JPH10114956A - Method of boiling countermeasure by groundwater - Google Patents

Method of boiling countermeasure by groundwater

Info

Publication number
JPH10114956A
JPH10114956A JP26893296A JP26893296A JPH10114956A JP H10114956 A JPH10114956 A JP H10114956A JP 26893296 A JP26893296 A JP 26893296A JP 26893296 A JP26893296 A JP 26893296A JP H10114956 A JPH10114956 A JP H10114956A
Authority
JP
Japan
Prior art keywords
groundwater
boiling
crushed
shaft
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP26893296A
Other languages
Japanese (ja)
Inventor
Tateo Kobayashi
健郎 小林
Fumiaki Sakata
文昭 坂田
Mikihiko Tanaka
幹彦 田中
Akira Gosou
章 五艘
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Fujimi Koken Co Ltd
Original Assignee
Maeda Corp
Fujimi Koken Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp, Fujimi Koken Co Ltd filed Critical Maeda Corp
Priority to JP26893296A priority Critical patent/JPH10114956A/en
Publication of JPH10114956A publication Critical patent/JPH10114956A/en
Withdrawn legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provie a method of construction, by which boiling can be stopped quickly and easily even when boiling by groundwater is generated in the excavating plate of a shaft, etc. SOLUTION: In the method of boiling-countermeasure construction by groundwater, crushed stones 12 are put to an excavating plate 5, in which boiling 6 by groundwater 4 is generated, in the excavation process of a shaft and a cutting, etc., 10 for construction. Accordingly, a crushed-stone heap 13 in specified height is heaped up. The crushed-stone heap 13 inhibits the election energy of groundwater 4 by its own weight. Only groundwater 4 is drained through clearances 15 formed among each mutual crushed stone 12 constituting the crushed-stone heap 13.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は地下水によるボイリ
ング対策工法に関し、更に詳細に言えば、砂質地盤に立
坑や建築物の根切り等の掘削工事を行う際に好適なボイ
リング対策工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for countermeasures against boiling due to groundwater, and more particularly, to a method suitable for countermeasures against boiling when performing excavation work such as pitting or excavation of a building on sandy ground.

【0002】[0002]

【従来の技術】地盤に立坑や建築物の根切り等(以下、
立坑等という)の掘削工事を行うには、図3に示すよう
に地盤Gにシートパイル、連壁、連続柱列坑壁などの山
留1を施工した後に立坑10等の掘削を開始する。この
ような掘削の進行に伴い、腹起2によって山留1を横方
向に止めるとともに、この腹起2の間に切梁3を入れる
ことによって山留1の安定を図りつつ、さらに下方へ掘
削を進めていく。そして、掘削を所定の深度まで施工し
たところで、捨てコンクリート等の処理を行い、構造物
の施工やトンネル発進等の段取り等の次の作業に移行し
て行く。
2. Description of the Related Art Shafts and root excavation of buildings on the ground
In order to perform the excavation work of the shaft, the excavation of the shaft 10, etc. is started after the pile 1 such as the sheet pile, the continuous wall, and the continuous column shaft wall is constructed on the ground G as shown in FIG. With the progress of such excavation, the ridge 1 is stopped in the lateral direction by the bulge 2 and the ridge 1 is inserted between the bulges 2 to stabilize the ridge 1 while excavating further downward. I will proceed. Then, when the excavation has been performed to a predetermined depth, processing of discarded concrete or the like is performed, and the process proceeds to the next operation such as construction of a structure or setup such as starting a tunnel.

【0003】ところで、立坑等の掘削工事が砂質地盤に
対して行われる場合には、地下水4が山留1の根入れ下
方1aを伝わって立坑10の内部に流れ込み、さらに上
方に流れて土砂粒子と共に掘削盤5に噴出して、いわゆ
るボイリング6が発生した。
[0003] When excavation work such as a shaft is performed on sandy ground, groundwater 4 flows along the lower part 1a of the ridge 1 and flows into the shaft 10, and then flows further upward to sediment. The particles were ejected to the excavator 5 together with the particles, and so-called boiling 6 occurred.

【0004】図4に示すように地下水流が土砂粒子9に
作用し、重心wと浮心uとの偏距eが土砂粒子9を回転
させる結果、土砂粒子9が踊りだして激しく撹乱され、
これが更に発達してパイピング現象を生じて水道7を形
成し、遂には土砂粒子9を噴出することによりボイリン
グ6が生じた。
As shown in FIG. 4, the groundwater flow acts on the sediment particles 9, and the distance e between the center of gravity w and the floating center u rotates the sediment particles 9. As a result, the sediment particles 9 dance and are violently disturbed.
This further developed and caused a piping phenomenon to form the water supply 7, and finally, the spouting of the earth and sand particles 9 resulted in the boiling 6.

【0005】このように噴出した土砂粒子9は山形状に
盛り上がり、その結果、水道7の周辺に緩みを生じさせ
ると共に、水道7内の流水力によって、たちまち地盤G
が抜けて、地表の陥没を惹起するに至った。
[0005] The earth and sand particles 9 erupted in this manner rise in a mountain shape, and as a result, the periphery of the water supply 7 is loosened.
Came off, causing the surface to sink.

【0006】そこで、地質条件、周辺の条件、施工法等
により地下水対策工として、立坑10等の周囲に予めデ
ィープウエルを掘削しておき、地下水をディープウエル
から揚水するようにしたり、あるいは薬液等を地盤に注
入して地盤の透水性を減少させることが行われた。
Therefore, as a countermeasure against groundwater, depending on the geological conditions, peripheral conditions, construction method, etc., a deep well is excavated in advance around the shaft 10 or the like, and groundwater is pumped from the deep well. Was injected into the ground to reduce the permeability of the ground.

【0007】しかし、このようなボイリング6は掘削最
終盤に生じるとは限らず、不測の事態として掘削途中に
生じる場合もある。この場合には、ボイリングの対策工
として、1)立坑等を水没させて地下水位を低下させて
から揚水し、その後掘削を行ったり、2)立坑等を水没
させてから水中掘削を行い、水中コンクリートを打設し
てから揚水したり、3)立坑を水没させてからウエイル
ポイントを打設し、ウエルポイントによって土砂粒子の
流入を防止しながら揚水し、次いでコンクリートを打設
する、などのボイリング対策工が行われた。
However, such boiling 6 does not always occur at the final stage of excavation, and may occur during excavation as an unexpected situation. In this case, as a countermeasure for boiling, 1) submerge the shaft, etc. to lower the groundwater level and then pump up water, and then excavate, or 2) submerge the shaft, etc., and perform underwater excavation. 3) Submerge the shaft and place a water point after placing the concrete. 3) Pour the water while preventing the inflow of sediment particles by the well point, and then place concrete. Boiling countermeasures were taken.

【0008】[0008]

【発明が解決しようとする課題】しかし、前述した従来
のこの種の地下水対策工では、以下のような問題があっ
た。すなわち、ディープウエルを立坑等の周囲に予め掘
削するには、周囲に十分なスペースを要する上、ディー
プウエル掘削のコストが大幅にかかるために経済的では
なかった。また、掘削の途中に発生したボイリングの対
策工として、立坑等を水没させて水中コンクリートを打
設したり、ウエルポイントを打設する場合には時間がか
かり、対応の大幅な遅れによって地表陥没による被害が
大きくなるおそれがあった。
However, the above-described conventional groundwater countermeasure works have the following problems. That is, in order to excavate a deep well around a shaft or the like in advance, a sufficient space is required around the excavation, and the cost of the deep well excavation is large, so that it is not economical. In addition, as a countermeasure against boiling that occurred during excavation, it takes time to immerse a shaft or the like in submerged concrete and place underwater concrete, or to place well points. There was a risk that the damage would increase.

【0009】しかも、上記対策工では、その後に揚水し
たり、水中コンクリートや、ウエルポイントなどの大規
模な仮設物を用意したり、あるいはこれらの後始末を要
するため、作業が煩雑であり、仮設物がコストを高騰さ
せるため、経済的にも問題があった。
In addition, the above countermeasures require the subsequent pumping, preparation of large-scale temporary objects such as underwater concrete and well points, or the necessity of cleaning up these items. There was also an economic problem, because the cost of goods increased.

【0010】さらに、ボイリングの発生個所は、山留の
近傍に限らず、しかも上記ボイリング対策工を施した後
に、ボイリングの発生個所が移動する傾向があり、迅速
なボイリング対策はきわめて厄介であった。
[0010] Furthermore, the location of the occurrence of boiling is not limited to the vicinity of the ridge, and the location of occurrence of the boiling tends to move after the above-mentioned countermeasure for the above-mentioned boil is taken. .

【0011】本発明の目的は、このような従来の問題点
を解決するためになされたもので、立坑等の掘削盤に地
下水によるボイリングが発生しても、迅速、かつ容易に
ボイリングを止めることができるようにした地下水によ
るボイリング対策工法を提供することにある。
SUMMARY OF THE INVENTION An object of the present invention is to solve such a conventional problem. Even if boring due to groundwater occurs in a drilling machine such as a vertical shaft, it is possible to quickly and easily stop the boiling. It is an object of the present invention to provide a method for countermeasures against boiling caused by groundwater.

【0012】[0012]

【課題を解決するための手段】本発明は地下水によるボ
イリング対策工法であり、前述した技術的課題を解決す
るために以下のように構成されている。すなわち、本発
明の地下水によるボイリング対策工法は、立坑等の掘削
工程において、地下水によるボイリングが発生した掘削
盤に砕石を投入して所定高さの砕石山を盛り上げ、この
砕石山の自重で地下水の噴出エネルギーを抑制し、さら
に、砕石山を構成する各砕石相互の間に形成される隙間
を通して地下水のみを排水可能としたことを特徴とす
る。以下、この発明の重要な構成要素について更に詳細
に説明する。
Means for Solving the Problems The present invention relates to a method for countermeasures against boiling due to groundwater, and is constituted as follows in order to solve the above-mentioned technical problems. In other words, the method of the present invention for countermeasures against boiling by groundwater is that, in an excavation process such as a shaft, a crushed stone is poured into a drilling machine in which boiling by groundwater has occurred to excavate a crushed rock mountain having a predetermined height, and the groundwater is weighed by its own weight. It is characterized in that the blast energy is suppressed and that only groundwater can be drained through gaps formed between the crushed stones constituting the crushed stone mountain. Hereinafter, important components of the present invention will be described in more detail.

【0013】前記砕石には砕石相互の間に形成される隙
間を通して地下水のみを排水することが可能であれば適
宜のものを用いることができるが、日本工業規格(JI
S)A5001−1995で規定される単粒度砕石、1
号(60〜100m/m)、及び/または2号(40〜8
m/m)を用いるのが好ましい。
As the crushed stone, any suitable crushed stone can be used as long as only groundwater can be drained through a gap formed between the crushed stones.
S) Single-grain crushed stone specified in A5001-1995, 1
No. (60-100 m / m ) and / or No. 2 (40-8
0 m / m 2 ).

【0014】また、砕石山の高さは、砕石の自重により
ボイリングを抑制することが可能であればよく、40〜
60cmが好ましい。しかし、上記範囲で地下水の噴出エ
ネルギーを抑制することが不可能であれば、前記の高さ
の上限を超えた砕石山を盛り上げる。あるいは、地下水
の噴出エネルギーが小さければ上記の範囲以下であって
もよい。
[0014] The height of the crushed stone is only required to be able to suppress boiling by the weight of the crushed stone.
60 cm is preferred. However, if it is impossible to suppress the discharge energy of the groundwater in the above range, the crushed rock mass exceeding the upper limit of the height is raised. Alternatively, the energy may be equal to or less than the above range as long as the blast energy of groundwater is small.

【0015】さらに、砕石の投入手段としては、予め砕
石を積載したダンプカーを立坑の周囲に少なくとも1台
配置すればよいが、複数台のダンプカーやクラムを設け
ることが好ましい。
Further, as a means for charging crushed stone, at least one dump truck loaded with crushed stone may be arranged around the shaft in advance, but it is preferable to provide a plurality of dump trucks and crumbs.

【0016】本発明の地下水によるボイリング対策工法
によると、ボイリングが掘削盤に発生したら、その個所
へ予め用意した砕石を投入する。すると、砕石の自重に
より土砂粒子の踊りだしを抑制し、砕石の粒子間の隙間
がストレーナの作用を行って地下水のみを排水する。
According to the method of countermeasures against groundwater-based boiling according to the present invention, when boiling occurs in a drilling machine, crushed stone prepared in advance is put into the location. Then, the movement of the earth and sand particles is suppressed by the weight of the crushed stone, and the gap between the particles of the crushed stone acts as a strainer to drain only groundwater.

【0017】[0017]

【発明の実施の形態】以下、本発明の地下水によるボイ
リング対策工法を図に示される実施形態について更に詳
細に説明する。図1には本発明の一実施形態に係る地下
水によるボイリング対策工法の施工状態の説明図であ
り、図2は砕石の盛り立て状態を示す説明図である。
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a perspective view showing a construction method of a countermeasure against boil- ing with groundwater according to the present invention. FIG. 1 is an explanatory diagram of a construction state of a method for countermeasures against boiling due to groundwater according to one embodiment of the present invention, and FIG. 2 is an explanatory diagram showing a crushed stone pile state.

【0018】まず、砂質の地盤Gにシートパイル、連
壁、連続柱列坑壁などの山留1を施工してから、立坑1
0の掘削を開始する。掘削の進行に伴い、腹起2によっ
て山留1を横方向に止めるとともに、この腹起2の間に
切梁3を入れて山留1の安定を図りながら図1に示すよ
うに立坑10の掘削を進めていく。
First, a ridge 1 such as a sheet pile, a continuous wall, a continuous column shaft wall, etc. is constructed on a sandy ground G, and then a shaft 1 is formed.
0 excavation is started. As the excavation progresses, the ridge 1 is stopped in the lateral direction by the gusset 2, and the cutting beam 3 is inserted between the gussets 2 to stabilize the ridge 1 as shown in FIG. Continue drilling.

【0019】さらに、JIS A5001−1995に
定める1号、及び/または2号の単粒度砕石12を予め
積載したダンプカー8を立坑10の周辺に配置してあ
る。なお、図1においてダンプカー8は1台だけ図示し
ているが、1台に限らず複数台設置してもよい。その他
に図示していないがクラムも設置してある。
Further, a dump truck 8 previously loaded with single-grained crushed stones 12 of No. 1 and / or No. 2 specified in JIS A5001-1995 is arranged around the shaft 10. Although only one dump truck 8 is shown in FIG. 1, the number is not limited to one, and a plurality of dump trucks may be installed. Although not shown, a crumb is also provided.

【0020】立坑10の掘削中において、地下水4が山
留1の根入れ下方1aを伝わって立坑10内に流れ、さ
らに上方に流れて、図3に示すように地盤の土砂粒子9
と共に掘削盤5から噴出してボイリング6が発生した
ら、直ちにダンプカー8を駆動してボイリング発生個所
に砕石12を投入し、砕石山13を所定高さhに盛り上
げてボイリング6の抑制にかかる。図1ではボイリング
6は山留1の近傍に発生した場合を示すが、ボイリング
6は一個所で抑制されると、他の個所に移行することが
しばしばある。その場合には、ボイリング6が移行した
個所に向けて、図示しないクラム等でさらに砕石12を
投入することによって対応する。
During the excavation of the shaft 10, the groundwater 4 flows through the lower part 1a of the embankment 1 and flows into the shaft 10, further flows upward, and as shown in FIG.
At the same time, when the boring 6 is generated by erupting from the excavator 5, the dump truck 8 is immediately driven to put the crushed stone 12 into the location where the boiling has occurred, and the crushed stone pile 13 is raised to a predetermined height h to control the boiling 6. FIG. 1 shows a case where the boiling 6 occurs near the ridge 1, but when the boiling 6 is suppressed in one place, it often shifts to another place. In that case, the crushed stone 12 is further charged with a crumb or the like (not shown) toward the location where the boiling 6 has moved.

【0021】砕石山13の高さhは、本実施形態におい
て通常40〜60cmである。これは、土砂粒子9の噴
出により形成される山形状の隆起が高々数十cmである
こと、水中コンクリートによるボイリングの抑制にはコ
ンクリート厚が10〜20cm程度であること、及び地
下水頭Hの出水口断面積倍した噴出力が砕石山底部に分
散され、砕石山自重よりも小さいこと、などから上記の
砕石山13の高さを設定した。もちろん、砕石山13の
高さhは上記範囲に限定されることはない。
The height h of the crushed rock pile 13 is usually 40 to 60 cm in the present embodiment. This is because the mountain-shaped ridge formed by the ejection of the sediment particles 9 is at most several tens of centimeters, the concrete thickness is about 10 to 20 cm in order to suppress the boiling caused by the underwater concrete, and The height of the crushed rock mountain 13 was set in view of the fact that the jet power multiplied by the water mouth cross-sectional area was dispersed at the bottom of the crushed rock mountain and smaller than the weight of the crushed rock mountain. Of course, the height h of the crushed rock mountain 13 is not limited to the above range.

【0022】砕石山13はその自重により土砂粒子9を
地盤Gから噴出させる地下水4の噴出エネルギーを抑制
すると共に、砕石山13を構成する砕石12の相互の間
に形成される隙間15がストレーナの役割を果たし、地
下水4のみが排出される。
The crushed stone pile 13 suppresses the energy of the groundwater 4 that causes the earth and sand particles 9 to be ejected from the ground G by its own weight, and a gap 15 formed between the crushed stones 12 constituting the crushed stone pile 13 forms a strainer of the strainer. It plays a role and only groundwater 4 is drained.

【0023】上記のように、砕石12をボイリング6の
発生個所に投入することによって、地下水の噴出エネル
ギーを抑制することができれば、立坑10等がそれ自身
大きなウエルとなっているので、土砂粒子9を引き出さ
ずに地下水位を低下させることが可能となり、ボイリン
グ6が終息する。そして、この時点からさらに掘削を開
始する。
As described above, if the blasted stone 12 is put into the location where the boiling 6 is generated, the energy of the spouting of the groundwater can be suppressed, the shaft 10 and the like themselves become large wells. And the groundwater level can be lowered without drawing water, and the boiling 6 ends. Then, excavation is further started from this point.

【0024】[0024]

【発明の効果】以上説明したように、本発明の地下水に
よるボイリング対策工法によれば、地下水によるボイリ
ングが発生した掘削盤に砕石を投入し、所定高さに盛り
上げるだけで砕石の自重により地下水の噴出エネルギー
を抑制し、土砂粒子の撹拌を防止するともに、ストレー
ナとして地下水のみを排水することができるで、予め砕
石を積載したダンプカーなどを立坑等の周囲に待機させ
ておくだけで、直ちに経済的にボイリングに対応するこ
とができ、地下水位低下による地盤の沈下を最小限に止
めることができる。しかも、ボイリング発生個所が移動
しても直ちにフレキシブルに対応することができる。
As described above, according to the method of the present invention for countermeasures against boiling by using groundwater, the crushed stone is put into the excavator in which the boring due to the groundwater has occurred, and is simply raised to a predetermined height. In addition to suppressing jetting energy and preventing sedimentation of sediment particles, it can drain only groundwater as a strainer.Even if a dump truck loaded with crushed stones is kept waiting around a shaft, etc., it is economical immediately. Therefore, it is possible to cope with boiling and to minimize the subsidence of the ground due to lowering of the groundwater level. In addition, even if the location where the boiling occurs is moved, it is possible to respond immediately and flexibly.

【0025】本発明では、掘削工に用いられている砕石
を用いて、従来工法のように水中コンクリートやウエル
ポイント等を打設するなどの大規模な仮設を要しないの
で、従来工法のように後片付けの特別処理が全く不要
で、掘削と一緒に土捨てとして処理でき、また立坑等の
掘削時に不測のボイリングが発生してもフレキシブルに
対応でき、経済的で安全である。
In the present invention, large-scale temporary construction such as underwater concrete or well points is not required by using crushed stones used for excavation as in the conventional construction method. It does not require any special treatment for cleaning up, it can be treated as soil dumping together with excavation, and it can flexibly cope with unexpected boiling during excavation of shafts, etc., and is economical and safe.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施形態に係る地下水によるボイリン
グ対策工法の施工状態の説明図である。
FIG. 1 is an explanatory diagram of a construction state of a method for countermeasures against boiling due to groundwater according to an embodiment of the present invention.

【図2】本発明の実施形態における砕石の盛り立て状態
の詳細を示す部分説明図である。
FIG. 2 is a partial explanatory view showing details of a crushed stone erected state in the embodiment of the present invention.

【図3】立坑等の掘削時におけるボイリングの発生状態
の説明図である。
FIG. 3 is an explanatory diagram of a state of occurrence of boiling when excavating a shaft or the like.

【図4】土砂粒子が地下水流によって撹乱される原因の
説明図である。
FIG. 4 is an explanatory diagram of a cause of sediment particles being disturbed by a groundwater flow.

【符号の説明】[Explanation of symbols]

4 地下水 5 掘削盤 6 ボイリング 10 立坑 12 砕石 13 砕石山 15 隙間 4 Groundwater 5 Excavator 6 Boiling 10 Shaft 12 Crushed Stone 13 Crushed Stone Mountain 15 Clearance

───────────────────────────────────────────────────── フロントページの続き (72)発明者 田中 幹彦 東京都千代田区富士見二丁目10番26号前田 建設工業株式会社内 (72)発明者 五艘 章 東京都千代田区飯田橋3丁目11番18号(光 邦ビル)フジミ工研株式会社内 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Mikihiko Tanaka 2-10-26 Fujimi, Chiyoda-ku, Tokyo Maeda Construction Industry Co., Ltd. (72) Inventor Akira Gobo 3-1-1-18 Iidabashi, Chiyoda-ku, Tokyo (Kokuni Building) Inside Fujimi Koken Co., Ltd.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 立坑や建築用根切り等の掘削工程におい
て、地下水によるボイリングが発生した掘削盤に砕石を
投入して所定高さの砕石山を盛り上げ、この砕石山の自
重で地下水の噴出エネルギーを抑制し、さらに、砕石山
を構成する各砕石相互の間に形成される隙間を通して地
下水のみを排水可能としたことを特徴とする地下水によ
るボイリング対策工法。
In an excavation process such as a shaft or a root excavation for a building, crushed stone is injected into an excavator in which boiling due to groundwater has occurred to excavate a crushed rock mountain having a predetermined height. A method for preventing groundwater boiling, characterized in that only groundwater can be drained through gaps formed between the crushed stones constituting the crushed stone mountain.
JP26893296A 1996-10-09 1996-10-09 Method of boiling countermeasure by groundwater Withdrawn JPH10114956A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP26893296A JPH10114956A (en) 1996-10-09 1996-10-09 Method of boiling countermeasure by groundwater

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP26893296A JPH10114956A (en) 1996-10-09 1996-10-09 Method of boiling countermeasure by groundwater

Publications (1)

Publication Number Publication Date
JPH10114956A true JPH10114956A (en) 1998-05-06

Family

ID=17465293

Family Applications (1)

Application Number Title Priority Date Filing Date
JP26893296A Withdrawn JPH10114956A (en) 1996-10-09 1996-10-09 Method of boiling countermeasure by groundwater

Country Status (1)

Country Link
JP (1) JPH10114956A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103243720A (en) * 2013-05-20 2013-08-14 中冶天工集团有限公司 Soft foundation ultra-deep foundation pit supporting method
CN103821149A (en) * 2014-02-28 2014-05-28 中天建设集团有限公司 Large-scale deep foundation pit slope remaining soil digging and pit-in-pit concrete post casting construction method
CN105002913A (en) * 2015-08-06 2015-10-28 中铁隆工程集团有限公司 Strongly-permeable stratum deep foundation pit bottom sealing water stopping structure and construction method thereof
CN110306557A (en) * 2019-07-10 2019-10-08 武汉立诚岩土工程有限公司 Earthwork digging method based on basement deep-foundation pit engineering
CN113585436A (en) * 2021-08-13 2021-11-02 中国一冶集团有限公司 Tubular pile system permeates water

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103243720A (en) * 2013-05-20 2013-08-14 中冶天工集团有限公司 Soft foundation ultra-deep foundation pit supporting method
CN103821149A (en) * 2014-02-28 2014-05-28 中天建设集团有限公司 Large-scale deep foundation pit slope remaining soil digging and pit-in-pit concrete post casting construction method
CN105002913A (en) * 2015-08-06 2015-10-28 中铁隆工程集团有限公司 Strongly-permeable stratum deep foundation pit bottom sealing water stopping structure and construction method thereof
CN110306557A (en) * 2019-07-10 2019-10-08 武汉立诚岩土工程有限公司 Earthwork digging method based on basement deep-foundation pit engineering
CN110306557B (en) * 2019-07-10 2021-04-13 武汉立诚岩土工程有限公司 Earth excavation method based on basement deep foundation pit engineering
CN113585436A (en) * 2021-08-13 2021-11-02 中国一冶集团有限公司 Tubular pile system permeates water

Similar Documents

Publication Publication Date Title
CN113789797A (en) Steel sheet pile cofferdam construction method for deeply covering sand and gravel layer
CN109208594B (en) Treatment method for steel casing sinking meeting boulder, steel casing structure and drilled pile
JPH10114956A (en) Method of boiling countermeasure by groundwater
JP5975266B2 (en) Attachment for crushed stone pile formation
JP2916595B2 (en) Wastewater discharge method in the pneumatic caisson method
JP4982631B2 (en) Liquefaction countermeasure method under breakwater by underground wall construction
CN113026848B (en) Construction method of continuous high-spraying impervious wall by planing and milling method
US20160326871A1 (en) Surface access borehole resource extraction method
CN109826201A (en) A kind of weak soil foundation pit step method for protecting support
RU2700152C1 (en) Method for artificial development of technogenic reserves
CN114215066A (en) Open cut foundation pit side wall collapse prevention excavation construction method
CN113338924A (en) Control method for surface subsidence range by natural caving method
JP3224008B2 (en) Underwater ground improvement method
JP4451007B2 (en) 浚 渫 Method
JPH10114957A (en) Method of sand boiling-preventive construction in excavation work of shaft, etc.
JPH09302659A (en) Construction method of drawing high pressure water injection type deformed place pile and device therefor
CN214330130U (en) Punching bored concrete pile circulation finished product mud pit
RU2125160C1 (en) Method for bore-hole hydraulic mining of solid minerals
JP2005030135A (en) Dredging device and dredging method by use of grab bucket
RU2186215C1 (en) Mining method of water-bearing sand-gravel deposits
RU2180399C1 (en) Process of underwater excavation of gravel and sand mixture
JPH1037202A (en) Cutting excavation method and device removing underground spring water
JP3877817B2 (en) Excavation sediment transport method in pneumatic caisson
JP2899915B2 (en) Settlement method of latent box body and latent box body
RU1768754C (en) Method for opencast mining of water-bearing deposits

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20040106