JPH09228476A - Wooden building construction method - Google Patents

Wooden building construction method

Info

Publication number
JPH09228476A
JPH09228476A JP5824096A JP5824096A JPH09228476A JP H09228476 A JPH09228476 A JP H09228476A JP 5824096 A JP5824096 A JP 5824096A JP 5824096 A JP5824096 A JP 5824096A JP H09228476 A JPH09228476 A JP H09228476A
Authority
JP
Japan
Prior art keywords
floor
pillar
panel
laid
horizontal member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP5824096A
Other languages
Japanese (ja)
Inventor
Susumu Moriyama
進 森山
Isao Yoshinaga
功 吉永
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Noda Corp
Original Assignee
Noda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Noda Corp filed Critical Noda Corp
Priority to JP5824096A priority Critical patent/JPH09228476A/en
Publication of JPH09228476A publication Critical patent/JPH09228476A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide a new erection method for a wooden building in which the reduction of the construction period and the costdown are compatible. SOLUTION: Sills are laid on foundations and the first floor panels are laid on the sills and the first floor columns are fitted in fitting notches provided on the first floor panels to erect the first floor columns on the sills. The first floor external wall panels 18 are installed between the first floor columns and the first floor horizontal members are laid on the first floor columns to form the first floor framework. The second floor panels are laid on the first floor horizontal members and the second floor columns are fitted in the fitting notches provided on the second floor panels to erect the second floor columns on the first floor horizontal members. And the second floor external wall panels 24 are installed between the second floor columns and the second floor horizontal members are laid on the second floor columns to form the second floor framework. Roof trusses 16 are laid on the second floor horizontal members and sheathing roof panels 17 are laid thereon.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は木造建築工法に関す
る。
The present invention relates to a wooden construction method.

【0002】[0002]

【従来の技術】特公昭55−6133号公報には、基礎
上に土台、根太を架設して一階床張りを全面的に行い、
次いで柱、梁、桁を建て込んで一階軸組を組み立て、前
記一階の梁、桁に対して腰掛金物を介してその梁、桁と
同一平面をなすように根太を架設して二階床張りを全面
的に行い、次いで柱、梁、桁を建て込んで二階軸組を組
み立て、その上部に屋根材を架設することによる木造建
築工法が提案されている。
2. Description of the Related Art In Japanese Patent Publication No. 55-6133, a foundation and a joist are erected on a foundation, and the first floor is entirely covered with a floor.
Next, pillars, beams, and girders are erected to assemble the first-floor frame, and joists are erected on the first-floor beams and girders through a metal fitting so as to be flush with the beams and girders. A timber construction method has been proposed in which the entire floor is stretched, and then columns, beams and girders are erected to assemble a two-story frame, and a roofing material is erected above the frame.

【0003】この工法は、建築工事のコストダウンおよ
び工期の短縮を図ることができると共に、住宅の質を向
上させることができるものとされている。
This construction method can reduce the cost of construction work and shorten the construction period, and can improve the quality of houses.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、この工
法は、在来の木造軸組建築工法と比較すると、通し柱を
用いない点で建て込みが容易となり、また柱材料として
長尺材を用いる必要がない等の利点を有するものの、腰
掛金物を使い、一階の小梁または大引きを取り付けて根
太を架設するため、該腰掛金物の取付に手間と時間がか
かり、コストを上昇させる欠点を伴う。
However, when compared with the conventional wooden frame construction method, this method is easier to install because it does not use through columns, and it is necessary to use a long material as a column material. Although there are advantages such as not being provided, the use of the stools and the installation of the joists by attaching the small beams or the large pulleys on the first floor require labor and time for mounting the stools, which has the disadvantage of increasing the cost.

【0005】また、床面上にランナーおよび頭継ぎによ
って支持された間柱を建て込み、下地材を取り付けるも
のであるため、材積が増え、これに伴うコスト増も避け
ることができない。
[0005] Further, since a stud supported by a runner and a head joint is erected on the floor surface and a base material is attached, the material volume is increased, and an increase in cost due to this is inevitable.

【0006】[0006]

【課題を解決するための手段】そこで本発明は上記従来
技術の問題点に鑑み、工期短縮とコストダウンを両立さ
せることのできる新規な木造建築工法を提供することを
目的とする。
SUMMARY OF THE INVENTION Accordingly, it is an object of the present invention to provide a novel wooden construction method capable of realizing both a shortened construction period and a reduced cost in view of the above-mentioned problems of the prior art.

【0007】すなわち本発明による木造建築工法は、
(a)基礎上に土台を架設し、(b)一階柱の嵌合用切
り込みが任意箇所に設けられると共に裏面には根太およ
び必要に応じて根太間に断熱材が取り付けられた一階床
パネルを土台上に敷設し、(c)一階床パネルに設けら
れた嵌合用切り込みに一階柱を嵌合して土台上に一階柱
を建て込み、(d)構造用板の裏面に補強桟および必要
に応じて断熱材が、その外周部において土台、一階柱お
よび一階横架材に対する接合用の欠除部を形成するよう
に取り付けられてなる一階外壁パネルを一階柱間に建て
込み、(e)一階柱上に一階横架材を架設して一階軸組
を組み立て、(f)二階柱の嵌合用切り込みが任意箇所
に設けられると共に裏面には根太および必要に応じて根
太間に断熱材が取り付けられた二階床パネルを一階横架
材上に敷設し、(g)二階床パネルに設けられた嵌合用
切り込みに二階柱を嵌合して一階横架材上に二階柱を建
て込み、(h)構造用板の裏面に補強桟および必要に応
じて断熱材が、その外周部において一階横架材、二階柱
および二階横架材に対する接合用の欠除部を形成するよ
うに取り付けられてなる二階外壁パネルを二階柱間に建
て込み、(i)二階柱上に二階横架材を架設して二階軸
組を組み立て、(j)二階横架材上に屋根トラスを架設
した上に野地パネルを敷設する、ことを特徴とする木造
建築工法である。
That is, the wooden building method according to the present invention
(A) First-floor panel in which a foundation is erected on the foundation, (b) notches for fitting the first-floor pillar are provided at arbitrary positions, and a joist on the back surface and, if necessary, a heat insulating material is attached between the joists. Is laid on the base, and (c) the first floor pillar is fitted into the notch for fitting provided on the first floor panel to build the first floor pillar on the base, and (d) the back surface of the structural plate is reinforced. The first-floor outer wall panel, which is attached so as to form a cutout portion for joining to the base, the first-floor pillar, and the first-floor horizontal member at the outer peripheral portion of the crosspiece and the heat insulating material as necessary, is provided between the first-floor pillars. (E) Assemble the first floor horizontal member on the first floor pillar to assemble the first floor framing, and (f) Make a notch for fitting the second floor pillar at any place and have a joist on the back side. According to the above, lay a second floor panel with a heat insulating material installed between the joists on the horizontal material of the first floor, ) The second floor pillar is fitted in the fitting notch provided on the second floor panel, and the second floor pillar is built on the first-floor cross member, and (h) a reinforcing crosspiece and a heat insulating material are provided on the back surface of the structural plate. A second-floor outer wall panel, which is attached so as to form a first-floor horizontal member, a second-floor pillar, and a notch for joining to the second-floor horizontal member at the outer peripheral portion, is built between the second-floor pillars, and (i) the second floor The wooden construction method is characterized in that the second-floor horizontal member is erected on the pillar to assemble a second-floor frame, and (j) the roof truss is erected on the second-floor horizontal member, and then the field panel is laid.

【0008】[0008]

【発明の実施の形態】布基礎、ベタ基礎等の基礎1上に
アンカーボルトの固定により土台2を架設する(図
1)。土台2の補強のために火打ち材を架設し、または
火打ち金物を釘、ボルトあるいはかすがい等によって固
定することができる。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A base 2 is erected on a foundation 1 such as a cloth foundation or solid foundation by fixing anchor bolts (FIG. 1). A fired material can be erected to reinforce the base 2, or a fired metal can be fixed with nails, bolts, scissors, or the like.

【0009】土台2には予め防腐処理を施しておくこと
が好ましい。
It is preferable that the base 2 be subjected to antiseptic treatment in advance.

【0010】土台2の間に大引き3、床束4の施工を行
う。大引き3は土台2にのせ掛けたり、羽子板ボルトや
添え束を用いて、釘打ちまたはビスのねじ込みにより固
定される。床束4は玉石、くつ石等の上に立てられ、釘
打ちにより大引き3に固定され、針金による締め付け、
根がらみぬき、中ぬき、通しぬき等により立設される。
A large pull 3 and a floor bundle 4 are installed between the bases 2. The large pull 3 is mounted on the base 2 or fixed by nailing or screwing a screw using a battledore bolt or a bundle. The floor bundle 4 is erected on a cobblestone, a pebbles stone, etc., fixed to the pulling wire 3 by nailing, tightening with a wire,
It is erected by rooting, hollowing, and threading.

【0011】基礎1がベタ基礎の場合は、大引き3と固
定された床束4の近傍の基礎部分にホールインアンカー
を打ち込み、大引き3に設けられる貫通孔より該ホール
インアンカーにボルトをねじ込み、ナットにて締め付け
ることにより床束4を立設してもよい。
When the foundation 1 is a solid foundation, a hole-in anchor is driven into the foundation portion in the vicinity of the floor bundle 4 fixed to the large pull 3 and a bolt is attached to the hole-in anchor through a through hole provided in the large pull 3. The floor bundle 4 may be erected by screwing in and tightening with nuts.

【0012】このようにして取り付けられた土台2、大
引き3上に一階床パネル5を敷設し、釘の打ち込みやビ
スのねじ込み等によって固定する(図2)。
The first-floor floor panel 5 is laid on the base 2 and the large pull 3 thus attached, and fixed by nailing, screwing in screws or the like (FIG. 2).

【0013】一階床パネル5は、板材6の裏面に根太7
および必要に応じて該根太間に断熱材8が取り付けられ
てなる(図12、図13)。板材6には合板、繊維板、
パーティクルボード等を用いることができる。断熱材8
としては無機繊維板、無機繊維マット、合成樹脂発泡板
等を用いることができる。
The floor panel 5 on the first floor has a joist 7 on the back surface of the plate 6.
And the heat insulating material 8 is attached between the joists as needed (FIG. 12, FIG. 13). Plywood, fiberboard,
A particle board or the like can be used. Insulation 8
As the material, an inorganic fiber board, an inorganic fiber mat, a synthetic resin foam board, or the like can be used.

【0014】このように一階床パネル5には予め根太7
および断熱材8が一体に設けられているため、根太およ
び断熱材の施工が不要となり、工期の短縮が図られる。
In this way, joists 7 are previously attached to the floor panel 5 on the first floor.
And since the heat insulating material 8 is integrally provided, it is not necessary to construct the joists and the heat insulating material, and the construction period can be shortened.

【0015】根太7を板材6の側縁端より張り出して取
り付け、その張り出し部7’において釘打ちすることに
より床パネル5を土台2や大引き3に固定するよう構成
することができる(図12)。この場合には、張り出し
部7’を利用して床パネル5を釘打ち固定した後に、板
材6の側縁端より張り出している部分に別のパネル(図
示せず)を嵌合固定して閉塞する。根太7に張り出しを
設けない場合(図13)には、板材6の上から直に釘打
ちを行う。
It is possible to fix the floor panel 5 to the base 2 or the large pull 3 by attaching the joist 7 by projecting from the side edge of the plate member 6 and nailing it at the projecting portion 7 '(FIG. 12). ). In this case, the floor panel 5 is nailed and fixed using the overhanging portion 7 ′, and then another panel (not shown) is fitted and fixed to the portion overhanging from the side edge of the plate member 6 to close it. To do. When the joist 7 is not provided with an overhang (FIG. 13), nailing is performed directly from above the plate member 6.

【0016】図12および図13においては図示省略さ
れているが、一階床パネル5の任意箇所には一階柱10
を嵌合するための切り込み9が設けられる(図2)。一
階床パネル5の切り込み9形成箇所においては根太7が
土台2上に載置されないことになるため、土台2のサイ
ドに根太受け(図示せず)を取り付けた後に一階床パネ
ル5の敷設を行う。
Although not shown in FIGS. 12 and 13, the first-floor pillar 10 is provided at an arbitrary position on the first-floor floor panel 5.
A notch 9 is provided to fit in (FIG. 2). Since the joists 7 are not placed on the foundation 2 at the cut 9 forming portion of the first floor panel 5, the floor floor panel 5 is laid after the joists (not shown) are attached to the sides of the foundation 2. I do.

【0017】次いで、敷設された一階床パネル5の上を
作業場所として、プレカットされた一階柱10を切り込
み9に嵌合して建て込みを行う(図3)。一階柱10と
土台2には短ほぞ差し等の仕口加工が施されて建て込み
が行われると共に、かすがいや短ざく金物等の金物を用
いて固定され補強される。
Next, the pre-cut first-floor pillar 10 is fitted into the notch 9 to be installed using the laid first-floor panel 5 as a work place (FIG. 3). The first-floor pillar 10 and the base 2 are subjected to joint processing such as short mortice and built-in, and are fixed and reinforced by using metal objects such as braces and short metal objects.

【0018】建て込みの完了した一階柱10間に一階外
壁パネル18を建て込む(図4)。一階外壁パネル18
は、構造用板19の裏面に任意数の補強桟20および必
要に応じて断熱材21が、その外周部において土台2、
一階柱10および後に架設される一階横架材11に対す
る接合用の欠除部22を形成するように取り付けられて
なるものであり、その構成例が図14に示されている。
構造用板19には合板、繊維板、パーティクルボード等
が用いられ、断熱材21には無機繊維板、無機繊維マッ
ト、合成樹脂発泡板等が用いられる。
An outer wall panel 18 on the first floor is built between the pillars 10 on which the first floor has been built (FIG. 4). First floor exterior wall panel 18
Is an arbitrary number of reinforcing bars 20 and optionally a heat insulating material 21 on the back surface of the structural plate 19, and the base 2,
It is attached so as to form a notch 22 for joining to the first-floor pillar 10 and the first-floor horizontal member 11 to be installed later, and a configuration example thereof is shown in FIG.
Plywood, fiber board, particle board, etc. are used for the structural board 19, and inorganic fiber board, inorganic fiber mat, synthetic resin foam board, etc. are used for the heat insulating material 21.

【0019】一階外壁パネル18には予め補強桟20お
よび断熱材21が一体に取り付けられているため、補強
桟(間柱)および断熱材の施工が不要となり、工期の短
縮が図られる。
Since the reinforcing bar 20 and the heat insulating material 21 are integrally attached to the outer wall panel 18 of the first floor in advance, it is not necessary to install the reinforcing bar (stud) and the heat insulating material, and the construction period can be shortened.

【0020】図14に示される外壁パネル18は、その
裏面における左右(図において上下)の欠除部22に一
階柱10を嵌入し、下端(図において左右のいずれか)
の欠除部22には土台2を嵌入した状態として、構造用
板19の表面より釘打ち固定する。また、補強桟20を
土台2および一階柱10に対して短ざく金物、L形金物
等の金物を用いて固定し補強する。
In the outer wall panel 18 shown in FIG. 14, the first floor columns 10 are fitted in the left and right (upper and lower in the figure) notches 22 on the rear surface thereof, and the lower end (either the left or right in the figure) is inserted.
The base 2 is fitted into the notch 22 and is fixed by nailing from the surface of the structural plate 19. In addition, the reinforcing bar 20 is fixed and reinforced with respect to the base 2 and the first-floor pillar 10 by using a metal fitting such as a short metal fitting or an L-shaped metal fitting.

【0021】図14の構成例では補強桟20が一つの縦
桟として示されているが、横桟として形成してもよく、
縦桟と横桟の両方を設けてもよい。また、補強桟20は
必要に応じて複数本設けることができる。
Although the reinforcing bar 20 is shown as one vertical bar in the configuration example of FIG. 14, it may be formed as a horizontal bar.
Both vertical and horizontal rails may be provided. Further, a plurality of reinforcing bars 20 can be provided if necessary.

【0022】図15は外壁パネル18の他の構成例を示
し、補強桟20の両端に任意長さの駒部材23を取り付
けたものである。駒部材23は断熱材21の木口面と面
一に設けられ、この駒部材23から釘を打ち込みあるい
はビスをねじ込むことにより、欠除部22に嵌入される
土台2、柱10、14、横架材11、15に対して固着
し補強することができる。
FIG. 15 shows another structural example of the outer wall panel 18, in which a piece member 23 having an arbitrary length is attached to both ends of the reinforcing bar 20. The piece member 23 is provided so as to be flush with the ostium surface of the heat insulating material 21, and a nail 2, a screw, or a screw is screwed from the piece member 23 to the base 2, the pillars 10 and 14, which are fitted to the cutout portion 22, and the horizontal bridge. The materials 11 and 15 can be fixed and reinforced.

【0023】外壁パネル18は、その構造用板19の裏
面の欠除部22が土台2および一階柱10と接するよう
に一階柱10間に建て込み、片側の一階柱10に釘打ち
して仮止めを行う。一階柱10は一階床パネル5の切り
込み9に嵌合されると共に仕口により土台2上に建て込
みされている状態であるため、柱間隔の調整が可能であ
り、外壁パネル18の建て込みを容易に行うことができ
る。
The outer wall panel 18 is built between the first floor pillars 10 so that the notch 22 on the back surface of the structural plate 19 contacts the base 2 and the first floor pillars 10, and nailed to the first floor pillars 10 on one side. And temporarily fix it. Since the first-floor pillar 10 is fitted in the notch 9 of the first-floor floor panel 5 and is built on the base 2 by a joint, the pillar interval can be adjusted, and the outer wall panel 18 can be built. Can be easily included.

【0024】次に、一階柱10上に梁、桁、胴差し、火
打ち材等の一階横架材11を架設する(図5)。火打ち
材に代えて火打金物を用いてもよい。一階柱10と一階
横架材11には短ほぞ差し等の仕口加工が施されて架設
が行われると共に、羽子板ボルト、箱金物、短ざく金物
等の金物を用いて固定され補強される。
Next, the first-floor horizontal member 11 such as beams, girders, girders, and fired materials is erected on the first-floor pillar 10 (FIG. 5). A flint metal may be used instead of the flint material. The first floor pillars 10 and the first floor horizontal members 11 are erected by making connections such as short mortises, and are fixed and reinforced by using hardware such as battledore bolts, box metal fittings, and short metal fittings. It

【0025】更に、外壁パネル18を釘打ち、ビスのね
じ込み等によって一階柱10に固定する。また、外壁パ
ネル18の裏面に取り付けられる補強桟20と土台2、
一階柱10および一階横架材11とを短ざく金物、L形
金物等の金物を用いて固定し補強する。
Further, the outer wall panel 18 is fixed to the first floor pillar 10 by nailing and screwing in screws. In addition, the reinforcing bar 20 and the base 2, which are attached to the back surface of the outer wall panel 18,
The first floor pillar 10 and the first floor horizontal member 11 are fixed and reinforced with a metal fitting such as a short metal fitting or an L-shaped metal fitting.

【0026】以上のようにして一階軸組が組み立てられ
る。
The first-order framework is assembled as described above.

【0027】次いで、一階横架材11上に釘の打ち込み
やビスのねじ込み等によって二階床パネル12を敷設固
定する(図6)。二階床パネル12は、一階床パネル5
と同様に、板材の裏面に根太および必要に応じて根太間
に断熱材が取り付けられる(図12、図13参照)と共
に、二階柱14を嵌合するための切り込み13が任意箇
所に設けられてなる。
Next, the second-floor floor panel 12 is laid and fixed on the first-floor cross member 11 by hammering in nails or screwing screws (FIG. 6). The second floor panel 12 is the first floor panel 5
Similarly, a heat insulating material is attached to the back of the plate material between the joists and, if necessary, the joists (see FIGS. 12 and 13), and a notch 13 for fitting the second floor pillar 14 is provided at an arbitrary position. Become.

【0028】一階床パネル5と同様、二階床パネル12
の板材には合板、繊維板、パーティクルボード等が用い
られ、断熱材としては無機繊維板、無機繊維マット、合
成樹脂発泡板等が用いられる。このように二階床パネル
12にも予め根太および必要な場合には更に断熱材が一
体に設けられているため、根太および断熱材の施工が不
要となり、工期の短縮が図られる。
As with the first floor panel 5, the second floor panel 12
As the plate material, plywood, fiber board, particle board, etc. are used, and as the heat insulating material, inorganic fiber board, inorganic fiber mat, synthetic resin foam board, etc. are used. In this way, since the joist and the heat insulating material are further integrally provided in advance on the second floor panel 12 if necessary, the construction of the joist and the heat insulating material becomes unnecessary, and the construction period can be shortened.

【0029】一階床パネル5について前述したように、
根太を板材の側縁端より張り出して取り付ける場合には
該張り出し部を利用して釘打ちを行うことにより二階床
パネル12を横架材11上に固定した後、別のパネルを
嵌合して張り出し部を閉塞する。根太に張り出し部を設
けない場合には、板材の上から直に釘打ちを行う。
As described above for the first-floor floor panel 5,
When the joists are attached by protruding from the side edge of the plate, the second floor panel 12 is fixed on the horizontal member 11 by nailing using the protruding portion, and then another panel is fitted. Block the overhang. If the joists are not provided with overhangs, nail them directly from above the plate.

【0030】また、二階床パネル12の切り込み13形
成箇所においては根太が一階横架材11上に載置されな
いことになるため、一階横架材11に根太受け(図示せ
ず)を取り付けた後に二階床パネル12の敷設を行う。
Further, since joists are not placed on the first-floor horizontal member 11 at the positions where the notches 13 of the second-floor floor panel 12 are formed, a joist receiver (not shown) is attached to the first-floor horizontal member 11. After that, the second floor panel 12 is laid.

【0031】次いで、敷設された二階床パネル12の上
を作業場所として、プレカットされた二階柱14を切り
込み13に嵌合して建て込みを行う(図7)。二階柱1
4と一階横架材11には短ほぞ差し等の仕口加工が施さ
れて建て込みが行われると共に、かすがいや短ざく金物
等の金物を用いて固定され補強される。
Next, using the laid second floor panel 12 as a work place, the precut second floor pillars 14 are fitted into the notches 13 for building (FIG. 7). Upstairs pillar 1
4 and the first-floor horizontal member 11 are subjected to joint processing such as short mortice and built in, and are fixed and reinforced by using metal objects such as braces and short metal objects.

【0032】建て込みの完了した二階柱14間に二階外
壁パネル24を建て込み、更に二階横架材15を架設す
る(図8)。二階外壁パネル24の建て込み、および二
階横架材15の架設は、前述した一階柱10間への一階
外壁パネル18の建て込み(図4)と同様にして行われ
る。
The second-floor outer wall panel 24 is built between the second-floor pillars 14 that have been built, and the second-floor horizontal member 15 is installed (FIG. 8). The second-floor outer wall panel 24 and the second-floor horizontal member 15 are erected in the same manner as the first-floor outer wall panel 18 (FIG. 4) between the first-floor pillars 10 described above.

【0033】二階外壁パネル24は、一階外壁パネル1
8と同様の構成を有するものであってよく、構造用板の
裏面に任意数の補強桟および必要に応じて断熱材が、そ
の外周部において一階横架材11、二階柱14および二
階横架材15に対する接合用の欠除部を形成するように
取り付けられてなる(図14および図15参照)。
The outer wall panel 24 on the second floor is the outer wall panel 1 on the first floor.
8 may have the same structure as that of 8, and an arbitrary number of reinforcing bars and optionally a heat insulating material may be provided on the back surface of the structural plate at the outer peripheral portion of the first-floor cross member 11, the second-floor post 14 and the second-floor lateral plate. It is attached so as to form a notch for joining to the frame member 15 (see FIGS. 14 and 15).

【0034】すなわち、二階外壁パネル24は、その構
造用板の裏面の欠除部が一階横架材11および二階柱1
4と接するように二階柱14間に建て込み、片側の二階
柱14に釘打ちして仮止めを行う。二階柱14は二階床
パネル12の切り込み13に嵌合されると共に仕口によ
り一階横架材11上に建て込みされている状態であるた
め、柱間隔の調整が可能であり、二階外壁パネル24の
建て込みを容易に行うことができる。
That is, in the second-floor outer wall panel 24, the notch on the back surface of the structural plate has the first-floor horizontal member 11 and the second-floor pillar 1.
It is built between the second floor pillars 14 so as to contact with 4, and nailed to the second floor pillar 14 on one side to temporarily fix it. Since the second-floor pillar 14 is fitted into the notch 13 of the second-floor floor panel 12 and is built on the first-floor horizontal member 11 by means of a joint, the column spacing can be adjusted, and the second-floor outer wall panel. 24 can be built easily.

【0035】二階横架材15の架設も、前述した一階横
架材11の架設と同様にして行われる。すなわち、二階
柱14上に梁、桁、胴差し、火打ち材(または火打ち金
物)等の二階横架材15を架設するものであり、二階柱
14と二階横架材15には短ほぞ差し等の仕口加工が施
されて架設が行われると共に、羽子板ボルト、箱金物、
短ざく金物等の金物を用いて固定され補強される。そし
て、更に、二階外壁パネル24を釘打ち、ビスのねじ込
み等によって二階柱14に固定すると共に、二階外壁パ
ネル24の裏面に取り付けられる補強桟と一階横架材1
1、二階柱14および二階横架材15とを短ざく金物、
L形金物等の金物を用いて固定し補強する。
The second-floor horizontal member 15 is also erected in the same manner as the first-floor member 11 described above. That is, a second-floor horizontal member 15 such as a beam, a girder, a girder, or a fired material (or a fired metal) is erected on the second-floor pillar 14. The joint processing is applied and the installation is done, and the battledore bolts, box hardware,
It is fixed and reinforced by using metal objects such as short metal parts. Further, the second-floor outer wall panel 24 is nailed and fixed to the second-floor pillar 14 by screwing in screws, and the reinforcing bar and the first-floor horizontal member 1 attached to the back surface of the second-floor outer wall panel 24.
First and second-floor pillars 14 and second-floor horizontal members 15 and metal fittings,
Fix and reinforce by using hardware such as L-shaped hardware.

【0036】二階外壁パネル24にも予め補強桟および
断熱材が一体に取り付けられているため、補強桟(間
柱)および断熱材の施工が不要となり、工期の短縮が図
られる。
Since the reinforcing bar and the heat insulating material are integrally attached to the outer wall panel 24 of the second floor in advance, it is not necessary to install the reinforcing bar (stud) and the heat insulating material, and the construction period can be shortened.

【0037】以上のようにして二階軸組が組み立てられ
る。
The second floor framing is assembled as described above.

【0038】必要に応じて、一階柱10と二階柱14の
必要箇所をホールダウン金具を用いて連結固着する。
If necessary, the first floor pillar 10 and the second floor pillar 14 are fixedly connected to each other by using hole-down fittings.

【0039】次いで、二階横架材15上に屋根トラス1
6を架設する(図9)。屋根トラス16は陸梁、合掌、
真束、方杖、釣り束等を、仕口加工、ボルト締め、箱金
物、短ざく金物、合板あるいは鋼板のガゼットプレート
を用いて組み立てられ、2階横架材15上に架設され、
釘打ちやビスのねじ込み等によって固定される。
Next, the roof truss 1 is mounted on the second floor horizontal member 15.
Install 6 (Fig. 9). The roof truss 16 is a land beam, gassho,
A true bundle, a walking stick, a fishing bundle, etc. are assembled using a joint processing, bolting, box metal fittings, short metal fittings, plywood or steel plate gusset plates, and are erected on the second floor horizontal member 15.
It is fixed by nailing or screwing in screws.

【0040】また、屋根トラス16間に横桟を固着した
り、あおり止め金物、短ざく金物、L形金物、かすがい
等の金物を用いて補強することができる。屋根トラス1
6同士を母屋を用いて架設してもよい。
Further, a horizontal crosspiece can be fixed between the roof trusses 16 and can be reinforced by using an anti-slip hardware, a short metal hardware, an L-shaped metal hardware, a brazing metal hardware or the like. Roof truss 1
You may erect 6 each other using a purlin.

【0041】屋根トラス16は一体ごとに二階横架材1
5上に架設しても、複数体を一ユニットとしてユニット
ごとに架設しても、あるいは屋根として全体を組み立て
た後に架設してもよい。
The roof truss 16 is a second horizontal member 1 for each unit.
5 may be installed, a plurality of units may be installed as one unit for each unit, or a roof may be installed after the whole is assembled.

【0042】屋根トラス16上に野地パネル17を敷設
し(図10)、外装工事が終了する(図11)。
The field panel 17 is laid on the roof truss 16 (FIG. 10), and the exterior work is completed (FIG. 11).

【0043】[0043]

【発明の効果】本発明の木造建築工法によれば、通し柱
を使用せず、一階柱および二階柱の建て込みよりも先に
敷設される一階および二階の床上を作業場所として使え
るため作業性に優れ、工期が大幅に短縮され、雨仕舞い
が良好であり、したがって早期に内装工事に取りかかる
ことができる等の効果を有する。
According to the wooden construction method of the present invention, work can be performed without using through columns, and the first and second floors laid before the first and second floor columns can be used as work places. It has excellent effects, the construction period is significantly shortened, the rain is good, and the interior work can be started early.

【0044】また、材料のサイズが小さく、材積が少な
く、標準化された規格品が用いられるため、大幅なコス
トダウンがなされる。
Further, the size of the material is small, the material volume is small, and standardized standard products are used, so that the cost is greatly reduced.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明による木造建築工法における土台架設工
程を示す斜視図である。
FIG. 1 is a perspective view showing a base erection step in a wooden building method according to the present invention.

【図2】図1の工程に引き続いて行われる一階床パネル
敷設を示す斜視図である。
FIG. 2 is a perspective view showing a first-floor floor panel laying process performed subsequent to the step of FIG.

【図3】図2の工程に引き続いて行われる一階柱建て込
みを示す斜視図である。
FIG. 3 is a perspective view showing a first-floor pillar erection performed subsequent to the step of FIG.

【図4】図3の工程に引き続いて行われる一階横架材架
設を示す斜視図である。
FIG. 4 is a perspective view showing a first-floor horizontal member installation that is performed subsequent to the step of FIG.

【図5】図4の工程に引き続いて行われる二階床パネル
敷設を示す斜視図である。
FIG. 5 is a perspective view showing the second-floor floor panel laying performed subsequent to the step of FIG.

【図6】図5の工程に引き続いて行われる二階柱建て込
みを示す斜視図である。
FIG. 6 is a perspective view showing the second floor pillar erection that is performed subsequent to the step of FIG. 5;

【図7】図6の工程に引き続いて行われる二階横架材架
設を示す斜視図である。
FIG. 7 is a perspective view showing a second-floor horizontal member installation which is performed subsequent to the step of FIG.

【図8】図7の工程に引き続いて行われる屋根トラス建
て込みを示す斜視図である。
8 is a perspective view showing a roof truss erection that is performed subsequent to the step of FIG. 7. FIG.

【図9】図8の工程に引き続いて行われる野地パネル敷
設を示す斜視図である。
9 is a perspective view showing a field panel laying performed following the step of FIG. 8. FIG.

【図10】図9の工程に引き続いて行われる外壁パネル
取付を示す斜視図である。
FIG. 10 is a perspective view showing outer wall panel attachment performed subsequent to the step of FIG.

【図11】図1ないし図10の工程により外装工事が終
了した状態を示す斜視図である。
FIG. 11 is a perspective view showing a state in which the exterior work is completed by the steps of FIGS. 1 to 10.

【図12】床パネルの構成例を示す斜視図である。FIG. 12 is a perspective view showing a configuration example of a floor panel.

【図13】床パネルの他の構成例を示す斜視図である。FIG. 13 is a perspective view showing another configuration example of the floor panel.

【図14】外壁パネルの構成例を示す斜視図である。FIG. 14 is a perspective view showing a configuration example of an outer wall panel.

【図15】外壁パネルの他の構成例を示す斜視図であ
る。
FIG. 15 is a perspective view showing another configuration example of the outer wall panel.

【符号の説明】[Explanation of symbols]

1 基礎 2 土台 5 一階床パネル 6 板材 7 根太 8 断熱材 9 切り込み 10 一階柱 11 一階横架材 12 二階床パネル 13 切り込み 14 二階柱 15 二階横架材 16 屋根トラス 17 野地パネル 18 一階外壁パネル 19 構造用板 20 補強桟 21 断熱材 22 欠除部 23 駒部材 24 二階外壁パネル 1 Foundation 2 Base 5 First-floor panel 6 Board material 7 joist 8 Insulation material 9 Notch 10 First-floor pillar 11 First-floor cross-member 12 Second-floor panel 13 Notch 14 Second-floor pillar 15 Second-floor horizontal material 16 Roof truss 17 Field panel 18-1 Outer-floor wall panel 19 Structural board 20 Reinforcing bar 21 Insulation material 22 Missing part 23 Piece member 24 Second-floor outer wall panel

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】(a)基礎上に土台を架設し、(b)一階
柱の嵌合用切り込みが任意箇所に設けられると共に裏面
には根太および必要に応じて根太間に断熱材が取り付け
られた一階床パネルを前記土台上に敷設し、(c)前記
一階床パネルに設けられた嵌合用切り込みに一階柱を嵌
合して前記土台上に一階柱を建て込み、(d)構造用板
の裏面に補強桟および必要に応じて断熱材が、その外周
部において土台、一階柱および一階横架材に対する接合
用の欠除部を形成するように取り付けられてなる一階外
壁パネルを前記一階柱間に建て込み、(e)前記一階柱
上に一階横架材を架設して一階軸組を組み立て、(f)
二階柱の嵌合用切り込みが任意箇所に設けられると共に
裏面には根太および必要に応じて根太間に断熱材が取り
付けられた二階床パネルを前記一階横架材上に敷設し、
(g)前記二階床パネルに設けられた嵌合用切り込みに
二階柱を嵌合して前記一階横架材上に二階柱を建て込
み、(h)構造用板の裏面に補強桟および必要に応じて
断熱材が、その外周部において一階横架材、二階柱およ
び二階横架材に対する接合用の欠除部を形成するように
取り付けられてなる二階外壁パネルを前記二階柱間に建
て込み、(i)前記二階柱上に二階横架材を架設して二
階軸組を組み立て、(j)前記二階横架材上に屋根トラ
スを架設した上に野地パネルを敷設する、ことを特徴と
する木造建築工法。
Claims: (a) A foundation is laid on a foundation, and (b) notches for fitting a first floor pillar are provided at arbitrary places, and a back joist and a heat insulating material between joists as necessary are attached to the back surface. A first floor panel is laid on the base, and (c) a first floor pillar is fitted into a notch for fitting provided on the first floor panel to build the first floor pillar on the base; ) A reinforcing bar and, if necessary, a heat insulating material are attached to the back surface of the structural plate so as to form a cutout portion for joining to the base, the first floor pillar and the first floor horizontal member at the outer peripheral portion thereof. A floor outer wall panel is built between the first floor pillars, (e) a first floor horizontal member is erected on the first floor pillars to assemble a first floor frame, (f)
Laying a second floor panel with a notch for fitting of the second floor pillar provided at an arbitrary position and a joist on the back surface and a heat insulating material between the joists as necessary, on the first floor horizontal member,
(G) Fitting a second floor pillar into the fitting notch provided in the second floor floor panel to build a second floor pillar on the first floor horizontal member, and (h) a reinforcing bar and a necessary crosspiece on the back surface of the structural board. Accordingly, a heat insulating material is installed between the second-floor pillars so as to form a first-floor lateral cross-member, a second-floor pillar, and a second-floor outer-panel on the outer peripheral portion thereof so as to form a notch for joining to the second-floor horizontal cross-member. And (i) a second-floor horizontal member is erected on the second-floor pillar to assemble a second-floor framework, and (j) a roof truss is erected on the second-floor horizontal member, and a field panel is laid. Wooden construction method to do.
JP5824096A 1996-02-22 1996-02-22 Wooden building construction method Pending JPH09228476A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5824096A JPH09228476A (en) 1996-02-22 1996-02-22 Wooden building construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5824096A JPH09228476A (en) 1996-02-22 1996-02-22 Wooden building construction method

Publications (1)

Publication Number Publication Date
JPH09228476A true JPH09228476A (en) 1997-09-02

Family

ID=13078590

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5824096A Pending JPH09228476A (en) 1996-02-22 1996-02-22 Wooden building construction method

Country Status (1)

Country Link
JP (1) JPH09228476A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102089484B1 (en) * 2019-01-18 2020-03-17 휴센 주식회사 A structure assembly system including a roof module of a wooden building

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102089484B1 (en) * 2019-01-18 2020-03-17 휴센 주식회사 A structure assembly system including a roof module of a wooden building

Similar Documents

Publication Publication Date Title
US4211043A (en) Precast concrete building module form
JPH09228476A (en) Wooden building construction method
JP2973356B2 (en) Wooden construction method
EP0072814B1 (en) A beam-like building component of curable material, a method of manufacturing such a building component, and a method for producing a frame or structure for a building or part of a building with the use of such building material
JPH06346515A (en) Unit building
JPH09228475A (en) Wooden building construction method
JP2973357B2 (en) Wooden construction method
WO2001029338A2 (en) Shear wall panel
JP2003049484A (en) Construction method for wooden house
JP2001220818A (en) Steel framework structure
US20040040255A1 (en) Building method and structure
JPH0734538A (en) Wooden building
JP4456233B2 (en) Horizontal member for building and panel provided with the same
JP3517798B2 (en) Reinforcement metal fittings for wooden structures
JP3247657B2 (en) Construction method of reinforced concrete building
JPH0518404Y2 (en)
JP2504476Y2 (en) Handrail wall mounting structure
JP3048719U (en) Earthquake-resistant hardware for wooden buildings
JPH10183760A (en) Construction method for building
JPH09296542A (en) Frame for prefabricated house, and prefabricated house
JP2002235373A (en) Improving method for conventional means
JPH11303203A (en) Erection method of two-storied wooden house
JPH0616552U (en) Hollow reinforced beam and its bracket
JPH11140975A (en) Frame structure and frame constructing method in residence made of steel
JPH10159234A (en) Roof unit of wooden building and roof structure using the same and construction method thereof