JPH11131074A - Operation of coke oven - Google Patents

Operation of coke oven

Info

Publication number
JPH11131074A
JPH11131074A JP30058097A JP30058097A JPH11131074A JP H11131074 A JPH11131074 A JP H11131074A JP 30058097 A JP30058097 A JP 30058097A JP 30058097 A JP30058097 A JP 30058097A JP H11131074 A JPH11131074 A JP H11131074A
Authority
JP
Japan
Prior art keywords
carbonization
coal
time
chamber
coke oven
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP30058097A
Other languages
Japanese (ja)
Inventor
Hidetaka Sugibe
英孝 杉辺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
Original Assignee
Kawasaki Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawasaki Steel Corp filed Critical Kawasaki Steel Corp
Priority to JP30058097A priority Critical patent/JPH11131074A/en
Publication of JPH11131074A publication Critical patent/JPH11131074A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide a method for operating a coke oven to equalize the carbonization times all over the coke oven and to prevent improper carbonization, by reducing within a definite range a quantity of coal to be charged to a carbonization chamber where an operating cycle time (from the initiation of heatup to the completion of generating gases) was behind the set point. SOLUTION: The method comprises reducing a quantity of coal to be charged to a carbonization chamber where an operating cycle time (i.e., time required from the initiation of heatup to the completion of generating gases) was Δt (h.) behind the set operating cycle time ts (h.) by a quantity of at least (δt/ts )×100 (%) and that within a quantity of <=20% of the normal quantity of coal to be charged.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、コークス炉の操業
方法の改良に関し、特に、炭化不良コークスの押出しを
未然に防止することが可能なコークス炉の操業方法に関
する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an improvement in a method of operating a coke oven, and more particularly to an operation method of a coke oven capable of preventing extrusion of poorly carbonized coke.

【0002】[0002]

【従来の技術】コークス炉には、燃料,空気の供給方
法、蓄熱室の配列、燃焼室等の構造の違いにより種々の
タイプがある。一般に、下部に蓄熱室、上部には交互に
配列した燃焼室と炭化室とを備えて、それぞれ炉長方向
に多数に分割配置されている。その炭化室に粉体状の原
料石炭を装入して、燃料ガスと空気を蓄熱室で予熱した
のち燃焼室で燃焼し、その燃焼熱を隣接の炭化室に伝熱
せしめて室内の石炭を乾留する。炭化室内の石炭は、空
気を遮断して加熱されると温度上昇に伴って水分や吸蔵
CO,CH4 等を放出していき、300℃を越えると石
炭自体の熱分解が始まってガス,化合水やタールが急激
に発生するとともに軟化溶融する。そして500℃近く
になると再び固化して多孔質塊状の半成コークスとな
る。更に温度が上昇して900℃以上になると揮発分の
放出はほぼ終了して高温乾留コークスになる。上記の加
熱開始からガス発生終了迄の所要時間を火落ち時間と称
する。この火落ち時間の経過で、炉内の石炭乾留は終了
する筈であるが、実際には炉蓋の近傍などでは乾留の進
行が部分的に遅れる結果、完全にはコークスになってい
ない。そこで、更に1〜数時間程度の熟成及び均熱化の
時間(置時間と称する)を置いた後、炭化室内から押し
出している。この置時間と前記火落ち時間との合計を炭
化時間といい、これが押し出しサイクルとなる。
2. Description of the Related Art There are various types of coke ovens depending on the method of supplying fuel and air, the arrangement of heat storage chambers, and the structure of combustion chambers and the like. Generally, a lower part is provided with a heat storage chamber, and an upper part is provided with a combustion chamber and a carbonization chamber which are arranged alternately. Powdered raw coal is charged into the coking chamber, the fuel gas and air are preheated in the regenerator, burned in the combustion chamber, and the combustion heat is transferred to the adjacent coking chamber to remove the coal in the room. Carbonize. When the coal in the coking chamber is heated while shutting off the air, it releases moisture, occluded CO, CH 4, etc. as the temperature rises, and when it exceeds 300 ° C., thermal decomposition of the coal itself starts and gas and chemical Water and tar are rapidly generated and soften and melt. Then, when the temperature becomes close to 500 ° C., it solidifies again to form a porous mass semi-coke. When the temperature further rises to 900 ° C. or higher, the release of volatile components is almost complete, and high-temperature carbonized coke is obtained. The time required from the start of the heating to the end of the gas generation is referred to as a burn-out time. The coal carbonization in the furnace should end after the burn-down time, but in fact, the progress of the carbonization near the furnace lid is partially delayed, so that coke is not completely formed. Therefore, after an additional time of about 1 to several hours for aging and soaking (referred to as an installation time), the material is extruded from the carbonization chamber. The sum of the placing time and the fire-out time is called a carbonization time, and this is an extrusion cycle.

【0003】適切な火落ち時間を経ずに、乾留が不完全
なままで押し出すと、残存揮発分が空気との接触で不完
全燃焼して煤(黒煙)が放散されるという問題がある。
反対に乾留過多であると過剰にエネルギーが浪費される
ため経済的損失をまねくという問題がある。一般に、所
要の火落ち時間の長短は、石炭自体の性状の他に、各炭
化室の装入密度,昇温速度,最終到達温度等の乾留条件
や、付着カーボン量などの個々の炭化室(窯)の状態等
によっても影響され、炭化室間でバラツキが生じる。
[0003] If the carbonization is extruded in an incomplete state without an appropriate burn-off time, the remaining volatiles are incompletely burned in contact with the air and soot (black smoke) is emitted. .
On the other hand, if the carbonization is excessive, there is a problem that excessive energy is wasted and economic loss is caused. Generally, the length of the required burn-off time depends on the properties of the coal itself, the dry density conditions such as the charging density, heating rate, and final temperature of each carbonization chamber, and the individual carbonization chambers (such as the amount of carbon adhering). It is also affected by the condition of the kiln, etc., causing variations between the carbonization chambers.

【0004】コークス炉の操業のポイントは各窯毎の炭
化時間の均一性の確保にあり、炉の各窯間の火落ち時間
のバラツキ対策が重要とされている。そのためには、各
炭化室における火落ち時間の把握と炉温の把握が必須で
ある。火落ち時間については、実際の操業で炭化処理し
た後に炉を開けて状態を観察し、今回処理にあたり設定
した火落ち時間の適否を確認して、次回の処理に反映さ
せるという方法が採られている。
[0004] The point of operating a coke oven is to ensure the uniformity of the carbonization time for each kiln, and it is important to take measures against variations in the burn-out time between the kilns of the furnace. For that purpose, it is essential to grasp the burn-out time and the furnace temperature in each carbonization chamber. Regarding the burn-out time, a method was adopted in which the furnace was opened after carbonization in the actual operation, the state was observed, the suitability of the burn-off time set for this treatment was confirmed, and this was reflected in the next treatment. I have.

【0005】また、通常の室炉式コークス炉では、乾留
に必要な熱は、燃焼室と炭化室との間に介在する炉壁れ
んがを通して、両側から炭化室内の石炭層に伝達され
る。すなわち、乾留における火落ちは伝熱律速であり、
基本的には当該炉壁の温度で決定される。それゆえ、火
落ち時間を所定値に保つべく、炉内温度を把握して燃焼
室に供給する燃焼ガス量の調整を行う。このため種々の
温度測定方法が提案されている。
[0005] In a normal coke oven coke oven, heat required for carbonization is transferred from both sides to a coal bed in the coking chamber through a furnace wall brick interposed between the combustion chamber and the coking chamber. That is, the fire fall in carbonization is heat transfer rate-limiting,
Basically, it is determined by the temperature of the furnace wall. Therefore, in order to keep the burn-out time at a predetermined value, the furnace temperature is grasped and the amount of combustion gas supplied to the combustion chamber is adjusted. For this reason, various temperature measuring methods have been proposed.

【0006】[0006]

【発明が解決しようとする課題】しかしながら、温度把
握のために数十室もある各炭化室毎に温度センサを設置
すると、莫大な費用を要することになるという未解決の
課題がある。
However, there is an unsolved problem that if a temperature sensor is installed in each of several tens of carbonization chambers for grasping the temperature, an enormous cost will be required.

【0007】また、たとえ火落ち時間や炉温が各炭化室
毎に把握され、炭化不良となる炭化室の分布状態が事前
に検知されたとしても、それら全ての炭化不良の炭化室
からの押し出しを完全に回避することは実際には難し
い。というのは、炭化不良となった炭化室に対しては、
他の炭化室よりも火落ち時間を長くとる(置時間は同一
でよい)ことで十分な乾留状態が得られるのであるが、
その場合、押し出しサイクルが設定値より長くなる結
果、炉全体の計画押し出しサイクルから外れて、いわゆ
る飛び窯となってしまう。この飛び窯が出ると、コーク
ス炉の付帯設備である装炭車,押出機,ガイド車等の移
動が不規則,不連続となる。これにより、次回サイクル
のための炭化室への装炭時に石炭の誤装入をまねき易く
なって生産本数の低下を来すばかりでなく、炉上面に石
炭が飛散して発塵する危険性があるという未解決の課題
がある。
Further, even if the burn-down time and the furnace temperature are grasped for each coking chamber and the distribution state of the coking chambers in which the carbonization is defective is detected in advance, all of the carbonization chambers in which the carbonization is defective are extruded from the coking chamber. It is actually difficult to avoid completely. Because, for the carbonization chamber which became poor carbonization,
By taking a longer burn-down time than the other carbonization chambers (the same setting time is required), a sufficient dry distillation state can be obtained,
In that case, the extrusion cycle becomes longer than the set value, resulting in a so-called flying kiln deviating from the planned extrusion cycle of the entire furnace. When this flying kiln comes out, the movement of the coal-charging truck, the extruder, the guide truck, etc., which are the auxiliary equipment of the coke oven, becomes irregular and discontinuous. This makes it easier to mischarge coal when charging it into the coking chamber for the next cycle, which not only reduces the production volume, but also reduces the risk of coal scattering and dusting on the furnace upper surface. There is an unsolved problem.

【0008】また、炉温や火落ち時間を把握して燃焼ガ
ス量を調整したとしても、コークス炉の熱容量が大きい
ことから応答に時間がかかる。そのため、当該処理サイ
クルにおける調整効果を、処理が終了して押し出された
コークスをみて確認し、その結果を勘案して次回処理サ
イクルで更に調整を実施するというフィードバックサイ
クル処理を数回繰り返すことが必要となり、その間の炭
化不良は避けられないという未解決の課題もある。
[0008] Even if the combustion gas amount is adjusted by grasping the furnace temperature and the burnout time, it takes a long time to respond due to the large heat capacity of the coke oven. Therefore, it is necessary to repeat the feedback cycle process several times, in which the adjustment effect in the processing cycle is checked by checking the coke extruded after the process is completed, and further adjustment is performed in the next processing cycle in consideration of the result. However, there is an unsolved problem that poor carbonization is inevitable.

【0009】本発明は、このような従来のコークス炉に
おける課題を解決するためになされたものであり、火落
ち時間が設定値より遅れた炭化室に対する装炭量を、一
定の範囲内で減量することにより炉全体の炭化時間を均
一化せしめて、以後の炭化不良を未然に防止するコーク
ス炉の操業方法を提供することを目的とす。
SUMMARY OF THE INVENTION The present invention has been made to solve such a problem in a conventional coke oven, and reduces the amount of coal charged to a coking chamber whose burn-out time is later than a set value within a certain range. Accordingly, it is an object of the present invention to provide a method of operating a coke oven in which the carbonization time of the entire furnace is made uniform and a subsequent carbonization failure is prevented.

【0010】[0010]

【課題を解決するための手段】上記の目的を達成するた
めに、本発明に係るコークス炉の操業方法にあっては、
通常の装炭量で乾留したときに、設定火落ち時間t
S (hr)に対してΔt(hr)だけ火落ちが遅れた炭
化室への装炭量を、前記通常の装炭量よりも(Δt/t
S )×100(%)以上減じることを特徴とする。
In order to achieve the above object, a method of operating a coke oven according to the present invention comprises:
When the carbonization is carried out with a normal coal charge, the set fire time t
The amount of coal charged to the coking chamber where the fire was delayed by Δt (hr) with respect to S (hr) is set to (Δt / t)
S ) × 100 (%) or more.

【0011】ここで、請求項1記載のコークス炉の操業
方法において、前記火落ちが遅れた炭化室への装炭量の
減少程度は、通常の装炭量の20%減を上限とするのが
よい。20%を越えて装炭量を減量しても、もはや火落
ち時間の短縮率は飽和してしまい効果が認められないた
めである。
In the method for operating a coke oven according to the first aspect of the present invention, the degree of decrease in the amount of coal charged into the coking chamber where the fire has been delayed is limited to a maximum of 20% of the normal amount of coal charged. Is good. This is because even if the amount of coal is reduced by more than 20%, the shortening rate of the burn-down time is saturated and the effect is not recognized.

【0012】[0012]

【発明の実施の形態】以下、本発明の実施の一形態を図
面を参照して説明する。図1〜図3は、本発明を好適に
適用できるコークス炉の一例を示す概要図で、図1は斜
視図、図2はそのII−II断面図、図3は図2のIII − I
II断面図である。図示のものは、カールスチル式コーク
ス炉であって、炉体下部に多数の蓄熱室1が隣接させて
設置され、その各蓄熱室の上部に燃焼室2と炭化室3と
が交互にそれぞれ70〜100室程、炉長方向に配列さ
れている。蓄熱室1は蓄熱れんが4により、燃焼室2は
整流板(ダクト)5により、いずれも二分割構造とされ
ており、両室の間は炉壁れんが6で仕切られている。燃
料ガス及び空気は蓄熱室1で予熱された後、整流板5に
設けた開口5aから6段に分かれて燃焼室2に供給され
て燃焼する。そのため上下の温度差は少ない。燃焼後の
ガスは、隣接する蓄熱室1を通り蓄熱れんが4で熱回収
された後、煙道7を経て排出される。燃焼室2内の燃焼
熱は炉壁れんが6を通して炭化室3内の石炭層に伝達さ
れ、これを加熱する。蓄熱れんが4や整流板5により各
燃焼室2の加熱はできるだけ均一に行われるようになっ
ているが、実際は炉蓋9,10のある端の方が昇温しに
くく、例えば炭化室3の中央部が1000℃のとき両端
部800℃程度になる。
An embodiment of the present invention will be described below with reference to the drawings. 1 to 3 are schematic views showing an example of a coke oven to which the present invention can be suitably applied. FIG. 1 is a perspective view, FIG. 2 is a sectional view taken along line II-II, and FIG.
It is II sectional drawing. The illustrated one is a Carl still coke oven, in which a number of heat storage chambers 1 are installed adjacent to each other at the lower part of the furnace body, and a combustion chamber 2 and a carbonization chamber 3 are alternately provided above each heat storage chamber. About 100 chambers are arranged in the furnace length direction. The heat storage chamber 1 is divided into two parts by a heat storage brick 4, and the combustion chamber 2 is divided into two parts by a flow straightening plate (duct) 5. After being preheated in the heat storage chamber 1, the fuel gas and the air are supplied to the combustion chamber 2 from the opening 5 a provided in the flow straightening plate 5 and burned in six stages. Therefore, the difference between the upper and lower temperatures is small. The gas after combustion passes through the adjacent heat storage chamber 1 and is recovered by the heat storage brick 4 and then discharged through the flue gas 7. The heat of combustion in the combustion chamber 2 is transferred to the coal bed in the coking chamber 3 through the furnace wall brick 6 and heats it. The heat storage brick 4 and the rectifying plate 5 heat the combustion chambers 2 as uniformly as possible. However, in practice, the ends of the furnace lids 9 and 10 are less likely to heat up. When the temperature is 1000 ° C., both ends are about 800 ° C.

【0013】このコークス炉の付帯設備として、石炭塔
12から移載した石炭を各炭化室3内に装入口3aから
投入する装炭車13、炭化室3内のコークスを外に押し
出す押出機14、押し出されたコークスを受け止めて下
方に落とすコークガイド車15、そのコークガイド車1
5から落とされた赤熱コークスを廃熱回収用の消化装置
に搬送する消化電車16等を備えている。
[0013] As ancillary equipment of the coke oven, coal loaded from coal tower 12 is fed into each coking chamber 3 through charging inlet 3a, coal loading truck 13; extruder 14 for extruding coke in coking chamber 3 to the outside; A coke guide vehicle 15 that receives the extruded coke and drops the coke, and the coke guide vehicle 1
A digestion train 16 for transporting the red hot coke dropped from 5 to a digester for waste heat recovery is provided.

【0014】上記コークス炉の操業にあたり、初めは各
炭化室3内に通常の操業における装炭量で石炭を装入す
る。その量は各炭化室3とも同一量である。先に述べた
火落ち時間に及ぼす各種要因を勘案して、その装炭量に
対応する火落ち時間tS (hr)を設定し、これに1〜
2時間の置時間を加えた炭化時間をもって押し出しサイ
クルとする。そして、燃焼室2に燃料ガスを予め設定し
た所定の流量で供給して燃焼させ、炭化室3内の石炭層
を加熱する。押し出しサイクル時間が経過したら加熱を
止めて、炉蓋9,10を開く。このとき、未だ乾留不十
分であった炭化室3のコークスは残存揮発分が空気との
接触で不完全燃焼して煤を出すので(発塵)見分けるこ
とができ、その炭化室3は炭化不良と判断される。
In the operation of the coke oven, coal is initially charged into each coking chamber 3 with the amount of coal charged in a normal operation. The amount is the same for each carbonization chamber 3. Taking into account the various factors affecting the burn-down time described above, a burn-down time t S (hr) corresponding to the amount of coal charged is set.
The extrusion cycle is defined as the carbonization time obtained by adding the two-hour storage time. Then, the fuel gas is supplied to the combustion chamber 2 at a predetermined flow rate and burned, and the coal layer in the carbonization chamber 3 is heated. When the extrusion cycle time has elapsed, the heating is stopped and the furnace lids 9 and 10 are opened. At this time, the coke in the carbonization chamber 3 which was still insufficiently carbonized can be discriminated because the remaining volatile components incompletely burn in contact with air to emit soot (dust generation). Is determined.

【0015】炭化不良の炭化室3は炉蓋9,10閉じて
再加熱する。発塵が認められなくなるまで加熱を行い、
その再加熱所要時間Δt(hr)を求めれば、その分が
火落ちの遅れた時間であり、換言すれば短縮すべき火落
ち時間である。次いで、コークス炉1の全炭化室3内の
コークスは押出機14で炉外へ排出する。この押し出し
作業は、押出機14を順次移動させながら繰り返され
る。排出が終われば、次のサイクルの装炭を行う。この
とき、炭化不良と判断された炭化室3への装炭量は減量
する。その減量の程度(装炭量削減率)は、通常の装炭
量で乾留した前回のサイクルにおける設定火落ち時間t
S (hr)に対する火落ち遅れ時間Δt(hr)の割合
(火落ち時間短縮率)と少なくとも同率とする。すなわ
ち、(Δt/tS )×100(%)以上の減量とする。
The carbonization chamber 3 having poor carbonization is heated again by closing the furnace lids 9 and 10. Heat until no dust is observed,
If the required reheating time Δt (hr) is obtained, the time is the time required for the fire to be delayed, in other words, the time required for the fire to be reduced. Next, the coke in the coking chamber 3 of the coke oven 1 is discharged out of the oven by the extruder 14. This extrusion operation is repeated while sequentially moving the extruder 14. After discharging, coal is charged in the next cycle. At this time, the amount of coal charged to the carbonization chamber 3 determined to be poor in carbonization is reduced. The degree of the weight reduction (coal charge reduction rate) is determined by the set fire time t in the previous cycle in which the carbonization was performed using the normal coal charge.
At least the same ratio as the ratio of the burnout delay time Δt (hr) to S (hr) (the burnout time reduction ratio). That is, the (Δt / t S) × 100 (%) or more weight loss.

【0016】この装炭量の減量により、前回サイクルで
は炭化不良となった炭化室3については、単位石炭当た
りの受熱量が多くなり、火落ち時間が前回より短縮され
ると共に乾留の遅れた部分のコークス化が促進される。
そのため、押出計画を乱すことなく、炭化不良炭化室の
コークス押し出しを確実に防止することができる。
Due to the reduction in the amount of coal charged, the amount of heat received per unit coal increases in the carbonization chamber 3 in which the carbonization was poor in the previous cycle, the burn-out time was shortened from the previous time, and the portion where carbonization was delayed was reduced. Coke is promoted.
For this reason, it is possible to reliably prevent coke extrusion in the poor carbonization chamber without disturbing the extrusion plan.

【0017】但し、図4に示した実炉での試験結果によ
れば、装炭量削減の火落ち時間短縮効果は必ずしも直線
的ではない。すなわち、装炭量が20%以下のうちは火
落ち時間短縮率との関係は略直線的であるが、装炭量が
20%を越えると火落ち時間短縮率が飽和してしまい、
得策とはいえなくなる。それゆえ、本発明における装炭
量削減率の上限は20%とするのがよい。
However, according to the test results in the actual furnace shown in FIG. 4, the effect of reducing the amount of coal charged to shorten the burnout time is not always linear. That is, the relationship with the burn-down time reduction rate is substantially linear when the coal loading is 20% or less, but the burn-down time reduction rate is saturated when the coal loading exceeds 20%,
It's not a good idea. Therefore, the upper limit of the coal loading reduction rate in the present invention is preferably set to 20%.

【0018】また、装炭量削減率の値に対して対応する
火落ち時間短縮率の値の方が小さくなっている。例え
ば、装炭量削減率20%,10%,5%に対して火落ち
時間短縮率はそれぞれ13%,7%、3.5%であり、
火落ち時間短縮率のおよそ1.5倍が装炭量削減率にな
っている。したがって、目標とする火落ち時間短縮率Δ
t/tS を達成するには、その1.5倍の数値の装炭量
削減率とするのが好ましい。
Further, the value of the burnout time reduction rate corresponding to the value of the coal charge reduction rate is smaller. For example, the reduction rate of fire time is 13%, 7%, and 3.5%, respectively, while the reduction rate of coal quantity is 20%, 10%, and 5%.
Approximately 1.5 times the reduction rate of fire time is the reduction rate of coal charge. Therefore, the target burnout time reduction rate Δ
In order to achieve t / t S , it is preferable to set the coal reduction rate to a value that is 1.5 times the value.

【0019】かくして、本発明にあっては、コークス炉
の多数の炭化室のうち炭化不良傾向となった炭化室につ
いては、予め装炭量を減量して炭化不良の発生する危険
性を排除したうえで操業を継続する。これにより、その
間に燃焼ガス量の調整を着実に実行する余地ができ、当
該ガス量調整の完了後は通常の装炭量への復帰がなされ
る。
Thus, according to the present invention, the risk of carbonization failure is eliminated by reducing the amount of carbonization in advance in the carbonization chambers which tend to be carbonized out of a large number of carbonization chambers of the coke oven. To continue operations. As a result, there is room for steady adjustment of the combustion gas amount during that time, and after the completion of the gas amount adjustment, the normal coal charge amount is returned.

【0020】(実施例)以下に、実施例により本発明の
効果を説明する。カールスチル式の高さ6m級の室炉を
用いて、1室(窯)あたりの通常装炭量30.5ドライ
トン/窯にて実験した。1日当たり稼働率は130%
(押し出しサイクル=火落ち時間+置時間=24hr/
130×100=18.5hr)に設定した。内訳は、
火落ち時間16.5hr、置時間2hrである。この条
件で処理した時に設定火落ち時間16.5hrを越える
炭化室は、全102室中の25室あり、表1に示すよう
に、目視判定でそのうちの約半数に押し出し時の発塵が
認められた。
(Examples) The effects of the present invention will be described below with reference to examples. An experiment was conducted with a normal furnace loading of 30.5 drytons / kiln per room (kiln) using a carstill still type furnace having a height of 6 m. 130% daily occupancy rate
(Extrusion cycle = fire fall time + placement time = 24 hr /
130 × 100 = 18.5 hr). The breakdown is
The burn-out time was 16.5 hr and the placing time was 2 hr. When treated under these conditions, there were 25 carbonized chambers that exceeded the set burn-out time of 16.5 hr, out of a total of 102 chambers, and as shown in Table 1, about half of them were found to have generated dust during extrusion by visual judgment. Was done.

【0021】[0021]

【表1】 [Table 1]

【0022】そこで、これらの発塵炭化室に対する装炭
量を次の通り減量した。 設定火落ち時間tS :16.5hr 火落ち遅れ時間Δt: 0.8hr よって 火落ち時間短縮率Δt/tS ×100=4.8% この火落ち時間短縮率の1.5倍を装炭削減率とする。
Therefore, the amount of coal charged to these dust generating chambers was reduced as follows. Set fire time t S : 16.5 hr Fire time delay time Δt: 0.8 hr Therefore, fire time shortening rate Δt / t S × 100 = 4.8% We assume reduction rate.

【0023】このように発塵炭化室の装炭量を削減して
再度コークス炉の操業を行ったところ、火落ち時間が設
定値16.5hrを越える炭化室は半減した。特に、1
hr以上越えるものは皆無であった。これにより押し出
し時の発塵はゼロとなり当初の押し出し計画を乱すこと
なく操業することができた。
When the operation of the coke oven was performed again while reducing the amount of coal charged in the dusting carbonization chamber, the number of carbonization chambers in which the burn-out time exceeded the set value of 16.5 hr was reduced by half. In particular, 1
Nothing exceeded hr or more. As a result, dust generation during extrusion was reduced to zero, and the operation could be performed without disturbing the original extrusion plan.

【0024】一方、比較例として、上記実施例と同一炉
を用い、実施例の終了後すぐに、全炭化室とも通常の装
炭量(30.5ドライトン/窯)に戻して、定法通りの
操業を3日間継続して行った。その後、火落ち時間短縮
率Δt/tS の0.5倍(5割)の装炭量削減率として
発塵炭化室に対する装炭量を減量した。
On the other hand, as a comparative example, the same furnace as in the above example was used. Immediately after the end of the example, the normal coal loading (30.5 dryton / kiln) was returned to the entire coking chamber, and the usual method was followed. The operation was continued for three days. Thereafter, and it reduced the Sosumi amount for dusting coking chamber as Sosumi reduction ratio of 0.5 times the fire fall time saving rate Δt / t S (5 percent).

【0025】その結果、火落ち時間は短縮されたもの
の、設定値16.5hrを越える炭化室は80%程度あ
り、特に、1hr以上越えるものが20%残存した。押
し出し時の発塵も減少はしたが、なお1/4の残存が認
められた。
As a result, although the burnout time was shortened, about 80% of the carbonized chambers exceeded the set value of 16.5 hr, and in particular, 20% of the chambers exceeded 1 hr or more. Although dusting at the time of extrusion was also reduced, 1/4 remaining was still observed.

【0026】[0026]

【発明の効果】以上説明したように、本発明に係るコー
クス炉の操業方法によれば、火落ちが遅れた炭化室への
装炭量を一定の範囲内で減量するため、各炭化室毎に高
価な温度センサを設置することなく炉全体の炭化時間が
均一化できて、飛び窯や炭化不良が未然に防止されると
いう効果を奏する。
As described above, according to the method of operating a coke oven according to the present invention, the amount of coal charged into the coking chamber where the fire has been delayed is reduced within a certain range. Therefore, the carbonization time of the entire furnace can be made uniform without installing an expensive temperature sensor, and the effect of preventing a skipping kiln and poor carbonization can be prevented.

【0027】また、押し出し時の発塵も防止できて環境
保護に貢献できるという効果が得られる。また、押し出
し時に不完全燃焼して放散されていたCガスを回収でき
て、省エネルギーにも効果を発揮する。
Further, it is possible to prevent dust from being generated at the time of pushing out, which contributes to environmental protection. In addition, C gas which has been incompletely burned and exhaled at the time of extrusion can be recovered, which is also effective in energy saving.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明のコークス炉の一例を示す斜視図であ
る。
FIG. 1 is a perspective view showing an example of a coke oven of the present invention.

【図2】図1のII−II断面図である。FIG. 2 is a sectional view taken along line II-II of FIG.

【図3】図2のIII − III断面図である。FIG. 3 is a sectional view taken along line III-III of FIG. 2;

【図4】装炭量削減率と火落ち時間短縮率との関係を示
す図である。
FIG. 4 is a diagram showing a relationship between a coal loading reduction rate and a fire-fall time reduction rate.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 通常の装炭量で乾留したときに、設定火
落ち時間tS (hr)に対してΔt(hr)だけ火落ち
が遅れた炭化室への装炭量を、前記通常の装炭量よりも
少なくとも(Δt/tS )×100(%)減じることを
特徴とするコークス炉の操業方法。
When the carbonization is carried out at a normal amount of coal, the amount of coal to be supplied to the carbonization chamber, which is delayed by Δt (hr) with respect to the set burn-out time t S (hr), is calculated as the normal amount. A method for operating a coke oven, characterized in that at least (Δt / t s ) × 100 (%) is reduced from the amount of coal charged.
【請求項2】 請求項1記載のコークス炉の操業方法に
おいて、前記火落ちが遅れた炭化室への装炭量の減少程
度は、通常の装炭量の20%減を上限とするコークス炉
の操業方法。
2. The coke oven operating method according to claim 1, wherein the degree of decrease in the amount of coal charged into the coking chamber where the fire has been delayed is limited to a maximum of 20% of the normal amount of coal charged. Operating method.
JP30058097A 1997-10-31 1997-10-31 Operation of coke oven Pending JPH11131074A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP30058097A JPH11131074A (en) 1997-10-31 1997-10-31 Operation of coke oven

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP30058097A JPH11131074A (en) 1997-10-31 1997-10-31 Operation of coke oven

Publications (1)

Publication Number Publication Date
JPH11131074A true JPH11131074A (en) 1999-05-18

Family

ID=17886558

Family Applications (1)

Application Number Title Priority Date Filing Date
JP30058097A Pending JPH11131074A (en) 1997-10-31 1997-10-31 Operation of coke oven

Country Status (1)

Country Link
JP (1) JPH11131074A (en)

Cited By (33)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008224462A (en) * 2007-03-13 2008-09-25 Taiheiyo Cement Corp Organic carbon amount measuring method and solid carbon amount measuring method
JP2017529429A (en) * 2014-08-28 2017-10-05 サンコーク テクノロジー アンド ディベロップメント リミテッド ライアビリティ カンパニー Method and system for optimizing coke plant operation and output
US10016714B2 (en) 2012-12-28 2018-07-10 Suncoke Technology And Development Llc Systems and methods for removing mercury from emissions
US10041002B2 (en) 2012-08-17 2018-08-07 Suncoke Technology And Development Llc Coke plant including exhaust gas sharing
US10047295B2 (en) 2012-12-28 2018-08-14 Suncoke Technology And Development Llc Non-perpendicular connections between coke oven uptakes and a hot common tunnel, and associated systems and methods
US10053627B2 (en) 2012-08-29 2018-08-21 Suncoke Technology And Development Llc Method and apparatus for testing coal coking properties
US10323192B2 (en) 2012-12-28 2019-06-18 Suncoke Technology And Development Llc Systems and methods for improving quenched coke recovery
US10526541B2 (en) 2014-06-30 2020-01-07 Suncoke Technology And Development Llc Horizontal heat recovery coke ovens having monolith crowns
US10526542B2 (en) 2015-12-28 2020-01-07 Suncoke Technology And Development Llc Method and system for dynamically charging a coke oven
US10619101B2 (en) 2013-12-31 2020-04-14 Suncoke Technology And Development Llc Methods for decarbonizing coking ovens, and associated systems and devices
US10760002B2 (en) 2012-12-28 2020-09-01 Suncoke Technology And Development Llc Systems and methods for maintaining a hot car in a coke plant
US10851306B2 (en) 2017-05-23 2020-12-01 Suncoke Technology And Development Llc System and method for repairing a coke oven
US10883051B2 (en) 2012-12-28 2021-01-05 Suncoke Technology And Development Llc Methods and systems for improved coke quenching
US10927303B2 (en) 2013-03-15 2021-02-23 Suncoke Technology And Development Llc Methods for improved quench tower design
US10947455B2 (en) 2012-08-17 2021-03-16 Suncoke Technology And Development Llc Automatic draft control system for coke plants
US10968393B2 (en) 2014-09-15 2021-04-06 Suncoke Technology And Development Llc Coke ovens having monolith component construction
US10968395B2 (en) 2014-12-31 2021-04-06 Suncoke Technology And Development Llc Multi-modal beds of coking material
US10975309B2 (en) 2012-12-28 2021-04-13 Suncoke Technology And Development Llc Exhaust flow modifier, duct intersection incorporating the same, and methods therefor
US11008518B2 (en) 2018-12-28 2021-05-18 Suncoke Technology And Development Llc Coke plant tunnel repair and flexible joints
US11021655B2 (en) 2018-12-28 2021-06-01 Suncoke Technology And Development Llc Decarbonization of coke ovens and associated systems and methods
US11060032B2 (en) 2015-01-02 2021-07-13 Suncoke Technology And Development Llc Integrated coke plant automation and optimization using advanced control and optimization techniques
US11071935B2 (en) 2018-12-28 2021-07-27 Suncoke Technology And Development Llc Particulate detection for industrial facilities, and associated systems and methods
US11098252B2 (en) 2018-12-28 2021-08-24 Suncoke Technology And Development Llc Spring-loaded heat recovery oven system and method
US11142699B2 (en) 2012-12-28 2021-10-12 Suncoke Technology And Development Llc Vent stack lids and associated systems and methods
US11261381B2 (en) 2018-12-28 2022-03-01 Suncoke Technology And Development Llc Heat recovery oven foundation
US11395989B2 (en) 2018-12-31 2022-07-26 Suncoke Technology And Development Llc Methods and systems for providing corrosion resistant surfaces in contaminant treatment systems
US11486572B2 (en) 2018-12-31 2022-11-01 Suncoke Technology And Development Llc Systems and methods for Utilizing flue gas
US11508230B2 (en) 2016-06-03 2022-11-22 Suncoke Technology And Development Llc Methods and systems for automatically generating a remedial action in an industrial facility
US11760937B2 (en) 2018-12-28 2023-09-19 Suncoke Technology And Development Llc Oven uptakes
US11767482B2 (en) 2020-05-03 2023-09-26 Suncoke Technology And Development Llc High-quality coke products
US11788012B2 (en) 2015-01-02 2023-10-17 Suncoke Technology And Development Llc Integrated coke plant automation and optimization using advanced control and optimization techniques
US11851724B2 (en) 2021-11-04 2023-12-26 Suncoke Technology And Development Llc. Foundry coke products, and associated systems, devices, and methods
US11946108B2 (en) 2021-11-04 2024-04-02 Suncoke Technology And Development Llc Foundry coke products and associated processing methods via cupolas

Cited By (62)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008224462A (en) * 2007-03-13 2008-09-25 Taiheiyo Cement Corp Organic carbon amount measuring method and solid carbon amount measuring method
US11692138B2 (en) 2012-08-17 2023-07-04 Suncoke Technology And Development Llc Automatic draft control system for coke plants
US10611965B2 (en) 2012-08-17 2020-04-07 Suncoke Technology And Development Llc Coke plant including exhaust gas sharing
US10041002B2 (en) 2012-08-17 2018-08-07 Suncoke Technology And Development Llc Coke plant including exhaust gas sharing
US10947455B2 (en) 2012-08-17 2021-03-16 Suncoke Technology And Development Llc Automatic draft control system for coke plants
US11441077B2 (en) 2012-08-17 2022-09-13 Suncoke Technology And Development Llc Coke plant including exhaust gas sharing
US10053627B2 (en) 2012-08-29 2018-08-21 Suncoke Technology And Development Llc Method and apparatus for testing coal coking properties
US10975309B2 (en) 2012-12-28 2021-04-13 Suncoke Technology And Development Llc Exhaust flow modifier, duct intersection incorporating the same, and methods therefor
US11845037B2 (en) 2012-12-28 2023-12-19 Suncoke Technology And Development Llc Systems and methods for removing mercury from emissions
US11939526B2 (en) 2012-12-28 2024-03-26 Suncoke Technology And Development Llc Vent stack lids and associated systems and methods
US10047295B2 (en) 2012-12-28 2018-08-14 Suncoke Technology And Development Llc Non-perpendicular connections between coke oven uptakes and a hot common tunnel, and associated systems and methods
US10016714B2 (en) 2012-12-28 2018-07-10 Suncoke Technology And Development Llc Systems and methods for removing mercury from emissions
US11359145B2 (en) 2012-12-28 2022-06-14 Suncoke Technology And Development Llc Systems and methods for maintaining a hot car in a coke plant
US11117087B2 (en) 2012-12-28 2021-09-14 Suncoke Technology And Development Llc Systems and methods for removing mercury from emissions
US10760002B2 (en) 2012-12-28 2020-09-01 Suncoke Technology And Development Llc Systems and methods for maintaining a hot car in a coke plant
US10323192B2 (en) 2012-12-28 2019-06-18 Suncoke Technology And Development Llc Systems and methods for improving quenched coke recovery
US11142699B2 (en) 2012-12-28 2021-10-12 Suncoke Technology And Development Llc Vent stack lids and associated systems and methods
US10883051B2 (en) 2012-12-28 2021-01-05 Suncoke Technology And Development Llc Methods and systems for improved coke quenching
US11008517B2 (en) 2012-12-28 2021-05-18 Suncoke Technology And Development Llc Non-perpendicular connections between coke oven uptakes and a hot common tunnel, and associated systems and methods
US10927303B2 (en) 2013-03-15 2021-02-23 Suncoke Technology And Development Llc Methods for improved quench tower design
US11746296B2 (en) 2013-03-15 2023-09-05 Suncoke Technology And Development Llc Methods and systems for improved quench tower design
US10619101B2 (en) 2013-12-31 2020-04-14 Suncoke Technology And Development Llc Methods for decarbonizing coking ovens, and associated systems and devices
US11359146B2 (en) 2013-12-31 2022-06-14 Suncoke Technology And Development Llc Methods for decarbonizing coking ovens, and associated systems and devices
US10526541B2 (en) 2014-06-30 2020-01-07 Suncoke Technology And Development Llc Horizontal heat recovery coke ovens having monolith crowns
JP2018141175A (en) * 2014-08-28 2018-09-13 サンコーク テクノロジー アンド ディベロップメント リミテッド ライアビリティ カンパニー Method and system for optimizing coke plant operation and output
US11053444B2 (en) 2014-08-28 2021-07-06 Suncoke Technology And Development Llc Method and system for optimizing coke plant operation and output
US10920148B2 (en) 2014-08-28 2021-02-16 Suncoke Technology And Development Llc Burn profiles for coke operations
JP2020169335A (en) * 2014-08-28 2020-10-15 サンコーク テクノロジー アンド ディベロップメント リミテッド ライアビリティ カンパニー Method and system for optimizing coke plant operation and output
US10308876B2 (en) 2014-08-28 2019-06-04 Suncoke Technology And Development Llc Burn profiles for coke operations
US9976089B2 (en) 2014-08-28 2018-05-22 Suncoke Technology And Development Llc Coke oven charging system
JP2017529429A (en) * 2014-08-28 2017-10-05 サンコーク テクノロジー アンド ディベロップメント リミテッド ライアビリティ カンパニー Method and system for optimizing coke plant operation and output
US11795400B2 (en) 2014-09-15 2023-10-24 Suncoke Technology And Development Llc Coke ovens having monolith component construction
US10968393B2 (en) 2014-09-15 2021-04-06 Suncoke Technology And Development Llc Coke ovens having monolith component construction
US10975311B2 (en) 2014-12-31 2021-04-13 Suncoke Technology And Development Llc Multi-modal beds of coking material
US10975310B2 (en) 2014-12-31 2021-04-13 Suncoke Technology And Development Llc Multi-modal beds of coking material
US10968395B2 (en) 2014-12-31 2021-04-06 Suncoke Technology And Development Llc Multi-modal beds of coking material
US11060032B2 (en) 2015-01-02 2021-07-13 Suncoke Technology And Development Llc Integrated coke plant automation and optimization using advanced control and optimization techniques
US11788012B2 (en) 2015-01-02 2023-10-17 Suncoke Technology And Development Llc Integrated coke plant automation and optimization using advanced control and optimization techniques
US11214739B2 (en) 2015-12-28 2022-01-04 Suncoke Technology And Development Llc Method and system for dynamically charging a coke oven
US10526542B2 (en) 2015-12-28 2020-01-07 Suncoke Technology And Development Llc Method and system for dynamically charging a coke oven
US11508230B2 (en) 2016-06-03 2022-11-22 Suncoke Technology And Development Llc Methods and systems for automatically generating a remedial action in an industrial facility
US11845898B2 (en) 2017-05-23 2023-12-19 Suncoke Technology And Development Llc System and method for repairing a coke oven
US10851306B2 (en) 2017-05-23 2020-12-01 Suncoke Technology And Development Llc System and method for repairing a coke oven
US11505747B2 (en) 2018-12-28 2022-11-22 Suncoke Technology And Development Llc Coke plant tunnel repair and anchor distribution
US11261381B2 (en) 2018-12-28 2022-03-01 Suncoke Technology And Development Llc Heat recovery oven foundation
US11845897B2 (en) 2018-12-28 2023-12-19 Suncoke Technology And Development Llc Heat recovery oven foundation
US11597881B2 (en) 2018-12-28 2023-03-07 Suncoke Technology And Development Llc Coke plant tunnel repair and flexible joints
US11643602B2 (en) 2018-12-28 2023-05-09 Suncoke Technology And Development Llc Decarbonization of coke ovens, and associated systems and methods
US11680208B2 (en) 2018-12-28 2023-06-20 Suncoke Technology And Development Llc Spring-loaded heat recovery oven system and method
US11071935B2 (en) 2018-12-28 2021-07-27 Suncoke Technology And Development Llc Particulate detection for industrial facilities, and associated systems and methods
US11021655B2 (en) 2018-12-28 2021-06-01 Suncoke Technology And Development Llc Decarbonization of coke ovens and associated systems and methods
US11760937B2 (en) 2018-12-28 2023-09-19 Suncoke Technology And Development Llc Oven uptakes
US11098252B2 (en) 2018-12-28 2021-08-24 Suncoke Technology And Development Llc Spring-loaded heat recovery oven system and method
US11365355B2 (en) 2018-12-28 2022-06-21 Suncoke Technology And Development Llc Systems and methods for treating a surface of a coke plant
US11008518B2 (en) 2018-12-28 2021-05-18 Suncoke Technology And Development Llc Coke plant tunnel repair and flexible joints
US11193069B2 (en) 2018-12-28 2021-12-07 Suncoke Technology And Development Llc Coke plant tunnel repair and anchor distribution
US11486572B2 (en) 2018-12-31 2022-11-01 Suncoke Technology And Development Llc Systems and methods for Utilizing flue gas
US11819802B2 (en) 2018-12-31 2023-11-21 Suncoke Technology And Development Llc Methods and systems for providing corrosion resistant surfaces in contaminant treatment systems
US11395989B2 (en) 2018-12-31 2022-07-26 Suncoke Technology And Development Llc Methods and systems for providing corrosion resistant surfaces in contaminant treatment systems
US11767482B2 (en) 2020-05-03 2023-09-26 Suncoke Technology And Development Llc High-quality coke products
US11851724B2 (en) 2021-11-04 2023-12-26 Suncoke Technology And Development Llc. Foundry coke products, and associated systems, devices, and methods
US11946108B2 (en) 2021-11-04 2024-04-02 Suncoke Technology And Development Llc Foundry coke products and associated processing methods via cupolas

Similar Documents

Publication Publication Date Title
JPH11131074A (en) Operation of coke oven
US11021655B2 (en) Decarbonization of coke ovens and associated systems and methods
JP2914198B2 (en) Coking furnace coal charging method and apparatus
KR101431841B1 (en) Method and device for the coking of high volatility coal
CN104593015A (en) Formcoke refining method and device thereof
JPH07109461A (en) Production of coke
JPH05132673A (en) Equipment for producing coke
CN214307121U (en) Garbage self-heating type intermittent pyrolysis device
JP2000073067A (en) Operation of coke oven
JP3779405B2 (en) Hatching method and hatching apparatus
JP3260218B2 (en) Manufacturing method of coke for blast furnace
JPH09208965A (en) Red-hot coke transporting apparatus of chamber coke oven
JPH07109460A (en) Production of coke
CN204529731U (en) A kind of formed coke refining equipment
JPS63112686A (en) Method of promoting carbonization in oven mouth portion of coke oven
JPH06184540A (en) Process for producing coke and equipment therefor
JPH0532974A (en) Method for controlling dry distillation in coke oven
JP2884979B2 (en) Prevention method of black smoke generation in coke oven chimney
JPH07109468A (en) Method for thermally baking semicoke
JPH07113079A (en) Carbonization promoting method for coking, coking process and oven door of coke oven
JPH07173471A (en) Production of coke
JPH06336588A (en) Production of coke, and method and apparatus for recovering steam
JPH07118638A (en) Vertical chamber style coke oven
JPS61231088A (en) Method and apparatus for burning and removing adhered carbon in carbonizing chamber of coke oven
JPH07109457A (en) Production of coke