JPH1088793A - Base form process and assembled reinforcing bars used therefor - Google Patents

Base form process and assembled reinforcing bars used therefor

Info

Publication number
JPH1088793A
JPH1088793A JP24670596A JP24670596A JPH1088793A JP H1088793 A JPH1088793 A JP H1088793A JP 24670596 A JP24670596 A JP 24670596A JP 24670596 A JP24670596 A JP 24670596A JP H1088793 A JPH1088793 A JP H1088793A
Authority
JP
Japan
Prior art keywords
reinforcing bar
foundation
assembled
bar
base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP24670596A
Other languages
Japanese (ja)
Inventor
Tamotsu Kawai
合 保 河
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kanegafuchi Chemical Industry Co Ltd
Original Assignee
Kanegafuchi Chemical Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kanegafuchi Chemical Industry Co Ltd filed Critical Kanegafuchi Chemical Industry Co Ltd
Priority to JP24670596A priority Critical patent/JPH1088793A/en
Publication of JPH1088793A publication Critical patent/JPH1088793A/en
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a base form process and assembled reinforcing bars, which allows base form members to be simply and surely arranged at predetermined positions, without they being caught by the assembled reinforcing bars and without causing any hindrance, when a concrete placing space is defined between forms. SOLUTION: In a base form process 300, a base form member 30 composed of an outer base form 302, an inner base form 301 and a separator 303 arranged between the forms so as to define a space therebetween, is set up so as to surround assembled reinforcing bars, and concrete is placed between the forms so as to form a footing. In this case, horizontal reinforcing bars 17 on rise-up reinforcing bars 18 are assembled at a position above the upper end position 122A of the footing and below a separator 303 position D lowermost of the base frame member 300, in a stand-up condition.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、コンクリート基礎
型枠工法及び当該工法に用いる組立鉄筋に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a concrete foundation formwork method and an assembling rebar used in the method.

【0002】[0002]

【従来の技術】従来より、一般的に木造建築物の基礎型
枠工法として、図12〜図14に示したように、下記に
示すような基礎型枠工法が用いられている。すなわち、
この工法では、予め掘削した根切り底である地面の上に
ランマを用いて割栗石101を突き固め、突き固められ
た割栗石101の上に、捨てコンクリート102を打設
する。そして、捨てコンクリート102の上面に、スペ
ーサ104を介して巾筋106、106を一定間隔に配
置した後、布筋108、108を巾筋106に対して直
交するように結束して格子状に組設して基礎鉄筋110
を配置する。この基礎鉄筋110の中央部の巾筋106
と布筋108との交差部位109、109に、基礎鉄筋
110に対して垂直な方向に縦筋112、112を結束
して立設した後、この縦筋112、112に対して直交
するように水平に横筋114、114を結束して、組立
鉄筋116を配筋する(図12参照)。この組立鉄筋1
16の配筋と平行して、布基礎120のフーチング12
2部分を打設するための一対の内側基礎型枠130及び
外側基礎型枠131を、組立鉄筋116を囲撓するよう
に対向するように立設して、セパレータ132、横バタ
134、フォームタイ(登録商標)136にて外方向に
拡がったり、内方に倒れないように緊結固定し、フーチ
ング122のためのコンクリート打設空間を形成して、
コンクリートを打設してフーチング122を形成する
(図13参照)。そして、フーチング122のコンクリ
ート打ちが完了した後、内側基礎型枠130及び外側基
礎型枠131を解体した後、前述したフーチング122
の型枠組立と同様にして、布基礎120の地中ばり上部
124の基礎型枠140、141を立設、緊結固定しコ
ンクリートを打設して、布基礎120の地中ばり上部1
24を形成することによって布基礎120を構築してい
る(図14参照)。
2. Description of the Related Art Conventionally, as shown in FIGS. 12 to 14, the following basic formwork method has been generally used as a basic formwork method for a wooden building. That is,
In this method, a splitter stone 101 is compacted using a rammer on the ground, which is a root excavated in advance, and a discarded concrete 102 is cast on the compacted stone 101. Then, the width reinforcements 106, 106 are arranged at regular intervals on the upper surface of the discarded concrete 102 via the spacer 104, and then the cloth reinforcements 108, 108 are bound so as to be orthogonal to the width reinforcement 106, and assembled in a lattice. Installed and basic reinforcement 110
Place. The width reinforcement 106 at the center of the basic reinforcement 110
The vertical bars 112, 112 are bundled and erected in the direction perpendicular to the base reinforcing bar 110 at the intersections 109, 109 between the reinforcing bars 108 and the reinforcing bars 108 so that the vertical bars 112, 112 are perpendicular to the vertical bars 112, 112. The horizontal bars 114 are tied horizontally to arrange the assembly reinforcing bars 116 (see FIG. 12). This rebar 1
16 and the footing 12 of the cloth foundation 120
A pair of inner base formwork 130 and outer base formwork 131 for casting the two parts are erected so as to oppose each other so as to surround the assembled reinforcing bar 116, and a separator 132, a horizontal flutter 134, and a foam tie are formed. (Registered trademark) 136 to secure the concrete placing space for the footing 122 by tightening and fixing so as not to spread outward or fall inward.
The footing 122 is formed by casting concrete (see FIG. 13). Then, after the concrete casting of the footing 122 is completed, the inner foundation formwork 130 and the outer foundation formwork 131 are disassembled, and the above-described footing 122 is removed.
In the same manner as in the formwork assembly, the foundation formwork 140, 141 of the underground beam upper portion 124 of the cloth foundation 120 is erected, tightly fixed, and concrete is cast, and the underground beam upper portion 1 of the fabric foundation 120 is mounted.
The fabric foundation 120 is constructed by forming 24 (see FIG. 14).

【0003】ところで、このような一連の基礎型枠工事
においては、土木作業員によるものと、型枠大工及び鉄
筋工などによる作業に分類され、いずれも熟練した技術
が必要となっている。すなわち、それぞれ特殊な技術を
必要とするので、根切り、ランマによる突き固め等の土
木作業は土木作業員が行い、型枠工事は型枠工が行い、
配筋工事などの鉄筋工が行うなどそれぞれ別々の熟練作
業員が行っているのが実状である。そのため、例えば、
型枠工が鉄筋工の作業を行うことは困難であり、昨今の
熟練した作業者が減少している建設業界にあっては、現
場によってこれらの作業者が不足しており、必要なとき
に専門職の作業者が現場にいないことが多々あり、代わ
りの作業者では作業が行うことができないので、その結
果工期の遅延をきたしてしまうなどの問題があった。
[0003] Incidentally, such a series of basic formwork works are classified into work by a civil engineer and work by a formwork carpenter and a reinforcing steelwork, and both require skilled skills. In other words, each requires a special technique, civil engineering work such as root cutting, ramming and the like is performed by civil engineering workers, formwork is performed by formwork,
Actually, each of them is performed by a different skilled worker, such as rebar construction work such as rebar construction work. So, for example,
It is difficult for formworkers to carry out rebar work, and in the construction industry where the number of skilled workers is decreasing these days, these workers are scarce at the site, and when necessary, In many cases, there is no professional worker on site, and work cannot be performed by a substitute worker. As a result, there has been a problem that the construction period is delayed.

【0004】このため、昨今では、図15に示したよう
に、巾筋206と布筋208とで格子状に溶接で組設し
た基礎鉄筋210と、縦筋212と横筋214とで溶接
にて組設された立ち上がり筋211とで構成され、基礎
鉄筋210の中央部の巾筋206と布筋208との交差
部位209、209に、基礎鉄筋210に対して垂直方
向に立設可能に、立ち上がり筋211を基礎鉄筋210
にバネ材を備えたクリップ部材213にて連結してなる
いわゆる組立基礎鉄筋200が用いられている。すなわ
ち、この組立基礎鉄筋200を用いれば、現場にて捨て
コンクリート102の上面に折り畳み状態の組立基礎鉄
筋200を配置した後、立ち上がり筋211を基礎鉄筋
210に対して垂直方向に立設するだけで組立鉄筋が施
工できるので、鉄筋工として熟練していない型枠工だけ
でも基礎型枠工事が施工できるので注目を浴びている。
For this reason, recently, as shown in FIG. 15, a base reinforcing bar 210 assembled by welding a width bar 206 and a cloth bar 208 in a grid pattern, and a vertical bar 212 and a horizontal bar 214 by welding. It is composed of the rising bars 211 assembled, and rises at intersections 209 and 209 between the width bars 206 and the cloth bars 208 at the center of the base reinforcing bars 210 so as to be able to stand vertically in relation to the base reinforcing bars 210. Reinforcing bar 211 to basic reinforcing bar 210
A so-called assembled basic reinforcing bar 200 connected by a clip member 213 provided with a spring material is used. That is, if this assembled basic reinforcing bar 200 is used, the folded up basic reinforcing bar 200 is disposed on the upper surface of the discarded concrete 102 at the site, and then the rising bars 211 are simply erected in the vertical direction with respect to the basic reinforcing bar 210. Since assembly rebars can be constructed, it has attracted attention because foundation formwork can be carried out only by unskilled formwork.

【0005】一方、このような布基礎を施工する場合、
寒冷地などでは、冬期において地面が80cm以上も凍
結する場合があり、地面の凍結によって布基礎が不均衡
に持ち上げられ、建築物の設計強度の狂いや破損の原因
にもなっている。従って、寒冷地において住宅の基礎を
施工する場合に、図16に示したように、基礎用型枠自
体を断熱性を有する樹脂発泡体などの合成樹脂で構成し
た打込み基礎型枠が用いられている。
On the other hand, when such a cloth foundation is constructed,
In a cold region, the ground may freeze more than 80 cm in the winter, and the freezing of the ground raises the cloth foundation imbalancedly, causing the design strength of the building to be out of order or causing breakage. Therefore, when a foundation for a house is constructed in a cold region, as shown in FIG. 16, a driving foundation form in which the foundation form itself is made of a synthetic resin such as a resin foam having heat insulating properties is used. I have.

【0006】[0006]

【発明が解決しようとする課題】ところで、前述したよ
うな断熱性を有する合成樹脂から構成した打込み基礎型
枠では、図16に示したように、一対の内側基礎型枠4
00と外側基礎型枠401をセパレータ432を介して
一定間隔離間して配置して布基礎のコンクリート打設空
間を形成したものである。しかしながら、この場合、セ
パレータ432、横バタ、フォームタイ436などを通
じて、外気の低温が布基礎のコンクリート部分又は建築
物の内側にまで伝わることになるので、断熱性が維持で
きないことになる。
By the way, as shown in FIG. 16, a pair of inner foundation forms 4 is used in a driving foundation form made of synthetic resin having heat insulation as described above.
The concrete foundation space 401 is formed by arranging the outer foundation formwork 401 and the outer foundation formwork 401 at a fixed interval with a separator 432 therebetween. However, in this case, the low temperature of the outside air is transmitted to the concrete portion of the cloth foundation or the inside of the building through the separator 432, the horizontal flap, the foam tie 436, and the like, so that the heat insulating property cannot be maintained.

【0007】そのため、昨今では、図17に示したよう
に、布基礎を打設するための合成樹脂の発泡体からなる
打ち込みタイプの内側基礎型枠301と外側基礎型枠3
02と、両型枠301、302を一定間隔離間するため
に両型枠の間に一体成形されたセパレータ303とから
なる打ち込みタイプの基礎型枠部材300を用いて、布
基礎を打設構成している。
For this reason, as shown in FIG. 17, recently, a driving-type inner base formwork 301 and an outer base formwork 3 made of a synthetic resin foam for setting a cloth base.
A fabric base is cast by using a driving-type base frame member 300 including a base member 02 and a separator 303 integrally formed between the two forms to separate the two forms 301 and 302 by a predetermined distance. ing.

【0008】しかしながら、図15に示したような基礎
型枠部材300では、セパレータ303の間隙304を
縫って縦筋及び横筋を組み立てていかなければならず、
非常に煩雑な作業となっていた。そこで、この基礎型枠
部材300を用いて、鉄筋組立の省力化を図るために、
図15に示したような組立基礎鉄筋200を用いること
が考えられるが、この場合、基礎型枠工事を行おうとす
れば、現場にて捨てコンクリート102の上面に折り畳
み状態の組立基礎鉄筋200を配置し、立ち上がり筋2
11を基礎鉄筋210に対して垂直方向に立設し、基礎
型枠部材300を上方より捨てコンクリート102の上
に立設しようとする場合に、セパレータ303が組立基
礎鉄筋200の横筋214につかえることになるため、
この基礎型枠部材300に従来の組立基礎鉄筋200を
用いることは不可能であった。
However, in the basic form member 300 as shown in FIG. 15, the vertical streaks and the horizontal streaks must be assembled by sewing the gap 304 of the separator 303.
It was a very complicated task. Therefore, in order to save labor in assembling the rebar using the basic form member 300,
Although it is conceivable to use the assembled basic reinforcing bar 200 as shown in FIG. 15, in this case, if the foundation formwork is to be performed, the folded assembled basic reinforcing bar 200 is placed on the upper surface of the discarded concrete 102 at the site. And riser 2
11 is erected in the vertical direction with respect to the base rebar 210, and when the base form member 300 is to be discarded from above and is to be erected on the concrete 102, the separator 303 can be used as the horizontal bar 214 of the assembled base rebar 200. To become
It was impossible to use the conventional assembled base reinforcing bar 200 for the base form member 300.

【0009】本発明は、このような現状に鑑み、外側基
礎型枠と内側基礎型枠と、両型枠を一定間隔離間するた
めに両型枠の間に配設されたセパレータとからなる基礎
型枠部材を、組立基礎鉄筋を囲撓するように立設して、
型枠間にコンクリート打設空間を形成する際にも、組立
基礎鉄筋につかえたりすることなく、何ら支障をきたす
ことなく、基礎型枠部材を簡単、確実に所定位置に配置
できる基礎型枠工法、及びそのための組立基礎鉄筋を提
供することを目的とする。
In view of the above situation, the present invention provides a foundation comprising an outer foundation form, an inner foundation form, and a separator disposed between the two forms to separate the two forms by a certain distance. Formwork members are erected to surround the assembling base rebar,
Basic formwork method that can easily and securely place the basic formwork members in the specified position without forming the concrete placing space between the formwork and holding the assembly base rebar without any trouble. , And an assembling base reinforcing bar therefor.

【0010】[0010]

【課題を解決するための手段】本発明は、前述したよう
な従来技術における課題及び目的を達成するために発明
なされたものであって、本発明の基礎型枠工法は、巾筋
と布筋とで格子状に組設した基礎鉄筋と、縦筋と横筋と
で組設され、前記基礎鉄筋に対して垂直方向に立設可能
に基礎鉄筋に連結してなる立ち上がり筋とで構成される
組立基礎鉄筋を、立ち上がり筋が立設状態となるように
捨てコンクリート上に配筋するとともに、外側基礎型枠
と内側基礎型枠と、両型枠を一定間隔離間するために両
型枠の間に配設されたセパレータとからなる基礎型枠部
材を、前記組立基礎鉄筋を囲撓するように立設した後、
前記型枠間にコンクリートを打設して布基礎を構築する
基礎型枠工法において、前記組立基礎鉄筋の立ち上がり
筋の横筋を、立設状態でフーチング上端位置よりも上方
で、且つ前記基礎型枠部材の最下方のセパレータ位置よ
りも下方に位置するように組設した組立基礎鉄筋を用い
ることを特徴とする基礎型枠工法である。
SUMMARY OF THE INVENTION The present invention has been made in order to achieve the above-mentioned objects and objects of the prior art. An assembling composed of a base reinforcing bar assembled in a grid pattern with a vertical bar and a horizontal bar, and a rising bar connected to the basic reinforcing bar so as to be able to be erected vertically with respect to the basic reinforcing bar. Place the reinforcing bars on the concrete so that the rising bars are in the standing state, and place them between the outer and inner foundation forms and between the two forms to separate them by a certain distance. After erecting the base form member comprising the disposed separator so as to surround the assembled base rebar,
In a foundation formwork method of casting a concrete between the formworks to construct a cloth foundation, a horizontal streak of a rising streak of the assembling base reinforcing bar is located above an upper end position of a footing in an upright state, and A foundation formwork method characterized by using an assembling foundation rebar assembled so as to be located below a lowermost separator position of a member.

【0011】また、本発明の組立基礎鉄筋は、巾筋と布
筋とで格子状に組設した基礎鉄筋と、縦筋と横筋とで組
設され、前記基礎鉄筋に対して垂直方向に立設可能に基
礎鉄筋に連結してなる立ち上がり筋とで構成される組立
基礎鉄筋であって、立ち上がり筋の横筋を、立設状態で
フーチング上端位置よりも上方で、且つ基礎型枠部材の
最下方のセパレータ位置よりも下方に位置するように組
設したことを特徴とする組立基礎鉄筋である。
[0011] Further, the assembled basic reinforcing bar of the present invention is composed of a basic reinforcing bar assembled in a grid pattern with a width reinforcing bar and a cloth reinforcing bar, and a vertical reinforcing bar and a horizontal reinforcing bar, and stands upright in a direction perpendicular to the basic reinforcing bar. An assembling base reinforcing bar comprising a rising bar connected to a base reinforcing bar so as to be able to be set up, wherein a horizontal streak of the rising bar is located above an upper end position of a footing in a standing state, and a lowermost portion of a base form member. Characterized in that it is installed below the separator position of (1).

【0012】このような、組立基礎鉄筋を用いた基礎型
枠工法では、立ち上がり筋の横筋の取付位置は、立ち上
がり筋を基礎鉄筋に対して垂直方向に立設した状態で、
フーチング上端位置よりも上方に位置し、且つ基礎型枠
部材の最下方のセパレータ位置よりも下方に位置するす
るように組設されているので、組立基礎鉄筋を囲撓する
ように、基礎型枠部材を上方より捨てコンクリートの上
に配置する場合に、セパレータが組立基礎鉄筋の立ち上
がり筋の横筋につかえることがない。従って、基礎型枠
部材を上方より捨てコンクリート上の所定位置に簡単容
易に立設することができるので、コンクリート打設空間
を確実に形成でき、コンクリートを打設して布基礎を構
築することができる。
[0012] In the foundation form method using the assembled basic reinforcing bar, the mounting position of the horizontal reinforcing bar is set in a state where the vertical reinforcing bar is erected in the vertical direction with respect to the basic reinforcing bar.
Since it is installed so as to be located above the upper end position of the footing and below the lowermost separator position of the base form member, the base form is bent so as to surround the assembled base reinforcing bar. When the member is disposed on the concrete discarded from above, the separator does not get stuck on the horizontal streaks of the rising bars of the assembling base rebar. Therefore, since the foundation form member can be easily and erected at a predetermined position on the concrete by discarding the foundation form member from above, a concrete casting space can be reliably formed, and concrete can be cast to construct a cloth foundation. it can.

【0013】さらに、本発明の基礎型枠工法は、前述し
た基礎型枠工法において、前記組立基礎鉄筋の立ち上が
り筋の横筋を省略して、縦筋のみを基礎鉄筋に立設可能
に連結してなる組立基礎鉄筋を用いることを特徴とする
基礎型枠工法である。
Further, according to the foundation formwork method of the present invention, in the above-mentioned foundation formwork method, the horizontal bars of the rising bars of the assembled base bars are omitted, and only the vertical bars are connected to the base bars so as to be erected. This is a foundation formwork method characterized by using an assembling foundation rebar.

【0014】また、本発明の組立基礎鉄筋は、巾筋と布
筋とで格子状に組設した基礎鉄筋と、縦筋のみを基礎鉄
筋に対して垂直方向に立設可能に連結した立ち上がり筋
とで構成したことを特徴とする組立基礎鉄筋である。
[0014] Further, the assembled basic reinforcing bar of the present invention comprises a basic reinforcing bar assembled in a lattice shape with a width reinforcing bar and a cloth reinforcing bar, and a rising reinforcing bar in which only the vertical reinforcing bars are connected so as to be able to be erected in a direction perpendicular to the basic reinforcing bars. And an assembling basic reinforcing bar.

【0015】さらに、本発明の基礎型枠工法は、巾筋と
布筋とで格子状に組設した基礎鉄筋と、前記巾筋と布筋
の連結位置に設けられた縦筋装着部とで構成される組立
基礎鉄筋を、捨てコンクリート上に配筋するとともに、
前記基礎鉄筋の縦筋装着部材に、縦筋を装着して基礎用
鉄筋を構設し、外側基礎型枠と内側基礎型枠と、両型枠
を一定間隔離間するために両型枠の間に配設されたセパ
レータとからなる基礎型枠部材を、前記組立基礎鉄筋を
囲撓するように立設した後、前記型枠間にコンクリート
を打設して布基礎を構築することを特徴とする基礎型枠
工法である。
Further, the foundation formwork method of the present invention comprises a base reinforcing bar assembled in a lattice shape with a width bar and a reinforcing bar, and a vertical bar mounting portion provided at a connecting position of the width bar and the reinforcing bar. While arranging the assembling foundation rebar constructed on discarded concrete,
A vertical bar is attached to the vertical bar mounting member of the basic reinforcing bar to form a reinforcing bar, and the outer and inner base frames and the inner and lower base frames are separated from each other by a certain distance to separate the both frames. A base form member consisting of a separator and a separator disposed on the base foundation member is erected so as to surround the assembled base reinforcing bar, and then a concrete foundation is cast between the form forms to construct a cloth base. This is the basic formwork method.

【0016】また、本発明の組立基礎鉄筋は、巾筋と布
筋とで格子状に組設した基礎鉄筋と、前記巾筋と布筋の
連結位置に設けられた縦筋装着部とで構成される組立基
礎鉄筋である。
Further, the assembled basic reinforcing bar of the present invention comprises a basic reinforcing bar assembled in a lattice shape with a width reinforcing bar and a reinforcing bar, and a vertical bar mounting portion provided at a connecting position of the width reinforcing bar and the reinforcing bar. This is the basic rebar to be assembled.

【0017】これらの組立基礎鉄筋を用いた基礎型枠工
法では、立ち上がり筋を構成する横筋が存在しないの
で、組立基礎鉄筋を囲撓するように、基礎型枠部材を上
方より捨てコンクリートの上に配置する場合に、セパレ
ータが組立基礎鉄筋の立ち上がり筋に全くつかえること
がない。従って、基礎型枠部材を上方より捨てコンクリ
ート上の所定位置によりいっそう簡単容易に立設するこ
とができるので、コンクリート打設空間を確実に形成で
き、コンクリートを打設して布基礎を構築することがで
きる。
In the foundation form method using these assembled foundation rebars, since there is no horizontal streak constituting a rising streak, the foundation form member is discarded from above so as to surround the assembled foundation rebar and is placed on concrete. When arranging, the separator does not come into contact with the rising bars of the assembling base rebar at all. Therefore, the foundation form member can be discarded from above and more easily and easily erected at a predetermined position on the concrete, so that the concrete placing space can be reliably formed, and the cloth foundation is constructed by placing concrete. Can be.

【0018】[0018]

【発明の実施の形態】本発明の組立基礎鉄筋では、立ち
上がり筋を立設状態でその立設状態を保持するクランプ
部材を付設するのが、組立基礎鉄筋を固定できるので好
ましい。
BEST MODE FOR CARRYING OUT THE INVENTION In the assembled basic reinforcing bar of the present invention, it is preferable to provide a clamp member for holding the standing upright in an upright state, since the assembled basic reinforcing bar can be fixed.

【0019】また、本発明の組立基礎鉄筋では、前記縦
筋装着部が、縦筋を挿着可能なパイプ部材又は縦筋を挿
着可能な孔部を有する部材で構成されているのが好まし
い。さらに、基礎型枠部材は、特に限定されるものでは
なく、非発泡合成樹脂でも良いが、断熱性の観点からす
れば、発泡合成樹脂が好ましく、例えば、発泡ポリスチ
レン、発泡ポリエチレン、発泡ポリプロピレン、発泡ポ
リウレタンなどが使用可能であり、これらの発泡成形が
可能な樹脂を、例えば、5〜80倍程度に発泡させなが
ら所望の形状に形成すれば、樹脂発泡体の中に優れた独
立気泡が形成され、優れた断熱性を示すようになる。
Further, in the assembled basic reinforcing bar of the present invention, it is preferable that the vertical bar mounting portion is constituted by a pipe member into which the vertical bar can be inserted or a member having a hole through which the vertical bar can be inserted. . Further, the base form member is not particularly limited, and may be a non-foamed synthetic resin. However, from the viewpoint of heat insulation, a foamed synthetic resin is preferable. For example, foamed polystyrene, foamed polyethylene, foamed polypropylene, foamed foam, Polyurethane and the like can be used, and if these foamable resins are formed into a desired shape while foaming them, for example, about 5 to 80 times, excellent closed cells are formed in the resin foam. , And exhibit excellent heat insulating properties.

【0020】[0020]

【実施例】以下、本発明の実施例を図面に基づいてより
詳細に説明する。図1は、本発明の基礎型枠工法に用い
る組立基礎鉄筋の第1の実施例の斜視図、図2はクラン
プ部材の拡大斜視図、図3は、図1の組立基礎鉄筋を用
いて布基礎を構築する本発明の基礎型枠工法を説明する
分解斜視図、図4は、図3の基礎型枠工法の組み立てた
状態を示す斜視図である。
Embodiments of the present invention will be described below in detail with reference to the drawings. FIG. 1 is a perspective view of a first embodiment of an assembled basic reinforcing bar used in the foundation formwork method of the present invention, FIG. 2 is an enlarged perspective view of a clamp member, and FIG. 3 is a cloth using the assembled basic reinforcing bar of FIG. FIG. 4 is an exploded perspective view illustrating a foundation formwork method of the present invention for constructing a foundation, and FIG. 4 is a perspective view showing an assembled state of the foundation formwork method of FIG.

【0021】図1において、組立基礎鉄筋10は、複数
の一定間隔離間した巾筋11と、巾筋11に対して直交
するように、格子状に組設した3本の布筋12A〜12
Cとからなる基礎鉄筋13を備えている。この場合、中
央の布筋12B以外の両端の端部布筋12Aと12Cと
巾筋11とは溶接にて固着されている。そして、中央の
布筋12Bの巾筋11との交差位置14で、縦筋15が
布筋12Bに溶接にて固着されており、交差位置14に
おいて、中央の布筋12、巾筋11及び縦筋15を、バ
ネ材などを備えたクリップ部材16にて連結することに
よって、縦筋15が中央の布筋12Bを支点として、矢
印A方向に折り畳み、拡開自在に構成されている。ま
た、この縦筋15に直交するように、1本の横筋17が
溶接にて固着され組設されており、この縦筋15と横筋
17とで立ち上がり筋18を構成している。このよう
に、立ち上がり筋18は、交差位置14を支点として、
基礎鉄筋13に対して垂直方向に立設可能に構成されて
いる。
In FIG. 1, an assembling basic reinforcing bar 10 is composed of a plurality of width bars 11 which are separated from each other at a fixed interval, and three cloth reinforcing bars 12A to 12A which are assembled in a lattice so as to be orthogonal to the width bars 11.
C is provided. In this case, the end reinforcements 12A and 12C at both ends other than the central reinforcement 12B and the width reinforcement 11 are fixed by welding. A vertical bar 15 is fixed to the reinforcing bar 12B by welding at a position 14 where the central reinforcing bar 12B and the width bar 11 intersect. At the crossing position 14, the central reinforcing bar 12, the width bar 11 and the vertical By connecting the streaks 15 with a clip member 16 provided with a spring material or the like, the vertical streaks 15 are folded in the direction of arrow A with the center cloth streaks 12B as a fulcrum, and are configured to be freely expandable. Further, one horizontal streak 17 is fixedly attached by welding so as to be orthogonal to the vertical streak 15, and the vertical streak 15 and the horizontal streak 17 constitute a rising streak 18. In this way, the rising line 18 is set with the intersection position 14 as a fulcrum.
It is configured to be able to be erected vertically with respect to the base reinforcing bar 13.

【0022】また、巾筋11には、中央の布筋12Bと
の交差位置14に、立ち上がり筋18を基礎鉄筋13に
対して垂直方向に立設した際に、立ち上がり筋18を基
礎鉄筋13に対して固定するためのクランプ部材19が
付設されている。このクランプ部材19は、図3に示し
たように、巾筋11に垂直に固定された略コの字状のク
ランプ部材本体19Aと、クランプ部材本体19Aの上
部先端部に設けられた縦筋15を固定するためのクラン
プ部19Bから構成されている。なお、このクランプ部
材19としては、金属製であっても、合成樹脂製であっ
ても構わない。また、本実施例の場合には、クランプ部
材19を巾筋11に付設したが、立ち上がり筋18の縦
筋15に設けて、巾筋11をクランプする構造であって
もよく、このクランプ部材の形状も種々変更可能であ
る。
When the rising bar 18 is erected perpendicularly to the base reinforcing bar 13 at the intersection 14 with the central reinforcing bar 12B, the rising bar 18 is attached to the base reinforcing bar 13. A clamp member 19 is provided for fixing the clamp member. As shown in FIG. 3, the clamp member 19 includes a substantially U-shaped clamp member main body 19A fixed vertically to the width streak 11, and a vertical streak 15 provided at the upper end of the clamp member main body 19A. Is constituted by a clamp portion 19B for fixing the. Note that the clamp member 19 may be made of metal or synthetic resin. Further, in the case of the present embodiment, the clamp member 19 is attached to the width streak 11, but a structure in which the clamp member 19 is provided to the vertical streak 15 of the rising streak 18 to clamp the width streak 11 may be used. The shape can also be variously changed.

【0023】一方、立ち上がり筋18の横筋17の取付
位置は、基礎鉄筋13に対して垂直方向に立設した状態
で、フーチング上端位置よりも上方で、且つ後述するよ
うに、基礎型枠部材の最下方のセパレータ位置よりも下
方に位置するように組設されている。
On the other hand, the mounting position of the horizontal bar 17 of the rising bar 18 is set above the upper end position of the footing in a state of standing upright with respect to the basic reinforcing bar 13 and, as will be described later, of the base frame member. It is installed so as to be located below the lowermost separator position.

【0024】なお、本実施例の場合に、布筋12の数を
3本とし、巾筋11と中央の布筋12Bとの交差位置1
4に、一つの立ち上がり筋18を基礎鉄筋13に対して
立設可能に連結したが、この数は何ら限定されるもので
はなく、例えば、布筋12の数を4本とし、中央の2本
の布筋と巾筋との2箇所の交差部位に、それぞれ立ち上
がり筋18を立設可能に連結してもよい(以下の実施例
においても同様である。
In the case of the present embodiment, the number of the reinforcing bars 12 is three, and the intersection 1 between the width bar 11 and the central reinforcing bar 12B is 1
In FIG. 4, one rising bar 18 is connected to the base reinforcing bar 13 so as to be able to be erected, but the number is not limited at all. For example, the number of the reinforcing bars 12 is four, and the center two bars are provided. The rising streaks 18 may be respectively connected to the two intersections of the cloth streaks and the width stitches so as to be able to be erected (the same applies to the following embodiments).

【0025】このように構成される本発明の組立基礎鉄
筋を用いて布基礎を構築する本発明の基礎型枠工法を図
3〜図4に基づいて以下に説明する。先ず、捨てコンク
リート102の上面に、スペーサ104を介して折り畳
み状態の組立基礎鉄筋10を配置した後、立ち上がり筋
18を、交差位置14を支点として、基礎鉄筋13に対
して垂直方向に立設して、中央の布筋12Bとの交差位
置14に設けられたクランプ部材19のクランプ部19
Bに、立ち上がり筋18の縦筋15を固定することによ
って、立ち上がり筋18を基礎鉄筋13に対して固定す
る。
A foundation formwork method of the present invention for constructing a cloth foundation using the assembled foundation reinforcing bar of the present invention thus configured will be described below with reference to FIGS. First, after the assembled basic reinforcing bar 10 in the folded state is disposed on the upper surface of the discarded concrete 102 via the spacer 104, the rising bars 18 are erected vertically with respect to the basic reinforcing bar 13 with the intersection position 14 as a fulcrum. Thus, the clamp portion 19 of the clamp member 19 provided at the intersection 14 with the central reinforcing bar 12B.
By fixing the vertical bar 15 of the rising bar 18 to B, the rising bar 18 is fixed to the basic reinforcing bar 13.

【0026】その後、組立基礎鉄筋10を囲撓するよう
に、対向する合成樹脂発泡体からなる打ち込みタイプの
内側基礎型枠301と外側基礎型枠302と、両型枠3
01、302を一定間隔離間するために両型枠の間に一
体成形されたセパレータ303とからなる打ち込みタイ
プの基礎型枠部材300を上方より捨てコンクリート1
02の上に配置する。そして、これにより、フーチング
122及び地中ばり上部124のためのコンクリート打
設空間Cを形成して、さらにこの横筋17の上方に適宜
横筋(図示せず)を常法にしたがって配筋した後、コン
クリートを打設して布基礎120を構築する。この際、
立ち上がり筋18の横筋17の取付位置は、立ち上がり
筋18を基礎鉄筋13に対して垂直方向に立設した状態
で、フーチング上端位置122Aよりも上方に位置し、
且つ基礎型枠部材300の最下方のセパレータ位置Dよ
りも下方に位置するするように組設されているので、組
立基礎鉄筋10を囲撓するように、基礎型枠部材300
を上方より捨てコンクリート102の上に配置する場合
に、セパレータ303が組立基礎鉄筋10の立ち上がり
筋18の横筋17につかえることがない。従って、基礎
型枠部材300を上方より捨てコンクリート102上の
所定位置に簡単容易に立設することができるので、コン
クリート打設空間Cを確実に形成でき、コンクリートを
打設して布基礎120を構築することができる。
Thereafter, the inner base formwork 301 and the outer base formwork 302 of the drive-in type made of synthetic resin foam facing each other so as to bend and surround the assembling base rebar 10, and the two formworks 3.
And a separator 303 integrally formed between the two molds in order to keep the first and second molds 01 and 302 apart from each other.
02. Then, a concrete placing space C for the footing 122 and the underground beam upper portion 124 is thereby formed, and after appropriately arranging a horizontal bar (not shown) above the horizontal bar 17 according to a conventional method, The cloth foundation 120 is constructed by casting concrete. On this occasion,
The mounting position of the horizontal bar 17 of the rising bar 18 is located above the footing upper end position 122A in a state where the rising bar 18 is erected in the vertical direction with respect to the base reinforcing bar 13,
And since it is assembled so as to be located below the lowermost separator position D of the base form member 300, the base form member 300 is bent so as to surround the assembled base reinforcing bar 10.
Is disposed on the concrete 102 which is discarded from above, the separator 303 does not get stuck on the horizontal streak 17 of the rising streak 18 of the assembling base reinforcing bar 10. Therefore, since the foundation form member 300 can be easily and erected at a predetermined position on the concrete 102 by throwing away from above, the concrete placing space C can be reliably formed, and the concrete foundation is cast to form the cloth foundation 120. Can be built.

【0027】なお、基礎型枠部材300は、特に限定さ
れるものではないが、非発泡合成樹脂でも良いが、断熱
性の観点からすれば、発泡合成樹脂が好ましく、例え
ば、発泡ポリスチレン、発泡ポリエチレン、発泡ポリプ
ロピレン、発泡ポリウレタンなどが使用可能であり、こ
れらの発泡成形が可能な樹脂を、例えば、5〜80倍程
度に発泡させながら所望の形状に形成すれば、樹脂発泡
体の中に優れた独立気泡が形成され、優れた断熱性を示
すようになる。
The base frame member 300 is not particularly limited, but may be a non-foamed synthetic resin. However, from the viewpoint of heat insulation, a foamed synthetic resin is preferable. , Foamed polypropylene, foamed polyurethane, and the like can be used. If these foamable resins are formed into a desired shape while being foamed, for example, about 5 to 80 times, an excellent resin foam is obtained. Closed cells are formed, and exhibit excellent heat insulating properties.

【0028】図5は、本発明の基礎型枠工法に用いる組
立基礎鉄筋の第2の実施例の斜視図、図6は、図5の組
立基礎鉄筋を用いて布基礎を構築する本発明の基礎型枠
工法を説明する分解斜視図、図7は、図6の基礎型枠工
法の組み立てた状態を示す斜視図である。
FIG. 5 is a perspective view of a second embodiment of an assembled basic reinforcing bar used in the foundation formwork method of the present invention. FIG. 6 is a perspective view of a cloth foundation constructed by using the assembled basic reinforcing bar of FIG. FIG. 7 is an exploded perspective view for explaining the basic form method, and FIG. 7 is a perspective view showing an assembled state of the basic form method of FIG.

【0029】この実施例の組立基礎鉄筋は、図1に示し
た組立基礎鉄筋と基本的には同様な構成であり、同一の
構成部材には同一の参照番号を付している。この実施例
の組立基礎鉄筋10では、第1の実施例において、立ち
上がり筋18を構成する横筋17を省略して縦筋15の
みで立ち上がり筋18を構成して、基礎鉄筋13に立設
可能に連結した点が相違する。
The assembled basic reinforcing bar of this embodiment has basically the same configuration as the assembled basic reinforcing bar shown in FIG. 1, and the same components are denoted by the same reference numerals. In the assembled basic reinforcing bar 10 of this embodiment, the horizontal reinforcing bar 17 constituting the rising bar 18 is omitted and the vertical bar 15 alone forms the rising bar 18 in the first embodiment, so that the standing reinforcing bar 18 can be erected on the basic reinforcing bar 13. The difference is that they are linked.

【0030】このように構成される本発明の組立基礎鉄
筋を用いて布基礎を構築する基礎型枠工法を図6〜図7
に基づいて以下に説明する。先ず、捨てコンクリート1
02の上面に、スペーサ104を介して折り畳み状態の
組立基礎鉄筋10を配置した後、立ち上がり筋18を、
交差位置14を支点として、基礎鉄筋13に対して垂直
方向に立設して、中央の布筋12Bとの交差位置14に
設けられたクランプ部材19のクランプ部19Bに、立
ち上がり筋18の縦筋15を固定することによって、立
ち上がり筋18を基礎鉄筋13に対して固定する。
FIGS. 6 and 7 show a foundation formwork method for constructing a cloth foundation using the assembled foundation rebar of the present invention thus constructed.
This will be described below based on First, discarded concrete 1
After disposing the assembled basic reinforcing bar 10 in the folded state on the upper surface of the base member 02 via the spacer 104, the rising bar 18 is
With the crossing position 14 as a fulcrum, the vertical streak of the upright streak 18 is provided on the clamp portion 19B of the clamp member 19 provided at the crossing position 14 with the central reinforcing bar 12B by being erected in the vertical direction with respect to the basic reinforcing bar 13. By fixing 15, the rising bars 18 are fixed to the base reinforcing bar 13.

【0031】その後、組立基礎鉄筋10を囲撓するよう
に、対向する合成樹脂発泡体からなる打ち込みタイプの
内側基礎型枠301と外側基礎型枠302と、両型枠3
01、302を一定間隔離間するために両型枠の間に一
体成形されたセパレータ303とからなる打ち込みタイ
プの基礎型枠部材300を上方より捨てコンクリート1
02の上に配置する。そして、これにより、フーチング
122及び地中ばり上部124のためのコンクリート打
設空間Cを形成して、さらに適宜横筋(図示せず)を常
法にしたがって配筋した後、コンクリートを打設して布
基礎120を構築する。この際、立ち上がり筋18に
は、第1の実施例とは相違して、横筋17が存在しない
ので、組立基礎鉄筋10を囲撓するように、基礎型枠部
材300を上方より捨てコンクリート102の上に配置
する場合に、セパレータ303が組立基礎鉄筋10の立
ち上がり筋18に全くつかえることがない。従って、第
1の実施例に比較して、基礎型枠部材300を上方より
捨てコンクリート102上の所定位置によりいっそう簡
単容易に立設することができるので、コンクリート打設
空間Cを確実に形成でき、コンクリートを打設して布基
礎120を構築することができる。
Thereafter, the inner base formwork 301 and the outer base formwork 302 of the driving type made of synthetic resin foam facing each other so as to deflect the assembled base rebar 10, and the two formworks 3.
And a separator 303 integrally formed between the two molds in order to keep the first and second molds 01 and 302 apart from each other.
02. Thus, a concrete placing space C for the footing 122 and the underground beam upper portion 124 is formed, and after appropriately arranging horizontal streaks (not shown) according to a conventional method, concrete is cast. Build the cloth foundation 120. At this time, unlike the first embodiment, the rising bars 18 do not have the horizontal bars 17, so that the foundation form member 300 is discarded from above so as to bend the concrete foundation 102 so as to surround the assembled foundation reinforcing bar 10. In the case where it is arranged on the upper side, the separator 303 does not come into contact with the rising bar 18 of the assembled basic reinforcing bar 10 at all. Therefore, as compared with the first embodiment, the foundation form member 300 can be more easily and easily erected at a predetermined position on the concrete 102 by discarding the concrete form from above, so that the concrete placing space C can be reliably formed. , Concrete can be cast to build the fabric foundation 120.

【0032】図8は、本発明の基礎型枠工法に用いる組
立基礎鉄筋の第3の実施例の斜視図、図9は、図8の組
立基礎鉄筋を用いて布基礎を構築する本発明の基礎型枠
工法を説明する分解斜視図、図10は、図9の基礎型枠
工法の組み立てた状態を示す斜視図である。
FIG. 8 is a perspective view of a third embodiment of an assembling foundation reinforcing bar used in the foundation formwork method of the present invention. FIG. 9 is a perspective view of a cloth foundation using the assembling foundation reinforcing bar of FIG. FIG. 10 is an exploded perspective view illustrating the basic form method, and FIG. 10 is a perspective view showing an assembled state of the basic form method of FIG.

【0033】この実施例の組立基礎鉄筋は、図1に示し
た組立基礎鉄筋と基本的には同様な構成であり、同一の
構成部材には同一の参照番号を付している。この実施例
の組立基礎鉄筋10では、第1の実施例において、立ち
上がり筋18を構成する横筋17を省略するとともに、
巾筋11と中央の布筋12Bとの交差位置14に、縦筋
15からなる立ち上がり筋18を基礎鉄筋13に対して
垂直方向に挿入して立設固定するために、パイプ部材か
ら構成される縦筋装着部30を設けてあり、着脱自在な
縦筋15のみで立ち上がり筋18を構成した点が相違す
る。なお、このパイプ部材の長さは特に限定されるもの
ではなく、また、このパイプ部材の材質も、例えば、金
属製、合成樹脂など種々変更可能である。
The assembled basic reinforcing bar of this embodiment has basically the same configuration as the assembled basic reinforcing bar shown in FIG. 1, and the same components are denoted by the same reference numerals. In the assembled basic reinforcing bar 10 of this embodiment, the horizontal bars 17 constituting the rising bars 18 are omitted in the first embodiment.
At the crossing position 14 between the width reinforcement 11 and the central cloth reinforcement 12B, a rising member 18 composed of a vertical line 15 is vertically inserted into the foundation reinforcing bar 13 and is vertically fixed to the base reinforcing bar 13 to be erected and fixed. A different point is that a vertical streak attaching portion 30 is provided, and a stand-up streak 18 is constituted only by a detachable vertical streak 15. The length of the pipe member is not particularly limited, and the material of the pipe member can be variously changed, for example, made of metal or synthetic resin.

【0034】このように構成される本発明の組立基礎鉄
筋を用いて布基礎を構築する基礎型枠工法を図9〜図1
0に基づいて以下に説明する。先ず、捨てコンクリート
102の上面に、スペーサ104を介して、巾筋11と
布筋12A〜12Cとからなる基礎鉄筋13を配置した
後、縦筋15を縦筋装着部30に挿入して、基礎鉄筋1
3に対して垂直方向に立設して、縦筋15からなる立ち
上がり筋18を基礎鉄筋13に対して固定して、組立基
礎鉄筋10を組み立てる。
FIGS. 9 to 1 show a foundation formwork method for constructing a cloth foundation using the assembled basic reinforcing bar of the present invention constructed as described above.
0 will be described below. First, after the base reinforcing bar 13 composed of the width bar 11 and the cloth bars 12A to 12C is arranged on the upper surface of the discarded concrete 102 via the spacer 104, the vertical bar 15 is inserted into the vertical bar mounting portion 30, and Reinforcing bar 1
3, the upright bar 18 composed of the vertical bar 15 is fixed to the base bar 13, and the assembled base bar 10 is assembled.

【0035】その後、組立基礎鉄筋10を囲撓するよう
に、対向する合成樹脂発泡体からなる打ち込みタイプの
内側基礎型枠301と外側基礎型枠302と、両型枠3
01、302を一定間隔離間するために両型枠の間に一
体成形されたセパレータ303とからなる打ち込みタイ
プの基礎型枠部材300を上方より捨てコンクリート1
02の上に配置する。そして、これにより、フーチング
122及び地中ばり上部124のためのコンクリート打
設空間Cを形成して、さらに適宜横筋(図示せず)を常
法にしたがって配筋した後、コンクリートを打設して布
基礎120を構築する。この際、立ち上がり筋18に
は、第1の実施例とは相違して、横筋17が存在しない
ので、組立基礎鉄筋10を囲撓するように、基礎型枠部
材300を上方より捨てコンクリート102の上に配置
する場合に、セパレータ303が組立基礎鉄筋10の立
ち上がり筋18に全くつかえることがない。従って、本
実施例においても第1の実施例に比較して、基礎型枠部
材300を上方より捨てコンクリート102上の所定位
置によりいっそう簡単容易に立設することができるの
で、コンクリート打設空間Cを確実に形成でき、コンク
リートを打設して布基礎120を構築することができ
る。
Thereafter, the inner base formwork 301 and the outer base formwork 302 of the drive-in type made of synthetic resin foam facing each other so as to deflect the assembled base reinforcing bar 10 and the two formworks 3.
And a separator 303 integrally formed between the two molds in order to keep the first and second molds 01 and 302 apart from each other.
02. Thus, a concrete placing space C for the footing 122 and the underground beam upper portion 124 is formed, and after appropriately arranging horizontal streaks (not shown) according to a conventional method, concrete is cast. Build the cloth foundation 120. At this time, unlike the first embodiment, the rising bars 18 do not have the horizontal bars 17, so that the foundation form member 300 is discarded from above so as to bend the concrete foundation 102 so as to surround the assembled foundation reinforcing bar 10. In the case where it is arranged on the upper side, the separator 303 does not come into contact with the rising bar 18 of the assembled basic reinforcing bar 10 at all. Therefore, also in this embodiment, compared with the first embodiment, the base form member 300 can be more easily and easily erected at a predetermined position on the concrete 102 by discarding the concrete form from above. Can be reliably formed, and the cloth foundation 120 can be constructed by casting concrete.

【0036】図11は、本発明の基礎型枠工法に用いる
組立基礎鉄筋の第4の実施例の斜視図である。この実施
例の組立基礎鉄筋は、図6に示した第3の実施例の組立
基礎鉄筋と基本的には同様な構成であり、同一の構成部
材には同一の参照番号を付している。
FIG. 11 is a perspective view of a fourth embodiment of an assembled basic reinforcing bar used in the foundation formwork method of the present invention. The assembled basic reinforcing bar of this embodiment has basically the same configuration as the assembled basic reinforcing bar of the third embodiment shown in FIG. 6, and the same components are denoted by the same reference numerals.

【0037】この実施例の組立基礎鉄筋10では、第3
の実施例において、縦筋15からなる立ち上がり筋18
を基礎鉄筋13に対して垂直方向に挿入して立設固定す
る縦筋装着部30を、11と中央の布筋12Bとの交差
位置14に、立ち上がり筋18を基礎鉄筋13に対して
垂直方向に挿入して立設固定するための孔部32を有す
る円環状部材からなる縦筋装着部30とした点が相違す
る。なお、本実施例の場合には、別の部材からなる縦筋
装着部30を用いたが、例えば、巾筋若しくは布筋を屈
曲して孔部を構成することも可能である。また、このよ
うに構成される本発明の組立基礎鉄筋を用いて布基礎を
構築する基礎型枠工法は、基本的には第3の実施例と同
様であるので省略する。
In the assembled basic reinforcing bar 10 of this embodiment, the third
In the embodiment shown in FIG.
The vertical bar mounting portion 30 is inserted vertically into the base reinforcing bar 13 and fixed upright, and the rising bar 18 is inserted in the vertical direction with respect to the base reinforcing bar 13 at the intersection 14 between the 11 and the central reinforcing bar 12B. And a vertical streak mounting portion 30 formed of an annular member having a hole 32 for inserting and fixing it vertically. In the present embodiment, the vertical streak mounting portion 30 made of another member is used. However, it is also possible to form a hole by bending a width streak or a cloth streak, for example. Further, a foundation form method for constructing a fabric foundation using the assembled foundation rebar of the present invention configured as described above is basically the same as that of the third embodiment, and will not be described.

【0038】なお、上述した実施例では、布基礎のフー
チング部及び地中ばり上部に対応した一体の基礎型枠部
材300を用いたが、布基礎のフーチング部分を打設す
るための合成樹脂の発泡体からなる打ち込みタイプのフ
ーチング内側基礎型枠、フーチング外側基礎型枠を用い
て布基礎のフーチングを打設した後、このフーチングの
上方に、合成樹脂発泡体からなる内側基礎型枠と外側基
礎型枠と、両型枠を一定間隔離間するために両型枠の間
に一体成形されたセパレータとからなる打ち込みタイプ
の基礎型枠部材を用いて、布基礎の地中ばり上部を打設
構成することも可能である。
In the above-described embodiment, the integrated foundation frame member 300 corresponding to the footing portion of the cloth foundation and the upper part of the underground beam is used. However, a synthetic resin for casting the footing portion of the cloth foundation is used. After the footing of the cloth foundation is cast using the driving-type footing inner base formwork and the footing outer base formwork made of foam, the inner base formwork and the outer foundation made of synthetic resin foam are placed above the footing. The upper part of the underground beam of the cloth foundation is driven by using a driving type base frame member composed of a mold and a separator integrally formed between the two forms to separate the two forms from each other. It is also possible.

【0039】[0039]

【発明の効果】本発明に係る基礎型枠工法及びそのため
の組立基礎鉄筋は、組立基礎鉄筋の立ち上がり筋の横筋
を、立設状態でフーチング上端位置よりも上方で、且つ
前記基礎型枠部材の最下方のセパレータ位置よりも下方
に位置するように組設した組立基礎鉄筋を用いたので、
組立基礎鉄筋を囲撓するように、基礎型枠部材を上方よ
り捨てコンクリートの上に配置してコンクリート打設空
間を形成する場合に、セパレータが組立基礎鉄筋の立ち
上がり筋の横筋につかえることがなく、捨てコンクリー
ト上の所定位置に簡単容易に立設することができるの
で、コンクリート打設空間を簡単、確実に形成でき、コ
ンクリートを打設して布基礎を構築することができる。
The foundation formwork method according to the present invention and the assembling foundation reinforcing bar for the same are arranged such that the horizontal streaks of the rising bars of the assembling foundation rebar are located above the upper end position of the footing in the upright state, and that Since the base reinforcing bar assembled so as to be located below the lowermost separator position was used,
When laying the foundation form member above the concrete to form a concrete placing space so as to deflect the assembling base rebar, the separator does not stick to the horizontal streaks of the rising bars of the assembling base rebar. Since it can be easily and erected at a predetermined position on the discarded concrete, a concrete casting space can be simply and reliably formed, and concrete can be cast to construct a cloth foundation.

【0040】また、本発明の基礎型枠工法及びそのため
の組立基礎鉄筋は、組立基礎鉄筋の立ち上がり筋の横筋
を省略して、縦筋のみを基礎鉄筋に立設可能に連結して
なる組立基礎鉄筋を用いるため、立ち上がり筋を構成す
る横筋が存在しないので、組立基礎鉄筋を囲撓するよう
に、基礎型枠部材を上方より捨てコンクリートの上に配
置する場合に、セパレータが組立基礎鉄筋の立ち上がり
筋に全くつかえることがない。従って、基礎型枠部材を
上方より捨てコンクリート上の所定位置によりいっそう
簡単容易に立設することができるので、コンクリート打
設空間を確実に形成でき、コンクリートを打設して布基
礎を構築することができる。
Further, the foundation formwork method of the present invention and the assembling foundation reinforcing bar for the same are omitted from the horizontal streaks of the rising bars of the assembling foundation reinforcing bar, and only the vertical bars are connected to the foundation reinforcing bar so as to be able to be erected. Since the reinforcing bars are used, there are no horizontal bars constituting the rising bars, so when the base form member is disposed above the concrete so as to deflect the assembled reinforcing bars, when the separator is mounted on the concrete, There is no stuck in the muscle. Therefore, the foundation form member can be discarded from above and more easily and easily erected at a predetermined position on the concrete, so that the concrete placing space can be reliably formed, and the cloth foundation is constructed by placing concrete. Can be.

【0041】従って、現場にて捨てコンクリートの上面
に折り畳み状態の組立基礎鉄筋を配置した後、立ち上が
り筋を基礎鉄筋に対して垂直方向に立設するだけで組立
鉄筋が施工できるので、鉄筋工として熟練していない型
枠工だけでも基礎型枠工事が施工できる。
Accordingly, the assembled reinforcing bar can be constructed simply by arranging the rising reinforcing bar in the vertical direction with respect to the basic reinforcing bar after disposing the folded basic reinforcing bar on the upper surface of the discarded concrete at the site. The foundation formwork can be performed only by unskilled formworkers.

【0042】さらに、巾基礎型枠工法及びそのための組
立基礎鉄筋は、巾筋と布筋とで格子状に組設した基礎鉄
筋と、前記巾筋と布筋の連結位置に設けられた縦筋装着
部とで構成される組立基礎鉄筋を用いて、縦筋を縦筋装
着部に装着して基礎用鉄筋を構設するので、この場合に
も、横筋が存在しないので、基礎型枠部材を上方より捨
てコンクリートの上に配置する場合に、セパレータが組
立基礎鉄筋の立ち上がり筋に全くつかえることがない。
Further, the width-base formwork method and the assembling base reinforcement therefor include a base reinforcement assembled in a lattice shape with the width reinforcement and the reinforcement, and a vertical reinforcement provided at a connecting position of the width reinforcement and the reinforcement. Since the vertical bars are attached to the vertical bar mounting section and the reinforcing bars for the foundation are constructed by using the assembled basic reinforcing bar composed of the mounting section, in this case also, there is no horizontal bar, so the base form member is When placed on concrete that is discarded from above, the separator does not come into contact with the rising bars of the assembling base rebar at all.

【0043】従って、現場にて捨てコンクリートの上面
に巾筋と布筋とで格子状に組設した基礎鉄筋を配置した
後、立ち上がり筋を構成する縦筋を、縦筋装着部に装着
して基礎鉄筋に対して垂直方向に立設するだけで組立鉄
筋が施工できるので、鉄筋工として熟練していない型枠
工だけでも基礎型枠工事が施工できる。
Therefore, after arranging the base reinforcing bars assembled in a grid pattern with the width bars and the cloth bars on the upper surface of the discarded concrete at the site, the vertical bars constituting the rising bars are mounted on the vertical bar mounting portion. Since the assembling rebar can be constructed simply by erected in the vertical direction with respect to the foundation rebar, foundation formwork can be performed only by a formwork unskilled as a rebar.

【0044】このように、一連の基礎型枠工事において
は、型枠大工及び鉄筋工などの熟練した特殊な技術を必
要とすることなく、型枠工事ならびに配筋工事を同時に
簡単に行えるので、昨今の熟練した作業者が減少してい
る建設業界にあっても、工期の遅延をきたしてしまうな
どの問題がない極めて優れた発明である。
As described above, in a series of foundation form work, the form work and the reinforcing work can be simultaneously and easily performed without the need for skilled and special skills such as form carpenters and reinforcing bars. This is an extremely excellent invention which does not cause problems such as delaying the construction period even in the construction industry where the number of skilled workers is decreasing in recent years.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の基礎型枠工法に用いる組立基礎鉄筋の
第1の実施例の斜視図である。
FIG. 1 is a perspective view of a first embodiment of an assembled basic reinforcing bar used in a foundation formwork method according to the present invention.

【図2】クランプ部材の拡大斜視図である。FIG. 2 is an enlarged perspective view of a clamp member.

【図3】図1の組立基礎鉄筋を用いて布基礎を構築する
本発明の基礎型枠工法を説明する分解斜視図である。
FIG. 3 is an exploded perspective view illustrating a foundation formwork method of the present invention for constructing a cloth foundation using the assembled foundation rebar of FIG. 1;

【図4】図3の基礎型枠工法の組み立てた状態を示す斜
視図である。
FIG. 4 is a perspective view showing an assembled state of the foundation formwork method of FIG. 3;

【図5】本発明の基礎型枠工法に用いる組立基礎鉄筋の
第2の実施例の斜視図である。
FIG. 5 is a perspective view of a second embodiment of an assembled basic reinforcing bar used in the foundation formwork method of the present invention.

【図6】図5の組立基礎鉄筋を用いて布基礎を構築する
本発明の基礎型枠工法を説明する分解斜視図である。
FIG. 6 is an exploded perspective view illustrating a foundation formwork method of the present invention for constructing a cloth foundation using the assembled foundation rebar of FIG. 5;

【図7】図6の基礎型枠工法の組み立てた状態を示す斜
視図である。
FIG. 7 is a perspective view showing an assembled state of the foundation form method of FIG. 6;

【図8】本発明の基礎型枠工法に用いる組立基礎鉄筋の
第3の実施例の斜視図である。
FIG. 8 is a perspective view of a third embodiment of an assembling foundation rebar used in the foundation formwork method of the present invention.

【図9】図8の組立基礎鉄筋を用いて布基礎を構築する
本発明の基礎型枠工法を説明する分解斜視図である。
FIG. 9 is an exploded perspective view illustrating a foundation formwork method of the present invention for constructing a cloth foundation using the assembled foundation rebar of FIG. 8;

【図10】図9の基礎型枠工法の組み立てた状態を示す
斜視図である。
FIG. 10 is a perspective view showing an assembled state of the basic formwork method of FIG. 9;

【図11】本発明の基礎型枠工法に用いる組立基礎鉄筋
の第3の実施例の斜視図である。
FIG. 11 is a perspective view of a third embodiment of an assembled basic reinforcing bar used in the foundation formwork method of the present invention.

【図12】従来の基礎型枠工法の配筋方法を説明する斜
視図である。
FIG. 12 is a perspective view illustrating a reinforcing method of a conventional foundation form method.

【図13】従来の基礎型枠工法の布基礎のフーチング部
分を構築する方法を説明する断面図である。
FIG. 13 is a cross-sectional view for explaining a method of constructing a footing portion of a cloth foundation in a conventional foundation form method.

【図14】従来の基礎型枠工法の布基礎の地中ばり部分
を構築する方法を説明する断面図である。
FIG. 14 is a cross-sectional view illustrating a method of constructing an underground beam portion of a cloth foundation in a conventional foundation form method.

【図15】従来の組立基礎鉄筋の斜視図である。FIG. 15 is a perspective view of a conventional assembled basic reinforcing bar.

【図16】従来の樹脂発泡体からなる基礎型枠を用いた
基礎型枠工法のを説明する断面図である。
FIG. 16 is a cross-sectional view illustrating a conventional base form method using a base form made of a resin foam.

【図17】従来の樹脂発泡体からなる基礎型枠を用いた
基礎型枠工法のを説明する断面図である。
FIG. 17 is a cross-sectional view for explaining a basic formwork method using a conventional base form made of a resin foam.

【符号の説明】[Explanation of symbols]

10・・・組立基礎鉄筋 11・・・巾筋 12A〜12C・・・布筋 13・・・基礎鉄筋 15・・・縦筋 16・・・クリップ部材 17・・・横筋 18・・・立ち上がり筋 19・・・クランプ部材 30・・・縦筋装着部 102・・・捨てコンクリート 104・・・スペーサ 120・・・布基礎 122・・・フーチング 124・・・地中ばり上部 300・・・基礎型枠部材 301・・・内側基礎型枠 302・・・外側基礎型枠 303・・・セパレータ DESCRIPTION OF SYMBOLS 10 ... Assembly basic reinforcing bar 11 ... Width reinforcing bar 12A-12C ... Cloth reinforcing bar 13 ... Basic reinforcing bar 15 ... Vertical bar 16 ... Clip member 17 ... Horizontal bar 18 ... Standing bar 19 ... Clamping member 30 ... Vertical streak mounting part 102 ... Discarded concrete 104 ... Spacer 120 ... Cloth foundation 122 ... Footing 124 ... Underground beam upper part 300 ... Foundation type Frame member 301 ・ ・ ・ Inner basic form 302 ・ ・ ・ Outer basic form 303 ・ ・ ・ Separator

Claims (9)

【特許請求の範囲】[Claims] 【請求項1】 巾筋と布筋とで格子状に組設した基礎鉄
筋と、縦筋と横筋とで組設され、前記基礎鉄筋に対して
垂直方向に立設可能に基礎鉄筋に連結してなる立ち上が
り筋とで構成される組立基礎鉄筋を、立ち上がり筋が立
設状態となるように捨てコンクリート上に配筋するとと
もに、 外側基礎型枠と内側基礎型枠と、両型枠を一定間隔離間
するために両型枠の間に配設されたセパレータとからな
る基礎型枠部材を、前記組立基礎鉄筋を囲撓するように
立設した後、前記型枠間にコンクリートを打設して布基
礎を構築する基礎型枠工法において、 前記組立基礎鉄筋の立ち上がり筋の横筋を、立設状態で
フーチング上端位置よりも上方で、且つ前記基礎型枠部
材の最下方のセパレータ位置よりも下方に位置するよう
に組設した組立基礎鉄筋を用いることを特徴とする基礎
型枠工法。
1. A base reinforcing bar assembled in a grid pattern with a width reinforcing bar and a cloth reinforcing bar, and a vertical reinforcing bar and a horizontal reinforcing bar. The base reinforcing bar is connected to the basic reinforcing bar so as to be able to stand vertically in relation to the basic reinforcing bar. In addition to disposing the assembled foundation reinforcing bar composed of the standing uprights on the concrete so that the standing uprights are in the standing state, the outer and inner foundation formwork and both formwork are spaced at a fixed interval. After erecting a base form member consisting of a separator disposed between both forms to separate the base form member so as to surround the assembled base rebar, concrete is poured between the form forms. In the foundation formwork method of constructing the cloth foundation, the horizontal streaks of the rising bars of the assembled foundation rebar are located above the upper end position of the footing in the standing state, and below the lowermost separator position of the foundation form member. For use with an assembly foundation rebar assembled to be positioned Foundation formwork construction method according to claim Rukoto.
【請求項2】 巾筋と布筋とで格子状に組設した基礎鉄
筋と、縦筋と横筋とで組設され、前記基礎鉄筋に対して
垂直方向に立設可能に基礎鉄筋に連結してなる立ち上が
り筋とで構成される組立基礎鉄筋を、立ち上がり筋が立
設状態となるように捨てコンクリート上に配筋するとと
もに、 外側基礎型枠と内側基礎型枠と、両型枠を一定間隔離間
するために両型枠の間に配設されたセパレータとからな
る基礎型枠部材を、前記組立基礎鉄筋を囲撓するように
立設した後、前記型枠間にコンクリートを打設して布基
礎を構築する基礎型枠工法において、 前記組立基礎鉄筋の立ち上がり筋の横筋を省略して、縦
筋のみを基礎鉄筋に立設可能に連結してなる組立基礎鉄
筋を用いることを特徴とする基礎型枠工法。
2. A base reinforcing bar assembled in a grid pattern with a width reinforcing bar and a cloth reinforcing bar, and a vertical reinforcing bar and a horizontal reinforcing bar. The base reinforcing bar is connected to the basic reinforcing bar so as to be able to be erected vertically with respect to the basic reinforcing bar. In addition to disposing the assembled foundation reinforcing bar composed of the standing uprights on the concrete so that the standing uprights are in the standing state, the outer and inner foundation formwork and both formwork are spaced at a fixed interval. After erecting a base form member consisting of a separator disposed between both forms to separate the base form member so as to surround the assembled base rebar, concrete is poured between the form forms. In a foundation formwork method for constructing a cloth foundation, the horizontal reinforcing bars of the assembled reinforcing bars are omitted, and only the vertical bars are connected to the basic reinforcing bars so as to be erected. Foundation formwork method.
【請求項3】 巾筋と布筋とで格子状に組設した基礎鉄
筋と、前記巾筋と布筋の連結位置に設けられた縦筋装着
部とで構成される組立基礎鉄筋を、捨てコンクリート上
に配筋するとともに、 前記基礎鉄筋の縦筋装着部材に、縦筋を装着して基礎用
鉄筋を構設し、 外側基礎型枠と内側基礎型枠と、両型枠を一定間隔離間
するために両型枠の間に配設されたセパレータとからな
る基礎型枠部材を、前記組立基礎鉄筋を囲撓するように
立設した後、前記型枠間にコンクリートを打設して布基
礎を構築することを特徴とする基礎型枠工法。
3. An assembling basic reinforcing bar composed of a base reinforcing bar assembled in a lattice shape with a width reinforcing bar and a reinforcing bar, and a vertical reinforcing bar mounting portion provided at a connection position of the width reinforcing bar and the reinforcing bar. While arranging reinforcing bars on concrete, a vertical bar is attached to the vertical bar mounting member of the above-mentioned reinforcing bar to form a reinforcing bar for the foundation, and the outer and inner foundation forms are separated from each other by a certain distance. After forming a base form member consisting of a separator disposed between both form forms to erode the assembled base reinforcing bar, concrete is poured between the form forms to form a cloth. A foundation formwork method characterized by building a foundation.
【請求項4】 巾筋と布筋とで格子状に組設した基礎鉄
筋と、縦筋と横筋とで組設され、前記基礎鉄筋に対して
垂直方向に立設可能に基礎鉄筋に連結してなる立ち上が
り筋とで構成される組立基礎鉄筋であって、立ち上がり
筋の横筋を、立設状態でフーチング上端位置よりも上方
で、且つ基礎型枠部材の最下方のセパレータ位置よりも
下方に位置するように組設したことを特徴とする組立基
礎鉄筋。
4. A base reinforcing bar assembled in a grid pattern with a width reinforcing bar and a reinforcing bar, and assembled with a vertical reinforcing bar and a horizontal reinforcing bar, and connected to the basic reinforcing bar so as to be able to stand in a vertical direction with respect to the basic reinforcing bar. An assembling basic reinforcing bar composed of a rising bar comprising: a horizontal bar of the rising bar positioned above an upper end position of a footing in an upright state and lower than a lowermost separator position of a base form member. An assembling foundation rebar characterized by being assembled in such a manner as to be assembled.
【請求項5】 巾筋と布筋とで格子状に組設した基礎鉄
筋と、縦筋のみを基礎鉄筋に対して垂直方向に立設可能
に連結した立ち上がり筋とで構成したことを特徴とする
組立基礎鉄筋。
5. A reinforcing bar comprising a base reinforcing bar assembled in a lattice shape with a width reinforcing bar and a reinforcing bar, and a rising bar connected only to a vertical bar so as to be able to stand in a vertical direction with respect to the basic reinforcing bar. Assembling basic rebar.
【請求項6】 前記立ち上がり筋を立設状態でその立設
状態を保持するクランプ部材を付設したことを特徴とす
る請求項4又は5に記載の組立基礎鉄筋。
6. The assembled basic reinforcing bar according to claim 4, further comprising a clamp member for holding the rising bar in an upright state.
【請求項7】 巾筋と布筋とで格子状に組設した基礎鉄
筋と、前記巾筋と布筋の連結位置に設けられた縦筋装着
部とで構成される組立基礎鉄筋。
7. An assembling basic reinforcing bar comprising a basic reinforcing bar assembled in a lattice shape with a width reinforcing bar and a reinforcing bar, and a vertical bar mounting portion provided at a connecting position of the width reinforcing bar and the reinforcing bar.
【請求項8】 前記縦筋装着部が、縦筋を挿着可能なパ
イプ部材で構成されていることを特徴とする請求項7に
記載の組立基礎鉄筋。
8. The assembling foundation reinforcing bar according to claim 7, wherein said vertical bar mounting portion is formed of a pipe member into which a vertical bar can be inserted.
【請求項9】 前記縦筋装着部が、縦筋を挿着可能な孔
部を有する部材で構成されていることを特徴とする請求
項7に記載の組立基礎鉄筋。
9. The assembled basic reinforcing bar according to claim 7, wherein said vertical bar mounting portion is formed of a member having a hole through which a vertical bar can be inserted.
JP24670596A 1996-09-18 1996-09-18 Base form process and assembled reinforcing bars used therefor Pending JPH1088793A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP24670596A JPH1088793A (en) 1996-09-18 1996-09-18 Base form process and assembled reinforcing bars used therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP24670596A JPH1088793A (en) 1996-09-18 1996-09-18 Base form process and assembled reinforcing bars used therefor

Publications (1)

Publication Number Publication Date
JPH1088793A true JPH1088793A (en) 1998-04-07

Family

ID=17152417

Family Applications (1)

Application Number Title Priority Date Filing Date
JP24670596A Pending JPH1088793A (en) 1996-09-18 1996-09-18 Base form process and assembled reinforcing bars used therefor

Country Status (1)

Country Link
JP (1) JPH1088793A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008115629A (en) * 2006-11-06 2008-05-22 Toshimasa Watanabe Concrete foundation form
CN111622496A (en) * 2020-06-22 2020-09-04 中国五冶集团有限公司 Super large shear force wall unilateral template reinforced structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008115629A (en) * 2006-11-06 2008-05-22 Toshimasa Watanabe Concrete foundation form
JP4526129B2 (en) * 2006-11-06 2010-08-18 利正 渡辺 Concrete foundation formwork
CN111622496A (en) * 2020-06-22 2020-09-04 中国五冶集团有限公司 Super large shear force wall unilateral template reinforced structure

Similar Documents

Publication Publication Date Title
EP0410981B1 (en) Concrete forming system
US5771648A (en) Foam form concrete system
US8365489B1 (en) Building system and method of constructing a multi-walled structure
US20110131907A1 (en) Building system and method of constructing a multi-walled structure
JP2001295298A (en) Foundation for columnar structure and its work execution method
KR102269141B1 (en) Deck plate wall installation method using underground pavement
JP2535722B2 (en) Reinforcement concrete column and steel beam connection structure and building construction method
JPH1088793A (en) Base form process and assembled reinforcing bars used therefor
JP2019065641A (en) Rock fall guard fence
JPH1150468A (en) Pc concrete strip footing and installation method thereof
JPH08260481A (en) Form for concrete placing for footing, and construction of footing therewith
JPH0913390A (en) Constructing method of concrete foundation or wall body
JPH04261915A (en) Slope frame constructing block and method for constructing slope frame thereof
JP2001220858A (en) Concrete reinforced body and its assembly method
JP2988814B2 (en) Precast concrete foundation structure
JP2700637B2 (en) Slope stable structure
JPH09296551A (en) Reinforcement built-up structure of concrete wall, and building method of concrete wall using it
JPH10219894A (en) Concrete formwork structure
JP2006118236A (en) Fiber-reinforced concrete-made permanent form
JP2005054444A (en) Precast concrete plate, concrete slab using the same, and its construction method
JP2952823B2 (en) Construction method of greening method frame
JP2817967B2 (en) Fabric foundation and construction method
JPH0738390Y2 (en) Formwork for legal form
JPH0633073Y2 (en) Precast concrete beam
JPH11131692A (en) Unit joint bar