JPH09235978A - Construction method of shaft by use of immersion block - Google Patents

Construction method of shaft by use of immersion block

Info

Publication number
JPH09235978A
JPH09235978A JP4460096A JP4460096A JPH09235978A JP H09235978 A JPH09235978 A JP H09235978A JP 4460096 A JP4460096 A JP 4460096A JP 4460096 A JP4460096 A JP 4460096A JP H09235978 A JPH09235978 A JP H09235978A
Authority
JP
Japan
Prior art keywords
shaft
block
excavated
soil
blocks
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP4460096A
Other languages
Japanese (ja)
Inventor
Hisashi Tamura
久 田村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SADA KENSETSU KK
Original Assignee
SADA KENSETSU KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SADA KENSETSU KK filed Critical SADA KENSETSU KK
Priority to JP4460096A priority Critical patent/JPH09235978A/en
Publication of JPH09235978A publication Critical patent/JPH09235978A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a construction method excellent in workability and economical efficiency and with less troubles like vibration, noise, slurry treatment, etc., by which a shaft can be constructed by use of relatively simple equipment even in a small space. SOLUTION: A shaft opening is excavated from the ground level down to a depth in which an immersion block 2 can stand for itself and a hanger frame base 3 is installed there. An excavating device 8 is erected through a rotary device 7 or the like. The excavating device 8 is rotated and advanced to a specified depth of the shaft 1 while injecting a solidifying agent like cement milk from the front end to agitate and mix the solidifying agent and the soil. After the excavating device 8 has been pulled out, cylindrical immersion blocks 2 are settled down in the slurry of soil in the excavated hole by making use of the own weight while connecting the blocks one by one. After completed settling of the immersion blocks 2, the solidified soil in the immersion blocks is excavated and discharged and base concrete 14 is placed on the bottom of the shaft 1.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本願発明は、小口径推進工法
用の立坑、マンホール兼用立坑等の施工における沈設ブ
ロックを用いた立坑の施工方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a vertical shaft using a submerged block in the construction of a vertical shaft for a small diameter propulsion method, a vertical shaft for manholes and the like.

【0002】[0002]

【従来の技術および発明が解決しようとする課題】従
来、マンホール兼用立坑において、円筒状のプレキャス
トコンクリート製のブロックを深さ方向に接合したもの
等が用いられている。その場合の用途、需要としては、
内径が900mm以下程度のものがかなりの割合を占めて
いる。
2. Description of the Related Art Heretofore, in a manhole / shaft, a cylindrical precast concrete block joined in the depth direction has been used. In that case, the application and demand
Those having an inner diameter of 900 mm or less account for a considerable proportion.

【0003】従来の施工方法としては、山留めのための
シートパイルを施工し、設置位置を大きく掘り、マンホ
ールブロックの据付け後、まわりを埋め戻し、シートパ
イルを引き抜くといった方法が一般的である。
As a conventional construction method, there is generally used a method of constructing a sheet pile for retaining a mountain, digging the installation position largely, and after installing the manhole block, backfilling the surroundings and pulling out the sheet pile.

【0004】しかし、その場合、掘削のための設備が大
がかりとなり、不経済であるばかりでなく、建物等が密
集している地域では、掘削のための装置の搬入が困難と
なる場合も多い。
However, in that case, the equipment for excavation becomes large and uneconomical, and it is often difficult to carry in the equipment for excavation in an area where buildings and the like are densely packed.

【0005】また、埋め戻し後、シートパイルを引き抜
く際のシートパイルに付着した土砂等の影響等もあり、
そのボリューム分の空隙が圧密沈下の原因となったり、
掘削底部に支持用のH形鋼等を配置し、その上にマンホ
ールを載せるといったことも行われているが、その場合
も隣接建物等に対する沈下の悪影響が生ずる恐れがある
等の問題がある。また、薬液注入等の地盤改良について
は薬液による地下の汚染の問題がある。
[0005] Further, when the sheet pile is pulled out after backfilling, there is also an influence of soil and the like adhering to the sheet pile, and the like.
The voids of that volume may cause consolidation settlement,
An H-section steel or the like for support is arranged at the bottom of the excavation, and a manhole is placed on the H-section steel. However, in this case, there is a problem that the settlement may adversely affect an adjacent building or the like. In addition, there is a problem of underground contamination with chemicals for ground improvement such as injection of chemicals.

【0006】一方、内径が2〜3m程度のマンホール兼
用沈設立坑の施工に適するものとして、本願発明者によ
る筒状の沈設ブロックを順次内部を掘削しながら接合、
沈設して行く施工方法が、特開平6−117176号公
報に記載されている。
On the other hand, as a construction suitable for a manhole-combined sinking pit having an inner diameter of about 2 to 3 m, a tubular sinking block by the inventor of the present application is joined while sequentially excavating the inside,
A construction method for digging is described in JP-A-6-117176.

【0007】しかし、通常、最下段の沈設ブロックに刃
口を設ける必要があり、特殊な製品となることからコス
トが高く付いたり、また地下水位が高い場合等、ボイリ
ング等による掘削底部からの水の浸入に対する対策が必
要であるといった問題がある。また、一般部についても
筒状ブロックとして市販のものが利用しにくいため、コ
ストパーフォーマンス等の面からも適用条件が限定され
ている。
[0007] Normally, however, it is necessary to provide a blade opening in the bottommost submerged block, which is a special product, which adds to the cost, and when the groundwater level is high, the water from the bottom of the excavation due to boiling etc. There is a problem that measures against the intrusion of Moreover, since it is difficult to use a commercially available cylindrical block for the general portion, the application conditions are limited in terms of cost performance and the like.

【0008】本願発明は、需要の多い小口径の立坑の施
工に適し、狭隘な場所でも比較的簡易な設備で施工で
き、振動、騒音、泥水処理等の問題の少ない施工性、経
済性に優れた沈設ブロックを用いた立坑の施工方法を提
供することを目的としている。
INDUSTRIAL APPLICABILITY The present invention is suitable for construction of a shaft with a small diameter, which is in great demand, can be constructed by a relatively simple facility even in a narrow place, and has excellent workability and economical efficiency with less problems such as vibration, noise and muddy water treatment. The purpose of the present invention is to provide a method for constructing a vertical shaft using a submerged block.

【0009】[0009]

【課題を解決するための手段】本願発明の沈設ブロック
を用いた立坑の施工方法は、上述のように比較的小口径
の立坑の施工に適するものであり、まず立坑設置位置を
掘削装置で原地盤の土砂に固化材を注入混合してスラリ
ー化させながら所定深さまで掘削して行く。そして、掘
削装置を引き抜いた後、筒状の沈設ブロックを順次深さ
方向に接合しながら、自重を利用して坑口より土砂と固
化材が混合されてスラリー化している掘削孔内に沈設し
て行き、沈設完了後、沈設ブロック内の硬化した土砂を
再度掘削排除することで、立坑の構築を行うものであ
る。
The method for constructing a vertical shaft using the sinking block of the present invention is suitable for constructing a vertical shaft having a relatively small diameter as described above. A solidifying material is poured into and mixed with the earth and sand to form a slurry, which is excavated to a predetermined depth. Then, after pulling out the excavation device, while sequentially joining the cylindrical sunk blocks in the depth direction, by using the self-weight to deposit the sediment and the solidifying material from the pit into the slurry in the excavation hole After the completion of the digging, the shaft is constructed by excavating and removing the hardened soil in the sunk block again.

【0010】沈設ブロックとしては、市販されている1
号人孔用の内径900mmの円筒状のプレキャストコンク
リート製のものが安価に利用できるが、寸法、形状、材
質とも必ずしもこれに限定されない。
As the submerged block, a commercially available 1
A cylindrical precast concrete with an inner diameter of 900 mm for a person's hole can be inexpensively used, but the size, shape, and material are not necessarily limited thereto.

【0011】固化材としては、地下汚染等の問題の生じ
にくいセメントミルクその他、セメント系のものが一般
的であり、土砂と攪拌混合してスラリー化した状態で沈
設ブロックが自重を利用して沈設できる程度とする。
The solidifying material is generally cement milk or other cement-based material which does not easily cause problems such as underground pollution, and the settling block is settling by utilizing its own weight in a state of stirring and mixing with earth and sand to form a slurry. It is possible.

【0012】また、施工工程との関係で、硬化時間を比
較的長くとる必要があり、1つの立坑について沈設ブロ
ックの設置が完了する例えば1〜2日の間、ブロックの
沈設が容易である程度の状態を維持できる配合を行う。
[0012] In addition, it is necessary to take a relatively long curing time in relation to the construction process, and it is easy to lay down the blocks for a period of 1-2 days when the installation of the laid blocks is completed for one vertical shaft. Formulate to maintain the condition.

【0013】攪拌式の掘削装置としては、回転シャフト
の先端に攪拌翼を備え、シャフト内を通じて攪拌翼部分
からセメントミルク等の固化材を噴出させる攪拌式もの
が一般的であるが、これについても種々の形式のものが
利用可能である。
As a stirring type excavating device, a stirring type generally equipped with a stirring blade at the tip of a rotating shaft and ejecting a solidifying material such as cement milk from the stirring blade portion through the shaft is also common. Various types are available.

【0014】接合した沈設ブロックを必要数、所定深さ
まで沈設したら、沈設ブロックがそれ以上沈下しないよ
うにして(例えば坑口で高さ調整部材を兼ねた鋼棒等で
吊り支持しておく)、固化材を混合した土砂の養生を行
い、沈設ブロック内部について、あらためてミニクラム
シェルあるいはオーガー等を利用して掘削、排土を行
う。
After the required number of joined submerged blocks have been submerged to a predetermined depth, the submerged blocks are prevented from further sinking (for example, suspended and supported by a steel rod or the like also serving as a height adjusting member at the wellhead) and solidified. The soil mixed with the material is cured, and the inside of the sunk block is excavated and discharged again using the mini clam shell or auger.

【0015】なお、沈設にあたり事前にブロック内壁に
親水性ウレタン剤を塗布、乾燥したブロックをスラリー
の中に沈下することにより、親水性ウレタンと水が反応
膨潤するため、固化材は内壁に固着することなく容易に
排除できる。
It should be noted that the hydrophilic urethane agent is applied to the inner wall of the block before the deposition, and the dried block is submerged in the slurry, so that the hydrophilic urethane and water react and swell, so that the solidifying material is fixed to the inner wall. Can be easily eliminated without

【0016】また、沈設ブロックの外壁面については、
固化材を混合した土砂の硬化により空隙を生ずることな
く強度が得られ、周囲に地盤沈下などの悪影響を及ぼす
心配がない。
Regarding the outer wall surface of the submerged block,
By hardening the soil mixed with the solidifying material, strength can be obtained without generating voids, and there is no fear of adverse effects such as ground subsidence.

【0017】本願の請求項2は、上記の施工方法を適用
する立坑底部の地盤が軟弱な場合において、立坑に対す
る支持力を確保し、立坑施工時の下面からのボイリング
等による地下水の浸入を阻止すること等を目的として、
最下段の沈設ブロック位置からさらに所要の深さまで、
例えば300〜1500mm程度を、固化材の注入と原地
盤の土砂との攪拌により必要な支持力が確保できる強度
に地盤改良して、沈設ブロックの設置および立坑底面部
のベースコンクリートの打設を行う場合を限定したもの
である。
According to claim 2 of the present application, when the ground at the bottom of the vertical shaft to which the above-mentioned construction method is applied is soft, a supporting force for the vertical shaft is secured, and intrusion of groundwater due to boiling etc. from the lower surface during vertical shaft construction is prevented. For the purpose of doing
From the bottom sunk block position to the required depth,
For example, about 300-1500 mm is improved to the strength that can secure the necessary supporting force by injecting the solidifying material and stirring with the earth and sand of the original ground, and installing the sunk block and placing the base concrete on the bottom of the shaft. It is a limited case.

【0018】このようにして立坑底部の軟弱な地盤を改
良しつつ、沈設ブロックの設置および立坑下端のベース
コンクリートの打設を行うことで、信頼性の高い確実な
施工が行なえる。
In this way, while improving the soft ground at the bottom of the shaft, by installing the sunk block and placing the base concrete at the lower end of the shaft, reliable and reliable construction can be performed.

【0019】[0019]

【発明の実施の形態】図1は本願発明の施工方法の一実
施形態として、道路下を通る小口径推進工法用の立坑を
構築する場合において、内径が900〜1200mm程度
のプレキャストコンクリート製の沈設ブロック2を用い
た立坑1の構築の様子を示したものである。施工手順に
沿って説明すると、以下のようになる。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 1 is an embodiment of a construction method of the present invention, in which a precast concrete deposit having an inner diameter of about 900 to 1200 mm is constructed in the case of constructing a shaft for a small-diameter propulsion method passing under a road. It shows how the shaft 1 is constructed using the block 2. The following is an explanation along the construction procedure.

【0020】(1) 舗装撤去と自立深さまで仮掘削 立坑施工位置に位置出しマーキングを行い、舗装を撤去
して最下段の沈設ブロック2が自立できる深さまで坑口
部分を地上から掘削する。
(1) Pavement removal and temporary excavation up to the self-sustaining depth Positioning marking is performed at the vertical shaft construction position, the pavement is removed, and the wellhead portion is excavated from the ground to a depth at which the lowest sunk block 2 can stand on its own.

【0021】(2) ハンガー架設台の据付け(以上、図1
(a) 参照) 坑口にハンガー架設台3を架け渡し、その外側には施工
休止時や養生時に坑口を覆う覆工板を架設するための覆
工板受梁4を設置する。
(2) Installation of the hanger erection table (above, Fig. 1
(See (a)) The hanger erection table 3 is laid over the wellhead, and a lining plate support beam 4 for erection of a lining board that covers the wellhole at the time of construction suspension or curing is installed on the outside of the hanger erection platform 3.

【0022】図2は坑口のハンガー架設台3、覆工板受
梁4および覆工板5等の位置関係を示したもので、四隅
には吊り上げるための吊り金具6が設けられている。
FIG. 2 shows the positional relationship among the hanger erection table 3, the lining plate receiving beam 4, the lining plate 5 and the like at the wellhead, and hanging fittings 6 for lifting are provided at the four corners.

【0023】(3) 回転装置、グラウトポンプの据付け ハンガー架設台3の上に回転装置7を設置し、またミキ
サーから固化材を送り込むためのグラウトポンプ等の据
付けを行う。
(3) Installation of rotating device and grout pump The rotating device 7 is installed on the hanger installation table 3, and the grout pump for feeding the solidifying material from the mixer is installed.

【0024】(4) 掘削装置の立込み、グラウトホース接
続 先端に掘削ビットや攪拌翼等を設けた掘削装置8を、ラ
フタークレーン9等の比較的簡易なクレーンを用いて、
回転装置7の中心を通して建込み、掘削装置8の中空シ
ャフト内を通って地盤内に固化材を注入するためのグラ
ウトホース10を接続する。
(4) Installation of excavation equipment, connection of grout hose The excavation equipment 8 provided with an excavation bit, a stirring blade, etc. at the tip is used with a relatively simple crane such as a rough terrain crane 9.
The grout hose 10 for injecting the solidifying material into the ground is connected through the hollow shaft of the excavator 8 which is built through the center of the rotating device 7.

【0025】(5) 固化材混合掘削(以上、図1(b) 参
照) 掘削装置8を回転させて先端からセメントミルク等のセ
メント系の固化材を注入しながら所定深さまで、立坑1
の掘削および固化材と土砂の攪拌混合を行う。なお、回
転装置7の油圧モータ7aについては、ラフタークレー
ン9のオイルポートからの油圧で、必要なトルクを与え
ることができる。
(5) Solidified material mixed excavation (see FIG. 1 (b) above) The excavator 8 is rotated to inject a cement-based solidified material such as cement milk from the tip to a predetermined depth until the vertical shaft 1
Excavation and mixing of solidified material and earth and sand with stirring. It should be noted that the hydraulic motor 7a of the rotating device 7 can be given a required torque by the hydraulic pressure from the oil port of the rough terrain crane 9.

【0026】(6) 床付け 軟弱な地盤等では、支持力の確保やボイリング等による
掘削底部からの地下水の浸入を考慮する必要があり、底
部の300〜1500mm程度について、固化材を攪拌翼
部分等から噴出して、土砂と攪拌混合し、その部分の地
盤改良を行う。
(6) Flooring In soft ground, etc., it is necessary to take into consideration the securing of bearing capacity and the infiltration of groundwater from the bottom of the excavation due to boiling, etc. It is spouted from the etc. and mixed with earth and sand by stirring to improve the ground.

【0027】(7) コンクリートブロックの吊り下ろし 掘削装置8を引き上げた後、沈設ブロック2をラフター
クレーン9で吊り支持しつつ、坑口で順次上方の沈設ブ
ロック2を接合しながら、固化材と土砂が混合攪拌され
てスラリー状となっている掘削孔内にゆっくりと沈設し
て行き、最下段の沈設ブロック2の下端が先端処理部1
1内に位置するようにする。
(7) Lifting of concrete block After pulling up the excavation device 8, while suspending and supporting the submerged block 2 with the rough terrain crane 9, the solidified material and the earth and sand are removed while the upper submerged block 2 is being joined at the wellhead. The mixture is agitated and slowly sunk into the excavation hole that is in the form of a slurry.
It should be located within 1.

【0028】(8) 高さ調整鋼棒による固定 接合した沈設ブロック2の高さ調整については、沈設ブ
ロック2の個数と、坑口において最上段の沈設ブロック
2とハンガー架設台3とをつなぐ高さ調整鋼棒12によ
り調整し、位置を固定することができる。なお、最上段
部分については、必要に応じ、図3に示すような鋼製の
円形補助土留13を用いる。この円形補助留13はボル
ト等で沈設ブロック2の上端に固定できるようになって
いる。
(8) Fixing with height-adjusting steel rod For adjusting the height of the submerged blocks 2 joined together, the number of submerged blocks 2 and the height at which the topmost submerged block 2 and the hanger erection platform 3 are connected at the wellhead The position can be fixed by adjusting with the adjusting steel rod 12. In addition, as for the uppermost part, a circular circular auxiliary soil retaining piece 13 made of steel as shown in FIG. 3 is used if necessary. The circular auxiliary fastener 13 can be fixed to the upper end of the submerged block 2 with a bolt or the like.

【0029】(9) 養生 1〜3日程度養生し、固化材を混合した土砂を硬化させ
る。
(9) Curing: Curing is carried out for about 1 to 3 days to cure the earth and sand mixed with the solidifying material.

【0030】(10)立坑内掘削、残土処理 沈設ブロック2によって構成される立坑1内を再度掘削
し、土砂を排除する。
(10) Vertical shaft excavation and residual soil treatment The vertical shaft 1 constituted by the submerged block 2 is excavated again to remove the earth and sand.

【0031】(11)ベースコンクリート打設(以上、図1
(c) 参照) 立坑1の底部にベースコンクリート14を打設し、立坑
1の構築が完了する。
(11) Placing of base concrete (above, Fig. 1
(See (c)) The base concrete 14 is placed at the bottom of the shaft 1 to complete the construction of the shaft 1.

【0032】図4は本願発明の施工方法の他の実施形態
を示したもので、施工方法における施工条件や基本的な
構成は図1の実施形態と同様である。
FIG. 4 shows another embodiment of the construction method of the present invention. The construction conditions and basic structure of the construction method are the same as those of the embodiment of FIG.

【0033】この例では、第1工程として、掘削装置8
で直径300mmの削孔を行い(図4(a) 参照)、第2工
程として掘削装置8に攪拌翼8aを取り付けて、直径1
300mmの削孔を行い、掘削装置8の引き上げの際に攪
拌翼8aの上面から固化材を噴出させながら土砂との攪
拌混合を行う(図4(b) 参照)。
In this example, as the first step, the excavator 8
Drilling with a diameter of 300 mm (see Fig. 4 (a)) was carried out, and as a second step, the stirring blade 8a was attached to the excavator 8 and
A hole of 300 mm is drilled, and when the drilling device 8 is pulled up, the solidified material is jetted from the upper surface of the stirring blade 8a while stirring and mixing with the earth and sand (see FIG. 4 (b)).

【0034】掘削装置8の支持はラフタークレーンある
いは建柱機等で行うことができる。図4(c) では坑口部
分にガイドとなる振止め15を設置し、掘削装置8のシ
ャフトを回転させて掘削を行い、スイベル16を介し
て、固化材や水等を掘削装置8のシャフト内を通して供
給できるようになっている。
The excavation device 8 can be supported by a rough terrain crane or a construction pole machine. In FIG. 4 (c), a swing stop 15 serving as a guide is installed at the wellhead portion, and the shaft of the excavator 8 is rotated to excavate, and the solidified material, water, and the like are fed into the shaft of the excavator 8 via the swivel 16. Can be supplied through.

【0035】図5は立坑底部の地盤が軟弱な場合におけ
る掘削底部の処理に関し、立坑1全体の概要を示したも
のである。
FIG. 5 shows an outline of the shaft 1 as a whole concerning the treatment of the excavation bottom when the ground at the bottom of the shaft is soft.

【0036】この例では図に示すように最下段の沈設ブ
ロックの先端からL(=300mm〜1500mm)の深さ
について、固化材の注入と原地盤の土砂との攪拌混合に
よる地盤改良を行い、この部分に必要な支持力を与えて
いる。
In this example, as shown in the figure, at a depth of L (= 300 mm to 1500 mm) from the tip of the lowermost submerged block, the ground is improved by injecting the solidifying material and stirring and mixing with the soil of the original ground, It gives the necessary support to this part.

【0037】沈設ブロック2の沈設深さに関する位置決
めは、坑口の高さ調整鋼棒12によって行い、沈設ブロ
ック内の硬化した土砂を掘削排除した後、ベースコンク
リート14を打設する。
Positioning of the submerged block 2 with respect to the submerged depth is carried out by the height adjusting steel rod 12 of the wellhead, and after excavating the hardened earth and sand in the submerged block, the base concrete 14 is placed.

【0038】[0038]

【発明の効果】 立坑の径よりわずかに大きい程度の最小限の掘削で沈
設ブロックの沈設を行うことができるため、簡易な設備
で効率良く施工を行うことができる。
[Effects of the Invention] Since the submerged block can be laid down by the minimum excavation which is slightly larger than the diameter of the vertical shaft, the construction can be carried out efficiently with simple equipment.

【0039】圧密沈下その他、周辺地盤に与える影響
がほとんどなく、またほとんど無騒音、無振動の施工が
可能である。また、薬液注入による地盤改良のような地
盤の汚染の心配もない。
There is almost no effect on the surrounding ground such as consolidation settlement, and there is almost no noise and no vibration. In addition, there is no need to worry about soil contamination such as ground improvement due to injection of a chemical solution.

【0040】掘削その他の設備も非常に簡易なものが
利用でき、経済的である。また、狭隘な場所での施工も
可能である。
Very simple drilling and other equipment can be used, which is economical. It is also possible to work in narrow places.

【0041】特に、小口径の立坑の掘削においては、
無駄がなく、迅速かつ経済的な施工が可能である。
In particular, when excavating a small-diameter vertical shaft,
There is no waste and quick and economical construction is possible.

【0042】請求項2に係る発明の場合、軟弱地盤
で、地下水位が高い場合等でも掘削底部からの水の浸入
を抑え、効率の良い施工が可能であるとともに、支持力
が確保され、掘削底部にヘドロ等が生じず、品質の良い
立坑が構築できる。
In the case of the invention according to claim 2, even in the case of soft ground and high groundwater level, the intrusion of water from the bottom of the excavation is suppressed, efficient construction is possible, and the supporting force is secured, and excavation is ensured. No sludge is generated on the bottom, and a high-quality shaft can be constructed.

【図面の簡単な説明】[Brief description of drawings]

【図1】(a) 〜(c) は本願発明の施工方法の一実施形態
における施工手順を示す鉛直断面図である。
1A to 1C are vertical sectional views showing a construction procedure in an embodiment of a construction method of the present invention.

【図2】回転装置や覆工板を備える坑口の構造の概要を
示したもので、(a)は平面図、(b) は鉛直断面図であ
る。
FIG. 2 shows an outline of the structure of a wellhead equipped with a rotating device and a lining plate, (a) is a plan view and (b) is a vertical sectional view.

【図3】立坑の最上段に設置した円形補助土留の一例を
示したもので、(a)は平面図、(b) は鉛直断面図であ
る。
FIG. 3 shows an example of a circular auxiliary soil retention installed at the uppermost stage of the shaft, where (a) is a plan view and (b) is a vertical sectional view.

【図4】(a) 〜(c) は本願発明の施工方法の他の実施形
態における施工手順を示す鉛直断面図である。
4A to 4C are vertical cross-sectional views showing a construction procedure in another embodiment of the construction method of the present invention.

【図5】掘削底部の処理を説明するための鉛直断面図で
ある。
FIG. 5 is a vertical cross-sectional view for explaining the processing of the excavation bottom.

【符号の説明】[Explanation of symbols]

1…立坑、2…沈設ブロック、3…ハンガー架設台、4
…覆工板受梁、5…覆工板、6…吊り金具、7…回転装
置、7a…油圧モータ、8…掘削装置、9…ラフターク
レーン、10…グラウトホース、11…先端処理部、1
2…高さ調整鋼棒、13…円形補助土留、14…ベース
コンクリート、15…振止め、16…スイベル
1 ... Vertical shaft, 2 ... Sinking block, 3 ... Hanger installation stand, 4
... lining plate receiving beam, 5 ... lining plate, 6 ... hanging metal fitting, 7 ... rotating device, 7a ... hydraulic motor, 8 ... excavating device, 9 ... rough terrain crane, 10 ... grout hose, 11 ... tip processing unit, 1
2 ... Height-adjusting steel rod, 13 ... Circular auxiliary soil retaining, 14 ... Base concrete, 15 ... Swing stop, 16 ... Swivel

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 立坑設置位置を掘削装置で原地盤の土砂
に固化材を注入混合してスラリー化させながら所定深さ
まで掘削し、前記掘削装置を引き抜いた後、筒状の沈設
ブロックを順次深さ方向に接合しながら自重を利用して
坑口より前記土砂と固化材がスラリー化した掘削孔内に
沈設して行き、沈設完了後、前記沈設ブロック内の硬化
した土砂を掘削排除することを特徴とする沈設ブロック
を用いた立坑の施工方法。
1. A vertical installation position is excavated to a predetermined depth by pouring and mixing a solidifying material into the earth and sand of an original ground by an excavating device to form a slurry, and after pulling out the excavating device, a cylindrical submerged block is sequentially deepened. It is characterized in that the earth and sand and the solidifying material are sunk into the slurry excavation hole from the pit using its own weight while joining in the vertical direction, and after the completion of the digging, the hardened earth and sand in the sunk block is excavated and removed. A method of constructing a vertical shaft using a submerged block.
【請求項2】 立坑底部の地盤が軟弱な場合において、
最下段の沈設ブロック位置から所要の深さまでを、固化
材の注入と原地盤の土砂との攪拌により必要な支持力が
確保できる強度に地盤改良して、前記沈設ブロックの設
置および立坑底面部のベースコンクリートの打設を行う
ことを特徴とする請求項1記載の沈設ブロックを用いた
立坑の施工方法。
2. When the ground at the bottom of the shaft is soft,
From the bottom sunk block position to the required depth, the ground is improved to the strength that can secure the necessary supporting force by injecting the solidifying material and stirring with the soil of the original ground, and installing the sunk block and the bottom of the shaft. The method for constructing a vertical shaft using a sunk block according to claim 1, wherein base concrete is placed.
JP4460096A 1996-03-01 1996-03-01 Construction method of shaft by use of immersion block Withdrawn JPH09235978A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4460096A JPH09235978A (en) 1996-03-01 1996-03-01 Construction method of shaft by use of immersion block

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4460096A JPH09235978A (en) 1996-03-01 1996-03-01 Construction method of shaft by use of immersion block

Publications (1)

Publication Number Publication Date
JPH09235978A true JPH09235978A (en) 1997-09-09

Family

ID=12695956

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4460096A Withdrawn JPH09235978A (en) 1996-03-01 1996-03-01 Construction method of shaft by use of immersion block

Country Status (1)

Country Link
JP (1) JPH09235978A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102287191A (en) * 2011-06-30 2011-12-21 河北建设勘察研究院有限公司 Large-diameter engineering well wall back filling cementation quick slurry stirring construction method
CN109577990A (en) * 2018-12-24 2019-04-05 中冶建工集团有限公司 A kind of pouring construction method of jacking construction active well

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102287191A (en) * 2011-06-30 2011-12-21 河北建设勘察研究院有限公司 Large-diameter engineering well wall back filling cementation quick slurry stirring construction method
CN109577990A (en) * 2018-12-24 2019-04-05 中冶建工集团有限公司 A kind of pouring construction method of jacking construction active well

Similar Documents

Publication Publication Date Title
JP2008231810A (en) Underground structure construction method
CN110144887A (en) Vast sky stake bored pile construction method
JP3752560B2 (en) Basic structure for constructing a new building in an existing basement and its construction method
JPH05222729A (en) Execution method for cast-in-place concrete pile, etc.
KR101765879B1 (en) Composite block for ground reinforcement and reinforceing method of the foundation bottom using the same
JPH09235978A (en) Construction method of shaft by use of immersion block
JP3827309B2 (en) Auxiliary pile method and embedded pile method
JP2004316118A (en) Immersion method for caisson
JPH10292410A (en) Execution method for small-diameter shaft, connecting method for small-diameter shaft and buried pipe, and connecting method for buried pipe utilizing small-diameter shaft
JPH03257215A (en) Pile constructing method
JP3673171B2 (en) Concrete pile setting method
JP2005139632A (en) Excavation method
JP3890426B2 (en) Group pile construction method, group pile structure and pile holder
CN209620034U (en) Active X-shaped double-row pile foundation pit support structure
JP3108757B2 (en) Pneumatic caisson sinking method
JP2963802B2 (en) How to build an underground parking
JP3297158B2 (en) How to build underwater structures
JP2635934B2 (en) Shaft construction method
JPH1030242A (en) Execution method for small-diameter shaft
JPH0442493B2 (en)
JPH0748818A (en) Construction method for structure
JP2002146775A (en) Diaphragm-wall construction method
JPH01256624A (en) Concrete filling solidification piling method for steel pipe foot protection
JPH1121909A (en) Whole rotational type caisson and immersion method thereof
JP2000178983A (en) Foundation construction method

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20030506