JPH10114941A - Traveling crane for driving pile - Google Patents

Traveling crane for driving pile

Info

Publication number
JPH10114941A
JPH10114941A JP27088496A JP27088496A JPH10114941A JP H10114941 A JPH10114941 A JP H10114941A JP 27088496 A JP27088496 A JP 27088496A JP 27088496 A JP27088496 A JP 27088496A JP H10114941 A JPH10114941 A JP H10114941A
Authority
JP
Japan
Prior art keywords
pile
auxiliary
driving device
sheave
point
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP27088496A
Other languages
Japanese (ja)
Other versions
JP3712801B2 (en
Inventor
惇 ▲吉▼野
Atsushi Yoshino
Masatoshi Hara
正敏 原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YOSHINO KENSETSU KK
Kobe Steel Ltd
Original Assignee
YOSHINO KENSETSU KK
Kobe Steel Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YOSHINO KENSETSU KK, Kobe Steel Ltd filed Critical YOSHINO KENSETSU KK
Priority to JP27088496A priority Critical patent/JP3712801B2/en
Publication of JPH10114941A publication Critical patent/JPH10114941A/en
Application granted granted Critical
Publication of JP3712801B2 publication Critical patent/JP3712801B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Jib Cranes (AREA)

Abstract

PROBLEM TO BE SOLVED: To dispense with the aligning work of a pile-driving device and a pile head, by pivoting point sheaves hanging a main hook suspending the pile- driving device through a main rope and auxiliary sheaves hanging auxiliary hooks suspending the pile through whip ropes, on the same axial line. SOLUTION: Four point sheaves 3 hanging a main hook 5 suspending a pile-driving device 10 through a main rope 4 and auxiliary sheaves 7, 7 hanging auxiliary hooks 9, 9 suspending a steel pipe pile P through whip ropes 8, 8, are fitted to one point sheave pin 2. Accordingly, the center of the pile-driving device 10 and the center of the pile head of the steel pipe pile P have already coincided with each other at the time when these have been hung. In this way, it is not necessary that the lattice boom is lowered a little and also operators wait the attenuation of the forward and backward swing, on aligning the pile- driving device and the pile head, and hence, the pile-driving efficiency can be increased.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、例えば基礎工事等
のために地盤に杭を打ち込む杭打設用移動式クレーンの
改善に関し、より詳しくは、杭打ち装置と地盤に打設す
る杭の杭頭との心を容易に合わせることを可能ならしめ
るようにした杭打設用移動式クレーンの技術分野に属す
るものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an improvement of a mobile crane for driving a pile for driving a pile into the ground for, for example, foundation work, and more particularly to a pile driving device and a pile for driving a pile into the ground. The present invention belongs to the technical field of a mobile crane for driving piles, which makes it possible to easily align the mind with the head.

【0002】[0002]

【従来の技術】周知のとおり、移動式クレーンは、主と
してビル等の各種建築物の建設現場等において各種資材
のクレーン作業に使用されている。このような用途以外
には、例えば油圧式、機械式のバイブロハンマー等の杭
打ち装置を吊持することにより各種建築物を構築するた
めの基礎工事、河川の岸壁や港湾工事等における連壁構
築のための杭打ち機としても多用されている。以下、従
来例に係る移動式クレーンを利用した杭打ち機、つまり
基礎工事等のための杭打設用移動式クレーンの構成を、
杭打ち装置と杭とを吊持した状態を示すそのラチスブー
ム頂部付近の構成説明図の図2と、杭打ち装置と杭とを
吊持した状態を示すそのラチスブーム頂部付近の模式的
構成説明図の図3とを参照しながら説明する。
2. Description of the Related Art As is well known, mobile cranes are mainly used for crane work of various materials at construction sites of various buildings such as buildings. Other than such applications, for example, foundation work for constructing various buildings by suspending a pile driving device such as a hydraulic or mechanical vibro hammer, connecting wall construction in river quay and harbor construction, etc. It is also heavily used as a pile driver. Hereinafter, a pile driving machine using a mobile crane according to a conventional example, that is, a configuration of a mobile crane for pile driving for foundation work and the like,
FIG. 2 of a configuration explanatory diagram near the top of the lattice boom showing a state where the pile driving device and the pile are suspended, and FIG. 2 is a schematic configuration explanatory diagram near the top of the lattice boom showing the state where the pile driving device and the pile are suspended. This will be described with reference to FIG.

【0003】先ず、従来例に係る杭打設用移動式クレー
ン本体の構成(図示省略)を説明すると、これは、前後
進かつ操行自在な履帯走行式の走行台車の上に、運転
席、エンジン、各種油圧機器類、ウインチ類、ガントリ
ー、カウンターウエイト等を備え、旋回モータにより左
右方向に可逆自在に旋回される旋回体が旋回ベアリング
を介して搭載されると共に、この旋回体に水平なブーム
フットピンを介して、ウインチにより巻取り・巻戻され
るブーム起伏ロープにより起伏される鋼管が骨組形成さ
れてなる構成のラチスブームが支持されてなる構成にな
っている。
First, the construction (not shown) of a conventional crane body for driving a pile according to a conventional example will be described. , Various hydraulic equipment, winches, gantry, counterweight, etc., a revolving structure that is reversibly revolved in the left and right direction by a revolving motor is mounted via a revolving bearing, and a horizontal boom foot A lattice boom having a structure in which a steel pipe raised and lowered by a boom raising and lowering rope wound up and down by a winch is formed via a pin is supported.

【0004】次に、図2および図3を参照しながら、杭
打設用移動式クレーンのラチスブーム頂部付近の構成を
説明する。即ち、図2に示す符号1は、図示しない前記
旋回体により起伏自在に支持されてなるラチスブーム
で、このラチスブーム1の先端にはポイントシーブピン
2を水平支持するポイントシーブ支持ブラケット1aが
設けられている。このポイントシーブピン2により、図
3に示すように、複数のポイントシーブ3が軸支されて
おり、そしてこれらポイントシーブ3により杭を打設す
る杭打ち装置10を吊持する主フック5を巻上げ・巻下
げる主巻ロープ4が掛装されている。
Next, a configuration near the top of a lattice boom of a mobile crane for driving piles will be described with reference to FIGS. 2 and 3. FIG. That is, reference numeral 1 shown in FIG. 2 denotes a lattice boom supported by the revolving body (not shown) so as to be able to move up and down. A point sheave support bracket 1a for horizontally supporting a point sheave pin 2 is provided at the tip of the lattice boom 1. I have. As shown in FIG. 3, a plurality of point sheaves 3 are pivotally supported by the point sheave pins 2, and a main hook 5 for suspending a pile driving device 10 for driving a pile with these point sheaves 3 is hoisted. -The main winding rope 4 to be wound is mounted.

【0005】また、ラチスブーム1の先端には、図2に
示すように、補助ブーム6が突設されており、この補助
ブーム6の先端に設けられた補助シーブピン6aによっ
て補助シーブ7が軸支されている。そして、この補助シ
ーブ7には、地盤に打設すべき杭Pを吊持する補助フッ
ク9を巻上げ・巻下げる補巻ロープ8が掛装されてなる
構成になっている。
As shown in FIG. 2, an auxiliary boom 6 protrudes from the tip of the lattice boom 1, and the auxiliary sheave 7 is pivotally supported by an auxiliary sheave pin 6a provided at the tip of the auxiliary boom 6. ing. The auxiliary sheave 7 is provided with an auxiliary hoisting rope 8 for hoisting and lowering an auxiliary hook 9 for suspending a pile P to be driven into the ground.

【0006】従って、このような構成になる杭打設用移
動式クレーンにより、地盤に杭Pを打設するときには、
図示しない主巻ウインチで主巻ロープ4を巻下げ・巻上
げることによって主フック5で杭打ち装置10を吊持
し、図示しない補巻ウインチで補巻ロープ8を巻下げ・
巻上げることによって補助フック9で地盤に打設すべき
杭Pを吊持する。そして、補巻ウインチで補巻ロープ8
を巻下げて杭Pを下降させると共に、地盤に垂直に立設
する。次いで、地盤に立設された杭Pの杭頭の中心に杭
打ち装置10の中心を合致させるためにラティスブーム
1を少し伏せて心合わせを行う。
Therefore, when the pile P is driven into the ground by the mobile crane for driving a pile having such a configuration,
By lowering and winding the main winding rope 4 with a main winding winch (not shown), the pile driving device 10 is suspended with the main hook 5 and the auxiliary winding rope 8 is lowered with an auxiliary winding winch (not shown).
The pile P to be driven into the ground is suspended by the auxiliary hook 9 by winding up. Then, using the auxiliary winch, the auxiliary rope 8
And lower the pile P to stand vertically on the ground. Next, in order to make the center of the pile driving device 10 coincide with the center of the pile head of the pile P erected on the ground, the lattice boom 1 is slightly lowered and centered.

【0007】このようにして杭打ち装置10の中心と杭
Pの杭頭の中心との心合わせが終了すると、主巻ウイン
チにより主巻ロープ4を巻下げて杭打ち装置10を下降
させると共に、例えば杭打ち装置10の油圧チャックに
より杭Pの杭頭部を掴んで杭Pの打設が開始されること
になる。なお、杭Pを地盤に打設する前に、上記のよう
に、杭打ち装置10と杭Pの杭頭との心合わせを行うの
は、地盤に杭Pを垂直に打設するためであって、もし杭
打ち装置10と杭Pの杭頭との心が合っていないと杭P
が傾いた状態で打設されてしまうからである。
When the centering of the pile driving device 10 and the center of the pile head of the pile P is completed in this way, the main winding rope 4 is lowered by the main winding winch, and the pile driving device 10 is lowered. For example, the driving of the pile P is started by grasping the pile head of the pile P by the hydraulic chuck of the pile driving device 10. Before the pile P is driven into the ground, the centering of the pile driving device 10 and the pile head of the pile P is performed as described above in order to drive the pile P vertically into the ground. If the pile driver 10 and the pile head of the pile P are not aligned, the pile P
This is because they are driven in an inclined state.

【0008】[0008]

【発明が解決しようとする課題】上記従来例に係る杭打
設用移動式クレーンによると、図2や図3から良く理解
されるように、杭の吊持位置が杭打ち装置の吊持位置よ
りも前方位置であって、それらの吊持位置が前後にづれ
ている。従って、地盤に垂直に立設された杭を打設する
前に、上記のとおり、必ず杭打ち装置と杭の杭頭との心
合わせ作業を行わなければならない。
According to the mobile crane for setting a pile according to the conventional example, as is well understood from FIGS. 2 and 3, the hanging position of the pile is determined by the hanging position of the pile driving device. And their hanging positions are shifted forward and backward. Therefore, as described above, the centering work between the pile driving device and the pile head must be performed before driving the pile vertically erected on the ground.

【0009】杭打ち装置と杭の杭頭との心合わせのため
に、ラチスブームを伏せて杭打ち装置を前方方向に移動
(前方への移動距離は杭打設用移動式クレーンの大きさ
によって相違するが、例えば600mm程度である。)
させると、この杭打ち装置はラチスブームを起伏自在に
支持するフットピンを中心とする半径の円弧を描いて移
動するが、ラチスブームの停止時における移動速度の水
平成分に起因する慣性力のために杭打ち装置が前後に揺
れるので、杭の杭頭に対する杭打ち装置の位置を確認す
るために、この杭打ち装置の揺幅が一定の範囲内の揺幅
に減衰するまで待つ必要がある。
In order to align the pile driving device with the pile head, the lattice boom is turned down and the pile driving device is moved forward (the distance to move forward depends on the size of the pile driving movable crane). However, it is, for example, about 600 mm.)
When this is done, this pile driving device moves in an arc with a radius centered on the foot pin that supports the lattice boom up and down, but due to the inertial force caused by the horizontal component of the moving speed when the lattice boom stops, the pile driving device As the device swings back and forth, it is necessary to wait until the rocking width of the pile driving device has attenuated to a certain range in order to confirm the position of the pile driving device with respect to the pile head of the pile.

【0010】ラチスブームを伏せるという作業の所要時
間は高々10秒程度であって、それ程の長時間を必要と
しない。しかしながら、通常、ラチスブームを伏せて杭
打ち装置の揺れの減衰を待つということを数回繰返さな
ければならない。つまり、杭打ち装置の揺れの振幅の減
衰を待つという繰返しに要する時間が例えば5分以上も
かかるので、杭の打設作業能率を向上させることができ
ないという解決すべき課題があった。
The time required for the operation of lowering the lattice boom is at most about 10 seconds, and does not require such a long time. However, it usually must be repeated several times to lay down the lattice boom and wait for the sway of the pile driver to decay. In other words, the time required for the repetition of waiting for the amplitude of the swing of the pile driving device to attenuate is, for example, 5 minutes or more, and there is a problem to be solved in that the efficiency of the pile driving operation cannot be improved.

【0011】従って、本発明の目的とするところは、杭
打ち装置と杭の杭頭との心合わせ作業を不要ならしめる
杭打設用移動式クレーンを提供することである。
Accordingly, an object of the present invention is to provide a mobile crane for driving a pile, which eliminates the need for aligning the pile driving device and the pile head of the pile.

【0012】[0012]

【課題を解決するための手段】発明者等は、杭打設用移
動式クレーンを、杭打ち装置と杭の杭頭との心が合うよ
うにを吊持し得る構成にすれば、ラチスブームを少し伏
せると共に、これに起因して生じる杭打ち装置の揺れの
減衰を待つというような心合わせ作業が不要になると考
えてなしたものである。
Means for Solving the Problems The inventors of the present invention have proposed a construction in which a mobile crane for driving piles can be suspended so that the center of a pile driving device and a pile head of a pile are aligned with each other. It is thought that the centering work such as waiting for the swaying of the pile driving device caused by this to be slightly lowered becomes unnecessary.

【0013】従って、上記課題を解決するために、本発
明の請求項1に係る杭打設用移動式クレーンが採用した
手段は、起伏自在なラチスブームの先端のポイントシー
ブ支持ブラケットによりポイントシーブピン(2) を支持
し、このポイントシーブピン(2) によりポイントシーブ
(3) を軸支し、このポイントシーブ(3) により杭を打設
する杭打ち装置を吊持する主フック(5) を巻上げ・巻下
げる主巻ロープ(4) を掛装すると共に、前記ポイントシ
ーブ(3) の外側であって、かつ前記ポイントシーブピン
(2) の径方向の中心を通る軸心位置において補助シーブ
(7) ,(7) を軸支し、これら補助シーブ(7) ,(7) のそ
れぞれに打設すべき杭を吊持する補助フック(9) を巻上
げ・巻下げる補巻ロープ(8) を掛装したことを特徴とす
る。
Therefore, in order to solve the above-mentioned problems, the means adopted by the mobile crane for driving piles according to claim 1 of the present invention uses a point sheave pin (point sheave pin) by a point sheave support bracket at the tip of an up-and-down movable lattice boom. 2) and the point sheave pin (2)
(3), and a main hoisting rope (4) for hoisting and lowering a main hook (5) for suspending a pile driving device for driving a pile by the point sheave (3). Outside the point sheave (3) and the point sheave pin
(2) Auxiliary sheave at the axial position passing through the radial center of
Auxiliary rope (8) that supports (7) and (7), and hoisting and lowering auxiliary hooks (9) for suspending piles to be driven into each of these auxiliary sheaves (7) and (7) Is mounted.

【0014】また、上記課題を解決するために、本発明
の請求項2に係る杭打設用移動式クレーンが採用した手
段は、請求項1に記載の杭打設用移動式クレーンにおい
て、前記補助シーブ(7) ,(7) を軸支するピンが、前記
ポイントシーブ(3) を軸支するポイントシーブピン(2)
であることを特徴とする。
According to a second aspect of the present invention, there is provided a pile driving mobile crane according to the first aspect of the present invention. A pin for supporting the auxiliary sheave (7), (7) is a point sheave pin (2) for supporting the point sheave (3).
It is characterized by being.

【0015】[0015]

【発明の実施の形態】以下、本発明の実施の形態に係る
杭打設用移動式クレーンの構成を、杭打ち装置と杭とを
吊持した状態を示す模式的主要部構成説明図の図1を参
照しながら説明する。但し、杭打設用移動式クレーン本
体の構成については履帯式の走行台車と、旋回体、ラチ
スブームとを備えてなる構成であって、従来例に係る杭
打設用移動式クレーン本体と同構成であるから、杭打設
用移動式クレーン本体に係る説明は割愛し、主としてそ
の構成上相違する点について、従来と同一のもの並びに
同一機能を有するものを同一符号を以て説明する。
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a schematic explanatory view of a main part of a mobile crane for driving a pile according to an embodiment of the present invention, showing a state in which a pile driving device and a pile are suspended. 1 will be described. However, the configuration of the mobile crane body for driving a pile is a configuration including a crawler-type traveling vehicle, a revolving unit, and a lattice boom, and is the same as that of the mobile crane body for driving a pile according to the conventional example. Therefore, the explanation of the mobile crane body for pile driving is omitted, and the points that are different mainly in the configuration will be described with the same reference numerals for those having the same functions and those having the same functions as those in the related art.

【0016】即ち、図において示す符号2は、図示しな
いラチスブームの先端のポイントシーブ支持ブラケット
により水平支持されてなるポイントシーブピンで、この
ポイントシーブピン2の長手方向の中央部分には4個の
ポイントシーブ3,3,3,3が取付けられると共に、
前記ポイントシーブピン2のこれら4個のポイントシー
ブ3,3,3,3の外側位置に2個の補助シーブ7,7
が取付けられている。
That is, reference numeral 2 shown in the drawing denotes a point sheave pin horizontally supported by a point sheave support bracket at the tip of a lattice boom (not shown), and four points are provided at the center of the point sheave pin 2 in the longitudinal direction. With sheaves 3,3,3,3 attached,
Two auxiliary sheaves 7, 7 are located outside the four point sheaves 3, 3, 3, 3 of the point sheave pin 2.
Is installed.

【0017】前記4個のポイントシーブ3,3,3,3
には主フック5が、図示しない主巻ウインチによって巻
上げ・巻下げられる主巻ロープ4を介して吊持されてい
る。より詳しくは、前記主フック5は、そのフック支持
ピン5aに取付けられた4個のフックシーブ5b,5
b,5b,5bと前記ポイントシーブ3,3,3,3と
に主巻ロープ4が掛回されることにより吊持されてお
り、そしてこの主フック5には周知の構成になる杭打ち
装置10が吊持されている。なお、上記のとおり、ポイ
ントシーブ3とフックシーブ5bとは何れも4個ずつ配
設されているが、これはただ単なる設計上の問題であっ
て、例えば3個ずつ以下であっても、また5個ずつ以上
であっても良いものである。
The four point sheaves 3, 3, 3, 3
The main hook 5 is suspended via a main winding rope 4 which is wound up and down by a main winding winch (not shown). More specifically, the main hook 5 includes four hook sheaves 5b, 5 attached to its hook support pins 5a.
b, 5b, 5b and the point sheaves 3, 3, 3, 3 are hung by being wound around a main winding rope 4, and the main hook 5 has a pile driving device having a well-known configuration. 10 are suspended. As described above, the point sheave 3 and the hook sheave 5b are all provided four each. However, this is merely a design problem. It may be more than one by one.

【0018】前記2個の補助シーブ7,7のそれぞれに
は、図示しない補巻ウインチによって同期して巻上げ・
巻下げられる補巻ロープ8が掛装されると共に、これら
補巻ロープ8には補助フック9が取付けられている。そ
して、これら補助フック9,9に掛けられてなる吊上用
ロープ9a,9aが、外周部に固着されている逆Uの字
状の吊フック(必要に応じて着脱される。)に掛けられ
ることにより円筒状の鋼管杭Pが吊持されている。な
お、特に円筒状の鋼管杭Pである必要がなく、例えば角
筒状の鋼管杭であっても、また矢板であっても良い。つ
まり、杭の形状は工事の種類により選択されるものであ
る。
Each of the two auxiliary sheaves 7 and 7 is wound up in synchronization with an auxiliary winch (not shown).
Auxiliary ropes 8 to be lowered are mounted, and auxiliary hooks 9 are attached to the auxiliary ropes 8. The lifting ropes 9a, 9a hung on the auxiliary hooks 9, 9 are hung on inverted U-shaped hanging hooks (attached and detached as necessary) fixed to the outer peripheral portion. As a result, the cylindrical steel pipe pile P is suspended. In addition, it is not necessary to be a cylindrical steel pipe pile P in particular. For example, it may be a square tubular steel pipe pile or a sheet pile. That is, the shape of the pile is selected according to the type of construction.

【0019】以下、上記構成になる杭打設用移動式クレ
ーンの作用態様を説明すると、上記のとおり、杭打ち装
置10を吊持する主フック5を主巻ロープ4を介して吊
持する4個のポイントシーブ3,3,3,3と、鋼管杭
Pを吊持する補助フック9,9を補巻ロープ9,9を介
して吊持する補助シーブ7,7とは何れも1本のポイン
トシーブピン2に取付けられているので、従来例に係る
杭打設用移動式クレーンのように、杭打ち装置と杭との
心合わせを行うに際してラチスブームを少し伏せるまで
もなく、杭打ち装置10の中心と鋼管杭Pの杭頭の中心
とはこれらが吊持された時点で既に合致している。
The operation of the pile driving mobile crane having the above construction will be described below. As described above, the main hook 5 for suspending the pile driving device 10 is suspended via the main winding rope 4. Each of the point sheaves 3,3,3,3 and the auxiliary sheave 7,7 for suspending the auxiliary hook 9,9 for suspending the steel pipe pile P via the auxiliary rope 9,9 is one. Since it is attached to the point sheave pin 2, unlike the conventional mobile crane for driving a pile, it is not necessary to slightly lower the lattice boom when aligning the pile driving device with the pile. And the center of the pile head of the steel pipe pile P already match when they are suspended.

【0020】従って、前記補巻ロープ7,7を同期させ
て巻下げて鋼管杭Pを下降させると共に、下降させた鋼
管杭Pを地盤に垂直に立設する。次いで、主巻ウインチ
により主巻ロープ4を巻下げて主フック5下降させるだ
けで、杭打ち装置10は地盤に立設されている鋼管杭P
の杭頭の中心に向かって前後方向に揺れることなく下降
するから、従来例に係る杭打設用移動式クレーンのよう
に、杭打ち装置と杭の杭頭との心合わせを行うに際して
ラチスブームを少し伏せる必要も、また杭打ち装置10
の前後方向の揺れの減衰を待つ必要もない。
Therefore, the steel pipe piles P are lowered by lowering the auxiliary ropes 7 and 7 in synchronization with each other, and the lowered steel pipe piles P are erected vertically on the ground. Next, only by lowering the main winding rope 4 by the main winding winch and lowering the main hook 5, the pile driving device 10 allows the steel pipe pile P standing upright on the ground.
As it descends without swinging back and forth toward the center of the pile head, the lattice boom is used to align the pile driving device with the pile head, as in the conventional mobile crane for driving a pile. It is necessary to lie down a little,
There is no need to wait for the front-rear sway to decay.

【0021】そのため、本発明の実施の形態に係る杭打
設用移動式クレーンによれば、従来例に係る杭打設用移
動式クレーンに比較して、極めて短時間のうちに鋼管杭
Pの打設作業を開始することができ、鋼管杭Pの打設作
業能率の向上に対して大いに寄与することができるとい
う極めて優れた効果がある。
Therefore, according to the mobile crane for driving a pile according to the embodiment of the present invention, compared with the mobile crane for driving a pile according to the conventional example, the steel pipe pile P can be moved in an extremely short time. There is an extremely excellent effect that the casting operation can be started, which can greatly contribute to improvement in the efficiency of the driving operation of the steel pipe pile P.

【0022】なお、以上では、上記のとおり、杭打ち装
置10を吊持する主フック5を主巻ロープ4を介して吊
持する4個のポイントシーブ3,3,3,3と、鋼管杭
Pを吊持する補助フック9,9を補巻ロープ9,9を介
して吊持する2個の補助シーブ7,7とは何れも1本の
ポイントシーブピン2に取付けられている杭打設用移動
式クレーンを例として説明したが、これら4個のポイン
トシーブ3,3,3,3と2個の補助シーブ7,7とは
同一軸線を回転中心とする位置に軸支されていれば良
い。
In the above description, as described above, the four point sheaves 3, 3, 3, 3 for suspending the main hook 5 for suspending the pile driving device 10 via the main winding rope 4, and the steel pipe pile The two auxiliary sheaves 7, 7 for suspending the auxiliary hooks 9, 9 for suspending the P via the auxiliary ropes 9, 9 are all pile driving that are attached to one point sheave pin 2. The mobile crane described above has been described as an example, but if these four point sheaves 3, 3, 3, 3 and the two auxiliary sheaves 7, 7 are pivotally supported at a position about the same axis as the center of rotation. good.

【0023】従って、4個のポイントシーブ3,3,
3,3と、補助シーブ7,7とをそれぞれ個別のピンに
よって軸支する構成にすることができるので、上記実施
の形態に係る杭打設用移動式クレーンによって本発明の
技術的思想の範囲が限定されるものではなく、また本発
明の技術的思想の範囲を逸脱しない範囲内における設計
変更等は自由自在である。
Therefore, the four point sheaves 3, 3,
Since the third and third sheaves 7 and 7 can be pivotally supported by individual pins, the range of the technical idea of the present invention is achieved by the pile driving mobile crane according to the above embodiment. Is not limited, and design changes and the like can be freely made without departing from the scope of the technical idea of the present invention.

【0024】[0024]

【発明の効果】以上詳述したように、本発明の請求項1
に係る杭打設用移動式クレーンによれば杭打ち装置を吊
持する主フックを主巻ロープを介して吊持するポイント
シーブと、杭を吊持する補助フックを補巻ロープを介し
て吊持する補助シーブとは同一軸線上において軸支され
ており、また本発明の請求項2に係る杭打設用移動式ク
レーンによれば杭打ち装置を吊持する主フックを主巻ロ
ープを介して吊持するポイントシーブと、杭を吊持する
補助フックを補巻ロープを介して吊持する補助シーブと
は何れもポイントシーブピンによって軸支されている。
As described in detail above, claim 1 of the present invention
According to the mobile crane for pile driving according to the above, a point sheave for suspending the main hook for suspending the pile driving device via the main winding rope and an auxiliary hook for suspending the pile via the auxiliary winding rope. The auxiliary sheave to be carried is axially supported on the same axis, and according to the mobile crane for pile driving according to claim 2 of the present invention, the main hook for suspending the pile driving device is connected via the main winding rope. Both the point sheave for suspending and suspending the pile and the auxiliary sheave for suspending the auxiliary hook for suspending the pile via the auxiliary rope are pivotally supported by point sheave pins.

【0025】従って、本発明に係る杭打設用移動式クレ
ーンによれば、杭打ち装置の中心と杭の杭頭の中心とは
これらが吊持された時点で既に合致しており、杭打ち装
置は地盤に立設されている杭の杭頭の中心に向かって前
後方向に揺れることなく下降するので、従来例に係る杭
打設用移動式クレーンのように、杭打ち装置と杭の杭頭
との心合わせを行うに際してラチスブームを少し伏せる
までもなく、また杭打ち装置の揺れの減衰を待つまでも
なく杭の打設作業を開始することができ、杭の打設作業
能率の向上に対して大いに寄与することができるという
極めて優れた効果がある。
Therefore, according to the mobile pile crane of the present invention, the center of the pile driving device and the center of the pile head of the pile already coincide with each other when they are suspended. Since the device descends without swinging in the front-rear direction toward the center of the pile head of the pile standing on the ground, the pile driving device and the pile When aligning with the head, it is possible to start pile driving without having to turn the lattice boom down a little and wait for the sway of the pile driving device to attenuate, improving the efficiency of pile driving. There is an extremely excellent effect that it can greatly contribute to this.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施の形態に係る杭打設用移動式クレ
ーンの、杭打ち装置と杭とを吊持した状態を示す模式的
主要部構成説明図である。
FIG. 1 is a schematic main portion configuration explanatory view showing a state in which a pile driving device and a pile are suspended in a mobile crane for driving piles according to an embodiment of the present invention.

【図2】従来例に係り、杭打ち装置と杭とを吊持した状
態を示す杭打設用移動式クレーンのラチスブーム頂部付
近の構成説明図である。
FIG. 2 is a configuration explanatory view of the vicinity of the top of a lattice boom of a mobile pile driving crane showing a state where a pile driving device and a pile are suspended according to a conventional example.

【図3】従来例に係り、杭打ち装置と杭とを吊持した状
態を示す杭打設用移動式クレーンのラチスブーム頂部付
近の模式的構成説明図である。
FIG. 3 is a schematic structural explanatory view of the vicinity of the top of a lattice boom of a mobile pile driving crane showing a state where a pile driving device and a pile are suspended according to a conventional example.

【符号の説明】[Explanation of symbols]

1…ラチスブーム,1a…ポイントシーブ支持ブラケッ
ト 2…ポイントシーブピン 3…ポイントシーブ 4…主巻ロープ 5…主フック.5a…フック支持ピン,5b…フックシ
ーブ 7…補助シーブ 8…補巻ロープ 9…補助フック,9a…吊上用ロープ 10…杭打ち装置 P…鋼管杭
DESCRIPTION OF SYMBOLS 1 ... Lattice boom, 1a ... Point sheave support bracket 2 ... Point sheave pin 3 ... Point sheave 4 ... Main rope 5 ... Main hook. 5a ... hook support pin, 5b ... hook sheave 7 ... auxiliary sheave 8 ... auxiliary rope 9 ... auxiliary hook, 9a ... lifting rope 10 ... pile driving device P ... steel pipe pile

フロントページの続き (72)発明者 原 正敏 兵庫県高砂市荒井町新浜2丁目3番1号 株式会社神戸製鋼所高砂製作所内Continued on the front page (72) Inventor Masatoshi Hara 2-3-1, Shinhama, Arai-cho, Takasago-shi, Hyogo Inside Kobe Steel, Ltd. Takasago Works

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 起伏自在なラチスブームの先端のポイン
トシーブ支持ブラケットによりポイントシーブピン(2)
を支持し、このポイントシーブピン(2) によりポイント
シーブ(3) を軸支し、このポイントシーブ(3) により杭
を打設する杭打ち装置を吊持する主フック(5) を巻上げ
・巻下げる主巻ロープ(4) を掛装すると共に、前記ポイ
ントシーブ(3) の外側であって、かつ前記ポイントシー
ブピン(2) の径方向の中心を通る軸心位置において補助
シーブ(7) ,(7) を軸支し、これら補助シーブ(7) ,
(7) のそれぞれに打設すべき杭を吊持する補助フック
(9)を巻上げ・巻下げる補巻ロープ(8) を掛装したこと
を特徴とする杭打設用移動式クレーン。
A point sheave pin (2) is provided by a point sheave support bracket at the tip of an undulating lattice boom.
The point sheave pin (2) supports the point sheave (3), and the point sheave (3) winds and winds the main hook (5) that suspends the pile driving device for setting the pile. At the same time, the main sheave rope (4) to be lowered is hung, and the auxiliary sheave (7) is located outside the point sheave (3) and at the axial center passing through the radial center of the point sheave pin (2). (7), and these auxiliary sheaves (7),
(7) Auxiliary hooks for hanging piles to be cast
A mobile crane for driving piles, which is equipped with an auxiliary rope (8) for hoisting and lowering (9).
【請求項2】 前記補助シーブ(7) ,(7) を軸支するピ
ンが、前記ポイントシーブ(3) を軸支するポイントシー
ブピン(2) であることを特徴とする請求項1に記載の杭
打設用移動式クレーン。
2. A pin sheave pin (2) for supporting said point sheave (3), said pin supporting said auxiliary sheaves (7), (7). Mobile crane for pile driving.
JP27088496A 1996-10-14 1996-10-14 Mobile crane for pile driving Expired - Fee Related JP3712801B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP27088496A JP3712801B2 (en) 1996-10-14 1996-10-14 Mobile crane for pile driving

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP27088496A JP3712801B2 (en) 1996-10-14 1996-10-14 Mobile crane for pile driving

Publications (2)

Publication Number Publication Date
JPH10114941A true JPH10114941A (en) 1998-05-06
JP3712801B2 JP3712801B2 (en) 2005-11-02

Family

ID=17492314

Family Applications (1)

Application Number Title Priority Date Filing Date
JP27088496A Expired - Fee Related JP3712801B2 (en) 1996-10-14 1996-10-14 Mobile crane for pile driving

Country Status (1)

Country Link
JP (1) JP3712801B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103147441A (en) * 2012-12-03 2013-06-12 龙源电力集团股份有限公司 Method for controlling construction verticality of large-sized single pile
CN115450205A (en) * 2022-09-24 2022-12-09 贾龙国 Construction structure and construction process for inserting prestressed pipe pile into triaxial mixing pile
WO2024083707A1 (en) 2022-10-18 2024-04-25 Dieseko Group B.V. Pile lifting device

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102425167B (en) * 2011-11-25 2013-10-30 天津港航工程有限公司 Pile sinking method for driving large-diameter steel pipe pile in intertidal zone

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103147441A (en) * 2012-12-03 2013-06-12 龙源电力集团股份有限公司 Method for controlling construction verticality of large-sized single pile
CN115450205A (en) * 2022-09-24 2022-12-09 贾龙国 Construction structure and construction process for inserting prestressed pipe pile into triaxial mixing pile
CN115450205B (en) * 2022-09-24 2024-01-26 贾龙国 Construction structure and construction process for inserting pre-stress pipe pile into triaxial stirring pile
WO2024083707A1 (en) 2022-10-18 2024-04-25 Dieseko Group B.V. Pile lifting device
NL2033339B1 (en) * 2022-10-18 2024-05-06 Dieseko Group B V Pile lifting device

Also Published As

Publication number Publication date
JP3712801B2 (en) 2005-11-02

Similar Documents

Publication Publication Date Title
CN206188254U (en) Mobile lifting bracket for building bridge
JP4092665B1 (en) Long member start-up set device for excavator
JPH10114941A (en) Traveling crane for driving pile
CN213142094U (en) Water quenching equipment for carburizing steel forging
CN211338603U (en) Gantry frame of crawler crane
JPS5943797A (en) Turning derrick
JP3637173B2 (en) Excavator lifting device
CN218493543U (en) Drill rod retracting mechanism and pile driver using same
CN215160519U (en) Pile turning device for offshore wind power tower
CN211971560U (en) Column type cantilever crane
JPH0643224Y2 (en) Steel pipe pile placing device
JP2515531B2 (en) Boom swiveling crane
JPH11100191A (en) Jack-up device of construction machine and turning method for jack-up cylinder
JPS6322922A (en) Multipurpose working ship
JPS5842497Y2 (en) pile driver
CN217102703U (en) Bridge girder erection machine upset hoist of pier hoist and mount
CN217808423U (en) Municipal administration subway foundation ditch is with device that unearths perpendicularly
CN214570251U (en) Derrick mast lifting mechanism convenient to operate
CN109653200B (en) River piling machine
JPH0629221Y2 (en) Steel pipe pile placing device
JPH0754227Y2 (en) Mobile crane
JPH0319518Y2 (en)
JP3815756B2 (en) Temporary elevator for fistula and its transportation method
JPH0647823B2 (en) Steel pipe pile construction method
JPH0447275Y2 (en)

Legal Events

Date Code Title Description
A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A712

Effective date: 20040918

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20041203

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050413

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050419

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050608

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050809

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20050818

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080826

Year of fee payment: 3

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090826

Year of fee payment: 4

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090826

Year of fee payment: 4

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100826

Year of fee payment: 5

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100826

Year of fee payment: 5

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110826

Year of fee payment: 6

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120826

Year of fee payment: 7

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130826

Year of fee payment: 8

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees