CN211338603U - A crawler crane gantry - Google Patents

A crawler crane gantry Download PDF

Info

Publication number
CN211338603U
CN211338603U CN201922043889.2U CN201922043889U CN211338603U CN 211338603 U CN211338603 U CN 211338603U CN 201922043889 U CN201922043889 U CN 201922043889U CN 211338603 U CN211338603 U CN 211338603U
Authority
CN
China
Prior art keywords
crawler
door type
type frame
portal frame
bed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201922043889.2U
Other languages
Chinese (zh)
Inventor
赵洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DALIAN UNIVERSITY OF TECHNOLOGY (XUZHOU) ENGINEERING MACHINERY RESEARCH CENTER
Original Assignee
DALIAN UNIVERSITY OF TECHNOLOGY (XUZHOU) ENGINEERING MACHINERY RESEARCH CENTER
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DALIAN UNIVERSITY OF TECHNOLOGY (XUZHOU) ENGINEERING MACHINERY RESEARCH CENTER filed Critical DALIAN UNIVERSITY OF TECHNOLOGY (XUZHOU) ENGINEERING MACHINERY RESEARCH CENTER
Priority to CN201922043889.2U priority Critical patent/CN211338603U/en
Application granted granted Critical
Publication of CN211338603U publication Critical patent/CN211338603U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Jib Cranes (AREA)

Abstract

The utility model discloses a crawler crane door type frame, including track bed, door type frame one and door type frame two, it has the pivot to embed on the track bed lateral wall, the pivot has two, pivot one side is rotated through the bearing and is connected with door type frame one, the pivot opposite side is rotated through the bearing and is connected with door type frame two. Has the advantages that: the utility model discloses a set up door type frame one and door type frame two for the device can carry out the operation of hanging up of double hook simultaneously, great improvement work efficiency, is favorable to big batch hoisting task's quick completion.

Description

一种履带式起重机门型架A crawler crane gantry

技术领域technical field

本实用新型涉及履带式起重机技术领域,具体涉及一种履带式起重机门型架。The utility model relates to the technical field of crawler cranes, in particular to a crawler crane portal frame.

背景技术Background technique

履带式起重机,是一种高层建筑施工用的自行式起重机。是一种利用履带行走的动臂旋转起重机。履带接地面积大,通过性好,适应性强,可带载行走,适用于建筑工地的吊装作业。可进行挖土、夯土、打桩等多种作业。但因行走速度缓慢,长距离转移工地需要其他车辆搬运。The crawler crane is a self-propelled crane for high-rise building construction. It is a boom rotating crane that uses the crawler to travel. The crawler has a large grounding area, good passability, strong adaptability, and can walk with load, which is suitable for hoisting operations on construction sites. It can perform various operations such as excavation, rammed earth, and piling. However, due to the slow walking speed, other vehicles are required for long-distance transfer of the site.

现有的履带式起重机的门型架只有一组吊钩,工作方式较为单一,单次只能吊升一组物件,效率较低,对于大批量的货物,工作速度较慢。The gantry of the existing crawler crane has only one set of hooks, and the working mode is relatively simple. Only one set of objects can be lifted at a time, and the efficiency is low. For large quantities of goods, the working speed is slow.

实用新型内容Utility model content

(一)要解决的技术问题(1) Technical problems to be solved

为了克服现有技术不足,现提出一种履带式起重机门型架,解决现有履带式起重机的门型架只有一组吊钩,工作方式较为单一,单次只能吊升一组物件,效率较低,对于大批量的货物,工作速度较慢的问题。In order to overcome the shortcomings of the existing technology, a crawler crane gantry is proposed, which solves the problem that the existing crawler crane gantry has only one set of hooks, the working mode is relatively simple, and only one set of objects can be lifted at a time, and the efficiency Lower, for large quantities of goods, the problem of slower work speed.

(二)技术方案(2) Technical solutions

本实用新型通过如下技术方案实现:本实用新型提出了一种履带式起重机门型架,包括履带床、门型架一以及门型架二,所述履带床一侧壁上内嵌有转轴,所述转轴有两个,所述转轴一侧通过轴承转动连接有所述门型架一,所述转轴另一侧通过轴承转动连接有所述门型架二。The utility model is realized through the following technical solutions: the utility model proposes a crawler crane portal frame, which includes a crawler bed, a portal frame and a portal frame two, wherein a rotating shaft is embedded in a side wall of the crawler bed, There are two rotating shafts, one side of the rotating shaft is rotatably connected to the first portal frame through a bearing, and the other side of the rotating shaft is rotatably connected to the second portal frame through a bearing.

通过采用上述技术方案,所述门型架一和所述门型架二均通过所述转轴可在所述履带床上调节倾角,所述门型架一和所述门型架二为双工位工作模式。By adopting the above technical solution, the first portal frame and the second portal frame can both adjust the inclination angle on the crawler bed through the rotating shaft, and the first portal frame and the second portal frame are double stations Operating mode.

进一步的,所述履带床顶部焊接有立柱,所述立柱有两组,所述立柱顶部通过轴承转动动连接有滑轮一。Further, the top of the crawler bed is welded with uprights, there are two groups of the uprights, and the top of the uprights is rotatably connected with a pulley through a bearing.

通过采用上述技术方案,所述立柱用来用固定和支撑设备的吊升线。By adopting the above technical solution, the vertical column is used to fix and support the hoisting line of the equipment.

进一步的,所述履带床顶部靠近所述立柱一侧通过卡槽固定有卷扬筒一,所述履带床顶部靠近所述立柱另一侧通过卡槽固定有卷扬筒二,所述卷扬筒一和所述卷扬筒二上均缠绕有吊绳。Further, one side of the top of the crawler bed close to the column is fixed with a hoisting drum 1 through a slot, and the other side of the top of the crawler bed close to the column is fixed with a hoist drum 2 through a slot, and the hoist is Both the first drum and the second hoisting drum are wound with suspending ropes.

通过采用上述技术方案,所述卷扬筒一和所述卷扬筒二由同一个电机控制,实现同步的吊升作业By adopting the above technical solution, the hoisting drum 1 and the hoisting drum 2 are controlled by the same motor to realize synchronous hoisting operation

进一步的,所述门型架一和所述门型架二顶部转动连接有滑轮二,所述吊绳嵌套在所述滑轮一以及所述滑轮二上。Further, a second pulley is rotatably connected to the top of the first portal frame and the second portal frame, and the hanging rope is nested on the first pulley and the second pulley.

进一步的,所述吊绳上嵌套有收线器,所述吊绳一端滑动连接有吊钩。Further, a wire take-up is nested on the hanging rope, and a hook is slidably connected to one end of the hanging rope.

通过采用上述技术方案,所述吊绳是一种金属钢筋,所述收线器用来限制所述吊绳的位置,避免所述吊绳出现打结现象。By adopting the above technical solution, the suspending rope is a metal steel bar, and the wire take-up device is used to limit the position of the suspending rope to avoid knotting of the suspending rope.

进一步的,所述履带床顶部靠近所述卷扬筒一以及所述卷扬筒二一侧均焊接有固定块,所述固定块一侧壁上转动连接有液压杆,所述液压杆与所述门型架一以及所述门型架二均通过螺栓连接。Further, a fixing block is welded on the top of the crawler bed close to the hoisting drum 1 and the hoisting drum 2, and a hydraulic rod is rotatably connected to the side wall of the fixing block, and the hydraulic rod is connected with the hoisting drum. The first portal frame and the second portal frame are connected by bolts.

通过采用上述技术方案,所述固定块用来固定支撑所述液压杆,所述液压杆可拖动所述门型架一和门型架二沿着转轴转动,调节所述门型架一和门型架二倾角。By adopting the above technical solution, the fixing block is used to fix and support the hydraulic rod, and the hydraulic rod can drag the gantry 1 and gantry 2 to rotate along the rotating shaft, and adjust the gantry 1 and gantry 2 to rotate along the shaft. Two inclinations of the portal frame.

(三)有益效果(3) Beneficial effects

本实用新型相对于现有技术,具有以下有益效果:Compared with the prior art, the utility model has the following beneficial effects:

为解决现有履带式起重机的门型架只有一组吊钩,工作方式较为单一,单次只能吊升一组物件,效率较低,对于大批量的货物,工作速度较慢的问题,本实用新型通过设置门型架一和门型架二,使得装置可同时进行双吊钩的吊升作业,大大的提高了工作效率,有利于大批量起重任务的快速完成。In order to solve the problem that the gantry of the existing crawler crane has only one set of hooks, the working mode is relatively simple, only one set of objects can be lifted at a time, and the efficiency is low. By arranging the first portal frame and the second portal frame, the utility model enables the device to simultaneously perform the lifting operation of the double hooks, greatly improving the work efficiency and facilitating the rapid completion of large-scale lifting tasks.

附图说明Description of drawings

图1是本实用新型所述一种履带式起重机门型架的结构示意图;Fig. 1 is the structural representation of a kind of crawler crane portal frame according to the present utility model;

图2是本实用新型所述一种履带式起重机门型架中履带床与转轴的位置关系示意图;2 is a schematic diagram of the positional relationship between a crawler bed and a rotating shaft in a crawler crane portal frame according to the present invention;

图3是本实用新型所述一种履带式起重机门型架的左视图。Figure 3 is a left side view of a crawler crane portal frame according to the present invention.

附图标记说明如下:The reference numerals are explained as follows:

1、履带床;2、门型架一;3、门型架二;4、吊钩;5、立柱;6、卷扬筒一;7、卷扬筒二;8、滑轮一;9、滑轮二;10、吊绳;11、液压杆;12、固定块;13、转轴;14、收线器。1. Crawler bed; 2. Portal frame 1; 3. Portal frame 2; 4. Hook; 5. Upright column; 6. Hoisting drum 1; 7. Hoisting drum 2; Two; 10, hanging rope; 11, hydraulic rod; 12, fixed block; 13, shaft; 14, wire take-up.

具体实施方式Detailed ways

为了使本实用新型的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本实用新型进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本实用新型,并不用于限定本实用新型。In order to make the purpose, technical solutions and advantages of the present utility model more clearly understood, the present utility model will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention, and are not intended to limit the present invention.

如图1-图3所示,本实施例中的一种履带式起重机门型架,包括履带床1、门型架一2以及门型架二3,履带床1一侧壁上内嵌有转轴13,转轴13有两个,转轴13一侧通过轴承转动连接有门型架一2,转轴13另一侧通过轴承转动连接有门型架二3,门型架一2和门型架二3均通过转轴13可在履带床1上调节倾角,门型架一2和门型架二3为双工位工作模式。As shown in Figures 1-3, a crawler crane portal frame in this embodiment includes a crawler bed 1, a portal frame 2 and a portal frame 2 3. A side wall of the crawler bed 1 is embedded with a Rotating shaft 13, there are two rotating shafts 13, one side of the rotating shaft 13 is connected with a portal frame 1 2 through a bearing, and the other side of the rotating shaft 13 is connected with a portal frame 2 3 through a bearing rotation, a portal frame 1 2 and a portal frame 2 3 The inclination angle can be adjusted on the crawler bed 1 through the rotating shaft 13, and the portal frame 1 2 and the portal frame 2 3 are in double-station working mode.

履带床1顶部焊接有立柱5,立柱5有两组,立柱5顶部通过轴承转动动连接有滑轮一8,立柱5用来用固定和支撑设备的吊升线。The top of the crawler bed 1 is welded with a column 5, and there are two groups of columns 5. The top of the column 5 is rotatably connected with a pulley 8 through a bearing. The column 5 is used to fix and support the hoisting line of the equipment.

履带床1顶部靠近立柱5一侧通过卡槽固定有卷扬筒一6,履带床1顶部靠近立柱5另一侧通过卡槽固定有卷扬筒二7,卷扬筒一6和卷扬筒二7上均缠绕有吊绳10,卷扬筒一6和卷扬筒二7由同一个电机控制,实现同步的吊升作业。One side of the top of the crawler bed 1 close to the column 5 is fixed with a hoisting drum 1 6 through a slot, and the other side of the top of the crawler bed 1 near the column 5 is fixed with a hoisting drum 2 7, a hoisting drum 1 6 and a hoisting drum. The second 7 is wound with a suspending rope 10, and the first hoisting drum 6 and the second hoisting drum 7 are controlled by the same motor to realize the synchronous lifting operation.

门型架一2和门型架二3顶部转动连接有滑轮二9,吊绳10嵌套在滑轮一8以及滑轮二9上,吊绳10是一种金属钢筋。Two pulleys 9 are rotatably connected to the tops of the first portal frame 2 and the second portal frame 3. The hanging rope 10 is nested on the first pulley 8 and the second pulley 9. The hanging rope 10 is a metal steel bar.

吊绳10上嵌套有收线器14,吊绳10一端滑动连接有吊钩4,收线器14用来限制吊绳10的位置,避免吊绳10出现打结现象。A wire take-up 14 is nested on the hanging rope 10 , and one end of the hanging rope 10 is slidably connected with a hook 4 .

履带床1顶部靠近卷扬筒一6以及卷扬筒二7一侧均焊接有固定块12,固定块12一侧壁上转动连接有液压杆11,液压杆11与门型架一2以及门型架二3均通过螺栓连接,固定块12用来固定支撑液压杆11,液压杆11可拖动门型架一2和门型架二3沿着转轴13转动,调节门型架一2和门型架二3倾角。A fixed block 12 is welded on the top of the crawler bed 1 near the hoisting drum 1 6 and the hoisting drum 2 7. A hydraulic rod 11 is rotatably connected to a side wall of the fixing block 12. The hydraulic rod 11 is connected to the portal frame 1 2 and the door. The frames 2 and 3 are connected by bolts, and the fixing block 12 is used to fix and support the hydraulic rod 11. The hydraulic rod 11 can drag the portal frame 1 2 and the portal frame 2 3 to rotate along the rotating shaft 13, and adjust the portal frame 1 2 and the portal frame 2. Gantry two 3 inclination.

本实施例的具体实施过程如下:首先将履带床1安装在履带移动机构上,并将卷扬筒一6和卷扬筒二7接入到履带机的电机输出端,即可正常使用装置,用户通过控制室内的操作杆控制卷扬筒一6和卷扬筒二7工作,吊绳10在滑轮一8和滑轮二9的支撑下滑动,带动吊钩4上升或者下降来起重物件,门型架一2和门型架二3上的两组吊钩4可实现装置同时起重两组物件,大大的提高了起重工作的效率,有利于大批量起重任务的快速完成,节省了人力物力的投入时间,进而节省了成本。The specific implementation process of this embodiment is as follows: first, the crawler bed 1 is installed on the crawler moving mechanism, and the first hoisting drum 6 and the second hoisting drum 7 are connected to the motor output end of the crawler machine, and the device can be used normally, The user controls the hoisting drum 1 6 and the hoisting drum 2 7 to work through the operating lever in the control room, the suspending rope 10 slides under the support of the pulley 1 8 and the pulley 2 9, and drives the hook 4 to rise or fall to lift the objects. The two sets of hooks 4 on the frame 1 2 and the portal frame 2 3 can realize the device to lift two sets of objects at the same time, which greatly improves the efficiency of lifting work, is conducive to the rapid completion of large-scale lifting tasks, and saves money. Human and material resources are invested in time, thereby saving costs.

上面所述的实施例仅仅是对本实用新型的优选实施方式进行描述,并非对本实用新型的构思和范围进行限定。在不脱离本实用新型设计构思的前提下,本领域普通人员对本实用新型的技术方案做出的各种变型和改进,均应落入到本实用新型的保护范围,本实用新型请求保护的技术内容,已经全部记载在权利要求书中。The above-mentioned embodiments merely describe the preferred embodiments of the present invention, and do not limit the concept and scope of the present invention. Under the premise of not departing from the design concept of the present invention, various modifications and improvements made by ordinary persons in the art to the technical solutions of the present invention shall fall within the protection scope of the present invention. The content has been fully described in the claims.

Claims (6)

1. A gantry of a crawler crane, comprising: including track bed (1), door type frame one (2) and door type frame two (3), it has pivot (13) to embed on track bed (1) a lateral wall, pivot (13) have two, pivot (13) one side is rotated through the bearing and is connected with door type frame one (2), pivot (13) opposite side is rotated through the bearing and is connected with door type frame two (3).
2. A crawler crane gantry according to claim 1, wherein: the top welding of track bed (1) has stand (5), stand (5) have two sets ofly, stand (5) top is rotated through the bearing and is moved and be connected with pulley (8).
3. A crawler crane gantry according to claim 2, wherein: the top of the crawler bed (1) is close to one side of the upright post (5) and is fixedly provided with a first hoisting drum (6) through a clamping groove, the top of the crawler bed (1) is close to the other side of the upright post (5) and is fixedly provided with a second hoisting drum (7) through a clamping groove, and hoisting ropes (10) are wound on the first hoisting drum (6) and the second hoisting drum (7).
4. A crawler crane gantry according to claim 3, wherein: the top parts of the first door-shaped frame (2) and the second door-shaped frame (3) are rotatably connected with a second pulley (9), and the lifting rope (10) is nested on the first pulley (8) and the second pulley (9).
5. A crawler crane gantry according to claim 4, wherein: a wire winding device (14) is nested on the lifting rope (10), and one end of the lifting rope (10) is connected with a lifting hook (4) in a sliding mode.
6. A crawler crane gantry according to claim 5, wherein: the top of the crawler bed (1) is close to the first hoisting cylinder (6) and one side of the second hoisting cylinder (7) is welded with a fixing block (12), a hydraulic rod (11) is rotatably connected to one side wall of the fixing block (12), and the hydraulic rod (11) is connected with the first portal frame (2) and the second portal frame (3) through bolts.
CN201922043889.2U 2019-11-25 2019-11-25 A crawler crane gantry Expired - Fee Related CN211338603U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922043889.2U CN211338603U (en) 2019-11-25 2019-11-25 A crawler crane gantry

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922043889.2U CN211338603U (en) 2019-11-25 2019-11-25 A crawler crane gantry

Publications (1)

Publication Number Publication Date
CN211338603U true CN211338603U (en) 2020-08-25

Family

ID=72093873

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922043889.2U Expired - Fee Related CN211338603U (en) 2019-11-25 2019-11-25 A crawler crane gantry

Country Status (1)

Country Link
CN (1) CN211338603U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110872065A (en) * 2019-11-25 2020-03-10 大连理工大学(徐州)工程机械研究中心 A crawler crane gantry
CN113651251A (en) * 2021-07-27 2021-11-16 淮阴工学院 A kind of asphalt fixing plate handling device on both sides of road

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110872065A (en) * 2019-11-25 2020-03-10 大连理工大学(徐州)工程机械研究中心 A crawler crane gantry
CN113651251A (en) * 2021-07-27 2021-11-16 淮阴工学院 A kind of asphalt fixing plate handling device on both sides of road

Similar Documents

Publication Publication Date Title
CN103848360B (en) A kind of group tower tower crane being provided with packaged type balance weight system
CN211338603U (en) A crawler crane gantry
CN219363058U (en) Rocker suspension crane for building construction
CN206799021U (en) A kind of full circle swinging traveling derrick crane
CN210676745U (en) Simple pile head reinforcing steel bar straightening device
CN210393460U (en) Lifting device capable of rotating and stretching
CN206590793U (en) Connect arm assembly and the movable arm tower crane comprising the device in the air
CN208024056U (en) A kind of double flat arm ground type pole
CN202429923U (en) Travelling cable crane
CN206015665U (en) Movable reinforcement cage installs equipment
CN107986207A (en) A kind of bow member job platform and bow member Operation Van
CN209554663U (en) An Anti-Swing Crane Hoisting Mechanism
CN107235422A (en) It is exclusively used in the crane device of lifting steel pipes and welding
CN2204334Y (en) Front-probe support for machine-digging working-surface
CN110872065A (en) A crawler crane gantry
CN206955487U (en) It is exclusively used in lifting steel pipes and the crane device of welding
CN215828211U (en) Horizontal hoisting device for construction
CN212425253U (en) Hoisting device for installing steel plate warehouse
CN209536821U (en) A kind of gantry crane for Metro construction
CN221479334U (en) Multifunctional operation mechanism
CN208684253U (en) One kind preventing crane shaking device
CN204162317U (en) A kind of double leval jib high pedestal jib crane
CN218201875U (en) Oil press sling
CN221275026U (en) Lifting hook portal crane
CN215516432U (en) Movable microminiature crane for track

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200825