JPH11117575A - Steel tower construction for transmission line and method thereof - Google Patents

Steel tower construction for transmission line and method thereof

Info

Publication number
JPH11117575A
JPH11117575A JP27619197A JP27619197A JPH11117575A JP H11117575 A JPH11117575 A JP H11117575A JP 27619197 A JP27619197 A JP 27619197A JP 27619197 A JP27619197 A JP 27619197A JP H11117575 A JPH11117575 A JP H11117575A
Authority
JP
Japan
Prior art keywords
tower
existing
new
main
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP27619197A
Other languages
Japanese (ja)
Inventor
Yoshiji Otsubo
芳次 大坪
Seiji Itoda
誠治 糸田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Electric Power Development Co Ltd
Original Assignee
Electric Power Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Development Co Ltd filed Critical Electric Power Development Co Ltd
Priority to JP27619197A priority Critical patent/JPH11117575A/en
Publication of JPH11117575A publication Critical patent/JPH11117575A/en
Pending legal-status Critical Current

Links

Landscapes

  • Electric Cable Installation (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a steel tower construction of transmission line and a method thereof capable of executing footing work with hot line to shorten a stop period of time and, at the same time, applying a conventional wrapping method to build-up work of the steel tower. SOLUTION: A new steel tower TN main body (panels K2-K16) except for the lowest panel of a steel tower is installed to the outside of the existing steel tower TO in the same direction in a plane view without contacting the existing steel tower TO. Four new footings FN-FN are positioned between four exisisting footings FO-FO to install. In the lowest panel, main clumn members P1 and P1 making a pair to new footings FN-FN are so extended upward by showing an upper opened V-shape, and the upper parts of the said pair of main column members P1 and P1 are connected to a main column member P2 of the new steel tower main body (panels K2-K16).

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、送電線の建替・増
強工事に関し、鉄塔の上部構造は従来の包込工法が採用
できる形状とし、新設基礎は既設基礎の間に配置するこ
とを可能とする送電線の鉄塔構造およびその工法に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to the construction and enhancement of transmission lines, in which the superstructure of a tower is shaped so that a conventional wrapping method can be adopted, and a new foundation can be placed between existing foundations. The present invention relates to a transmission tower structure of a transmission line and its construction method.

【0002】[0002]

【従来の技術】電力需要地の近傍においては、地域開発
の進展により新たな送電ルートの確保は厳しくなってお
り、電力需要の増加に対しては既設送電線の増容量化に
より対処することが多くなっている。そして、送電線の
増容量化に伴い、送電線の建替工事が必要になる。
2. Description of the Related Art In the vicinity of a power demand area, securing new power transmission routes has become strict due to progress in regional development, and it is possible to cope with an increase in power demand by increasing the capacity of existing transmission lines. More. In addition, as the capacity of the transmission line increases, the construction of the transmission line is required.

【0003】ここで、従来の送電線建替工事は下記
(a)〜(d)の通りがある。 (a)撤去工法;既設送電線を一旦撤去した後、新規の
送電線を建設する方法で、停止期間が長くなることか
ら、仮送電線を設置することを必要とすることが多い。
また、停止が可能な場合でも、既設電線の仮留めなどの
仮設備を必要とする。
Here, conventional transmission line rebuilding work is as follows (a) to (d). (A) Removal method: A method of constructing a new transmission line after temporarily removing the existing transmission line, which requires a temporary transmission line to be installed because the outage period becomes longer.
In addition, even when stopping is possible, temporary facilities such as temporary fixing of existing electric wires are required.

【0004】(b)包込工法;既設鉄塔の外側に新規の
鉄塔を建設する方法である。鉄塔基礎は既設基礎に接触
しないよう配置することから、停止期間は短いが鉄塔敷
地は拡幅用地の取得が必要となる。
(B) Encapsulation method: A method of constructing a new tower outside the existing tower. Since the tower foundation is placed so that it does not contact the existing foundation, the suspension period is short, but it is necessary to acquire land for widening the tower site.

【0005】(c)回転鉄塔;(45度鉄塔) この鉄塔
は、既設基礎の間に新規の基礎を配置するものであり、
既設基礎を有効に利用することを目的としている。ただ
し、上部構造は既設鉄塔と平面的に45度方向が異なるこ
とから、工事に際しては既設鉄塔と接触し既設部材の間
隙を通す方法などが採用されている。また、停止期間は
短いが、鉄塔組立工事は既設部材と輻輳し複雑化する。
(C) Rotating tower; (45-degree tower) This tower is to place a new foundation between existing foundations.
The purpose is to use the existing foundation effectively. However, since the upper structure is different from the existing tower by 45 degrees in plan view, a method of contacting the existing tower and passing through the gap between the existing members has been adopted during construction. Although the suspension period is short, the tower assembly work is complicated by congestion with existing members.

【0006】(d)嵩上げ工法;既設鉄塔を油圧ジャッ
キ等により持ち上げ、鉄塔下部に新規の鉄塔材料を挿入
する工法である。この工法は、使用する鉄塔は既設を使
用することから、送電線の増強工事等においては使用で
きない。
(D) Raising method: A method of lifting an existing tower with a hydraulic jack or the like and inserting a new tower material into a lower part of the tower. This method cannot be used for reinforcement of transmission lines, etc., because existing steel towers are used.

【0007】[0007]

【発明が解決しようとする課題】前記従来の各工法にお
いて送電線の増容量化に対して使用できる工法は(a)
〜(c)であるが、(a)の撤去工法は停止期間の長期
化を伴うと共に仮設備工事を伴う問題点があり、使用で
きない。また、(b)の包込工法は新規基礎と限定した
位置に拡幅用地を必要する欠点がある。さらに、(c)
の回転鉄塔等は基礎工事は活線で可能となるものの上部
組立工事は既設鉄塔と輻輳し、構造・施工が複雑とな
る。
In each of the above-mentioned conventional methods, a method which can be used for increasing the capacity of a transmission line is as follows.
However, the removal method shown in (a) cannot be used because it involves a problem in that the suspension period is lengthened and temporary facilities are constructed. Further, the enclosing method (b) has a drawback that a widening land is required at a position limited to a new foundation. Further, (c)
Although the rotating towers can be used for live work for foundation work, the upper assembly work will be congested with existing towers, complicating the structure and construction.

【0008】また、既設送電線の元位置での建替工事
は、停止期間並びにコスト面から一般的に包込工法を採
用している。この包込工法では、既設鉄塔の外側に新規
鉄塔を配置するため新規の鉄塔基礎は既設鉄塔の外側と
なり、設置箇所も限定されたものとなる。この場合、拡
幅用地が必要となるが土地の利用形態から不可能な場合
があり既設鉄塔を撤去後、新規鉄塔を建設することとな
る。
[0008] In the rebuilding work at the original position of the existing transmission line, the enclosing method is generally adopted from the standpoint of downtime and cost. In this wrapping method, a new tower is arranged outside the existing tower, so that the new tower foundation is located outside the existing tower, and the installation location is also limited. In this case, widening land is required, but it may not be possible due to the land use form, and after removing the existing tower, a new tower will be constructed.

【0009】本発明は、前記従来の工事形態の問題点を
解消し、かつ、それらの長所を各々活用可能にするもの
であって、基礎工事を活線で可能とし停止期間を短くで
きると共に、鉄塔の組み立て工事には従来の包込工法を
適用できるようにしかつ拡幅用地を不要にできる送電線
の鉄塔構造およびその工法を提供することを目的とす
る。
The present invention solves the above-mentioned problems of the conventional construction form and makes it possible to utilize the advantages of each of them. It is an object of the present invention to provide a transmission tower structure and a method for assembling a transmission tower, which can apply a conventional wrapping method and eliminate the need for a widening site.

【0010】[0010]

【課題を解決するための手段】本発明は、上記の目的を
達成するため、次の構成を有する。請求項1の発明は、
既設鉄塔の外側に包込工法により設置する新設鉄塔であ
って、鉄塔の下端部構造以外の新設鉄塔本体を既設鉄塔
と平面視同方向に形成し、新設基礎を既設基礎に対して
平面視で回転させた位置に設置し、前記下端部構造を、
該新設基礎と新設鉄塔の主柱材とを斜めの主柱材で連結
するものとしたことを特徴とする送電線の鉄塔構造であ
る。請求項2の発明は、既設鉄塔の外側に包込工法によ
り設置する新設鉄塔であって、鉄塔の最下パネルを除く
新設鉄塔本体を既設鉄塔の外側に該既設鉄塔と接触せず
かつ平面視同方向に配置し、既設基礎の間に位置して新
設基礎を設置し、最下パネルでは、各新設基礎に対の主
柱材が上開きのV字形状を呈して上方に延びるように設
置し、かつ、この対の主柱材上部を新設鉄塔本体の主柱
材に連結したことを特徴とする送電線の鉄塔構造であ
る。請求項3の発明は、最下パネルの対の主柱材が新設
鉄塔本体の主柱材に連結される複数の交点同士は、水平
材で連結されたことを特徴とする請求項2に記載の送電
線の鉄塔構造である。請求項4の発明は、既設鉄塔の外
側に包込工法により設置する際に、既設基礎の間に位置
して新設基礎を設置する工程と、各新設基礎に対の主柱
材が上開きのV字形状を呈して上方に延びるように最下
パネルを設置する工程と、新設鉄塔本体パネルを既設鉄
塔の外側に該既設鉄塔と接触せずかつ平面視同方向に組
み立てると共に既設鉄塔を解体する工程と、を含んで既
設鉄塔を新設鉄塔に立て替えるようにしたことを特徴と
する送電線の鉄塔構造の工法である。請求項5の発明
は、最下パネルの設置工程では既設送電線の送電を続行
し、最下パネルより上のパネル組み立てる工程では、既
設送電線の送電を停止して複数の腕金毎に、腕金の近傍
までパネル組み立てを行い、組み立て後に送電線を主柱
材に仮留めし、かつ腕金を撤去する工程を繰り返すこと
を特徴とする請求項4に記載の送電線の鉄塔構造の工法
である。請求項6の発明は、既設鉄塔の撤去後に新設鉄
塔の対角材を設置することを特徴とする請求項4または
5に記載の送電線の鉄塔構造の工法である。
The present invention has the following configuration to achieve the above object. The invention of claim 1 is
A new tower to be installed outside of the existing tower by the wrapping method, the new tower body other than the lower end structure of the tower is formed in the same direction as the existing tower in plan view, and the new foundation is viewed in plan with respect to the existing foundation. Installed in a rotated position, the lower end structure,
The power transmission tower structure is characterized in that the new foundation and the main pillar material of the new steel tower are connected by an oblique main pillar material. The invention according to claim 2 is a new tower to be installed outside the existing tower by the enclosing method, wherein the main body of the new tower except for the lowermost panel of the tower is not in contact with the existing tower outside the existing tower and in plan view. In the same direction, a new foundation is installed between existing foundations, and at the bottom panel, each new foundation is installed so that a pair of main pillars has a V-shape that opens upward and extends upward. And an upper part of the pair of main pillars connected to a main pillar of the new tower body. The invention according to claim 3 is characterized in that a plurality of intersections where the pair of main pillars of the lowermost panel are connected to the main pillar of the new tower main body are connected by horizontal members. Power transmission tower structure. The invention according to claim 4 is a method of installing a new foundation located between existing foundations when installing the existing foundation on the outside of the existing steel tower, and a method of opening a pair of main pillars on each new foundation. Installing the lowermost panel so as to have a V-shape and extend upward, assembling the new tower body panel outside the existing tower in the same direction as in plan view without contacting the existing tower and dismantling the existing tower. And a step of replacing an existing tower with a new tower. The invention of claim 5 is that, in the step of installing the lowermost panel, the transmission of the existing transmission line is continued, and in the step of assembling the panel above the lowermost panel, the transmission of the existing transmission line is stopped, and for each of the plurality of arms, 5. The method according to claim 4, wherein the panel is assembled to the vicinity of the arm, and after the assembly, the step of temporarily fixing the transmission line to the main pillar and removing the arm is repeated. It is. The invention of claim 6 is the method of constructing a transmission line tower structure according to claim 4 or 5, wherein a diagonal member of the new tower is installed after the existing tower is removed.

【0011】本発明の送電線鉄塔構造およびその工法に
よれば、鉄塔の下端部構造(最下パネルなど)以外の新
設鉄塔本体を既設鉄塔と平面視同方向に形成し、新設基
礎を既設基礎に対して平面視で回転させた位置に設置
し、前記下端部構造は、該新設基礎と新設鉄塔の主柱材
とを斜めの主柱材で連結する。この結果、新設鉄塔本体
は既設鉄塔と同方向に設置できかつ新設基礎に対してほ
ぼ45°回転させた方向に設置できる。
According to the power transmission tower structure and the method of construction of the present invention, a new tower main body other than the lower end structure of the tower (such as the lowermost panel) is formed in the same direction as the existing tower in plan view, and the new foundation is installed. And the lower end structure connects the new foundation and the main column material of the new steel tower with an oblique main column material. As a result, the new tower body can be installed in the same direction as the existing tower, and can be installed in a direction rotated by approximately 45 ° with respect to the new foundation.

【0012】また、最下パネルは、各新設基礎に対の主
柱材が上開きのV字形状を呈して上方に延びるように設
置し、かつ、この対の主柱材上部を新設鉄塔本体の主柱
材に連結したので、最下パネルの主柱材をV字形状に設
置するだけの極めて簡単な構造で包込工法を実現でき
る。
[0012] The lowermost panel is installed on each new foundation so that a pair of main pillars has an upwardly open V-shape and extends upward. , The wrapping method can be realized with an extremely simple structure in which the main pillar of the lowermost panel is installed in a V-shape.

【0013】したがって、本発明では、鉄塔の最下パネ
ルを工夫し、基礎工事は活線による施工を可能として、
停止期間を短くできる。また、上部鉄塔組立工事は、包
込工法による施工を可能とするので、鉄塔構造は既往の
構造で対応でき設計・施工は簡素化できることとなる。
また、新設基礎が既設基礎の間に設置できるので拡幅用
地を不要にできる。
Therefore, in the present invention, the bottom panel of the tower is devised so that the foundation work can be performed by live lines.
The suspension period can be shortened. In addition, since the upper tower assembling work can be performed by the enclosing method, the tower structure can be used with the existing structure, and the design and construction can be simplified.
In addition, since a new foundation can be installed between the existing foundations, a widening site can be eliminated.

【0014】なお、最下パネルの対の主柱材が新設鉄塔
本体の主柱材に連結される複数の交点同士を、水平材で
連結されたものにすれば、交点の連結により最下パネル
と新設鉄塔本体の連結部が簡単な構造で強固になる。ま
た、最下パネルの設置工程では既設送電線の送電を続行
し、最下パネルより上のパネル組み立てる工程では、既
設送電線の送電を停止するので、基礎工事は活線で可能
になるので停止期間が短くて済むと共に、電線を主柱材
に仮留めして腕金を撤去する工程を繰り返すので、腕金
を撤去する際に別途に電線支持部工事を行う必要がな
く、さらに工期を短縮化できる。また、既設鉄塔の撤去
後に新設鉄塔の対角材を設置するので、対角材により鉄
塔剛性が高まると共に既設鉄塔の撤去後であるので対角
材設置が容易である。
If the plurality of intersections where the pair of main pillars of the lowermost panel are connected to the main pillar of the new tower body are connected by horizontal members, the lowermost panel is connected by the connection of the intersections. The connection between the new tower and the new tower is simple and strong. Also, in the installation process of the bottom panel, the transmission of the existing transmission line is continued, and in the process of assembling the panel above the bottom panel, the transmission of the existing transmission line is stopped. In addition to shortening the period, the process of temporarily fixing the wire to the main pillar and removing the arm bar is repeated, so there is no need to separately construct the wire support part when removing the arm bar, further shortening the construction period Can be Further, since the diagonal members of the new tower are installed after the removal of the existing tower, the rigidity of the towers is increased by the diagonal members, and the installation of the diagonal members is easy since the existing towers are removed.

【0015】[0015]

【発明の実施の形態】以下、図面を参照して本発明の実
施形態を詳細に説明する。図1〜図5は、本発明の実施
形態にかかる送電線の鉄塔構造の説明図であって、実線
で示される新設鉄塔TNを破線で示される既設鉄塔TO
と比較して示す図である。図1は最下パネルと基礎の平
面図であり、図2(A視)は正面方向から見た図であ
り、図3(B視)は正面より45度ずれた斜め方向から
見た図であり、図4は新設鉄塔TNと既設鉄塔TOとの
全体図、図5は(C視)断面図である。
Embodiments of the present invention will be described below in detail with reference to the drawings. 1 to 5 are explanatory diagrams of a transmission tower structure according to an embodiment of the present invention, in which a new tower TN indicated by a solid line is replaced with an existing tower TO indicated by a broken line.
It is a figure shown in comparison with. FIG. 1 is a plan view of the lowermost panel and the foundation. FIG. 2 (A) is a diagram viewed from the front, and FIG. 3 (B) is a diagram viewed from an oblique direction shifted from the front by 45 degrees. FIG. 4 is an overall view of the new tower TN and the existing tower TO, and FIG. 5 is a sectional view (viewed from C).

【0016】図に示すように、前記送電線の鉄塔構造に
おいては、鉄塔の最下パネルK1を除く新設鉄塔TN本
体(パネルK2〜K16)を既設鉄塔TOの外側に該既
設鉄塔TOと接触せずかつ平面視同方向に配置する。そ
して、4つの既設基礎FO〜FOのそれぞの間に位置し
てそれぞれ4つの新設基礎FN〜FNを設置する。最下
パネルK1では、各新設基礎FN〜FNに対の主柱材P
1、P1が上開きのV字形状を呈して上方に延びるよう
に設置し、かつ、この対の主柱材P1、P1上部を新設
鉄塔本体(パネルK2〜K16)の主柱材P2に連結す
る。また、最下パネルK1の対の主柱材P1、P1が新
設鉄塔本体(パネルK2〜K16)の主柱材P2に連結
される複数の交点10、10…同士は、水平材S1で連
結されており、パネルK1とパネルK2の接点の断面を
示す図5に示すように、既設鉄塔TOを取り巻いて新設
鉄塔TNが設けられる。なお、最下パネルK1にはその
外、主柱材P1、P1、と水平材S1間などに水平方向
および上下方向に適宜の補強材(符号14で示す)が設
けられて構造上の強度が向上するようにしている。
As shown in the figure, in the tower structure of the transmission line, the new tower TN body (panels K2 to K16) except for the lowermost panel K1 of the tower is brought into contact with the existing tower TO outside the existing tower TO. And are arranged in the same direction in plan view. Then, four new foundations FN to FN are respectively installed between the four existing foundations FO to FO. In the lowermost panel K1, each of the new foundations FN to FN has a pair of main pillars P
1, P1 is installed so as to exhibit a V-shape that opens upward and extend upward, and the upper part of the pair of main pillars P1, P1 is connected to the main pillar P2 of the new tower body (panels K2 to K16). I do. A plurality of intersections 10, 10,... Where the pair of main pillars P1, P1 of the lowermost panel K1 are connected to the main pillar P2 of the new tower body (panels K2 to K16) are connected by a horizontal bar S1. As shown in FIG. 5 showing a cross section of a contact point between the panel K1 and the panel K2, a new tower TN is provided around the existing tower TO. In addition, the lowermost panel K1 is additionally provided with appropriate reinforcing members (indicated by reference numeral 14) in the horizontal and vertical directions between the main pillars P1, P1, and the horizontal member S1, and the like, so that structural strength is improved. I try to improve.

【0017】建替工事において、図1〜図4に示すよう
に、新設基礎FNは、活線状態において4個の既設基礎
FOの間に4個が設置される。それぞれの新設基礎FN
上に2本の主柱材P1、P1をV字型に支持する構造で
連結する。この建替工事にあたって、新設鉄塔TNを組
み立を開始した時点では、既設鉄塔TOは撤去されずそ
のまま残っていて、新設鉄塔TNの建設途中において、
既設鉄塔TOが部分的に撤去されていき、新設鉄塔TN
を建設と既設鉄塔TOの撤去を交互に行う。
In the rebuilding work, as shown in FIGS. 1 to 4, four new foundations FN are installed between four existing foundations FO in a live state. Each new foundation FN
The two main pillars P1, P1 are connected by a structure supporting the V-shape on the upper side. At the time of the rebuilding work, when the construction of the new tower TN was started, the existing tower TO was left as it was without being removed, and during the construction of the new tower TN,
The existing tower TO was partially removed and the new tower TN
Construction and removal of the existing tower TO will be performed alternately.

【0018】建替工事の各施工工程を図6〜図10に詳
細に説明する。図6に示すように、新設鉄塔TNの最下
パネルK1の組立において、主柱材P1から主柱材P2
に連結される際、新設基礎FNが既設基礎FOに対して
45度ずれていた角度を既設鉄塔TOと同様な角度に形
成し、以降の上部組立(パネルK2〜パネルK16)に
おいては、新設鉄塔TNが既設鉄塔TOを包み込む形で
組み立てられる。そして、パネルK1においては、主柱
材P1と主柱材P2の交点10、10同士を水平材S1
で連結し構成される。この際、既設鉄塔TOを包み込む
ため、新設鉄塔TNの対角材12、12(図5参照)は
設置出来ないが、これは、既設鉄塔TOをすべて撤去し
た後に設置する。
Each construction step of the rebuilding work will be described in detail with reference to FIGS. As shown in FIG. 6, in assembling the lowermost panel K1 of the new steel tower TN, the main column material P1 is changed to the main column material P2.
When the new foundation FN is connected to the existing foundation FO, an angle of 45 degrees is deviated from the existing foundation FO to an angle similar to that of the existing tower TO. In the subsequent upper assembly (panel K2 to panel K16), the new tower FN is used. The TN is assembled so as to wrap the existing tower TO. Then, in the panel K1, the intersections 10, 10 of the main pillar P1 and the main pillar P2 are connected to each other by the horizontal
It is connected and configured. At this time, since the existing tower TO is wrapped around, the diagonal members 12 and 12 (see FIG. 5) of the new tower TN cannot be installed. However, this is installed after removing the existing tower TO entirely.

【0019】そして、パネルK2以上のパネルは、既設
鉄塔TOの電気を停止し、包み込む形でパネルK3まで
組み立てられる。その後に既設鉄塔TOの電線C2及び
電線C3を新設鉄塔TNの主柱材Pに仮留する(図6参
照)。
Then, the panels K2 and above are assembled up to the panel K3 by stopping the electricity of the existing tower TO and wrapping the panels. Thereafter, the electric wires C2 and C3 of the existing tower TO are temporarily fastened to the main pillar P of the new tower TN (see FIG. 6).

【0020】次に、既設鉄塔TOの腕金a2及び腕金a
3を解体し、パネルK4を組み立て、架空地線g及び電
線c1を主柱材Pに仮留めする(図7参照)。仮留め終
了後、既設鉄塔TOの腕金ag及び腕金a1を解体する
(図8参照)。既設鉄塔TOを順次解体した後に、新設
鉄塔TNのパネルK5から頂部パネルK16まで順次組
立を行い(図9参照)、さらに腕金AG、A1〜A3を
取り付けて、主柱材Pに仮留していた架空地線g及び電
線c1〜c3をそれぞれ腕金AG並びに腕金A1〜A3
に移線される(図10参照)。
Next, the arm a2 and the arm a of the existing tower TO
3 is disassembled, the panel K4 is assembled, and the overhead ground wire g and the electric wire c1 are temporarily fixed to the main pillar P (see FIG. 7). After the temporary fastening is completed, the arm bar ag and the arm bar a1 of the existing tower TO are dismantled (see FIG. 8). After the existing tower TO is dismantled sequentially, the new tower TN is assembled sequentially from the panel K5 to the top panel K16 (see FIG. 9), and further, the arm members AG, A1 to A3 are attached and temporarily anchored to the main pillar P. The imaginary ground wire g and the electric wires c1 to c3 that have been
(See FIG. 10).

【0021】実施形態の送電線鉄塔構造およびその工法
によれば、新設鉄塔TNの最下パネルK1以外の新設鉄
塔本体(パネルK2〜K16)を既設鉄塔TOと平面視
同方向に形成し、新設基礎FNを既設基礎FOに対して
平面視で回転させた位置に設置し、前記最下パネルは、
該新設基礎FNと新設鉄塔TNの主柱材P2とを斜めの
主柱材P1で連結する。この結果、新設鉄塔TN本体は
既設鉄塔TOと同方向に設置できかつ新設基礎FNに対
してほぼ45°回転させた方向に設置できる。この45
度に捻っている形状より、新設鉄塔TNは「ツイスト鉄
塔」と称することができる。
According to the transmission line tower structure and the method of construction of the embodiment, the new tower main body (panels K2 to K16) other than the lowermost panel K1 of the new tower TN is formed in the same direction as the existing tower TO in the plan view. The foundation FN is installed at a position rotated in plan view with respect to the existing foundation FO, and the lowermost panel is
The new foundation FN and the main pillar P2 of the new steel tower TN are connected by an oblique main pillar P1. As a result, the new tower TN body can be installed in the same direction as the existing tower TO, and can be installed in a direction rotated by approximately 45 ° with respect to the new foundation FN. This 45
The newly installed tower TN can be referred to as a “twisted tower” because of its twisted shape.

【0022】また、最下パネルK1は、各新設基礎FN
に対の主柱材P1、P1上部を新設鉄塔本体の主柱材P
2、P2に連結しており、主柱材をV字形状に設置する
だけなので極めて簡単な構造で包込工法を実現できる。
The lowermost panel K1 is provided with each new foundation FN.
The upper part of the pair of main pillars P1, P1 is the main pillar P of the new tower body
2, since it is connected to P2 and the main pillars are simply installed in a V-shape, the wrapping method can be realized with an extremely simple structure.

【0023】したがって、実施形態では、鉄塔の最下パ
ネルを工夫し、基礎工事は活線による施工を可能とし
て、停止期間を短くでき、かつ、上部鉄塔組立工事は、
包込工法による施工を可能とするので、鉄塔構造は既往
の構造で対応でき設計・施工は簡素化できることとな
る。なお、複数の交点10、10…同士は、水平材S1
で連結するので、交点の連結により最下パネルK1と新
設鉄塔TN本体の連結部が簡単な構造で強固になる。
Therefore, in the embodiment, the lowermost panel of the tower is devised so that the foundation work can be performed by hot wire, the stop period can be shortened, and the assembling work of the upper tower is
Since the construction using the enclosing method is possible, the steel tower structure can be used with the existing structure, and the design and construction can be simplified. The plurality of intersections 10, 10,...
The connection at the intersection makes the connection between the lowermost panel K1 and the new tower TN body strong with a simple structure.

【0024】既設鉄塔TOの電線C2、C3を主柱材P
(P2)に仮留めして腕金ag、a1〜a3を撤去する
工程を繰り返すので、腕金を撤去する際に別途に電線支
持部工事を行う必要がなく、工期を短縮化できる。ま
た、既設鉄塔TOの撤去後に新設鉄塔TNの対角材12
を設置するので、対角材12により鉄塔剛性が高まると
共に既設鉄塔の撤去後であるので対角材12設置が容易
である。
The electric wires C2 and C3 of the existing tower TO are connected to the main pillar P
Since the process of removing the arm members ag and a1 to a3 by temporarily fixing the arm members to (P2) is repeated, it is not necessary to separately perform a wire support part work when removing the arm members, and the construction period can be shortened. In addition, after removing the existing tower TO, the diagonal timber 12 of the new tower TN is removed.
Is installed, the rigidity of the tower is increased by the diagonal members 12, and the diagonal members 12 can be easily installed since the existing steel towers have been removed.

【0025】[0025]

【発明の効果】以上説明した通り、本発明によれば、新
設鉄塔が既設鉄塔に対して例えば45度程度捻転した位
置に基礎を設け、最下パネルの上部で既設鉄塔と同様の
角度に戻するので、基礎工事を活線で可能とし停止期間
を短くできると共に、鉄塔の組み立て工事には従来の包
込工法を適用できる。
As described above, according to the present invention, the foundation is provided at a position where the new tower is twisted by, for example, about 45 degrees with respect to the existing tower, and is returned to the same angle as the existing tower at the upper part of the lowermost panel. As a result, the foundation work can be performed by live lines, and the downtime can be shortened, and the conventional wrapping method can be applied to the construction work of the steel tower.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一実施形態の新設鉄塔と既設鉄塔を示
す平面図である。
FIG. 1 is a plan view showing a new tower and an existing tower according to an embodiment of the present invention.

【図2】図1のA方向視図である。FIG. 2 is a view as viewed in a direction A in FIG. 1;

【図3】図1のB方向視図である。FIG. 3 is a view as viewed in a direction B in FIG. 1;

【図4】本発明の一実施形態の新設鉄塔と既設鉄塔を示
す側方視の全体図である。
FIG. 4 is an overall side view showing a new tower and an existing tower according to an embodiment of the present invention.

【図5】図4におけるC方向断面視図である。FIG. 5 is a sectional view in the direction C in FIG. 4;

【図6】既設鉄塔から図4の新設鉄塔に建て替える手順
の説明図である。
FIG. 6 is an explanatory diagram of a procedure for rebuilding an existing pylon to a new pylon of FIG. 4;

【図7】図6に続く建て替える手順の説明図である。FIG. 7 is an explanatory diagram of the rebuilding procedure following FIG. 6;

【図8】図7に続く建て替える手順の説明図である。FIG. 8 is an explanatory diagram of the rebuilding procedure following FIG. 7;

【図9】図8に続く建て替える手順の説明図である。FIG. 9 is an explanatory diagram of the rebuilding procedure following FIG. 8;

【図10】図9に続く建て替える手順の説明図である。FIG. 10 is an explanatory diagram of the rebuilding procedure following FIG. 9;

【符号の説明】[Explanation of symbols]

FN 新設基礎 F0 既設基礎 TN 新設鉄塔 T0 既設鉄塔 P 新設主柱材 p 既設主柱材 K 新設パネル k 既設パネル S1 新設水平材 a 既設腕金 g 架空地線 c 電線 FN New foundation F0 Existing foundation TN New tower T0 Existing tower P New main pole p Existing main pole K New panel k Existing panel S1 New horizontal material a Existing arm g g Overhead ground wire c Electric wire

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 既設鉄塔の外側に包込工法により設置す
る新設鉄塔であって、 鉄塔の下端部構造以外の新設鉄塔本体を既設鉄塔と平面
視同方向に形成し、新設基礎を既設基礎に対して平面視
で回転させた位置に設置し、 前記下端部構造を、該新設基礎と新設鉄塔の主柱材とを
斜めの主柱材で連結するものとしたことを特徴とする送
電線の鉄塔構造。
Claims: 1. A new tower installed by an enclosing method outside an existing tower, wherein a new tower body other than a lower end structure of the tower is formed in the same direction as the existing tower in plan view, and a new foundation is used as an existing foundation. The lower end structure is connected to the main pillar of the new foundation and the main pillar of the new tower with an oblique main pillar. Tower structure.
【請求項2】 既設鉄塔の外側に包込工法により設置す
る新設鉄塔であって、 鉄塔の最下パネルを除く新設鉄塔本体を既設鉄塔の外側
に該既設鉄塔と接触せずかつ平面視同方向に配置し、 既設基礎の間に位置して新設基礎を設置し、 最下パネルでは、各新設基礎に対の主柱材が上開きのV
字形状を呈して上方に延びるように設置し、かつ、この
対の主柱材上部を新設鉄塔本体の主柱材に連結したこと
を特徴とする送電線の鉄塔構造。
2. A new pylon installed outside the existing pylon by an enclosing method, wherein the main body of the new pylon except for the lowermost panel of the pylon does not come into contact with the existing pylon outside the existing pylon and is in the same direction in plan view. And a new foundation is installed between existing foundations. In the bottom panel, each main foundation has a pair of main pillars with an open V
A tower structure for a transmission line, characterized in that it is installed so as to have a U-shape and extends upward, and the upper portion of the pair of main columns is connected to the main column of a new tower body.
【請求項3】 最下パネルの対の主柱材が新設鉄塔本体
の主柱材に連結される複数の交点同士は、水平材で連結
されたことを特徴とする請求項2に記載の送電線の鉄塔
構造。
3. The feeder according to claim 2, wherein a plurality of intersections at which the pair of main pillars of the lowermost panel are connected to the main pillar of the new tower body are connected by horizontal members. Electric tower structure.
【請求項4】 既設鉄塔の外側に包込工法により設置す
る際に、 既設基礎の間に位置して新設基礎を設置する工程と、 各新設基礎に対の主柱材が上開きのV字形状を呈して上
方に延びるように最下パネルを設置する工程と、 新設鉄塔本体パネルを既設鉄塔の外側に該既設鉄塔と接
触せずかつ平面視同方向に組み立てると共に既設鉄塔を
解体する工程と、を含んで既設鉄塔を新設鉄塔に立て替
えるようにしたことを特徴とする送電線の鉄塔構造の工
法。
4. A step of installing a new foundation between existing foundations when installing the existing foundation on the outside of a steel tower by a wrapping method, and a V-shape in which a pair of main columns is opened upward on each new foundation. A step of installing a lowermost panel so as to extend upward in shape and a step of disassembling the existing tower and assembling the new tower body panel outside the existing tower in the same direction as in plan view without contacting the existing tower. A method of constructing a power transmission tower structure in which an existing tower is replaced with a new tower.
【請求項5】 最下パネルの設置工程では既設送電線の
送電を続行し、最下パネルより上のパネル組み立てる工
程では、既設送電線の送電を停止して、複数の腕金毎
に、腕金の近傍までパネル組み立てを行い、組み立て後
に送電線を主柱材に仮留めし、かつ腕金を撤去する工程
を繰り返すことを特徴とする請求項4に記載の送電線の
鉄塔構造の工法。
5. The step of installing the lowermost panel, the power transmission of the existing transmission line is continued. In the step of assembling the panel above the lowermost panel, the transmission of the existing transmission line is stopped. 5. The method according to claim 4, wherein the panel is assembled to the vicinity of the gold, and after the assembly, the step of temporarily fixing the transmission line to the main pillar and removing the arm bar is repeated.
【請求項6】 既設鉄塔の撤去後に新設鉄塔の対角材を
設置することを特徴とする請求項4または5に記載の送
電線の鉄塔構造の工法。
6. The method according to claim 4, wherein a diagonal member of a new tower is installed after removing the existing tower.
JP27619197A 1997-10-08 1997-10-08 Steel tower construction for transmission line and method thereof Pending JPH11117575A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP27619197A JPH11117575A (en) 1997-10-08 1997-10-08 Steel tower construction for transmission line and method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP27619197A JPH11117575A (en) 1997-10-08 1997-10-08 Steel tower construction for transmission line and method thereof

Publications (1)

Publication Number Publication Date
JPH11117575A true JPH11117575A (en) 1999-04-27

Family

ID=17565975

Family Applications (1)

Application Number Title Priority Date Filing Date
JP27619197A Pending JPH11117575A (en) 1997-10-08 1997-10-08 Steel tower construction for transmission line and method thereof

Country Status (1)

Country Link
JP (1) JPH11117575A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004300872A (en) * 2003-04-01 2004-10-28 Shikoku Electric Power Co Inc Steel tower for power transmission cable
WO2014007563A2 (en) * 2012-07-04 2014-01-09 (주)서해전설 Steel-tower lifting device, and steel-tower lifting method and steel-tower maintenance method using the device
KR101966005B1 (en) * 2018-03-12 2019-04-04 한전케이피에스 주식회사 Construction method for tubular pole using existing steel tower
JP2022068092A (en) * 2020-10-16 2022-05-09 株式会社アイ・ティ・シ・コンサルティング Structural steelwork constructed around existing columnar body and construction method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004300872A (en) * 2003-04-01 2004-10-28 Shikoku Electric Power Co Inc Steel tower for power transmission cable
WO2014007563A2 (en) * 2012-07-04 2014-01-09 (주)서해전설 Steel-tower lifting device, and steel-tower lifting method and steel-tower maintenance method using the device
WO2014007563A3 (en) * 2012-07-04 2014-02-20 (주)서해전설 Steel-tower lifting device, and steel-tower lifting method and steel-tower maintenance method using the device
KR101966005B1 (en) * 2018-03-12 2019-04-04 한전케이피에스 주식회사 Construction method for tubular pole using existing steel tower
JP2022068092A (en) * 2020-10-16 2022-05-09 株式会社アイ・ティ・シ・コンサルティング Structural steelwork constructed around existing columnar body and construction method thereof

Similar Documents

Publication Publication Date Title
CN101979791B (en) Ring beam and annular corbel column reinforced connection joint construction method
CN109372129A (en) The novel full assembly concrete frame joint of one kind and its construction method
CN109372130A (en) The novel full assembly concrete shaped section steel frame node of one kind and its construction method
KR100565865B1 (en) Construction method of concrete arch bridge
CN105970993A (en) Underwater connection structure for precast piles and precast bearing platform, and construction method thereof
JP4104910B2 (en) How to build arch ribs for concrete arch bridges
JPH11117575A (en) Steel tower construction for transmission line and method thereof
JP4107179B2 (en) Construction method of steel structure
CN213682477U (en) Upper cover structure system applied to track operation line
CN215519210U (en) Assembled building based on mathematical computation
JPH08296209A (en) Method for reinforcing foundation part of elevated bridge
CN112922227B (en) Assembly type concrete main beam and secondary beam joint and construction method thereof
CN112095780A (en) Upper cover structure system applied to track operation line and implementation method thereof
CN209292868U (en) Precast assembly bridge piers with pile foundation
JP2004156388A (en) Construction method of arch structure, dome structure and its construction method
JPH01290806A (en) Construction method for bridge
JP2946074B2 (en) Large roof erection method
CN114892735B (en) In-situ processing method for quality defect of pile foundation of power transmission tower
CN205400119U (en) Inside replacement structure of existing building
CN104032894B (en) Frame column root structure and the method for generation thereof
CN215519163U (en) Connecting module for joint of multiple frame beams and stand columns of underground garage
JP3318717B2 (en) Construction method of PC cable stayed bridge
CN211775105U (en) Prefabricated column and beam column connecting structure comprising same
CN207878252U (en) Prefabricated assembled bridge
CN219157415U (en) Pier stud expansion joint fixing device

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040902

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20040902

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060413

A131 Notification of reasons for refusal

Effective date: 20060418

Free format text: JAPANESE INTERMEDIATE CODE: A131

A02 Decision of refusal

Effective date: 20060808

Free format text: JAPANESE INTERMEDIATE CODE: A02