JPH093821A - Finisher - Google Patents

Finisher

Info

Publication number
JPH093821A
JPH093821A JP15770895A JP15770895A JPH093821A JP H093821 A JPH093821 A JP H093821A JP 15770895 A JP15770895 A JP 15770895A JP 15770895 A JP15770895 A JP 15770895A JP H093821 A JPH093821 A JP H093821A
Authority
JP
Japan
Prior art keywords
screed
construction
upper layer
lower layer
vehicle body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP15770895A
Other languages
Japanese (ja)
Inventor
Seiichiro Kikuta
誠一郎 菊田
Yoshinori Okawa
賢紀 大川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Heavy Industries Ltd
Original Assignee
Mitsubishi Heavy Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Heavy Industries Ltd filed Critical Mitsubishi Heavy Industries Ltd
Priority to JP15770895A priority Critical patent/JPH093821A/en
Publication of JPH093821A publication Critical patent/JPH093821A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Road Paving Machines (AREA)

Abstract

PURPOSE: To pave both a lower layer and an upper layer at the same time by installing a lower layer construction screed and an upper layer construction screed to a chassis so that they may be independent from each other. CONSTITUTION: A lower layer construction screed 4a is mounted on a frame of track links 9 by way of a leveling arm 4d. An upper layer construction screed 4b is mounted on a chassis 1 and a rib 8 rigidly connected to the chassis 1 by way of a leveling arm 3b. A very consistency concrete material (RCC) supplied to a hopper 2 is distributed to a front stage screw 6a and a rear stage screw 6b respectively by means of a lower layer construction feeder 7a and an upper layer construction feeder 7b. After the RCC material spreads to both sides from the central part of the chassis 1, the concrete is consolidated with the screed 4a so that the lower layer may be paved. At the same time, after the RCC material spreads from both ends of the chassis 1 to the inside, the concrete is consolidated with the screed 4b so that the upper layer may be paved.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、RCC(Roller Compa
cted Concrete:超固練りコンクリート)材を路盤に敷き
固めて鉄道用軌道を舗装する場合などに適用されるフィ
ニッシャーに関する。
The present invention relates to an RCC (Roller Compa
cted Concrete: A finisher that is applied when paving railway tracks by laying cted concrete on a roadbed.

【0002】[0002]

【従来の技術】図2はアスファルト合材を路盤に敷き固
めて道路を舗装する場合などに使用されている従来のフ
ィニッシャーの説明図である。図において、本フィニッ
シャーはアスファルト合材を容れて貯留するホッパー
2、ホッパー2内のアスファルト合材(舗装材)を移送
するフィーダ、フィーダで送られるアスファルト合材を
左右に広げるスクリュー6、スクリュー6によって広げ
られたアスファルト合材を敷き固めるタンパー、敷き均
すスクリード4などが、走行する車体1に上下に揺動可
能に設けられたレベリングアーム3の先端部に取付けら
れているフローティング形式のもので、レベリングアー
ム3はその基端部が車体1に支持されて車体1の後方へ
延び、揺動する先端部にスクリード4が懸吊された状態
で取付けられており、このスクリード4の自重によって
アスファルト合材に一定の面圧を掛けて敷き均すように
なっている。
2. Description of the Related Art FIG. 2 is an explanatory view of a conventional finisher used when paving a road by laying an asphalt mixture on a roadbed. In the figure, the finisher includes a hopper 2 for containing and storing the asphalt mixture, a feeder for transferring the asphalt mixture (paving material) in the hopper 2, a screw 6 for spreading the asphalt mixture sent by the feeder to the left and a right, and a screw 6. A tamper that spreads and spreads the spread asphalt mixture, a screed 4 that spreads it evenly, and the like is a floating type that is attached to the tip of a leveling arm 3 that is vertically swingably provided on the traveling vehicle body 1. The leveling arm 3 has its base end supported by the vehicle body 1 and extends rearward of the vehicle body 1, and is attached with the screed 4 suspended from the swinging tip portion. A certain amount of surface pressure is applied to the material to spread it.

【0003】[0003]

【発明が解決しようとする課題】上記のような従来のフ
ィニッシャーにおいて、RCC材を用いて鉄道用軌道を
舗装する場合は25cm程度の厚さが必要であるが、従来
のフィニッシャーを用いてRCC材を敷き固める場合の
施工厚さは15cm程度が限界で、鉄道用軌道として所要
の強度および精度を出すためには上下2層に分割して施
工する必要がある。従って、舗装に要する時間が倍にな
り、また材料の供給や他の作業用機械による運搬なども
一方向からアクセスすることができない。なお、コンク
リート専用のフィニッシャーはタンパの打撃音が大き
く、夜間に民家の近くで施工する軌道工事などには騒
音、振動などの面で使用することができない。
In the conventional finisher as described above, when paving a railroad track using RCC material, a thickness of about 25 cm is required. However, using the conventional finisher, RCC material is required. When laying and hardening, the construction thickness is limited to about 15 cm, and in order to obtain the required strength and accuracy as a railroad track, it is necessary to divide it into upper and lower layers. Therefore, the time required for paving is doubled, and the supply of materials and transportation by other working machines cannot be accessed from one direction. In addition, the finisher dedicated to concrete has a large tampering noise, and cannot be used in terms of noise and vibration for track construction performed near a private house at night.

【0004】[0004]

【課題を解決するための手段】本発明に係るフィニッシ
ャーは上記課題の解決を目的にしており、車体に第一の
ベアリングアームを介して懸吊された下層部施工用のス
クリードと、該下層部施工用のスクリードよりも後方に
位置して上記車体に第二のベアリングアームを介して懸
吊された上層部施工用のスクリードと、それぞれの上記
スクリードへ舗装材を供給して均す手段とを備えた構成
を特徴とする。
SUMMARY OF THE INVENTION A finisher according to the present invention is intended to solve the above-mentioned problems, and includes a screed for constructing a lower layer portion suspended from a vehicle body via a first bearing arm, and the lower layer portion. A screed for construction of an upper layer, which is located behind the screed for construction and suspended by a second bearing arm on the vehicle body, and a means for supplying and leveling paving material to each of the screeds. It is characterized by the structure provided.

【0005】また、本発明に係るフィニッシャーは、車
体に第一のベアリングアームを介して懸吊された下層部
施工用のスクリードと、該下層部施工用のスクリードよ
りも後方に位置して上記車体に第二のベアリングアーム
を介して懸吊された上層部施工用のスクリードと、それ
ぞれの上記スクリードへ舗装材を供給して均す手段とを
備え、上記上層部施工用のスクリードの央部が下方へ突
出しているとともに上記上層部施工用のスクリードへは
両側から舗装材が供給される構成を特徴とする。
The finisher according to the present invention includes a screed for construction of a lower layer portion suspended from the vehicle body through a first bearing arm, and the screed for construction of the lower layer portion located behind the screed for construction of the lower layer portion. A screed for upper layer construction suspended via a second bearing arm, and means for supplying and leveling a paving material to each of the screeds, and the central portion of the screed for upper layer construction is The construction is characterized in that the pavement material is projected from the lower side and is supplied from both sides to the screed for constructing the upper layer portion.

【0006】[0006]

【作用】即ち、本発明に係るフィニッシャーにおいて
は、車体に第一のベアリングアームを介して下層部施工
用のスクリードが懸吊されるとともに車体に第二のベア
リングアームを介して上層部施工用のスクリードが下層
部施工用のスクリードよりも後方に位置して懸吊されそ
れぞれのスクリードへ舗装材が供給されて均されるよう
になっており、車体に下層部施工用のスクリードと上層
部施工用のスクリードとが互いに独立して設けられ上下
層部施工用のスクリードへ舗装材が供給されて均される
ことにより下層部の舗装と上層部の舗装とが同時に行わ
れる。
That is, in the finisher according to the present invention, the screed for construction of the lower layer is suspended from the vehicle body via the first bearing arm, and the screed for construction of the upper layer from the vehicle body is constructed via the second bearing arm. The screed is positioned behind the screed for construction of the lower layer and is suspended so that the paving material is supplied to each screed and leveled, and the screed for construction of the lower layer and the construction of the upper layer are constructed on the vehicle body. The screeds are provided independently of each other, and the pavement material is supplied to the screeds for constructing the upper and lower layers to be leveled, whereby the pavement of the lower layer and the pavement of the upper layer are simultaneously performed.

【0007】また、本発明に係るフィニッシャーにおい
ては、車体に第一のベアリングアームを介して下層部施
工用のスクリードが懸吊されるとともに車体に第二のベ
アリングアームを介して央部が下方へ突出している上層
部施工用のスクリードが下層部施工用のスクリードより
も後方に位置して懸吊されそれぞれのスクリードへ舗装
材が供給されて均されるとともに上層部施工用のスクリ
ードへは両側から舗装材が供給されるようになってお
り、車体に下層部施工用のスクリードと上層部施工用の
スクリードとが互いに独立して設けられ上下層部施工用
のスクリードへ舗装材が供給されて均されることにより
下層部の舗装と上層部の舗装とが同時に行われる。ま
た、上層部施工用のスクリードの央部が下方へ突出して
いるとともに上層部施工用のスクリードへは両側から舗
装材が供給されることにより上層部の舗装時に溝が容易
に作成される。
Further, in the finisher according to the present invention, the screed for constructing the lower layer is suspended from the vehicle body via the first bearing arm, and the central portion of the vehicle body is lowered downward from the vehicle body via the second bearing arm. The projecting screed for construction of the upper layer is positioned behind the screed for construction of the lower layer and suspended, and paving material is supplied to each screed and leveled, and to the screed for construction of the upper layer from both sides. Pavement material is supplied, and a screed for construction of the lower layer and a screed for construction of the upper layer are provided independently of each other on the vehicle body, and the screed for construction of the upper and lower layers is supplied with the pavement material and leveled. As a result, the lower layer pavement and the upper layer pavement are simultaneously performed. Further, since the central portion of the screed for constructing the upper layer projects downward and the pavement material is supplied to the screed for constructing the upper layer from both sides, a groove can be easily created during paving of the upper layer.

【0008】[0008]

【実施例】図1は本発明の一実施例に係るフィニッシャ
ーの説明図である。図において、本実施例に係るフィニ
ッシャーは、RCC(Roller Compacted Concrete:超固
練りコンクリート)材を路盤に敷き固めて鉄道用軌道を
舗装する場合などに使用されるもので、下層部施工用と
上層部施工用の2つのスクリード4a,4bを車体1に
懸吊した状態で取付けることにより、折り返すことなく
一方向の走行だけで道床を所定の厚さに舗装するととも
に、施工時に枕木設置用の溝も作成するようになってい
る。即ち、図に示すように本フィニッシャーの下層施工
部にはスクリード4aがレベリングアーム3aを介して
履帯9のフレーム部に取付けられており、その間に面圧
を調整するスクリードシリンダ5aが取付けられてい
る。また、上層施工部にはスクリード4bがレベリング
アーム3bを介して車体1および車体1に剛結されたリ
ブ8に取付けられており、その間に面圧を調整するスク
リードシリンダ5bが取付けられている。本フィニッシ
ャーのフィーダは3列からなり、下層部施工用のフィー
ダ7aは車体1中央に、上層部施工用のフィーダ7bは
下層部施工用のフィーダ7aの両側に設けられている。
また、舗装材を広げるスクリューは2つのスクリュー6
a,6bから構成されており、前段スクリュー6aは車
体1中央から両側へRCC材を広げるように回転し、後
段スクリュー6bは車体1両側から中央へRCC材を広
げるように回転する。上層部施工用のスクリード4bは
枕木設置用の溝を施工時に作成することができるように
3分割されており、中央のスクリード4b1 が所定の高
さだけ低くなっている。図における符号4b2 は両端の
スクリード、10は車輪である。
1 is an explanatory view of a finisher according to an embodiment of the present invention. In the figure, the finisher according to the present embodiment is used for laying an RCC (Roller Compacted Concrete) material on a roadbed to pave a railway track, for example, for lower layer construction and upper layer construction. By installing the two screeds 4a and 4b for partial construction on the vehicle body 1 in a suspended state, the roadbed is paved to a predetermined thickness by running in only one direction without folding back, and a groove for installing sleepers at the time of construction. Is also created. That is, as shown in the figure, the screed 4a is attached to the frame portion of the crawler belt 9 via the leveling arm 3a in the lower layer construction portion of the finisher, and the screed cylinder 5a for adjusting the surface pressure is attached therebetween. . A screed 4b is attached to the vehicle body 1 and a rib 8 rigidly connected to the vehicle body 1 via a leveling arm 3b in the upper layer construction portion, and a screed cylinder 5b for adjusting the surface pressure is attached therebetween. The feeder of this finisher is composed of three rows, the feeder 7a for lower layer construction is provided in the center of the vehicle body 1, and the feeder 7b for upper layer construction is provided on both sides of the feeder 7a for lower layer construction.
In addition, the screw that spreads the paving material is two screws 6
The front stage screw 6a rotates so as to spread the RCC material from the center of the vehicle body 1 to both sides, and the rear stage screw 6b rotates so as to spread the RCC material from both sides of the vehicle body 1 to the center. Screed 4b for the upper portion construction is divided into three so as to be able to create a groove for sleepers installed at time of construction, the center of the screed 4b 1 is lower by a predetermined height. Reference numeral 4b 2 in the figure denotes screeds at both ends, and 10 denotes wheels.

【0009】ホッパー2に供給されたRCC材は下層部
施工用のフィーダ7aおよび上層部施工用のフィーダ7
bにより前段、後段スクリュー6a,6bに分配され
る。前段スクリュー6aはRCC材を鉄道用軌道の中央
から両端へ、後段スクリュー6bは両端から中央へ広げ
るように回転し、上下各層とも幅方向に均等にRCC材
が供給される。そして、このRCC材を下層部、上層部
施工用のスクリード4a,4bが独立して締固め、上層
部施工時には枕木設置用の溝も作成する。即ち、下層部
の舗装は、ホッパー2の中央から送られて来るRCC材
が前段スクリュー6aにより車体1中央から両側へ広げ
られた後、下層部施工用のスクリード4aにより締め固
められる。また、上層部の舗装は、ホッパー2の両端か
ら送られて来るRCC材が後段スクリュー6bにより車
体1両端から内側へ広げられた後、上層部施工用のスク
リード4bにより締め固められる。また、舗装時におけ
る押圧力の調節はスクリードシリンダ5a,5bの圧力
を調節することにより、レベリングアーム3a,3bを
介してスクリード4a,4bの面圧が調節される。ま
た、枕木設置用の溝の施工はRCC材が車体1両端から
内側へ広げられた後、上層部施工用のスクリード4bが
3分割されて低く設けられている中央のスクリード4b
1 により溝を作りながら締固める。ホッパー2に供給さ
れたRCC材は下層部施工用のフィーダ7aおよび上層
部施工用のフィーダ7bにより上下各層の施工に必要な
量が前段、後段スクリュー6a,6bに分配される。
The RCC material supplied to the hopper 2 is a feeder 7a for lower layer construction and a feeder 7 for upper layer construction.
It is distributed to the front and rear screws 6a and 6b by b. The front-stage screw 6a rotates so as to spread the RCC material from the center to both ends of the railroad track, and the rear-stage screw 6b rotates so as to spread from both ends to the center, so that the RCC material is uniformly supplied in the width direction in each of the upper and lower layers. Then, the screeds 4a and 4b for constructing the lower layer portion and the upper layer portion are independently compacted from this RCC material, and a groove for installing sleepers is also created at the time of constructing the upper layer portion. That is, in the pavement of the lower layer portion, the RCC material sent from the center of the hopper 2 is spread from the center of the vehicle body 1 to both sides by the front stage screw 6a, and then compacted by the screed 4a for construction of the lower layer portion. Further, in the pavement of the upper layer portion, the RCC material fed from both ends of the hopper 2 is spread inward from both ends of the vehicle body 1 by the rear stage screws 6b, and then compacted by the screed 4b for constructing the upper layer portion. Further, the pressure of the screed cylinders 5a, 5b is adjusted by adjusting the pressure of the screed cylinders 5a, 5b during paving so that the surface pressure of the screeds 4a, 4b is adjusted via the leveling arms 3a, 3b. In addition, in order to construct the groove for installing the sleepers, after the RCC material is spread inward from both ends of the vehicle body 1, the screed 4b for constructing the upper layer is divided into three, and the screed 4b at the center is provided low.
1. Compact while making a groove. The RCC material supplied to the hopper 2 is distributed by the feeder 7a for construction of the lower layer and the feeder 7b for construction of the upper layer to the pre- and post-stage screws 6a, 6b in an amount necessary for construction of the upper and lower layers.

【0010】RCC材を用いて鉄道用軌道を舗装する場
合は25cm程度の厚さが必要であるが、従来のフィニッ
シャーを用いてRCC材を敷き固める場合の施工厚さは
15cm程度が限界で、鉄道用軌道として所要の強度およ
び精度を出すためには上下2層に分割して施工する必要
がある。従って、舗装に要する時間が倍になり、また材
料の供給や他の作業用機械による運搬なども一方向から
アクセスすることができない。なお、コンクリート専用
のフィニッシャーはタンパの打撃音が大きく、夜間に民
家の近くで施工する軌道工事などには騒音、振動などの
面で使用することができないが、本フィニッシャーにお
いては従来のフィニッシャーのスクリードと同じスクリ
ードを用いて下層部施工用と上層部施工用との2つのス
クリード4a,4bを作り、車体1にレベリングアーム
3a,3bを介して懸吊された状態で取付けて1回の施
工で道床を所定の厚さに舗装するとともに上層部の施工
時に枕木設置用の溝も作成することができるように上層
部施工用のスクリード4bを3分割して中央のスクリー
ド4b1 は両端のスクリード4b2 よりも所定の高さだ
け低くし、また2つのスクリード4a,4bが独立して
締め固めを行うようにホッパー2から供給されるRCC
材を前段の下層部施工用のスクリード4aと後段の上層
部施工用のスクリード4bとに分配して供給できるよう
にフィーダ7a,7b,7bを3列にしており、フィー
ダ7a,7bからのRCC材を広げる方向が相反する2
つの前段スクリュー6aと後段スクリュー6bとにより
RCC材が幅方向に均等に分配されて下層部および上層
部施工用2つのスクリード4a,4bにより1回の施工
で上下各層を舗装することができる。また、上層部施工
用のスクリード4bが3分割されていることにより枕木
設置用の溝も同時に施工することができる。
When paving a railroad track using RCC materials, a thickness of about 25 cm is required. However, when laying and hardening RCC materials using a conventional finisher, the construction thickness is about 15 cm. In order to obtain the required strength and accuracy as a railroad track, it is necessary to construct it by dividing it into upper and lower two layers. Therefore, the time required for paving is doubled, and the supply of materials and transportation by other working machines cannot be accessed from one direction. The dedicated finisher for concrete has a large tampering noise and cannot be used in terms of noise, vibration, etc. for track construction etc. that is performed near a private house at night, but with this finisher, the screed of the conventional finisher is used. Two screeds 4a and 4b for lower layer construction and upper layer construction are made using the same screed, and are attached to the vehicle body 1 in a suspended state via the leveling arms 3a and 3b, so that the screed can be constructed once. The screed 4b for construction of the upper layer is divided into three parts so that the groove for installing sleepers can be created at the same time as paving the roadbed to a predetermined thickness, and the screed 4b 1 at the center is the screed 4b at both ends. and a predetermined height than 2 low and two screed 4a, R that 4b is supplied from the hopper 2 as independently perform compaction CC
The feeders 7a, 7b, 7b are arranged in three rows so that the material can be distributed and supplied to the screed 4a for constructing the lower layer of the preceding stage and the screed 4b for constructing the upper layer of the latter stage, and the RCC from the feeders 7a, 7b is used. The directions to spread the material are opposite 2
The RCC material is evenly distributed in the width direction by the one front-stage screw 6a and the rear-stage screw 6b, and the upper and lower layers can be paved by the single construction by the two screeds 4a and 4b for constructing the lower layer and the upper layer. Moreover, since the screed 4b for constructing the upper layer is divided into three, a groove for installing sleepers can be constructed at the same time.

【0011】[0011]

【発明の効果】本発明に係るフィニッシャーは前記のよ
うに構成されており、下層部の舗装と上層部の舗装とが
同時に行われるので、1回の施工で上下各層の舗装が完
成する。
The finisher according to the present invention is constructed as described above, and the pavement of the lower layer portion and the pavement of the upper layer portion are performed at the same time, so that the pavement of the upper and lower layers is completed by one-time construction.

【図面の簡単な説明】[Brief description of drawings]

【図1】図1(a)は本発明の一実施例に係るフィニッ
シャーの正面図、同図(b)は同図(a)におけるB−
B矢視断面図、同図(c)はその上層部施工用のスクリ
ードの正面図である。
FIG. 1 (a) is a front view of a finisher according to an embodiment of the present invention, and FIG. 1 (b) is B- in FIG. 1 (a).
A sectional view taken in the direction of the arrow B, (c) is a front view of a screed for constructing an upper layer thereof.

【図2】図2は従来のフィニッシャーの正面図である。FIG. 2 is a front view of a conventional finisher.

【符号の説明】[Explanation of symbols]

1 車体 2 ホッパー 3a 下層部施工用のレベリングアーム 3b 上層部施工用のレベリングアーム 4a 下層部施工用のスクリード 4b 上層部施工用のスクリード 4b1 枕木溝施工用のスクリード 4b2 上層部両端施工用のスクリード 5a 下層部施工用のスクリードシリンダ 5b 上層部施工用のスクリードシリンダ 6a 前段スクリュー 6b 後段スクリュー 7a 下層部施工用のフィーダ 7b 上層部施工用のフィーダ 8 リブ 9 履帯 10 車輪1 vehicle body 2 hopper 3a leveling arm for lower layer construction 3b leveling arm for upper layer construction 4a screed for lower layer construction 4b screed for upper layer construction 4b 1 sleeper groove construction screed 4b 2 upper layer both ends construction Screed 5a Screed cylinder for lower layer construction 5b Screed cylinder for upper layer construction 6a Pre-stage screw 6b Rear stage screw 7a Feeder for lower layer construction 7b Feeder for upper layer construction 8 Rib 9 Tracks 10 Wheels

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 車体に第一のベアリングアームを介して
懸吊された下層部施工用のスクリードと、該下層部施工
用のスクリードよりも後方に位置して上記車体に第二の
ベアリングアームを介して懸吊された上層部施工用のス
クリードと、それぞれの上記スクリードへ舗装材を供給
して均す手段とを備えたことを特徴とするフィニッシャ
ー。
1. A screed for constructing a lower layer portion suspended from a vehicle body via a first bearing arm, and a second bearing arm located behind the screed for constructing the lower layer portion on the vehicle body. A finisher comprising: screeds for constructing an upper layer suspended via the above-mentioned screeds; and means for supplying and leveling a paving material to each of the screeds.
【請求項2】 上記上層部施工用のスクリードの央部が
下方へ突出しているとともに上記上層部施工用のスクリ
ードへは両側から舗装材が供給されることを特徴とする
請求項1に記載のフィニッシャー。
2. The pavement material is supplied from both sides to the screed for constructing the upper layer portion while the central portion of the screed for constructing the upper layer portion projects downward. Finisher.
JP15770895A 1995-06-23 1995-06-23 Finisher Withdrawn JPH093821A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15770895A JPH093821A (en) 1995-06-23 1995-06-23 Finisher

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15770895A JPH093821A (en) 1995-06-23 1995-06-23 Finisher

Publications (1)

Publication Number Publication Date
JPH093821A true JPH093821A (en) 1997-01-07

Family

ID=15655643

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15770895A Withdrawn JPH093821A (en) 1995-06-23 1995-06-23 Finisher

Country Status (1)

Country Link
JP (1) JPH093821A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016199908A (en) * 2015-04-09 2016-12-01 国立大学法人 東京大学 Construction method for concrete pavement structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016199908A (en) * 2015-04-09 2016-12-01 国立大学法人 東京大学 Construction method for concrete pavement structure

Similar Documents

Publication Publication Date Title
JP2981180B2 (en) Slip foam paver for road pavement
US20030072613A1 (en) Adjusting arrangement for steerable transport assembly for self-propelled construction vehicle
US4778305A (en) Slip-form paver with laterally moveable paving tool
JP4076118B2 (en) Attached equipment for finishers
DE69130728D1 (en) Asphalt paver
US6715957B2 (en) Paving apparatus with retractable pavement forming assembly
JP2008082147A (en) Asphalt finisher and asphalt paving method using the same
JPH093821A (en) Finisher
US3844670A (en) Method and apparatus for restoring concrete road surfaces
CN110438861B (en) Double-color asphalt pavement structure and construction process thereof
JP2004011347A (en) Apparatus for leveling paving material
JPH0721605Y2 (en) Paver leveling device
JP2586935B2 (en) Construction method and construction equipment of roller compacted concrete pavement
JPH03206201A (en) Method and machine for paving road with rolled concrete
JP3182878U (en) Concrete paving machine
US3905714A (en) Method for restoring concrete road surfaces
JPH0726506A (en) Asphalt pavement construction method and device thereof
JPS6343215Y2 (en)
JP2594711Y2 (en) Pavement compaction equipment
JP3091132B2 (en) Paving method
JP3256049B2 (en) High compaction construction machine
JPS6215290Y2 (en)
JP2523836Y2 (en) Concrete spreader
JPS5841202Y2 (en) leveling device
JPH05195510A (en) Method and device for compacting end of pavement material

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20020903