JPH11205318A - Network supervisory and controlling method and system - Google Patents

Network supervisory and controlling method and system

Info

Publication number
JPH11205318A
JPH11205318A JP10003068A JP306898A JPH11205318A JP H11205318 A JPH11205318 A JP H11205318A JP 10003068 A JP10003068 A JP 10003068A JP 306898 A JP306898 A JP 306898A JP H11205318 A JPH11205318 A JP H11205318A
Authority
JP
Japan
Prior art keywords
alarm
main cause
network
network management
management system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP10003068A
Other languages
Japanese (ja)
Other versions
JP3305248B2 (en
Inventor
Daisuke Taniguchi
大輔 谷口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NEC Corp
Original Assignee
NEC Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NEC Corp filed Critical NEC Corp
Priority to JP00306898A priority Critical patent/JP3305248B2/en
Publication of JPH11205318A publication Critical patent/JPH11205318A/en
Application granted granted Critical
Publication of JP3305248B2 publication Critical patent/JP3305248B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To eliminate the need for an effect development information table and to reduce the loads of an operator in changing network configuration by judging a main cause in cooperation between respective sub network management systems. SOLUTION: When a main cause judgement part 23 receives an alarm from the inside of a sub network through an alarm reception part 24, whether or not it is a main cause alarm generated inside the present network as the main cause of a device fault or the like is decided in a received alarm classifying part 1. When it is inside the present management, the alarm is reported to a host system and an under-generation main cause alarm list 3 is updated. Upon receiving the alarm incapable of being immediately judged, the present management part and an influence judgement part 21 inside the opposite sub network management system of a fault device are inquired and a response by an effect judgement inquiry part 2 is waited for by timer monitoring. The effect judgement part 21 develops effect from the information of the under- generation main cause alarm list 3 and a configuration management data base 5 and updates the held under-generation main cause alarm list 6 in the case of being within the present management sub network.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、基幹系伝送設備に
関するネットワークオペレーションシステムにおけるネ
ットワーク監視制御方法とシステムに関する。
The present invention relates to a method and system for monitoring and controlling a network in a network operation system for a backbone transmission facility.

【0002】[0002]

【従来の技術】図4は従来のネットワーク監視制御シス
テムの一例を示す図である。
2. Description of the Related Art FIG. 4 is a diagram showing an example of a conventional network monitoring and control system.

【0003】複数のサブネットワーク管理システム(以
下SB−NMSと称す)およびそれらを統合するネット
ワーク管理システム(以下NMSと称す)とから構成さ
れる統合ネットワーク管理システムにおいて、監視対象
となる伝送装置より通知される主原因警報、およびその
影響警報が一時に集中して通知されるため、それらの中
から主原因警報のみを識別する主原因判定処理を迅速に
行うことが求められる。例えば、通信障害警報が受信さ
れた堤合、その主原因が装置自体の故障によるものか通
信ケーブル等の伝送路障害によるものかは、その警報通
知内容単独では判定できない。判定するためには、自身
のネットワーク内で発生中の他の警報通知、および、他
のネットワーク内で発生中の警報通知との相関で判定さ
れる必要がある。
In an integrated network management system composed of a plurality of sub-network management systems (hereinafter, referred to as SB-NMS) and a network management system (hereinafter, referred to as NMS) for integrating them, a notification is transmitted from a transmission apparatus to be monitored. Since the main cause alarms and their effect alarms are notified in a concentrated manner at one time, it is required to quickly perform a main cause determination process for identifying only the main cause alarms among them. For example, it is not possible to determine whether the communication failure alarm has been received and whether the main cause is a failure of the device itself or a transmission line failure of a communication cable or the like by the content of the alarm notification alone. In order to make the determination, it is necessary to make a determination based on a correlation with another alarm notification occurring in the own network and an alarm notification occurring in another network.

【0004】従来方式においては、これらの相関関係を
予め発生瞥報とそれによって発生が予想される影響警報
の一覧として各ネットワークを総括した形式でNMS1
00−0に影響展開情報テーブル101を登録してお
き、下位SB−NMS201−0,202−0からの替
報通知内容についてこの影響展開情報テーブル101を
基に主影響警報の判定を行っている。
[0004] In the conventional system, these correlations are summarized in advance in a form in which each network is summarized as an occurrence report and a list of influence warnings which are expected to occur.
The impact deployment information table 101 is registered at 00-0, and the main impact alert is determined based on the impact deployment information table 101 with respect to the contents of the replacement notification from the lower SB-NMSs 201-0 and 202-0. .

【0005】[0005]

【発明が解決しようとする課題】ネットワークの新設、
および構成変更の際に、オペレータはSB−NMSのデ
ータべース更新と同時に、NMSの影響展開情報テーブ
ルの更新を入力する必要があり、構成情報更新に関する
オペレータの保守作業の負荷を増大させている。
[Problems to be Solved by the Invention] New establishment of a network,
When the configuration is changed, the operator needs to input the update of the NMS impact deployment information table at the same time as the update of the SB-NMS database. I have.

【0006】本発明の目的は、上位システム(NMS)
において従来方式の影響展開情報テーブルを持つことな
く影響展開処理を行い、ネットワーク構成変更時のオペ
レータの負荷を軽減するネットワーク監視制御方法とシ
ステムを提供することである。
An object of the present invention is to provide a host system (NMS)
It is an object of the present invention to provide a network monitoring control method and system for performing an impact deployment process without having an impact deployment information table of the conventional method and reducing the load on an operator when changing the network configuration.

【0007】[0007]

【課題を解決するための手段】本発明のネットワーク監
視制御方法は、複数のサブネットワーク管理システムお
よびそれらを統合するネットワーク管理システムから構
成される統合ネットワーク管理システムにおける各サブ
ネットワーク管理システム毎に、自サブネットワーク内
の装置に発生した障害による警報を受信すると、装置故
障を含む障害の主原因が明らかな障害の警報として、上
位システムに通知すると同時に、発生中主原因警報とし
て保持するステップと、発生中主原因警報から、前記発
生中主原因警報の影響を受けて障害状態になる装置を選
出する影響展開の記録を行い、影響警報一覧として保持
するステップとを有する。
A network monitoring and control method according to the present invention is provided for each sub-network management system in an integrated network management system comprising a plurality of sub-network management systems and a network management system integrating them. Receiving an alarm due to a failure that has occurred in a device in the sub-network, notifying the host system as a failure alarm that clearly indicates the main cause of the failure including the device failure, and simultaneously holding the alarm as a occurring main cause alarm; Recording an impact deployment for selecting a device which becomes in a failure state under the influence of the occurring main cause alarm from the middle main cause alarm, and holding the same as an impact alert list.

【0008】さらに、各サブネットワーク管理システム
毎に、警報受信時に主原因として即座に判定不可能な警
報については、接続関係を有する他のネットワークに発
生中主原因警報が保持されたかを問い合わせを行うステ
ップを有する。一方、他のネットワークから、発生中障
害が自ネットワーク管内の装置の主原因障害として保持
されているかどうかの問い合わせがあった場合、自管理
システム内に発生中主原因警報が保持されている記載が
ある場合にのみ、問い合わせ元システムに応答を返すス
テップと、他のサブネットワーク管理システムに前記の
問い合わせを行った後、他のサブネットワーク管理シス
テムにからの応答を待ち、応答が無い場合にのみ、主原
因警報と判定して上位システムに転送し、自サブネット
ワーク管理システム内に発生中主原因警報として保持す
るステップとを有する。
Further, for each sub-network management system, for an alarm which cannot be immediately determined as a main cause at the time of receiving an alarm, an inquiry is made as to whether or not the occurring main cause alarm is held in another network having a connection relationship. With steps. On the other hand, if there is an inquiry from another network as to whether the occurring fault is held as the main cause failure of the device in the own network, the description that the occurring main cause alarm is held in the self-management system is described. Only when there is, a step of returning a response to the inquiry source system, and after performing the above inquiry to the other sub-network management system, waits for a response from the other sub-network management system, only when there is no response, Determining the main cause alarm, transferring the same to the host system, and holding the same as the occurring main cause alarm in the own sub-network management system.

【0009】本発明のネットワーク監視制御システム
は、各サブネットワーク管理システム間の連携におい
て、主原因の判定を行う方式を提案する。サブネットワ
ーク管理システムにおいて、警報受信時に装置故障等の
主原因として明らかな警報を上位システムに通知すると
同時に発生中主原因警報として保持する機能と、発生中
主原因警報から自身の構成管理情報データベースを基に
影響展開を行い影響警報一覧として保持する機能と、警
報受信時に主原因として即座に判定不可能な警報につい
ては、自管理部内の影響判定機能、および他のサブネッ
トワーク管理システムの影響判定機能へ問い合わせを行
う機能と、影響判定処理においては、影響警報一覧に存
在する警報に関して問い合わせがあった場合に、問い合
わせ元システムに影響警報応答を返す機能と、主原因判
定機能は影響判定機能からの応答を待ち、応答が無い場
合に、主原因警報と判定して上位システムに転送する機
能とを各サブネットワーク管理システムに持たせること
により統合の主原因判定可能なネットワーク監視制御シ
ステムを実現する。
[0009] The network monitoring and control system of the present invention proposes a method of determining a main cause in cooperation between sub-network management systems. In the sub-network management system, a function to notify an upper-level system of an alarm that is obvious as a main cause of a device failure or the like at the time of receiving an alarm, and at the same time hold the same as an occurring main cause alarm, and to store its own configuration management information database from the occurring main cause alarm. A function that deploys the impact on the basis and stores it as a list of impact alerts, and an alert that cannot be immediately judged as the main cause when an alert is received, an impact judgment function in its own management unit, and an impact judgment function of other subnetwork management systems In the impact determination process, the function to return an impact alarm response to the inquiring system when an inquiry is made regarding an alarm in the impact alarm list, and the main cause determination function A function to wait for a response and, if there is no response, determine that it is the main cause alarm and transfer it to the host system Realizing the main cause determinable network monitoring control system integration by providing each sub-network management system.

【0010】上記により、本発明の方式では、上位シス
テム(NMS)での影響展開情報テーブルが不要とな
る。
As described above, in the method of the present invention, the influence development information table in the upper system (NMS) becomes unnecessary.

【0011】[0011]

【発明の実施の形態】本発明の実施の形態について図面
を参照して詳細に説明する。
Embodiments of the present invention will be described in detail with reference to the drawings.

【0012】図1は本発明のネットワーク監視制御シス
テムの一実施の形態のブロック図で、主原因判定機能の
動作系統を示す図である。
FIG. 1 is a block diagram of an embodiment of a network monitoring and control system according to the present invention, showing an operation system of a main cause determining function.

【0013】ネットワーク管理システム(以下NMSと
称す)100は複数のサブネットワーク管理システム
(以下SB−NMSと称す)201、202を収容す
る。各サブネットワーク管理システムにおいて、主原因
判定部23、および影響判定部21を持つ構成とするこ
とにより、統合主原因判定可能なネットワーク監視制御
システムを実現する。
A network management system (hereinafter, referred to as NMS) 100 accommodates a plurality of sub-network management systems (hereinafter, referred to as SB-NMSs) 201, 202. In each of the sub-network management systems, a network monitoring control system capable of integrated main cause determination is realized by having a configuration having the main cause determination unit 23 and the influence determination unit 21.

【0014】SB−NMS201の管理下の、ネットワ
ークA内に装置31乃至34を有し、SB−NMS20
2の管理下のネットワークB内には装置35乃至37を
有する。
The network A has devices 31 to 34 under the control of the SB-NMS 201, and the SB-NMS 20
In the network B under the management of No. 2, devices 35 to 37 are provided.

【0015】ネットワークAの装置32に障害が発生す
るとSB−NMS201ないの警報受信部24を受信
し、主原因判定部23がこれを判定し、主原因警報と認
めると除王位通知部22を介してNMS100の警報受
信部14に報告し、これと同時に影響判定部21に発生
中主原因警報を転送する。影響判定部21は該転送によ
り発生中主原因警報一覧3に記録し、かつ構成管理デー
タベース5に記録し、さらに、該発生中種原因警報の影
響により障害状態になる影響警報装置を選出する影響展
開してそれらの装置を記録した影響展開一覧表6を作成
する影響展開部4と、影響判定部の送信受信を扱う影響
判定/応答部7を有する。
When a failure occurs in the device 32 of the network A, the SB-NMS 201 receives an alarm receiving unit 24, and the main cause determining unit 23 determines this. Then, the alarm is reported to the alarm receiving unit 14 of the NMS 100, and at the same time, the occurring main cause alarm is transferred to the influence determining unit 21. The influence determination unit 21 records the generated main cause alarm list 3 by the transfer and records it in the configuration management database 5, and further selects an influence alarm device that is in a failure state due to the effect of the occurring type cause alarm. It has an impact deployment unit 4 that creates an impact deployment table 6 that develops and records those devices, and an impact determination / response unit 7 that handles transmission and reception of the impact determination unit.

【0016】主原因判定部23は警報受信部24からの
主原因警報を受信し、上位通信部22判定不明のとき、
影響判定部21へ転送する受信警報分類部1と、不明時
棚おSB−NMSへ紹介するときの待ち合わせ時間管理
をする影響判定問い合わせ部2とからなる。
The main cause judging section 23 receives the main cause alarm from the alarm receiving section 24.
It comprises a reception alarm classifying unit 1 for transferring to the influence judging unit 21 and an effect judging inquiry unit 2 for managing a waiting time when introducing to the shelf-unknown SB-NMS.

【0017】主原因判定部23、および影響判定部21
の動作について詳細を、SB−NMSでの影響展開部4
を示す図2および図3(a)、(b)を参照して説明す
る。
The main cause determination unit 23 and the influence determination unit 21
The details of the operation of the above are described in the influence development unit 4 in the SB-NMS.
2 and FIGS. 3 (a) and 3 (b).

【0018】まず、サブネットワーク管理システム内の
主原因判定部23が警報受信部24を介して所管するサ
ブネットワーク内の装置からの警報を受信すると、受信
警報分類部1(図2)において、装置故障等の主原因と
して自ネットワーク内発生主原因警報であるかどうかを
判定する(ステップ51)。自管内の発生主原因警報と
して明らかな警報を上位通知部22を介して上位システ
ム100に通知すると同時に、影響判定部21内に保持
されている発生中主原因警報一覧3に記録してこれを更
新する(ステップ52)。主原因判定部23が主原因と
して即座に判定不可能な警報を受信した場合については
(ステップ51)、自管理部および障害装置の相手方の
サブネットワーク管理システム内の影響判定部21へ問
い合わせを行い(ステップ53)、タイマ監視による影
響判定問い合わせ部2による応答待ち状態に入る(ステ
ップ54)。影響判定部21においては、発生中主原因
警報一覧3および構成管理データベース5の情報から影
響展開を行い、自管理サブネットワーク内の場合、保持
している発生中影響展開警報一覧6を更新する(ステッ
プ55)。
First, when the main cause determination unit 23 in the subnetwork management system receives an alarm from a device in the jurisdiction subnetwork via the alarm reception unit 24, the reception alarm classification unit 1 (FIG. 2) It is determined whether or not the main cause of the failure is a main cause alarm in the own network (step 51). At the same time, the upper-level notification unit 22 notifies the higher-level system 100 of a clear alarm as the main cause alarm in the own jurisdiction, and simultaneously records the alarm in the occurring main-cause alarm list 3 held in the influence determination unit 21 and records this. Update (step 52). When the main cause determination unit 23 receives an alarm that cannot be immediately determined as the main cause (step 51), the main cause determination unit 23 inquires the self-management unit and the influence determination unit 21 in the sub-network management system of the partner of the faulty device. (Step 53), and enters a state of waiting for a response from the influence determination inquiry unit 2 by timer monitoring (Step 54). The influence determination unit 21 performs the effect development from the occurring main cause alarm list 3 and the information in the configuration management database 5, and updates the stored occurring effect development alarm list 6 that is stored in the own management subnetwork ( Step 55).

【0019】また、他のSB−NWSの主原因判定部2
3から問い合わせされると(ステップ61)、当該警報
について、発生中影響展開警報一覧6を点検し(ステッ
プ62)、発生中影響展開一覧6に存在する場合、問い
合わせ元の主原因判定部23に影響判定/応答部7によ
り自管理システム所属の影響警報であることを判定結果
として通知し(ステップ64)、また、一覧に存在しな
い場合、主原因判定部23への応答を返さない(ステッ
プ65)。
Further, another SB-NWS main cause determination unit 2
3 (step 61), the generated effect development alarm list 6 is checked for the alarm (step 62), and if the alarm is present in the occurring effect development list 6, the main cause determination unit 23 of the inquiry source is checked. The effect judgment / response unit 7 notifies the result of the judgment that the alarm belongs to the self-management system as a result of the judgment (step 64). If the alarm is not present in the list, no response is returned to the main cause judgment unit 23 (step 65). ).

【0020】主原因判定部23の応答待ち状態について
影響判定問い合わせ部2のタイムアウトを検出した場合
(ステップ56)、当該警報が自管理部所属の主原因警
報として上位通知部22に転送すると、ともに影響判定
部21内に保持されている発生中主原因警報一覧3を更
新する(ステップ52,53)。タイムアウトせずに影
響警報である判定結果を受信した場合、自管理部所属の
障害警報ではないとみなして該当警報を廃棄し上位通知
機能への転送は行わない(ステップ57)。
When a timeout of the influence determination inquiry unit 2 is detected in the response waiting state of the main cause determination unit 23 (step 56), the alarm is transferred to the higher-level notification unit 22 as a main cause alarm belonging to the own management unit. The occurrence main cause alarm list 3 held in the influence determination unit 21 is updated (steps 52 and 53). If the determination result that is the influence alarm is received without time-out, the alarm is regarded as not the failure alarm belonging to the own management unit, the corresponding alarm is discarded, and the transfer to the higher-level notification function is not performed (step 57).

【0021】本発明の方式では、主原因判定を各サブネ
ットワーク管理システムの連携により実現することによ
り、上位システムでの影響展開情報テーブルが不要とな
る。
In the method of the present invention, the main cause determination is realized by the cooperation of the respective sub-network management systems, so that the influence development information table in the upper system becomes unnecessary.

【0022】[0022]

【発明の効果】以上説明したように、本発明はサブネッ
トワーク管理部段階で、障害警報の主原因影響判定が行
われ、該障害の影響展開も記録更新された上でネットワ
ーク管5理部に報告されるので、ネットワーク管理部で
は主原因判定および影響判定の必要性がなくなり、処理
の迅速化が図られる効果がある。
As described above, according to the present invention, the main cause and effect determination of the fault alarm is performed at the sub-network management unit stage, and the effect development of the fault is recorded and updated, and then the network management unit 5 performs the determination. Since this is reported, the network management unit eliminates the need for the main cause determination and the impact determination, and has the effect of speeding up the processing.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明のネットワーク監視制御方法が適用され
たシステムの一実施の形態のブロック図である。
FIG. 1 is a block diagram of an embodiment of a system to which a network monitoring control method of the present invention is applied.

【図2】図1に示す影響判定部22と主原因判定部23
の詳細ブロック図である。
FIG. 2 is a diagram illustrating an influence determining unit 22 and a main cause determining unit 23 illustrated in FIG. 1;
It is a detailed block diagram of.

【図3】(a)は問い合わせサブネットワーク管理シス
テムの影響判定部21のフローチャート、(b)は問い
合わせを受けた他のサブネットワーク管理システムの影
響判定部21のフローチャートである。
3A is a flowchart of an influence determination unit 21 of an inquiry sub-network management system, and FIG. 3B is a flowchart of an influence determination unit 21 of another sub-network management system that has received an inquiry.

【図4】従来のネットワーク監視制御システムの一例の
ブロックっ図である。
FIG. 4 is a block diagram of an example of a conventional network monitoring and control system.

【符号の説明】[Explanation of symbols]

1 受信警報分類部 2 影響判定問い合わせ部 3 発生中影響展開警報一覧 4 影響展開部 5 構成管理データンベース 6 影響警報一覧表 7 影響判定/応答部 21 影響判定部 22 上位通知部 23 主原因判定部 24 警報受信部 25 構成管理データベース 32〜37 装置 100 NMS 201、202 BS−NMS DESCRIPTION OF REFERENCE NUMERALS 1 Received alarm classification unit 2 Impact determination inquiry unit 3 Influence deployment alarm list during occurrence 4 Impact deployment unit 5 Configuration management database 6 Impact alert list 7 Impact determination / response unit 21 Impact determination unit 22 Upper notification unit 23 Main cause determination Unit 24 alarm receiving unit 25 configuration management database 32 to 37 device 100 NMS 201, 202 BS-NMS

───────────────────────────────────────────────────── フロントページの続き (51)Int.Cl.6 識別記号 FI H04M 3/00 ──────────────────────────────────────────────────の Continued on the front page (51) Int.Cl. 6 Identification code FI H04M 3/00

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 複数のサブネットワーク管理システムお
よびそれらを統合するネットワーク管理システムから構
成される統合ネットワーク管理システムにおけるネット
ワーク監視制御方法において、 サブネットワーク管理システムが、自ネットワーク内の
装置に発生した障害による警報を受信すると、装置故障
を含む障害の主原因が明らかな障害の警報として、上位
システムに通知すると同時に、発生中主原因警報として
保持するステップと、 発生中主原因警報から、前記発生中主原因警報の影響を
受けて障害状態になる装置を選出する影響展開の記録を
行い、影響警報一覧として保持するステップと、警報受
信時に主原因として即座に判定不可能な警報について
は、他のサブネットワーク管理システムに問い合わせを
行うステップと、 サブネットワーク管理システムから、発生中障害が自ネ
ットワーク管内の装置の主原因障害として保持されてい
るかどうかどうかの問い合わせがあった場合、自管理シ
ステムに発生中主原因警報として保持されている場合に
のみ、問い合わせ元システムに応答を返すステップと、 他のネットワーク管理システムの影響判定機能からの応
答を待つ場合、応答が無い場合に、主原因警報と判定し
て上位システムに転送し、自管理システム内の発生中主
原因警報として保持するステップとを有することを特徴
とするネットワーク監視制御方法。
1. A network monitoring and control method in an integrated network management system including a plurality of sub-network management systems and a network management system that integrates the plurality of sub-network management systems. Receiving an alarm, notifying the host system as an alarm of a failure whose main cause of the failure including the device failure is obvious, and simultaneously holding the alarm as an occurring main cause alarm; and A step of recording the effect development for selecting a device that becomes a faulty state due to the influence of the cause alarm and maintaining it as a list of the effect alarms. Querying the network management system; If the network management system inquires whether the fault that is occurring is held as the main cause fault of the device in the own network, only when the self-management system holds the fault as the main cause alarm, Returning a response to the inquiring system, and waiting for a response from the impact determination function of another network management system.If there is no response, it is determined to be the main cause alarm and transferred to the higher-level system. Holding the alarm as a main cause alarm during occurrence.
【請求項2】 前記他のサブネットワーク管理システム
の影響判定機能からの応答待ち状態が、予め設定された
時間を限度とするようにタイマーにより時間管理を受け
る請求項1記載のネットワーク監視制御方法。
2. The network monitoring and control method according to claim 1, wherein the response waiting state from the influence determination function of said another sub-network management system is time-managed by a timer so as to limit a preset time.
【請求項3】 前記他のサブネットワーク管理システム
に問い合わせるステップが前記影響警報一覧の自ネット
ワーク内の該当装置に最も近い装置を有する他のサブネ
ットワーク管理システムに問い合わせることを含む請求
項1または2記載のネットワーク監視制御方法。
3. The method according to claim 1, wherein the step of querying the other sub-network management system includes querying another sub-network management system having a device closest to the corresponding device in the own network in the impact alert list. Network monitoring control method.
【請求項4】 複数のサブネットワーク管理システムお
よびそれらを統合するネットワーク管理システムから構
成される統合ネットワーク管理システムにおけるネット
ワーク監視制御システムにおいて、 サブネットワーク管理システムが、警報受信時に、装置
故障等の主原因として明らかな警報を、上位システムに
通知すると同時に、発生中主原因警報一覧表に発生中主
原因警報として保持する手段と、 発生中主原因警報から自装置の構成管理情報データベー
スを基に主原因障害の影響を受けて障害状態となる装置
を選出する影響装置の展開を行い影響警報一覧として保
持する手段と、 警報受信時に主原因として即座に判定不可能な警報につ
いては、自装置の影響判定手段および他のサブネットワ
ーク管理システムの影響判定手段へ問い合わせを行う手
段と、 他のサブネットワーク管理システムから、発生中障害が
自サブネットワーク管内の装置の主原因障害として自装
置の影響警報一覧に存在するかどうかの問い合わせがあ
った場合、自装置の影響警報一覧に記載がある場合にの
み、問い合わせ元システムに応答を返す手段と、 他のネットワーク管理システムの影響判定機能からの応
答を待ち、応答が無い場合に、主原因警報と判定して上
位システムに転送し、自装置の発生中主原因警報として
保持する手段とを有することを特徴とするネットワーク
監視制御システム。
4. A network monitoring and control system in an integrated network management system comprising a plurality of sub-network management systems and a network management system that integrates the plurality of sub-network management systems. Means for notifying the upper-level system of the obvious alarm as well as holding it as an occurring main cause alarm in the occurring main cause alarm list, and the main cause based on the configuration management information database of the own device from the occurring main cause alarm Select a device that will be in a faulted state due to the effect of the fault.Deploy the affected device and maintain it as a list of affected alarms.For alarms that cannot be immediately determined as the main cause when receiving an alarm, determine the impact of the own device. The means and means of determining the impact of other subnetwork management systems From the other sub-network management system, if there is an inquiry as to whether or not the occurring fault is in the list of the effect alarms of its own device as the main cause failure of the device in its own sub-network, A means to return a response to the inquiring system only when it is listed in the impact alarm list, and a response from the impact determination function of another network management system. Means for transferring the information to a system and holding the alarm as a main cause alarm during the occurrence of the own apparatus.
【請求項5】 前記他のサブネットワーク管理システム
の影響判定機能からの応答待ち状態が、予め設定された
時間を限度とするようにタイマーにより時間管理を受け
る請求項4記載のネットワーク監視制御システム。
5. The network monitoring and control system according to claim 4, wherein a response waiting state from the influence determination function of said another sub-network management system is time-managed by a timer so as to limit a preset time.
【請求項6】 前記他のサブネットワーク管理システム
に問い合わせる手段が、前記影響警報一覧の自管理ネッ
トワーク内の該当装置に最も近い装置を有する他のサブ
ネットワーク管理システムに問い合わせることを含む請
求項1または2記載のネットワーク監視制御システム。
6. The apparatus according to claim 1, wherein the means for inquiring of the other subnetwork management system includes inquiring of another subnetwork management system having a device closest to a corresponding device in the self-management network of the impact alarm list. 3. The network monitoring and control system according to 2.
JP00306898A 1998-01-09 1998-01-09 Network monitoring control method and system Expired - Fee Related JP3305248B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP00306898A JP3305248B2 (en) 1998-01-09 1998-01-09 Network monitoring control method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP00306898A JP3305248B2 (en) 1998-01-09 1998-01-09 Network monitoring control method and system

Publications (2)

Publication Number Publication Date
JPH11205318A true JPH11205318A (en) 1999-07-30
JP3305248B2 JP3305248B2 (en) 2002-07-22

Family

ID=11547025

Family Applications (1)

Application Number Title Priority Date Filing Date
JP00306898A Expired - Fee Related JP3305248B2 (en) 1998-01-09 1998-01-09 Network monitoring control method and system

Country Status (1)

Country Link
JP (1) JP3305248B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004289824A (en) * 2003-03-17 2004-10-14 Tyco Telecommunications (Us) Inc System and method for fault diagnosis using distributed alarm correlation
US7564778B2 (en) 2003-12-09 2009-07-21 Fujitsu Limited Method of and control node for detecting failure
JP2010226306A (en) * 2009-03-23 2010-10-07 Kddi Corp Network management system and program

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004289824A (en) * 2003-03-17 2004-10-14 Tyco Telecommunications (Us) Inc System and method for fault diagnosis using distributed alarm correlation
JP4554964B2 (en) * 2003-03-17 2010-09-29 タイコ エレクトロニクス サブシー コミュニケーションズ エルエルシー System and method for fault diagnosis using distributed alarm correlation
US7564778B2 (en) 2003-12-09 2009-07-21 Fujitsu Limited Method of and control node for detecting failure
JP2010226306A (en) * 2009-03-23 2010-10-07 Kddi Corp Network management system and program

Also Published As

Publication number Publication date
JP3305248B2 (en) 2002-07-22

Similar Documents

Publication Publication Date Title
US6859889B2 (en) Backup system and method for distributed systems
CN101032123B (en) Method and apparatus for determining impact of faults on network service
CN100452759C (en) Ip redundancy with improved failover notification
CN101099398B (en) Method and devices for matching data between a manager and an agent in a management network
CN106878096B (en) VNF state detection notification method, device and system
JP3305248B2 (en) Network monitoring control method and system
JP4673532B2 (en) Comprehensive alignment process in a multi-manager environment
CN113824595B (en) Link switching control method and device and gateway equipment
WO1997050209A1 (en) A method for fault control of a telecommunications network and a telecommunications system
JP2004064395A (en) Device and method of channel switching, and its program
JPH04252533A (en) Fault notice system
KR100547872B1 (en) An apparatus and method for detecting hard-ware alarm with in case of hard-ware alarm device fault state in mobile communication system
JP2003008523A (en) Method and system for monitoring facility
JP2010045624A (en) Maintenance system
JP2002244828A (en) Device condition control system
JP2000010949A (en) Relay type decentralized health check control system and method
JP2002026948A (en) Network system
US7197551B2 (en) Method and system for implementing supervision in a telecommunication system
KR100959895B1 (en) System and method for controlling of alarm monitoring map
KR100235570B1 (en) The method of the cluster management for the cluster management master system of the parallel ticom
JP2546165B2 (en) Online system and its line selection method
JP2004258806A (en) Distributed control system
KR19980066622A (en) Remote system failure management device and method using radio pager
JPH04332227A (en) Failure information transmission destination control system
CN115174356A (en) Cluster alarm reporting method, device, equipment and medium

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees