JPH1040285A - Construction drawing management system - Google Patents

Construction drawing management system

Info

Publication number
JPH1040285A
JPH1040285A JP21509096A JP21509096A JPH1040285A JP H1040285 A JPH1040285 A JP H1040285A JP 21509096 A JP21509096 A JP 21509096A JP 21509096 A JP21509096 A JP 21509096A JP H1040285 A JPH1040285 A JP H1040285A
Authority
JP
Japan
Prior art keywords
construction
information
management system
data
attribute
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP21509096A
Other languages
Japanese (ja)
Inventor
Hideki Hara
秀樹 原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NEC Corp
Original Assignee
NEC Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NEC Corp filed Critical NEC Corp
Priority to JP21509096A priority Critical patent/JPH1040285A/en
Publication of JPH1040285A publication Critical patent/JPH1040285A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Processing Or Creating Images (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PROBLEM TO BE SOLVED: To enable reflection on a change of information under construction while temporary matching to an equipment management system after completion of the construction by cutting out construction information from drawing information and attribute information held by the equipment management system and separating it from information managed by the equipment management system. SOLUTION: At the time of starting the construction, with respect to a construction area part, the drawing information and the attribute information on the equipment management system 10 which is retrieved by an equipment data retrieving means 21 is cut out by a construction data cutting-out means 40 based on the original drawing information and the original attribute information. A construction information management means 42 manages the history of the construction. Then, the construction data (the construction drawing information and the construction attribute information) is processed using a data processing means 22 provided in the equipment management system 10. Then, after a construction design specification is completed and the construction is ordered, if the construction is completed, the construction drawing information and the construction attribute information is reflected on the original data of the equipment management system 10 based on the construction data including the change of information under construction.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、工事図面管理方式
に関し、特に、コンピュータ等情報処理装置を利用した
設備管理システムにおける工事図面管理方式に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction drawing management system, and more particularly to a construction drawing management system in a facility management system using an information processing device such as a computer.

【0002】[0002]

【従来の技術】この種の従来の工事図面管理システムと
して、例えば特開平5−314198号公報には、図面
の認識機能と認識された図形構成要素に対するデータ処
理機能を備えたシステムとして、設備に関する図面を図
面情報として入力し、その図面情報を構成している特定
の設備に関する図面構成要素を抽出してその種別を認識
し、その種別が認識できた図形構成要素の各々に種別に
対応する属性データを付与するように構成してなる設備
管理システムが提案されている。また、特開平6−35
981号公報には、屋外配線工事等に関する図面を管理
する図面データ管理方法として、重複する工事設計図デ
ータをマスタ図面データベースに正しく更新するように
した管理方法が提案されている。
2. Description of the Related Art As a conventional construction drawing management system of this kind, for example, Japanese Patent Laid-Open Publication No. Hei 5-314198 discloses a system having a drawing recognition function and a data processing function for recognized graphic components. A drawing is input as drawing information, drawing components related to a specific facility constituting the drawing information are extracted and their types are recognized, and attributes corresponding to the types are recognized for each of the graphic components whose types are recognized. An equipment management system configured to provide data has been proposed. Also, Japanese Patent Application Laid-Open No. 6-35
Japanese Patent Publication No. 981 proposes a drawing data management method for managing drawings relating to outdoor wiring work and the like, in which overlapping construction design data is correctly updated in a master drawing database.

【0003】上記特開平5−314198号公報にも提
案されるように、従来のコンピュータ等情報処理装置に
よる設備管理システムにおいては、図面の入力、検索、
保存と、図面上の設備の存在を認識させ、属性情報と関
係付けを行い、設備の属性情報をも同一コンピュータで
管理することを可能とする。
As proposed in Japanese Patent Application Laid-Open No. Hei 5-314198, a conventional facility management system using an information processing device such as a computer requires input, search, and drawing of drawings.
Storage and recognition of the existence of the equipment on the drawing, association with attribute information, and management of the attribute information of the equipment with the same computer are enabled.

【0004】また、上記特開平6−35981号公報に
提案される図面データ管理方法においては、複数枚の工
事図面を時系列で管理し、整合を取りながら、マスタ図
面の更新を行う機能を有する。
The drawing data management method proposed in Japanese Patent Laid-Open No. 6-35981 has a function of managing a plurality of construction drawings in time series and updating a master drawing while maintaining consistency. .

【0005】[0005]

【発明が解決しようとする課題】しかしながら、上記し
た従来技術は、下記記載の問題点を有している。
However, the above-mentioned prior art has the following problems.

【0006】(1)第1の問題点は、図面情報と属性情
報の2つの情報が、同時に多重管理できない、というこ
とである。
(1) The first problem is that two pieces of information, ie, drawing information and attribute information, cannot be multiplex-managed at the same time.

【0007】その理由は、従来の設備管理システムは、
資産の管理を目的としたシステムであり、工事管理を考
慮したシステムではないことによる。
The reason is that the conventional equipment management system is
This is because the system is designed for asset management and not for construction management.

【0008】(2)第2の問題点は、工事によって変更
された図面情報及び属性情報を同時に設備管理システム
に反映できない、ということである。
(2) The second problem is that drawing information and attribute information changed by construction cannot be simultaneously reflected in the equipment management system.

【0009】その理由は、従来の技術で時系列管理・更
新できるのは、図面情報しか考慮されていないことによ
る。
The reason is that the time series can be managed and updated by the conventional technique because only the drawing information is considered.

【0010】このように、従来の設備管理システムにお
いては、工事に際し、現在システムが保持している図面
情報及び属性情報を利用して、工事管理システムを構築
することは、考慮されておらず、図面の修正がある場合
の図面の更新機能のみが、実現されているにすぎない。
As described above, in the conventional equipment management system, no consideration is given to constructing a construction management system using the drawing information and the attribute information currently held by the system at the time of construction. Only the drawing update function when there is a drawing correction is implemented.

【0011】したがって、本発明は、上記事情に鑑みて
なされたものであって、その目的は、工事情報を設備管
理システムが保持している図面情報及び属性情報から、
切り出し、設備管理システムが管理する情報から分離す
ることにより、工事中の図面の変更や属性情報の変更
を、設備管理システムに影響を与えることを可能とする
とともに、工事中の情報変更を、工事完了後設備管理シ
ステムに時間的な整合を取りつつ、反映することを可能
とする工事図面管理方式を提供することにある。
Accordingly, the present invention has been made in view of the above circumstances, and has as its object to convert construction information from drawing information and attribute information held by an equipment management system.
By separating the information from the information managed by the equipment management system, changes in the drawings and attribute information during construction can be affected by the equipment management system. It is an object of the present invention to provide a construction drawing management system which can reflect the information after completion in the equipment management system while keeping time alignment.

【0012】[0012]

【課題を解決するための手段】前記目的を達成するた
め、本発明の工事図面管理方式は、管理対象設備に関す
る図面情報と属性情報とを一元管理する設備管理システ
ムにおいて、工事状況を管理するための図面情報及び属
性情報を工事管理システムとして、設備管理の情報との
二重管理可能とする手段を備えたことを特徴とする。
In order to achieve the above object, a construction drawing management system according to the present invention provides a construction management system for centrally managing drawing information and attribute information on a facility to be managed. Means for enabling the drawing information and the attribute information to be double-managed as equipment management information as a construction management system.

【0013】本発明においては、前記設備管理システム
の情報から、工事管理システムにおける工事範囲に該当
する図面情報を属性情報とともに切り出す手段を備えた
ことを特徴とする。
The present invention is characterized in that there is provided means for cutting out drawing information corresponding to a construction range in the construction management system together with attribute information from information of the facility management system.

【0014】また、本発明においては、前記設備管理シ
ステムの情報に影響を及ぼすことなく、前記図面情報及
び属性情報を追加及び修正する手段を備えたことを特徴
とする。
Further, the present invention is characterized in that there is provided means for adding and correcting the drawing information and the attribute information without affecting information of the equipment management system.

【0015】さらに、本発明においては、工事完了時
に、工事情報を正規の設備情報とするために、工事管理
システムのもつ図面情報及び属性情報を、前記設備管理
システムの図面情報及び属性情報に対して、変更部分の
み反映させる手段を備えたことを特徴とする。
Further, in the present invention, when the construction is completed, the drawing information and the attribute information of the construction management system are replaced with the drawing information and the attribute information of the facility management system so that the construction information becomes the regular equipment information. And means for reflecting only the changed portion.

【0016】本発明の概要を以下に説明する。本発明に
おいては、工事開始時に、工事範囲部に関して、設備管
理システム上の図面情報及び属性情報を切り出す手段
(図1の40)を有する。さらに、工事履歴を管理する
ための工事情報管理手段(図1の42)を有する。そし
て、工事図面情報、工事属性情報は、設備管理システム
の持つデータ加工手段(図1の22)を用いて、データ
の保守を可能とする。
The outline of the present invention will be described below. The present invention has means (40 in FIG. 1) for cutting out the drawing information and the attribute information on the facility management system with respect to the construction range part at the start of the construction. Further, there is a construction information management means (42 in FIG. 1) for managing the construction history. The construction drawing information and the construction attribute information can be maintained using the data processing means (22 in FIG. 1) of the equipment management system.

【0017】さらに、工事完了時は、工事情報を元に、
工事図面情報及び工事属性情報を設備管理システムの元
データに反映する手段(図1の41)を有する。
Further, upon completion of the construction, based on the construction information,
There is means (41 in FIG. 1) for reflecting the construction drawing information and the construction attribute information in the original data of the facility management system.

【0018】オペレータは、工事が行われる範囲を設備
管理システム上で検索された該当図面上で指定する。工
事データ切出手段は、その入力情報を元に、図面情報及
び属性情報を取り出し、工事図面記録部(図1の43)
及び工事属性記録部(図1の44)に保存する。
The operator specifies the range in which the construction is to be performed on the relevant drawing searched on the facility management system. The construction data extracting means extracts the drawing information and the attribute information based on the input information, and records the construction drawing recording unit (43 in FIG. 1).
And in the construction attribute recording unit (44 in FIG. 1).

【0019】そのとき、工事情報管理手段が、切り出し
・反映の整合性をとるために、工事情報の入力をオペレ
ータに促す。オペレータが入力した情報は、工事情報記
録部(図1の45)に記録される。
At this time, the construction information management means urges the operator to input construction information in order to obtain consistency of cutout and reflection. The information input by the operator is recorded in the construction information recording unit (45 in FIG. 1).

【0020】データ加工手段は、オペレータに図面記録
部及び属性記録部のデータに影響を与えることなく、工
事図面記録部(図1の43)及び工事属性記録部(図1
の44)のデータの加工を可能とする。
The data processing means does not affect the data of the drawing recording section and the attribute recording section to the operator, and the construction drawing recording section (43 in FIG. 1) and the construction attribute recording section (FIG. 1).
44) enables data processing.

【0021】工事が完了した時点で、オペレータは工事
データ反映手段を使って、工事データを元データに反映
することを指示する。
When the construction is completed, the operator instructs to reflect the construction data on the original data by using the construction data reflecting means.

【0022】工事データ反映手段は、工事情報管理手段
を用い、反映すべき工事データと、反映先の図面データ
及び属性データを求める。反映のためのデータの確認が
できたところで、必要な情報を反映する。反映後は、反
映履歴を工事情報記憶部(図1の45)に保存する。
The construction data reflecting means uses construction information management means to obtain construction data to be reflected, drawing data and attribute data to be reflected. Once the data for reflection has been confirmed, the necessary information is reflected. After the reflection, the reflection history is stored in the construction information storage unit (45 in FIG. 1).

【0023】[0023]

【発明の実施の形態】次に、本発明の実施の形態につい
て図面を参照して詳細に説明する。
Next, embodiments of the present invention will be described in detail with reference to the drawings.

【0024】図1は、本発明の実施の形態に係る設備管
理システムの構成を示す図である。本発明の実施の形態
において、設備管理システム10は、オペレータが入出
力装置11の情報を基に作成する入力情報を利用し、後
述する各構成要素を用いて、工事図面管理機能を実現す
る。
FIG. 1 is a diagram showing a configuration of an equipment management system according to an embodiment of the present invention. In the embodiment of the present invention, the facility management system 10 realizes a construction drawing management function using input information created by an operator based on information of the input / output device 11 and using each component described later.

【0025】図1を参照すると、設備管理システム10
は、所有する図面情報及び属性情報を検索するための設
備データ検索手段21と、所有する図面情報及び属性情
報を加工するための設備データ加工手段22に加えて、
さらに、工事データの作成、管理を行うために、工事管
理システム23が付加されて構成されている。なお、図
1において、設備データ検索手段21と設備データ加工
手段22は既存の設備管理システムに具備された構成を
用いることができる。
Referring to FIG. 1, an equipment management system 10
In addition to equipment data search means 21 for searching owned drawing information and attribute information, and equipment data processing means 22 for processing owned drawing information and attribute information,
Further, a construction management system 23 is added to create and manage construction data. In FIG. 1, the equipment data search means 21 and the equipment data processing means 22 can use the configuration provided in the existing equipment management system.

【0026】工事管理システム23は、元図面情報及び
元属性情報から、図面情報及び属性情報を工事データと
して切り出す工事データ切出手段40と、工事図面情報
及び工事属性情報を元図面及び元属性情報に反映する、
工事データ反映手段41と、工事データの切り出し、反
映及び履歴管理のために、工事情報を入力・検索する、
工事情報管理手段42と、を備えている。
The construction management system 23 includes construction data extracting means 40 for extracting drawing information and attribute information as construction data from the original drawing information and original attribute information, and the construction drawing information and construction attribute information based on the original drawing and original attribute information. To reflect on
A construction data reflecting means 41 for inputting / searching construction information for extracting, reflecting, and managing the history of the construction data;
And construction information management means 42.

【0027】データ部は、元図面を保管する、図面記録
部24と、元属性を保管する、属性記録部25と、工事
図面を保管する、工事図面記録部43と、工事属性を保
管する、工事属性記録部44と、工事情報を保管する、
工事情報記録部45と、からなる。
The data section stores the original drawings, a drawing recording section 24, stores the original attributes, an attribute recording section 25, stores the construction drawings, a construction drawing recording section 43, and stores the construction attributes. A construction attribute recording unit 44 for storing construction information;
And a construction information recording unit 45.

【0028】図2は、本発明の実施の形態のシステム全
体の処理動作を説明するためのフローチャートである。
FIG. 2 is a flowchart for explaining the processing operation of the entire system according to the embodiment of the present invention.

【0029】図2を参照して、工事開始時に、工事範囲
部に関して、設備管理システム上の図面情報及び属性情
報を工事データ切り出し手段40により切り出す(ステ
ップA)。さらに、工事履歴を管理するための工事情報
管理手段(図1の42)を有する。そして、工事データ
(工事図面情報、工事属性情報)を、設備管理システム
の持つデータ加工手段22を用いて、データを加工する
(ステップB)。
Referring to FIG. 2, at the start of construction, drawing information and attribute information on the facility management system are cut out by the construction data cutting means 40 for the work range portion (step A). Further, there is a construction information management means (42 in FIG. 1) for managing the construction history. Then, the construction data (construction drawing information, construction attribute information) is processed using the data processing means 22 of the equipment management system (step B).

【0030】そして、工事設計書が完成し、工事発注
後、工事が完了した時(ステップS2〜S4)は、工事
データを基に、工事図面情報及び工事属性情報を設備管
理システムの元データに反映する(ステップC)。
When the work design document is completed and the work is completed after the work order (steps S2 to S4), the work drawing information and the work attribute information are converted to the original data of the equipment management system based on the work data. Reflect (Step C).

【0031】図2を参照して説明した本発明の実施の形
態の処理動作(ステップA、B、C)について、以下に
詳細に説明する。
The processing operation (steps A, B, C) of the embodiment of the present invention described with reference to FIG. 2 will be described in detail below.

【0032】図3は、本発明の実施の形態における工事
データ切り出し処理(図2のステップA)の処理フロー
を説明するための流れ図である。図1及び図3の流れ図
を参照して、本発明の実施の形態における工事データ切
り出し処理の動作を以下に詳細に説明する。
FIG. 3 is a flowchart for explaining a processing flow of construction data cutout processing (step A in FIG. 2) according to the embodiment of the present invention. The operation of the construction data cutout processing according to the embodiment of the present invention will be described below in detail with reference to the flowcharts of FIGS.

【0033】オペレータは、設備データ検索手段21を
利用して、工事の対象となる図面を検索し、入出力装置
11に表示させる(ステップA1)。
The operator uses the equipment data search means 21 to search for a drawing to be constructed and displays it on the input / output device 11 (step A1).

【0034】オペレータは、今回工事の対象となる範囲
を、入出力装置11から表示中の図面上に情報入力を行
う(ステップA2)。
The operator inputs information on the range to be constructed this time from the input / output device 11 on the drawing being displayed (step A2).

【0035】入出力制御部20は、入力情報を工事デー
タ切り出し手段40へ伝達する(ステップA3)。
The input / output control unit 20 transmits the input information to the construction data extracting means 40 (Step A3).

【0036】工事データ切り出し手段40は、工事範囲
情報を、図面切り出し機能50及び属性切り出し情報5
1のそれぞれに伝達する(ステップA4)。
The construction data extracting means 40 converts the construction range information into the drawing extracting function 50 and the attribute extracting information 5.
1 (step A4).

【0037】工事情報管理手段42が、工事情報入力機
能54を起動し、工事情報の入力をオペレータに促す
(ステップA5)。
The construction information management means 42 activates the construction information input function 54 to urge the operator to input construction information (step A5).

【0038】オペレータは、切り出し図面に関する情報
を入出力装置11より入力する(ステップA6)。
The operator inputs information relating to the cut-out drawing from the input / output device 11 (step A6).

【0039】入力情報は、工事情報記録部45に保存さ
れるとともに、その際の管理番号が、工事管理番号とし
て、工事データ切り出し手段40に提供される(ステッ
プA7)。
The input information is stored in the construction information recording section 45, and the management number at that time is provided to the construction data extracting means 40 as a construction management number (step A7).

【0040】図面切り出し機能50が起動され、工事管
理番号をキーとして、工事範囲を元に、該当範囲の図面
データのコピーが工事図面記録部43に保存される(ス
テップA8)。
The drawing cut-out function 50 is activated, and a copy of the drawing data of the applicable range is stored in the construction drawing recording unit 43 based on the construction range, using the construction management number as a key (step A8).

【0041】また属性切り出し機能51が起動され、工
事管理番号をキーとして、工事範囲を元に、該当範囲の
属性データのコピーが工事属性記録部44に保存される
(ステップA9)。
The attribute extraction function 51 is activated, and a copy of the attribute data of the applicable range is stored in the construction attribute recording unit 44 based on the construction range using the construction management number as a key (step A9).

【0042】次に、本発明の実施の形態における、切り
出された工事データの加工方法(図2のステップB)に
ついて、図4の流れ図を参照して説明する。
Next, a method of processing the cut-out construction data (step B in FIG. 2) according to the embodiment of the present invention will be described with reference to a flowchart of FIG.

【0043】オペレータは、工事情報検索機能55を起
動する(ステップB1)。
The operator activates the construction information search function 55 (step B1).

【0044】登録されている工事情報の一覧が表示され
るので、その中から加工対象の工事データを選択する
(ステップB2)。
A list of registered construction information is displayed, and construction data to be processed is selected from the list (step B2).

【0045】工事図面の加工の場合は、工事管理番号を
キーとして、図面検索機能30を用いて、工事図面を検
索する(ステップB3−1)。
In the case of processing a construction drawing, a construction drawing is searched using the drawing search function 30 with the construction management number as a key (step B3-1).

【0046】属性データの加工の場合は、工事管理番号
をキーとして、属性検索機能31を用いて、属性データ
を検索する(ステップB3−2)。
In the case of processing attribute data, attribute data is searched using the attribute search function 31 using the construction management number as a key (step B3-2).

【0047】検索された工事図面に対し、図面加工機能
32を用い、図面の加工を行う(ステップB4−1)。
The searched construction drawings are processed using the drawing processing function 32 (step B4-1).

【0048】検索された属性データに対し、属性加工機
能33を用い、属性データの修正、追加、削除を行う
(ステップB4−2)。
Using the attribute processing function 33, the attribute data is corrected, added, and deleted from the retrieved attribute data (step B4-2).

【0049】次に、本発明の実施の形態における、工事
完了時の工事データの元データへの反映処理(図2のス
テップC)について、図5の流れ図を参照して説明す
る。
Next, the process of reflecting the construction data upon the completion of the construction (step C in FIG. 2) according to the embodiment of the present invention will be described with reference to the flowchart of FIG.

【0050】オペレータは、工事情報検索機能55を起
動する(ステップC1)。
The operator activates the construction information search function 55 (Step C1).

【0051】登録されている工事情報の一覧が表示され
るので、その中から工事完了となる工事データを選択す
る(ステップC2)。
A list of registered construction information is displayed, and the construction data that completes the construction is selected from the list (step C2).

【0052】工事完了となる工事管理番号を持つ図面の
一覧が表示されるので、元データに反映すべき工事図面
を選択する。なお、この工事図面上にある設備の属性デ
ータも自動的に反映対象となる(ステップC3)。
A list of drawings having a construction management number indicating completion of the construction is displayed, and a construction drawing to be reflected in the original data is selected. The attribute data of the equipment on the construction drawing is also automatically reflected (step C3).

【0053】オペレータが工事データ反映手段41の実
行を指示する。図面反映機能52により工事図面が元図
面に反映されるとともに、属性反映機能53により属性
データが元データに反映される(ステップC4)。
The operator instructs execution of the construction data reflecting means 41. The construction drawing is reflected on the original drawing by the drawing reflection function 52, and the attribute data is reflected on the original data by the attribute reflection function 53 (step C4).

【0054】[0054]

【実施例】上記した本発明の実施の形態について、さら
に具体的に説明すべく、本発明の実施例について図面を
参照して以下に説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS In order to more specifically describe the above-described embodiment of the present invention, an embodiment of the present invention will be described below with reference to the drawings.

【0055】図6および図7を参照して、本発明を施設
管理システムに適用した実施例を説明する。
An embodiment in which the present invention is applied to a facility management system will be described with reference to FIGS.

【0056】図6(A)は、今回建築物の増築が行われ
る予定の付近の図面を画面上に表示しているイメージを
示している。図6(B)は、増築前の建築物の属性デー
タの一部を画面上に表示していることを示している。図
6(C)は、画面上でオペレータが工事の範囲を指定す
る操作のイメージを示している。図6(D)は、工事図
面を編集して建築物を増築した図面を作成しているイメ
ージを示している。
FIG. 6A shows an image in which a drawing in the vicinity of an area where a building is to be added this time is displayed on a screen. FIG. 6B shows that a part of the attribute data of the building before the extension is displayed on the screen. FIG. 6C shows an image of an operation in which an operator specifies a range of a construction on the screen. FIG. 6D shows an image in which a construction drawing is edited to create a drawing in which a building is added.

【0057】図7(E)は、工事図面の編集が終わった
状態の画面イメージを示している。図7(F)は、増築
に伴う建築物の属性データの変更を入力している状態を
示している。図7(G)は、工事図面反映後の元図面の
状態を示している。図7(H)は、工事データ反映後の
建築物の属性データの変更状態を示す。
FIG. 7E shows a screen image in a state where editing of the construction drawing has been completed. FIG. 7F shows a state in which a change in the attribute data of the building accompanying the extension has been input. FIG. 7 (G) shows the state of the original drawing after reflecting the construction drawing. FIG. 7H shows a change state of the attribute data of the building after the construction data is reflected.

【0058】次に、本発明の実施例の動作について、図
6及び図7を参照して詳細に説明する。
Next, the operation of the embodiment of the present invention will be described in detail with reference to FIGS.

【0059】図6を参照すると、本実施例の設備管理シ
ステムでは、建築物管理システムを取り扱うものとす
る。今回建物の増築が予定されている。図6(A)に
は、増築の対象となる建物が表示されている。工事の計
画書(増築後の状態図)を作成する必要がある(なおか
つ既存のデータは、工事完了まで手を加えてはならな
い)。
Referring to FIG. 6, it is assumed that the equipment management system of this embodiment handles a building management system. The expansion of the building is planned this time. FIG. 6A shows a building to be added. It is necessary to prepare a construction plan (state diagram after the extension) (and do not modify existing data until the completion of the construction).

【0060】そこで、工事管理システムを用いて、まず
工事データを作成する。
Therefore, first, construction data is created using the construction management system.

【0061】工事データは、図6(C)に示すように、
元図面上で矩形枠を入力するだけで、図面データと属性
データの両方を同時に工事データとすることができる。
The construction data is, as shown in FIG.
By simply inputting a rectangular frame on the original drawing, both the drawing data and the attribute data can be used as construction data at the same time.

【0062】次に、工事設計書を作成するために、工事
データを加工する。
Next, construction data is processed in order to create a construction design document.

【0063】図6(D)及び図7(E)では、CAD
(計算機支援型設計システム)にて工事図面の修正等編
集を行っている。
In FIGS. 6D and 7E, the CAD
(Computer-aided design system) edits construction drawings, etc.

【0064】また、図7(F)では、増築に伴って変わ
る属性情報の修正を行っている。
In FIG. 7F, the attribute information that changes with the extension is modified.

【0065】工事設計書は、工事の完了まで保持され
る。そして、工事が完了し、元図面に反映する必要がで
きたところで、反映作業を行う。反映は、反映対象とな
る図面を選択することだけで、元図面側の図面データ及
び属性データに自動的に反映される。反映後の結果が図
7(G)及び図7(H)となる。例えば図7(G)にお
いては、工事データの反映後、自動的に元図面が修正さ
れ、図7(H)においては、工事完了後の建築物の延面
積は63m2であることが検索されている。
The construction design document is held until the completion of the construction. Then, when the construction is completed and it becomes necessary to reflect the original drawing, the reflection work is performed. The reflection is automatically reflected on the drawing data and the attribute data of the original drawing only by selecting the drawing to be reflected. The result after the reflection is shown in FIG. 7 (G) and FIG. 7 (H). For example, in FIG. 7 (G), after the construction data is reflected, the original drawing is automatically corrected, and in FIG. 7 (H), it is searched that the total area of the building after the completion of the construction is 63 m 2. ing.

【0066】次に、本発明の第2の実施例について、図
8を参照して説明する。
Next, a second embodiment of the present invention will be described with reference to FIG.

【0067】1枚の元図面に対して、工事図面は、1枚
である必要はない。工事図面同士が重ならない図8
(A)の場合はもちろん、図8(B)に示すように、工
事図面同士が重なっている場合でも、工事図面の反映方
式として、工事図面単位ごとに行っているため、元図面
側で重複に切り出されていることを認識する情報と、反
映時に重複部でどちらのデータを有効にするかを選択す
ることにより、重なりのある工事図面の管理を可能とす
る。
The construction drawing does not need to be one for one original drawing. Figure 8 where construction drawings do not overlap
In the case of (A), as shown in FIG. 8B, even if the construction drawings overlap each other, the construction drawings are reflected in the unit of the construction drawings as a reflection method of the construction drawings. It is possible to manage overlapping construction drawings by selecting information that recognizes that the drawing is cut out, and selecting which data is valid in the overlapping part at the time of reflection.

【0068】さらに、本発明の第2の実施例の変形例と
して、図8(C)に示すように、工事図面の切り出し角
度は、傾きをつけた場合であっても、可能である。切り
出し時に角度をつけて切り出し、工事設計図としては、
回転図形を出力させることで、任意の角度の工事図面を
作成することができる。
Further, as a modification of the second embodiment of the present invention, as shown in FIG. 8 (C), the cutout angle of the construction drawing can be made even if it is inclined. At the time of cutting, cut out at an angle, as a construction plan,
By outputting a rotated figure, a construction drawing at an arbitrary angle can be created.

【0069】[0069]

【発明の効果】以上説明したように、本発明によれば下
記記載の効果を奏する。
As described above, according to the present invention, the following effects can be obtained.

【0070】(1)第1の効果は、設備図面及び設備属
性データが元データと工事データとして二重管理ができ
る、ということである。これにより元データに影響を与
えることなく、工事設計が可能となる。
(1) The first effect is that the equipment drawing and the equipment attribute data can be dually managed as the original data and the construction data. This enables construction design without affecting the original data.

【0071】その理由は、本発明においては、工事図面
及び工事属性データを、工事図面切り出し時に別のデー
タベースに情報を切り出して登録するため、データに変
更を加えても、元図には影響が及ばないことによる。
The reason is that, in the present invention, the construction drawing and the construction attribute data are extracted and registered in another database when the construction drawing is cut out, so that even if the data is changed, the original drawing is not affected. It does not reach.

【0072】(2)第2の効果は、工事情報も同時に管
理できる、ということである。これにより、工事の実施
時期等の工事の履歴管理が可能となる。
(2) The second effect is that construction information can be managed at the same time. As a result, it is possible to manage the history of the work such as the execution time of the work.

【0073】その理由は、本発明においては、工事図面
を管理するために、工事図面にはそれぞれに工事情報を
入力しており、この工事情報を利用することにより、図
面と属性情報の管理のみならず、工事の履歴も把握でき
る、ためである。
The reason is that, in the present invention, in order to manage construction drawings, construction information is input to each construction drawing, and by using this construction information, only the management of drawings and attribute information is performed. In addition, the construction history can be grasped.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施の形態に係る設備管理システムの
システム構成を示す図である。
FIG. 1 is a diagram showing a system configuration of a facility management system according to an embodiment of the present invention.

【図2】本発明の実施の形態の工事管理方式の処理動作
を説明するためのフローチャートである。
FIG. 2 is a flowchart illustrating a processing operation of a construction management system according to the embodiment of the present invention.

【図3】本発明の実施の形態における切り出し処理の動
作を説明するためのフローチャートである。
FIG. 3 is a flowchart for explaining an operation of a cutout process according to the embodiment of the present invention.

【図4】本発明の実施の形態における工事データ加工処
理の動作を説明するためのフローチャートである。
FIG. 4 is a flowchart illustrating an operation of construction data processing according to the embodiment of the present invention.

【図5】本発明の実施の形態における工事データ反映処
理の動作を説明するためのフローチャートである。
FIG. 5 is a flowchart for explaining the operation of construction data reflection processing in the embodiment of the present invention.

【図6】本発明の実施例を説明するための図であり、設
備管理システム上での工事管理方式の表示画面を模式的
に示す図である。
FIG. 6 is a diagram for explaining the embodiment of the present invention, and is a diagram schematically showing a display screen of a construction management system on the equipment management system.

【図7】本発明の実施例を説明するための図であり、設
備管理システム上での工事管理方式の表示画面を模式的
に示す図である。
FIG. 7 is a diagram for explaining the embodiment of the present invention, and is a diagram schematically showing a display screen of a construction management system on the equipment management system.

【図8】本発明の別の実施の形態を説明するための図で
ある。
FIG. 8 is a diagram for explaining another embodiment of the present invention.

【符号の説明】[Explanation of symbols]

10 設備管理システム 11 入出力装置 20 入出力制御部 21 設備データ検索手段 22 設備データ加工手段 23 工事管理システム 24 図面記憶部 25 属性記憶部 30 図面検索機能 31 属性検索機能 32 図面加工機能 33 属性加工機能 40 工事データ切り出し手段 41 工事データ反映手段 42 工事情報管理手段 43 工事図面記憶部 44 工事属性記憶部 45 工事情報記憶部 50 図面切り出し機能 51 属性反映機能 52 図面反映機能 53 属性反映機能 54 工事情報入力機能 55 工事情報検索機能 Reference Signs List 10 equipment management system 11 input / output device 20 input / output control unit 21 equipment data search means 22 equipment data processing means 23 construction management system 24 drawing storage unit 25 attribute storage unit 30 drawing search function 31 attribute search function 32 drawing processing function 33 attribute processing Function 40 Construction data extraction means 41 Construction data reflection means 42 Construction information management means 43 Construction drawing storage unit 44 Construction attribute storage unit 45 Construction information storage unit 50 Drawing extraction function 51 Attribute reflection function 52 Drawing reflection function 53 Attribute reflection function 54 Construction information Input function 55 Construction information search function

───────────────────────────────────────────────────── フロントページの続き (51)Int.Cl.6 識別記号 庁内整理番号 FI 技術表示箇所 G06F 15/62 K ──────────────────────────────────────────────────続 き Continued on the front page (51) Int.Cl. 6 Identification code Agency reference number FI Technical display location G06F 15/62 K

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】管理対象設備に関する図面情報と属性情報
とを一元管理する設備管理システムにおいて、 工事状況を管理するための図面情報及び属性情報を工事
管理システムとして、設備管理の情報との二重管理可能
とする手段を備えたことを特徴とする工事図面管理方
式。
An equipment management system for centrally managing drawing information and attribute information on equipment to be managed, wherein the drawing information and attribute information for managing the construction status are used as a construction management system, and the information on the equipment management is duplicated. A construction drawing management system, characterized by comprising means for enabling management.
【請求項2】前記設備管理システムの情報から、工事管
理システムにおける工事範囲に該当する図面情報を属性
情報とともに切り出す手段を備えたことを特徴とする請
求項1記載の工事図面管理方式。
2. The construction drawing management system according to claim 1, further comprising means for cutting out drawing information corresponding to a construction range in the construction management system together with attribute information from the information of the equipment management system.
【請求項3】前記設備管理システムの情報に影響を及ぼ
すことなく、前記図面情報及び属性情報を追加及び修正
する手段を備えたことを特徴とする請求項1又は2記載
の工事図面管理方式。
3. The construction drawing management system according to claim 1, further comprising means for adding and correcting said drawing information and attribute information without affecting information of said equipment management system.
【請求項4】工事完了時に、工事情報を正規の設備情報
とするために、工事管理システムのもつ図面情報及び属
性情報を、前記設備管理システムの図面情報及び属性情
報に対して、変更部分のみ反映させる手段を備えたこと
を特徴とする請求項1又は2記載の工事図面管理方式。
4. When the construction is completed, the drawing information and the attribute information of the construction management system are replaced with the drawing information and the attribute information of the facility management system only in a changed part in order to make the construction information regular equipment information. 3. The construction drawing management system according to claim 1, further comprising a reflecting unit.
【請求項5】工事開始時に、工事範囲部について、設備
管理システムが備える図面情報及び属性情報を切り出
し、その写しを工事図面情報、及び工事属性情報として
記憶する手段と、 前記切り出された工事図面情報、及び工事属性情報につ
いて、前記設備管理システムに具備されたデータ加工手
段を用いて加工がなされ、さらに、 工事履歴を管理するための工事情報管理手段と、 工事完了時は、工事情報を元に、工事図面情報及び工事
属性情報を前記設備管理システムの元データに反映する
手段と、 を備えたことを特徴とする工事管理システム。
5. A means for extracting drawing information and attribute information provided in a facility management system for a construction area at the start of construction, and storing a copy of the information as construction drawing information and construction attribute information; Information and construction attribute information are processed using the data processing means provided in the equipment management system. Further, construction information management means for managing the construction history, and when the construction is completed, the Means for reflecting construction drawing information and construction attribute information in the original data of the equipment management system.
JP21509096A 1996-07-26 1996-07-26 Construction drawing management system Pending JPH1040285A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21509096A JPH1040285A (en) 1996-07-26 1996-07-26 Construction drawing management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP21509096A JPH1040285A (en) 1996-07-26 1996-07-26 Construction drawing management system

Publications (1)

Publication Number Publication Date
JPH1040285A true JPH1040285A (en) 1998-02-13

Family

ID=16666593

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21509096A Pending JPH1040285A (en) 1996-07-26 1996-07-26 Construction drawing management system

Country Status (1)

Country Link
JP (1) JPH1040285A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11312233A (en) * 1998-04-27 1999-11-09 Hitachi Ltd Graphic data managing method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11312233A (en) * 1998-04-27 1999-11-09 Hitachi Ltd Graphic data managing method

Similar Documents

Publication Publication Date Title
US6636774B2 (en) CAD supporting apparatus, and CAD supporting program storage medium
US7386793B2 (en) Apparatus, method and program for supporting a review
JP2008217651A (en) Design support device, design support method and program
JPH1040285A (en) Construction drawing management system
JP3887571B2 (en) Software design requirement extraction support method, software design requirement determination support method, software design support method, and program
JP3441155B2 (en) Information management search device
JP2003150762A (en) Cooperation method for project information and its system
KR20020045008A (en) management system for information of drawing and operation method for this system
JP3167412B2 (en) Database search processor
JPH10171784A (en) Device for preparing document
JP2000148232A (en) Display image data generation system of central monitor and control equipment
JPH0795267B2 (en) How to reuse software specifications
JPH08202769A (en) Document preparing device
JP2000284827A (en) Design assisting device for plant screen
JPH1185582A (en) Data processor
JP2671345B2 (en) Computer system product management support device and support method
JP3889067B2 (en) Document management apparatus and document management method
JPH0713752A (en) Control method/device for program revision
JP2020161102A (en) Drawing creation support device, drawing creation support program and drawing creation support method
JPH08221265A (en) Supporting device for developing software
JPH0744359A (en) Memo document preparing method and memo document selecting method in case tool
JP2011003130A (en) Program, method and device for managing information
JPH09212354A (en) Visual programming system
JPH06139061A (en) Program specification inverse preparing method
JPH0535802A (en) Album type image database system

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 19990601