であり、図1(A)は連系遮断器CB1以外に電
源G1と電源G2とを連系可能な連系遮断器CBがある場
合、図1(B)は当該連系遮断器CBがない場合であ
る。いま、電源G1のフィーダ上の地点Fにおいて事故
が発生したとする。この時、被融通区間L1に電源を供
給しようとする電源をG2(G1の第1隣接電源)とす
る。図1(A),(B)に示すように、一段玉突融通
は、電源G2が被融通区間L1に対する電源供給を担当す
るため、自分が担当している負荷の一部(区間L3)を、
更に電源G3(G2の隣接電源であり、電源G1にとっては
第2隣接電源)に担当させる方法である。
[0012] Figure 1 is a diagram for explaining the concept of the ball突融through a one-stage, FIG. 1 (A) interconnection can connects the power supply G 1 and a power supply G 2 other than the interconnection circuit breaker CB 1 FIG. 1B shows a case where there is a system breaker CB and a case where there is no interconnecting breaker CB. Now, the accident occurred at a point F on the feeder of the power supply G 1. At this time, the power to be supplied power to the flexible section L 1 G 2 (first adjacent power G 1). As shown in FIG. 1 (A), (B), one stage ball突融communication, since the power supply G 2 is responsible for power supply to the flexible section L 1, a portion of the load for which you are responsible (section L 3 ),
Further, the power supply G 3 (a power supply adjacent to the power supply G 2 and a second power supply adjacent to the power supply G 1 ) is assigned.

【0013】このためにまず、電源G1,G2間の最上流
の連系遮断器CB1を閉とし、この連系遮断器CB1より
も下流にあって電源G2,G3間にある連系遮断器CB2
閉とする。図1(A)のように、連系遮断器CB1以外
に電源G1と電源G2とを連系可能な連系遮断器CBがあ
る場合には、電源G2,G3の供給予備力をできるだけ平
均化するように、連系遮断器CB1とCB2との間にある
電源G2のフィーダ上のスイッチS1を開とする。一方、
図1(B)のように、連系遮断器CB1以外に電源G1
電源G2とを連系可能な連系遮断器CBがない場合に
は、電源G2のフィーダ上の連系点より下流の範囲内で
できるだけ上流にあるスイッチS1(結果的に図1(A)
と同様)を開とする。これにより、電源G2の供給予備
力をできるだけ大きくすることができる。このとき、電
源G2が電源G1の分担分の一部を連系点から分担するこ
とが不可能であったり、電源G3が電源G2の負荷の一部
を分担できる連系遮断器CB2が見つからなかった場合
には、一段の玉突融通は不可能であると判定する。
For this purpose, first, the most upstream interconnection breaker CB 1 between the power sources G 1 and G 2 is closed, and is located downstream of the interconnection breaker CB 1 and between the power sources G 2 and G 3 . some interconnection circuit breaker CB 2 is closed. As shown in FIG. 1 (A), the in the case where the power supply G 1 and a power supply G 2 other than the interconnection breaker CB 1 has interconnection possible interconnection circuit breaker CB is supplied spare power G 2, G 3 to average as much as possible the forces, the switch S 1 on the feeder of the power supply G 2 located between the interconnection circuit breaker CB 1 and CB 2 opened. on the other hand,
As shown in FIG. 1 (B), the in the absence of a power supply G 1 and a power supply G 2 is interconnection possible interconnection circuit breaker CB in addition to interconnection breaker CB 1 is interconnection on the feeder supply G 2 The switch S 1 as far upstream as possible within the range downstream of the point (FIG. 1 (A)
Open). Thus, it is possible to maximize the reserve capacity of the power supply G 2. At this time, interconnection breaker power G 2 can be shared or it is impossible to share a part of the share of the power supply G 1 from interconnection point, the power supply G 3 some of the load of the power supply G 2 If CB 2 is not found, it is determined that one-stage ballistic accommodation is impossible.

【0014】図2は二段の玉突融通の概念を説明するた
めの図であり、図2(A)は連系遮断器CB1以外に電
源G1と電源G2とを連系可能な連系遮断器CBがある場
合、図2(B)は当該連系遮断器CBがない場合であ
る。なお、一般に二段玉突融通は、フィーダの規模が大
きく、一段の玉突融通では融通不可能な場合に用いられ
る。図2(A),(B)に示すように、二段玉突融通
は、電源G2が担当している負荷の一部(区間L3)を電
源G3(G2の隣接電源であり、電源G1にとっては第2隣
接電源)に担当させると共に、更に、電源G3が担当し
ている負荷の一部(区間L5)を電源G4(G3の隣接電源
であり、電源G1にとっては第3隣接電源)に担当させ
る方法である。
[0014] Figure 2 is a diagram for explaining the concept of the ball突融through two stages, FIG. 2 (A) capable of interconnection with a power supply G 1 and a power supply G 2 other than the interconnection circuit breaker CB 1 FIG. 2B shows a case where there is the interconnection breaker CB and a case where there is no interconnection breaker CB. In general, the two-stage ballistics are used when the size of the feeder is large and the one-stage ballistics cannot be accommodated. As shown in FIGS. 2 (A) and 2 (B), in the two-stage ball-and-shoot interchange, a part (section L 3 ) of the load assigned to the power supply G 2 is a power supply G 3 (adjacent power supply to G 2 ). The power supply G 1 is assigned to a second adjacent power supply, and a part of the load (section L 5 ) assigned to the power supply G 3 is also assigned to a power supply G 4 (an adjacent power supply to G 3 , This is a method for 1 to be assigned to the third adjacent power supply.

【0015】このためにまず、電源G1,G2間の最上流
の連系遮断器CB1を閉とし、この連系遮断器CB1より
も下流にあって電源G2,G3間にある連系遮断器CB2
閉とする。また、連系遮断器CB2よりも下流にあって
電源G3,G4間にある連系遮断器CB3を閉とする。図2
(A)に示すように、連系遮断器CB1以外に、その下
流に電源G1,G2間を連系可能な連系遮断器CBがある
場合には、電源G2,G3の供給予備力をできるだけ平均
化するように、連系遮断器CB1とCB2との間にある電
源G2のフィーダ上のスイッチS1を開とし、連系遮断器
CB2とCB3との間にある電源G3のフィーダ上のスイ
ッチS2を開とする。一方、図2(B)のように、連系
遮断器CB1以外に電源G1と電源G2とを連系可能な連
系遮断器CBがない場合には、電源G2の供給予備力を
できるだけ大きくするように、電源G2のフィーダ上の
連系点より下流の範囲内でできるだけ上流にあるスイッ
チS1を開とし、連系遮断器CB2とCB3との間にある
電源G3のフィーダ上のスイッチS2を開とする(結果的
に図2(A)と同様)。このとき、電源G2が電源G1
分担分の一部を連系点から分担することが不可能であっ
たり、電源G3が電源G2の負荷の一部を分担できる連系
遮断器CB2が見つからなかった場合、または、電源G4
が電源G3の負荷の一部を分担できる連系遮断器CB3
見つからなかった場合には、二段の玉突融通は不可能で
あると判定する。
Firstly Therefore, the power G 1, interconnection circuit breaker CB 1 the most upstream among G 2 is closed, between the power supply G 2, G 3 In the downstream of the interconnection circuit breaker CB 1 some interconnection circuit breaker CB 2 is closed. Further, the power supply G 3, interconnection circuit breaker CB 3 in between G 4 In the downstream of the interconnection circuit breaker CB 2 is closed. FIG.
(A), the other than interconnection breaker CB 1, when between power G 1, G 2 has interconnection possible interconnection circuit breaker CB is downstream thereof, the power supply G 2, G 3 to average as possible reserve capacity, the switch S 1 on the feeder of the power supply G 2 located between the interconnection circuit breaker CB 1 and CB 2 is opened, the interconnection circuit breaker CB 2 and CB 3 the switch S 2 on the feeder power G 3 and open in between. On the other hand, as shown in FIG. 2 (B), when there is no interconnection possible interconnection circuit breaker CB and power G 1 and a power supply G 2 other than the interconnection circuit breaker CB 1 is reserve capacity of the power supply G 2 the so to maximize, the switch S 1 in as much as possible upstream in the downstream of the range from the connecting point of the power supply G 2 feeder is opened, the power supply G located between the interconnection circuit breaker CB 2 and CB 3 3 of the switch S 2 on the feeder is opened (similar to results in FIG. 2 (a)). At this time, interconnection breaker power G 2 can be shared or it is impossible to share a part of the share of the power supply G 1 from interconnection point, the power supply G 3 some of the load of the power supply G 2 If CB 2 is not found or power supply G 4
There when the interconnection circuit breaker CB 3 that can share some of the load of the power supply G 3 not found, it is determined that it is impossible ball突融through two stages.

【0016】次に、玉突融通の具体的方法について説明
する。配電線は、電源,フィーダ遮断器,負荷,開閉器
(連系遮断器),負荷,開閉器,………,負荷という並
びとし、これらをノードとして探索処理を行うことによ
り、玉突融通のための電源、連系遮断器、開閉器を決定
することができる。その具体的処理は以下のとおりであ
る。
Next, a specific method of the ball-shock accommodation will be described. The distribution lines are arranged in the order of power supply, feeder breaker, load, switch (interconnection breaker), load, switch, ..., load, and by performing search processing using these as nodes, Power supply, interconnection breaker, switchgear can be determined. The specific processing is as follows.

【0017】(1)探索処理1:各配電線ごとに電源端
から下流方向へ探索 各配電線ごとに電源端から下流方向に探索を行う。ここ
では、すべての配電線について探索を行い、ノード情報
を収集する。ノードの種類は、電源、負荷、フィーダ遮
断器、連系遮断器、開閉器の5種類とする。探索の結
果、各配電線・ノードについて以下の情報が得られる。 ・負荷総量,供給予備力 ・現状での供給電源 ・上流負荷ノード番号,下流負荷ノード番号 ・連系遮断器数,連系遮断器番号 ・被融通区間内のノード数,ノード番号
(1) Search processing 1: Search downstream from the power supply end for each distribution line Search is performed downstream from the power supply end for each distribution line. Here, search is performed for all distribution lines, and node information is collected. There are five types of nodes: power supply, load, feeder breaker, interconnection breaker, and switch. As a result of the search, the following information is obtained for each distribution line / node. • Total load, supply reserve • Current supply power • Upstream load node number, downstream load node number • Number of interconnected circuit breakers, number of interconnected circuit breakers • Number of nodes and node numbers in flexible sections

【0018】(2)探索処理2:被融通区間内の一つの
ノードから全方向へ 被融通区間内の一つのノードから全方向に探索を行い、
その結果、被融通区間に対する以下の情報が得られる。 ・被融通区間の負荷量総和L1 ・第1隣接電源(G2)群
(2) Searching process 2: Searching in all directions from one node in the flexible section From one node in the flexible section in all directions,
As a result, the following information on the interchanged section is obtained. - loading of the flexible segment sum L 1, the first adjacent power (G 2) group

【0019】(3)玉突融通の必要性判定 玉突融通の要否判定を行う。各電源G2の供給予備力R
2の総和(ΣRG2)と被融通区間の負荷量総和L1とに
より判定する。すなわち、 ΣRG2≧L1ならば、通常の融通処理で十分 ΣRG2<L1ならば、玉突融通が必要 と判定する。その結果、玉突融通が必要と判定された
ら、以下の処理を行う。
(3) Necessity determination of ballistic accommodation Whether or not ballistic accommodation is necessary is determined. Supply reserve R of each power supply G 2
Determining by the sum of G 2 and the (ΣRG 2) and the load amount sum L 1 of the flexible section. That is, if ΣRG 2 ≧ L 1 , the normal accommodation processing is sufficient, and if ΣRG 2 <L 1 , it is determined that ballistic accommodation is necessary. As a result, if it is determined that ballistic accommodation is necessary, the following processing is performed.

【0020】(4)玉突対象電源候補のソート 被融通区間の隣接電源を、供給予備力が小さい順に並び
替える。
(4) Sorting of Power Source Candidates for Collision The adjacent power sources in the section to be interchanged are rearranged in ascending order of reserve power.

【0021】(5)一段玉突融通の単独実行 上記(4)でソートした玉突対象電源候補のうち、先頭
の隣接電源を一段玉突融通のための玉突対象電源(被玉
突融通電源)G2とする。玉突対象電源G2の隣接電源の
うちで、最大の供給予備力を持つ電源を玉突電源G3
し、同時に、電源G3の供給予備力(RG3)による玉突
融通の可否を判定する。すなわち、 (ΣRG2+RG3)≧L1ならば、一段玉突融通が可能 (ΣRG2+RG3)<L1ならば、一段玉突融通が不可能 と判定する。
(5) Independent execution of single-stage collision accommodation Among the collision-target power supply candidates sorted in (4) above, the first adjacent power supply is a collision-target power supply for single-stage collision accommodation (a target collision accommodation power supply). ) and G 2. Of the adjacent power ball collision target power G 2, a power supply with a maximum reserve capacity and balls突電source G 3, at the same time, determine whether the ball突融communication by the reserve force of the power supply G 3 (RG 3) I do. That is, if (ΣRG 2 + RG 3 ) ≧ L 1 , the one-stage collision is possible. If (ΣRG 2 + RG 3 ) <L 1 , it is determined that the one-stage collision is not possible.

【0022】その結果、一段玉突融通が不可能と判定さ
れた場合には、上記(4)のソート結果に従って、次に
小さな供給予備力を有する電源を玉突対象電源G2とし
て同様の判定を行う。一段玉突融通が可能と判定された
場合には、現在の玉突対象電源G2及び玉突電源G3によ
り一段の玉突融通を行うための連系遮断器、分離スイッ
チを探し、これらが見つかればすべての処理を終了す
る。見つからなければ、更に(4)のソート結果に従っ
て、次に小さな供給予備力を有する電源を玉突対象電源
2として、上述の処理を行う。(4)でソートした電
源のすべてを玉突対象電源G2としても連系遮断器、分
離スイッチが決定できない場合には、一段玉突融通の単
独実行は失敗となり、一段玉突融通の複数実行を行うた
め、次の処理(6)へ移行する。
As a result, if it is determined that the one-stage collision is not possible, the power source having the next smaller supply reserve is determined as the collision target power source G 2 according to the sorting result of (4). I do. When the one step ball突融communication is judged to be the interconnection circuit breaker for performing stage ball突融through by the current ball collision target power G 2 and ball突電source G 3, locate the separation switch, these If found, all processing ends. If not found, according to further sort result of (4), then power supply having a small reserve capacity as Tama突target power G 2, performs the processing described above. Also interconnection circuit breaker all power sorted as ball impact target power G 2 (4), when the separation switch can not be determined singly executing the first stage ball突融communication fails and multiple execution of one step ball突融communication To perform the following processing (6).

【0023】(6)一段玉突融通の複数実行 前述の(4)でソートした電源のうち先頭の電源を一段
玉突融通のための玉突対象電源G2とする。この玉突対
象電源G2の隣接電源のうちで、最大の供給予備力を持
つ電源を玉突電源G3とする。そして、現在の玉突対象
電源G2及び玉突電源G3により一段の玉突融通を行うた
めの連系遮断器、分離スイッチを探し、これらが見つか
れば、(4)のソート結果に従って、一つずつ一段玉突
融通の実行を加えていき、被融通区間内の全負荷量を供
給できるようになった時点で、一段玉突融通の複数実行
が成功したとしてすべての処理を終了する。残りのすべ
ての玉突対象電源に対して一段玉突融通を行っても、被
融通区間内の全負荷量を供給できなければ、一段玉突融
通の複数実行が失敗であるとして、二段玉突融通の単独
実行を検討するため、次の処理(7)へ移行する。
[0023] (6) and ball collision target power G 2 for stage ball突融through the top of the power supply of the power source sorted by one step ball突融through multiple executions of the above-mentioned (4). Among the neighboring power of the ball collision target power G 2, a power supply with a maximum reserve capacity with the ball突電source G 3. The interconnection circuit breaker for performing stage ball突融through by the current ball collision target power G 2 and ball突電source G 3, locate the separation switches, if found these, according to the sort result of (4) one The execution of one-stage ball abutment is added one by one, and when it becomes possible to supply the entire load in the section to be accommodated, all the processes are terminated assuming that a plurality of executions of the one-stage ball abutment have succeeded. If the full load in the section to be interchanged cannot be supplied even if the one-stage ball interchange is performed for all the remaining ballistic target power supplies, the two-stage ball The process proceeds to the next process (7) in order to consider independent execution of the sudden accommodation.

【0024】(7)二段玉突融通の単独実行 前述の(4)でソートした電源のうち先頭の電源を二段
玉突融通のための玉突対象電源G2とする。この玉突対
象電源G2の隣接電源のうちで最大の供給予備力を持つ
電源を第1の玉突電源G3とし、この玉突対象電源G3
隣接電源のうちで最大の供給予備力を持つ電源を第2の
玉突電源G4とする。同時に、電源G3の供給予備力(R
3)と電源G4の供給予備力(RG4)とによる融通可能
性を判定する。すなわち、 (ΣRG2+RG3+RG4)≧L1ならば、二段玉突融通が
可能 (ΣRG2+RG3+RG4)<L1ならば、二段玉突融通が
不可能 と判定する。
[0024] (7) and ball collision target power G 2 for the two-stage ball突融through the power head of the power sorted through a double ball突融through a single execution of the above (4). Power with the maximum reserve capacity among the adjacent power supply of the ball collision target power G 2 is a first ball突電source G 3, maximum reserve capacity among the adjacent power supply of the ball collision target power G 3 power with the second ball突電source G 4. At the same time, the reserve force of the power supply G 3 (R
G 3 ) and the supply reserve (RG 4 ) of the power supply G 4 determine the flexibility. In other words, if (ΣRG 2 + RG 3 + RG 4 ) ≧ L 1 , two-stage ballistic accommodation is possible. If (ΣRG 2 + RG 3 + RG 4 ) <L 1 , two-stage ballistic accommodation is not possible. judge.

【0025】その結果、二段玉突融通が不可能と判定さ
れた場合には、上記(4)のソート結果に従って、次に
小さな供給予備力を有する電源を玉突対象電源G2とし
て同様の判定を行う。二段玉突融通が可能と判定された
場合には、現在の玉突対象電源G2及び玉突電源G3,G4
により二段の玉突融通を行うための連系遮断器、分離ス
イッチを探し、これらが見つかればすべての処理を終了
する。見つからなければ、更に(4)のソート結果に従
って、次に小さな供給予備力を有する電源を玉突対象電
源G 2として、上述の処理を行う。(4)でソートした
電源のすべてを玉突対象電源G2としても連系遮断器、
分離スイッチが決定できない場合には、二段玉突融通の
単独実行は失敗となり、二段玉突融通の単独実行と一段
玉突融通の複数実行を検討するため、次の処理(8)へ
移行する。
As a result, it is determined that the two-stage ball-throwing accommodation is impossible.
In the case of the following, according to the sorting result of (4) above,
A power supply having a small reserve reserve is a power supply G that is a target for collision.Twoage
To make a similar determination. It has been determined that two-tiered ballistics can be accommodated.
In this case, the current target power source GTwoAnd the power supply GThree, GFour
Interconnected circuit breaker and separation switch for two-stage
Search for switches and terminate all processing if found
I do. If not found, further sort according to (4)
Power supply with the next smallest supply reserve
Source G TwoThe above processing is performed. Sorted by (4)
All of the power supplies are targeted power supplies GTwoAs an interconnected circuit breaker,
If the separation switch cannot be determined,
The single execution failed, and the two-stage
Go to the next process (8) to consider multiple executions
Transition.

【0026】(8)二段玉突融通の単独実行と一段玉突
融通の複数実行 前述の(4)でソートした電源のうち先頭の電源を二段
玉突融通のための玉突対象電源G2、この玉突対象電源G
2の隣接電源のうちで最大の供給予備力を持つ電源を第
1の玉突電源G3、この玉突電源G3の隣接電源のうちで
最大の供給予備力を持つ電源を第2の玉突電源G4とし
て、二段玉突融通を行うための連系遮断器、分離スイッ
チを探し、これらが見つかれば、(4)のソート結果に
従って、一つずつ一段玉突融通の実行を加えていき、被
融通区間内の全負荷量を供給できるようになった時点
で、二段玉突融通の単独実行と一段玉突融通の複数実行
が成功したとしてすべての処理を終了する。残りのすべ
ての玉突対象電源に対して一段玉突融通を加えても、被
融通区間内の全負荷量を供給できなければ、二段玉突融
通の単独実行と一段玉突融通の複数実行が失敗であると
して、二段玉突融通の複数実行を検討するため、次の処
理(9)へ移行する。
(8) Independent execution of two-stage ballistics and multiple executions of one-stage ballistics Among the power sources sorted in the above (4), the first power source is a power source G for the two-stage ballistics. 2. This power source G
Power with the maximum reserve capacity among the two adjacent power supply first ball突電source G 3, up to the second ball power with reserve capacity in one of the adjacent power supply of the ball突電source G 3 as突電source G 4, two-stage ball突融communication interconnection circuit breaker for performing, locate the separation switches, if found these, (4) according to the sort result of the addition of the execution of one by one single stage ball突融communication At this point, when it becomes possible to supply the entire load in the accommodated section, all the processes are terminated assuming that the single-stage ball-shock interchange and the single-stage ball-shake interchange have been successfully executed. If the full load in the section to be accommodated cannot be supplied even if the single-stage ball-swap is added to all the remaining ball-jump target power supplies, the two-stage ball-swap alone and the single-stage ball-swap can be executed multiple times. Is determined to have failed, the process proceeds to the next process (9) to consider a plurality of executions of the two-stage ball collision.

【0027】(9)二段玉突融通の複数実行 前述の(4)でソートした電源のうち先頭の電源を二段
玉突融通のための玉突対象電源G2、この玉突対象電源G
2の隣接電源のうちで最大の供給予備力を持つ電源を第
1の玉突電源G3、この玉突電源G3の隣接電源のうちで
最大の供給予備力を持つ電源を第2の玉突電源G4とし
て、二段玉突融通を行うための連系遮断器、分離スイッ
チを探し、これらが見つかれば、(4)のソート結果に
従って、一つずつ二段玉突融通の実行を加えていき、被
融通区間内の全負荷量を供給できるようになった時点
で、二段玉突融通の複数実行が成功したとしてすべての
処理を終了する。残りのすべての玉突対象電源に対して
二段玉突融通を加えても、被融通区間内の全負荷量を供
給できなければ、二段玉突融通の複数実行が失敗である
として、すべての処理を終了する。
(9) A plurality of executions of the two-stage ball-shock interchange The top power source among the power sources sorted in the above-mentioned (4) is the ball-gather target power source G 2 for the two-stage ball-shake interchange,
Power with the maximum reserve capacity among the two adjacent power supply first ball突電source G 3, up to the second ball power with reserve capacity in one of the adjacent power supply of the ball突電source G 3 As the power supply G 4 , an interconnection breaker and a separation switch for performing the two-stage ball collision are searched, and if these are found, the execution of the two-stage ball collision is performed one by one according to the sorting result of (4). Then, at the time when the entire load amount in the section to be accommodated can be supplied, all the processes are terminated assuming that the multiple execution of the two-stage ball abutment has succeeded. Even if two-stage ballistics are added to all remaining ballistic target power sources, if the full load in the section to be accommodated cannot be supplied, multiple executions of the two-stage ballistics are considered to have failed and all Is completed.

【0028】図3は、この実施形態を適用してシミュレ
ーションを行ったモデル配電系統を示しており、No.
4のフィーダの地点Fにおいて事故が発生し、斜線部が
被融通区間になった場合を模擬している。シミュレーシ
ョンでは、被融通区間内の負荷は、No.3とNo.5
のフィーダを電源とし、No.1,No.2の電源から
二段の玉突融通を行った。その結果、スイッチSW1,
SW2を開、遮断器CB1,CB2を閉とすることによ
り、No.2のフィーダ負荷をNo.1のフィーダに部
分的に分担させ、No.3のフィーダ負荷をNo.2の
フィーダに部分的に分担させることにより、玉突融通が
行われてNo.3のフィーダも融通対象電源として利用
可能になることが確認された。
FIG. 3 shows a model power distribution system simulated by applying this embodiment.
4 simulates a case where an accident has occurred at the point F of the feeder and the hatched portion has become a flexible section. In the simulation, the load in the section to be accommodated is No. 3 and No. 5
No. is used as a power source. 1, No. Two stages of ballistic accommodation were performed from the power source of No. 2. As a result, the switches SW1,
By opening SW2 and closing circuit breakers CB1 and CB2, No. No. 2 feeder load No. No. 1 is partially assigned to the feeder. The feeder load of No. 3 is No. No. 2 is partially assigned to the feeder, so that the ballistic accommodation is performed and It was confirmed that the feeder of No. 3 could also be used as a power source for interchange.

【0029】次に、請求項2記載の発明の実施形態を説
明する。前述した請求項1記載の発明は、ESを用いた
一段、二段の玉突融通により、被融通区間に対する電源
を決定するものであるが、請求項2記載の発明は、被融
通区間を電源に最適に分担させるような実際の融通計算
をGAによって実行するものである。すなわち、ES及
びGAの役割分担は以下のとおりである。 ES:玉突融通への対処も含め、被融通区間に対する電
源とその供給予備力を求める。 GA:ESにより求められた各電源に対し、最適に負荷
を分担する。いわゆる融通計算を実行する。
Next, an embodiment of the present invention will be described. According to the first aspect of the present invention, the power supply for the section to be accommodated is determined by one-stage or two-stage ballistic interchange using the ES. In this case, the actual accommodation calculation for optimally sharing the data is executed by the GA. That is, the roles of the ES and the GA are as follows. ES: Find the power supply for the section to be interchanged and its supply reserve, including the measures for the ballistic interchange. GA: Load is optimally shared for each power supply determined by ES. A so-called accommodation calculation is performed.

【0030】請求項2記載の発明は、請求項1記載の発
明による玉突融通方法を前提とした、GAによる負荷分
担の具体的決定手順をその要旨としている。つまり、玉
突対象電源G2の供給予備力RG2を電源容量とし、各電
源G2への連系遮断器の位置における電圧を電源電圧と
して、GAによる負荷融通計算を実行する。
The gist of the invention according to claim 2 is a specific procedure for determining the load sharing by the GA on the premise of the ball abutting method according to the invention described in claim 1. That is, the reserve capacity RG 2 ball collision target power G 2 and power supply capacity, the voltage at the location of the interconnection circuit breaker for each power supply G 2 as a power supply voltage, to perform load interchange calculation by GA.

【0031】ここで、負荷融通における各負荷の電源フ
ィーダの決定は、グラフの分割問題として定式化するこ
とができるが、ここでは、以下のように目的関数及び制
約条件を定めて定式化するものとする。
Here, the determination of the power supply feeder of each load in the load interchange can be formulated as a graph division problem. In this case, the objective function and the constraint condition are defined and formulated as follows. And

【0032】A.目的関数 停電する負荷ノードの負荷量総和の最小化及び電源の供
給予備力の平均化 B.制約条件 (1)放射状制約 各負荷への供給電源は1つでなくてはならず、ループ運
用は行わない。 (2)電源容量制約 分割された部分グラフに属する負荷ノードの負荷量総和
は、電源容量を超えてはならない。 (3)フィーダ容量制約 各フィーダを流れる電流は容量限界を超えてはならな
い。 (4)電圧制約 各負荷ノード電圧は上下限値範囲内でなければならな
い。
A. Objective function Minimize the total load of the load nodes that fail and average the power supply reserve B. Restrictions (1) Radial restriction There must be one power supply to each load, and no loop operation is performed. (2) Power supply capacity restriction The sum of the load amounts of the load nodes belonging to the divided subgraph must not exceed the power supply capacity. (3) Feeder capacity restriction The current flowing through each feeder must not exceed the capacity limit. (4) Voltage restrictions Each load node voltage must be within the upper and lower limit value range.

【0033】次に、各電源への負荷配分を決定するため
のGAによる定式化について述べる。なお、この内容は
特開平7−203630号公報(特願平6−12098
号)に詳述されている。 (1)ストリング表現方法 ストリングとは遺伝子型に相当し、解を一次元的な文字
配列により表現したものである。GAでは、ストリング
長ができるだけ短く、ストリング操作によって上記制約
条件に違反する死滅ストリングを生成しにくいような表
現方法が求められる。この条件を考慮し、本実施形態で
は、被融通区間の負荷数の長さのストリングとし、各ス
トリング位置は各負荷の上流側の電源・負荷番号を10
進法にて示すストリング表現を用いた。この表現による
と、各ストリング位置に使用できる数値を限定でき、従
来の各スイッチの入切状態を2進法で表現する方法に比
べて、ストリング操作による死滅ストリングの発生数を
少なくできると共に、ストリング長も短くなることから
最適解を高速に求めることが可能である。
Next, a description will be given of a formulation by GA for determining the load distribution to each power supply. The contents are described in JP-A-7-203630 (Japanese Patent Application No. Hei 6-12098).
No.). (1) String representation method A string corresponds to a genotype, and a solution is represented by a one-dimensional character array. In GA, an expression method is required in which the string length is as short as possible, and it is difficult to generate a dead string that violates the above-described constraint by string manipulation. In consideration of this condition, in the present embodiment, a string having the length of the number of loads in the section to be accommodated is used, and each string position is set to a power supply / load number on the upstream side of each load.
The string representation shown in base was used. According to this expression, the numerical value that can be used for each string position can be limited, and the number of dead strings generated by the string operation can be reduced as compared with the conventional method of expressing the ON / OFF state of each switch in a binary system. Since the length is also shortened, it is possible to quickly find the optimal solution.

【0034】(2)初期ストリングの生成方法 電源の供給予備力に応じて、確率的に分担負荷を決定す
る発見的なアルゴリズムを用いる。つまり、供給予備力
が大きい電源にできるだけ負荷を分担させるものであ
り、隣接電源の供給予備力を考慮しながら各隣接電源に
より電力を供給する負荷を放射状かつ確率的に徐々に決
定していき、すべての負荷について電源が決定した状態
での負荷融通状態をストリング表現に変換して初期スト
リングを生成する。これにより、最適解に近い解の近傍
に分散している初期値を与えることができ、高速最適化
が可能になる。
(2) Initial String Generation Method A heuristic algorithm is used to stochastically determine the shared load according to the power supply reserve. In other words, the load is allocated as much as possible to the power supply having a large reserve reserve, and the load to be supplied with power by each neighboring power supply is gradually and stochastically determined in consideration of the reserve reserve of the neighboring power supply, An initial string is generated by converting the load accommodation state in a state where the power supply is determined for all loads into a string expression. As a result, initial values dispersed near a solution close to the optimal solution can be given, and high-speed optimization can be performed.

【0035】(3)ストリングの評価・選択 ストリングは、電源の供給予備力に基づき適応度を評価
して適応度の高いストリングを選択する。すなわち、ス
トリングは、供給予備力が平均している場合に適応度が
高く、供給予備力が負になる場合に大きくペナルティを
与えるように評価する。また、ストリング間の適当な競
合状態を保つためにリニアスケーリング(D.E.Goldber
g, Genetic Algorithms in Search, Optimization, and
MachineLearning, Addison - Wesley, 1989による)
を用いた。ストリングの選択方法は、確定的手法と確率
的手法とを組み合わせた、Remainder Stochastic Sampl
ing with Replacement(D.E.Goldberg, Genetic Algori
thms in Search, Optimization, and Machine Learnin
g, Addison - Wesley, 1989による)を用いた。
(3) Evaluation and Selection of Strings Strings are evaluated for fitness based on the reserve capacity of power supply, and strings with high fitness are selected. That is, the string is evaluated so as to have a high fitness when the supply reserve is averaged and to give a large penalty when the supply reserve is negative. In addition, linear scaling (DEGoldber
g, Genetic Algorithms in Search, Optimization, and
MachineLearning, Addison-by Wesley, 1989)
Was used. String selection method is Remainder Stochastic Sampl, which combines deterministic method and stochastic method.
ing with Replacement (DEGoldberg, Genetic Algori
thms in Search, Optimization, and Machine Learnin
g, Addison-by Wesley, 1989).

【0036】(4)ストリング操作 a.交差 ここでは1点交差(単純交差)を用いることとし、前記
ストリング表現を用いた場合、交差は交差位置の負荷と
隣接する負荷の境を交差位置として、負荷融通状態を部
分的に他の融通状態に入れ替えることを意味しており、
二つの親の染色体の組替えにより子の染色体を作る操作
に相当する。多点交差の使用も考えられるが、交差によ
り電源がない部分系統が複数作成される場合があり、以
下に述べる修正オペレータが複雑になる。従って、ここ
では簡単な1点交差を用いた。
(4) String operation a. Intersection Here, a one-point intersection (simple intersection) is used, and in the case of using the string expression, the intersection is defined as the intersection position between the load at the intersection position and the adjacent load, and the load accommodation state is partially changed to another accommodation state. It means to switch to the state,
This corresponds to an operation of creating a child chromosome by rearrangement of two parent chromosomes. Although use of a multipoint intersection is conceivable, a plurality of sub-systems having no power supply may be created due to the intersection, which complicates a correction operator described below. Therefore, a simple one-point intersection was used here.

【0037】b.修正オペレータ 修正オペレータは、交差により死滅ストリングが生成さ
れた場合に、制約を満たすように部分的にストリングを
修正することを意味する。具体的には、交差によって電
源がない部分系統が生じた場合に、この部分系統に隣接
する電源フィーダのうち、予備力が一番大きいものに部
分系統が接続されるようにストリングを修正する。
B. Correction Operator The correction operator means that when a dead string is generated by an intersection, the string is partially corrected to satisfy the constraint. Specifically, when a partial system having no power supply occurs due to the intersection, the string is corrected so that the partial system is connected to the power supply feeder adjacent to the partial system having the largest reserve power.

【0038】c.突然変異 突然変異は、遺伝子を一定の確率で変化させる操作に相
当し、交差により得られた解の近傍を探索する意義を持
ち、これによって局所解への落ち込みを防止することが
できる。具体的には、各ストリング位置の1ビットの変
換であり、負荷融通問題においてはただ1つの負荷の供
給電源を変更することを意味する。ある負荷とその上流
負荷が共に同じ電源を有することが必要である放射状制
約及び輸送経路制約を満たしながら、1つの負荷のみの
供給電源を変更、つまり負荷の上流の方向を変更するこ
とができるのは、異なる電源フィーダから供給されてい
る負荷に隣接する負荷のみである。従って、このような
負荷のみ突然変異を可能とする。
C. Mutation Mutation is equivalent to an operation of changing a gene with a certain probability, and has a significance of searching for a neighborhood of a solution obtained by crossing, thereby preventing a drop to a local solution. Specifically, this is conversion of one bit at each string position, and in the load accommodation problem, it means that the power supply of only one load is changed. It is possible to change the power supply of only one load, i.e. change the direction upstream of the load, while satisfying the radial and transit route constraints that a load and its upstream loads must both have the same power supply. Are only the loads adjacent to the loads being supplied from different power supply feeders. Therefore, only such a load enables mutation.

【0039】図4は、この発明の実施形態を適用してシ
ミュレーションを行ったモデル配電系統を示しており、
No.4のフィーダの地点Fにおいて事故が発生し、斜
線部が被融通区間になった場合を模擬している。GAの
パラメータは、交差確率:0.5、突然変異確率:0.
01、ストリング数:50として玉突融通のシミュレー
ションを行った。なお、これらのパラメータ条件は、様
々な系統に対しても何ら問題なく適用可能である。シミ
ュレーションでは、被融通区間内の負荷は、No.3と
No.5のフィーダを電源とし、No.1,No.2の
電源から二段の玉突融通を行った。その結果、スイッチ
SW1,SW2を開、遮断器CB1,CB2を閉とする
ことにより、No.2のフィーダ負荷をNo.1のフィ
ーダに部分的に分担させ、No.3のフィーダ負荷をN
o.2のフィーダに部分的に分担させることにより、玉
突融通が行われてNo.3のフィーダも融通対象電源と
して利用可能になる。更に、被融通区間がGAによって
最適に分割された結果、スイッチSW3を開くことによ
り、No.3とNo.5のフィーダに負荷が割り当てら
れることが確認された。
FIG. 4 shows a model power distribution system simulated by applying the embodiment of the present invention.
No. 4 simulates a case where an accident has occurred at the point F of the feeder and the hatched portion has become a flexible section. The parameters of GA are cross probability: 0.5, mutation probability: 0.
01, the number of strings: 50, and simulation of ballistic accommodation was performed. Note that these parameter conditions can be applied to various systems without any problem. In the simulation, the load in the section to be accommodated is No. 3 and No. No. 5 as a power source. 1, No. Two stages of ballistic accommodation were performed from the power source of No. 2. As a result, by opening the switches SW1 and SW2 and closing the circuit breakers CB1 and CB2, No. 2 feeder load No. No. 1 is partially assigned to the feeder. 3 feeder load N
o. No. 2 is partially assigned to the feeder, so that the ballistic accommodation is performed and The third feeder can also be used as a power source to be interchanged. Further, as a result of the section to be accommodated being optimally divided by the GA, the switch SW3 is opened, whereby the No. 3 and No. It was confirmed that the load was assigned to 5 feeders.

【0040】[0040]

【発明の効果】以上のように請求項1記載の発明は、E
Sにより玉突融通への対処も含め、被融通区間に対する
電源とその供給予備力を求めるものであり、また、請求
項2記載の発明は、その後、ESにより求められた電源
を用いて、各電源に対しGAにより最適に負荷を分担す
るものである。これにより、融通電源を最大限に拡大
し、被融通区間が最小限になるような負荷配分を可能に
して信頼性の高い負荷融通を行うことができる。
As described above, according to the first aspect of the present invention, the E
In S, the power supply for the section to be accommodated and its reserve reserve are obtained, including the handling of the ballistic accommodation, and the invention according to claim 2 thereafter uses the power supply obtained by ES to determine each power supply. The load is optimally shared by the GA with respect to the power supply. As a result, it is possible to maximize the capacity of the interchange power supply and to distribute the load such that the section to be interchanged is minimized, thereby performing highly reliable load interchange.

【図面の簡単な説明】[Brief description of the drawings]

【図1】請求項1の発明の実施形態における一段玉突融
通の概念図である。
FIG. 1 is a conceptual diagram of a one-stage ball-throwing accommodation according to an embodiment of the present invention.

【図2】請求項1の発明の実施形態における二段玉突融
通の概念図である。
FIG. 2 is a conceptual diagram of a two-stage ball-adjustment according to the first embodiment of the present invention.

【図3】請求項1の発明の実施形態を適用してシミュレ
ーションを行ったモデル配電系統を示す図である。
FIG. 3 is a diagram showing a model power distribution system obtained by performing a simulation by applying the embodiment of the first aspect of the present invention;

【図4】請求項2の発明の実施形態を適用してシミュレ
ーションを行ったモデル配電系統を示す図である。
FIG. 4 is a diagram showing a model power distribution system simulated by applying the embodiment of the invention of claim 2;

【符号の説明】[Explanation of symbols]

1,G2,G3,G4 電源 CB,CB1,CB2,CB3 連系遮断器 L1 被融通区間 L2,L3,L4,L5 区間 S1,S2 スイッチ F 事故点 G 1, G 2, G 3 , G 4 power CB, CB 1, CB 2, CB 3 consecutive system breaker L 1 the flexible section L 2, L 3, L 4 , L 5 sections S 1, S 2 switch F Accident point

───────────────────────────────────────────────────── フロントページの続き (72)発明者 藤田 超徹 神奈川県川崎市川崎区田辺新田1番1号 富士電機株式会社内 (72)発明者 福山 良和 神奈川県川崎市川崎区田辺新田1番1号 富士電機株式会社内 ──────────────────────────────────────────────────続 き Continuing from the front page (72) Inventor Tohoku Fujita 1-1, Tanabe-Nitta, Kawasaki-ku, Kawasaki, Kanagawa Prefecture Inside Fuji Electric Co., Ltd. (72) Inventor Yoshikazu Fukuyama 1, Tanabe-Nitta, Kawasaki-ku, Kawasaki-ku, Kanagawa Prefecture No. 1 Inside Fuji Electric Co., Ltd.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 配電系統の構成、供給電力の被融通区
間、各負荷容量及び各電源並びに電源容量が与えられた
ときに、被融通区間への再送電を行うために開閉手段の
入切により各負荷に対する電源フィーダを決定し、被融
通区間以外から被融通区間へ電力を融通する負荷融通方
法であって、被融通区間の負荷量総和が隣接電源群の供
給予備力総和を上回る場合に、前記隣接電源群に隣接す
る別の隣接電源群から順次、電力を供給する玉突融通方
法において、 配電系統を構成するノードをオブジェクト知識を用いて
表現し、被融通区間内の1つのノードから全方向に探索
を行って被融通区間の負荷量総和及び第1隣接電源群を
検出し、被融通区間の負荷量総和と第1隣接電源群の供
給予備力総和とを比較して玉突融通の要否を判定し、玉
突融通が必要と判定された場合は第1隣接電源群のうち
供給予備力が最も小さい電源から玉突対象電源とし、こ
の玉突対象電源に隣接する第2隣接電源の中で供給予備
力が最も大きい電源を第1の玉突電源として探索し、前
記第1隣接電源群の供給予備力総和と第1の玉突電源の
供給予備力との和と、被融通区間の負荷量総和とを比較
して一段玉突融通の可否を判定し、一段玉突融通が可能
と判定された場合に、各隣接電源を連系する開閉手段及
びフィーダ上の開閉手段の開閉状態を決定し、 前記一段玉突融通が不可能と判定された場合に、前記第
1の玉突電源に隣接する第3隣接電源の中で供給予備力
が最も大きい電源を第2の玉突電源として探索し、前記
第1隣接電源群の供給予備力総和と第1及び第2の玉突
電源の供給予備力との和と、被融通区間の負荷量総和と
を比較して二段玉突融通の可否を判定し、二段玉突融通
が可能と判定された場合に、各隣接電源を連系する開閉
手段及びフィーダ上の開閉手段の開閉状態を決定するこ
とを特徴とする配電系統における負荷融通方法。
When a configuration of a power distribution system, a section to be supplied with power supply, each load capacity, each power supply, and a power supply capacity are given, opening and closing means are turned on and off to perform retransmission of power to the section to be supplied. Determine the power supply feeder for each load, a load accommodation method for accommodating power from the non-interchangeable section to the interchangeable section, where the total load amount of the interchanged section exceeds the total supply reserve of the adjacent power supply group, In a ball-swap method for sequentially supplying power from another adjacent power supply group adjacent to the adjacent power supply group, a node constituting a power distribution system is expressed using object knowledge, and all nodes from one node in the interchanged section are The search is performed in the direction to detect the total load amount and the first adjacent power supply group in the interchanged section, and compares the total load amount in the interchanged section with the total supply reserve capacity of the first adjacent power supply group to determine whether or not the ballistic interchange is available. Judgment of necessity and accommodation of the ball If it is determined that it is necessary, the power supply with the smallest supply reserve in the first adjacent power supply group is set as a collision target power supply, and the power supply with the largest supply reserve among the second adjacent power supplies adjacent to this collision target power supply As a first collision power supply, and comparing the sum of the supply reserve power of the first adjacent power supply group and the supply reserve power of the first collision power supply with the total load amount of the section to be interchanged. It is determined whether the one-stage ball collision is possible or not, and when it is determined that the one-stage ball collision is possible, the open / close state of the opening / closing means for interconnecting each adjacent power supply and the opening / closing means on the feeder is determined. If it is determined that the power supply is not possible, a power supply having the largest supply reserve among the third adjacent power supplies adjacent to the first ballistic power supply is searched for as the second ballistic power supply, and the first adjacent power supply is searched for. The sum of the supply reserve of the group and the supply reserves of the first and second bump power supplies; A comparison is made between the load sum of the sections to determine whether or not the two-stage ball-thrust can be accommodated. If it is determined that the two-stage ball-thrust interchange is possible, the opening / closing means for interconnecting the adjacent power sources and the opening / closing means on the feeder are determined. A load accommodating method in a distribution system, characterized by determining an open / closed state of a load.
【請求項2】 請求項1記載の方法により決定された一
段または二段の玉突融通方法に基づいて、 隣接電源の供給予備力を考慮しながら各隣接電源により
電力を供給する負荷を放射状かつ確率的に徐々に決定し
ていき、すべての負荷について電源が決定した状態での
負荷融通状態をストリング表現に変換して初期ストリン
グを生成し、その後、これらの初期ストリングに対し、
電源の供給予備力に基づき適応度を評価して適応度の高
いストリングを選択し、しかる後、ストリング表現にお
ける隣接負荷の境を交差位置として交差を行い、その結
果、配電系統に存在する制約条件に違反する死滅ストリ
ングが生成された場合にストリングを修正すると共に、
ストリング表現におけるストリング位置の1ビットを変
換して前記制約条件を満たすように唯一の負荷の供給電
源方向を変更して突然変異操作を行う遺伝的アルゴリズ
ムにより、被融通区間を各電源に対し最適に分担させる
ことを特徴とする配電系統における負荷融通方法。
2. The method according to claim 1, wherein a load supplied by each adjacent power supply is radiated while taking into consideration the supply reserve of the adjacent power supply, based on the one-stage or two-stage ball-adjustment method determined. It is determined stochastically gradually, the load accommodation state in the state where the power supply is determined for all loads is converted into a string representation to generate initial strings, and then, for these initial strings,
The fitness is evaluated based on the supply reserve of the power supply, and a string having a high fitness is selected. Thereafter, the intersection is performed with the boundary between adjacent loads in the string representation as an intersection position. As a result, the constraint conditions existing in the power distribution system are obtained. If a dead string is generated that violates
A genetic algorithm that performs a mutation operation by changing the direction of the power supply of the only load so as to satisfy the above constraint by converting one bit of the string position in the string representation, to optimize the flexible section for each power supply A load accommodating method in a distribution system, characterized by sharing.
JP10093310A 1998-04-06 1998-04-06 Load interchange method in power distribution system Withdrawn JPH11289662A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10093310A JPH11289662A (en) 1998-04-06 1998-04-06 Load interchange method in power distribution system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10093310A JPH11289662A (en) 1998-04-06 1998-04-06 Load interchange method in power distribution system

Publications (1)

Publication Number Publication Date
JPH11289662A true JPH11289662A (en) 1999-10-19

Family

ID=14078758

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10093310A Withdrawn JPH11289662A (en) 1998-04-06 1998-04-06 Load interchange method in power distribution system

Country Status (1)

Country Link
JP (1) JPH11289662A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010034792A (en) * 2008-07-28 2010-02-12 Keio Gijuku Method and apparatus for controlling power supply of network
JP2011199928A (en) * 2010-03-17 2011-10-06 Mitsubishi Electric Corp Method of controlling distribution system
JP2016025799A (en) * 2014-07-23 2016-02-08 株式会社日立製作所 System supervisory control device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010034792A (en) * 2008-07-28 2010-02-12 Keio Gijuku Method and apparatus for controlling power supply of network
JP2011199928A (en) * 2010-03-17 2011-10-06 Mitsubishi Electric Corp Method of controlling distribution system
JP2016025799A (en) * 2014-07-23 2016-02-08 株式会社日立製作所 System supervisory control device

Similar Documents

Publication Publication Date Title
Wu et al. Ensemble strategies for population-based optimization algorithms–A survey
Ramirez-Rosado et al. Genetic algorithms applied to the design of large power distribution systems
Gonçalves et al. A hybrid genetic algorithm for assembly line balancing
US8793202B2 (en) Restoration switching analysis with genetic algorithm
Tom et al. Transit route network design using frequency coded genetic algorithm
Toune et al. Comparative study of modern heuristic algorithms to service restoration in distribution systems
EP2507751B1 (en) Restoration switching analysis with modified genetic algorithm
Abdelaziz Genetic algorithm-based power transmission expansion planning
Tsang et al. A family of stochastic methods for constraint satisfaction and optimization
CN111289845A (en) Active power distribution network fault positioning method and system
Ahmad et al. Multi-objective quantum-inspired Artificial Immune System approach for optimal network reconfiguration in distribution system
JPH11289662A (en) Load interchange method in power distribution system
Dorterler A new genetic algorithm with agent-based crossover for the generalized assignment problem
Keung et al. A genetic algorithm approach to the multiple machine tool selection problem
Wu et al. A new binary coding particle swarm optimization for feeder reconfiguration
Banerjee et al. Minimization of reliability indices and cost of power distribution systems in urban areas using an efficient hybrid meta-heuristic algorithm
JPH0946906A (en) Interchanging method of load in distribution system
Chyzy et al. Evolutionary algorithm for state assignment of finite state machines
JPH11262181A (en) Load interchange mode determination method of electric power distribution system
WO2021166391A1 (en) Power distribution network creation method and creation device
Wang et al. A hybrid genetic algorithm for multiobjective structural optimization
Nappu et al. Path-relinking Grey Wolf Optimizer for Solving Operation Sequencing Problem
JPH11252794A (en) Power distribution system loss minimizing method
JPH0869490A (en) System and method for interchanging distribution load
JP3781522B2 (en) Method for determining load accommodation in distribution system

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20050607