JPH11236105A - Product physical distribution control method and device thereof - Google Patents

Product physical distribution control method and device thereof

Info

Publication number
JPH11236105A
JPH11236105A JP4057798A JP4057798A JPH11236105A JP H11236105 A JPH11236105 A JP H11236105A JP 4057798 A JP4057798 A JP 4057798A JP 4057798 A JP4057798 A JP 4057798A JP H11236105 A JPH11236105 A JP H11236105A
Authority
JP
Japan
Prior art keywords
shipping
work
plan
reference value
product
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP4057798A
Other languages
Japanese (ja)
Inventor
Takao Nakajima
隆夫 中島
Yuji Kanda
雄二 神田
Akio Nagano
昭男 長野
Daisuke Kodama
大佐 児玉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Nippon Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Corp filed Critical Nippon Steel Corp
Priority to JP4057798A priority Critical patent/JPH11236105A/en
Publication of JPH11236105A publication Critical patent/JPH11236105A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • General Factory Administration (AREA)
  • Warehouses Or Storage Devices (AREA)

Abstract

PROBLEM TO BE SOLVED: To improve efficiency of a cargo collecting work by indicating interruption to a product shipping operation facility so as to forward products in a warehouse to the quay on the shipping position for preferentially executing a work for short delivery generation until the short delivery is generated when short delivery is judged to generate. SOLUTION: An obstacle prediction judging part 10 takes in respectively operation progress information 95 from an operation progress information memory part 25, and shipping plan information 94 from a shipping plan information memory part 24. When a forwarding work in a storehouse is continued to operate as it is in accordance with the plan, against a cargo handling work progressing at present on a shipping quay, delivery of shipping objective products from the warehouse by pallets and carriers to the shipping quay is delayed, shipping products disappear on the quay, and it is computed whether interruption of a shipping work by a quay crane is generated or not. When generation of interruption of the shipping is judged to generate, an emergent work interruption control part 11 is started, an objective work is most preferentially interrupted as an emergent work, and it is replaced with an appropriate operation order.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、倉庫の製品を船積
み出荷するためのスケジュールを、自動的に且つ高精度
に作成するための制御方法とその制御装置に関するもの
である。
[0001] 1. Field of the Invention [0002] The present invention relates to a control method and a control apparatus for automatically and accurately creating a schedule for loading and shipping products in a warehouse.

【0002】[0002]

【従来の技術】例えば、倉庫内にある製品を船積場であ
る岸壁にクレーン及び搬送車輌を使用して搬送するため
の出荷作業の計画は、オペレータによって作成されてお
り、変動要素が多く、オペレータの勘と経験に頼らざる
を得ないことから、精度が低く、修正も頻繁に行わなけ
ればならず、作業負荷の高いものであった。
2. Description of the Related Art For example, a shipping work plan for transporting a product in a warehouse to a quay, which is a loading dock, by using a crane and a transport vehicle is prepared by an operator. Because of having to rely on intuition and experience, the accuracy was low, corrections had to be made frequently, and the work load was high.

【0003】また、クレーン及び搬送車輌の運行はオペ
レータの作業指示により行われ、これはオンライン端末
を介して、人の判断に基づいた作業指示を出す形式のた
め、タイミングのずれや作業順のずれが発生し、その修
正で手動介入が繰り返されるといった悪循環の環境下で
行われていた。このため、近年、この計画作成を計算機
を用いて自動的に行う方法、例えば、倉庫から岸壁に製
品を搬送するためのバース計画や倉庫への製品の入出庫
計画について、単独のスケジューラが提案されている。
[0003] The operation of the crane and the transport vehicle is performed in accordance with the work instructions of the operator, and this is a form in which a work instruction based on human judgment is issued through an online terminal. And a manual cycle was repeated with the correction. For this reason, in recent years, a single scheduler has been proposed for automatically creating this plan using a computer, for example, for a berth plan for transporting products from a warehouse to a quay or for a product entry / exit plan for a warehouse. ing.

【0004】[0004]

【発明が解決しようとする課題】前記計算機で自動的に
計画作成を行うとしても、計画と実出荷作業のズレが基
準値よりも大きくなった段階において、計画の組み替え
作業を行うために、計画と実出荷作業の間にはタイムラ
グが発生して船積み作業時間が延長して、多大な滞船料
を支払わなければならない。
Even if a plan is automatically created by the computer, when the difference between the plan and the actual shipping work becomes larger than a reference value, the plan must be rearranged. There is a time lag between the actual shipping work and the shipping work time is prolonged, and a large berthing fee must be paid.

【0005】また、天候等により積み込み対象船舶の入
港が遅れた場合等には、頻繁に計画と実出荷作業にずれ
が発生する場合がある。この際には前記のように、その
都度、計画を組み替えなければならず、その計算機の占
有率が高くなって、他の処理が出来なくなり、専用のも
のとしなければならない問題を有するものであった。本
発明は出荷計画を計算機等を用いて自動的に作成し、そ
の作成した計画に従って実出荷作業を行うに際して、作
成した計画と実出荷作業のズレを早期に予測し、そのズ
レの発生を防止し、荷切れによる船積み作業の延長を防
止し、更に、計画の組み替え作業の発生頻度を減少する
ことにより上記問題を解決することを課題とするもので
ある。
[0005] In addition, when the port to be loaded is delayed due to the weather or the like, there may be a frequent deviation between the plan and the actual shipping operation. In this case, as described above, the plan must be rearranged each time, and the occupancy of the computer increases, so that other processes cannot be performed and there is a problem that the computer must be dedicated. Was. The present invention automatically prepares a shipping plan using a computer or the like, and when performing an actual shipping operation according to the created plan, predicts a gap between the created plan and the actual shipping work at an early stage, and prevents the occurrence of the gap. It is another object of the present invention to solve the above-mentioned problem by preventing an extension of a loading operation due to an out-of-load and reducing a frequency of occurrence of a rearrangement operation of a plan.

【0006】[0006]

【課題を解決するための手段】本発明は上記課題を解決
するためになされたものであり、その手段1は、倉庫の
製品を船積み出荷するための出荷計画を計画部でスケジ
ューリングし、このスケジューリングした出荷計画情報
に基づいて、倉庫の製品をクレーン及び運搬車輌等の製
品出荷作業設備に船積み出荷する作業指示を行い、この
作業指示に基づいて行う前記製品出荷作業設備が船積み
実出荷作業の進捗状況と前記スケジューリングした出荷
計画を比較して両者のズレ量を求め、このズレ量が予め
設定した基準値を越えると前記計画部に計画作成指示を
行う製品物流制御方法において、前記計画部でスケジュ
ーリングした出荷計画と前記実出荷作業の進捗状況から
該出荷計画に従って実出荷作業を行った場合に船積み出
荷する位置の岸壁に荷切れが発生するか否か及び荷切れ
発生時刻を判定し、荷切れが発生すると判定した場合に
は、その荷切れが発生する時刻までにその荷切れ発生作
業を優先的に行う様に倉庫の製品を船積み出荷する位置
の岸壁に出荷するように割り込み指示を前記クレーン、
運搬車輌等の製品出荷作業設備に行う製品物流制御方法
である。
Means for Solving the Problems The present invention has been made to solve the above-mentioned problems. Means 1 is to schedule a shipping plan for loading and shipping products in a warehouse by a planning unit, Based on the shipping plan information, the work order for loading and shipping the products in the warehouse to the product shipping work facilities such as cranes and transport vehicles is issued, and the product shipping work equipment performed based on the work instructions performs the progress of the actual shipping work. In a product logistics control method for comparing a situation with the scheduled shipping plan to obtain a deviation amount between the two and when the deviation amount exceeds a preset reference value, the planning unit is instructed to make a plan. The quay at the position to be loaded and shipped when the actual shipping work is performed according to the shipping plan and the progress of the actual shipping work Judgment is made as to whether or not unloading occurs and the time of unloading. If it is determined that unloading occurs, the warehouse will give priority to the unloading work by the time when the unloading occurs. The crane, which instructs to interrupt the product to be shipped to the quay in the position to be loaded and shipped,
This is a product distribution control method performed on a product shipping work facility such as a transport vehicle.

【0007】更に、手段2は、前記計画部でスケジュー
リングした出荷計画と前記実出荷作業の操業実績情報を
比較して、両者のズレ量を求め、このズレ量が予め設定
した基準値を越える作業が発生している場合には、ズレ
が発生している作業の種類別にズレ発生原因を、荒天影
響、配船遅れ等により発生する外乱と、計画に使用する
計画基準値が実操業と合わないために発生する内乱に解
析すると共にこの解析した結果を原因別に区分し、更
に、この解析されたズレ発生原因区分別に前記出荷計画
値と操業実績値のズレを定量化する処理を行い、この解
析したズレ発生原因区分別ズレ量を基に前記計画基準値
を修正する製品物流制御方法である。
Further, the means 2 compares the shipping plan scheduled by the planning section with the operation result information of the actual shipping work to determine the amount of deviation between the two, and the work in which the amount of deviation exceeds a preset reference value. If there is a gap, the cause of the gap depending on the type of work in which the gap is occurring, the disturbance caused by stormy weather effects, delays in ship assignment, etc., and the plan standard value used for planning does not match the actual operation In order to analyze the resulting disturbance, the result of this analysis is classified according to the cause, and furthermore, a process of quantifying the difference between the shipment plan value and the actual operation value is performed for each analyzed cause of the difference, and the analysis is performed. This is a product distribution control method for correcting the plan reference value based on the deviation amount for each of the deviation occurrence categories.

【0008】手段3は、倉庫の製品を船積み出荷するた
めの出荷計画をスケジューリングする計画部と、計画部
で得られる出荷計画情報に基づいて、倉庫の製品をクレ
ーン及び運搬車輌等の製品出荷作業設備で搬送して船積
み出荷する作業指示を行う操業制御部と、前記製品出荷
作業設備の実出荷作業の進捗状況と前記計画部で作成し
た出荷計画を比較して両者のズレ量を求め、このズレ量
が予め設定した基準値を越えると前記計画部に計画作成
指示を行う修正フィードバック部Bを有する製品物流制
御装置において、前記計画部でスケジューリングした出
荷計画と前記実出荷作業の進捗状況から該出荷計画に従
って実出荷作業を行った場合に船積み出荷する位置の岸
壁に荷切れが発生するか否か及び荷切れ発生時刻を判定
し、荷切れが発生すると判定した場合には、その荷切れ
が発生する時刻までにその荷切れ発生作業を優先的に行
う様に倉庫の製品を船積み出荷する位置の岸壁に出荷す
るように割り込み指示を前記クレーン及び運搬車輌等の
製品出荷作業設備に指示を出す修正フィードバック部A
を有する製品物流制御装置である。
Means 3 are a planning section for scheduling a shipping plan for loading and shipping the products in the warehouse, and a product shipping operation such as cranes and transport vehicles based on the shipping plan information obtained by the planning section. An operation control unit that issues work instructions for transporting and shipping by equipment, and comparing the progress of the actual shipping work of the product shipping work equipment with the shipping plan created by the planning unit to determine the amount of deviation between the two, When the deviation exceeds a preset reference value, in a product distribution control device having a correction feedback unit B for instructing the planning unit to make a plan, a shipping plan scheduled by the planning unit and a progress status of the actual shipping work are used. If actual shipping work is performed in accordance with the shipping plan, it is determined whether or not the quay at the shipping / shipping position will be unloaded and the time of unloading, and the unloading will occur. If it is determined that the unloading will occur by the time the unloading occurs, the crane and the crane and the interrupt instruction to ship the products in the warehouse to the quay at the position where the products are loaded and shipped so as to give priority to the unloading work. Correction feedback section A that issues instructions to product shipping work equipment such as transport vehicles
Is a product distribution control device having:

【0009】手段4は、前記計画部でスケジューリング
した出荷計画と前記実出荷作業の操業実績情報を比較し
て、両者のズレ量を求め、このズレ量が予め設定した基
準値を越える作業が発生している場合には、ズレが発生
している作業の種類別にズレ発生原因を、荒天影響、配
船遅れ等により発生する外乱と、計画に使用する計画基
準値が実操業と合わないために発生する内乱に解析する
と共にこの解析した結果を原因別に区分し、更に、この
解析されたズレ発生原因区分別に計画値と実績値のズレ
を定量化する処理を行う解析部と、該解析部の解析結果
情報と計画基準値記憶部に記憶した計画基準値を比較し
て差異があるか否かの判定を行い、差異があると判定さ
れた場合は、前記計画基準値記憶部に記憶した計画基準
値を修正する修正フィードバック部Cを有する製品物流
制御装置である。
Means 4 compares the shipping plan scheduled by the planning section with the operation result information of the actual shipping work to determine the amount of deviation between the two, and when the amount of deviation exceeds a preset reference value, an operation occurs. If there is a shift, the cause of the shift is determined by the type of work in which the shift occurs, because the disturbance caused by stormy weather, delays in ship assignment, etc., and the plan reference value used for planning does not match the actual operation. An analyzing unit that analyzes the generated disturbance and classifies the analyzed result according to cause, and further performs a process of quantifying a difference between a planned value and an actual value according to the analyzed difference occurrence cause class; and The analysis result information is compared with the plan reference value stored in the plan reference value storage unit to determine whether there is a difference. If it is determined that there is a difference, the plan stored in the plan reference value storage unit is determined. Correction to correct the reference value A product distribution control device having a fed back portion C.

【0010】本発明の修正フィードバック部Aにより、
計画に従って実出荷作業を行うに際して、作成した計画
と実出荷作業のズレ量を事前に早期予測し、そのズレ量
を発生させない様に作業指示を変更する制御を行うこと
により、岸壁での荷切れによる船積み作業の延長を防止
し、滞船料の削減を実現する。更に修正フィードバック
部Cにより、計画に使用する基準値を常に実績値と比較
解析し、常に基準値を実際の操業に見合った値に保つこ
とにより、計画自体の精度を高位に安定させ、他の修正
フィードバック部の起動を必要最小限に抑えることによ
り、計算機の負荷を最小限にとどめることができる。
According to the modified feedback section A of the present invention,
When carrying out actual shipping work according to the plan, the amount of misalignment between the created plan and the actual shipping work is predicted at an early stage in advance, and control is performed to change the work instructions so that the amount of deviation does not occur. To prevent the lengthening of shipping work and reduce berthing charges. Further, the correction feedback section C constantly analyzes and compares the reference value used for the plan with the actual value, and always keeps the reference value at a value commensurate with the actual operation, thereby stabilizing the accuracy of the plan itself at a high level, By minimizing the activation of the correction feedback unit, the load on the computer can be minimized.

【0011】修正フィードバック部Bを有する製品物流
制御装置に、修正フィードバック部A及び修正フィード
バック部Cを併用することにより、自動かつ高効率な製
品物流制御を実現することが可能となる。
By using the correction feedback section A and the correction feedback section C together with the product distribution control device having the correction feedback section B, automatic and highly efficient product distribution control can be realized.

【0012】[0012]

【発明の実施の形態】本発明の実施の形態として、製鐵
業において、製造した圧延コイル(以下単に製品と称
す)を一時貯蔵する倉庫から船積みする岸壁までキャリ
アカーで搬送する場合を例にとって説明する。まず、製
品出荷作業の概要を説明する。
BEST MODE FOR CARRYING OUT THE INVENTION As an embodiment of the present invention, a case will be described in which, in a steel industry, a manufactured rolling coil (hereinafter simply referred to as a product) is transported by a carrier car from a temporary storage warehouse to a quay for loading. explain. First, an outline of the product shipping operation will be described.

【0013】図2に示すように、製造ライン53で製造
された製品55は複数の倉庫クレーン57を設置した倉
庫51に一時保管し、その後、出荷命令がかかり出荷対
象となると、前記倉庫クレーン57で吊り上げられて所
定の積卸し場に待機している空のパレット30に積載す
る。そして、このパレット30は運搬車輌としてのキャ
リア31で出荷岸壁50まで運搬して、該出荷岸壁50
に該パレット30を据置く。この据置いたパレット30
上から製品40を岸壁クレーン52で船54に船積みす
るものである。
As shown in FIG. 2, a product 55 manufactured on a manufacturing line 53 is temporarily stored in a warehouse 51 in which a plurality of warehouse cranes 57 are installed. And is loaded on an empty pallet 30 waiting at a predetermined unloading place. Then, the pallet 30 is transported to the shipping quay 50 by the carrier 31 as a transport vehicle, and the shipping quay 50 is
Is placed on the pallet 30. This stationary pallet 30
The product 40 is loaded onto a ship 54 by a quay crane 52 from above.

【0014】そして、この製品の出荷作業は、複数ある
キャリア31内で最適なものを選択し、そのキャリア3
1への作業指示を出す順序とタイミングをコントロール
することにより行われる。次に、全体の基本的な構成を
説明する。図1に示すように、製品出荷作業をスケジュ
ーリングする装置は、大別すると、出荷計画をスケジュ
ーリングする計画部1と、該計画部1で作成した出荷計
画に基づいてパレット30、キャリア31、倉庫クレー
ン57に作業指示を出すことにより製品55の搬送をコ
ントロールする操業制御部2、前記出荷計画と操業実績
記憶部26からの操業実績とのズレを解析する解析部
3、操業進捗情報記憶部25からの操業進捗状況に応じ
て作業指示の修正(作業順入れ替え)を行う修正フィー
ドバック部A、前記出荷計画と操業進捗状況のズレに対
して計画修正(計画再起動)を行う修正フィードバック
部B、解析部3からの解析結果を基に計画作成時の内部
基準値の修正を行う修正フィードバック部Cの6つの処
理部によって構成されている。それぞれの処理部間の情
報伝達は、使用目的に応じた、複数の情報記憶部を介し
たデータのやりとりにより行われ、常に適正な自動スケ
ジュール系を維持するサイクリックな仕組みとなってい
る。
In this product shipping operation, an optimum one is selected from the plurality of carriers 31 and the carrier 3 is selected.
This is performed by controlling the order and timing of issuing the work instruction to the first. Next, the overall basic configuration will be described. As shown in FIG. 1, a device for scheduling a product shipping operation is roughly divided into a planning unit 1 for scheduling a shipping plan, a pallet 30, a carrier 31, and a warehouse crane based on the shipping plan created by the planning unit 1. An operation control unit 2 that controls the conveyance of the product 55 by issuing a work instruction to the operation unit 57, an analysis unit 3 that analyzes a deviation between the shipping plan and the operation result from the operation result storage unit 26, and an operation progress information storage unit 25. Feedback section A for correcting the work instruction (replacement of the work order) in accordance with the operation progress status, correction feedback section B for performing a plan correction (plan restart) for the deviation between the shipping plan and the operation progress status, analysis It is composed of six processing units of a correction feedback unit C for correcting an internal reference value at the time of creating a plan based on the analysis result from the unit 3. Information transmission between the respective processing units is performed by exchanging data via a plurality of information storage units according to the purpose of use, and has a cyclical mechanism that always maintains an appropriate automatic schedule system.

【0015】更に、詳細に説明する。計画部1は、バー
ス計画スケジューラ4と入出庫計画スケジューラ5から
構成されており、ホストコンピュータから切り離した分
散処理システムである。計画作成処理に際して、計画部
1は基本情報記憶部21に予め記憶されている倉庫51
内にある出荷製品情報(サイズ、重量、員数、品種、対
象船名、濡れ可否等)、設備(倉庫及び岸壁のクレー
ン、キャリア等)の能力及び稼働休止計画情報(補修・
点検時間等)、配船情報(船名、入港時刻等)、天気情
報(降水確率、台風情報等)等の(情報は変更発生都
度、自動あるいは手動で更新登録されて常に最新情報に
維持されている)情報群91と、操業進捗情報記憶部2
5に記憶されているリアルタイムで最新情報に更新され
た、岸壁荷役作業等の操業進捗情報95を定期的に取り
込み、更に、基準値設定部29に記憶している過去の統
計値によって設定された岸壁クレーンサイクルタイム、
付帯作業標準時間等の内部基準となる値等である計画基
準値20を取り込み、この取り込みが完了するとバース
計画スケジューラ4が起動する。
Further details will be described. The planning unit 1 is a distributed processing system that includes a berth planning scheduler 4 and an entry / exit planning scheduler 5, and is separated from the host computer. At the time of the plan creation processing, the planning unit 1 stores the warehouse 51 stored in the basic information storage unit 21 in advance.
Shipment product information (size, weight, number of breeds, variety, target ship name, wetness etc.), equipment (warehouse and quay cranes, carriers, etc.) and shutdown plan information (repair
(Inspection time, etc.), vessel assignment information (ship name, port entry time, etc.), weather information (precipitation probability, typhoon information, etc.) (Each time a change occurs, information is automatically or manually updated and registered and always kept up to date. Information group 91 and the operation progress information storage unit 2
The operation progress information 95 such as quay cargo handling work updated to the latest information in real time stored in the storage unit 5 is periodically taken in, and further set based on past statistical values stored in the reference value setting unit 29. Quay crane cycle time,
A plan reference value 20, which is a value serving as an internal reference such as a standard time for ancillary work, is fetched. When this fetch is completed, the berth planning scheduler 4 is started.

【0016】バース計画スケジューラ4は、 取り込んだ各種設備の能力、稼働休止計画情報等の
各情報を基に、出荷岸壁50に複数存在する岸壁クレー
ン52及び付帯設備の計画作成時間範囲内の時系列的な
荷役能力を判定する。 この判定した荷役能力と前記入力した出荷製品情
報、配船情報等の各情報により、積み込み対象船54と
岸壁クレーン52を紐付ける。
The berth planning scheduler 4 performs a chronological analysis of a plurality of quay cranes 52 existing on the shipping quay 50 and ancillary facilities within a planning time range on the basis of various information such as the acquired capacity of various facilities and operation suspension plan information. The effective cargo handling capacity. The loading target ship 54 and the quay crane 52 are associated with each other such as the determined cargo handling capacity and the input shipping product information, ship allocation information, and the like.

【0017】 その紐付け結果と前記入力した計画基
準値、出荷製品員数情報、天気情報等の各情報を基にし
て積み込み対象船54毎の荷役作業時間(開始時間と終
了時間)を算定する。 この算定結果を基に、岸壁クレーン52毎に時系列
に荷役作業時間を割り付ける。
The cargo handling time (start time and end time) for each loading target ship 54 is calculated based on the linking result and the input information such as the plan reference value, the number of shipped products, and the weather information. Based on the calculation result, the cargo handling time is allocated in time series for each quay crane 52.

【0018】 この割り付け結果を別途設けた表示画
面上に32時間分ビジュアル表示し、出荷作業管制員の
共通情報として利用される。入出庫スケジューラ5は、
上記バース計画スケジューラ4で算定した積み込み対象
船54毎の荷役作業時間(開始時間と終了時間)と、予
め上位計算機で作成され、出庫ロット情報記憶部23に
記憶されている積み込み対象船54毎のロット(パレッ
ト1台分が1ロット)量、各ロット内製品量、倉庫内置
き場位置、パレット内積み付け位置等の製品出庫ロット
編成情報93と、入庫ロット情報記憶部22に記憶され
ている製造ライン53から倉庫51に搬入される製品5
5のロット量とその各ロッド内製品量、パレット内積み
付け位置、倉庫51内置き場位置等の入庫ロット編成情
報92と、操業進捗情報記憶部25に記憶されリアルタ
イムで最新情報に更新されている倉庫51の入出庫積み
卸し作業、浜出作業等の進捗情報95、更には、基準値
設定部29に記憶している、過去の統計値によって設定
された倉庫クレーンサイクルタイム、付帯作業標準時間
等の内部基準となる値である計画基準値20を取り込
む。
This allocation result is visually displayed for 32 hours on a separately provided display screen, and is used as common information for shipping work controllers. The entry / exit scheduler 5,
The loading / unloading work time (start time and end time) calculated by the berth planning scheduler 4 for each loading target ship 54 and each loading target ship 54 created in advance by the host computer and stored in the outgoing lot information storage unit 23. Product delivery lot organization information 93 such as lot (one lot for one pallet), product quantity in each lot, warehouse storage position, pallet loading position, etc., and manufacturing stored in the storage lot information storage unit 22 Product 5 delivered to warehouse 51 from line 53
The lot number 5 and the received lot organization information 92 such as the product amount in each rod, the pallet stacking position, the storage position in the warehouse 51, and the like, and are stored in the operation progress information storage unit 25 and updated to the latest information in real time. Progress information 95 such as loading / unloading and loading / unloading work of the warehouse 51, beaching work, etc., and furthermore, a warehouse crane cycle time, ancillary work standard time, etc. stored in the reference value setting unit 29 and set by past statistical values. A plan reference value 20, which is a value serving as an internal reference, is taken.

【0019】 そして、この取り込んだ荷役作業時
間、出庫ロット情報93、入庫ロット情報92、設備稼
働休止計画情報91、計画基準値20等の各情報を基に
して出荷対象となる製品40を適切な時刻に倉庫51か
ら出荷岸壁50への浜出を実現するために倉庫51に複
数存在する倉庫クレーン57に対して、輻輳しないよう
に、各倉庫クレーン57毎の出庫(倉庫51内に在る製
品をパレット30に積み込む)作業を時系列的に自動割
り付けを行う。
Then, the product 40 to be shipped is appropriately determined based on each of the loaded cargo handling work time, outgoing lot information 93, incoming lot information 92, equipment operation suspension plan information 91, plan reference value 20, and the like. In order to realize beaching from the warehouse 51 to the shipping quay 50 at the time, a plurality of warehouse cranes 57 existing in the warehouse 51 are unloaded from each warehouse crane 57 so as not to be congested (products in the warehouse 51). Are loaded on the pallet 30).

【0020】 更に、この割り付け結果と前記取り込
んだ荷役作業場所、倉庫51内製品置き場位置、計画基
準値20等の情報を基にして出荷製品40を倉庫51か
ら出荷岸壁50へ浜出するために該製品40を載せるパ
レット30の配車場所とその時刻、更には、パレット3
0を運搬するキャリア31の配車場所と時刻、パレット
30の搬送先及び搬送先到着時刻等を有する出荷計画情
報94を演算し、出荷計画情報記憶部24に記憶する。
Further, on the basis of this allocation result and the information of the imported cargo handling work place, the product storage position in the warehouse 51, the plan reference value 20, etc., the shipping products 40 are moved from the warehouse 51 to the shipping quay 50. The dispatch location and the time of the pallet 30 on which the product 40 is placed, and furthermore, the pallet 3
The shipping plan information 94 including the location and time of the carrier 31 carrying the 0, the transport destination of the pallet 30 and the arrival time of the transport destination is calculated and stored in the shipping plan information storage unit 24.

【0021】 この各倉庫クレーン57への割り付け
結果は32時間分ビジュアル表示され、出荷作業管制員
の共通情報として利用される。尚、計画部1で得られる
自動スケジューリング結果である出荷計画情報94は出
荷作業管制員の判断によって、ビジュアル表示されてい
る分散系端末画面上で、マウスあるいはキーボードによ
り容易にマニュアル修正することが可能である。
The result of assignment to each warehouse crane 57 is visually displayed for 32 hours, and is used as common information for shipping work controllers. The shipping plan information 94, which is the result of the automatic scheduling obtained by the planning unit 1, can be easily manually corrected by a mouse or a keyboard on the visual display of the distributed terminal according to the judgment of the shipping work controller. It is.

【0022】操業制御部2は、キャリア/パレット選択
部6と配車指示制御部7から構成されており、リアルタ
イムでオンライン処理される。処理に際しては、キャリ
ア/パレット選択部6において、出荷計画情報記憶部2
4に記憶されている出荷計画情報94のパレット30及
びキャリア31の配車時刻とその場所の各情報と、複数
あるパレット30及びキャリア31の使用状況等の情報
を基に、各キャリア31の配車時刻になる毎に複数ある
空のキャリア31と複数ある空のパレット30から移動
時間が最小となるキャリア31とパレット30の組み合
わせを選択する。
The operation control section 2 comprises a carrier / pallet selecting section 6 and a dispatch instruction control section 7, and is processed online in real time. At the time of processing, the carrier / pallet selector 6 stores the shipping plan information storage 2
4, the dispatch time of each carrier 31 based on the information on the dispatch time and the location of the pallet 30 and the carrier 31 of the shipping plan information 94 and the information such as the usage status of the plurality of pallets 30 and the carrier 31. Is selected, a combination of the carrier 31 and the pallet 30 having the minimum moving time is selected from the plurality of empty carriers 31 and the plurality of empty pallets 30.

【0023】配車指示制御部7は、 キャリア/パレット選択部6で選択したキャリア3
1に対して配車命令を行う。そして、この配車命令を受
けたキャリア31は指定された時刻に、指定された場所
に移動する。 更に、この指定された場所にパレット30及びキャ
リア31が到着したことを確認すると倉庫クレーン57
に該パレット30に製品40の積み込みを指示する。
The dispatch instruction control unit 7 controls the carrier 3 selected by the carrier / pallet selecting unit 6.
1 is dispatched. Then, the carrier 31 that has received the dispatch instruction moves to the designated place at the designated time. Further, when it is confirmed that the pallet 30 and the carrier 31 have arrived at the designated place, the warehouse crane 57
Is instructed to load the product 40 on the pallet 30.

【0024】 次に、この製品40のパレット30へ
の積み込みが完了したことを確認すると、前記積み込み
対象船の製品置き場に搬送することをキャリア31に指
示する。 この指示に従ってキャリア31が走行して対象船の
製品置き場にパレット30を載置したことを確認する
と、岸壁クレーン52に製品40の対象船54への積み
込み指示を出す。
Next, when it is confirmed that the loading of the product 40 on the pallet 30 is completed, the carrier 31 is instructed to transport the product 40 to the product storage area of the ship to be loaded. After confirming that the carrier 31 has traveled and placed the pallet 30 on the product storage area of the target ship according to this instruction, the quay crane 52 issues an instruction to load the product 40 into the target ship 54.

【0025】操業進捗情報記憶部25は、倉庫51及び
出荷岸壁50に存在する出荷作業に関わる倉庫クレーン
57、岸壁クレーン52、パレット30及びキャリア3
1の各設備の操業(稼働)の進捗(例えば、各クレーン
の吊り回数、キャリアの目的地到着信号等)情報95を
前記各設備に設けたセンサー等(図示せず)から逐次取
り込んで記憶し、この記憶情報は作業の進捗に合わせて
リアルタイムに更新される。
The operation progress information storage unit 25 stores warehouse cranes 57, quay cranes 52, pallets 30, and carriers 3 related to shipping operations existing in the warehouse 51 and the shipping quay 50.
1. Information 95 on the progress of operation (operation) of each facility (for example, the number of times each crane is hung, the arrival signal of the destination of the carrier, etc.) information 95 is sequentially taken from sensors and the like (not shown) provided in each facility and stored. The stored information is updated in real time in accordance with the work progress.

【0026】更に、操業実績情報記憶部26は各積み込
み対象船54に関わる作業が完了する毎に、その操業実
績(例えば、荷役作業開始時刻,終了時刻等)情報96
を記憶し、一定期間保持する。解析部3は、発生原因解
析部8と差異定量解析部9から構成されており、定期的
に一括して処理する形態である。
Further, each time the work related to each loading target ship 54 is completed, the operation result information storage unit 26 stores the operation result (eg, cargo handling work start time, end time, etc.) information 96.
Is stored for a certain period of time. The analysis unit 3 includes an occurrence cause analysis unit 8 and a difference quantitative analysis unit 9, and is a form in which processing is periodically and collectively performed.

【0027】解析処理に際しては、まず、出荷計画情報
記憶部24からの出荷計画情報94と操業実績記憶部2
6からの操業実績情報96を解析情報記憶部27を介し
て予め設定されたタイミングで解析情報97として取り
込み、発生原因解析部8が起動し、下記解析〜を行
う。 前記解析情報97より出荷計画と操業実績のズレ
(作業開始時刻及び作業終了時刻)が予め設定した基準
値以上発生している箇所、即ち、作業の種類(倉庫積込
作業、浜出作業、岸壁荷役作業等)を選別する。
In the analysis process, first, the shipping plan information 94 from the shipping plan information storage unit 24 and the operation result storage unit 2
6 is fetched as analysis information 97 at a preset timing via the analysis information storage unit 27 via the analysis information storage unit 27, the occurrence cause analysis unit 8 is activated, and the following analysis is performed. Based on the analysis information 97, the location where the deviation between the shipping plan and the actual operation (work start time and work end time) is equal to or greater than a preset reference value, that is, the type of work (warehouse loading work, beaching work, quay) Sorting).

【0028】 ズレが発生している作業の種類別にズ
レ発生原因を、荒天影響、配船遅れ等により発生する外
乱と、計画に使用する基準値20が実操業と合わないた
めに発生する内乱に層別処理する。即ち、基本情報記憶
部21に記憶した設備稼働休止情報、配船情報、天気情
報等を逐次入力し、計画を作成した時点と、その後の上
記情報の変化状態をチェックして、その変化量が予め設
定した基準値以上にズレている場合は、荒天影響、配船
遅れ、キャリア、クレーンの突発故障等により発生する
外乱と判定し、また、前記変化量にズレが認められない
場合は、外乱に該当しないと判断し、計画に使用する基
準値が実操業と合わないために発生する内乱と判定す
る。
The causes of the displacement for each type of work in which the displacement is occurring include disturbances caused by stormy weather effects, delays in ship assignment, and disturbances caused by a reference value 20 used for planning not matching actual operation. Perform stratified processing. That is, the equipment operation stoppage information, ship allocation information, weather information, etc. stored in the basic information storage unit 21 are sequentially input, and the time when the plan is created and the subsequent change state of the above information are checked. If the deviation is larger than the preset reference value, it is determined that the disturbance is caused by stormy weather effects, delays in ship arrangement, sudden failure of the carrier or crane, etc. Is determined to be not applicable, and it is determined that the internal disturbance occurs because the reference value used for planning does not match the actual operation.

【0029】 この様にして内乱と判定した場合には
結果を前記作業種類及びその作業に使用される設備別
(倉庫クレーン、岸壁クレーン、キャリア等の各号機)
に区分選別する。ズレ定量解析部9は、発生原因解析部
8で解析された発生原因別(作業種類、使用設備別)に
計画値と実績値のズレを定量化する処理を行う。
When it is determined that a disturbance has occurred in this manner, the result is classified according to the type of the work and the equipment used for the work (each unit such as a warehouse crane, a quay crane, and a carrier).
Sorting. The deviation quantitative analysis unit 9 performs a process of quantifying the deviation between the planned value and the actual value for each occurrence cause (for each type of work and equipment used) analyzed by the occurrence cause analysis unit 8.

【0030】解析結果記憶部28は前記解析部3で解析
された結果情報98を記憶する。修正フィードバック部
Aは、障害予知判定部10と緊急作業割込制御部11か
ら構成されている。この障害予知判定部10は、操業進
捗情報記憶部25から操業進捗情報95、出荷計画情報
記憶部24から出荷計画情報94を各々取り込み、現在
進捗中の出荷岸壁50での荷役作業に対して、倉庫51
での出庫作業をこのまま計画順通りの操業を続けた場合
に、パレット30及びキャリア31で、倉庫51から出
荷対象製品40の出荷岸壁50への浜出が遅れてしま
い、岸壁50に積み込み製品40が無くなり、岸壁クレ
ーン52での積み込み(荷役)作業の中断が発生するか
否かを計算する。そして、積み込み作業の中断が発生す
る(岸壁50に積み込み製品40が無くなる)と判定し
た場合、緊急作業割込制御部11が起動し、対象となる
作業を緊急作業として最優先の作業として割り込ませる
制御が働き、下記の様にして適正な作業順の入れ替えを
行う。
The analysis result storage unit 28 stores the result information 98 analyzed by the analysis unit 3. The correction feedback unit A includes a failure prediction determination unit 10 and an emergency work interrupt control unit 11. The failure prediction determination unit 10 captures the operation progress information 95 from the operation progress information storage unit 25 and the shipment plan information 94 from the shipment plan information storage unit 24, respectively. Warehouse 51
If the unloading operation is continued as planned, the delivery of the products 40 to be shipped from the warehouse 51 to the shipping quay 50 by the pallet 30 and the carrier 31 is delayed by the pallet 30 and the carrier 31. Is calculated, and whether the loading (loading) work by the quay crane 52 is interrupted or not is calculated. Then, when it is determined that the loading operation is interrupted (the loading product 40 disappears on the quay 50), the emergency operation interrupt control unit 11 is activated, and the target operation is interrupted as the highest priority operation as the emergency operation. The control is activated, and the proper work order is changed as follows.

【0031】通常、浜出作業はキャリア31及び倉庫ク
レーン57に作業指示が出されることにより行われる。
配車指示制御部7で出された作業指示は、操業制御部2
にある作業指示登録ファイルに一旦登録され、その作業
を行うキャリア31或いは倉庫クレーン57が空くまで
登録されたままの状態になる。この作業指示は計画に従
って登録されるので、通常操業では複数の作業指示が発
生し、待ち行列を形成することになる。作業が紐付く
(実行される)のは、基本的に登録時刻順であるが、前
記緊急作業割込制御部11が働いた場合に限り、緊急作
業対象となったものを待ち行列の先頭に入れ替える処理
を行う。緊急対象作業に作業指示が出ていない場合は、
その場で作業指示を出し、待ち行列の先頭に登録され
る。これにより、緊急対象作業は、作業指示登録ファイ
ルに登録され次の作業より優先的に実行されることにな
る。
Normally, the beaching work is performed by giving a work instruction to the carrier 31 and the warehouse crane 57.
The work instruction issued by the dispatch instruction control unit 7 is transmitted to the operation control unit 2.
Is temporarily registered in the work instruction registration file, and remains registered until the carrier 31 or the warehouse crane 57 performing the work becomes empty. Since the work instructions are registered according to the plan, a plurality of work instructions are generated in the normal operation, and a queue is formed. The work is linked (executed) basically in the order of the registration time. However, only when the emergency work interrupt control unit 11 operates, the emergency work target is placed at the head of the queue. Perform the replacement process. If there are no work instructions for urgent work,
A work instruction is issued on the spot and registered at the head of the queue. As a result, the emergency target work is registered in the work instruction registration file and is executed with higher priority than the next work.

【0032】また、この修正フィードバック部Aは進捗
中の操業の変化にダイレクトに対応させるため、リアル
タイムで自動処理される。また、必要に応じて、手動介
入による作業順変更を可能にすることが好ましい。修正
フィードバック部Bは、計画差異判定部12と計画再起
動制御部13から構成されており、この計画差異判定部
12は出荷計画情報記憶部24から出荷計画情報94、
操業進捗情報記憶部25から操業進捗情報95を取り込
み、出荷計画情報94と操業進捗情報95を比較してそ
の差異量を求め、その差異量が予め設定した基準値を越
えているか否かの判定を行う。もし、差異量が基準値を
越えた場合は、計画再起動制御部13が起動し、計画部
1を再起動する。この修正フィードバック部Bは、操業
制御部2を適正に起動するために、リアルタイムで自動
処理され、操業進捗との整合性を図りながら出荷計画情
報94を適宜更新する。また、必要に応じて、手動介入
による再起動も可能である。全体の処理系の中で、修正
フィードバック部Bは、修正フィードバック部Aの起動
頻度を抑える役割も持つ。更に、修正フィードバック部
Bの計画再起動制御部13は、計画差異判定部12での
判定結果による起動の他に、予め設定した時間経過に基
づき、計画と操業進捗の差異の有無に関係なく定期的に
計画部1を再起動する定期自動リスケジューリング機能
も持つ。
The correction feedback section A is automatically processed in real time in order to directly cope with a change in the ongoing operation. In addition, it is preferable that the work order can be changed by manual intervention as necessary. The correction feedback unit B includes a plan difference determining unit 12 and a plan restart control unit 13. The plan difference determining unit 12 stores the shipping plan information 94 from the shipping plan information storage unit 24,
The operation progress information 95 is fetched from the operation progress information storage unit 25, the shipping plan information 94 and the operation progress information 95 are compared to determine the difference, and it is determined whether the difference exceeds a preset reference value. I do. If the difference amount exceeds the reference value, the plan restart control unit 13 starts, and restarts the plan unit 1. The correction feedback unit B is automatically processed in real time in order to appropriately start the operation control unit 2, and updates the shipping plan information 94 as appropriate while maintaining consistency with the operation progress. Further, if necessary, a restart by manual intervention is also possible. In the entire processing system, the correction feedback unit B also has a role of suppressing the activation frequency of the correction feedback unit A. Further, the plan restart control unit 13 of the correction feedback unit B periodically starts based on the elapse of a preset time irrespective of whether there is a difference between the plan and the operation progress, in addition to the start based on the determination result of the plan difference determination unit 12. It also has a periodic automatic rescheduling function for periodically restarting the planning unit 1.

【0033】修正フィードバック部Cは、比較評価判定
部14と基準値修正制御部15から構成されており、こ
の比較評価判定部14は、解析結果記憶部28から解析
結果情報98を、予め設定した期間毎に定期的に取り込
み、この解析結果情報98と計画基準値20の値を比較
して差異があるか否かの判定を統計的に検定して行う。
比較評価判定部14で差異があると判定された場合は、
基準値修正制御部15が起動され、計画基準値20を解
析結果情報98に基づく基準値に修正する。これにより
修正された計画基準値20の値は、次回計画部1が起動
する時点から有効となる。修正フィードバック部Cの処
理は、統計的な検定が行われるため、ある程度のデータ
数を確保する必要がある。従って、予め設定した期間単
位に一括して処理する形態をとる。また、修正フィード
バック部Cの基準値修正制御部15は、計画基準値20
を適正な値に修正する方法として、一旦、出力表示し、
それを基に人為的な判断で計画基準値20の変更を行う
方法と、自動修正する方法の2つの方法から構成されて
おり、どちらかを選択することにより機能する。
The correction feedback section C comprises a comparative evaluation judging section 14 and a reference value correction control section 15. The comparative evaluation judging section 14 sets analysis result information 98 from the analysis result storage section 28 in advance. The analysis result information 98 is periodically taken in every period, and the analysis result information 98 is compared with the plan reference value 20 to determine whether there is any difference by performing a statistical test.
If the comparative evaluation determination unit 14 determines that there is a difference,
The reference value correction control unit 15 is activated, and corrects the plan reference value 20 to a reference value based on the analysis result information 98. The value of the plan reference value 20 corrected in this way becomes effective from the next time the planning unit 1 starts. In the processing of the correction feedback unit C, since a statistical test is performed, it is necessary to secure a certain number of data. Therefore, a mode is adopted in which processing is performed collectively in a preset period unit. In addition, the reference value correction control unit 15 of the correction feedback unit C
As a method of correcting to an appropriate value, once output and display,
It is composed of two methods, a method of changing the plan reference value 20 by an artificial judgment based on that and a method of automatic correction, and functions by selecting either one.

【0034】[0034]

【発明の効果】本発明により、倉庫の製品を船積み出荷
する作業指示を、自動的に且つ高精度に行うことが出来
ると共に出荷作業の効率化を図ることが可能となり、岸
壁での荷切れによる船積み作業の延長を抑制して船の滞
船料を削減出来、出荷計画の作成回数を低減することが
出来、この分野における効果は大きい。
According to the present invention, it is possible to automatically and accurately perform a work instruction for loading and shipping products in a warehouse, and to improve the efficiency of shipping work. The extension of the loading operation can be suppressed to reduce the demurrage fee of the ship, and the number of times of preparing the shipping plan can be reduced, and the effect in this field is great.

【図面の簡単な説明】[Brief description of the drawings]

【図1】製品物流制御装置の機能構成を示す図。FIG. 1 is a diagram showing a functional configuration of a product distribution control device.

【図2】製品出荷作業に関わる設備構成を示す図。FIG. 2 is a diagram showing an equipment configuration related to a product shipping operation.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 児玉 大佐 大分県大分市大字西ノ洲1番地 新日本製 鐵株式会社大分製鐵所内 ──────────────────────────────────────────────────続 き Continuing from the front page (72) Inventor Colonel Kodama 1 Oshinozu, Oita-shi, Oita Prefecture Inside Nippon Steel Corporation Oita Works

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 倉庫の製品を船積み出荷するための出荷
計画を計画部でスケジューリングし、このスケジューリ
ングした出荷計画情報に基づいて、倉庫の製品をクレー
ン及び運搬車輌等の製品出荷作業設備に船積み出荷する
作業指示を行い、この作業指示に基づいて行う前記製品
出荷作業設備が船積み実出荷作業の進捗状況と前記スケ
ジューリングした出荷計画を比較して両者のズレ量を求
め、このズレ量が予め設定した基準値を越えると前記計
画部に計画作成指示を行う製品物流制御方法において、
前記計画部でスケジューリングした出荷計画と前記実出
荷作業の進捗状況から該出荷計画に従って実出荷作業を
行った場合に船積み出荷する位置の岸壁に荷切れが発生
するか否か及び荷切れ発生時刻を判定し、荷切れが発生
すると判定した場合には、その荷切れが発生する時刻ま
でにその荷切れ発生作業を優先的に行う様に倉庫の製品
を船積み出荷する位置の岸壁に出荷するように割り込み
指示を前記クレーン、運搬車輌等の製品出荷作業設備に
行うことを特徴とする製品物流制御方法。
1. A planning section schedules a shipping plan for loading and shipping products in a warehouse, and loads and ships products in a warehouse to product shipping work facilities such as cranes and transport vehicles based on the scheduled shipping plan information. The product shipping work equipment that performs the work instruction based on the work instruction compares the progress of the actual shipping work with the scheduled shipping plan to determine the amount of deviation between the two, and the amount of deviation is set in advance. In a product distribution control method for instructing the planning unit to create a plan when the standard value is exceeded,
From the shipping plan scheduled by the planning unit and the progress of the actual shipping work, whether or not unloading occurs at the quay at the position to be loaded and shipped when the actual shipping work is performed according to the shipping plan, and the unloading occurrence time If it is determined that unloading will occur, ship the products in the warehouse to the quay at the position where the products will be loaded and shipped so that the unloading work will be given priority by the time when the unloading occurs. A product distribution control method, wherein an interruption instruction is issued to a product shipping work facility such as the crane or the transport vehicle.
【請求項2】 前記計画部でスケジューリングした出荷
計画と前記実出荷作業の操業実績情報を比較して、両者
のズレ量を求め、このズレ量が予め設定した基準値を越
える作業が発生している場合には、ズレが発生している
作業の種類別にズレ発生原因を、荒天影響、配船遅れ等
により発生する外乱と、計画に使用する計画基準値が実
操業と合わないために発生する内乱に解析すると共にこ
の解析した結果を原因別に区分し、更に、この解析され
たズレ発生原因区分別に前記出荷計画値と操業実績値の
ズレを定量化する処理を行い、この解析したズレ発生原
因区分別ズレ量を基に前記計画基準値を修正することを
特徴とする製品物流制御方法。
2. A shipping plan scheduled by the planning unit and operation result information of the actual shipping work are compared to determine an amount of deviation between the two, and when a work in which the amount of deviation exceeds a preset reference value occurs. In the case where there is a shift, the cause of the shift for each type of work in which the shift occurs is caused by disturbance caused by stormy weather effects, delays in ship assignment, etc., and because the plan reference value used for planning does not match the actual operation Analyzing the internal disturbance and classifying the result of this analysis according to the cause, further quantifying the difference between the shipment plan value and the actual operation value for each analyzed cause of the difference A method of controlling product distribution, wherein the plan reference value is corrected based on a shift amount for each category.
【請求項3】 倉庫の製品を船積み出荷するための出荷
計画をスケジューリングする計画部と、計画部で得られ
る出荷計画情報に基づいて、倉庫の製品をクレーン及び
運搬車輌等の製品出荷作業設備で搬送して船積み出荷す
る作業指示を行う操業制御部と、前記製品出荷作業設備
の実出荷作業の進捗状況と前記計画部で作成した出荷計
画を比較して両者のズレ量を求め、このズレ量が予め設
定した基準値を越えると前記計画部に計画作成指示を行
う修正フィードバック部Bを有する製品物流制御装置に
おいて、前記計画部でスケジューリングした出荷計画と
前記実出荷作業の進捗状況から該出荷計画に従って実出
荷作業を行った場合に船積み出荷する位置の岸壁に荷切
れが発生するか否か及び荷切れ発生時刻を判定し、荷切
れが発生すると判定した場合には、その荷切れが発生す
る時刻までにその荷切れ発生作業を優先的に行う様に倉
庫の製品を船積み出荷する位置の岸壁に出荷するように
割り込み指示を前記クレーン及び運搬車輌等の製品出荷
作業設備に指示を出す修正フィードバック部Aを有する
ことを特徴とする製品物流制御装置。
3. A planning unit that schedules a shipping plan for loading and shipping products in a warehouse, and based on the shipping plan information obtained by the planning unit, the products in the warehouse are transferred to product shipping work facilities such as cranes and transport vehicles. An operation control unit that issues a work instruction for carrying and carrying and shipping, and comparing the progress of the actual shipping work of the product shipping work equipment with the shipping plan created by the planning unit to determine the amount of deviation between the two, When the value exceeds a preset reference value, in the product distribution control device having a correction feedback unit B for instructing the planning unit to make a plan, the shipping plan is determined based on the shipping plan scheduled by the planning unit and the progress of the actual shipping work. Determines whether or not unloading will occur on the quay at the shipping / shipping position and the time of unloading when the actual shipping work is performed according to, and determines that unloading occurs. In such a case, the crane, the transport vehicle, etc. are instructed to ship the products in the warehouse to the quay at the position where the products are to be loaded and shipped so that the unloading work will be given priority by the time when the unloading occurs. A product distribution control device comprising a correction feedback section A for issuing an instruction to a product shipping work facility of the present invention.
【請求項4】 前記計画部でスケジューリングした出荷
計画と前記実出荷作業の操業実績情報を比較して、両者
のズレ量を求め、このズレ量が予め設定した基準値を越
える作業が発生している場合には、ズレが発生している
作業の種類別にズレ発生原因を、荒天影響、配船遅れ等
により発生する外乱と、計画に使用する計画基準値が実
操業と合わないために発生する内乱に解析すると共にこ
の解析した結果を原因別に区分し、更に、この解析され
たズレ発生原因区分別に計画値と実績値のズレを定量化
する処理を行う解析部と、該解析部の解析結果情報と計
画基準値記憶部に記憶した計画基準値を比較して差異が
あるか否かの判定を行い、差異があると判定された場合
は、前記計画基準値記憶部に記憶した計画基準値を修正
する修正フィードバック部Cを有することを特徴とする
製品物流制御装置。
4. A shipping plan scheduled by the planning unit and operation result information of the actual shipping work are compared to obtain a shift amount between the two, and when a work in which the shift amount exceeds a preset reference value occurs. In the case where there is a shift, the cause of the shift for each type of work in which the shift occurs is caused by disturbance caused by stormy weather effects, delays in ship assignment, etc., and because the plan reference value used for planning does not match the actual operation An analysis unit that analyzes the internal disturbance and classifies the result of the analysis by cause, and further performs a process of quantifying a difference between a planned value and an actual value according to the analyzed cause of the difference; and an analysis result of the analysis unit. The information and the plan reference value stored in the plan reference value storage unit are compared to determine whether there is a difference. If it is determined that there is a difference, the plan reference value stored in the plan reference value storage unit is determined. Correction feedback to correct A product logistics control device having a lock section C.
JP4057798A 1998-02-23 1998-02-23 Product physical distribution control method and device thereof Pending JPH11236105A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4057798A JPH11236105A (en) 1998-02-23 1998-02-23 Product physical distribution control method and device thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4057798A JPH11236105A (en) 1998-02-23 1998-02-23 Product physical distribution control method and device thereof

Publications (1)

Publication Number Publication Date
JPH11236105A true JPH11236105A (en) 1999-08-31

Family

ID=12584354

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4057798A Pending JPH11236105A (en) 1998-02-23 1998-02-23 Product physical distribution control method and device thereof

Country Status (1)

Country Link
JP (1) JPH11236105A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001301927A (en) * 2000-04-25 2001-10-31 Matsushita Electric Works Ltd Loading work indicating method and its system
JP2002091536A (en) * 2000-09-13 2002-03-29 Nippon Steel Corp Managing method for integrated manufacture of steel product, scheduling device and storage medium
JP2010095333A (en) * 2008-10-16 2010-04-30 Jfe Steel Corp Device for planning and supporting warehousing work
JP2011225337A (en) * 2010-04-20 2011-11-10 Toyota Industries Corp Cargo handling system
JP2012086984A (en) * 2010-09-21 2012-05-10 Jfe Steel Corp Warehouse work plan creation device
JP5556975B1 (en) * 2012-10-15 2014-07-23 Jfeスチール株式会社 Shipping work plan creation system, shipping work plan creation method and shipping work method
JP2017188118A (en) * 2016-04-08 2017-10-12 リープヘル−ヴェルク ネンツィング ゲーエムベーハー System for digitally supporting work process

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001301927A (en) * 2000-04-25 2001-10-31 Matsushita Electric Works Ltd Loading work indicating method and its system
JP2002091536A (en) * 2000-09-13 2002-03-29 Nippon Steel Corp Managing method for integrated manufacture of steel product, scheduling device and storage medium
JP2010095333A (en) * 2008-10-16 2010-04-30 Jfe Steel Corp Device for planning and supporting warehousing work
JP2011225337A (en) * 2010-04-20 2011-11-10 Toyota Industries Corp Cargo handling system
JP2012086984A (en) * 2010-09-21 2012-05-10 Jfe Steel Corp Warehouse work plan creation device
JP5556975B1 (en) * 2012-10-15 2014-07-23 Jfeスチール株式会社 Shipping work plan creation system, shipping work plan creation method and shipping work method
JP2017188118A (en) * 2016-04-08 2017-10-12 リープヘル−ヴェルク ネンツィング ゲーエムベーハー System for digitally supporting work process

Similar Documents

Publication Publication Date Title
CN110516976B (en) Automatic container terminal AGV (automatic guided vehicle) scheduling method capable of selecting loading and unloading completion time
JP5556975B1 (en) Shipping work plan creation system, shipping work plan creation method and shipping work method
TWI515523B (en) The method of generating the transfer schedule of the transport system and the transport vehicle
KR20150124958A (en) System and method for controlling at least two automated non-passing rail mounted gantry cranes
JP5686072B2 (en) Warehouse work plan creation device
CN117035371B (en) Port scheduling method and system based on big data
JPH11236105A (en) Product physical distribution control method and device thereof
US20180374017A1 (en) System and method for real time scheduling
US20230252395A1 (en) A quay crane operation method
CN116415787A (en) Logistics transportation vehicle dispatching method, system and device
JPH08272402A (en) Inference device for raw material transportation plan assignment of ships
JP2006124048A (en) Delivery system and delivery method
KR101686323B1 (en) Method and apparatus for controlling speed of conveyor
Dong et al. A dynamic delivery strategy for material handling in mixed-model assembly lines using decentralized supermarkets
CN117196269B (en) Intelligent transfer control method based on artificial intelligence and computer program medium
JP2022091599A (en) Bottleneck visualization device and bottleneck visualization method
US20190005414A1 (en) Rubust dynamic time scheduling and planning
JPH05298328A (en) Automatic correction device for production plan
CN117383269A (en) Automatic wharf operation machine instruction automatic changing and gradual detail method and system
CN118037006B (en) Site bridge job scheduling method and scheduling system
CN114506689B (en) Operation method and system for container terminal
JP3289844B2 (en) Raw material transport control method
JP3161330B2 (en) Inbound and outbound processing instructions
JPH08215994A (en) Scheduler support system and method therof
JP2024049526A (en) Shipping System

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20041116

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20041130

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20050329