JPH10135098A - System and method for production - Google Patents

System and method for production

Info

Publication number
JPH10135098A
JPH10135098A JP24366897A JP24366897A JPH10135098A JP H10135098 A JPH10135098 A JP H10135098A JP 24366897 A JP24366897 A JP 24366897A JP 24366897 A JP24366897 A JP 24366897A JP H10135098 A JPH10135098 A JP H10135098A
Authority
JP
Japan
Prior art keywords
time
production
lot
prototype
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP24366897A
Other languages
Japanese (ja)
Inventor
Toshihiro Morii
敏博 森井
Atsuyoshi Koike
淳義 小池
Sadao Shimosha
貞夫 下社
Masaru Kobayashi
勝 小林
Tsutomu Okabe
勉 岡部
Masao Sakata
正雄 坂田
Atsushi Tomizawa
淳 富澤
Kazuo Horiguchi
和男 堀口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP24366897A priority Critical patent/JPH10135098A/en
Publication of JPH10135098A publication Critical patent/JPH10135098A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Abstract

PROBLEM TO BE SOLVED: To accurately predict the arrival time of a trial lot by manufacturing the trial lot through a substantial physical process which does not give processing waiting time. SOLUTION: A trial lot is manufactured through a substantial physical process, which does not produce processing waiting times. Therefore, a production information management system 23 is provided for sharing the progress predicting information of the trial lot scheduled in real time one second by one second by fetching the state of a line which changes from time to time, the arranged state of each member, and the state of each section contributing to the trial manufacture among the sections contributing to the trial manufacture, so that the sections can make preparation by recognizing the timing and contents of the matters to be done. In addition, the real time schedule information is shared among the sections by respectively installing terminals 13-22 to the sections. Therefore, the production efficiency of the line can be prevented from being deteriorated.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は工業製品の生産シス
テム、および生産方法に関し、特に半導体製品、又は薄
膜製品などの特定のロットの開発期間短縮を図る生産シ
ステム、および生産方法に関するものである。
The present invention relates to a production system and a production method for industrial products, and more particularly to a production system and a production method for shortening the development period of a specific lot of a semiconductor product or a thin film product.

【0002】[0002]

【従来の技術】近年、半導体製品のニーズは多様化し、
特にカスタム品は他社との競合が激化している。このた
め、顧客のニーズにあわせて、必要な時期に製品をタイ
ムリーに納品することがシェアを確保することになる。
よって、製品受注から納入までの期間短縮を工夫するこ
とに各社力を入れている。特に、試作品の顧客への納入
期間短縮や、製品の試作から量産移管までの期間短縮を
工夫することは、重要である。しかし、製品の開発には
複雑な手順と工程を経るので、開発期間短縮は容易では
ない。半導体製品の開発手順を簡単に説明すると、ま
ず、顧客または市場のニーズを満足する機能をもつ製品
を設計部署が設計し、設計図面を作成する。この図面が
承認されると,この設計図面をもとに、マスク製造部署
が後述するリソグラフィ装置で使用するマスクを作成
し,プロセス開発部署が工程フローと製造仕様書、作業
指示書を作成する。この工程フロー、製造仕様書、作業
指示書が、承認されると、製造ラインのオペレータはこ
の工程フローと製造仕様書の指示に従って各種製造工程
処理と検査を行い、単結晶シリコンウエーハ上に半導体
素子を作る。半導体製造には、ウエーハの表面を洗浄す
る洗浄装置、表面に均一な酸化膜を形成する酸化処理装
置、ウエーハ上に不純物原子を拡散する拡散処理装置、
ウエーハ上に金属膜を形成するスパッタ装置、前述した
マスクを用いて、ウエーハ上にパターン化されたレジス
ト膜を形成するリソグラフィ装置、リソグラフィ装置に
より形成されたパターン化されたレジスト膜に沿って、
ウエーハを加工するエッチング装置、不純物原子をウエ
ーハに注入するイオン打ち込み装置等が使用される。こ
れら、半導体製品の製造装置は、加工精度の限界領域で
使用されるため、試作を行う場合には、各工程の製造装
置において、事前に加工条件調整が行われる。この作業
時間は装置の状態、要求される加工精度によってばらつ
く。このようにして、各種製造工程処理を経て試作品が
完成すると試作品は検査にまわされ、テスタにより,機
能が正常に動作するか、また、狙った性能が保証される
か試験される。このテストプログラムは設計部署が作成
する。通常、試作は数回繰り返されて、最適な、設計仕
様詳細、製造仕様詳細が絞りこまれていく。
2. Description of the Related Art In recent years, the needs of semiconductor products have diversified,
In particular, custom products are intensifying competition with other companies. For this reason, timely delivery of the product at the required time according to the needs of the customer will secure the market share.
Therefore, each company is focusing on reducing the time from product order to delivery. In particular, it is important to devise ways to shorten the time required to deliver prototypes to customers and to reduce the time required from product trial production to mass production transfer. However, product development involves complicated procedures and processes, and it is not easy to shorten the development period. To briefly explain the semiconductor product development procedure, first, a design department designs a product having a function that satisfies customer or market needs, and creates a design drawing. When this drawing is approved, the mask manufacturing department creates a mask to be used in a lithographic apparatus described later based on the design drawing, and the process development department creates a process flow, a manufacturing specification, and a work instruction. When the process flow, manufacturing specifications, and work instructions are approved, the operator of the manufacturing line performs various manufacturing process processes and inspections according to the instructions of the process flow and the manufacturing specifications, and the semiconductor device is placed on the single crystal silicon wafer. make. In semiconductor manufacturing, a cleaning apparatus for cleaning the surface of a wafer, an oxidation processing apparatus for forming a uniform oxide film on the surface, a diffusion processing apparatus for diffusing impurity atoms on the wafer,
Along with a sputtering apparatus for forming a metal film on a wafer, a lithographic apparatus for forming a patterned resist film on a wafer using the mask described above, and a patterned resist film formed by a lithographic apparatus,
An etching apparatus for processing a wafer, an ion implantation apparatus for implanting impurity atoms into the wafer, and the like are used. Since these semiconductor product manufacturing apparatuses are used in a region where the processing accuracy is limited, processing conditions are adjusted in advance in the manufacturing apparatus of each process when performing trial production. This work time varies depending on the state of the apparatus and the required processing accuracy. In this way, when the prototype is completed through various manufacturing process processes, the prototype is sent for inspection, and a tester is used to test whether the function operates normally and whether the intended performance is guaranteed. This test program is created by the design department. Normally, prototypes are repeated several times to narrow down the optimal design details and manufacturing specifications.

【0003】この試作品が、試作品検査に合格すると、
試作は完了する。この試作品はサンプル品として,顧客
に提供される。顧客がこのサンプル品の量産を注文する
と,量産ラインでは、新製品受け入れのための、量産試
作を行う。まず、量産試作に備えて、量産用製造装置で
は新製品用の加工条件の調整が行われる。この後、量産
ラインでは量産試作品が流され、この量産試作品が量産
試作検査に合格すると、顧客に出荷される。
[0003] When this prototype passes the prototype inspection,
The prototype is completed. This prototype is offered to customers as a sample. When a customer places an order for mass production of this sample product, the mass production line performs mass production trial production to accept a new product. First, in preparation for mass production trial, the processing conditions for a new product are adjusted in the mass production manufacturing apparatus. Thereafter, a mass production prototype is flown on the mass production line, and when the mass production prototype passes mass production prototype inspection, it is shipped to the customer.

【0004】以上、説明したように、製品の開発には複
雑な手順と工程を経るが、この手順の中で、開発期間短
縮に効果があるのは、試作ロットの製造期間を短縮する
こと、量産試作期間を短縮することである。
As described above, the development of a product involves complicated procedures and steps. Among these procedures, the effect of shortening the development period is to shorten the production period of a prototype lot. It is to shorten the mass production prototype period.

【0005】このためには、特開平7−211605号
公報で開示されているとおり、量産ラインにあわせて試
作用のラインを構築し、量産ラインを構成するリソグラ
フィ、エッチング、スパッタ等の、枚葉処理を行う装置
を試作ラインにおいても共用するのが有効である(図1
参照)。これにより、試作用のラインでは全工程が枚葉
処理化できるため、製造期間を短縮でき、試作製造を短
期間で繰返し行うことができる。なお,枚葉製造装置で
は,試作ロットを少数枚のウエーハで構成することによ
り,処理時間をさらに短縮できる。また、枚葉処理装置
を量産ラインと共有できるので、投資が節約できるし、
試作用加工条件を量産用加工条件へチューニングする期
間を短くできる。
For this purpose, as disclosed in Japanese Patent Application Laid-Open No. Hei 7-21605, a trial production line is constructed in accordance with a mass production line, and a single wafer such as lithography, etching, sputtering, etc. constituting the mass production line is manufactured. It is effective to share the processing equipment on the prototype line (Fig. 1
reference). As a result, in the trial operation line, all the processes can be performed on a single wafer, so that the manufacturing period can be shortened, and the trial manufacturing can be repeated in a short period of time. In the single-wafer manufacturing apparatus, the processing time can be further reduced by configuring the prototype lot with a small number of wafers. Also, since the single wafer processing equipment can be shared with the mass production line, investment can be saved,
The period for tuning the trial processing conditions to the mass production processing conditions can be shortened.

【0006】但し、このような,試作ラインと量産ライ
ンで共用している枚葉製造設備において、試作ロットの
到着時間を正確に予測できないと、以下のような不都合
が生じ、このラインの生産効率が低下する。という問題
がある。
However, in such a single-wafer manufacturing facility shared by the prototype line and the mass production line, if the arrival time of the prototype lot cannot be accurately predicted, the following inconvenience occurs, and the production efficiency of this line is raised. Decrease. There is a problem.

【0007】(1)試作ロットが予定より早く到着した
場合、以下の事象で、試作ロットが停滞する場合があ
る。
(1) When a prototype lot arrives earlier than expected, the prototype lot may stagnate due to the following events.

【0008】〔1〕製造設備が他のロット(量産ロッ
ト)を着工中。
[1] The manufacturing equipment is starting construction of another lot (mass production lot).

【0009】〔2〕製造設備が保全中。[2] The production equipment is under maintenance.

【0010】〔3〕製造設備において、試作ロット用加
工条件調整が完了していない。
[3] In the manufacturing equipment, adjustment of the processing conditions for the prototype lot has not been completed.

【0011】〔4〕担当オペレータが他の作業をしてい
て、手が離せない状況にいる。
[4] The operator in charge is doing other work and is in a situation where he cannot release his hand.

【0012】〔5〕試作ロットの処理に必要な製造仕様
書または、作業指示書が発行されていない。
[5] Manufacturing specifications or work instructions required for processing a prototype lot have not been issued.

【0013】(2)試作ロットが予定より遅く到着した
場合、量産ロットの生産が滞る。
(2) If the prototype lot arrives later than expected, the production of the mass production lot will be delayed.

【0014】(試作ロットの処理を最優先で行う場合、
試作ロットを停滞させないためには、事前に製造設備の
加工条件調整を完了し、製造設備とオペレータが他の作
業をしないで待機する必要がある。しかし、試作ロット
の到着が予定より遅い場合、その間、量産ロットの着工
と製造設備の保全ができないため量産ロットの生産が滞
る。)
(When the processing of the prototype lot is performed with the highest priority,
In order to prevent the prototype lot from stagnating, it is necessary to complete the adjustment of the processing conditions of the manufacturing equipment in advance, and the manufacturing equipment and the operator need to wait without performing other operations. However, if the arrival of the prototype lot is later than expected, the production of the mass production lot is delayed because the start of the mass production lot and the maintenance of the manufacturing equipment cannot be performed. )

【0015】[0015]

【発明が解決しようとする課題】以上より、量産ライン
にあわせて試作用のラインを構築し、量産ラインを構成
する枚葉処理を行う装置を試作ラインにおいても共用す
る生産ラインの生産効率を落とさないためには、試作ラ
インと量産ラインで共用する枚葉処理を行う製造装置に
おいて、試作ロットの着工日時を事前に正確に予測して
作業を進める必要がある。
SUMMARY OF THE INVENTION As described above, a production line is constructed in accordance with a mass production line, and the production efficiency of a production line in which an apparatus for performing single-wafer processing constituting the mass production line is shared with the prototype line is reduced. To avoid this, it is necessary to accurately predict the start date and time of the prototype lot in advance in a manufacturing apparatus that performs single-wafer processing that is shared by the prototype line and the mass production line before proceeding.

【0016】このためには、 課題1:試作ロットの製造に関し、事前に正確な日程計
画を立案する。
[0016] To this end, the problem 1: To prepare an accurate schedule in advance for the production of a prototype lot.

【0017】課題2:これを、計画どおり、前倒しや,
遅滞なく実施する。
Task 2: This is to be moved forward as planned,
Implement without delay.

【0018】課題1の試作ロットの正確な製造日程計画
立案に関しては、各工程の製造装置が試作ロット処理に
必要とする時間(以後、これを物理工完と定義する)
と、試作ロットの各工程での処理待ち時間を正確に知る
必要がある。物理工完は、各製造設備の処理レシピと加
工するウエーハ枚数がわかれば、算出できる。しかし、
試作ロットの各工程での処理待ち時間を正確に見積もる
ことは難しい。なぜならば、以下の事象が発生した場合
試作ロットの待ち時間が流動するからである。
Regarding the accurate production schedule planning of the prototype lot of the problem 1, the time required by the manufacturing apparatus in each process to process the prototype lot (hereinafter, this is defined as physical completion)
It is necessary to accurately know the processing waiting time in each process of the prototype lot. Physical completion can be calculated by knowing the processing recipe of each manufacturing facility and the number of wafers to be processed. But,
It is difficult to accurately estimate the processing waiting time in each process of a prototype lot. This is because the waiting time of the prototype lot flows when the following events occur.

【0019】〔1〕製造設備が他のロット(量産ロッ
ト)を着工中。
[1] The manufacturing facility is starting work on another lot (mass production lot).

【0020】〔2〕製造設備が保全中。[2] The manufacturing equipment is under maintenance.

【0021】〔3〕製造設備において、試作ロット用加
工条件調整が完了していない。
[3] In the manufacturing equipment, adjustment of the processing conditions for the prototype lot has not been completed.

【0022】〔4〕担当オペレータが他の作業をしてい
て、手が離せない状況にいる。
[4] The operator in charge is doing other work and is in a situation where he cannot release his hand.

【0023】〔5〕試作ロットの処理に必要な製造仕様
書または、作業指示書が発行されていない。
[5] Manufacturing specifications or work instructions required for processing a prototype lot have not been issued.

【0024】よって、課題1に対しては、試作ロットの
各工程での処理待ち時間を正確に見積もる必要がある。
Accordingly, for the problem 1, it is necessary to accurately estimate the processing waiting time in each process of the prototype lot.

【0025】また、課題2に対しては、試作ロットの正
確な製造日程計画を立案しても、以下の突発的な、事象
により、当初予定の日程計画と実際の試作ロットの生産
計画進行がずれてくることへの対応を考慮しなければな
らない。
Regarding the problem 2, even if an accurate production schedule of a prototype lot is prepared, the following unexpected event causes the schedule schedule initially planned and the production plan of an actual prototype lot to progress. We need to consider how to deal with the shift.

【0026】・製造装置の突発的なトラブルによる試作
ロットの停滞。
Stagnation of prototype lots due to unexpected troubles in manufacturing equipment.

【0027】・製造装置の試作ロット用加工条件調整が
もたつき、試作ロットが到着しても完了しない。
The adjustment of the processing conditions for the prototype lot of the manufacturing apparatus is delayed, and is not completed even when the prototype lot arrives.

【0028】・各工程で必要になる部材や、リソグラフ
ィ装置に必要なマスクのラインへの入荷が遅れる。
The arrival of parts required in each step and mask lines required for the lithographic apparatus is delayed.

【0029】[0029]

【課題を解決するための手段】このような課題を解決す
るために、本発明は、量産ラインにあわせて試作用のラ
インを構築し、量産ラインを構成する枚葉処理を行う装
置を試作ラインにおいても共用する生産システムにおい
て、試作ロットには,処理待ち時間を与えない、実質的
な物理工完で製造することを特徴とする。また、本発明
は、製造装置のトラブルや,部材の手配遅れ,試作製造
に関わる各部署の準備遅れなど,時々刻々変化する試作
ロットの進行状況の中で,試作ロットに処理待ち時間を
与えずに実質的な物理工完で製造するために,試作製造
にかかわる各部署が,いつ,何をすべきか事前に把握
し,準備できるように,時々刻々変化するラインの状況
や,部材手配状況,及び試作製造に関わる各部署の状況
を取り込んでリアルタイムにスケジュールした試作ロッ
トの秒単位の進行予測を,試作製造に関わる部署間で共
有させる生産情報管理システムを備えることを特徴とす
る。
SUMMARY OF THE INVENTION In order to solve the above-mentioned problems, the present invention is to construct a prototype line in accordance with a mass production line, and to provide an apparatus for performing a single-wafer processing which constitutes the mass production line. In the production system commonly used in the above, the prototype lot is manufactured by substantially complete physical engineering without giving a processing wait time. Further, in the present invention, a processing lot is not given a processing wait time to a prototype lot in a progressing state of the prototype lot which changes every moment such as a trouble of a manufacturing apparatus, a delay in arranging parts, a delay in preparation of each department related to a trial production, and the like. In order to make the production with substantial physics work, the departments involved in the trial production can understand in advance when and what to do and prepare for it, so that the situation of the line, which is constantly changing, And a production information management system for sharing the progress prediction in seconds of the prototype lot scheduled in real time by taking in the status of each department involved in the trial production between the departments involved in the trial production.

【0030】[0030]

【発明の実施の形態】以下、本発明の実施例を図面に基
づいて詳細に説明する。
Embodiments of the present invention will be described below in detail with reference to the drawings.

【0031】量産ラインにあわせて試作用のラインを構
築し、量産ラインを構成する枚葉処理を行う装置を試作
ラインにおいても共用する生産システムにおいて、図2
に示すように、試作ロットには処理待ち時間を与えな
い、実質的な物理工完で製造する。これにより、各工程
への試作ロットの着工予定日時は[投入日時]+[一番始
めの工程から着工開始日時を算出したい工程の前工程ま
での物理工完の総和]で正確に与えられる。
In a production system in which a trial production line is constructed in accordance with a mass production line and an apparatus for performing a single-wafer processing constituting the mass production line is also used in the prototype line, FIG.
As shown in (1), the prototype lot is manufactured with substantial physical processing without giving a processing wait time. As a result, the scheduled start date and time of the prototype lot for each process is accurately given by [input date and time] + [sum of physical work completion from the first process to the process before the process for which the start of the process is desired to be calculated].

【0032】なお、実質的な物理工完で製造するには次
の運用ルールを適用する。
The following operation rules are applied to manufacture with substantially complete physical engineering.

【0033】(1)試作ラインでの試作ロットの処理
は、前工程の処理が終わり次第、次工程の処理が開始さ
れる。製造設備の加工条件調整等の事前作業時間は、試
作ロットの到着前に完了している。
(1) In the processing of a prototype lot in the prototype line, the processing of the next step is started as soon as the processing of the previous step is completed. The pre-operation time, such as adjustment of the processing conditions of the manufacturing equipment, has been completed before the arrival of the prototype lot.

【0034】(2)試作ラインにおいて1台の設備で、
複数の試作ロットの処理が、かちあうことによる、待ち
を発生させない。このために,試作ラインへの試作ロッ
トの投入量は制限する。
(2) With one facility in the prototype line,
No waiting occurs due to the processing of a plurality of prototype lots. For this reason, the amount of prototype lots put into the prototype line is limited.

【0035】(3)試作ラインと量産ラインで共有され
る枚葉製造装置において、試作ロットの処理が予定され
ている時間には量産ロットの処理と製造設備の保全は行
わないように、事前に調整する。
(3) In the single-wafer manufacturing apparatus shared by the prototype line and the mass production line, the processing of the mass production lot and the maintenance of the manufacturing equipment are not performed during the time when the processing of the prototype lot is scheduled. adjust.

【0036】また、製造装置のトラブルや,部材の手配
遅れ,試作製造に関わる各部署の準備遅れなど,時々刻
々変化する試作ロットの進行状況の中で,試作ロットに
処理待ち時間を与えずに実質的な物理工完で製造するた
めに,試作製造にかかわる各部署が,いつ,何をすべき
か事前に把握し,準備できるように,時々刻々変化する
ラインの状況や,部材手配状況,及び試作製造に関わる
各部署の状況を取り込んでリアルタイムにスケジュール
した試作ロットの秒単位の進行予測情報を,試作製造に
関わる部署間で共有させる生産情報管理システムを備え
ることにより,当初予定の日程計画と実際の試作ロット
の生産計画進行がずれた場合にも、製造にかかわる各部
署が、それぞれの計画を、迅速に修正し対応できるの
で、試作ロットの当初製作日程計画に対する、実際の製
作進行のずれを最小限に押さえることができる。本生産
システムは、製造にかかわる各部署に端末を配置し、図
3に示すようなイメージで、以下の試作ロットのリアル
タイムスケジュール情報を各部署間で共有させる。
Further, in the progress of the prototype lot, which changes every moment, such as a trouble in the manufacturing equipment, a delay in arranging parts, and a delay in preparation of each department related to the trial production, the processing time is not given to the prototype lot. In order to make it possible for each department involved in the trial production to understand and prepare in advance for preparation and preparation for actual physical engineering, the line conditions that change every moment, the arrangement of parts, and By incorporating a production information management system that captures the status of each unit related to prototype manufacturing in seconds and predicts the progress of a prototype lot in real time, which is scheduled in real time, between the units involved in prototype manufacturing, it has a production information management system that can be used for initial planning and scheduling. Even when the actual production schedule of the production lot deviates, the departments involved in manufacturing can quickly correct and respond to their plans. For production scheduling, it is possible to minimize the deviation of the actual production progress. In this production system, terminals are arranged in each department involved in manufacturing, and the following real-time schedule information of the prototype lot is shared between the departments in an image as shown in FIG.

【0037】〔1〕試作ロットの製造日程の当初計画
と、実績と秒単位の進行予測のリアルタイム表示。
[1] Real-time display of the initial plan of the production schedule of the prototype lot, the actual results and the progress prediction in seconds.

【0038】〔2〕試作ラインを構成する製造装置の状
況(設備トラブル発生のリアルタイム通知等)。
[2] Status of manufacturing equipment constituting a prototype line (real-time notification of occurrence of equipment trouble, etc.)

【0039】〔3〕各部署での試作ロット製造準備の進
行状況(エンジニアによる製造装置の加工条件調整)。
[3] Progress of preparation for production of a prototype lot in each department (engineer's processing condition adjustment by an engineer).

【0040】〔4〕試作ラインの各工程に対する、製造
仕様書、作業指示書の発行の有無とその内容。
[4] Whether or not a manufacturing specification and a work instruction have been issued for each process of the prototype line and the contents thereof.

【0041】〔5〕部材と、マスクの納入予定または納
入実績。
[5] Delivery schedule or delivery results of members and masks.

【0042】この端末の情報は図4に示す生産情報管理
システム[23]により生成される。この生産情報管理シス
テム[23]のしくみと運用を以下説明する。
The terminal information is generated by the production information management system [23] shown in FIG. The structure and operation of this production information management system [23] will be described below.

【0043】生産情報管理システム[23]は、生産ライン
の製造にかかわる開発管理[1]、設計 [2], プロセス開
発[3]、ライン管理[4]、マスク製造[5]、部材メーカ
[6]、テスタ[7]、製造ライン[8]の各部署に置かれたシ
ステム端末[13]〜[20]から、各担当が随時入力する情報
(詳細は後述)と、製造ラインの製造設備[10]、ウエーハID
識別ソーティンク゛システム[11]や検査設備[12]からオンライン収
集した情報をリアルタイムに集めて、加工し、この情報
を各部署に置かれたシステム端末[13]〜[20]へ出力す
る。
The production information management system [23] includes development management [1], design [2], process development [3], line management [4], mask manufacturing [5], and component maker related to the production of the production line.
[6], the tester [7], the system terminal [13] to [20] located in each department of the production line [8], the information that each person inputs at any time (details will be described later), and the production of the production line Equipment [10], wafer ID
Information collected online from the identification sorting system [11] and inspection equipment [12] is collected in real time, processed, and output to the system terminals [13] to [20] located in each department.

【0044】以下,生産情報管理システム[23]の運用と
しくみを詳細に説明する。
Hereinafter, the operation and mechanism of the production information management system [23] will be described in detail.

【0045】(1)試作ロットの製造開始準備の運用 図5を用いて、試作ロットの製造開始準備の運用を説明
する。
(1) Operation for Preparing for Production Start of Prototype Lot The operation for preparing for production start of a prototype lot will be described with reference to FIG.

【0046】(1.1)開発管理[1]の作業 投入する試作ロットの情報(試作ロットNo、製品名、優
先度、等)をシステム端末[13]から入力する。
(1.1) Work of Development Management [1] Information on the prototype lot to be input (prototype lot number, product name, priority, etc.) is input from the system terminal [13].

【0047】なお、ラインに投入できるロットのMax数
は前述したように制限する必要があるため、その数もあ
らかじめシステム端末[13]より入力する。
Since the maximum number of lots that can be put into the line needs to be limited as described above, the number is also input in advance from the system terminal [13].

【0048】(1.2)生産情報管理システム[23]の処
理 システム端末[13]より登録された試作ロットの情報を、
表1に示すような、試作ロット管理リスト[24]へ登録す
る。このリストはFIFOと優先度により試作開始の順番の
並べ替えを行う。試作ロット管理リスト[24]では、登録さ
れたロットに関する情報(製品名、優先度、リスト登録
日時、投入予定日時、完成予定日時、図面登録期限と実
績、仕様書登録期限と実績、部材型登録期限と納入実
績、工程フロー登録期限と実績、製造仕様書登録期限と
実績、マスク発注期限と実績、部材発注期限と実績、
等)が参照できる。(試作ロット管理リスト[24]の運用詳
細は後述する。)
(1.2) Processing of the production information management system [23] The information of the prototype lot registered from the system terminal [13] is
It is registered in the prototype lot management list [24] as shown in Table 1. This list rearranges the order of starting the trial production by FIFO and priority. In the prototype lot management list [24], information on registered lots (product name, priority, list registration date and time, scheduled input date and time, scheduled completion date, drawing registration deadline and result, specification registration deadline and result, member type registration Deadlines and delivery results, process flow registration deadlines and results, manufacturing specifications registration deadlines and results, mask order deadlines and results, member order deadlines and results,
Etc.) can be referred to. (Details of the operation of the prototype lot management list [24] will be described later.)

【0049】[0049]

【表1】 [Table 1]

【0050】(1.3)開発管理[1]の作業 システム端末[13]を使って、試作ロット管理リスト[24]
へ、設計[2]が担当する次の作業の期限を登録する。
(図面作成,仕様書作成,試作ロットの製造に必要な部
材型指定、等)。同様にして、エンジニア[3]が担当す
る次の作業の期限も試作ロット管理リスト[24]へ登録す
る。(工程フロー作成,製造仕様書作成,各工程の製造
装置の物理工完見積もり,作業指示書作成、等) (1.4)生産情報管理システム[23]の処理 開発管理[1]の入力した情報をもとに、試作ロット管理リス
ト[24]に設計[2]エンジニア[3]の作業期限を登録する。
この情報は各システム端末から参照することができる。
(1.3) Work of development management [1] Using the system terminal [13], a prototype lot management list [24]
, Register the deadline for the next work in charge of design [2].
(Preparation of drawings, preparation of specifications, designation of component types required for production of prototype lots, etc.). Similarly, the deadline of the next work assigned by the engineer [3] is also registered in the prototype lot management list [24]. (Preparation of process flow, preparation of production specifications, estimation of physical work completion of production equipment for each process, preparation of work instructions, etc.) (1.4) Processing of production information management system [23] Input of development management [1] Based on the information, the work deadline of the design [2] engineer [3] is registered in the prototype lot management list [24].
This information can be referenced from each system terminal.

【0051】(1.5)設計[2]の作業 開発管理[1]の入力した登録期限までに、図面作成作
業,仕様書作成作業、部材型の指定を実行し,作成した
図面[キー:製品名]、仕様書[キー:製品名]、部材型指定[キ
ー:製品名,使用する工程名称]をシステム端末[13]より
登録する。もし、これらの作業が間に合わない場合は、
登録完了予定日時を変更して入力する。
(1.5) Work of design [2] By the registration deadline entered in development management [1], the drawing creation work, the specification creation work, and the specification of the member type are executed, and the created drawing [key: Register the product name], specification [key: product name], and material type designation [key: product name, process name to be used] from the system terminal [13]. If you ca n’t do that,
Change the registration completion schedule date and time and enter it.

【0052】(1.6)生産情報管理システム[23] 設計[2]の入力した図面,仕様書、部材型を図面・製造
仕様書DB[25]へ記憶する。この情報は各システム端末
から参照することができる。そして試作ロット管理リスト
[24]に図面、仕様書、部材型登録完了を登録する。登録
作業が間に合わないため、設計[2]が登録完了予定日を
変更すれば、それを試作ロット管理リスト[24]に登録す
る。この情報はアラームとして、各システム端末から参照す
ることができる。
(1.6) Production Information Management System [23] The drawings, specifications, and member types input by the design [2] are stored in the drawing / manufacturing specifications DB [25]. This information can be referenced from each system terminal. And the prototype lot management list
In [24], register the drawing, specification, and member type registration completion. If the design [2] changes the expected registration completion date, it is registered in the prototype lot management list [24] because the registration work cannot be completed in time. This information can be referenced from each system terminal as an alarm.

【0053】(1.7)エンジニア[3]の作業 開発管理[1]の入力した登録期限までに、工程フロー作成,
製造仕様書作成、作業指示書作成、各工程の製造装置の
物理工完(レシヒ゜,枚数の組合せ分)算出を実行し、作成
した工程フロー[キー:製品名]と製造仕様書[キー:製品
名、工程名称、作業指示書]をシステム端末[15]より登
録する。また、各工程の製造装置の物理工完見積もりは
製造仕様書に入力欄があり、そこに入力する。また、製
造仕様書には各工程で使用する製造装置名称と製造レシ
ピの入力欄がある。ここに製造装置名称と製造レシピを
入力する。また製造仕様書には各工程で使用する検査装
置名称と検査レシピの入力欄がある。ここに検査装置名
称と検査レシピを入力する。もしこれらの作業が間に合
わない場合は、登録完了予定日を変更して入力する。
(1.7) Work of engineer [3] By the registration deadline entered in development management [1], process flow creation,
The process flow [key: product name] and the manufacturing specifications [key: product] are created by creating the manufacturing specifications, creating work instructions, and calculating the physical completion of the manufacturing equipment for each process (combination of the ratio and the number of sheets). Name, process name, work instruction] from the system terminal [15]. In addition, there is an input column in the manufacturing specification sheet for the physical engineering completion estimate of the manufacturing apparatus in each process, and is input there. Further, the manufacturing specification has input fields for a manufacturing apparatus name and a manufacturing recipe used in each process. Here, a manufacturing apparatus name and a manufacturing recipe are input. In addition, the manufacturing specification has input fields for an inspection device name and an inspection recipe used in each process. Here, the inspection device name and the inspection recipe are input. If these tasks cannot be completed in time, change the registration completion date and enter it.

【0054】また、ここには、ウエーハID識別ソーティンク゛システム
へ指示するウエーハ#毎の挿入、抜き取り指示レシピの入力
欄がある。
Further, here, there is an input column for an insertion / extraction instruction recipe for each wafer # instructed to the wafer ID identification sorting system.

【0055】なお、製造仕様書と作業指示書は試作ロッ
トの製造の進行中でも必要に応じて,変更,新規登録を
行う場合がある (1.8)生産情報管理システム[23]の処理 エンジニア[3]の入力した工程フロー、製造仕様書、作業指
示書を図面・製造仕様書DB[25]へ記憶する。この情報
は各システム端末から参照することができる。
The production specifications and work instructions may be changed or newly registered as needed even during the production of the prototype lot. (1.8) Processing engineer of production information management system [23] The process flow, the production specification, and the work instruction entered in [3] are stored in the drawing / production specification DB [25]. This information can be referenced from each system terminal.

【0056】また、製造仕様書に記載されている製造レシ
ヒ゜、検査レシヒ゜、ウエーハ挿入抜取り指示を製造装置[10]とウエ
ーハID識別ソーティンク゛システム[11]、検査装置[12]にオンライン
回線でタ゛ウンロート゛する。そして、試作ロット管理リスト[24]
に工程フロー、製造仕様書、作業指示書登録完了を登録す
る。登録作業が間に合わないため、エンジニア[3]が登
録完了予定日時を変更すればそれを試作ロット管理リスト
[24]に登録する。この情報はアラームとして各システム端末
から参照することができる。
Also, the manufacturing lithography, inspection lithography, and wafer insertion / extraction instruction described in the manufacturing specifications are downloaded to the manufacturing apparatus [10], the wafer ID identification sorting system [11], and the inspection apparatus [12] via an online line. . And the prototype lot management list [24]
Register the process flow, manufacturing specifications, and work order registration completion in. Since the registration work is not in time, if the engineer [3] changes the scheduled completion date and time, it will be changed to the prototype lot management list
Register in [24]. This information can be referenced from each system terminal as an alarm.

【0057】(1.9)開発管理[1]の作業 設計[2]による図面,仕様書,部材型登録の完了と、エ
ンジニア[3]による工程フロー,製造仕様書,各工程毎
の製造装置毎の物理工完と作業指示書の登録完了を試作
ロット管理リスト[24]で確認する。なお、あらかじめ設計
[2]が登録する部材型の発注から納期に必要な時間は開
発管理[1]があらかじめシステム端末[13]から登録す
る。設計[2]とエンジニア[3]の作業が遅れている試作品
がある場合は、その試作ロットよりも優先度が低くて
も、設計[2]とエンジニア[3]の作業が完了している試作
品があれば、試作ロット管理リスト[24]上のロットの順序
変更を行う場合がある。
(1.9) Work of development management [1] Completion of registration of drawings, specifications, and member types by design [2], process flow by engineer [3], manufacturing specifications, and manufacturing equipment for each process Confirm the completion of each physical work and the registration of the work order in the prototype lot management list [24]. In addition, design in advance
The development management [1] registers in advance from the system terminal [13] the time required for the delivery date from ordering the member type registered in [2]. If there is a prototype whose design [2] and engineer [3] work is delayed, the work of design [2] and engineer [3] is completed even if the priority is lower than the prototype lot If there is a prototype, the order of lots on the prototype lot management list [24] may be changed.

【0058】(1.10)生産情報管理システム[23]の
処理 設計[2]による図面,仕様書,部材型登録と、エンジニ
ア[3]による工程フロー,製造仕様書,各工程毎の製造
装置毎の物理工完と作業指示書の登録が完了すると、試
作ロット進行予測計算機能[27]で、各試作ロットの投入か
ら完成までの総工完時間の計算を実行する。これは次の
手順で計算される。対象製品の工程フローを構成する各
工程名を検索キーに、図面・製造仕様書DBから、該当す
る製造仕様書を検索し、その中に記載されている製造設
備毎の物理工完テ゛ータを、工程フローの順序で、一番始め
の工程から最後の工程までの物理工完の総和を計算す
る。次に、試作ロット管理リスト[24]上の投入待ちロット
の投入予定日時と完成日時を計算して、試作ロット管理リ
スト[24]へ出力する。
(1.10) Processing of the production information management system [23] Registration of drawings, specifications, and member types by design [2], and process flows, manufacturing specifications by engineers [3], and manufacturing equipment for each process After the completion of each physical work and the registration of the work instruction, the total work completion time from the input of each prototype lot to completion is calculated by the prototype lot progress prediction calculation function [27]. This is calculated by the following procedure. Using the process names of the process flow of the target product as search keys, search the drawing / manufacturing specification DB for the relevant manufacturing specifications, and enter the physical engineering completion data for each manufacturing facility described in that. In the order of the process flow, the total of the physical processes from the first process to the last process is calculated. Next, the scheduled input date and time and the completion date and time of the lot waiting to be input on the prototype lot management list [24] are calculated and output to the prototype lot management list [24].

【0059】この投入予定日時と完成日時は待ちロット
のリストの並べ変えを行う度に再計算される。これは次
の手順で計算される。まず、投入日時の計算を行う。こ
れは、日程管理表DB[26]から、現在ラインで着工中の全
試作ロット情報を検索し、着工中のロット数が投入Max
数かどうか確認し、Max数に達しない場合には現在日時
を投入日時とする。また投入Max数のロットを着工中の
場合には、試作ラインで着工中の全試作ロットの日程管
理表の予定線(予定線の計算手順は後述する。)で、完
成予定日時の一番早い試作ロットの完成予定日時を試作
ロット管理リスト[24]先頭ロットの投入日時とする。投入
予定日時が決まれば、各試作ロットの総工完時間は計算
されているので、[完成予定日時]=[投入予定日時]+[総
工完時間]で計算される。以上計算された情報をもと
に、各試作ロットの日程計画を計算する。それには各試
作ロットの各工程での着工予定日時を計算する必要があ
るが、それは、計算対象となる試作ロットの投入予定日
時と各工程での物理工完を使って[各工程での試作ロッ
トの着工予定日時]=[投入日時]+[一番始めの工程から
着工予定日時を算出したい工程の前工程までの各工程の
物理工完の総和]で計算する。そして各試作ロットの部
材の製造開始時期を計算する。これは次の手順で計算さ
れる。まず、計算の対象となる試作ロットの工程で部材
を必要とする工程と部材型の発注から納期に必要な時間
を図面・製造仕様書DB[25]から検索し、この時間を上記
で計算した各試作ロットの工程で部材を必要とする工程
の着工開始日時から減算して求める。以上計算した情報
は日程管理表DB[26]に記憶され、[図3]に示す日程管理
表上の当初予定線と予測線として、各システム端末から
参照できる。当初予定線は各工程の着工開始予定日時を
打点しているものである。予測線は、当初予定線に対
し、実績線がずれてきた場合、当初予定線よりもより正
確に、次工程以降の各工程での試作ロット着工開始予定
日時を各部署の担当へ提供し、また試作ロットの製造進
行が当初予定日時と比較して、遅れているのか、進んで
いるのかの目安を提供する。予測線は着工を開始する前
は、当初予定線と一致している。(試作進行に伴う予測
線の更新手順は後述する。)以上の処理が完了すると、
試作ロット管理リスト[24]の進捗を投入準備完了にすすめ
る。
The input scheduled date and time and the completion date and time are recalculated every time the list of waiting lots is rearranged. This is calculated by the following procedure. First, the input date and time is calculated. This is because, from the schedule management table DB [26], information on all prototype lots currently under construction at the current line is searched, and the number of lots under construction is entered.
Check if it is a number, and if it does not reach the Max number, set the current date and time as the input date and time. When the lots with the maximum number of inputs are under construction, the scheduled completion date and time is the earliest in the scheduled line (the procedure for calculating the planned line will be described later) in the schedule management table of all the prototype lots under construction on the prototype line. The scheduled completion date and time of the prototype lot is set as the input date and time of the first lot of the prototype lot management list [24]. Once the scheduled input date and time is determined, the total work completion time of each prototype lot has been calculated, so it is calculated as [scheduled completion date] = [scheduled input date and time] + [total work completion time]. Based on the information calculated above, a schedule plan for each prototype lot is calculated. To do so, it is necessary to calculate the scheduled start date and time for each process in each prototype lot, and this is calculated using the scheduled input date and time of the prototype lot to be calculated and the physical work completion for each process. Scheduled lot start date / time] = [input date / time] + [sum of the physical work completion of each process from the first process to the process before the process for which the scheduled start date / time is to be calculated]. Then, the production start time of the members of each prototype lot is calculated. This is calculated by the following procedure. First, the time required for the delivery process from the order of the process and the order of the material type in the process of the prototype lot to be calculated was searched from the drawing / manufacturing specification DB [25], and this time was calculated above. It is obtained by subtracting from the start date and time of the start of the process that requires members in the process of each prototype lot. The information calculated above is stored in the schedule management table DB [26], and can be referred to from each system terminal as the initial planned line and the predicted line on the schedule management table shown in FIG. Initially, the scheduled line is a point at which the scheduled start date and time of each process is scheduled. When the actual line deviates from the initially scheduled line, the forecast line provides the scheduled start date and time of the start of the prototype lot in each process after the next process to the person in charge of each department more accurately than the initially planned line, It also provides an indication as to whether the production progress of the prototype lot is delayed or advanced compared to the originally scheduled date and time. Before the start of construction, the forecast line is consistent with the originally planned line. (The procedure for updating the prediction line accompanying the progress of the prototype will be described later.) When the above processing is completed,
Advance the progress of the prototype lot management list [24] to completion of input preparation.

【0060】(2)試作ロット製造開始の運用 (2.1)開発管理[1]の作業 試作ロット管理リスト[24]で、投入準備完了した試作ロットに
関し、投入開始指示を入力する。
(2) Operations for Starting Production of Prototype Lot (2.1) Development Management [1] Work Inputting a start instruction for the prototype lot whose preparation has been completed in the prototype lot management list [24].

【0061】(2.2)生産情報管理システム[23]の処
理 開発管理[1]により投入開始指示が入力された試作ロッ
トに関し、部材製造開始時期までに部材を自動的に発注
する。また、発注が完了すると、部材メーカに用意された
システム端末[ 18 ]からは部材の製造開始時期と納期が
参照できる。製造開始日時が来たら、アラームを生成し、そ
れを各システム端末に送信する。各システム端末はこの
情報を、音や画像点滅等により各部署の担当へアラームす
る。
(2.2) Processing of the Production Information Management System [23] For the prototype lot for which the input start instruction has been input by the development management [1], parts are automatically ordered by the time of starting the parts production. When the order is completed, the production start time and delivery date of the component can be referenced from the system terminal [18] prepared by the component maker. When the production start date and time comes, an alarm is generated and transmitted to each system terminal. Each system terminal alarms this information to the person in charge of each department by sound or image blinking.

【0062】そして、投入日時が来た試作ロットに関し、
投入開始をアラームで各システム端末に送信する。
Then, regarding the prototype lot whose input date and time has come,
The start of feeding is transmitted to each system terminal as an alarm.

【0063】(3)試作ロット製造中の運用 主に図6を用いて試作ロット製造中の運用について説明
する。
(3) Operation During Prototyping Lot Production The operation during trial production lot production will be described mainly with reference to FIG.

【0064】(3.1)マスク製造[5],部材メーカ[6]マスク 、部材の納入時期をシステム端末[17],[18]で確認し
て、試作ラインへの納入時期に間に合うように、マス
ク、部材を製造し、試作ラインへ納める。マスク製造
[5],部材メーカ[6]は、マスク、部材の製作が納期に十
分に間に合って進められると判断すれば,他の製品のマ
スクや部材の製造を行い、時間に余裕が無ければ、対象
試作ロットのマスクや部材の製造を最優先で進める。も
し、マスク、部材の納入が納期に間に合わない場合に
は、システム端末[17]、[18]を使って、試作ロット管理リ
スト[24]のマスク、部材納入予定日時を変更する。
(3.1) Mask manufacturing [5], member manufacturer [6] Check the delivery time of masks and members on the system terminals [17] and [18], and make sure that it is in time for delivery to the prototype line. , Masks and components are manufactured and delivered to the prototype line. Mask manufacturing
[5], the component maker [6], if it is judged that the production of masks and components can be carried out sufficiently in time for delivery, manufactures masks and components of other products, and if there is not enough time, the target Production of masks and members for prototype lots is a top priority. If the delivery of masks and components is not in time for delivery, the scheduled delivery date and time of masks and components in the prototype lot management list [24] are changed using the system terminals [17] and [18].

【0065】(3.2)生産情報管理システム[23]の処
理 もしマスク、部材の納入予定日時が変更された場合,図
7に示すように、変更された部材、マスクの納入予定日
時が、試作ロットの該当工程着工開始日時となるように
日程管理表の予測線を更新する。これは次の手順で計算
する。これは、着工開始予定日時を変更する工程以降の
予測線を消去して、現在の実績線と変更された部材、マ
スクの納入予定日時を直線でつなぎ、それ以降の予測線
を構成する打点を、[予測線上の各工程の試作ロット着
工開始予定日時]=[変更された着工開始予定日時]+[着工
開始予定日時が変更された工程から、着工開始予定日時
を算出したい工程の前工程までの物理工完の和]で計算
して打点する。この情報をアラームとして各システム端末に
送信する。各システム端末はこの情報をもとに、音や画
像点滅等により各部署の担当へアラームする。この情報は他
の部署のシステム端末より参照できる。
(3.2) Processing of Production Information Management System [23] If the scheduled delivery date and time of the masks and members are changed, as shown in FIG. The prediction line in the schedule management table is updated so as to be the start date and time of the process start of the prototype lot. This is calculated in the following procedure. This is to delete the forecast line after the process of changing the scheduled start date and time, connect the current actual line with the changed scheduled delivery date and time of the members and masks, and set the dots that make up the forecast line after that. , [Scheduled start date and time of the prototype lot for each process on the forecast line] = [Changed scheduled start date and time] + [From the process where the scheduled start date and time was changed to the process before the process for which the scheduled start date and time is to be calculated] Calculated by sum of physics engineering]. This information is transmitted to each system terminal as an alarm. Based on this information, each system terminal issues an alarm to the person in charge of each department by sound or image blinking. This information can be referenced from system terminals of other departments.

【0066】なお、部材、マスクの納入予定日時変更が
取り消されない限り、試作ロットの実績更新に伴う予測線
の更新は、上記手順により計算が続行される。
As long as the change of the scheduled delivery date and time of the member and the mask is not canceled, the update of the prediction line accompanying the update of the actual result of the prototype lot is continued by the above procedure.

【0067】(3.3)各部署の担当 修正された日程計画をシステム端末で確認し、その情報
をもとに,自分の作業計画の修正を行う。
(3.3) Responsibility of Each Department The revised schedule plan is confirmed on the system terminal, and based on the information, the own work plan is revised.

【0068】(3.4)エンジニア[3]の作業 製造ラインで試作ロットの製造が開始されると,エンジ
ニア[3]は,各工程での試作ロットの製造が遅滞無く行
われるように、エンジニア[3]が担当する、試作ライン
の各製造設備毎の加工条件調整及び製造仕様書の変更,
作業指示書発行を試作ロットの各工程到着までに完了さ
せるべく,システム端末[15]で,試作ロットの進行状況
を確認しながら、作業を行う。エンジニア[3]は,これ
らの作業が各工程着工開始日時までに十分に時間に余裕
を持って進められると判断すれば,他の作業(別製品の
作業など)を行い、時間に余裕が無ければ、これらの作
業に集中する。
(3.4) Work of Engineer [3] When the production of the prototype lot is started on the production line, the engineer [3] operates the engineer so that the production of the prototype lot in each process is performed without delay. [3] is responsible for adjusting the processing conditions and changing the manufacturing specifications for each manufacturing facility on the prototype line,
In order to complete the issuance of the work order by the arrival of each process of the prototype lot, work is performed while checking the progress status of the prototype lot at the system terminal [15]. If the engineer [3] judges that these operations can be carried out with sufficient time by the start date and time of each process, they will perform other operations (eg, work on a different product), and will not have enough time. If you concentrate on these tasks.

【0069】もし、これらの作業が、対象工程の試作ロ
ット着工開始予定に間に合わない場合には、システム端
末[15]を使って、日程管理表DB[26]の着工開始予定日
時を変更する。
If these operations are not in time for the start of the trial lot start of the target process, the scheduled start date and time of the schedule management table DB [26] is changed using the system terminal [15].

【0070】(3.5)生産情報管理システム[23]の処
理 エンジニアにより、着工開始予定日時変更の入力が有っ
た場合、予測線表の再計算を行う(計算の手順は、マス
ク、部材の納期変更と同じ)。この情報をアラームとして各
システム端末に送信する。各システム端末はこの情報
を、音や画像点滅等により各部署の担当へアラームする。
(3.5) Processing of the Production Information Management System [23] When the engineer inputs a change of the scheduled start date and time, the predicted line table is recalculated. Same as delivery date change). This information is transmitted to each system terminal as an alarm. Each system terminal alarms this information to the person in charge of each department by sound or image blinking.

【0071】(3.6)各部署の担当の作業 修正された日程計画をシステム端末で確認し、その情報
をもとに、自分の作業計画の修正を行う。
(3.6) Work assigned to each department Check the revised schedule plan on the system terminal, and modify its own work plan based on the information.

【0072】(3.7)ライン管理[4]の作業 量産ラインと共用する、試作ラインの製造装置の、試作
ロット着工開始予定日時を日程管理表で確認し、試作ロ
ットが遅滞なく着工できるように、量産ロットの着工計
画と製造設備のメンテナンス計画を立ててラインオペレ
ータへ指示する。計画を立てる時には、次の2点に注意
して進める。
(3.7) Operation of Line Management [4] The scheduled start date and time of the start of the production lot of the production equipment of the production line, which is shared with the mass production line, is confirmed in the schedule management table so that the production lot can be started without delay. Next, a start plan for the mass production lot and a maintenance plan for the manufacturing equipment are made, and the line operator is instructed. When planning, keep in mind the following two points.

【0073】〔1〕量産ロットの着工が、試作ロットの
着工予定日時とかちあわないように、量産ロットの着工
計画と製造設備のメンテナンス計画を調整する。
[1] The start plan of the mass production lot and the maintenance plan of the manufacturing equipment are adjusted so that the start of the start of the mass production lot does not conflict with the scheduled start date and time of the prototype lot.

【0074】〔2〕試作ロット製造のための製造設備の
加工条件調整が試作ロットの着工開始予定日時までに完
了するようにする。またこのとき、加工条件調整完了か
ら試作ロットの着工開始予定日時までに、無駄な待ち時
間が空かないようにする。
[2] Adjustment of the processing conditions of the manufacturing equipment for manufacturing the prototype lot is completed by the scheduled start date and time of the prototype lot. At this time, no unnecessary waiting time is left between the completion of the processing condition adjustment and the scheduled start date and time of the start of the prototype lot.

【0075】(3.8)ラインオペレータ[9]の作業 日程管理表で、試作ロットの進行状況を確認しながら、
ライン管理[4]の指示どおりに量産ロットの着工計画と
製造設備のメンテナンス計画を実行する。
(3.8) Checking the progress of the prototype lot in the work schedule management table of the line operator [9]
Execute the start plan of mass production lot and the maintenance plan of manufacturing equipment as instructed by line management [4].

【0076】また、試作ロットの着工開始と着工完了の
実績はその都度システム端末[20]に入力する。
The actual results of the start and the completion of the start of the prototype lot are input to the system terminal [20] each time.

【0077】但し、オンライン化された製造装置[10]の
場合は、着工開始と完了の実績は自動的に生産情報管理
システム[23]に上がる。
However, in the case of the online manufacturing apparatus [10], the results of the start and completion of the construction automatically increase to the production information management system [23].

【0078】(3.9)生産情報管理システム[23] ラインオペレータ[9]により入力された試作ロットの着
工実績をもとに、図8に示すように、日程管理表の実績
線と予測線を更新する。実績線は現在までに着工完了し
た各工程の着工開始日時を打点したものである。ここ
で、予測線の更新に関しては、[予測線上の各工程の試
作ロット着工開始予定日時]=[現在試作ロットを着工中
の工程の着工開始日時]+[現在着工中の工程から着工開
始日時を計算したい工程の前工程までの物理工完の和]
で計算される。この予測線の更新に伴い、マスク製造[5]、
部材メーカ[6]への、マスク、部材製作開始時期と納期も再計
算され、更新される。
(3.9) Production Information Management System [23] Based on the actual results of the start of the prototype lot input by the line operator [9], as shown in FIG. To update. The performance line is a plot of the start date and time of the start of each process completed to date. Here, regarding the update of the forecast line, [Scheduled start date and time of the start of the prototype lot for each process on the forecast line] = [Start date and time of the start of the process that is currently starting the start of the prototype lot] + [Start date and time of the start of the process currently being started. The sum of physics work up to the process before the process for which you want to calculate]
Is calculated. With the update of this forecast line, mask manufacturing [5],
The mask and member production start time and delivery date to the member manufacturer [6] are also recalculated and updated.

【0079】なお、現在着工中の工程で試作ロットの着
工開始実績が入力された日時と現在日時との差がこの工
程の物理工完を超えても、この工程の作業完了実績が入
力されない場合には、この情報をアラーム(試作ロット停
滞)として、各システム端末へ送信する。各システム端
末はこの情報を、音や画像点滅等により各部署の担当へ
アラームする。この情報は各システム端末から参照できる。
When the difference between the date and time when the actual start date of the start of the prototype lot is input in the process currently under construction and the current date and time exceeds the physical work completion of this process, the operation completion result of this process is not input. This information is transmitted to each system terminal as an alarm (prototype lot stagnation). Each system terminal alarms this information to the person in charge of each department by sound or image blinking. This information can be referenced from each system terminal.

【0080】(4)ラインで製造装置にトラブルが発生
した場合の運用 (4.1)製造ラインのオペレータ[9]の作業 試作ラインの製造設備にトラブルが発生した場合、オペ
レータ[9]は、トラブルの発生した設備名称とその状況
をシステム端末[20]へ入力する。
(4) Operation when trouble occurs in the production equipment on the line (4.1) Work of operator [9] on the production line When trouble occurs on the production equipment on the prototype line, the operator [9] Enter the name of the facility where the trouble occurred and its status into the system terminal [20].

【0081】(4.2)生産情報管理システム[23]の処
理 オペレータ[9]がシステム端末[20]から入力した情報をア
ラームとして各システム端末に送信する。各システム端末
はこの情報を、音や画像点滅等により各部署の担当へアラ
ームする。
(4.2) Processing of Production Information Management System [23] The information input by the operator [9] from the system terminal [20] is transmitted to each system terminal as an alarm. Each system terminal alarms this information to the person in charge of each department by sound or image blinking.

【0082】(4.3)エンジニア[3]の作業 トラブルが製造設備に関するものであり、これが試作ロ
ットの製造に影響を与えると判断した場合、製造設備の
復旧予定日時をシステム端末[15]より入力し、最優先で
復旧作業を行い,対応が終わり次第、その復旧日時をシ
ステム端末[15]より入力する。
(4.3) Work of Engineer [3] If it is determined that the trouble is related to the manufacturing equipment and this affects the production of the prototype lot, the date and time of the scheduled recovery of the manufacturing equipment is reported from the system terminal [15]. The recovery work is entered with the highest priority, and the recovery date and time is input from the system terminal [15] as soon as the response is completed.

【0083】(4.4)生産情報管理システム[23]の処
理 もし復旧予定日時が予測線上の試作ロットの着工開始予
定日時よりも遅くなる場合は,図7に示すように、製造
設備の復旧予定日時が試作ロットの該当工程着工開始日
時となるように予測線を更新する。(この計算は前述し
た、エンジニア[3]による着工開始予定日時変更入力に
伴う、予測線の更新と同じ方法で行われる。)但し、エ
ンジニア[3]により、復旧作業完了が入力された場合
で、その日時がトラブルによる着工開始日時変更時に表
示していた着工開始日時より早く完了した場合は、トラ
ブルによる着工開始予定日時変更で入力された情報を消
去して、予測線の再計算を行う。この情報をアラームとして
各システム端末に送信する。各システム端末はこの情報
をもとに、音や画像点滅等により各部署の担当へアラームす
る。この情報は他の部署のシステム端末より参照でき
る。
(4.4) Processing of the Production Information Management System [23] If the scheduled recovery date and time is later than the scheduled start date and time of the start of the prototype lot on the prediction line, as shown in FIG. The prediction line is updated so that the scheduled date and time is the start date and time of the start of the corresponding process of the prototype lot. (This calculation is performed in the same manner as the update of the forecast line when the engineer [3] enters the scheduled start date and time change.) However, when the engineer [3] inputs the completion of the recovery work, If the date and time is completed earlier than the start date and time of the start displayed when the start date and time of the trouble are changed, the information input in the change of the scheduled start date and time of the start due to the trouble is deleted and the prediction line is calculated again. This information is transmitted to each system terminal as an alarm. Based on this information, each system terminal issues an alarm to the person in charge of each department by sound or image blinking. This information can be referenced from system terminals of other departments.

【0084】(4.5)各部署の担当 修正された日程計画をシステム端末で確認し、その情報
をもとに,自分の作業計画の修正を行う。
(4.5) Responsibility of each department The revised schedule plan is confirmed on the system terminal, and based on the information, the own work plan is revised.

【0085】(4.6)開発管理[1] 試作ロットの製造が完了すると、試作ロット動作検査が
テスタ部門で行われるが、それに必要な、テスタの事前
手配を行う。手配は日程管理表により、試作ロット製造完
了日時を確認し、その日時にテスタが確保できるように
手配する。
(4.6) Development Management [1] When the manufacture of the prototype lot is completed, the prototype lot operation inspection is performed in the tester section, and the tester necessary for it is arranged in advance. Arrangements are made by confirming the date and time of completion of the production of the prototype lot from the schedule management table and making arrangements so that the tester can secure the date and time.

【0086】(4.7)テスタ部署[7] 試作ロットの進行状況を確認して、試作ロットの製造が
完了次第、動作検査が行えるようにテスタの準備を行
い、試作ロットが到着次第動作検査を行う。
(4.7) Tester section [7] The progress of the prototype lot is checked, and as soon as the production of the prototype lot is completed, the tester is prepared so that the operation test can be performed. I do.

【0087】また、本発明により、非常に短い期間で試
作ロットの製造を行えるが、本生産方式に加えて、さら
に、次の手段即ち、試作ロットの途中工程の検査装置に
よる検査は行わず、試作ロットの製造後の、テスタのみ
による動作検査を行う方法を採用すれば、試作ロットの
製造期間はさらに短縮されるので、途中工程の検査装置
による検査を行う方法で流す期間と比較して、2回以上
の試作を実施できる場合が出てくる。その場合は、途中
工程の検査工程は省略したほうが効率が良い。
According to the present invention, a prototype lot can be manufactured in a very short period of time. However, in addition to this production system, the following means, ie, inspection by an inspection device in the middle of the trial lot, is not performed. If the method of performing operation inspection using only a tester after the production of the prototype lot is adopted, the production period of the prototype lot can be further shortened. In some cases, two or more prototypes can be implemented. In that case, it is more efficient to omit the inspection step in the middle.

【0088】(5)試作完了後の運用 (5.1)生産情報管理システム[23]の処理 試作ロットの製造が完了すると、その試作ロットの情報
を試作ロット管理リスト[24]から消去し、日程管理線表
は保存する。このテ゛ータは開発管理[1]、エンジニア[3]等
により参考テ゛ータとして活用される。
(5) Operation after Prototype Completion (5.1) Processing of Production Information Management System [23] When the production of the prototype lot is completed, the information of the prototype lot is deleted from the prototype lot management list [24]. Save the schedule management line table. This data is used as reference data by development management [1], engineer [3], etc.

【0089】以上、本発明の生産システムを半導体製
造、または、薄膜製造の試作品の製造に用いた場合、試
作品の開発期間短縮に効果がある。また、本生産システ
ムは、試作品を製造する前の、実験品の製造に応用する
ことができる。
As described above, when the production system of the present invention is used for the production of a prototype of semiconductor production or thin film production, it is effective in shortening the development period of the prototype. In addition, the present production system can be applied to the production of experimental products before the production of prototypes.

【0090】また、本システムでは、試作ロットを実質
的な物理工完で製造することを特徴とするが、試作ロッ
トを特定の期間で製造する場合にも、応用できる。ま
た、量産ラインにあわせて試作ラインを構築し、量産ラ
インを構成する枚葉処理を行う装置を試作ラインにおい
ても共用する生産システムの形態をとらなくても、試作
ロットと量産ロットが混在生産される生産システムにお
いて、試作ロットを特定の期間で製造する場合には応用
できる。さらに、通常の量産ラインにおいても、特定の
ロットを特定の期間で製造する場合には、応用できる。
The present system is characterized in that a prototype lot is manufactured by substantially physical work, but the present invention can also be applied to a case where a prototype lot is manufactured in a specific period. In addition, a prototype line is constructed in line with the mass production line, and the prototype lot and the mass production lot can be mixedly produced without taking the form of a production system that shares the equipment that performs single-wafer processing that constitutes the mass production line with the prototype line. It can be applied to the case where a prototype lot is manufactured in a specific period in a production system. Further, the present invention can be applied to a case where a specific lot is manufactured in a specific period in a normal mass production line.

【0091】[0091]

【発明の効果】量産ラインにあわせて試作用のラインを
構築し、量産ラインを構成するリソグラフィ、エッチン
グ、スパッタ等の、枚葉処理を行う装置を試作ラインに
おいても共用する生産ラインにおいて、試作ラインと量
産ラインで共用している枚葉製造設備において、試作ロ
ットの到着時間を正確に予測できるため、以下のような
不都合が生じないので、このラインの生産効率が低下し
ない。
According to the present invention, a prototype line is constructed in accordance with a mass production line, and a single production line such as a lithography, etching, and sputter device that constitutes the mass production line is shared with the prototype line. Since the arrival time of the prototype lot can be accurately predicted in the single-wafer manufacturing facility shared with the mass production line, the following inconvenience does not occur, and the production efficiency of this line does not decrease.

【0092】(1)試作ロットが予定より早く到着した
場合、次の事象で、試作ロットが停滞する場合がある。
(1) When a prototype lot arrives earlier than expected, the prototype lot may be stagnated by the following events.

【0093】〔1〕製造設備が他のロット(量産ロッ
ト)を着工中。
[1] The manufacturing facility is starting work on another lot (mass production lot).

【0094】〔2〕製造設備が保全中。[2] The manufacturing equipment is under maintenance.

【0095】〔3〕製造設備において、試作ロット用加
工条件調整が完了していない。
[3] In the manufacturing facility, adjustment of the processing conditions for the prototype lot has not been completed.

【0096】〔4〕担当オペレータが他の作業をしてい
て、手が離せない状況にいる。
[4] The operator in charge is doing other work and is in a situation where he cannot release his hand.

【0097】〔5〕試作ロットの処理に必要な製造仕様
書または、作業指示書が発行されていない。
[5] Manufacturing specifications or work instructions required for processing a prototype lot have not been issued.

【0098】(2)試作ロットが予定より遅く到着した
場合、量産ロットの生産が滞る。
(2) When the prototype lot arrives later than expected, the production of the mass production lot is delayed.

【0099】(試作ロットの処理を最優先で行う場合、
試作ロットを停滞させないためには、事前に製造設備の
加工条件調整を完了し、製造設備とオペレータが他の作
業をしないで待機する必要がある。しかし、試作ロット
の到着が予定より遅い場合、その間、量産ロットの着工
と製造設備の保全ができないため量産ロットの生産が滞
る。)
(When the processing of the prototype lot is performed with the highest priority,
In order to prevent the prototype lot from stagnating, it is necessary to complete the adjustment of the processing conditions of the manufacturing equipment in advance, and the manufacturing equipment and the operator need to wait without performing other operations. However, if the arrival of the prototype lot is later than expected, the production of the mass production lot is delayed because the start of the mass production lot and the maintenance of the manufacturing equipment cannot be performed. )

【図面の簡単な説明】[Brief description of the drawings]

【図1】量産ラインにあわせて試作用のラインを構築
し、量産ラインを構成する枚葉処理を行う装置を試作ラ
インにおいても共用する生産システムを示す。
FIG. 1 shows a production system in which a prototype line is constructed in accordance with a mass production line, and an apparatus for performing single-wafer processing constituting the mass production line is also used in the prototype line.

【図2】通常ロットの製造方法と、本発明のロット製造
方法との比較を示す。
FIG. 2 shows a comparison between a normal lot manufacturing method and the lot manufacturing method of the present invention.

【図3】 本生産システムが試作に関わる部署に提供す
る情報の概要を示す。
FIG. 3 shows an outline of information provided by the production system to a department involved in trial production.

【図4】 本発明のシステムの構成を示す。FIG. 4 shows the configuration of the system of the present invention.

【図5】試作ロット製造準備として試作に関わる部署が
生産情報管理システムに入力する情報と、その情報をも
とに生産情報管理システムが生成する情報を示す。
FIG. 5 shows information input to a production information management system by a department involved in trial production in preparation for trial lot production and information generated by the production information management system based on the information.

【図6】本生産システムによる各工程での試作ロット製
造方法を示す。
FIG. 6 shows a method of manufacturing a prototype lot in each step by the present production system.

【図7】試作ロット製造中に発生したトラブルに対し
て、生産情報管理システムが実行する日程計画変更の計
算例を示す。
FIG. 7 shows a calculation example of a schedule change performed by the production information management system for a trouble that occurred during the production of a prototype lot.

【図8】試作ロットの各工程での処理実績更新に対し
て、生産情報管理システムが実行する日程計画変更の計
算例を示す。
FIG. 8 shows an example of calculating a schedule change performed by the production information management system with respect to the update of processing results in each process of a prototype lot.

【符号の説明】[Explanation of symbols]

1 … 開発管理部署、 2 … 設計部署、 3 … エン
ジニア部署、4 … ライン管理部署、 5 … マスク製
作部署、 6 … 部材メーカ、7 … テスタ、 8 …
製造ライン、 9 … ラインオペレータ、10 … 製
造装置、 11 … ウエーハID識別ソーテシィンク゛システム、12
… 検査装置、 13〜20 … システム端末、21
… 製造装置オンライン端末、 22 … 検査装置オン
ライン端末、23 … 生産情報管理システム、 24
… 試作ロット管理リスト、25 … 図面・製造仕様書D
B、 26 … 日程管理表DB、27 … 試作ロット進行
予測計算機能。
1 ... development management department, 2 ... design department, 3 ... engineer department, 4 ... line management department, 5 ... mask production department, 6 ... member manufacturer, 7 ... tester, 8 ...
Production line, 9 ... Line operator, 10 ... Production equipment, 11 ... Wafer ID identification sorting system, 12
... Inspection device, 13-20 ... System terminal, 21
... online terminal for manufacturing equipment, 22 ... online terminal for inspection equipment, 23 ... production information management system, 24
… Prototype lot management list, 25… Drawing / manufacturing specification D
B, 26: Schedule management table DB, 27: Prototype lot progress prediction calculation function.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 小林 勝 東京都小平市上水本町五丁目20番1号 株 式会社日立製作所半導体事業部内 (72)発明者 岡部 勉 茨城県ひたちなか市市毛882番地 株式会 社日立製作所計測器事業部内 (72)発明者 坂田 正雄 東京都小平市上水本町五丁目20番1号 株 式会社日立製作所半導体事業部内 (72)発明者 富澤 淳 東京都小平市上水本町五丁目20番1号 株 式会社日立製作所半導体事業部内 (72)発明者 堀口 和男 東京都小平市上水本町五丁目20番1号 株 式会社日立製作所半導体事業部内 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Masaru Kobayashi 5-2-1, Josuihonmachi, Kodaira-shi, Tokyo In the semiconductor division of Hitachi, Ltd. (72) Inventor Tsutomu Okabe 882 Ma, Hitachinaka-shi, Ibaraki (72) Inventor Masao Sakata Inventor Masao Sakata 5-20-1, Kamisumihonmachi, Kodaira-shi, Tokyo Incorporated Semiconductor Company, Hitachi Ltd. 5-20-1, Honmachi Semiconductor Division, Hitachi, Ltd. (72) Inventor Kazuo Horiguchi 5-20-1, Josuihonmachi, Kodaira City, Tokyo Inside Semiconductor Division, Hitachi, Ltd.

Claims (12)

【特許請求の範囲】[Claims] 【請求項1】量産ラインにあわせて試作用のラインを構
築し、量産ラインを構成する枚葉処理を行う装置を試作
ラインにおいても共用する生産システムにおいて、 試作ロットを実質的な物理工完で製造する制御手段を備
えたことを特徴とする生産システム。
1. A production system in which a prototype line is constructed in accordance with a mass production line, and an apparatus for performing single-wafer processing constituting the mass production line is also used in the trial production line. A production system comprising control means for producing.
【請求項2】前記制御手段が、製造にかかわる各部署に
設置された端末と、 各端末からのデータ入力を受け付けて登録し、制御対象
の特定ロットを実質的な物理工完で製造する日程管理表
データを登録データに基づき作成して、各端末にて参照
可能とし、前記いずれかの端末より前記日程管理表デー
タの遅延、又は早期化に関わる状況報告を受け付けた場
合には前記日程管理表データを再作成して各端末に通知
する生産情報管理システムとを備えていることを特徴と
する請求項1記載の生産システム。
2. The control means according to claim 1, wherein said control means receives terminals registered in each of the departments involved in the manufacturing, receives data input from each terminal and registers the data, and manufactures a specific lot to be controlled by substantially physical processing. The management table data is created based on the registered data, and can be referred to at each terminal, and when a status report relating to delay or advancement of the schedule management table data is received from any of the terminals, the schedule management is performed. The production system according to claim 1, further comprising: a production information management system that recreates table data and notifies each terminal of the table data.
【請求項3】前記生産情報管理システムは、前記各端末
に表示する前記制御対象の特定ロットの日程管理表デー
タを、工程フロー、当初計画、実績、及び予測のデータ
より構成することを特徴とする請求項2記載の生産シス
テム。
3. The production information management system according to claim 1, wherein the schedule management table data of the specific lot to be controlled, which is displayed on each terminal, comprises process flow, initial plan, actual, and forecast data. The production system according to claim 2, wherein
【請求項4】前記制御対象の特定ロットの日程管理表デ
ータを構成する当初計画、実績、及び予測の各データ
が、秒単位の時間軸における各工程の位置を表すことを
特徴とする請求項3記載の生産システム。
4. The system according to claim 1, wherein each of the initial plan, actual, and forecast data constituting the schedule management table data of the specific lot to be controlled represents a position of each process on a time axis in units of seconds. 3. The production system according to 3.
【請求項5】前記制御対象の特定ロットの日程管理表デ
ータを構成する当初計画データは、各工程の着工開始予
定日時、又は完成予定日時の少なくとも一方を表し、実
績データは着工開始実績日時、又は完了実績日時を表
し、予測データは実績データに基づき再計算された次工
程以降の着工開始予定日時、又は完成予定日時の少なく
とも一方を表すことを特徴とする請求項3、または請求
項4記載の生産システム。
5. The original plan data constituting the schedule management table data of the specific lot to be controlled represents at least one of a scheduled start date and time or a scheduled completion date and time of each process. 5. The method according to claim 3, wherein the predicted data represents at least one of the scheduled start date and time of the next process and the subsequent processes and the scheduled completion date and time recalculated based on the actual data. 6. Production system.
【請求項6】前記生産情報管理システムは、前記日程管
理表データを作成、又は再作成する際に、前記各部署に
て担当すべき作業の開始時期、又は期限の少なくとも一
方を作成し、各部署の前記端末より参照可能とすること
を特徴とする請求項2記載の生産システム。
6. The production information management system, when creating or re-creating the schedule management table data, creates at least one of a start time or a deadline of a work to be assigned by each of the departments, and 3. The production system according to claim 2, wherein the terminal can be referred to from the terminal of the department.
【請求項7】量産ラインにあわせて試作用のラインを、
該量産ラインを構成する枚葉処理を行う装置を該試作ラ
インにおいても共用する様に構築し、 試作ロットを実質的な物理工完で製造することを特徴と
する生産方法。
7. A trial production line according to a mass production line,
A production method characterized in that an apparatus for performing single-wafer processing constituting the mass production line is constructed so as to be shared also in the prototype line, and a prototype lot is manufactured with substantial physical work.
【請求項8】特定ロットを実質的な物理工完で製造する
日程管理表データを登録データに基づき作成し、 製造にかかわる各部署に設置された各端末にて前記日程
管理表データを参照可能とし、 前記いずれかの端末より前記日程管理表データの遅延、
又は早期化に関わる状況報告を受け付けた場合には前記
日程管理表データを再作成して各端末に通知することを
特徴とする生産方法。
8. Schedule management table data for manufacturing a specific lot with substantial physical processing is created based on the registered data, and the schedule management table data can be referred to at each terminal installed in each department involved in manufacturing. Delay of the schedule management table data from any of the terminals,
Alternatively, the production method is characterized in that, when a status report relating to the advancement is received, the schedule management table data is recreated and notified to each terminal.
【請求項9】前記各端末に表示する前記特定ロットの日
程管理表データが、工程フロー、当初計画、実績、及び
予測のデータより構成することを特徴とする請求項8記
載の生産方法。
9. The production method according to claim 8, wherein the schedule management table data of the specific lot displayed on each terminal comprises data of a process flow, an initial plan, an actual result, and a forecast.
【請求項10】前記特定ロットの日程管理表データを構
成する当初計画、実績、及び予測の各データが、秒単位
の時間軸における各工程の位置を表すことを特徴とする
請求項8記載の生産方法。
10. The system according to claim 8, wherein each of the initial plan, actual, and forecast data constituting the schedule management table data of the specific lot represents a position of each process on a time axis in units of seconds. Production method.
【請求項11】前記特定ロットの日程管理表データを構
成する当初計画データは、各工程の着工開始予定日時、
又は完成予定日時の少なくとも一方を表し、実績データ
は着工開始実績日時、又は完了実績日時を表し、予測デ
ータは実績データに基づき再計算された次工程以降の着
工開始予定日時、又は完成予定日時の少なくとも一方を
表すことを特徴とする請求項9、または請求項10記載
の生産方法。
11. The initial plan data constituting the schedule management table data of the specific lot includes scheduled start date and time of each process,
Or at least one of the scheduled completion date and time, the actual data indicates the actual start date and time of the start of construction, or the actual completed date and time, and the prediction data is the date and time of the scheduled start of the next process and the scheduled completion date and time after the next process recalculated based on the actual data. 11. The production method according to claim 9, wherein at least one of them is represented.
【請求項12】前記日程管理表データを作成、又は再作
成する際に、前記各部署にて担当すべき作業の開始時
期、又は期限の少なくとも一方を作成し、各部署の前記
端末より参照可能とすることを特徴とする請求項8記載
の生産方法。
12. When the schedule management table data is created or re-created, at least one of a start time and a deadline of work to be assigned in each section is created and can be referred to from the terminal in each section. 9. The production method according to claim 8, wherein:
JP24366897A 1996-09-09 1997-09-09 System and method for production Pending JPH10135098A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP24366897A JPH10135098A (en) 1996-09-09 1997-09-09 System and method for production

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP23752296 1996-09-09
JP8-237522 1996-09-09
JP24366897A JPH10135098A (en) 1996-09-09 1997-09-09 System and method for production

Publications (1)

Publication Number Publication Date
JPH10135098A true JPH10135098A (en) 1998-05-22

Family

ID=26533244

Family Applications (1)

Application Number Title Priority Date Filing Date
JP24366897A Pending JPH10135098A (en) 1996-09-09 1997-09-09 System and method for production

Country Status (1)

Country Link
JP (1) JPH10135098A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002132896A (en) * 2000-10-18 2002-05-10 Kusumoto Kasei Kk Measurement test system and program
US6990388B2 (en) 2003-12-26 2006-01-24 Renesas Technology Corp. Mass-production transfer support system and semiconductor manufacturing system
JP2006261546A (en) * 2005-03-18 2006-09-28 Dainippon Screen Mfg Co Ltd Substrate processing equipment
JP2007214550A (en) * 2000-03-07 2007-08-23 Asml Us Inc Recipe cascading of wafer processing system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007214550A (en) * 2000-03-07 2007-08-23 Asml Us Inc Recipe cascading of wafer processing system
JP2002132896A (en) * 2000-10-18 2002-05-10 Kusumoto Kasei Kk Measurement test system and program
US6990388B2 (en) 2003-12-26 2006-01-24 Renesas Technology Corp. Mass-production transfer support system and semiconductor manufacturing system
JP2006261546A (en) * 2005-03-18 2006-09-28 Dainippon Screen Mfg Co Ltd Substrate processing equipment

Similar Documents

Publication Publication Date Title
US5442561A (en) Production management system and its application method
US6434440B1 (en) Production estimate management system
US6647307B1 (en) Method for controlling queue time constraints in a fabrication facility
US6438436B1 (en) Production scheduling management system, and method of managing production scheduling
Johri Practical issues in scheduling and dispatching in semiconductor wafer fabrication
US6968248B1 (en) Agent reactive scheduling in an automated manufacturing environment
US7860595B2 (en) Production schedule creation device and method, production process control device and method, computer program, and computer-readable recording medium
Homem-de-Mello et al. Finding optimal material release times using simulation-based optimization
US7623936B1 (en) Determining scheduling priority using queue time optimization
CN109740813B (en) Analysis and prediction method for on-line product batch running state in wafer manufacturing
US6892106B2 (en) Balancing work release based on both demand and supply variables
US7257459B1 (en) Method and apparatus for scheduling pilot lots
JPH06203042A (en) Production line plan generating method
JPH10135098A (en) System and method for production
JP3283951B2 (en) Production management method and system
JP2011257803A (en) Production management system and production management method
JP2004295188A (en) Method for managing production using delivery time expectation
JPH06176032A (en) System and method for production control
JP2800795B2 (en) Production control method and production control device
JP2001028327A (en) Device manufacturing apparatus
JPH11176717A (en) Production method for semiconductor device, production management method/device for the semiconductor device
JP2005190031A (en) Bottleneck formation avoidance method and system in manufacturing of semiconductor device
KR20030024571A (en) Fabrication methods of semiconductor integrated circuit device and photomask
JP2005208891A (en) Control apparatus and processing system
JPH06176031A (en) System and method for production control

Legal Events

Date Code Title Description
A072 Dismissal of procedure

Free format text: JAPANESE INTERMEDIATE CODE: A072

Effective date: 20031209

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20040308

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070417

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20070814