JPH10139377A - Safety device of walking crane - Google Patents

Safety device of walking crane

Info

Publication number
JPH10139377A
JPH10139377A JP30712396A JP30712396A JPH10139377A JP H10139377 A JPH10139377 A JP H10139377A JP 30712396 A JP30712396 A JP 30712396A JP 30712396 A JP30712396 A JP 30712396A JP H10139377 A JPH10139377 A JP H10139377A
Authority
JP
Japan
Prior art keywords
jib
boom
pin
bracket
switch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP30712396A
Other languages
Japanese (ja)
Other versions
JP3716952B2 (en
Inventor
Yoshitoshi Sawafuji
佐敏 澤藤
Mitsuo Oya
光雄 大矢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Komatsu Ltd
Komatsu MEC Corp
Original Assignee
Komatsu Ltd
Komatsu MEC Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Komatsu Ltd, Komatsu MEC Corp filed Critical Komatsu Ltd
Priority to JP30712396A priority Critical patent/JP3716952B2/en
Publication of JPH10139377A publication Critical patent/JPH10139377A/en
Application granted granted Critical
Publication of JP3716952B2 publication Critical patent/JP3716952B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

PROBLEM TO BE SOLVED: To surely prevent a fall accident of a jib by controlling to stop crane work or a part of the operation, or give a warning by a warning means according to the status of a lock pin insert detector, a jib housing completion detector, and an upper part work mode switch for selecting a work mode. SOLUTION: One of a single top mode, a jib mode, a preparation mode is selected by an upper work mode switch 71, lock pin insertion is detected by a lock pin insert detector 70, and it is detected by a jib housing completion detector 33b that the jib is located in the housing position. According to the status of the switch 71 and the detectors 70, 33b depending on the detection signals, crane work or partial operation is stopped by a moment limiter controller 52 or a warning is given by a buzzer and displayed on a moment limiter display panel 40. Thus, it is possible to prevent a fall of a jib due to forgetting to insert a pin while the jib is projected and housed.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は移動式クレーンにお
ける安全装置に関し、特に作業モードスイッチの選択操
作ミス、および移動式クレーンの作業状態をチェックし
て、ジブの落下を防止するようにした移動式クレーンに
おける安全装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a safety device for a mobile crane, and more particularly to a mobile crane that checks the erroneous operation of a work mode switch and the working condition of the mobile crane to prevent the jib from falling. The present invention relates to a safety device for a crane.

【0002】[0002]

【従来の技術】移動式クレーンは、車体上に伸縮自在な
ブームを起伏自在に、かつ旋回自在に設けて、これらの
伸縮、起伏及び旋回の各操作によって吊り荷作業が行わ
れる。しかし、前記伸縮、起伏及び旋回の各操作による
作業可能範囲を拡大する必要がある場合には、ブームの
先端部にジブを装着して作業範囲を拡大できるようなジ
ブ装着型の移動式クレーンが使用される。このようなジ
ブ装着型の移動式クレーンの従来技術としては、例えば
図24〜図33に示すように、第1の従来技術として
「実開平5−44990号」公報、および第2の従来技
術として「実開平6−76283号」公報がある。
2. Description of the Related Art A mobile crane is provided with a telescopic boom on a vehicle body so as to be able to move up and down and swing freely. However, when it is necessary to expand the workable range by each of the above-mentioned expansion, contraction, undulation, and turning operations, a jib-mounted mobile crane that can expand the workable range by attaching a jib to the end of the boom is used. used. As a prior art of such a jib-mounted mobile crane, for example, as shown in FIGS. 24 to 33, as a first prior art, Japanese Utility Model Laid-Open No. 5-44990, and as a second prior art There is "Japanese Utility Model Laid-Open No. 6-76283".

【0003】第1および第2の従来技術は、図24にお
いて前後左右に車輪を有する下部走行体1の略中央の上
部に旋回自在に上部旋回体8を設け、上部旋回体8上に
は伸縮自在なブーム3を起伏自在に設けている。また、
上部旋回体8上の前方側面側には走行操作や作業機操作
が可能な運転室9が配設されている。ブーム3は多段伸
縮ブームであって、基段ブーム4乃至トップブーム6か
らなっている。また移動式クレーンの走行時等にはブー
ム3の側面にジブ7が装着されている。このジブ7は、
作業時に必要に応じて図29に示すロックピン(19a) 回
りに回動して、ブーム3の側面からブーム先端部に張り
出され、図31に示すようにブーム先端部に連結される
ようになっている。
In the first and second prior arts, an upper revolving structure 8 is provided so as to be rotatable at an upper portion substantially at the center of a lower traveling structure 1 having wheels in front, rear, left and right in FIG. A flexible boom 3 is provided so that it can be raised and lowered. Also,
A driver's cab 9 in which a traveling operation and a work machine operation can be performed is disposed on a front side surface of the upper revolving superstructure 8. The boom 3 is a multi-stage telescopic boom, and includes a base boom 4 to a top boom 6. A jib 7 is mounted on the side surface of the boom 3 when the mobile crane travels. This jib 7
At the time of work, it is rotated around the lock pin (19a) shown in FIG. 29 as necessary, so that it protrudes from the side surface of the boom 3 to the boom tip and is connected to the boom tip as shown in FIG. Has become.

【0004】このようなジブ装着型の移動式クレーンに
おけるジブ7の張出、格納装置を図面を参照しながら詳
細に説明する。図25はジブ7の格納状態を表す平面
図、図26は図25のトップブーム6とジブ7との連結
部詳細平面図、図27は張出状態での連結部側面図を表
している。基段ブーム4の側面後部にジブ7の固定用の
ラグ81が設けられ、ラグ81にジブ7の先端部に設け
られたラグ82がピン83により連結されている。ま
た、基段ブーム4の側面中央部にはラグ85が設けら
れ、ラグ85にジブ7の中央部に設けられたつの84が
係止され、ピン80により連結されている。
The extension and storage of the jib 7 in such a jib-mounted mobile crane will be described in detail with reference to the drawings. 25 is a plan view showing the stored state of the jib 7, FIG. 26 is a detailed plan view of the connecting portion between the top boom 6 and the jib 7 in FIG. 25, and FIG. 27 is a side view of the connecting portion in the extended state. A lug 81 for fixing the jib 7 is provided at a rear portion of the side surface of the base boom 4, and a lug 82 provided at the tip of the jib 7 is connected to the lug 81 by a pin 83. A lug 85 is provided at the center of the side surface of the base boom 4, and two lugs 84 provided at the center of the jib 7 are locked to the lug 85 and connected by pins 80.

【0005】図26に示すように、トップブーム6の先
端側面の左右にはラグ87a、87bが設けられ、ジブ
7の基端部にはトップブーム6のラグ87a、87bと
ジブ7をそれぞれ連結するロックピン19a、19bが
設けられている。ロックピン19a、19bは、それぞ
れを抜き差しするためのロックシリンダ17、18が取
着されている。また、ジブ7の基端部上面にはジブ7の
振出し(ピン80の回りにジブ7を回動すること)、張
出及び格納用の回動シリンダ63がそのチューブ側をピ
ン99によって回動自在に設けられている。回動シリン
ダ63のロッド側はリンク92及びリンク93の連結部
にピン96で回動自在に接続されている。またリンク9
3の他端側はジブ7の上面にピン97により回動自在に
取着され、リンク92の他端側は格納時にジブ7の上面
にピン94により回動自在に取着されている。
As shown in FIG. 26, lugs 87a and 87b are provided on the left and right sides of the tip side of the top boom 6, and lugs 87a and 87b of the top boom 6 are connected to the jib 7 at the base end of the jib 7. Lock pins 19a and 19b are provided. Lock cylinders 17 and 18 for attaching and removing the lock pins 19a and 19b are attached. On the upper surface of the base end of the jib 7, the rotation cylinder 63 for swinging out the jib 7 (rotating the jib 7 around the pin 80), extending and storing the tube is rotated by the pin 99 on the tube side. It is provided freely. The rod side of the rotary cylinder 63 is rotatably connected to a link between the link 92 and the link 93 by a pin 96. Link 9
The other end of 3 is rotatably attached to the upper surface of jib 7 by a pin 97, and the other end of link 92 is rotatably attached to the upper surface of jib 7 by a pin 94 during storage.

【0006】また、トップブーム6の上面にはスイッチ
ボックス89が配設されている。このスイッチボックス
89には、ロックシリンダ17、18及び回動シリンダ
63を操作するためのスイッチ(図示せず)が収納され
ている。さらに、上記のジブ7を基段ブーム4に固定す
るピン83、ピン80、リンク92を固定するピン9
4、ピン98等は、トップブーム6の上面から容易に抜
き差し可能なように位置している。
A switch box 89 is provided on the top surface of the top boom 6. The switch box 89 houses switches (not shown) for operating the lock cylinders 17 and 18 and the rotating cylinder 63. Further, a pin 83 for fixing the jib 7 to the base boom 4, a pin 80, and a pin 9 for fixing the link 92.
4. The pins 98 and the like are positioned so that they can be easily inserted and removed from the upper surface of the top boom 6.

【0007】第2の従来技術は、第1の従来技術におい
て図32(A)に示すように、図25に示すような基段
ブーム4の側面に設けられラグ85と、ジブ7に設けら
れたつの84とを連結するピン80を検出するリミット
スイッチ86が基段ブーム4に設置されている。また図
32(B)に示すように、図25に示すような基段ブー
ム4の側面に設けられラグ81と、ジブ7に設けられた
ラグ82とを連結するピン83を検出するリミットスイ
ッチ88が基段ブーム4に設置されている。図33に示
すように、トップブーム6用伸縮シリンダ141の駆動
回路には、トップブーム6の伸長側となる方向切換弁1
43のパイロット回路を開閉するソレノイド弁147が
介設されている。これらリミットスイッチ86,88
は、常時開接点同志および常時閉接点同志をそれぞれ直
列に接続したものを並列に接続した回路を、電源90と
ソレノイド弁147間に直列に接続した。
[0007] The second prior art is different from the first prior art in that a lug 85 provided on the side surface of the base boom 4 and a jib 7 as shown in FIG. A limit switch 86 for detecting a pin 80 connecting the pinion 84 is installed on the base boom 4. Further, as shown in FIG. 32B, a limit switch 88 for detecting a pin 83 connecting a lug 81 provided on the side surface of the base boom 4 and a lug 82 provided on the jib 7 as shown in FIG. Is installed on the base boom 4. As shown in FIG. 33, the drive circuit of the telescopic cylinder 141 for the top boom 6 includes a direction switching valve 1 on the extension side of the top boom 6.
A solenoid valve 147 for opening and closing the 43 pilot circuit is provided. These limit switches 86, 88
A circuit in which normally open contacts and normally closed contacts are connected in series, respectively, is connected in parallel, and a circuit is connected between the power supply 90 and the solenoid valve 147 in series.

【0008】第1の従来技術、および第2の従来技術は
次のように作用する。図26に示すようにジブ張出のと
きは、作業者はまずトップブーム6の上面に乗り、リン
ク92をジブ7に取着しているピン94を抜く。そし
て、スイッチボックス89のスイッチを操作して回動シ
リンダ63を作動してリンク92の先端部の孔をトップ
ブーム6の上面側端部に設けられた孔95に一致させ、
ピン98を孔95に挿入してリンク92とトップブーム
6を連結する。次に、図25に示すジブ7の先端部を基
段ブーム4に固定しているピン83を抜き、スイッチボ
ックス89により回動シリンダ63を作動して、図2
8、図29に示すようにジブ7をピン80の回りに振出
し、ジブ7の基端部のロックピン19aをトップブーム
6の先端部のラグ87aの孔に一致させる。この状態
で、図27に示すロックシリンダ17を操作してロック
ピン19aを挿入し、ラグ87aがジブ7に連結され
る。この後、ジブ7の中央部のつの84を固定している
ピン80を抜き、、図30に示すように運転室9内の操
作レバーによってブーム3を伸長し、ジブ7を支持して
いるつの84をラグ85から外す。これによりジブ7は
ロックピン19a及びピン98によって支持されること
になる。
[0008] The first prior art and the second prior art operate as follows. As shown in FIG. 26, when the jib is overhanging, the operator first gets on the upper surface of the top boom 6 and pulls out the pin 94 attaching the link 92 to the jib 7. Then, the switch of the switch box 89 is operated to operate the rotary cylinder 63 so that the hole at the distal end of the link 92 matches the hole 95 provided at the upper surface side end of the top boom 6,
The pin 98 is inserted into the hole 95 to connect the link 92 to the top boom 6. Next, the pin 83 that fixes the tip end of the jib 7 shown in FIG. 25 to the base boom 4 is pulled out, and the rotating cylinder 63 is operated by the switch box 89, and FIG.
8. As shown in FIG. 29, the jib 7 is swung around the pin 80, and the lock pin 19a at the base end of the jib 7 is aligned with the hole of the lug 87a at the tip of the top boom 6. In this state, the lock pin 19a is inserted by operating the lock cylinder 17 shown in FIG. 27, and the lug 87a is connected to the jib 7. Thereafter, the pin 80 fixing the two pieces 84 at the center of the jib 7 is pulled out, and the boom 3 is extended by the operation lever in the cab 9 as shown in FIG. Remove 84 from lug 85. As a result, the jib 7 is supported by the lock pin 19a and the pin 98.

【0009】次に、運転席9内の操作レバー又はスイッ
チボックス89内のスイッチの操作を行って回動シリン
ダ63を作動させてジブ7をロックピン19aの回りに
回動し、図31に示すようにブーム3の前方に張り出
す。スイッチボックス89によってロックシリンダ18
を作動してロックピン19bをトップブーム6のラグ8
7bの孔に挿入する。これによって、ジブ7とトップブ
ーム6との連結作業が完了する。ジブ7の格納作業は、
これまでと逆の手順で行なう。このようにして、作業者
は運転室9内又はトップブーム6の上部に乗って各シリ
ンダや作業機を操作し、ジブ7の張出及び格納作業を行
う。これと同時に作業者は各作業工程の完了、例えばロ
ックシリンダ17によりロックピン19aがラグ87a
の孔に確実に挿入されたこと等をトップブーム6の上部
で確認してから次の工程に進むようにしている。
Next, the operating lever in the driver's seat 9 or the switch in the switch box 89 is operated to operate the rotating cylinder 63 to rotate the jib 7 around the lock pin 19a, as shown in FIG. To the front of the boom 3 as shown. Lock cylinder 18 by switch box 89
To lock the lock pin 19b to the lug 8 of the top boom 6.
7b. Thereby, the connection work between the jib 7 and the top boom 6 is completed. The work of storing jib 7
Perform the procedure in the reverse order. In this way, the operator operates the cylinders and the working machines in the operator's cab 9 or on the top of the top boom 6 to extend and store the jib 7. At the same time, the worker completes each work process, for example, the lock pin 19a
After confirming at the upper part of the top boom 6 that the plug has been securely inserted into the hole, the process proceeds to the next step.

【0010】図33において、ピン80とピン83との
いずれか一方が挿入されている状態では、伸縮シリンダ
15が絶対に伸びないので、トップブーム6操作弁を誤
操作してもジブ7やラグ81,82,84,85等の破
損が防止される。
In FIG. 33, when one of the pins 80 and 83 is inserted, the telescopic cylinder 15 never extends, so that the jib 7 and the lug 81 are operated even if the operation valve of the top boom 6 is erroneously operated. , 82, 84, 85, etc., are prevented.

【0011】第3の従来技術は、第1、第2の従来技術
において、ジブ7のつの84を上下に二つ設置し、この
つの84が貫入する各穴をラグ85に設置することによ
り、ピン80を省略した構成であり、これによってジブ
7の張出・格納作業を大幅に簡略化したものである。
[0011] A third prior art is different from the first and second prior arts in that two pieces 84 of the jib 7 are installed on the upper and lower sides, and each hole through which the two pieces 84 penetrate is installed on the lug 85. The configuration is such that the pins 80 are omitted, thereby greatly simplifying the operation of extending and storing the jib 7.

【0012】[0012]

【発明が解決しようとする課題】しかしながら、前記第
1、第2の従来技術では次の問題点がある。 (1) ジブの張出、格納装置においては、作業者はブーム
3上に居て作業をしなければならないことが多いので、
高所及び狭所での作業における危険性が常に伴うことに
なる。 (2) 作業工程によっては工程完了の確認が非常に重要な
ものもある。例えば、ロックシリンダ17の操作でロッ
クピン19aをラグ87aの孔に挿入したときに完全に
挿入されない状態で、ピン80を抜いてブーム3を伸長
すると、ブーム3とジブ7との連結が外れ、ジブ7が落
下する危険性がある。 (3) ジブ7の格納時に、つの84とラグ85がピン80
によって連結されない状態で、ロックピン19aを抜い
てしまうと、同様にジブ7が落下する危険性がある。 (4) このような工程では工程完了(ピン挿入完了)の確
認を確実に行う必要があるが、従来は作業者の確認に頼
っているので作業者への負担が大きくなり過ぎて作業時
の疲労を増大すると共に、もし誤ってこの確認が不十分
であった場合は前記のような事故が発生する可能性があ
る。
However, the first and second prior arts have the following problems. (1) In the case of the jib overhanging and storage device, the worker often needs to be on the boom 3 and work.
There is always the danger of working at heights and in narrow places. (2) For some work processes, it is very important to confirm the completion of the process. For example, if the pin 80 is pulled out and the boom 3 is extended in a state where the lock pin 19a is not completely inserted when the lock pin 19a is inserted into the hole of the lug 87a by operating the lock cylinder 17, the connection between the boom 3 and the jib 7 is released. There is a risk that the jib 7 will fall. (3) When the jib 7 is stored, the two pins 84 and the lugs 85
If the lock pin 19a is pulled out in a state where the jib 7 is not connected, there is a danger that the jib 7 will similarly fall. (4) In such a process, it is necessary to securely confirm the completion of the process (pin insertion completed). However, since the conventional method relies on the confirmation of the operator, the burden on the operator becomes too large, In addition to increasing fatigue, if this confirmation is insufficient by mistake, the above-mentioned accident may occur.

【0013】また第3の従来技術では次の問題点があ
る。 (5) ジブ7の格納作業において、ジブフート部の左ピン
19aを抜いた後、ジブ格納ピン83を入れ忘れた場
合、 (6) ジブ格納時における整備中でジブ格納ピン83を抜
いて作業する場合、 (7)ジブ格納時にいたずらされてジブ格納ピン83が抜
かれていた場合、以上の場合には、これを検出してイン
タロックをかけることがないため、ブーム3を伸長操作
するとジブ7が落下する恐れがあった。
The third conventional technique has the following problems. (5) When the jib 7 is retracted, the jib foot pin 83 is pulled out, and then the jib storage pin 83 is forgotten to be inserted. (6) When the jib is stored during maintenance, the jib storage pin 83 is pulled out for work. (7) If the jib storage pin 83 has been pulled out due to mischief when the jib is stored, in this case, the jib 7 is dropped when the boom 3 is extended since the interlock is not detected by detecting this. There was a fear of doing.

【0014】本発明は、上記の問題点に着目してなされ
たものであり、作業者のブーム上での作業を少なくして
安全性を向上すると共に、ピン連結完了の不十分な確認
によるジブの落下事故等の発生を防止し、かつクレーン
作業状態をチェックする移動式クレーンの安全装置を提
供することを目的としている。
SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned problems. The present invention has been made to improve the safety by reducing the work of the operator on the boom and to improve the jib by insufficiently confirming the completion of the pin connection. An object of the present invention is to provide a safety device for a mobile crane that prevents the occurrence of a fall accident or the like and that checks the crane working state.

【0015】[0015]

【課題を解決するための手段、作用及び効果】上記の目
的を達成するために、本発明の第1発明に係る移動式ク
レーンにおける安全装置は、伸縮自在なブーム3と、こ
のブーム3の側方に固定手段30により支持されて格納
されるジブ7と、このジブ7のブラケット7とブーム3
先端の左右いずれか一方のブラケット61とに出入する
ロックピン19aとを有し、前記ジブ7使用時にはブラ
ケット15とブラケット61とに挿入されたロックピン
19aを中心に、ブーム3の側方に格納されたジブ7を
ブーム3の前方に回動して張出す移動式クレーンにおけ
る安全装置において、
To achieve the above object, a safety device for a mobile crane according to the first invention of the present invention comprises a telescopic boom 3 and a side of the boom 3. The jib 7 supported and stored by the fixing means 30 and the bracket 7 and the boom 3 of the jib 7
A lock pin 19a which enters and exits one of the right and left brackets 61, and is stored on the side of the boom 3 around the lock pin 19a inserted into the bracket 15 and the bracket 61 when the jib 7 is used. In a safety device for a mobile crane that rotates the extended jib 7 in front of the boom 3 to extend it,

【0016】ロックピン19aがブラケット15,16
に挿入されたことを検出するロックピン挿入検出器70
と、固定手段30の孔31aに挿入されて、ブーム3に
格納されたジブ7を固定するためのジブ格納ピン33
と、このジブ格納ピン33が孔31aに挿入されている
こと、またはジブ7がジブ格納位置にあることを検出す
るジブ格納完了検出器33b,33cと、ジブ7の格納
位置におけるブームまたはシングルトップモードと、ジ
ブ7の張出位置におけるジブモードと、ジブ7の張出、
格納操作を行う準備モードのいずれかの作業モードを選
択する上部作業モードスィッチ71と、これら検出器7
0,33b,33cと、スイッチ71の状況によりクレ
ーン作業、もしくはその一部操作を停止するか、あるい
は警報手段により警告するコントローラ52とを備えた
ことを特徴とする。
The lock pins 19a are connected to the brackets 15,16.
Lock pin insertion detector 70 for detecting insertion into
And a jib storage pin 33 inserted into the hole 31a of the fixing means 30 to fix the jib 7 stored in the boom 3.
Jib storage completion detectors 33b and 33c for detecting that the jib storage pin 33 is inserted into the hole 31a or that the jib 7 is at the jib storage position, and a boom or single top at the storage position of the jib 7 Mode, the jib mode at the overhang position of the jib 7, the overhang of the jib 7,
An upper operation mode switch 71 for selecting one of the operation modes of the preparation mode for performing the storing operation;
0, 33b, and 33c, and a controller 52 that stops the crane operation or a partial operation thereof according to the state of the switch 71, or warns by an alarm unit.

【0017】第1の発明によれば、ジブ格納時の格納
ピン33の入れ忘れによるジブ7の落下防止。ジブ張
出、格納作業中のロックピン19a、格納ピン33の入
れ忘れによるジブ7の落下防止。ジブ張出状態で上部
作業モードスイッチ71をブームモードに誤設定したこ
とを警告する。ジブ7を格納している時に上部作業モ
ードスイッチ71をジブモードに誤設定することを防止
するようにコントローラ52により自動的に制御する。
従ってジブ7の落下事故等を確実に防止できるため、ク
レーン作業の安全性が向上すると共に、確認作業が不要
となり作業者の疲労を大幅に軽減できる。
According to the first aspect, the jib 7 is prevented from falling due to forgetting to insert the storage pin 33 when the jib is stored. Prevents the jib 7 from falling due to forgetting to insert the lock pin 19a and the storage pin 33 during the jib overhang and the storage operation. It warns that the upper work mode switch 71 has been incorrectly set to the boom mode with the jib extended. The controller 52 automatically controls the upper work mode switch 71 to prevent the erroneous setting of the jib mode when the jib 7 is stored.
Therefore, since the fall accident of the jib 7 can be reliably prevented, the safety of the crane operation is improved, and the checking operation is not required, and the fatigue of the operator can be greatly reduced.

【0018】本発明の第2発明に係る移動式クレーンに
おける安全装置は、第1発明において、作業モードスィ
ッチ71で選択した各作業モードにおいて、コントロー
ラ52がロックピン挿入検出器70、およびジブ格納完
了検出器33b,33cからの検出信号を共に入力しな
いときには、警報ランプを点灯するか、警報ブザーを発
報するか、モニタパネルに文字によりディスプレイする
かの少なくとも一つにより警告するコントローラ52と
を備えたことを特徴とする。
In the safety device for a mobile crane according to the second invention of the present invention, in the first invention, in each work mode selected by the work mode switch 71, the controller 52 controls the lock pin insertion detector 70 and the jib storage completion. A controller 52 is provided for warning when at least one of the detection signals from the detectors 33b and 33c is not input, by turning on an alarm lamp, issuing an alarm buzzer, or displaying characters on a monitor panel. It is characterized by having.

【0019】第2発明によれば、コントローラ52がロ
ックピン挿入検出器70、およびジブ格納完了検出器3
3b,33cからの検出信号を共に入力しないときに
は、警報ランプを点灯するか、警報ブザーを発報する
か、モニタパネルに文字によりディスプレイするかの少
なくとも一つにより警告するか、またはブーム3伸長等
のクレーン作業の操作弁を自動的に操作不能とする。従
ってジブ7がブーム3に完全に格納されていない状態
で、不用意にブーム3伸長等のクレーン作業を行うこと
により、ジブ7がブーム3から落下するような事故を未
然に防止でき、安全性を大幅に向上することができる。
According to the second invention, the controller 52 includes the lock pin insertion detector 70 and the jib storage completion detector 3
When neither of the detection signals from 3b and 33c is input, an alarm lamp is turned on, an alarm buzzer is sounded, a warning is displayed by at least one of characters displayed on a monitor panel, or a boom 3 is extended. Automatically disables the operating valve for crane operation. Therefore, accidents such as the jib 7 dropping from the boom 3 can be prevented by performing crane operations such as extending the boom 3 carelessly in a state where the jib 7 is not completely stored in the boom 3, and the safety is improved. Can be greatly improved.

【0020】本発明の第3発明に係る移動式クレーンに
おける安全装置は、第1の発明において、移動式クレー
ンの走行操作と作業機操作とを選択する選択スイッチを
設置し、この選択スイッチが走行操作を選択したとき
に、ジブ格納完了検出器33b,33cの検出信号を入
力しないときには、走行中におけるジブ7の落下の危険
性を、警報ランプ、警報ブザー、あるいはメッセージ出
力等で警告するコントローラ52を備えたことを特徴と
する。
The safety device for a mobile crane according to the third invention of the present invention is the safety device according to the first invention, wherein a selection switch for selecting the traveling operation of the mobile crane and the operation of the work machine is installed, and the selection switch is driven. If the detection signal of the jib storage completion detectors 33b and 33c is not input when the operation is selected, the controller 52 warns the danger of the jib 7 falling during traveling by an alarm lamp, an alarm buzzer, a message output, or the like. It is characterized by having.

【0021】第3発明によれば、コントローラ52がジ
ブ格納完了検出器33b,33cからの検出信号を入力
しないときには、警報ランプを点灯するか、警報ブザー
を発報するか、モニタパネルにディスプレイする等によ
りジブ7がブーム3から落下する危険性を警告する。従
ってジブ7がブーム3に完全に格納されていない状態
で、不用意に移動式クレーンの走行させ場合に、ジブ7
がブーム3から落下するような事故を未然に防止でき、
安全性を大幅に向上することができる。
According to the third invention, when the controller 52 does not input the detection signals from the jib storage completion detectors 33b and 33c, the alarm lamp is turned on, the alarm buzzer is sounded, or the display is made on the monitor panel. The danger of the jib 7 dropping from the boom 3 is warned by, for example. Therefore, when the jib 7 is not completely stored in the boom 3 and the mobile crane runs carelessly,
Can be prevented from falling down from boom 3,
Safety can be greatly improved.

【0022】[0022]

【発明の実施の形態】以下、本発明の各実施例を図1〜
図23を参照して説明する。図1は、本発明に係わる移
動式クレーンの全体側面図であり、ジブ7の格納状態を
表している。図1においては、前記従来技術と同様な部
材には同一符号を付しその説明を省略する。ジブ7は車
体1に起伏可能に装着されたブーム3の左側方(右側方
でも可)に格納されている。ジブ7は、基端側のジブブ
ラケット11と先端側のジブ本体12とからなってい
る。ジブブラケット11とジブ本体12とは水平なピン
13によって起伏自在に連結されており、チルトシリン
ダ14によってピン13の回りに起伏可能となってい
る。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiments of the present invention will be described below with reference to FIGS.
This will be described with reference to FIG. FIG. 1 is an overall side view of a mobile crane according to the present invention, and shows a stored state of a jib 7. In FIG. 1, the same members as those of the above-described conventional technology are denoted by the same reference numerals, and the description thereof will be omitted. The jib 7 is stored on the left side (or right side) of the boom 3 mounted on the vehicle body 1 so as to be able to undulate. The jib 7 includes a jib bracket 11 on the proximal end side and a jib body 12 on the distal end side. The jib bracket 11 and the jib body 12 are connected by a horizontal pin 13 so as to be able to move up and down, and can be raised and lowered around the pin 13 by a tilt cylinder 14.

【0023】ジブ本体12は、図3,5、および図7に
詳細を示すような係止手段20と、図3,5、および図
8〜12に詳細を示すような固定手段30とによって、
基段ブーム4の左側面に固定されている。また、ジブ本
体12の先端上面にはアイドラシーブ123が配設さ
れ、先端部にジブシーブ124を設けている。ジブブラ
ケット11の基端部の左右には、図2,4,12,13
に詳細を示すように、それぞれ上下にブーム3との連結
用の左ブラケット15,15、および右ブラケット1
6,16(ブーム3の基端部から先端方向に向かい左右
を定める。以後同様とする)が設けられ、これら各左ブ
ラケット15と右ブラケット16の間には、それぞれ連
結用のロックピン19a,19bを挿入するためにロッ
クシリンダ17、18が配設されている。さらに、トッ
プブーム6の先端部にはトップシーブ(以後、シングル
トップと呼ぶ)125が設けられ、シングルトップ12
5を介して補巻ロープ121の先端に設けた補フック1
22が備えられている。
The jib body 12 is secured by a locking means 20 as shown in detail in FIGS. 3, 5 and 7 and a fixing means 30 as shown in FIGS. 3, 5 and 8 to 12 in detail.
It is fixed to the left side surface of the base boom 4. An idler sheave 123 is provided on the upper surface of the distal end of the jib body 12, and a jib sheave 124 is provided at the distal end. The left and right sides of the base end of the jib bracket 11 are shown in FIGS.
As shown in detail in FIG. 1, left and right brackets 15 and 15 for connecting to the boom 3 and a right bracket 1
6 and 16 (the left and right sides are determined from the base end of the boom 3 toward the distal end. The same applies hereinafter). Lock cylinders 17, 18 are provided for inserting the 19b. Further, a top sheave (hereinafter, referred to as a single top) 125 is provided at a distal end of the top boom 6, and a single top 12 is provided.
5 is an auxiliary hook 1 provided at the tip of the auxiliary rope 121 via
22 are provided.

【0024】図2は、ジブ7の格納状態におけるトップ
ブーム6の先端部、およびジブブラケット11の連結部
の平面図を表している。ジブブラケット11の上部には
回動シリンダ63が配設されていて、回動シリンダ63
のチューブ側はジブブラケット11の上面に回動自在に
取着され、ロッド側は第2リンク65の中央部に回動自
在に取着されている。第2リンク65の一端側はジブブ
ラケット11の上面に回動自在に取着されており、他端
側は第1リンク64の一端に回動自在に接続されてい
る。また、第1リンク64の他端は第3リンク66の一
端に回動自在に接続され、第3リンク66の他端はロッ
クピン19a(以後「左ピン19a」と記す)の後述す
るボス131に回動自在に接続されている。
FIG. 2 is a plan view of the tip of the top boom 6 and the connecting portion of the jib bracket 11 when the jib 7 is stored. A turning cylinder 63 is provided on the upper part of the jib bracket 11.
The tube side is rotatably attached to the upper surface of the jib bracket 11, and the rod side is rotatably attached to the center of the second link 65. One end of the second link 65 is rotatably attached to the upper surface of the jib bracket 11, and the other end is rotatably connected to one end of the first link 64. The other end of the first link 64 is rotatably connected to one end of a third link 66, and the other end of the third link 66 is a boss 131 of a lock pin 19a (hereinafter referred to as "left pin 19a"), which will be described later. Are rotatably connected.

【0025】トップブーム6の先端部左側の上下には、
ジブ7の連結用の左ブラケット61が設けられている。
上下の左ブラケット61にはそれぞれジブ7の左ブラケ
ット15の連結用の孔61aが設けられている。上方の
左ブラケット61には、さらに第1リンク64と第3リ
ンク66との接続部のピン67が挿入される連結用の孔
61bが設けられている。また、トップブーム6の先端
部右側の上下にはジブ7の連結用の右ブラケット62が
設けられ、上下の右ブラケット62にはそれぞれに連結
用の孔62aが設けられている。さらに、上方の左ブラ
ケット61の上面には孔61a部の上方にかけて第1ス
トッパ39が固着されており、同様にして、下方のブラ
ケット61の下面には孔61a部の下方にかけて第1ス
トッパ39が固着されている。また、トップブーム6の
左側面には、第2ストッパ42bがジブ7側に突出して
設けられている。
At the top and bottom of the left end of the top boom 6,
A left bracket 61 for connecting the jib 7 is provided.
The upper and lower left brackets 61 are provided with holes 61a for connecting the left bracket 15 of the jib 7 respectively. The upper left bracket 61 is further provided with a connection hole 61b into which a pin 67 of a connection portion between the first link 64 and the third link 66 is inserted. A right bracket 62 for connecting the jib 7 is provided above and below the right side of the tip end of the top boom 6, and a hole 62 a for connecting is provided in each of the upper and lower right brackets 62. Further, a first stopper 39 is fixed to the upper surface of the upper left bracket 61 over the hole 61a, and similarly, the first stopper 39 is secured to the lower surface of the lower bracket 61 below the hole 61a. It is fixed. A second stopper 42 b is provided on the left side surface of the top boom 6 so as to protrude toward the jib 7.

【0026】ジブブラケット11の基端部のブーム側の
上下には、トップブーム6と連結するための左ピン19
aが挿入される孔15aを有する左ブラケット15が設
けられ、ブーム側と反対側の上下にはロックピン19b
(「右ピン19b」と記す)が挿入される孔16aを有
する右ブラケット16が設けられている。さらに、上方
のブラケット15の上面で、かつ、孔15a部にはボス
131が設けられており、ボス131を孔15aが貫通
している。同様にして、下方のブラケット15の下面
で、かつ、孔15a部には孔15aが貫通したボス13
1が設けられている。また、ジブブラケット11のブー
ム側側面には、トップブーム6側に突出して第2ストッ
パ42aが設けられている。ジブ連結時に、上記上下の
ボス131をトップブーム6側の上下のブラケット61
の第1ストッパ39に押し当て、第2ストッパ42aを
トップブーム6側の第2ストッパ42bに当接させるこ
とにより、孔15aと孔61aとの位置が一致するよう
になっている。なお、第2ストッパ42a及び第2スト
ッパ42bは、いずれか一方であっても良い。
On the upper and lower sides of the base end of the jib bracket 11 on the boom side, left pins 19 for connecting to the top boom 6 are provided.
A left bracket 15 having a hole 15a into which a is inserted is provided, and lock pins 19b are provided on the upper and lower sides opposite to the boom side.
There is provided a right bracket 16 having a hole 16a into which (referred to as "right pin 19b") is inserted. Further, a boss 131 is provided on the upper surface of the upper bracket 15 and in the hole 15a, and the hole 15a penetrates the boss 131. Similarly, the lower surface of the bracket 15 and the boss 13 through which the hole 15a passes
1 is provided. A second stopper 42a is provided on the boom side surface of the jib bracket 11 so as to protrude toward the top boom 6 side. When connecting the jib, the upper and lower bosses 131 are connected to the upper and lower brackets 61 on the top boom 6 side.
Is pressed against the first stopper 39, and the second stopper 42a is brought into contact with the second stopper 42b on the top boom 6 side, so that the positions of the hole 15a and the hole 61a coincide. The second stopper 42a and the second stopper 42b may be either one.

【0027】図3は基段ブーム4とジブ本体12の中央
及び先端側の平面図である。ジブ本体12の略中央部に
は図6に詳細を示すような、ジブ7と基段ブーム4との
係止手段20が設置されている。また、ジブ本体12の
先端部分には図8〜図12に詳細を示すような、ジブ7
と基段ブーム4との固定手段30が設置されている。
FIG. 3 is a plan view of the center of the base boom 4 and the jib body 12 and the tip side thereof. At a substantially central portion of the jib body 12, a locking means 20 between the jib 7 and the base boom 4 as shown in detail in FIG. Also, a jib 7 as shown in detail in FIGS.
And a fixing means 30 for fixing the boom 4 to the base boom 4.

【0028】図3のX−X断面図である図6、および図
6のY−Y断面図である図7により係止手段20の詳細
について説明する。ジブ本体12のブーム3側の側面の
上下に、ブーム3の長手方向に突出した係止ピン21が
設けられている。上下の係止ピン21は、それぞれ基段
ブーム4側に設けられた係止ブラケット22の係止用の
孔22aに挿入されて係止されるようになっている。ま
た、係止ブラケット22の下部にはブーム3の長手方向
の孔22bを設けており、孔22bにはピン23が貫通
している。ピン23の長手方向の両端部には上下方向の
孔が設けられ、この両孔をネジ24が貫通している。両
方のネジ24の略中央で、かつ、ピン23の下方にはナ
ット24aが挿入されており、またネジ24の上下部は
基段ブーム4の側面の下部に支持されている。このよう
に、係止ブラケット22はピン23を介して両方のナッ
ト24aによって支持されている。そして、ナット24
aの位置をネジ24の方向にそって調整することによ
り、係止ブラケット22のブーム3の上下方向の位置が
調整できるようになっている。
The details of the locking means 20 will be described with reference to FIG. 6, which is a sectional view taken along line XX of FIG. 3, and FIG. 7, which is a sectional view taken along line YY of FIG. Locking pins 21 projecting in the longitudinal direction of the boom 3 are provided above and below the side surface of the jib body 12 on the boom 3 side. The upper and lower locking pins 21 are respectively inserted and locked into locking holes 22a of a locking bracket 22 provided on the base boom 4 side. A hole 22b in the longitudinal direction of the boom 3 is provided at a lower portion of the locking bracket 22, and a pin 23 penetrates the hole 22b. Vertical holes are provided at both ends in the longitudinal direction of the pin 23, and a screw 24 passes through both holes. A nut 24a is inserted substantially at the center of both screws 24 and below the pin 23, and the upper and lower portions of the screw 24 are supported by the lower portion of the side surface of the base boom 4. Thus, the locking bracket 22 is supported by the nuts 24a via the pins 23. And nut 24
By adjusting the position a along the direction of the screw 24, the vertical position of the boom 3 of the locking bracket 22 can be adjusted.

【0029】ブーム3の側面上部で、かつ、ピン23の
上方にはブラケット25が設けられており、このブラケ
ット25の上面には一対のネジ26を対向して設けてい
る。両方のネジ26はブーム3の側面に直角な方向を向
いており、その先端はお互いに対向している。また、両
方のネジ26にはそれぞれナット26aが挿入されてい
る。そして、係止ブラケット22の上部は両方のネジ2
6の先端部に挟まれた状態で支持されている。このよう
にして、ナット26aの位置を調整することによって、
係止ブラケット22のピン23の回りの傾斜を調整でき
るようになっている。
A bracket 25 is provided on the upper side surface of the boom 3 and above the pin 23, and a pair of screws 26 are provided on the upper surface of the bracket 25 to face each other. Both screws 26 face in a direction perpendicular to the side surface of the boom 3 and their tips face each other. A nut 26a is inserted into each of the screws 26. And the upper part of the locking bracket 22 has both screws 2
6 is supported in a state of being sandwiched between the tip portions. Thus, by adjusting the position of the nut 26a,
The inclination of the locking bracket 22 around the pin 23 can be adjusted.

【0030】ブラケット25の先端部には下方に延びた
支持板28が取着されていて、支持板28の下部にジブ
格納検出器29が取着されている。ジブ格納検出器29
は、ジブ7が格納完了したこと、すなわち係止ピン21
が係止ブラケット22の孔22aに完全に挿入されたこ
とを検出するものである。本実施例では、ジブ格納検出
器29の1つとして近接スイッチを使用した例を示して
おり、この近接スイッチの検知のためにジブ本体12側
に検知板29aを取着している。なお、ジブ格納検出器
29として近接スイッチを使用しているが、これに限定
されず、例えばリミットスイッチ等でもよい。
A support plate 28 extending downward is attached to the tip of the bracket 25, and a jib storage detector 29 is attached to a lower portion of the support plate 28. Jib storage detector 29
Indicates that the jib 7 has been retracted, that is, the locking pin 21
Is completely inserted into the hole 22a of the locking bracket 22. In the present embodiment, an example is shown in which a proximity switch is used as one of the jib storage detectors 29, and a detection plate 29a is attached to the jib body 12 for detecting the proximity switch. Although the proximity switch is used as the jib storage detector 29, the invention is not limited to this. For example, a limit switch may be used.

【0031】図8はジブ7をブーム3に格納する時の固
定手段30の第1実施例を示す詳細平面図であり、図9
は図8の側面図である。基段ブーム4の側面下部には側
方に突出したブラケット34が設けられていて、ジブ7
の先端部は格納状態ではこのブラケット34の上部に支
持され固定されている。ブラケット34の側面で、か
つ、ジブ7の基端部側にはジブ7の固定用の孔31aを
有するブラケット31が固着されており、また、ブラケ
ット34の側面で、かつ、ジブ7の先端部側にはジブ7
のガイド用の孔35aを有するブラケット35が取着さ
れている。ガイド用の孔35aの位置は、固定用の孔3
1aの位置よりジブ7側に近く設けている。
FIG. 8 is a detailed plan view showing a first embodiment of the fixing means 30 when the jib 7 is stored in the boom 3, and FIG.
FIG. 9 is a side view of FIG. At the lower side of the base boom 4, a bracket 34 protruding to the side is provided.
Is supported and fixed above the bracket 34 in the retracted state. A bracket 31 having a hole 31a for fixing the jib 7 is fixed to the side surface of the bracket 34 and to the base end side of the jib 7, and the side surface of the bracket 34 and the distal end portion of the jib 7. Jib 7 on the side
A bracket 35 having a guide hole 35a is attached. The position of the guide hole 35a is determined by the fixing hole 3a.
It is provided closer to the jib 7 than the position 1a.

【0032】また、ジブ本体12の側面にはブーム3側
の側方に突出したブラケット32が設けられていて、ブ
ラケット32にはジブ7の固定用の孔32aが設けられ
ている。ジブ本体12の側面には同じくブーム3側の側
方に突出したブラケット38が設けられ、基段ブーム4
のブラケット34の略中央部の上部にはピン38aを設
けている。ブラケット38のジブ先端側の側面には、ブ
ラケット36が設けられている。ジブ7の格納時には、
ブラケット38のブーム3側先端面をピン38aに当接
させることにより、ブラケット31の孔31aとブラケ
ット32の孔32aとの位置が一致するようになってい
る。そして、このとき、孔31aと孔32aとにピン3
3が挿入されて固定される。格納状態では、ピン33の
先端部にジブ格納ピン33aが挿入される。なお、ブラ
ケット38と当接するピン38aの先端部には衝撃吸収
用の緩衝部材が設けられてもよく、この緩衝部材はゴム
やバネ等で構成される。
A bracket 32 is provided on the side surface of the jib body 12 so as to protrude to the side of the boom 3, and the bracket 32 is provided with a hole 32 a for fixing the jib 7. A bracket 38 is provided on the side surface of the jib main body 12 and also protrudes to the side of the boom 3 side.
A pin 38a is provided at an upper portion of a substantially central portion of the bracket 34. A bracket 36 is provided on a side surface on the jib tip side of the bracket 38. When storing Jib 7,
The position of the hole 31a of the bracket 31 and the position of the hole 32a of the bracket 32 match by contacting the end face of the bracket 38 on the boom 3 side with the pin 38a. At this time, the pins 3 are inserted into the holes 31a and 32a.
3 is inserted and fixed. In the retracted state, the jib storage pin 33a is inserted into the tip of the pin 33. A shock absorbing buffer member may be provided at the tip of the pin 38a that contacts the bracket 38, and the buffer member is made of rubber, a spring, or the like.

【0033】図9において、ブラケット36の先端下面
36aは傾斜を有しており、この傾斜はブラケット34
の上面に対する先端下面36aの高さがその先端部から
基端部にかけて滑らかに低くなっている。また、図8に
おいてブラケット36の先端部は先端からブーム側の側
面36cにかけて傾斜部36bを有しており、ブラケッ
ト36の基端部の側面36cはジブ本体12の側面に略
平行になっている。さらに、ブラケット34のジブ基端
側の側面の上端部には、ブラケット36の先端下面36
aのガイド用のバー37がブラケット34の上面に平行
に固着されている。またブラケット34のジブ7の基端
部側側面には、図8(B)に詳細を示すようなジブ格納
ピン33が挿入されていることを検出するジブ格納ピン
入り検出器33bが設置されている。
In FIG. 9, the lower end surface 36a of the bracket 36 has an inclination, and this inclination is
The height of the lower end surface 36a with respect to the upper surface of the lower end is smoothly reduced from the front end portion to the base end portion. 8, the distal end of the bracket 36 has an inclined portion 36b from the distal end to the side surface 36c on the boom side, and the side surface 36c at the base end of the bracket 36 is substantially parallel to the side surface of the jib body 12. . Further, the lower end 36 of the bracket 36 is provided on the upper end of the side face on the jib base end side of the bracket 34.
The guide bar 37 a is fixed in parallel to the upper surface of the bracket 34. On the side of the bracket 34 near the base end of the jib 7, a detector 33b with a jib storage pin 33b for detecting that the jib storage pin 33 is inserted as shown in detail in FIG. I have.

【0034】図10はジブ7をブーム3に格納する時の
固定手段30の第2実施例を示す詳細平面図であり、図
8に示すようなブラケット34のジブ7の基端部側側面
に設置されている、格納ピン入り検出器33bの代わり
に、ジブ7が格納位置にあることを検出するジブ格納位
置検出器33cを備えている。その他の構成については
図8と同様のため説明を省略する。
FIG. 10 is a detailed plan view showing a second embodiment of the fixing means 30 when the jib 7 is stored in the boom 3, and the bracket 34 shown in FIG. A jib storage position detector 33c that detects that the jib 7 is at the storage position is provided instead of the installed detector 33b with a storage pin. Other configurations are the same as those in FIG.

【0035】図11は、図8、および図9に示すような
格納状態にあるジブ7をトップブーム6の前方に張り出
す時に、図5に示すようにジブ7を係止手段20の回り
に振出した時の固定手段30の詳細平面図であり、図1
2は図11の側面図である。ジブ7を「振り出す」と
は、ジブ7の先端部をブーム3より離す方向に動かすこ
とによってジブ7が係止ピン21の回りに回動し、ジブ
7の基端部のブラケット15の孔15aをトップブーム
6のブラケット61の孔61aに合わせる作業を言う。
FIG. 11 shows that when the jib 7 in the retracted state as shown in FIGS. 8 and 9 is extended toward the front of the top boom 6, the jib 7 is rotated around the locking means 20 as shown in FIG. FIG. 1 is a detailed plan view of the fixing means 30 when it is swung, and FIG.
2 is a side view of FIG. "Swinging out" the jib 7 means that the jib 7 is rotated around the locking pin 21 by moving the distal end of the jib 7 away from the boom 3 and the hole of the bracket 15 at the base end of the jib 7 is formed. This refers to the operation of aligning 15a with the hole 61a of the bracket 61 of the top boom 6.

【0036】ピン33は孔31a及び32aから抜か
れ、ジブ7の先端部はブーム3から離されている。ピン
33はブラケット35の孔35aに挿入されており、こ
の状態でピン33の側面はブラケット36の基端部のブ
ーム3側の側面36cに当接している。これによって、
ジブ7の先端部はピン33によってブーム3側に戻らな
いように固定される。このとき、図2におけるブラケッ
ト15のボス131がトップブーム6の第1ストッパに
当接して前後方向の位置決めがなされ、また、ジブ7側
の第2ストッパ42aがトップブーム6側の第2ストッ
パ42bに当接して左右方向の位置決めがなされること
により、孔15aをトップブーム6の孔61aに容易に
合わせることが可能となっている。
The pin 33 is removed from the holes 31a and 32a, and the tip of the jib 7 is separated from the boom 3. The pin 33 is inserted into the hole 35 a of the bracket 35, and in this state, the side surface of the pin 33 contacts the side surface 36 c of the base end of the bracket 36 on the boom 3 side. by this,
The tip of the jib 7 is fixed by a pin 33 so as not to return to the boom 3 side. At this time, the boss 131 of the bracket 15 in FIG. 2 abuts on the first stopper of the top boom 6 to perform positioning in the front-rear direction, and the second stopper 42a on the jib 7 side becomes the second stopper 42b on the top boom 6 side. The hole 15a can be easily aligned with the hole 61a of the top boom 6 by being positioned in the left-right direction by contacting the hole.

【0037】図13は図4に示すジブ7の振出状態から
孔15aおよび孔61aに挿入された左左ピン19a回
りに、シリンダ63により時計方向に回動されてブーム
3の前方に完全に張出され、左左ピン19aと同様にし
て孔16aおよび孔62aに右右ピン19bを挿入して
固定するように構成されている。
FIG. 13 shows the jib 7 shown in FIG. 4 being swung clockwise by the cylinder 63 around the left and right pins 19a inserted in the holes 15a and 61a from the swinging state of the jib 7 to completely stretch the boom 3 forward. The right and left pins 19b are inserted and fixed in the holes 16a and 62a in the same manner as the left and right pins 19a.

【0038】図14は図2におけるZ視図であり、上下
のブラケット15の間にロックシリンダ17および連結
用のピン19a部分の側面図である。ロックシリンダ1
7の上端部のチューブには第3リンク66の一端側が回
動自在に取着されており、またピン19cにより上方の
左ピン19aが取着されている。左ピン19aの軸心
は、ロックシリンダ17の軸心に一致させている。ま
た、第3リンク66の他端側の上面には、第1リンク6
4とトップブーム6のブラケット61の孔61bとを連
結するためのピン67が固着されている。さらに、ロッ
クシリンダ17の下端部のロッド側には下方の左ピン1
9aがピン19dにより取着されている。
FIG. 14 is a Z view in FIG. 2, and is a side view of the lock cylinder 17 and the connecting pin 19a between the upper and lower brackets 15. FIG. Lock cylinder 1
One end of a third link 66 is rotatably attached to the tube at the upper end of 7, and an upper left pin 19a is attached by a pin 19c. The axis of the left pin 19a coincides with the axis of the lock cylinder 17. The first link 6 is provided on the upper surface on the other end side of the third link 66.
A pin 67 for connecting the bracket 4 to the hole 61b of the bracket 61 of the top boom 6 is fixed. Further, a lower left pin 1 is provided on the rod side at the lower end of the lock cylinder 17.
9a is attached by a pin 19d.

【0039】上下のブラケット15はそれぞれコの字型
をしていて、コの字の上下の板15b、15c及び板1
5d、15eの間に、トップブーム6側に設置された孔
15aを有する上下のブラケット61をそれぞれ挟むよ
うにしている。上方の板15bの上面で、かつ、孔15
a部には孔15aが貫通しているボス131が設けられ
ている。同様にして、下方の板15eの下面で、かつ、
孔15a部には孔15aが貫通しているボス131が設
けられている。また、第1リンク64の第3リンク66
との連結部側は、同様に上下板64a、64bで構成さ
れ、上下板64a、64bの間にトップブーム6の上方
のブラケット61の孔61b部を挟むようになってい
る。
The upper and lower brackets 15 each have a U-shape, and the upper and lower plates 15b, 15c and 1
Upper and lower brackets 61 each having a hole 15a provided on the top boom 6 side are sandwiched between 5d and 15e. The upper surface of the upper plate 15b and the hole 15
A portion is provided with a boss 131 through which the hole 15a passes. Similarly, on the lower surface of the lower plate 15e,
A boss 131 through which the hole 15a passes is provided in the hole 15a. Also, the third link 66 of the first link 64
Similarly, the connecting portion side is constituted by upper and lower plates 64a and 64b, and the hole 61b of the bracket 61 above the top boom 6 is sandwiched between the upper and lower plates 64a and 64b.

【0040】また、ロックシリンダ17が最短に縮小し
ている状態のとき、ジブブラケット11の基端部からロ
ックシリンダ17の方に突出して設けたブラケット71
の先端部がロックシリンダ17のチューブとロッドの間
に挟まれるようになっている。この状態では、上方の左
ピン19aの先端は上方のブラケット15の板15cに
掛かっており、ピン67の先端は第1リンク64の下板
64bに掛かっている。また、下方の左ピン19aの先
端は下方のブラケット15の板15dに掛かっている。
これによって、ロックシリンダ17、第1リンク64、
上下の左ピン19a及びピン67はジブブラケット11
から外れないようになっている。
When the lock cylinder 17 is contracted to the shortest, the bracket 71 is provided to project from the base end of the jib bracket 11 toward the lock cylinder 17.
Of the lock cylinder 17 is sandwiched between the tube and the rod. In this state, the tip of the upper left pin 19a is hooked on the plate 15c of the upper bracket 15, and the tip of the pin 67 is hooked on the lower plate 64b of the first link 64. The tip of the lower left pin 19a is hooked on the plate 15d of the lower bracket 15.
Thereby, the lock cylinder 17, the first link 64,
The upper and lower left pins 19a and the pins 67 are connected to the jib bracket 11.
Not to come off.

【0041】ロックシリンダ17のロッドには、上方に
延びたブラケット69が取着されており、ブラケット6
9の上端には上下の左ピン19aの挿入完了を検出する
ためのロックピン挿入検出器70が取着されている。本
実施例では、ロックピン挿入検出器70の一例として近
接スイッチを採用しており、この近接スイッチの検出面
はロックシリンダ17の伸縮方向の下方を向いている。
また、ロックシリンダ17のチューブの下端部には下方
に延びたポール68が取着され、ポール68の下端に近
接スイッチの検知片68aが取着されている。
A bracket 69 extending upward is attached to the rod of the lock cylinder 17.
A lock pin insertion detector 70 for detecting completion of the insertion of the upper and lower left pins 19a is attached to the upper end of 9. In the present embodiment, a proximity switch is employed as an example of the lock pin insertion detector 70, and the detection surface of the proximity switch faces downward in the direction of expansion and contraction of the lock cylinder 17.
A pole 68 extending downward is attached to the lower end of the tube of the lock cylinder 17, and a detection piece 68a of the proximity switch is attached to the lower end of the pole 68.

【0042】図15は図13のA矢視図で、ロックシリ
ンダ17が伸長してジブ7とトップブーム6とを連結し
た状態をトップブーム6の側面から見た図である。ロッ
クシリンダ17が伸長し、上下の左ピン19aが上下の
ブラケット15の孔15aに完全に挿入されたときに、
ロックピン挿入検出器70の近接スイッチが検知片68
aを所定距離で検知して作動するようになっている。ま
た、ジブ7の張出のとき、上方のブラケット61の上面
及び下方のブラケット61の下面に設けられた上下の第
1ストッパ39にブラケット15のボス131を押し当
てている。これによって、孔15a及び孔61aの位置
が一致し、左ピン19aがスムーズに挿入できるように
なっている。
FIG. 15 is a view taken in the direction of the arrow A in FIG. 13, and is a view of the state in which the lock cylinder 17 is extended to connect the jib 7 and the top boom 6 as viewed from the side of the top boom 6. When the lock cylinder 17 is extended and the upper and lower left pins 19a are completely inserted into the holes 15a of the upper and lower brackets 15,
The proximity switch of the lock pin insertion detector 70 is
a is detected at a predetermined distance to operate. When the jib 7 is extended, the boss 131 of the bracket 15 is pressed against the upper and lower first stoppers 39 provided on the upper surface of the upper bracket 61 and the lower surface of the lower bracket 61. As a result, the positions of the hole 15a and the hole 61a match, and the left pin 19a can be inserted smoothly.

【0043】なお、図示してはいないがブラケット15
と同様にして、上下のブラケット16の間にはロックシ
リンダ18が設けられており、ロックシリンダ18のチ
ューブ側上端部に上方の右ピン19bが、及びロックシ
リンダ18のロッド側下端部に下方の右ピン19bが取
着されている。ロックシリンダ18が最短に縮小してい
る状態のときは、同じく、ジブブラケット11の基端部
からロックシリンダ18の方に突出して設けたブラケッ
ト(ブラケット71に相当)の先端部がロックシリンダ
18のチューブとロッドの間に挟まれるようになってお
り、上下の右ピン19bの先端はそれぞれ上下のブラケ
ット16のコの字板のシリンダ側板(板15c、板15
dに相当)に掛かっている。これによって、ロックシリ
ンダ18及び上下の右ピン19bはジブブラケット11
から外れないようになっている。
Although not shown, the bracket 15
Similarly, a lock cylinder 18 is provided between the upper and lower brackets 16, an upper right pin 19 b is provided at the upper end of the lock cylinder 18 on the tube side, and a lower pin 19 is provided at the lower end of the lock cylinder 18 on the rod side. The right pin 19b is attached. Similarly, when the lock cylinder 18 is contracted to the shortest position, the distal end of a bracket (corresponding to the bracket 71) provided to protrude from the base end of the jib bracket 11 toward the lock cylinder 18. The ends of the upper and lower right pins 19b are respectively connected to the cylinder side plates (plate 15c, plate 15c) of the U-shaped plates of the upper and lower brackets 16 respectively.
d). As a result, the lock cylinder 18 and the upper and lower right pins 19 b are connected to the jib bracket 11.
Not to come off.

【0044】図16は、本発明に係わる移動式クレーン
のジブの張出/格納を操作するためのフロントパネル4
0aを表しており、このフロントパネル40aは運転室
9内に設けられている。ジブ7の張出/格納作業を選択
するためのジブ張出/格納スイッチ41はシーソー型の
切替えスイッチになっている。ジブ張出/格納スイッチ
41を操作すると、図17、および図20に示す対応す
る出力接点がオンするようになっている。また、トップ
ブーム6の左側面のブラケット61とジブ7のブラケッ
ト15とが、左ピン19aによって完全に連結されたと
きに表示する左ピンロック完了表示器43、及びジブ7
の格納時に係止ピン21が係止ブラケット22の孔22
aに完全に挿入されたことを表示するジブ格納位置表示
器67が設けられている。またジブ7がブーム3に固定
されてジブ格納完了検出器33b,33cが検出したこ
とを表示するジブ格納完了表示器44が設けられてい
る。
FIG. 16 shows a front panel 4 for operating the extension / retraction of the jib of the mobile crane according to the present invention.
0a, and the front panel 40a is provided in the cab 9. The jib overhang / storage switch 41 for selecting the overhang / storage operation of the jib 7 is a seesaw type changeover switch. When the jib extension / retraction switch 41 is operated, the corresponding output contact shown in FIGS. 17 and 20 is turned on. Further, a left pin lock completion indicator 43 displayed when the bracket 61 on the left side of the top boom 6 and the bracket 15 of the jib 7 are completely connected by the left pin 19a, and the jib 7
When the lock pin 21 is retracted, the locking pin 21
A jib storage position indicator 67 is provided to indicate that the jib has been completely inserted into a. A jib storage completion indicator 44 is provided to display that the jib 7 is fixed to the boom 3 and detected by the jib storage completion detectors 33b and 33c.

【0045】そしてフロントパネル40aには作業モー
ドの切替えを行うモード切替スイッチ45を備えてお
り、図18に示す一本の操作レバー56aの一方向の操
作によってのみ、前記ロックシリンダ17(左ピン)、
回動シリンダ63及びロックシリンダ18(右ピン)の
作動が可能なように構成している。したがって、モード
切替スイッチ45によりこれらの内のどのシリンダによ
る作業を行うのかを選択できるようになっている。また
シリンダの作動方向は、前記ジブ張出/格納スイッチ4
1によって切り換えるようになっている。
The front panel 40a is provided with a mode changeover switch 45 for switching the operation mode. The lock cylinder 17 (left pin) is operated only by one operation of one operating lever 56a shown in FIG. ,
The rotation cylinder 63 and the lock cylinder 18 (right pin) can be operated. Therefore, it is possible to select which of these cylinders is to be used for the operation by the mode changeover switch 45. The operation direction of the cylinder is determined by the jib extension / retraction switch 4.
1 is switched.

【0046】図17〜図19にそれぞれ示す、本発明の
電気制御回路及び油圧制御回路の第1実施例について説
明する。図17に示す電気制御回路はモーメントリミッ
タコントローラ52とそれ以外のインターロック手段と
から構成されている。モーメントリミッタコントローラ
52はジブ張出時にブーム3の伸長可否を判定してブー
ム3の伸長を制御しており、例えばマイクロコンピュー
タ等で構成されている。モーメントリミッタコントロー
ラ52は運転室9に設置された図21、および図22に
示すような、モーメントリミッタ表示パネル40の上部
作業モードスイッチ71により、準備(ジブ張出/格
納)モード、ジブモード、ブーム/シングルトップモー
ドの各上部作業モード信号を入力しており、この準備
(ジブ張出/格納)モード信号に基づいてジブ自動張出
モードリレー46のコイル46cにオン−オフ指令を出
力している。また、ロックピン挿入検出器70の出力端
子はケーブルドラム72を介して、モーメントリミッタ
コントローラ52と左ピンロック完了表示器43とに並
列に接続されている。なお、本実施例の左ピンロック完
了表示器43は抵抗と発光ダイオード(以後、LEDと
呼ぶ)で構成されているが、ランプ等でもよい。また、
ロックピン挿入検出器70の電源端子は、車両搭載の図
示しないバッテリー電源ラインと、電源スイッチ(図示
せず)やヒューズF等及びケーブルドラム72を介して
接続されている。
A first embodiment of the electric control circuit and the hydraulic control circuit of the present invention shown in FIGS. 17 to 19 will be described. The electric control circuit shown in FIG. 17 includes a moment limiter controller 52 and other interlock means. The moment limiter controller 52 controls the extension of the boom 3 by judging whether or not the extension of the boom 3 is possible when the jib is extended, and is constituted by, for example, a microcomputer or the like. The moment limiter controller 52 is set in the preparation (jib extension / retraction) mode, jib mode, boom / boom mode by the upper operation mode switch 71 of the moment limiter display panel 40 as shown in FIG. 21 and FIG. Each upper work mode signal of the single top mode is input, and an ON / OFF command is output to the coil 46c of the jib automatic extension mode relay 46 based on the preparation (jib extension / retraction) mode signal. The output terminal of the lock pin insertion detector 70 is connected in parallel to the moment limiter controller 52 and the left pin lock completion indicator 43 via the cable drum 72. The left pin lock completion indicator 43 of the present embodiment is composed of a resistor and a light emitting diode (hereinafter, referred to as an LED), but may be a lamp or the like. Also,
The power terminal of the lock pin insertion detector 70 is connected to a battery power line (not shown) mounted on the vehicle via a power switch (not shown), a fuse F and the like, and a cable drum 72.

【0047】格納ピン入り検出器33bの出力はジブ格
納完了表示器44を点灯すると共に、モーメントリミッ
タコントローラ52に出力される。この格納ピン入り検
出器33bの出力と、前記ロックピン挿入検出器70の
出力を同時に入力するか、同時に入力しない時には、モ
ーメントリミッタコントローラ52は図18に示すブー
ムシリンダ141の切換操作弁143の伸長側パイロッ
ト操作部に接続された、アンロード弁50のソレノイド
50aに通電するようになっている。ソレノイド50a
の通電によりアンロード弁50がアンロードされるた
め、ブームシリンダ141のブーム伸長側操作が不可能
となる。
The output of the storage pin entry detector 33b turns on the jib storage completion indicator 44 and is output to the moment limiter controller 52. When the output of the storage pin input detector 33b and the output of the lock pin insertion detector 70 are simultaneously input or not input, the moment limiter controller 52 extends the switching operation valve 143 of the boom cylinder 141 shown in FIG. The solenoid 50a of the unload valve 50 connected to the side pilot operation unit is energized. Solenoid 50a
Since the unload valve 50 is unloaded by the energization of, the operation of the boom cylinder 141 on the boom extension side becomes impossible.

【0048】ジブ自動張出モードリレー46のa接点出
力46aのコモン端子は前記と同じくヒューズF等を介
してバッテリー電源ラインに接続され、a接点出力端子
はジブ張出/格納スイッチ41のコモン端子c、ジブ格
納位置検出器29、および格納ピン入り検出器33bの
電源端子、及びリレー47、48のa接点出力47a
1、48a1のコモン端子に並列に接続されている。ジ
ブ張出/格納スイッチ41の張出選択時の出力端子aは
リレー47のコイル47cに接続され、格納選択時の出
力端子bはリレー48のコイル48cと、ケーブルドラ
ム72を介してリレー51のコイル51cとに並列に接
続されている。また、ジブ格納位置検出器29の出力端
子はジブ格納位置表示器67と、これと並列にリレー4
8のa接点出力48a2を介してリレー49のコイル4
9cに接続されている。格納ピン入り検出器33bの出
力端子は、ジブ格納完了表示器44と、これと並列にモ
ーメントリミッタコントローラ52に接続されている。
The common terminal of the a-contact output 46a of the jib automatic extension mode relay 46 is connected to the battery power supply line via the fuse F or the like as described above, and the a-contact output terminal is the common terminal of the jib extension / storage switch 41. c, power supply terminals of the jib storage position detector 29 and storage pin input detector 33b, and a contact outputs 47a of relays 47 and 48
1, 48a1 are connected in parallel to the common terminals. The output terminal a of the jib extension / retraction switch 41 when the extension is selected is connected to the coil 47c of the relay 47, and the output terminal b when the storage is selected is connected to the coil 48c of the relay 48 and the relay 51 via the cable drum 72. It is connected in parallel with the coil 51c. The output terminal of the jib storage position detector 29 is connected to a jib storage position indicator 67 and a relay 4 in parallel with the jib storage position indicator 67.
8, the coil 4 of the relay 49 via the contact output 48a2
9c. The output terminal of the storage pin input detector 33b is connected to a jib storage completion indicator 44 and to a moment limiter controller 52 in parallel with the jib storage completion indicator 44.

【0049】a接点出力47a1、48a1の並列回路
の他端子側は、モード切替スイッチ45のコモン端子d
に、及びケーブルドラム72を介してジブ側切換弁73
のソレノイド73cに並列に接続されている。モード切
替スイッチ45の左ピン選択時の出力端子aは、リレー
47のa接点出力47a2とリレー49のa接点出力4
9a1との並列回路を介し、さらにケーブルドラム72
を介してリレー51のコモン端子51c1に接続されて
いる。同じく、モード切替スイッチ45の回動選択時の
出力端子b及び右ピン選択時の出力端子cは、それぞれ
ケーブルドラム72を介してリレー51の他のコモン端
子51c2及びコモン端子51c3に接続されている。
コモン端子51c1に対応するb接点出力51b1及び
a接点出力51a1は、それぞれロックシリンダ17を
駆動する左ロックシリンダ切換弁53のソレノイド53
d、53eに接続されている。また、同様に、コモン端
子51c2に対応するb接点出力51b2及びa接点出
力51a2は、それぞれ回動シリンダ63を駆動する回
動シリンダ切換弁54のソレノイド54d、54eに接
続され、コモン端子51c3に対応するb接点出力51
b3及びa接点出力51a3は、それぞれロックシリン
ダ18を駆動する右ロックシリンダ切換弁55のソレノ
イド55d、55eに接続されている。
The other terminal side of the parallel circuit of the contact outputs 47a1 and 48a1 is connected to the common terminal d of the mode changeover switch 45.
And the jib side switching valve 73 via the cable drum 72
Is connected in parallel to the solenoid 73c. The output terminal a of the mode changeover switch 45 when the left pin is selected is a contact output 47a2 of the relay 47 and a contact output 4a of the relay 49.
9a1 and a cable drum 72
Is connected to the common terminal 51c1 of the relay 51 via the. Similarly, the output terminal b when the mode changeover switch 45 is selected for rotation and the output terminal c when the right pin is selected are connected to the other common terminals 51c2 and 51c3 of the relay 51 via the cable drum 72, respectively. .
The b-contact output 51b1 and the a-contact output 51a1 corresponding to the common terminal 51c1 are provided by a solenoid 53 of a left lock cylinder switching valve 53 for driving the lock cylinder 17, respectively.
d, 53e. Similarly, the b-contact output 51b2 and the a-contact output 51a2 corresponding to the common terminal 51c2 are connected to the solenoids 54d and 54e of the rotary cylinder switching valve 54 for driving the rotary cylinder 63, respectively, and correspond to the common terminal 51c3. B contact output 51
The b3 and a contact outputs 51a3 are connected to solenoids 55d and 55e of the right lock cylinder switching valve 55 that drives the lock cylinder 18, respectively.

【0050】なお、上記の各リレーのコイル、表示器
(LED)、ソレノイド及び検出器(近接スイッチ)等
の他端側はバッテリーのグランドラインに接続されてい
る。また、ケーブルドラム72はブーム先端側と車体側
とを接続するケーブルを伸縮自在にするものである。
The other end of the coil, indicator (LED), solenoid, detector (proximity switch), etc. of each relay is connected to the ground line of the battery. The cable drum 72 makes the cable connecting the boom tip side and the vehicle body side extendable and contractible.

【0051】図18に示す油圧制御回路は、チルトシリ
ンダ14を操作するための操作レバー56aを有する操
作弁56からのパイロット管は方向切換弁57のパイロ
ット操作部に接続されている。油圧ポンプ58から吐出
された圧油は方向切換弁57のPポートに導かれ、方向
切換弁57のTポートはタンク59へ接続されている。
方向切換弁57のAポートは管路76、リール74a、
管路101及びパイロット操作逆止弁78を介してチル
トシリンダ14のヘッド側に接続され、Bポートは管路
77及びリール74bを介して方向切換弁73に接続さ
れている。
In the hydraulic control circuit shown in FIG. 18, a pilot pipe from an operation valve 56 having an operation lever 56a for operating the tilt cylinder 14 is connected to a pilot operation section of a direction switching valve 57. The pressure oil discharged from the hydraulic pump 58 is guided to the P port of the direction switching valve 57, and the T port of the direction switching valve 57 is connected to the tank 59.
The A port of the direction switching valve 57 is connected to the pipeline 76, the reel 74a,
The port B is connected to the head side of the tilt cylinder 14 via a pipe 101 and a pilot operation check valve 78, and the B port is connected to a direction switching valve 73 via a pipe 77 and a reel 74b.

【0052】方向切換弁73は圧油をチルトシリンダ1
4側に供給するかジブ張出/格納用の各ロックシリンダ
17、18及び回動シリンダ63側に供給するかを切り
換えるものである。方向切換弁73のAポートは、管路
102、カウンタバランス弁79を介してチルトシリン
ダ14のボトム側に接続されている。また、方向切換弁
73のBポートは管路103を介して回動シリンダ切換
弁54のPポートに、回動シリンダ切換弁54のTポー
トは管路104を介して右ロックシリンダ切換弁55の
Pポートに、右ロックシリンダ切換弁55のTポートは
管路105を介して左ロックシリンダ切換弁53のPポ
ートに、左ロックシリンダ切換弁53のTポートは管路
106及び逆止弁75を介して管路101に接続されて
いる。前記各左ロックシリンダ切換弁53、回動シリン
ダ切換弁54、及び右ロックシリンダ切換弁55の中立
位置bでは、PポートとTポート同士が内部で連通して
いる。
The directional control valve 73 supplies pressure oil to the tilt cylinder 1
It switches between supplying to the 4 side and supplying to the lock cylinders 17 and 18 and the rotating cylinder 63 for jib extension / retraction. The A port of the direction switching valve 73 is connected to the bottom side of the tilt cylinder 14 via a pipeline 102 and a counterbalance valve 79. The B port of the direction switching valve 73 is connected to the P port of the rotary cylinder switching valve 54 via the pipe 103, and the T port of the rotary cylinder switching valve 54 is connected to the right lock cylinder switching valve 55 via the pipe 104. The P port, the T port of the right lock cylinder switching valve 55 is connected to the P port of the left lock cylinder switching valve 53 via the line 105, and the T port of the left lock cylinder switching valve 53 is connected to the line 106 and the check valve 75. It is connected to the pipe line 101 via. At the neutral position b of each of the left lock cylinder switching valve 53, the rotary cylinder switching valve 54, and the right lock cylinder switching valve 55, the P port and the T port communicate with each other inside.

【0053】左ロックシリンダ切換弁53のA,Bポー
トは、それぞれ管路107及び管路108を介してロッ
クシリンダ17のボトム側及びヘッド側に接続されてい
る。また、右ロックシリンダ切換弁55のA,Bポート
は、それぞれ管路109及び管路110を介してロック
シリンダ18のボトム側及びヘッド側に接続されてい
る。さらに、回動シリンダ切換弁54のA,Bポート
は、それぞれ管路111及び管路112を介して回動シ
リンダ63のボトム側及びヘッド側に接続されている。
The A and B ports of the left lock cylinder switching valve 53 are connected to the bottom side and the head side of the lock cylinder 17 via a pipe 107 and a pipe 108, respectively. Further, the A and B ports of the right lock cylinder switching valve 55 are connected to the bottom side and the head side of the lock cylinder 18 via a pipe 109 and a pipe 110, respectively. Further, the A and B ports of the rotary cylinder switching valve 54 are connected to the bottom side and the head side of the rotary cylinder 63 via a pipe 111 and a pipe 112, respectively.

【0054】図19に示すブーム操作用油圧回路は、ブ
ームシリンダ141を操作するためのブームレバー14
2aを有するブーム操作弁142からのパイロット管は
方向切換弁143のパイロット操作部に接続されてい
る。油圧ポンプ58から吐出された圧油は方向切換弁1
43のPポートに導かれ、方向切換弁143のTポート
はタンク59へ接続されている。方向切換弁143のA
ポートはブームシリンダ141のヘッド側に接続され、
Bポートはカウンタバランス弁144を介してブームシ
リンダ141のボトム側に接続されている。
The boom operation hydraulic circuit shown in FIG. 19 includes a boom lever 14 for operating a boom cylinder 141.
The pilot pipe from the boom operation valve 142 having 2a is connected to the pilot operation part of the direction switching valve 143. The pressure oil discharged from the hydraulic pump 58 is supplied to the directional control valve 1
The directional control valve 143 is guided to the P port 43 and the T port of the directional control valve 143 is connected to the tank 59. A of the direction switching valve 143
The port is connected to the head side of the boom cylinder 141,
The B port is connected to the bottom side of the boom cylinder 141 via the counter balance valve 144.

【0055】方向切換弁143の一方のパイロット操作
部には、ソレノイド50aによって操作されるアンロー
ド弁50が接続されている。パイロットポンプ58aと
ブーム操作弁142とを接続する管路145は、圧力制
御弁146により一定のパイロット元圧に維持されてい
る。
An unload valve 50 operated by a solenoid 50a is connected to one pilot operation part of the direction switching valve 143. The pipeline 145 connecting the pilot pump 58a and the boom operation valve 142 is maintained at a constant pilot base pressure by the pressure control valve 146.

【0056】図20は本発明の電気制御回路の第2実施
例を示す図である。図17に示す第1実施例と共通する
部品には同一符号を付してその説明を省略し、異なる部
分についてのみ説明する。左ピン19aの挿入が完了す
ると、ロックピン挿入検出器70が検知片68aを検出
し、ロックピン挿入検出器70の出力が左ピンロック完
了表示器43を点灯すると共に、警報スイッチ69のコ
イルに通電するため、B接点となり、警報ブザー69a
と警報ランプ69bには通電されない。一方格納ピン3
3の入りを検出した格納ピン入り検出器33bの出力
も、警報スイッチ69のコイルに通電されるため、B接
点となり警報ブザー69aと警報ランプ69bとには通
電されない。従って左ピン19aの挿入が完了していな
いと共に、格納ピン33が入り状態にないときには、警
報スイッチ69のコイルに通電されないため、A接点と
なり警報ブザー69aと警報ランプ69bに通電される
ように構成されている。
FIG. 20 is a diagram showing a second embodiment of the electric control circuit of the present invention. Components common to those in the first embodiment shown in FIG. 17 are denoted by the same reference numerals, and description thereof will be omitted. Only different portions will be described. When the insertion of the left pin 19a is completed, the lock pin insertion detector 70 detects the detection piece 68a, and the output of the lock pin insertion detector 70 turns on the left pin lock completion indicator 43, and the coil of the alarm switch 69 As it is energized, it becomes a B contact and the alarm buzzer 69a
And the alarm lamp 69b is not energized. On the other hand, storage pin 3
The output of the storage pin insertion detector 33b which detects the entry of 3 is also energized to the coil of the alarm switch 69, so that it becomes a B contact and is not energized to the alarm buzzer 69a and the alarm lamp 69b. Therefore, when the insertion of the left pin 19a is not completed and the storage pin 33 is not in the ON state, the coil of the alarm switch 69 is not energized, so that the contact becomes the A contact and the alarm buzzer 69a and the alarm lamp 69b are energized. Have been.

【0057】図21は本発明に係る移動式クレーンのモ
ーメントリミッタ表示パネル40を示す図で、このモー
メントリミッタ表示パネル40には、ジブ作業、ブーム
/シングルトップ作業、および準備(ジブ張出/格納)
作業の各上部作業モードを選択するための、上部作業モ
ードスイッチ71が設置されている。図22図は図21
のP部拡大詳細である。
FIG. 21 is a view showing a moment limiter display panel 40 of the mobile crane according to the present invention. The moment limiter display panel 40 includes a jib operation, a boom / single top operation, and a preparation (jib extension / retraction). )
An upper operation mode switch 71 for selecting each upper operation mode of the operation is provided. FIG. 22 shows FIG.
It is an enlarged detail of a P part.

【0058】次に、図17〜図19に示す電気制御回路
及び油圧制御回路における作動について説明する。図1
7において、上部作業モードスイッチ71からモーメン
トリミッタコントローラ52に準備(ジブ張出/格納)
モード信号が出力されると、モーメントリミッタコント
ローラ52からジブ自動張出モードリレー46のコイル
46cに通電され、a接点出力46aがオンする。 (1) 準備モード(ジブチルトシリンダの操作) 図15のフロントパネル40aのジブ張出/格納スイッ
チ41が張出側及び格納側のいずれにも操作されていな
いときは、このスイッチのコモン端子cは出力端子a及
び出力端子bに接続されていない。よって、リレー4
7、48のコイル47c、48cは通電されずにa接点
出力47a1、48a1は共にオフのままとなり、方向
切換弁73のソレノイド73cは通電されない。したが
って、方向切換弁73はa位置になり、チルトレバー5
6の操作によってチルトシリンダ14が伸縮する。
Next, the operation of the electric control circuit and the hydraulic control circuit shown in FIGS. 17 to 19 will be described. FIG.
At 7, the upper work mode switch 71 prepares the moment limiter controller 52 (jib extension / retraction).
When the mode signal is output, the coil 46c of the jib automatic extension mode relay 46 is energized from the moment limiter controller 52, and the a contact output 46a is turned on. (1) Preparation mode (operation of dibutyl cylinder) When the jib extension / retraction switch 41 on the front panel 40a in FIG. 15 is not operated on either the extension side or the storage side, the common terminal c of this switch is used. Is not connected to the output terminal a and the output terminal b. Therefore, relay 4
The coils 47c, 48c of Nos. 7, 48 are not energized, the a-contact outputs 47a1, 48a1 remain off, and the solenoid 73c of the direction switching valve 73 is not energized. Therefore, the direction switching valve 73 is at the position a, and the tilt lever 5
The operation of 6 causes the tilt cylinder 14 to expand and contract.

【0059】例えば、チルトレバー56を手前に引く
と、方向切換弁57はa位置に切り換わり、油圧ポンプ
58から吐出された圧油のチルトレバー操作量に応じた
流量が管路77、リール74bを介して方向切換弁73
に導かれ、さらに方向切換弁73のa位置から管路10
2及びカウンタバランス弁79を介してチルトシリンダ
14のボトム側に流入する。チルトシリンダ14のヘッ
ド側から流出した油は、パイロット操作逆止弁78、管
路101、リール74a及び管路76を介して方向切換
弁57からタンク59へドレーンする。これによって、
チルトレバー操作量に応じた速度でチルトシリンダ14
は伸長する。チルトレバー56を反対方向に操作する
と、方向切換弁57はc位置に切り換わり、油圧ポンプ
58から吐出された圧油は上記と反対方向に流れ、チル
トレバー操作量に応じた速度でチルトシリンダ14は縮
小する。このとき、管路101の圧油は逆止弁75によ
って管路106側には流入しないようになっている。
For example, when the tilt lever 56 is pulled forward, the direction switching valve 57 is switched to the position a, and the flow rate of the hydraulic oil discharged from the hydraulic pump 58 according to the tilt lever operation amount is changed to the pipeline 77 and the reel 74b. Via the direction switching valve 73
From the position a of the directional control valve 73,
2 and flows into the bottom side of the tilt cylinder 14 via the counter balance valve 79. The oil that has flowed out from the head side of the tilt cylinder 14 drains from the direction switching valve 57 to the tank 59 via the pilot operation check valve 78, the pipeline 101, the reel 74a, and the pipeline 76. by this,
Tilt cylinder 14 at a speed corresponding to the amount of tilt lever operation
Extends. When the tilt lever 56 is operated in the opposite direction, the direction switching valve 57 is switched to the position c, and the pressure oil discharged from the hydraulic pump 58 flows in the opposite direction, and the tilt cylinder 14 is moved at a speed corresponding to the tilt lever operation amount. Shrinks. At this time, the pressure oil in the pipeline 101 is prevented from flowing into the pipeline 106 by the check valve 75.

【0060】(2) 準備モード(ジブ張出操作) ジブ張出/格納スイッチ41が張出側に操作されている
ときは、このスイッチのコモン端子cは出力端子aに接
続される。よって、リレー47のコイル47cが通電さ
れてa接点出力47a1がオンし、方向切換弁73のソ
レノイド73cが通電される。また、リレー51のコイ
ル51cは通電されないので、各b接点出力51b1、
51b2、51b3はコモン端子51c1、51c2、
51c3に接続されている。このため、方向切換弁73
はb位置に切り換わり、チルトレバー56の操作によっ
てジブ張出の操作が可能となる。
(2) Preparation mode (jib overhang operation) When the jib overhang / restore switch 41 is operated to the overhang side, the common terminal c of this switch is connected to the output terminal a. Therefore, the coil 47c of the relay 47 is energized, the a contact output 47a1 is turned on, and the solenoid 73c of the direction switching valve 73 is energized. Further, since the coil 51c of the relay 51 is not energized, each of the b-contact outputs 51b1,
51b2, 51b3 are common terminals 51c1, 51c2,
51c3. For this reason, the direction switching valve 73
Is switched to the position b, and the operation of the jib extension can be performed by operating the tilt lever 56.

【0061】(i) フロントパネル40aのモード切替ス
イッチ45を「左ピン」側に切り替えたときは、モード
切替スイッチ45のコモン端子dと端子aが接続する。
また、リレー47のa接点出力47a2はオンしている
ので、左ロックシリンダ切換弁53のソレノイド53d
が通電される。これによって、左ロックシリンダ切換弁
53はa位置に切り換わる。このとき、チルトレバー5
6を手前に引くと、方向切換弁57はa位置に切り換わ
り、油圧ポンプ58から吐出された圧油のチルトレバー
操作量に応じた流量が管路77、リール74bを介して
方向切換弁73に導かれる。
(I) When the mode changeover switch 45 on the front panel 40a is switched to the "left pin" side, the common terminal d and the terminal a of the mode changeover switch 45 are connected.
Further, since the a-contact output 47a2 of the relay 47 is on, the solenoid 53d of the left lock cylinder switching valve 53
Is energized. As a result, the left lock cylinder switching valve 53 switches to the position a. At this time, tilt lever 5
6, the direction switching valve 57 is switched to the position "a", and the flow rate corresponding to the tilt lever operation amount of the pressure oil discharged from the hydraulic pump 58 is changed via the pipe 77 and the reel 74b to the direction switching valve 73. It is led to.

【0062】さらに、方向切換弁73のb位置から管路
103、回動シリンダ切換弁54のb位置、管路10
4、右ロックシリンダ切換弁55のb位置及び管路10
5を介して左ロックシリンダ切換弁53のa位置に導か
れ、管路107からロックシリンダ17のボトム側に流
入する。ロックシリンダ17のヘッド側から流出した油
は、管路108、左ロックシリンダ切換弁53、管路1
06、逆止弁75、管路101、リール74a及び管路
76を介して方向切換弁57からタンク59へドレーン
する。これによって、チルトレバー引き量に応じた速度
でロックシリンダ17は伸長し、上下の左ピン19aが
挿入される。
Further, from the position b of the direction switching valve 73, the line 103, the position b of the rotary cylinder switching valve 54, the line 10
4. Position b of right lock cylinder switching valve 55 and conduit 10
The liquid is guided to the position a of the left lock cylinder switching valve 53 through the valve 5 and flows into the bottom side of the lock cylinder 17 from the pipe 107. The oil flowing out from the head side of the lock cylinder 17 is supplied to the pipeline 108, the left lock cylinder switching valve 53, the pipeline 1
06, drain from the directional control valve 57 to the tank 59 via the check valve 75, the pipeline 101, the reel 74a and the pipeline 76. As a result, the lock cylinder 17 is extended at a speed corresponding to the tilt lever pull amount, and the upper and lower left pins 19a are inserted.

【0063】(ii)モード切替スイッチ45を「回動」側
に切り替えたときは、モード切替スイッチ45のコモン
端子dと端子bが接続するので、回動シリンダ切換弁5
4のソレノイド54dが通電される。これによって、回
動シリンダ切換弁54はa位置に切り換わる。このと
き、チルトレバー56を手前に引くと、油圧ポンプ58
から吐出された圧油が方向切換弁57のa位置を介して
方向切換弁73に導かれ、方向切換弁73のb位置から
管路103を介して回動シリンダ切換弁54のa位置に
導かれ、管路111から回動シリンダ63のボトム側に
流入する。回動シリンダ63のヘッド側から流出した油
は、管路112、回動シリンダ切換弁54、管路10
4、逆止弁75、管路101及び管路76を介して方向
切換弁57からタンク59へドレーンする。これによっ
て、チルトレバー引き量に応じた速度で回動シリンダ6
3は伸長し、ジブ7がブーム3の側方から前方に上下の
左ピン19aの回りに回動する。
(Ii) When the mode changeover switch 45 is switched to the "rotation" side, the common terminal d and the terminal b of the mode changeover switch 45 are connected.
The fourth solenoid 54d is energized. As a result, the rotary cylinder switching valve 54 switches to the position a. At this time, when the tilt lever 56 is pulled forward, the hydraulic pump 58
Is discharged from the directional control valve 57 to the directional control valve 73 via the position a, and from the b position of the directional control valve 73 to the a position of the rotary cylinder switching valve 54 via the conduit 103. Then, it flows into the bottom side of the rotary cylinder 63 from the pipe line 111. The oil flowing out from the head side of the rotary cylinder 63 is supplied to the pipe 112, the rotary cylinder switching valve 54, the pipe 10
4. Drain from the directional control valve 57 to the tank 59 via the check valve 75, the pipe 101 and the pipe 76. As a result, the rotation cylinder 6 is rotated at a speed corresponding to the tilt lever pull amount.
3 is extended, and the jib 7 is pivoted forward and downward around the left and right pins 19a from the side of the boom 3.

【0064】(iii) モード切替スイッチ45を「右ピ
ン」側に切り替えたときは、モード切替スイッチ45の
コモン端子dと端子cが接続するので、右ロックシリン
ダ切換弁55のソレノイド55dが通電される。これに
よって、右ロックシリンダ切換弁55はa位置に切り換
わる。このとき、チルトレバー56を手前に引くと、同
様にして、油圧ポンプ58から吐出された圧油が方向切
換弁57のa位置を介して方向切換弁73に導かれ、方
向切換弁73のb位置から管路103、管路104を介
して右ロックシリンダ切換弁55のa位置に導かれ、管
路109からロックシリンダ18のボトム側に流入す
る。ロックシリンダ18のヘッド側から流出した油は、
管路110、右ロックシリンダ切換弁55、管路10
5、逆止弁75、管路101及び管路76を介して方向
切換弁57からタンク59へドレーンする。これによっ
て、チルトレバー引き量に応じた速度でロックシリンダ
18は伸長し、上下の右ピン19bが挿入される。
(Iii) When the mode changeover switch 45 is switched to the "right pin" side, the common terminal d and the terminal c of the mode changeover switch 45 are connected, so that the solenoid 55d of the right lock cylinder changeover valve 55 is energized. You. Thereby, the right lock cylinder switching valve 55 switches to the position a. At this time, when the tilt lever 56 is pulled forward, similarly, the pressure oil discharged from the hydraulic pump 58 is guided to the direction switching valve 73 via the position a of the direction switching valve 57, and the b From the position, it is guided to the a position of the right lock cylinder switching valve 55 via the pipes 103 and 104 and flows from the pipe 109 to the bottom side of the lock cylinder 18. The oil flowing out from the head side of the lock cylinder 18 is
Pipe 110, right lock cylinder switching valve 55, pipe 10
5. Drain from the directional control valve 57 to the tank 59 via the check valve 75, the pipe 101 and the pipe 76. As a result, the lock cylinder 18 extends at a speed corresponding to the tilt lever pull amount, and the upper and lower right pins 19b are inserted.

【0065】なお、上記のときにチルトレバー56を反
対方向に操作すると、方向切換弁57はc位置に切り換
わり、油圧ポンプ58から吐出された圧油は管路76、
管路101に導かれる。しかし、管路101の圧油は逆
止弁75によって管路106側には流入しないので、上
記の各シリンダは縮小することはない。よって、誤操作
を防止できる。
When the tilt lever 56 is operated in the opposite direction at the time described above, the direction switching valve 57 is switched to the position c, and the pressure oil discharged from the hydraulic pump 58 is supplied to the pipeline 76,
It is led to the conduit 101. However, since the pressure oil in the pipeline 101 does not flow into the pipeline 106 by the check valve 75, the above-described cylinders are not reduced. Therefore, erroneous operation can be prevented.

【0066】(3) 準備モード(ジブ格納操作) 次に、ジブ張出/格納スイッチ41が格納側に操作され
ているときは、このスイッチのコモン端子cは出力端子
bに接続される。よって、リレー48のコイル48cが
通電されてa接点出力48a1がオンし、方向切換弁7
3のソレノイド73cが通電される。また、同時にリレ
ー51のコイル51cが通電されるので、各a接点出力
51a1、51a2、51a3はコモン端子51c1、
51c2、51c3に接続される。このため、方向切換
弁73はb位置に切り換わり、チルトレバー56の操作
によってジブ格納の操作が可能となる。
(3) Preparation mode (jib storage operation) Next, when the jib extension / retraction switch 41 is operated to the storage side, the common terminal c of this switch is connected to the output terminal b. Therefore, the coil 48c of the relay 48 is energized, the contact a output 48a1 is turned on, and the directional control valve 7
The third solenoid 73c is energized. Further, since the coil 51c of the relay 51 is energized at the same time, the a contact outputs 51a1, 51a2, 51a3 are connected to the common terminal 51c1,
Connected to 51c2, 51c3. For this reason, the direction switching valve 73 switches to the position b, and the operation of the jib storage can be performed by operating the tilt lever 56.

【0067】(i) フロントパネル40aのモード切替
スイッチ45を「右ピン」側に切り替えたときは、モー
ド切替スイッチ45のコモン端子dと端子cが接続し、
右ロックシリンダ切換弁55のソレノイド55eが通電
される。これによって、右ロックシリンダ切換弁55は
c位置に切り換わる。このとき、操作レバー56を手前
に引くと、同様に、油圧ポンプ58から吐出された圧油
が方向切換弁57のa位置を介して方向切換弁73に導
かれ、方向切換弁73のb位置から管路103、右ロッ
クシリンダ切換弁55のc位置、管路110からロック
シリンダ18のヘッド側に流入する。ロックシリンダ1
8のボトム側から流出した油は、管路109、右ロック
シリンダ切換弁55、管路105、逆止弁75、管路1
01及び管路76を介して方向切換弁57からタンク5
9へドレーンする。これによって、操作レバー引き量に
応じた速度でロックシリンダ18は縮小し、上下の右ピ
ン19bが抜かれる。
(I) When the mode changeover switch 45 on the front panel 40a is switched to the “right pin” side, the common terminal d and the terminal c of the mode changeover switch 45 are connected,
The solenoid 55e of the right lock cylinder switching valve 55 is energized. As a result, the right lock cylinder switching valve 55 switches to the position c. At this time, when the operation lever 56 is pulled forward, similarly, the pressure oil discharged from the hydraulic pump 58 is guided to the direction switching valve 73 via the position a of the direction switching valve 57, and the position b of the direction switching valve 73 is similarly moved. From the pipe 103, the c position of the right lock cylinder switching valve 55, and the pipe 110 into the head side of the lock cylinder 18. Lock cylinder 1
The oil that has flowed out from the bottom side of line 8 is connected to line 109, right lock cylinder switching valve 55, line 105, check valve 75, line 1
01 and the directional control valve 57 to the tank 5
Drain to 9. Thus, the lock cylinder 18 contracts at a speed corresponding to the operation lever pull amount, and the upper and lower right pins 19b are pulled out.

【0068】(ii) モード切替スイッチ45を「回動」
側に切り替えたときは、回動シリンダ切換弁54のソレ
ノイド54eが通電される。これによって、回動シリン
ダ切換弁54はc位置に切り換わる。このとき、操作レ
バー56を手前に引くと、油圧ポンプ58から吐出され
た圧油が方向切換弁57のa位置、方向切換弁73のb
位置、管路103を介して回動シリンダ切換弁54のc
位置に導かれ、管路112から回動シリンダ63のヘッ
ド側に流入する。回動シリンダ63のボトム側から流出
した油は、管路111、逆止弁75及び管路76を介し
て方向切換弁57からタンク59へドレーンする。これ
によって、操作レバー引き量に応じた速度で回動シリン
ダ63は縮小し、ジブ7がブーム3の前方から側方に上
下の左ピン19aの回りに回動する。
(Ii) The mode switch 45 is turned.
Side, the solenoid 54e of the rotary cylinder switching valve 54 is energized. As a result, the rotary cylinder switching valve 54 switches to the position c. At this time, when the operating lever 56 is pulled forward, the pressure oil discharged from the hydraulic pump 58 is moved to the position a of the direction switching valve 57 and the position b of the direction switching valve 73.
Position, c of the rotary cylinder switching valve 54 via the conduit 103
It is guided to the position, and flows into the head side of the rotary cylinder 63 from the conduit 112. The oil flowing out from the bottom side of the rotary cylinder 63 drains from the direction switching valve 57 to the tank 59 via the pipe 111, the check valve 75, and the pipe 76. As a result, the rotary cylinder 63 contracts at a speed corresponding to the operation lever pull amount, and the jib 7 rotates around the upper and lower left pins 19a from the front of the boom 3 to the side.

【0069】(iii) モード切替スイッチ45を「左ピ
ン」側に切り替えたときは、モード切替スイッチ45の
コモン端子dと端子aが接続する。このとき、リレー4
7のa接点出力47a2はオフしているので、リレー4
9のa接点出力49a1のオン/オフによって、左ロッ
クシリンダ切換弁53のソレノイド53eの通電の可否
が決まる。すなわち、ジブ格納検出器29の一例の近接
スイッチが検知板29aを検知しているとき、ジブ格納
検出器29の出力はa接点出力48a2を介してリレー
49のコイル49cを通電し、このときのみ、a接点出
力49a1のオンによって左ロックシリンダ切換弁53
のソレノイド53eに通電される。これによって、左ロ
ックシリンダ切換弁53はc位置に切り換わる。
(Iii) When the mode switch 45 is switched to the “left pin” side, the common terminal d and the terminal a of the mode switch 45 are connected. At this time, relay 4
Since the contact output 47a2 of the relay 7 is off, the relay 4
Whether the solenoid 53e of the left lock cylinder switching valve 53 is energized is determined by the on / off of the a contact output 49a1 of No. 9. That is, when the proximity switch as an example of the jib storage detector 29 detects the detection plate 29a, the output of the jib storage detector 29 turns on the coil 49c of the relay 49 via the a contact output 48a2, and only at this time. , The left lock cylinder switching valve 53 is turned on by turning on the contact output 49a1.
Is energized. Thereby, the left lock cylinder switching valve 53 switches to the position c.

【0070】ここで、操作レバー56を手前に引くと、
方向切換弁57はa位置に切り換わり、油圧ポンプ58
から吐出された圧油が管路77、方向切換弁73のb位
置、管路103、管路105、左ロックシリンダ切換弁
53のc位置及び管路108からロックシリンダ17の
ヘッド側に流入する。ロックシリンダ17のボトム側か
ら流出した油は、管路107、逆止弁75及び管路76
を介して方向切換弁57からタンク59へドレーンす
る。これによって、操作レバー引き量に応じた速度でロ
ックシリンダ17は縮小し、上下の左ピン19aが抜か
れる。
Here, when the operation lever 56 is pulled forward,
The directional control valve 57 switches to the position a, and the hydraulic pump 58
From the pipe 77, the b-position of the direction switching valve 73, the pipe 103, the pipe 105, the c-position of the left lock cylinder switching valve 53, and the pipe 108 flow into the head side of the lock cylinder 17 from the pipe 108. . The oil flowing out from the bottom side of the lock cylinder 17 is supplied to the pipe 107, the check valve 75, and the pipe 76.
Through the directional control valve 57 to the tank 59. As a result, the lock cylinder 17 contracts at a speed corresponding to the operation lever pull amount, and the upper and lower left pins 19a are pulled out.

【0071】図17において、上部作業モードスイッチ
71からモーメントリミッタコントローラ52にジブモ
ード、またはブーム/シングルトップモード信号が出力
されると、モーメントリミッタコントローラモーメント
リミッタコントローラからジブ自動張出モードリレー4
6のコイル46cに通電されないため、a接点出力46
aがオフする。このときには通常のジブ作業、あるいは
ブーム/シングルトップ作業が可能となる。
In FIG. 17, when a jib mode or a boom / single top mode signal is output from the upper work mode switch 71 to the moment limiter controller 52, the momentary limiter controller and the jib automatic extension mode relay 4 are output from the moment limiter controller.
6 is not energized, so that the a contact output 46
a turns off. At this time, normal jib work or boom / single top work becomes possible.

【0072】前記準備(ジブ張出/格納)作業の手順に
ついて説明する。 (1) 準備(ジブ張出/格納)作業 (i) ジブ張出作業の手順 1)作業者は、ジブ7の固定手段30のピン33を抜き、
ジブ7の先端部を係止ピン21の回りに外側に振出した
後、ピン33をブラケット35のガイド用の孔35aに
挿入してジブ7が振り戻らないようにする。(図8〜図
12参照)これに伴って、ジブ7の基端部の上下のブラ
ケット15の上下板15b、15cの間に、及び上下板
15d、15eの間に、トップブーム6の左側面上下の
ブラケット61を挟み込み、お互いの孔15a及び孔6
1aを一致させる。また、第1リンク64の上下板64
a、64bの間にブラケット61を挟み込み、ピン67
とのブラケット61の孔61bを一致させる。
The procedure of the preparation (jib extension / storage) work will be described. (1) Preparation (jib overhang / retraction) work (i) Jib overhang work procedure 1) The operator pulls out the pin 33 of the fixing means 30 of the jib 7,
After the tip of the jib 7 is swung outward around the locking pin 21, the pin 33 is inserted into the guide hole 35a of the bracket 35 to prevent the jib 7 from swinging back. Accordingly, the left side surface of the top boom 6 is placed between the upper and lower plates 15b and 15c of the upper and lower brackets 15 at the base end of the jib 7 and between the upper and lower plates 15d and 15e. The upper and lower brackets 61 are sandwiched between the holes 15a and the holes 6 of each other.
1a is matched. The upper and lower plates 64 of the first link 64
a, 64b between the bracket 61 and the pin 67
And the hole 61b of the bracket 61 are matched.

【0073】2)運転室9内の操作パネルのジブ張出/格
納スイッチ41を「張出」側に、モード切替スイッチ4
5を「左ピン」側に切り換える。この状態で、操作レバ
ー56を引く。前述のように、ロックシリンダ17が伸
長し、上下の左ピン19aが上下のブラケット15の孔
15a及びブラケット61の61aに挿入される。ま
た、同時に、第3リンク66のピン67が第1リンク6
4の孔及び上部のブラケット61の孔61bに挿入され
る。 3)上下の左ピン19aの挿入が完了するまで待つ。左ピ
ン19aの挿入が完了すると、ロックピン挿入検出器7
0の一例である近接スイッチが検知片68aを検出し、
ロックピン挿入検出器70の出力が左ピンロック完了表
示43を点灯させる。と同時に、上記検出信号をモーメ
ントリミッタコントローラ52が入力する。
2) Set the jib extension / retraction switch 41 of the operation panel in the cab 9 to the “extension” side, and set the mode changeover switch 4
5 is switched to the “left pin” side. In this state, the operation lever 56 is pulled. As described above, the lock cylinder 17 extends, and the upper and lower left pins 19 a are inserted into the holes 15 a of the upper and lower brackets 15 and the 61 a of the bracket 61. At the same time, the pin 67 of the third link 66 is
4 and the hole 61b of the upper bracket 61. 3) Wait until the insertion of the upper and lower left pins 19a is completed. When the insertion of the left pin 19a is completed, the lock pin insertion detector 7
0, the proximity switch detects the detection piece 68a,
The output of the lock pin insertion detector 70 turns on the left pin lock completion display 43. At the same time, the detection signal is input to the moment limiter controller 52.

【0074】4)作業者は上記の左ピンロック完了表示器
43が点灯したことを確認してから、ジブ張出/格納ス
イッチ41の「張出」をオフ(これにより、ジブモード
となる)する。また、ブーム起伏レバー(図示せず)を
操作してブームを所定角度起こした後、ブーム伸縮レバ
ー(図示せず)を操作してブームを所定長さまで伸長す
る。このとき、モーメントリミッタコントローラ52
は、ロックピン挿入検出器70の上記検出信号が入力さ
れているときにのみ、ブーム3を伸長するようにしてい
る。よって、左ピン19aの挿入が完了しないままブー
ム3を伸長することが無くなるので、ジブ7の落下事故
等を防止でき、作業の安全性が向上で きる。 5)ブーム3を更に起こしながら、操作レバー56によっ
てジブ7を徐々に伏せる。ブーム角度が所定角度とな
り、ジブ7が鉛直になったら、補巻ロープ121を緩め
て補フック122を地面に寝かせる。補巻ロープ121
をジブ7の先端部のアイドラシーブ123及びジブシー
ブ124に通した後、補巻ロープ121を少し巻き上げ
て補フック122を地面から浮かせ、操作レバー56に
よってジブ7を最大に(ブーム3に対して略直角)伏せ
る。
4) After confirming that the above-mentioned left pin lock completion indicator 43 is lit, the operator turns off the "extension" of the jib extension / retraction switch 41 (this sets the jib mode). . Further, after operating the boom raising / lowering lever (not shown) to raise the boom by a predetermined angle, the user operates the boom extension / retraction lever (not shown) to extend the boom to a predetermined length. At this time, the moment limiter controller 52
Is designed to extend the boom 3 only when the detection signal of the lock pin insertion detector 70 is input. Therefore, since the boom 3 does not extend without the insertion of the left pin 19a being completed, a fall accident of the jib 7 can be prevented, and work safety can be improved. 5) The jib 7 is gradually lowered by the operation lever 56 while raising the boom 3 further. When the boom angle becomes a predetermined angle and the jib 7 becomes vertical, the auxiliary hoisting rope 121 is loosened and the auxiliary hook 122 is laid on the ground. Supplementary rope 121
Through the idler sheave 123 and the jib sheave 124 at the tip of the jib 7, the auxiliary rope 121 is slightly wound up to lift the auxiliary hook 122 from the ground, and the operation lever 56 maximizes the jib 7 (substantially with respect to the boom 3). Right angle) Prone.

【0075】6)ジブ張出/格納スイッチ41を「張出」
側に、モード切替スイッチ45を「回動」側に切り換
え、この状態で操作レバー56を引く。前述のように、
回動シリンダ63が伸長し、ジブ7がブーム3の前方に
回動する。図13に、回動シリンダ63が伸長してジブ
7をブーム3の前方に回動して張り出した状態を示して
いる。 7)モード切替スイッチ45を「右ピン」側に切り換え、
操作レバー56を引く。ロックシリンダ18が伸長し、
右ピン19bが上下のブラケット16とブラケット62
の孔16a、62aに挿入される。 8)ジブ張出/格納スイッチ41の「張出」をオフし(こ
れにより、ジブモードとなる)、操作レバー56によっ
てジブ7を起こしながら、ブーム3を略水平になるまで
最大に伏せる。 9)この後、補巻ロープ121の付け替え等を行う。
6) Set the jib extension / storage switch 41 to "extension".
Side, the mode changeover switch 45 is switched to the “rotation” side, and the operation lever 56 is pulled in this state. As aforementioned,
The rotation cylinder 63 extends, and the jib 7 rotates forward of the boom 3. FIG. 13 shows a state in which the rotating cylinder 63 is extended and the jib 7 is rotated forward of the boom 3 and extended. 7) Switch the mode changeover switch 45 to the “right pin” side,
Pull the operation lever 56. The lock cylinder 18 extends,
The right pin 19b is connected to the upper and lower brackets 16 and 62.
In the holes 16a and 62a. 8) The "extension" of the jib extension / retraction switch 41 is turned off (this results in a jib mode), and the jib 7 is raised by the operation lever 56, and the boom 3 is lowered to the maximum until it is substantially horizontal. 9) Thereafter, replacement of the auxiliary hoisting rope 121 is performed.

【0076】以上のように、ジブ7の振出し以後の左ピ
ン19aの挿入、ブーム3の起こし及び伸長、ジブ7の
伏せ及び回動、右ピン19bの挿入、ジブ7の起こし、
ブーム3の伏せ等の各操作が運転室9内でできるので、
作業時の安全性が高くなる。また、左ピン19aの挿入
完了を表示によって作業者に確認させると共に、左ピン
19aが挿入完了していないときは、モーメントリミッ
タコントローラ52がブーム3を伸長しないようにして
いる。よって、挿入が不完全な状態でのブーム3の伸長
によるジブ7の落下事故等を防止できる。
As described above, the insertion of the left pin 19a after the swing of the jib 7, the raising and extension of the boom 3, the downward and rotation of the jib 7, the insertion of the right pin 19b, the raising of the jib 7,
Since each operation such as prone boom 3 can be performed in the cab 9,
Safety during work is increased. Further, the operator is confirmed by the display that the insertion of the left pin 19a has been completed, and when the insertion of the left pin 19a has not been completed, the moment limiter controller 52 does not extend the boom 3. Accordingly, it is possible to prevent the jib 7 from dropping due to the extension of the boom 3 when the insertion is incomplete.

【0077】(ii) ジブ格納作業の手順 これまで説明した張出時の作業手順及び操作をほぼ逆に
行うことによって可能である。ここで、ジブ格納時は、
ジブ張出/格納スイッチ41を「格納」にする。但し、
張出時と一部異なる手順があり、以下にこの手順のみを
説明する。上記ジブ格納時の手順を逆に行って、ジブ7
をブーム3の前方から側方に回動し、さらにジブ7を起
こしてブーム3と略平行にしているものとする。(ここ
までは、上記9)から5)の逆手順を行う) この後、手順4)に対応する作業として、ブーム3を縮小
してジブ7の係止ピン21を係止ブラケット22の孔2
2aに挿入させる必要がある。図11はこのときのジブ
7の先端部をガイドする様子を表している。ブーム3の
縮小に伴って、ジブ7はブーム3の側面に沿ってブーム
3の基端部方向へ移動する。ジブ7側面のブラケット3
6の先端下面36aが、ブーム3のブラケット34のバ
ー37に当接する。ジブ7がブーム3の基端部方向へ移
動すると、先端下面36aはバー37に案内され、ブラ
ケット36がブラケット34上に乗るようになってい
る。
(Ii) Procedure for Jib Storage Work It is possible to perform the work procedure and operation at the time of overhang described above substantially in reverse. Here, when storing the jib,
The jib overhang / store switch 41 is set to "store". However,
There are some procedures that are different from those at the time of overhang, and only this procedure will be described below. Reverse the above procedure for storing the jib, and
Is turned laterally from the front of the boom 3 and the jib 7 is further raised to be substantially parallel to the boom 3. (Up to this point, the reverse procedure of the above 9) to 5) is performed.) Then, as a work corresponding to the procedure 4), the boom 3 is contracted and the locking pin 21 of the jib 7 is
2a. FIG. 11 shows a state in which the tip of the jib 7 is guided at this time. As the boom 3 shrinks, the jib 7 moves along the side surface of the boom 3 toward the base end of the boom 3. Bracket 3 on the side of the jib 7
The lower surface 36a of the end 6 contacts the bar 37 of the bracket 34 of the boom 3. When the jib 7 moves toward the base end of the boom 3, the lower end surface 36 a is guided by the bar 37, and the bracket 36 rides on the bracket 34.

【0078】また、ブラケット36の先端の傾斜部36
bがピン33の側面に当接しながらブラケット36は移
動し、最後にはブラケット36の側面36cがピン33
の側面に当接した状態にブラケット36はガイドされ
る。この状態のときにジブ7の係止ピン21が係止ブラ
ケット22の孔22aにちょうど挿入されるように、係
止ピン21と孔22aとの位置関係を調整しておく。こ
れは、ナット24aによる上下方向の調整、及びナット
26aによる左右方向の調整によって行うことができ
る。(図6、7参照)この結果、ブーム3の縮小に伴っ
て、ジブ7のブラケット36の先端下面36a及び傾斜
部36bがそれぞれバー37及びピン33によってガイ
ドされ、スムーズに係止ピン21が係止ブラケット22
の孔22aに挿入される。
The inclined portion 36 at the tip of the bracket 36
The bracket 36 moves while the b contacts the side surface of the pin 33, and finally the side surface 36 c of the bracket 36
The bracket 36 is guided in a state of contact with the side surface of the bracket 36. In this state, the positional relationship between the locking pin 21 and the hole 22a is adjusted so that the locking pin 21 of the jib 7 is just inserted into the hole 22a of the locking bracket 22. This can be performed by adjusting the nut 24a in the vertical direction and adjusting the nut 26a in the horizontal direction. (See FIGS. 6 and 7.) As a result, as the boom 3 is reduced, the lower end surface 36a and the inclined portion 36b of the bracket 36 of the jib 7 are guided by the bar 37 and the pin 33, respectively, and the locking pin 21 is smoothly engaged. Stop bracket 22
Into the hole 22a.

【0079】3)に対応する手順として、係止ピン21が
係止ブラケット22の孔22aに挿入完了するまで待
つ。係止ピン21の孔22aへの挿入が完了すると、ジ
ブ格納位置検出器29が検知板29aを検出し、ジブ格
納位置検出器29の検出出力がリレー49のコイル49
cを通電する。そして接点49a1を接続して左ピン19
aの操作を可能にする。2)に対応する手順として、ジブ
張出/格納スイッチ41を「格納」側にし、モード切替
スイッチ45を「左ピン」にしたとき、前述のように操
作レバー56を引くとロックシリンダ17を縮小できる
ようになり、左ピン19aを抜くことができる。この結
果、係止ピン21が孔22aに完全に挿入されて、ジブ
格納位置検出がされていないと左ピン19aを抜くこと
ができずジブ7が落下することを防止でき、作業の安全
性が向上する。
As a procedure corresponding to 3), the process waits until the locking pin 21 is completely inserted into the hole 22a of the locking bracket 22. When the insertion of the locking pin 21 into the hole 22a is completed, the jib storage position detector 29 detects the detection plate 29a, and the detection output of the jib storage position detector 29 outputs the coil 49 of the relay 49.
Power on c. Then, the contact 49a1 is connected to connect the left pin 19
The operation of a is enabled. As a procedure corresponding to 2), when the jib extension / retract switch 41 is set to the “retracted” side and the mode changeover switch 45 is set to the “left pin”, the lock cylinder 17 is reduced by pulling the operation lever 56 as described above. The left pin 19a can be pulled out. As a result, if the locking pin 21 is completely inserted into the hole 22a and the jib storage position is not detected, the left pin 19a cannot be pulled out and the jib 7 can be prevented from dropping, and work safety can be reduced. improves.

【0080】図20に示す電気制御回路の第2実施例の
作用について説明する。図17に示す第1実施例と共通
する部品には同一符号を付してその説明を省略し、異な
る部分についてのみ説明する。左ピン19aの挿入が完
了すると、ロックピン挿入検出器70が検知片68aを
検出し、ロックピン挿入検出器70の出力が左ピンロッ
ク完了表示器43を点灯すると共に、警報スイッチ69
のコイルを励磁してB接点に切り換わるため、警報ブザ
ー69aと警報ランプ69bとは作動しない。
The operation of the second embodiment of the electric control circuit shown in FIG. 20 will be described. Components common to those in the first embodiment shown in FIG. 17 are denoted by the same reference numerals, and description thereof will be omitted. Only different portions will be described. When the insertion of the left pin 19a is completed, the lock pin insertion detector 70 detects the detection piece 68a, the output of the lock pin insertion detector 70 turns on the left pin lock completion indicator 43, and the alarm switch 69
And the alarm buzzer 69a and the alarm lamp 69b do not operate.

【0081】一方ジブ格納ピン33の入りを検出した格
納ピン入り検出器33bの出力でも、警報スイッチ69
のコイルを励磁してB接点に切り換わるため、警報ブザ
ー69aと警報ランプ69bとは作動しない。即ち左ピ
ン19aがロック完了した張出時、または格納ピン33
の入りを検出する格納時には警報スイッチ69はB接点
に切り換わるため、警報ブザー68aと警報ランプ68
bとは作動しない。即ち左ピン19aがロック完了して
なく、しかもジブ格納ピン33の入りを検出すしないと
きには、警報スイッチ69はA接点に切り換わるため、
警報ブザー69aと警報ランプ69bとが作動して危険
であることを知らせる。つまりこの2つのピン19a,
33の両方が抜けていると警報する。この場合には特に
図16に示す第1実施例のようなソレノイド50aを有
するアンロード弁50を必要としなくとも、警報ブザー
69aと警報ランプ69bにより危険であることが分か
る。
On the other hand, the output of the storage pin insertion detector 33b which detects the insertion of the jib storage pin 33 is also used for the alarm switch 69.
And the alarm buzzer 69a and the alarm lamp 69b do not operate. That is, when the left pin 19a has been locked and the storage pin 33 has been extended.
The alarm switch 69 is switched to the contact B at the time of storage to detect the entry of the alarm, so that the alarm buzzer 68a and the alarm lamp 68
Does not work with b. That is, when the lock of the left pin 19a is not completed and the insertion of the jib storage pin 33 is not detected, the alarm switch 69 is switched to the A contact.
The alarm buzzer 69a and the alarm lamp 69b are activated to notify that it is dangerous. That is, these two pins 19a,
It warns that both 33 are missing. In this case, the alarm buzzer 69a and the alarm lamp 69b indicate that it is dangerous even if the unload valve 50 having the solenoid 50a as in the first embodiment shown in FIG. 16 is not required.

【0082】次に、図23に示す移動式クレーンの安全
装置の制御フローチャート、および表1により、本発明
に係る移動式クレーンの作業状態検出の制御について説
明する。
Next, the control for detecting the working state of the mobile crane according to the present invention will be described with reference to the control flowchart of the safety device for the mobile crane shown in FIG. 23 and Table 1.

【0083】[0083]

【表1】 [Table 1]

【0084】(1) 走行時 運転室9に設置された図示されないPTOスイッチによ
り「走行」を選択すると、図23においてステップS1
からS2に進む。 (i) ステップS2において、図11に示すジブ格納位置
検出器33bが格納ピン33が入っていることを検出す
ると、ステップS2からS3に進んで通常走行が行われ
る。この場合には表1の検出項;mに示すように、クレ
ーン車の状態は正常であるためブザーにより警告しな
い。しかしクレーン車の走行状態ではブーム等のクレー
ン作業は常に不可能のように設定されている。 (ii)ステップS2において、ジブ格納位置検出器33b
が格納ピン33が入っていることを検出しないと、ステ
ップS2からS4に進んで走行は可能であるが、走行時
に警報ブザーが発報されると共に、「格納ピン33が入
っていない」ことを図21のモーメントリミッタ表示パ
ネル40にディスプレイする。この場合には表1の検出
項;nに示すように、ジブ7落下の危険性があるためブ
ザーにより連続して警告する。
(1) Running When "running" is selected by a PTO switch (not shown) installed in the cab 9, step S1 in FIG.
To S2. (i) In step S2, when the jib storage position detector 33b shown in FIG. 11 detects that the storage pin 33 is inserted, the process proceeds from step S2 to S3, and normal traveling is performed. In this case, as shown by the detection item m in Table 1, the crane vehicle is in a normal state and does not warn with a buzzer. However, it is set such that crane work such as a boom is always impossible in a traveling state of a crane truck. (ii) In step S2, the jib storage position detector 33b
If it is not detected that the storage pin 33 is inserted, the process proceeds from step S2 to S4, and the vehicle can run. However, an alarm buzzer is issued at the time of driving, and it is determined that the storage pin 33 is not inserted. It is displayed on the moment limiter display panel 40 of FIG. In this case, there is a danger of the jib 7 dropping as shown in the detection item;

【0085】(2) 作業時(ジブモード、ブームモード、
準備モードの各作業モード共通) 運転室9に設置された図示されないPTOスイッチによ
り「作業」を選択すると、図23においてステップS1
からS5に進む。 (i) ステップS5において、左左ピン19a、ジブ格納
ピン33、および作業モードスイッチ71が正常であれ
ば、ステップS5からS6に進んで、表1に示すジブ作
業、ブーム/シングルトップ作業、および準備(ジブ張
出/格納)作業の各通常作業が行われる。この場合には
表1の検出項;a,f,i,jに示すように、クレーン
車の状態は正常であり、検出項;a,f,iではブザー
により警告しないと共に、ブーム等のクレーン作業が可
能となる。しかし検出項;jではジブ張出、格納のため
の準備作業を行うためブザーにより連続的に警告すると
共に、ブーム等のクレーン作業は不可能にする。
(2) During operation (jib mode, boom mode,
When "operation" is selected by a PTO switch (not shown) installed in the operator's cab 9 in step S1 in FIG.
To S5. (i) In step S5, if the left and right pins 19a, the jib storing pin 33, and the work mode switch 71 are normal, the process proceeds from step S5 to S6, and the jib work, boom / single top work shown in Table 1 and Each normal operation of the preparation (jib extension / storage) operation is performed. In this case, as shown in the detection items in Table 1, a, f, i, and j, the state of the crane vehicle is normal. Work becomes possible. However, in the detection term j, a warning is continuously given by a buzzer to perform a preparatory operation for the jib extension and storage, and a crane operation such as a boom is disabled.

【0086】(ii)ステップS5において、左左ピン19
a、格納ピン33、および作業モードスイッチ71が異
常であれば、ステップS5からS7に進む。 .ステップS7において作業モードスイッチ71の選
択が正しければ、ステップS7からS8に進む。 (a) ステップS8で左左ピン19aと格納ピン33が共
に抜けていれば、ステップS8からS9に進み、図17
に示すモーメントリミッタコントローラ52から図19
に示すアンロード弁50のソレノイド50aに通電さ
れ、ブームの切換操作弁の操作が不可能になるためブー
ムの伸し作業が停止し、警報ブザーが発報されると共
に、モーメントリミッタ表示パネル40のディスプレイ
に表1の検出項;d,h,lに示されるような、「危険
ジブ落下」、「確認 ジブ左ピン」、または「確認
格納ピン」のどれかを表示する。 (b) ステップS8で左左ピン19aと格納ピン33が共
に入っていれば、ステップS8からS10に進み、この
ような現象は実際あり得ないためコントローラ52等の
故障である。このような場合には表1の検出項;c,
g,kに示すように、図19のアンロード弁50のソレ
ノイド50aに通電され、ブーム作業を停止し、ブザー
で10秒間断続的に警報すると共に、ディスプレイに
「エラー」コードが表示される。
(Ii) In step S5, the left and right pins 19
If a, the storage pin 33, and the work mode switch 71 are abnormal, the process proceeds from step S5 to S7. . If the selection of the work mode switch 71 is correct in step S7, the process proceeds from step S7 to S8. (a) If both the left and right pins 19a and the storage pin 33 are disconnected in step S8, the process proceeds from step S8 to S9, and FIG.
19 from the moment limiter controller 52 shown in FIG.
, The solenoid 50a of the unload valve 50 is energized, and the operation of the boom switching operation valve becomes impossible, so that the extension operation of the boom is stopped, an alarm buzzer is issued, and the moment limiter display panel 40 "Dangerous jib drop", "Confirmation jib left pin", or "Confirmation" as shown in the detection items in Table 1 on the display; d, h, l
Displays one of the “storage pins”. (b) If the left and right pins 19a and the storage pin 33 are in the same position in step S8, the process proceeds from step S8 to S10. Since such a phenomenon is not actually possible, it is a failure of the controller 52 or the like. In such a case, the detection term in Table 1; c,
As shown in g and k, the solenoid 50a of the unload valve 50 in FIG. 19 is energized to stop the boom operation, intermittently warn for 10 seconds with a buzzer, and an "error" code is displayed on the display.

【0087】.ステップS7において作業モードスイ
ッチ71の選択が正しくなければ、ステップS7からS
11に進み、表1の検出項;b,eに示されるように、
「確認 作業モードスイッチ」、「確認 ジブ左ピ
ン」、または「確認 格納ピン」のどれかをモーメント
リミッタ表示パネルに表示すると共に、ブザーにより1
0秒間断続的に警報する。
[0087] If the selection of the work mode switch 71 is not correct in step S7, steps S7 to S
11 and the detection terms in Table 1;
One of “Confirmation work mode switch”, “Confirmation jib left pin” or “Confirmation storage pin” is displayed on the moment limiter display panel, and 1
Alarm intermittently for 0 seconds.

【0088】表1の制御により以下のような誤操作を防
止できるので安全となる。 (1) ジブ張出、格納中(ジブ準備モード)におけるピン
の入れ忘れによるジブの落下防止、抜き忘れによる破損
防止。 (2) ジブをブーム側面に格納しているときのピン入れ忘
れによるジブの落下防止。 (3) ジブをブーム前方へ張出した状態でブーム作業をす
るような作業モード選択ミスの警報。 (4) 走行中のジブピンの入れ忘れ、抜けによるジブ落下
防止。
The following erroneous operations can be prevented by the control shown in Table 1, which is safe. (1) Prevent the jib from dropping due to forgetting to insert the pin while the jib is overhanging and storing (jib preparation mode), and to prevent damage due to forgetting to pull out. (2) Prevent the jib from falling due to forgetting to insert the pin when the jib is stored on the side of the boom. (3) Warning of work mode selection error, such as performing boom work with the jib extended forward of the boom. (4) Prevents jib from falling due to forgetting to insert jib pin during running.

【0089】以上の各実施例ではブーム3の伸操作につ
いて説明したが、ブーム3の伸作業の他に、ブーム3の
縮、ブーム3の起・伏、ジブ7の起・伏、主ウインチ巻
上げ・巻下げ、補ウインチ巻上げ・巻下げ、左・右旋回
の計11の移動式クレーンの作業についても同様に制御
することが可能である。
In each of the above embodiments, the operation of extending the boom 3 has been described. In addition to the operation of extending the boom 3, the boom 3 is contracted, the boom 3 is raised and lowered, the jib 7 is raised and lowered, and the main winch is raised. It is also possible to control the work of the mobile crane 11 in total for lowering, raising and lowering the auxiliary winch, and turning left and right.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一実施例に係る移動式クレーンの側面
図である。
FIG. 1 is a side view of a mobile crane according to one embodiment of the present invention.

【図2】本発明の一実施例におけるジブ格納時の連結部
を示す平面図である。
FIG. 2 is a plan view showing a connecting portion when the jib is stored in one embodiment of the present invention.

【図3】本発明の一実施例におけるジブ格納状態の平面
図である。
FIG. 3 is a plan view of the jib retracted state in one embodiment of the present invention.

【図4】本発明の一実施例におけるジブ振出時の連結部
を示す平面図である。
FIG. 4 is a plan view showing a connecting portion when the jib is swung out according to the embodiment of the present invention.

【図5】本発明の一実施例におけるジブ振出状態を示す
平面図である。
FIG. 5 is a plan view showing a jib projecting state in one embodiment of the present invention.

【図6】図3のX−X断面図である。FIG. 6 is a sectional view taken along line XX of FIG. 3;

【図7】図6のY−Y断面図である。FIG. 7 is a sectional view taken along line YY of FIG. 6;

【図8】図3のP部詳細図で、(A)はジブ固定手段の
全体平面図、(B)は(A)のV矢視図である。
8 is a detailed view of a portion P in FIG. 3, wherein (A) is an overall plan view of the jib fixing means, and (B) is a view taken in the direction of arrow V in (A).

【図9】図8の側面図である。FIG. 9 is a side view of FIG.

【図10】図8に相当するジブ格納検出手段の第2実施
例を示す平面図である。
FIG. 10 is a plan view showing a second embodiment of the jib storage detecting means corresponding to FIG.

【図11】図5のQ部の振出直前の状態を示す平面図で
ある。
FIG. 11 is a plan view showing a state immediately before swinging of a Q portion in FIG. 5;

【図12】図11の側面図である。FIG. 12 is a side view of FIG. 11;

【図13】本発明の一実施例におけるジブ張出状態を示
す平面図である。
FIG. 13 is a plan view showing a jib overhang state in one embodiment of the present invention.

【図14】図2のZ矢視図である。14 is a view as viewed in the direction of the arrow Z in FIG. 2;

【図15】図12のA矢視図である。FIG. 15 is a view as viewed from the direction indicated by the arrow A in FIG. 12;

【図16】本発明の一実施例におけるフロントパネルを
示す平面図である。
FIG. 16 is a plan view showing a front panel according to one embodiment of the present invention.

【図17】本発明の一実施例における電気制御回路を示
す図である。
FIG. 17 is a diagram showing an electric control circuit according to one embodiment of the present invention.

【図18】本発明の一実施例における油圧制御回路を示
す図である。
FIG. 18 is a diagram showing a hydraulic control circuit according to one embodiment of the present invention.

【図19】本発明の一実施例における油圧制御回路を示
す図である。
FIG. 19 is a diagram showing a hydraulic control circuit according to one embodiment of the present invention.

【図20】図17に相当する本発明の第2実施例を示す
図である。
FIG. 20 is a diagram corresponding to FIG. 17, showing a second embodiment of the present invention.

【図21】本発明の一実施例におけるモーメントリミッ
タ表示パネルを示す図である。
FIG. 21 is a diagram showing a moment limiter display panel in one embodiment of the present invention.

【図22】図21のR部詳細図である。FIG. 22 is a detailed view of an R part in FIG. 21;

【図23】本発明の一実施例における安全装置の制御フ
ローチャートを示す図である。
FIG. 23 is a diagram showing a control flowchart of the safety device in one embodiment of the present invention.

【図24】従来技術を説明する移動式クレーンの全体側
面図である。
FIG. 24 is an overall side view of a mobile crane explaining a conventional technique.

【図25】従来技術の移動式クレーンのブームとジブの
ジブ格納状態における平面図である。
FIG. 25 is a plan view of the movable crane of the related art in the jib retracted state of the boom and the jib.

【図26】図23のブームとジブ連結部分の詳細平面図
である。
FIG. 26 is a detailed plan view of the boom and jib connecting portion of FIG. 23.

【図27】従来技術の移動式クレーンのジブ張出完了時
のブームとジブ連結部分の側面図である。
FIG. 27 is a side view of the boom and the jib connection portion of the conventional mobile crane when the jib overhang is completed.

【図28】従来技術の移動式クレーンのブームとジブの
ジブ振出状態における平面図である。
FIG. 28 is a plan view of a movable crane of the related art in a jib swinging state of a boom and a jib.

【図29】図28のブームとジブ連結部分の詳細平面図
である。
FIG. 29 is a detailed plan view of the boom and jib connecting portion of FIG. 28.

【図30】従来技術の移動式クレーンのジブ張出途中に
おける平面図である。
FIG. 30 is a plan view of a prior art mobile crane during jib extension.

【図31】従来技術の移動式クレーンのジブ張出完了状
態の平面図である。
FIG. 31 is a plan view of a mobile crane of the related art in a state where a jib overhang is completed.

【図32】図25のピン回りの断面詳細図で、(A)は
A−A断面図、(B)はB−B断面図である。
32 is a detailed cross-sectional view around a pin in FIG. 25, (A) is a cross-sectional view taken along AA, and (B) is a cross-sectional view taken along BB.

【図33】従来技術の移動式クレーンのブーム伸縮シリ
ンダの制御回路図である。
FIG. 33 is a control circuit diagram of a boom telescopic cylinder of a conventional mobile crane.

【符号の説明】[Explanation of symbols]

1…車体、3…ブーム、4…基段ブーム、6…トップブ
ーム、7…ジブ、8…上部旋回体、9…運転室、11…
ジブブラケット、12…ジブ本体、13、23、33、
38、80、83、94、96、97、98、99…ピ
ン、14…チルトシリンダ、15、16、25、31、
32、34、35、36、38、61、62、…ブラケ
ット、15a、16a、22a、22b、31a、32
a、35a、61a、61b、62a、95…孔、1
7、18…ロックシリンダ、19a…左ピン(請求項で
はロックピン)、19b…右ピン、15b,15c,1
5d,15e…板、20…係止手段、21…係止ピン、
22…係止ブラケット、24、26…ネジ、24a、2
6a…ナット、28…支持板、29…ジブ格納位置検出
器、29a…検知板、30…固定手段、33…ジブ格納
ピン、33a…ピン抜止めピン、33b…格納ピン入り
検出器(請求項ではジブ格納完了検出器)、33c…ジ
ブ格納完了検出器、36a…先端下面、36b…傾斜
部、36c…側面、37…バー、39…第1ストッパ、
40…モーメントリミッタ表示パネル、40a…フロン
トパネル、41…ジブ張出/格納スイッチ、42a、4
2b…第2ストッパ、43…左ピンロック完了表示器、
44…ジブ格納完了表示器、45…モード切替スイッ
チ、46、47、48、49、51…リレー、50…ア
ンロード弁、52…モーメントリミッタコントローラ、
53…左ロックシリンダ切換弁、54…回動シリンダ切
換弁、55…右ロックシリンダ切換弁、56a…操作レ
バー、56…操作弁、57、73…方向切換弁、58…
油圧ポンプ、58aパイロットポンプ、59…タンク、
63…回動シリンダ、64…第1リンク、65…第2リ
ンク、66…第3リンク、67…ジブ格納位置表示器、
68…ポール,68a…検知片、69…警報スイッチ、
69a…警報ブザー、69b…警報ランプ、70…ロッ
クピン挿入検出器、71…上部作業モードスイッチ、7
2…ケーブルドラム、74a、74b…リール、75…
逆止弁、76、77、101、102、103、10
4、105、106、107、108、109、11
0、111、112…管路、78…パイロット操作逆止
弁、79…カウンタバランス弁、81、82、85、8
7a、87b…ラグ、84…つの、89…スイッチボッ
クス、92、93…リンク、121…補巻ロープ、12
2…補フック、123…アイドラシーブ、124…ジブ
シーブ、125…シングルトップ、131…ボス、14
1…ブームシリンダ、142…ブーム操作弁、142a
…ブームレバー、143…方向切換弁、144…カウン
タバランス弁、145…管路、146…圧力制御弁。
DESCRIPTION OF SYMBOLS 1 ... Body, 3 ... Boom, 4 ... Base boom, 6 ... Top boom, 7 ... Jib, 8 ... Upper swing body, 9 ... Driver's cab, 11 ...
Jib bracket, 12 ... jib body, 13, 23, 33,
38, 80, 83, 94, 96, 97, 98, 99 ... pins, 14 ... tilt cylinders, 15, 16, 25, 31,
32, 34, 35, 36, 38, 61, 62,..., Brackets 15a, 16a, 22a, 22b, 31a, 32
a, 35a, 61a, 61b, 62a, 95 ... hole, 1
7, 18: lock cylinder, 19a: left pin (lock pin in claims), 19b: right pin, 15b, 15c, 1
5d, 15e: plate, 20: locking means, 21: locking pin,
22: locking bracket, 24, 26: screw, 24a, 2
6a: nut, 28: support plate, 29: jib storage position detector, 29a: detection plate, 30: fixing means, 33: jib storage pin, 33a: pin retaining pin, 33b: detector with storage pin (claim) , Jib storage completion detector), 33c ... jib storage completion detector, 36a ... lower end surface, 36b ... inclined portion, 36c ... side surface, 37 ... bar, 39 ... first stopper,
40: Moment limiter display panel, 40a: Front panel, 41: Jib extension / retract switch, 42a, 4
2b: second stopper, 43: left pin lock completion indicator,
44: Jib storage completion indicator, 45: Mode changeover switch, 46, 47, 48, 49, 51: Relay, 50: Unload valve, 52: Moment limiter controller,
53: Left lock cylinder switching valve, 54: Rotating cylinder switching valve, 55: Right lock cylinder switching valve, 56a: Operating lever, 56: Operating valve, 57, 73: Directional switching valve, 58 ...
Hydraulic pump, 58a pilot pump, 59 ... tank,
63: rotating cylinder, 64: first link, 65: second link, 66: third link, 67: jib storage position indicator,
68 ... pole, 68a ... detection piece, 69 ... alarm switch,
69a: alarm buzzer, 69b: alarm lamp, 70: lock pin insertion detector, 71: upper working mode switch, 7
2. Cable drum, 74a, 74b ... reel, 75 ...
Check valve, 76, 77, 101, 102, 103, 10
4, 105, 106, 107, 108, 109, 11
0, 111, 112: pipeline, 78: pilot operated check valve, 79: counterbalance valve, 81, 82, 85, 8
7a, 87b: lug, 84: one, 89: switch box, 92, 93: link, 121: auxiliary rope, 12
2: supplementary hook, 123: idle sheave, 124: jib sheave, 125: single top, 131: boss, 14
DESCRIPTION OF SYMBOLS 1 ... Boom cylinder, 142 ... Boom operation valve, 142a
.. Boom lever, 143 direction switching valve, 144 counterbalance valve, 145 pipe line, 146 pressure control valve.

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 伸縮自在なブーム(3) と、このブーム
(3) の側方に固定手段(30)により支持されて格納される
ジブ(7) と、このジブ(7) のブラケット(15)とブーム
(3) 先端の左右いずれか一方のブラケット(61)とに出入
するロックピン(19a) とを有し、前記ジブ(7) 使用時に
はブラケット(15)とブラケット(61)とに挿入されたロッ
クピン(19a) を中心に、ブーム(3) の側方に格納された
ジブ(7) をブーム(3) の前方に回動して張出す移動式ク
レーンにおける安全装置において、 ロックピン(19a) がブラケット(15)、(61)に挿入された
ことを検出するロックピン挿入検出器(70)と、 固定手段(30)の孔(31a) に挿入されて、ブーム(3) に格
納されたジブ(7) を固定するためのジブ格納ピン(33)
と、 このジブ格納ピン(33)が孔(31a) に挿入されているこ
と、またはジブ(7) がジブ格納位置にあることを検出す
るジブ格納完了検出器(33b,33c) と、 ジブ(7) の格納位置におけるブームまたはシングルトッ
プモードと、ジブ(7)の張出位置におけるジブモード
と、ジブ(7) の張出、格納操作を行う準備モードのいず
れかの作業モードを選択する上部作業モードスィッチ(7
1)と、 これら検出器(70,33b,33c) と、スイッチ(71)の状況に
よりクレーン作業、もしくはその一部操作を停止する
か、あるいは警告するコントローラ(52)とを備えたこと
を特徴とする移動式クレーンにおける安全装置。
A telescopic boom (3) and this boom
The jib (7) supported and stored by the fixing means (30) on the side of (3), the bracket (15) and the boom of this jib (7)
(3) A lock pin (19a) which goes into and out of one of the left and right brackets (61) at the tip, and a lock inserted into the bracket (15) and the bracket (61) when the jib (7) is used. In the safety device of a mobile crane that extends the jib (7) stored on the side of the boom (3) around the pin (19a) and extends it in front of the boom (3), the lock pin (19a) Was inserted into the bracket (15), (61) and the lock pin insertion detector (70), which was inserted into the hole (31a) of the fixing means (30), and stored in the boom (3). Jib storage pin (33) to secure jib (7)
A jib storage completion detector (33b, 33c) for detecting that the jib storage pin (33) is inserted into the hole (31a) or that the jib (7) is at the jib storage position; Upper work to select one of the boom or single top mode at the storage position of 7), the jib mode at the overhang position of the jib (7), and the preparation mode for extending and storing the jib (7). Mode switch (7
1), these detectors (70, 33b, 33c), and a controller (52) that stops or warns the crane operation or a part of its operation depending on the status of the switch (71). Safety devices in mobile cranes.
【請求項2】 請求項1において、作業モードスィッチ
(71)で選択した各作業モードにおいて、コントローラ5
2がロックピン挿入検出器(70)、およびジブ格納完了検
出器(33b,33c) からの検出信号を共に入力しないときに
は、警報ランプを点灯するか、警報ブザーを発報する
か、モニタパネルに文字によりディスプレイするかの少
なくとも一つにより警告するコントローラ(52)とを備え
たことを特徴とする移動式クレーンにおける安全装置。
2. The work mode switch according to claim 1,
In each work mode selected in (71), the controller 5
2 does not input the detection signals from the lock pin insertion detector (70) and the jib storage completion detector (33b, 33c), either turn on the alarm lamp, issue the alarm buzzer, or A safety device for a mobile crane, comprising: a controller (52) for giving a warning by at least one of displaying by text.
【請求項3】 請求項1において、移動式クレーンの走
行操作と作業機操作とを選択する選択スイッチを設置
し、この選択スイッチが走行操作を選択したときに、ジ
ブ格納完了検出器(33b,33c) からの検出信号を入力しな
いときには、走行中におけるジブの落下の危険性を、警
報ランプ、警報ブザー、あるいはメッセージ出力等で警
告するコントローラ(52)を備えたことを特徴とする移動
式クレーンにおける安全装置。
3. A jib storing completion detector (33b, 3b), wherein a selection switch for selecting a traveling operation and a work machine operation of the mobile crane is installed, and when the selection switch selects the traveling operation. 33c) A mobile crane characterized by comprising a controller (52) that warns of the danger of falling of the jib while driving by using an alarm lamp, an alarm buzzer, or a message output when the detection signal from the controller 33c) is not input. Safety devices in the.
JP30712396A 1996-11-01 1996-11-01 Safety device in mobile crane Expired - Fee Related JP3716952B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP30712396A JP3716952B2 (en) 1996-11-01 1996-11-01 Safety device in mobile crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP30712396A JP3716952B2 (en) 1996-11-01 1996-11-01 Safety device in mobile crane

Publications (2)

Publication Number Publication Date
JPH10139377A true JPH10139377A (en) 1998-05-26
JP3716952B2 JP3716952B2 (en) 2005-11-16

Family

ID=17965316

Family Applications (1)

Application Number Title Priority Date Filing Date
JP30712396A Expired - Fee Related JP3716952B2 (en) 1996-11-01 1996-11-01 Safety device in mobile crane

Country Status (1)

Country Link
JP (1) JP3716952B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003238075A (en) * 2002-02-08 2003-08-27 Tadano Ltd Jib housing device for crane truck
CN106379820A (en) * 2015-05-20 2017-02-08 鲁霄钢 Boom hoist provided with halting control system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003238075A (en) * 2002-02-08 2003-08-27 Tadano Ltd Jib housing device for crane truck
CN106379820A (en) * 2015-05-20 2017-02-08 鲁霄钢 Boom hoist provided with halting control system

Also Published As

Publication number Publication date
JP3716952B2 (en) 2005-11-16

Similar Documents

Publication Publication Date Title
JPH0270837A (en) Controller for position of working machine for construction machine
JP3640322B2 (en) Jib overhang, safety device in storage and control method thereof
CN110905404A (en) Omnibearing electric control drilling machine and control method thereof
JPH10139377A (en) Safety device of walking crane
KR20080021432A (en) Apparatus for fixing upper structure of excavator
JPH10139379A (en) Jib overhanging/storing operation device installed outside of operator cab of walking crane
US10829350B2 (en) Crane
JPH10139378A (en) Inspection/instructing device after projection and housing of jib in walking crane
JP7430068B2 (en) Display control device for work vehicles and work vehicles
JP4732060B2 (en) Steering device for work vehicle
JP2003164541A (en) Fireplug
JP6340298B2 (en) Work vehicle
CN116888330A (en) Engineering machinery
JP6342775B2 (en) Work vehicle
JP4754167B2 (en) Work vehicle control device
JP3604050B2 (en) Cabin lifting control device and control method for cabin lifting hydraulic crane vehicle
JP3958510B2 (en) Safety device for work vehicle
JP3964776B2 (en) Inspection equipment for aerial work platforms
JP2003040596A (en) Order picking vehicle
US20240003187A1 (en) Stair system for a working machine, working machine
JP2004249843A (en) Passage cutout device for moving cab of working machine
JP5852815B2 (en) Safety device for work machine having liftable cab
JP2576369Y2 (en) Hook storage device for vehicle-mounted cranes
JP3787056B2 (en) Safety device for high-altitude work equipment
JP3101158B2 (en) Cab-over vehicle step elevating device

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040705

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20041004

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20041118

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A712

Effective date: 20041118

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050824

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20050824

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees