JPH09209687A - Arrival shaft and construction thereof - Google Patents

Arrival shaft and construction thereof

Info

Publication number
JPH09209687A
JPH09209687A JP1663296A JP1663296A JPH09209687A JP H09209687 A JPH09209687 A JP H09209687A JP 1663296 A JP1663296 A JP 1663296A JP 1663296 A JP1663296 A JP 1663296A JP H09209687 A JPH09209687 A JP H09209687A
Authority
JP
Japan
Prior art keywords
shaft
construction
steel pipe
reaching
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP1663296A
Other languages
Japanese (ja)
Inventor
Tatsuo Yoshihara
辰雄 吉原
Hideaki Hirano
秀昭 平野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP1663296A priority Critical patent/JPH09209687A/en
Publication of JPH09209687A publication Critical patent/JPH09209687A/en
Pending legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Earth Drilling (AREA)

Abstract

PROBLEM TO BE SOLVED: To reduce construction precesses of a shaft by eliminating supporting works or the like and reduce the construction period and cost and obtain a reliable strength. SOLUTION: A circular shaft is formed by steel pipes 9 erected at the arrival side, in an arrival shaft in a small diameter shielding or a propulsive work thereof. Steel pipes 9 are erected while adding them, by the whole rotary type power easing jacks in the whole peripheral rotating all easing cast-in-place concrete pile work and the soil inside the steel pipes 9 is excavated and discharged by a hammer grab and after the slime-treatment in the tunnel, a bottom bed concrete is placed to construct the shaft.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、小口径シールド又
は同推進工法などにおける簡易な到達立坑に関するもの
である。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a simple reach shaft in a small-diameter shield or the same propulsion method.

【0002】[0002]

【従来の技術】例えばガス管などを布設する場合、小口
径シールド又は同推進工法が採用されることがある。こ
れは埋設管推進装置などで埋設管としてのガス管を埋設
するが、かかる埋設管の埋設は図9に示すように施工計
画にしたがって発進立坑1と到達立坑2とを予め掘削
し、発進立坑1側に反力体(壁)3を設置し、架台上で
駆動モータや減速機等の掘進機構4を推進ジャッキ5で
前後動できるように設けた推進装置6をセットする。
2. Description of the Related Art When laying a gas pipe, for example, a small-diameter shield or the same propulsion method may be adopted. This is to bury a gas pipe as a burial pipe by a burial pipe propulsion device, etc. The burial of such a burial pipe is performed by previously excavating a starting shaft 1 and a reaching shaft 2 according to a construction plan as shown in FIG. A reaction force body (wall) 3 is installed on the first side, and a propulsion device 6 is provided which is provided on a gantry so that a drive mechanism, a speed reducer, and other excavation mechanism 4 can be moved back and forth by a propulsion jack 5.

【0003】先端にオーガーヘッド7aを備え、内部に
スクリュー軸を貫通させた先導体7を推進装置6で推進
した後、地上でケーシングやスクリュー軸をセットした
埋設管8を先導体7に順次接続しながら、掘進機構4で
スクリュー軸を介してオーガーヘッド7aを回転させ、
掘削土はスクリュー軸により推進装置6側に搬送して排
出し、同時に推進ジャッキ5で全体を押し出して推進し
ていく。
An auger head 7a is provided at the tip, and a front conductor 7 having a screw shaft penetrated therein is propelled by a propulsion device 6, and then a buried pipe 8 having a casing and a screw shaft set on the ground is sequentially connected to the front conductor 7. While rotating the auger head 7a via the screw shaft by the excavation mechanism 4,
The excavated soil is conveyed to the propulsion device 6 side by the screw shaft and discharged, and at the same time, the whole of the propulsion jack 5 is pushed out and propelled.

【0004】先導体7が到達立坑2に達したならば、図
10に示すように到達立坑2から先導体7とオーガーヘッ
ド7aなどを回収し、発進立坑1から推進装置6やスク
リュー、ケーシング、油圧ホースなどを回収する。
If the leading conductor 7 reaches the reaching shaft 2,
As shown in FIG. 10, the front conductor 7 and the auger head 7a are recovered from the reaching shaft 2, and the propulsion device 6, the screw, the casing, the hydraulic hose and the like are recovered from the starting shaft 1.

【0005】このように埋設管推進装置などでガス管な
どの埋設管を埋設する場合、簡易な到達立坑2を必要と
するが、従来の到達立坑2は、例えば親杭・横矢板工
法、シートパイル工法、地中連続壁工法、ライナープレ
ート工法などによって築造していた。
When burying a buried pipe such as a gas pipe with a buried pipe propulsion device as described above, a simple reaching vertical shaft 2 is required, but the conventional reaching vertical shaft 2 is, for example, a parent pile / lateral sheet pile method, a sheet. It was built by the pile method, underground continuous wall method, liner plate method, etc.

【0006】親杭・横矢板工法はH形鋼などを親杭と
し、木矢板などを親杭間に渡して土留壁とするものであ
り、シートパイル工法はシートパイルを連続的に打ち込
み、土留壁とするものであり、地中連続壁工法は鉄筋コ
ンクリート壁、又は芯材(H形鋼等)入りコンクリート
壁、又はモルタル(またはソイルモルタル)壁を連続し
て築造し土留壁とするものであり、また、ライナープレ
ート工法はライナープレートを逆巻き工法にて組立て土
留壁とするものであり、シートパイル工法と地中連続壁
工法によるものは止水性土留壁であるが、親杭・横矢板
工法とライナープレート工法によるものは開水性土留壁
である。
In the main pile / lateral sheet pile construction method, H-section steel or the like is used as a main pile, and wood sheet pile or the like is passed between the main piles to form a retaining wall. In the sheet pile method, sheet piles are continuously driven into The underground continuous wall construction method is to construct a reinforced concrete wall, a concrete wall containing a core material (H-shaped steel, etc.), or a mortar (or soil mortar) wall in succession to make a retaining wall. In addition, the liner plate construction method is one in which the liner plate is assembled by the reverse winding construction method to form a retaining wall, and the sheet pile construction method and the underground continuous wall construction method are waterproof still retaining walls, but the main pile and side sheet pile construction method is The liner plate method is an open soil retaining wall.

【0007】[0007]

【発明が解決しようとする課題】前記工法のうち、親杭
・横矢板工法、シートパイル工法、地中連続壁工法によ
る埋設管の埋設の施工全体の工程の流れは、土留壁築造
後、掘削・土留支保工を施工し、構造物の築造後、埋戻
し・土留支保工撤去し、その後、地中連続壁工法を除い
て一般的には土留壁撤去を行うものとなるため、工程数
が多くなり、施工日数を要して工期の厳しい現場では対
応に苦しいものがある。
[Problems to be Solved by the Invention] Among the above-mentioned construction methods, the flow of the whole construction process of burying a buried pipe by the main pile / lateral sheet pile construction method, sheet pile construction method, underground wall construction method is・ Construction of earth retaining bars, construction of the structure, backfilling / removal of retaining earth retaining works, and then generally removing earth retaining walls except for underground continuous wall construction method. There are many, and it takes a lot of construction days, and there are things that are difficult to deal with at sites where the construction period is severe.

【0008】また、ライナープレート工法では小口径の
場合は人力作業が主体となるため、立坑の施工にはかな
りの日数を要する。又、湧水の多い場所では補助工法
(薬液注入、ディープウェルなど)を必要とするなど工
費もかさむ。
Further, in the liner plate construction method, in the case of a small diameter, manual work is mainly performed, so that it takes a considerable number of days to construct a vertical shaft. In addition, in places with a lot of spring water, auxiliary construction methods (chemical injection, deep well, etc.) are required, which increases the construction cost.

【0009】さらに、到達立坑の内部に配管設備等の作
工物を築造し、かうその作業内容も特殊な場合を除いて
一般的には過剰設備の場合が多く、工費の無駄となって
いる。
Further, except for the case where a work such as a piping facility is built inside the reaching shaft, the work contents are often excessive except for special cases, which is a waste of construction cost. .

【0010】本発明の目的は前記従来例の不都合を解消
し、支保工を不要とするなどして立坑の施工工種を削減
し、工期の短縮と工費の低減を図り、強度的にも信頼で
きる到達立坑およびその施工法を提供することにある。
The object of the present invention is to eliminate the inconveniences of the above-mentioned conventional examples, to reduce the type of construction work for vertical shafts by eliminating the need for supporting work, to shorten the construction period and the construction cost, and to be reliable in terms of strength. To provide a reaching shaft and its construction method.

【0011】[0011]

【課題を解決するための手段】本発明は前記目的を達成
するため、構造として、小口径シールド又は同推進工事
などにおける到達立坑であって、建て込んだ鋼管で円形
立坑に形成したこと、および工法として、全回転式パワ
ーケーシングジャッキで全周回転式オールケーシング場
所打杭工法により鋼管を継ぎ足しながら建て込み、鋼管
内の土砂をハンマーグラブで掘削、排土し、坑内のスラ
イム処理後、底盤コンクリートを打設して立坑を築造す
ることを要旨とするものである。
In order to achieve the above-mentioned object, the present invention has as a structure a reaching vertical shaft in a small-diameter shield or the same propulsion work, which is formed into a circular vertical shaft with built-in steel pipe, and As a construction method, a full-rotation power casing jack is used to build up all-rotational all-casing cast-in-place piles while adding steel pipes. The main idea is to construct a vertical shaft by casting.

【0012】請求項1記載の本発明によれば、建て込ん
だ鋼管で立坑を築造するから、簡単に施工でき、円形の
立坑となるので外部土圧や水圧に対して支保工なしで強
度が得られる。
According to the present invention as set forth in claim 1, since the vertical shaft is constructed from the built-in steel pipe, it can be easily constructed and becomes a circular vertical shaft, so that it has a strength against external earth pressure and water pressure without supporting work. can get.

【0013】請求項2記載の本発明によれば、全回転式
パワーケーシングジャッキで鋼管を建て込み、また、鋼
管内の土砂をハンマーグラブで掘削、排土し、しかも支
保工不要のため建て込みと掘削、排土がスピードアップ
し、工期が短縮する。
According to the second aspect of the present invention, the steel pipe is built by the full-rotation type power casing jack, and the earth and sand in the steel pipe is excavated and discharged by a hammer grab, and the support is not required. And excavation and soil removal will be speeded up and the construction period will be shortened.

【0014】[0014]

【発明の実施の形態】以下、図面について本発明の実施
の形態を詳細に説明する。図1は本発明の到達立坑の実
施形態の要部を示す縦断正面図、図2は同上平面図で、
例えば埋設管の到達側にφ2000mmの鋼管9を建て込ん
で、該鋼管9により円形の到達立坑2を築造する。
Embodiments of the present invention will be described below in detail with reference to the drawings. FIG. 1 is a vertical sectional front view showing a main part of an embodiment of a reaching shaft of the present invention, and FIG. 2 is a plan view of the same.
For example, a steel pipe 9 of φ2000 mm is built on the arrival side of the buried pipe, and a circular reaching shaft 2 is constructed by the steel pipe 9.

【0015】このようにして形成した到達立坑2は前記
の埋設管推進装置などでガス管10を埋設する場合の簡易
な到達立坑として鏡切り工で必要箇所を切欠き、ここの
先導管を誘導する。
The reaching shaft 2 formed in this way is a simple reaching shaft when the gas pipe 10 is buried by the above-mentioned buried pipe propulsion device, etc., and is cut out at a necessary portion by mirror cutting to guide the leading conduit here. To do.

【0016】さらに、到達立坑2はには布設するガス管
10を立ち上げ、これが他に水平に伸びるが、このように
ガス管10をが配管される上部の個所は適宜鋼管9の壁を
切断して、到達坑上部を拡幅して利用する。図中、11は
鋼管9の切除個所に建て込んだ軽量の鋼矢板、12は立坑
廻りの手すり、13は昇降ラダーを示す。
Further, the reaching shaft 2 is installed in the gas pipe.
10 is started up, and this extends horizontally to the other, but at the upper part where the gas pipe 10 is piped in this way, the wall of the steel pipe 9 is appropriately cut and the upper part of the reaching pit is widened and used. In the figure, 11 is a lightweight steel sheet pile built in the cut portion of the steel pipe 9, 12 is a handrail around a vertical shaft, and 13 is a lifting ladder.

【0017】次に鋼管9を建て込んで到達立坑2を築造
する工法を図3〜図8について説明する。図3のように
到達立坑を築造する施工現場に、発電機14、油圧ユニッ
ト15、掘削機本体16、カウンターウエイト17などで構成
する掘削機械を搬入し、発電機14と油圧ユニット15を電
気配線で接続し、また、油圧ユニット15と掘削機本体16
とを油圧配管で接続して組み立てる。
Next, a method of constructing the reaching shaft 2 by incorporating the steel pipe 9 will be described with reference to FIGS. As shown in Fig. 3, the excavator including the generator 14, hydraulic unit 15, excavator body 16, counterweight 17, etc. is brought into the construction site where the vertical shaft is to be built, and the generator 14 and hydraulic unit 15 are electrically wired. Connection with the hydraulic unit 15 and the excavator body 16
And connect with hydraulic piping to assemble.

【0018】掘削機本体16はアウトリガー兼用の昇降ジ
ャッキや鋼管9の外周のチャック抱持機構を備えた全回
転式パワーケーシングジャッキを使用し、カウンターウ
エイト17は例えば鉄板マットを使用する。
The excavator main body 16 uses an elevating jack that also serves as an outrigger and a full-rotation type power casing jack equipped with a chuck holding mechanism for the outer circumference of the steel pipe 9. The counterweight 17 uses, for example, an iron plate mat.

【0019】図4のように到達立坑2の掘削位置に、杭
芯廻りに杭径の引照点19を置き、周囲に地盤補強のため
に鉄板マットによるカウンターウエイト17を敷く。クレ
ーン18で掘削機本体16をつり上げ、鋼管9を抱かせて杭
芯引照点19と鋼管9の外径とを合致させて設置する。な
お、鋼管9の先端には掘削刃を形成しておく。
As shown in FIG. 4, a shining point 19 having a pile diameter is placed around the pile core at the excavation position of the reaching shaft 2, and a counterweight 17 made of an iron plate mat is laid around the pile for reinforcing the ground. The main body 16 of the excavator is lifted up by the crane 18, the steel pipe 9 is held, and the pile core lighting point 19 and the outer diameter of the steel pipe 9 are aligned with each other. An excavating blade is formed at the tip of the steel pipe 9.

【0020】次いで全周回転式オールケーシング場所打
杭工法で、図5のように鋼管9を抱かせた掘削機本体16
を時計方向に連続的に回転させながら鋼管9を押し込
み、クレーン18で吊ったハンマーグラブ20で鋼管9内の
土砂を掘削、排土する。
Next, by the all-circle rotary all-casing cast-in-place pile construction method, as shown in FIG. 5, the excavator body 16 holding the steel pipe 9 is held.
The steel pipe 9 is pushed in while continuously rotating in a clockwise direction, and the earth and sand in the steel pipe 9 is excavated and discharged by the hammer grab 20 hung by the crane 18.

【0021】鋼管9の押し込みの際は、トランシットま
たは下げ振りで直角2方向から押し込み方向を観測して
垂直度を得る。下部の鋼管9が下がり終えたならば、上
部の鋼管9を吊り込み、溶接継ぎの後、再び掘削を開始
する。
When pushing the steel pipe 9, the vertical direction is obtained by observing the pushing direction from two directions at right angles by a transit or a plumb bob. When the lower steel pipe 9 has finished lowering, the upper steel pipe 9 is suspended, welding is performed, and then excavation is started again.

【0022】所定深度まで鋼管9を建て込んだならば、
エスロンテープなどで深度を確認した後、坑内のスライ
ム処理を行う(図6参照)。スライムには坑内水中に浮
遊している物質と孔底に残留している掘り残しとがある
が、これらを除去するため、底部に弁状の内蓋21aのつ
いたスライムバケツ21を坑内水中に吊り入れ、掘削底で
3〜4回激しく上下させてスライムを攪拌し、着底後10
〜20分静止して沈殿を待った後、スライムバケツ21を静
かに引き上げる。
If the steel pipe 9 is built up to a predetermined depth,
After confirming the depth with Eslon tape, etc., slime treatment is performed inside the mine (see Fig. 6). Slime has substances floating in the mine water and uncut residue remaining at the bottom of the hole. To remove these, a slime bucket 21 with a valve-shaped inner lid 21a at the bottom is placed in the mine water. Suspend and vigorously move the slime up and down 3 to 4 times at the bottom of the excavation to stir the slime.
Stand still for 20 minutes, wait for precipitation, then gently pull up the slime bucket 21.

【0023】次に図7のようにトレミー管22を坑内に建
て込む。トレミー管22にはφ250 mmのフランジボルト
継ぎ型を使用し、必要に応じて1,2,3,4,6mを
組み合わせ、継ぎ部にはゴムパッキンを施して水密性を
確保する。かかるトレミー管22の建て込みは、坑内中心
に垂直に下ろし、坑内水とこれから打設するコンクリー
トとの混入を防ぐためにプランジャー23を入れ、上部に
コンクリート受けのためのホッパー24を取り付ける。
Next, as shown in FIG. 7, the tremie pipe 22 is installed inside the mine. A ø250 mm flange bolt joint type is used for the tremie pipe 22, 1,2,3,4,6 m are combined as required, and rubber joints are applied to the joint portion to ensure watertightness. The tremie pipe 22 is built vertically down to the center of the mine, a plunger 23 is inserted to prevent mixing of the mine water with concrete to be poured, and a hopper 24 for receiving a concrete is attached to the upper part.

【0024】そして、掘削機械やクレーンなどを鋼管9
の建て込み個所から移動し、図8に示すようにアジテー
タ車25を鋼管9の近くまで誘導し、トレミー管22のホッ
パー24にアジテータ車25のシュート26を掛けてトレミー
管22内にコンクリートを流し込み、鋼管9の底部に底盤
コンクリート28を打設する。
The steel pipe 9 is used for excavating machines and cranes.
8, move the agitator wheel 25 to near the steel pipe 9 as shown in FIG. 8, pour the chute 26 of the agitator wheel 25 on the hopper 24 of the tremie tube 22 and pour concrete into the tremie tube 22. The bottom concrete 28 is placed on the bottom of the steel pipe 9.

【0025】重錘29を付けたエスロンテープ27を鋼管9
内に吊り下ろし、底盤コンクリート28の天端計測を行
い、所定の高さに達したならば打ち止めする。
Eslon tape 27 with weight 29 attached to steel pipe 9
It is hung inside and the top end of the bottom concrete 28 is measured, and when it reaches a predetermined height, it is stopped.

【0026】[0026]

【発明の効果】以上述べたように本発明の到達立坑およ
びその施工法は、建て込んだ鋼管で立坑を築造するか
ら、簡単に施工でき、円形の立坑となるので外部土圧や
水圧に対して支保工なしで強度が得られる。
As described above, according to the ultimate shaft and its construction method of the present invention, since the vertical shaft is constructed by the built-in steel pipe, it can be easily constructed, and it becomes a circular vertical shaft. Strength can be obtained without supporting work.

【0027】また、全回転式パワーケーシングジャッキ
で鋼管を建て込み、鋼管内の土砂をハンマーグラブで掘
削、排土することで、建て込みと掘削、排土がスピード
アップし、工期が短縮するものである。
In addition, a steel pipe is built with a full-rotation type power casing jack, and the earth and sand in the steel pipe are excavated and discharged by a hammer grab to speed up the construction, excavation and earth removal, and shorten the construction period. Is.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の到達立坑の実施形態を示す縦断正面図
である。
FIG. 1 is a vertical sectional front view showing an embodiment of a reaching shaft of the present invention.

【図2】本発明の到達立坑の実施形態を示す平面図であ
る。
FIG. 2 is a plan view showing an embodiment of a reaching shaft of the present invention.

【図3】本発明の到達立坑の施工法を示す第1工程の正
面図である。
FIG. 3 is a front view of a first step showing a method of constructing a reaching shaft of the present invention.

【図4】本発明の到達立坑の施工法を示す第2工程の正
面図である。
FIG. 4 is a front view of a second step showing the method of constructing the reaching shaft of the present invention.

【図5】本発明の到達立坑の施工法を示す第3工程の正
面図である。
FIG. 5 is a front view of a third step showing the method of constructing the reaching shaft of the present invention.

【図6】本発明の到達立坑の施工法を示す第4工程の正
面図である。
FIG. 6 is a front view of a fourth step showing the method of constructing the reaching shaft of the present invention.

【図7】本発明の到達立坑の施工法を示す第5工程の正
面図である。
FIG. 7 is a front view of a fifth step showing the method of constructing the reaching shaft of the present invention.

【図8】本発明の到達立坑の施工法を示す第6工程の正
面図である。
FIG. 8 is a front view of a sixth step showing the method of constructing the reaching shaft of the present invention.

【図9】本発明の到達立坑の使用状態を示す要部の縦断
正面図である。
FIG. 9 is a vertical cross-sectional front view of essential parts showing a usage state of the reaching shaft of the present invention.

【図10】本発明の到達立坑の使用状態を示す要部の平
面図である。
FIG. 10 is a plan view of an essential part showing a usage state of the reaching shaft of the present invention.

【符号の説明】[Explanation of symbols]

1…発進立坑 2…到達立坑 3…反力体 4…推進機構 5…推進ジャッキ 6…推進装置 7…先導管 7a…オーガーヘッ
ド 8…埋設管 9…鋼管 10…ガス管 11…鋼矢板 12…手すり 13…昇降ラダー 14…発電機 15…油圧ユニット 16…掘削機本体 17…カウンターウエ
イト 18…クレーン 19…杭芯引照点 20…ハンマーグラブ 21…スライムバケツ 21a…内蓋 22…トレミー管 23…プランジャー 24…ホッパー 25…アジテータ車 26…シュート 27…エスロンテープ 28…底盤コンクリー
ト 29…重り
1 ... Starting shaft 2 ... Reaching shaft 3 ... Reaction force body 4 ... Propulsion mechanism 5 ... Propulsion jack 6 ... Propulsion device 7 ... Leading conduit 7a ... Auger head 8 ... Buried pipe 9 ... Steel pipe 10 ... Gas pipe 11 ... Steel sheet pile 12 ... Handrail 13… Lifting ladder 14… Generator 15… Hydraulic unit 16… Excavator body 17… Counterweight 18… Crane 19… Pile core light point 20… Hammer grab 21… Slime bucket 21a… Inner lid 22… Tremy tube 23… Plan Jar 24… Hopper 25… Agitator car 26… Shoot 27… Eslon tape 28… Bottom concrete 29… Weight

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 小口径シールド又は同推進工事などにお
ける到達立坑であって、到達側に建て込んだ鋼管で円形
立坑に形成したことを特徴とする到達立坑。
1. A reaching vertical shaft for a small-diameter shield or the same propulsion work, which is formed as a circular vertical shaft by a steel pipe built on the reaching side.
【請求項2】 全回転式パワーケーシングジャッキで全
周回転式オールケーシング場所打杭工法により鋼管を継
ぎ足しながら建て込み、鋼管内の土砂をハンマーグラブ
で掘削、排土し、坑内のスライム処理後、底盤コンクリ
ートを打設して立坑を築造することを特徴とする到達立
坑の施工法。
2. A full-rotation power casing jack is used to build up a steel pipe by the all-rotation all-casing cast-in-place pile construction method. A method for constructing a reaching shaft, which is characterized by pouring concrete to construct a shaft.
JP1663296A 1996-02-01 1996-02-01 Arrival shaft and construction thereof Pending JPH09209687A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1663296A JPH09209687A (en) 1996-02-01 1996-02-01 Arrival shaft and construction thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1663296A JPH09209687A (en) 1996-02-01 1996-02-01 Arrival shaft and construction thereof

Publications (1)

Publication Number Publication Date
JPH09209687A true JPH09209687A (en) 1997-08-12

Family

ID=11921747

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1663296A Pending JPH09209687A (en) 1996-02-01 1996-02-01 Arrival shaft and construction thereof

Country Status (1)

Country Link
JP (1) JPH09209687A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105909258A (en) * 2016-06-12 2016-08-31 中铁十九局集团轨道交通工程有限公司 Settlement control and compensation system and method for underneath pass existing building pipe-roofing construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105909258A (en) * 2016-06-12 2016-08-31 中铁十九局集团轨道交通工程有限公司 Settlement control and compensation system and method for underneath pass existing building pipe-roofing construction
CN105909258B (en) * 2016-06-12 2018-02-06 中铁十九局集团轨道交通工程有限公司 Under wear existing buildings pipe curtain construction settlement control compensation system and method

Similar Documents

Publication Publication Date Title
WO1996018001A1 (en) Pile head treating tool for cast-in-place pile, pile head treating method, and cast-in-place piling method
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
EP0407934A2 (en) Method for executing monolithic continuous straights or circular structural walls and a machine for realizing such a method
CN103924585A (en) Novel method for constructing wind power rock-embedded pile
JP7352048B1 (en) Construction method of large-span station with open wings and semi-top-down excavation and semi-reverse drilling
CN112609690A (en) Construction method of rotary drilling cast-in-place pile in sea-filling geological complex area
CN115478543B (en) Artificial hole digging pile foundation pit supporting structure and construction method
JPH09209687A (en) Arrival shaft and construction thereof
CN114635450A (en) Construction method for permanent steel pipe structural column of covered and excavated station
JPH11166231A (en) Bottom widening existing pile and embedding machine
JPH0369717A (en) Method and device for driving steel pipe pile for building off-shore structure
CN111576393A (en) Underground continuous wall construction method near subway
JP2799899B2 (en) Structure and construction method of branch of underground tunnel
JP2007309014A (en) Construction method for pile core body
JP7057582B1 (en) Underground construction method for large pipes and bottomed buried pipes
CN114607187B (en) Shaft type underground parking garage construction method of cast-in-situ supporting structure under slurry
JP2684531B2 (en) Vertical shaft or structure foundation pile construction method and construction apparatus
JP3896003B2 (en) Connection method and structure of shaft
JPH10292410A (en) Execution method for small-diameter shaft, connecting method for small-diameter shaft and buried pipe, and connecting method for buried pipe utilizing small-diameter shaft
JP2599617B2 (en) Underwater tunnel construction method
JP5865760B2 (en) Steel pipe press-fitting device moving device and steel pipe press-fitting device installation method
JP2996113B2 (en) How to build a shaft
JP2963802B2 (en) How to build an underground parking
JP2828786B2 (en) Casing shaft
CN108952007A (en) Construction is positioned manually in a kind of permanent steel column