JPH09137633A - Power-transmission line steel tower reconstruction method - Google Patents
Power-transmission line steel tower reconstruction methodInfo
- Publication number
- JPH09137633A JPH09137633A JP29657595A JP29657595A JPH09137633A JP H09137633 A JPH09137633 A JP H09137633A JP 29657595 A JP29657595 A JP 29657595A JP 29657595 A JP29657595 A JP 29657595A JP H09137633 A JPH09137633 A JP H09137633A
- Authority
- JP
- Japan
- Prior art keywords
- panel
- steel tower
- new
- existing
- transmission line
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Working Measures On Existing Buildindgs (AREA)
- Suspension Of Electric Lines Or Cables (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】この発明は、送電線鉄塔を建
替えることに関し、更に詳しくは、既設鉄塔敷地の範囲
内で既設鉄塔を撤去することなく、新規鉄塔を建設する
ことに関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to rebuilding a transmission line steel tower, and more particularly to constructing a new steel tower within an area of an existing steel tower site without removing the existing steel tower.
【0002】[0002]
【従来の技術】近年、住宅増加に伴い、市街地における
鉄塔建替工事が増加している。しかし、市街化により、
仮工事のスペースがなく、また、社有地が限られている
ため、技術上、建替が困難となるケースが多くなってい
る。2. Description of the Related Art In recent years, as the number of houses increases, the construction work of steel towers in urban areas is increasing. However, due to urbanization,
Since there is no space for temporary work and the company's land is limited, it is often difficult to rebuild due to technical reasons.
【0003】従来、送電線鉄塔の建替工事においては、
主に、1.元位置撤去新設工法、2.包込工法、3.T
LU工法(油圧リフトアップ)、4.TOP工法(タワ
ーオオバーラップ)等が知られている。Conventionally, in the rebuilding work of transmission line towers,
Mainly 1. Original construction method to remove former position, 2. Wrapping method, 3. T
LU method (hydraulic lift up), 4. The TOP construction method (tower overlap) and the like are known.
【0004】元位置撤去新設工法は、既設の鉄塔を撤去
して、既設の敷地内において、新規の鉄塔を建てる方法
であり、設置する敷地は変わらないものの停電する期間
が長くなる。そのため、通常は仮工事を行い、停電する
期間を短縮するようにしている。The original construction method of removing the original position is a method of removing an existing steel tower and constructing a new steel tower on the existing site. Although the site to be installed does not change, the power failure period becomes long. For this reason, temporary work is usually performed to reduce the period of power failure.
【0005】包込工法は、図7に示されるように、既設
の送電線鉄塔の基礎の外側に、新規の鉄塔の基礎を建設
し組付けをするものであり、停電する期間は短いが新た
に設置する基礎のため、鉄塔敷地の買い増しを必要とす
る。As shown in FIG. 7, the enclosing method is a method of constructing and assembling a new steel tower foundation outside the existing transmission line steel tower foundation. It will be necessary to purchase additional steel tower premises for the foundation to be installed at.
【0006】TLU工法は、従来、鉄塔敷地の買い増し
が困難な状況になっている状況に対して開発されたもの
で、既設の鉄塔を油圧リフトによって持ち上げ、下部に
新しい部材を組み付けることにより鉄塔を嵩上げするも
のであり、敷地を広げる必要がなく、短期間で工事を行
うことができる。しかし、基礎地盤が比較的堅牢である
ことや、既設の鉄塔基礎の流用や補強の範囲内に限定さ
れる。[0006] The TLU method has been developed for the situation where it has been difficult to buy more steel tower premises, and an existing steel tower is lifted by a hydraulic lift and a new member is attached to the lower part of the tower. The construction work can be done in a short period of time without the need to expand the site. However, it is limited to the extent that the foundation ground is relatively strong and the existing steel tower foundation is diverted or reinforced.
【0007】TOP工法もTLU工法と同様に、従来の
問題点を解決するために開発された工法で、既設の基礎
をそのまま使用し、既設の鉄塔を覆うように既設の外側
に新規の鉄塔を建設するものであり、敷地を広げて建設
する必要がない。しかし、既設の基礎をそのまま使用す
るため、既設の基礎の強度を越える場合には適応できな
い。Similar to the TLU method, the TOP method is a method developed to solve the conventional problems. The existing foundation is used as it is, and a new steel tower is installed outside the existing steel tower so as to cover the existing steel tower. It is constructed and there is no need to expand the site. However, since the existing foundation is used as it is, it cannot be applied when the strength of the existing foundation is exceeded.
【0008】[0008]
【発明が解決しようとする課題】従来のこれらの工法
は、仮工事に伴う工事費用が増えたり、そのための新た
な敷地が必要となる。特に、市街地においては新たな敷
地を買増することは極めて困難であるとともに、工事期
間が長期にわたって行なわれていた。また、TLU工法
やTOP工法の場合では、工事内容が限られ、大規模な
嵩上げや増強工事には不適であったり、基礎の強度を越
える場合には適応できないという問題が残されていた。However, these conventional construction methods require an increase in construction costs associated with temporary construction and a new site for that purpose. In particular, it is extremely difficult to purchase new sites in urban areas, and the construction period was long. Further, in the case of the TLU construction method and the TOP construction method, the work content is limited, and it remains unsuitable for large-scale upsizing and reinforcement work, and it is not applicable when the strength of the foundation is exceeded.
【0009】この発明は、上述の課題を解決するもので
あり、軟弱地盤での工事を可能にし、コストを掛けず、
新たな敷地を必要としないで、短期間の工事を可能にす
る新しい送電線鉄塔建替工法を提供することを目的とす
る。The present invention is to solve the above-mentioned problems and enables construction on soft ground without increasing the cost.
It is an object of the present invention to provide a new transmission tower reconstructing method that enables short-term construction without requiring a new site.
【0010】[0010]
【課題を解決するための手段】この発明にかかわる送電
線鉄塔建替工法では、上記課題を解決するため、複数段
載積されるパネル部と複数の送電線体を備えてなる送電
線鉄塔を建替する工法であって、既設鉄塔の基礎間に新
規鉄塔の基礎を建設し、前記既設の鉄塔に対して前記新
規の鉄塔が、平面視45度、方向を変えて建設されるこ
とを特徴とするものである。In order to solve the above-mentioned problems, in the transmission line steel tower rebuilding method according to the present invention, in order to solve the above-mentioned problems, a transmission line steel tower comprising a plurality of stacked panel parts and a plurality of transmission line bodies is provided. It is a construction method for rebuilding, in which a foundation of a new steel tower is constructed between the foundations of existing steel towers, and the new steel tower is constructed by changing the direction in plan view by 45 degrees with respect to the existing steel tower. It is what
【0011】また、好ましくは、前記パネルが縦方向に
配設される主柱材と、前記主柱材に対して横方向に配設
される腹材を備えて構成され、複数段の前記パネルの
内、少なくとも一部のパネルが、K字型部を含む腹材を
備え、前記パネルを組立てる際、K字型を構成する前記
腹材に仮設材を設け、前記腹材の一部を既設パネルの外
側に一時的に配設することを特徴とするものであればよ
い。Further, preferably, the panel comprises a main pillar material arranged in a vertical direction and an abdominal material arranged in a lateral direction with respect to the main pillar material, and the panel has a plurality of stages. Among them, at least a part of the panels is provided with an abdominal material including a K-shaped portion, and when the panels are assembled, a temporary material is provided on the abdominal material forming the K-shape, and a part of the abdominal material is already installed. What is characterized is that it is temporarily arranged on the outside of the panel.
【0012】[0012]
【発明の実施の形態】以下、この発明の一実施の形態を
図面に基づいて説明する。DESCRIPTION OF THE PREFERRED EMBODIMENTS One embodiment of the present invention will be described below with reference to the drawings.
【0013】図1は、既設鉄塔を新規鉄塔に建替する全
体図を示すものであり、新しく建設される新規鉄塔T
の、2点鎖線で示される既設鉄塔tに対する比較を示す
図である。そして、既設鉄塔tに対し、新規鉄塔Tが平
面視において、45度ずれた角度で示されている。図2
は、基礎組を平面から見た図であり、4個の新規基礎1
が、大口径ボーリングマシンによって、4個の既設基礎
21の間に場所打杭される。この基礎1上に、新規鉄塔
Tが既設鉄塔tに対して45度ずれるように建設され
る。この建替工事に当たっては、新規鉄塔Tを建設する
時点においては既設鉄塔tは撤去されずそのまま残って
いて、新規鉄塔Tの建設途中において既設鉄塔tが撤去
される。FIG. 1 shows an overall view of rebuilding an existing steel tower into a new steel tower, and a new steel tower T to be newly constructed.
It is a figure which shows the comparison with respect to the existing steel tower t shown by a two-dot chain line. Then, the new steel tower T is shown at an angle deviated from the existing steel tower t by 45 degrees in a plan view. FIG.
Is a plan view of the foundation set, showing four new foundations 1
However, it is cast in place between four existing foundations 21 by a large diameter boring machine. On this foundation 1, a new steel tower T is constructed so as to deviate from the existing steel tower t by 45 degrees. In this rebuilding work, the existing steel tower t is not removed at the time of constructing the new steel tower T and remains as it is, and the existing steel tower t is removed during the construction of the new steel tower T.
【0014】完成される新規鉄塔Tは、下端部から上方
部に向かうほど新規鉄塔TのパネルPが既設鉄塔tのパ
ネルpよりも相対的に広幅に形成され、図3に示される
ように、パネル区分としてクロスパネル(図3a)、交
差パネル(図3b)、上部未交差パネル(図3c)の3
段階の区別される。そして、新規基礎1のすぐ上に配設
されるパネルP1を最下段に、上方に向かって順に載積
されるP2、P3‥P19を備えて構成されることにな
る。In the completed new steel tower T, the panel P of the new steel tower T is formed to be relatively wider than the panel p of the existing steel tower t from the lower end toward the upper part, and as shown in FIG. 3 panel sections: cross panel (Fig. 3a), cross panel (Fig. 3b), and upper uncrossed panel (Fig. 3c).
The stages are distinguished. Then, the panel P1 disposed immediately above the new foundation 1 is arranged at the lowermost stage, and P2, P3, ...
【0015】パネルPは、縦方向に配設される主柱材2
と、主柱材2に対して、横面方向に配設される腹材3と
を含んで一組のパネル組を構成する。そして各パネルP
が下から順に組み付けられる。なお腹材3はパネル区分
によってその構成が異なり、クロスパネルと交差パネル
は同じ構成で、上部未交差パネルは異なる。The panel P is a main pillar member 2 arranged in the vertical direction.
And a belly member 3 arranged in the lateral direction with respect to the main pillar member 2 to form a panel set. And each panel P
Are assembled in order from the bottom. The configuration of the abdominal material 3 differs depending on the panel section, the cross panel and the cross panel have the same configuration, and the upper non-cross panel differs.
【0016】クロスパネルは、主柱材2と、横K字型に
形成されるK結構を一部に含む腹材3(腹材3の詳細に
ついては後述する。)を備えて構成され、新規鉄塔Tが
既設鉄塔t内にクロスする状態で使用されるパネルで、
例えば、パネルP1の場合は、既設鉄塔tのパネルp1
とほぼ同じ大きさに形成され、45度角度がずれた分、
主柱材と相手パネルの側面(腹材3)がお互いにクロス
状態にある。そして、上方のパネルに向かって、徐々に
新規鉄塔TのパネルPの幅が既設鉄塔tより相対的に大
きくなり、パネルP5あたりまでクロスパネルが続く。The cross panel comprises a main pillar member 2 and a belly member 3 (a detail of the belly member 3 will be described later) which partially includes a K-shaped member formed in a horizontal K shape. A panel used when the steel tower T crosses the existing steel tower t,
For example, in the case of the panel P1, the panel p1 of the existing steel tower t
It is formed in almost the same size as
The main pillar material and the side surface (belly material 3) of the mating panel are in a crossed state with each other. Then, toward the upper panel, the width of the panel P of the new steel tower T gradually becomes relatively larger than that of the existing steel tower t, and the cross panel continues up to around the panel P5.
【0017】また、交差パネルは、主柱材2と、横K字
型に形成されるK結構を一部に含む腹材3を備えて構成
され、新規鉄塔Tの側面が全面的に既設主柱材22と接
触交差する状態で使用されるパネルで、例えば、パネル
P6の場合、新規鉄塔Tのパネルの側面(腹材3)の長
さと、既設鉄塔tのパネルの対角線の長さがほぼ同じに
形成されている。The cross panel is composed of a main column member 2 and a belly member 3 which partially includes a horizontal K-shaped K structure, and the side surface of the new steel tower T is entirely the existing main member. In the panel used in a state of contacting and intersecting with the pillar member 22, for example, in the case of the panel P6, the length of the side surface (belly member 3) of the panel of the new steel tower T and the length of the diagonal line of the panel of the existing steel tower t are almost the same. Formed the same.
【0018】上部未交差パネルは、主柱材2と、X状に
配設されるダブルワーレン結構で形成される腹材3を備
えて構成され、新規鉄塔Tの全面が既設鉄塔tの外側に
配置される状態で使用されるパネルで、例えば、パネル
P7の場合は、新規鉄塔Tのパネル内に既設鉄塔tのパ
ネルが完全に収納される。The upper non-intersecting panel is composed of a main pillar material 2 and a belly material 3 formed of a double Warren structure arranged in an X shape, and the entire surface of the new steel tower T is located outside the existing steel tower t. In the case of the panel used in the arranged state, for example, the panel P7, the panel of the existing steel tower t is completely accommodated in the panel of the new steel tower T.
【0019】従って、パネルP1〜P6においては、各
パネルPは、K結構の腹材を備えたクロスパネルあるい
は交差パネルで構成され、P7〜19のパネルはダブル
ワーレン結構の腹材を備えた上部未交差パネルで構成さ
れることになる。そして、ダブルワーレン結構を構成し
ている上方のパネルに3組の送電線体12(既設鉄塔t
に使用されていたもの)が取りつけられる。Therefore, in the panels P1 to P6, each panel P is composed of a cross panel or a cross panel provided with a K-structured abdominal material, and the panels P7 to 19 are provided with an upper portion provided with a double warren-structured abdominal material. It will consist of unintersecting panels. Then, three sets of power transmission line bodies 12 (existing steel tower t
The one used for was attached.
【0020】図4〜6は、K結構されているパネルP部
の詳細を示すものであり、残されている既設鉄塔tに対
して、新規パネルを組み付ける状態を示すものである。
図4は、平面断面図であり、既設鉄塔tの主柱材22が
4本立設されて、ぞれぞれの主柱材22の外側に4本の
水平補助材24が両側の主柱材22に懸架されるように
主柱材22に固着されて、四角の枠を形成している。FIGS. 4 to 6 show details of the panel P section which is K-structured, and show a state in which a new panel is assembled to the remaining existing steel tower t.
FIG. 4 is a plan sectional view, in which four main pillar members 22 of the existing steel tower t are erected upright, and four horizontal auxiliary members 24 are provided outside each of the main pillar members 22. It is fixed to the main pillar material 22 so as to be suspended on 22, and forms a square frame.
【0021】新規パネルPを形成する新規の主柱材2
は、既設の主柱材22に対して、平面視において45度
ずれた位置に4本配設される。そして、既設の主柱材2
2及び水平補助材24に接触しない位置(水平補助材2
4の外側)に新規の水平補助材4が配設されるように、
それぞれ新規の主柱材2と水平補助材4の間に第1仮設
材5が取りつけられ、四角の枠を形成する。New main pillar material 2 forming a new panel P
4 are arranged at a position shifted by 45 degrees in a plan view with respect to the existing main pillar member 22. And the existing main pillar material 2
2 and a position that does not contact the horizontal auxiliary member 24 (horizontal auxiliary member 2
So that a new horizontal auxiliary member 4 is arranged on the outer side of 4),
A first temporary material 5 is attached between each new main pillar material 2 and horizontal auxiliary material 4 to form a square frame.
【0022】図5は、パネルPの正面図を示すものであ
り、両側に立設された新規の主柱材2は下方が広幅で、
上方に向かって狭くなっている。そして、水平補助材4
の中央部から、下方に向かって両側に広がるように第1
斜材6が配設される。第1斜材の下端部裏側には、図6
に示されるように、第1斜材6と同じ厚みの第2仮設材
7を介して、一端が主柱材2に固着された第2斜材8が
接続される。さらに、第2斜材8と、主柱材2との間
に、斜めに配設される第3斜材9と、水平に配設される
補強材10が取りつけられる。そして、水平補助材4と
2本の第1斜材6、第2斜材8で「K」字型を形成し
(以下K結構という。)、第2斜材8を除くK結構され
た部分が既設パネルpの主柱材22、水平補助材24と
の接触を回避するように、既設パネルpの外側に配設さ
れる。FIG. 5 is a front view of the panel P, in which the new main pillar members 2 erected on both sides are wide at the bottom,
It is narrowing upward. And the horizontal auxiliary material 4
From the central part of the
A diagonal member 6 is provided. On the back side of the lower end of the first diagonal member, as shown in FIG.
As shown in, the second diagonal member 8 having one end fixed to the main pillar member 2 is connected via the second temporary member 7 having the same thickness as the first diagonal member 6. Further, between the second diagonal member 8 and the main pillar member 2, a third diagonal member 9 obliquely arranged and a reinforcing member 10 horizontally arranged are attached. The horizontal auxiliary member 4, the two first diagonal members 6 and the second diagonal member 8 form a “K” shape (hereinafter referred to as “K”), and the K-shaped portion excluding the second diagonal member 8 is formed. Is disposed outside the existing panel p so as to avoid contact with the main pillar material 22 and the horizontal auxiliary material 24 of the existing panel p.
【0023】なお、腹材3は、水平補助材4、第1斜材
6、第2斜材8、第3斜材9、補強材10から構成さ
れ、4本の主柱材2と4面の腹材3を含めて1組のパネ
ルPが構成される。The belly member 3 is composed of a horizontal auxiliary member 4, a first diagonal member 6, a second diagonal member 8, a third diagonal member 9 and a reinforcing member 10, and four main pillar members 2 and 4 faces. A set of panels P including the abdominal material 3 is formed.
【0024】なお、仮設材5、7はK結構部を既設パネ
ルpより、外側に逃がすためのものであるから、仮設材
5、7の厚みLは、新規パネルの水平補助材4より外側
に突出された、既設鉄塔の突出部の長さ以上でなければ
ならないが、仮設材5、7の長尺方向の長さは、主柱材
1の一片の長さ程度あればよい。従って、仮設材に掛か
るコストは僅かなものである。Since the temporary members 5 and 7 are intended to allow the K structure portion to escape to the outside from the existing panel p, the thickness L of the temporary members 5 and 7 is set outside the horizontal auxiliary member 4 of the new panel. It must be longer than the length of the protruding portion of the existing steel tower that is projected, but the length of the temporary materials 5 and 7 in the longitudinal direction may be about the length of one piece of the main pillar 1. Therefore, the cost of the temporary material is low.
【0025】パネルPの建替は新規鉄塔Tの下端に配設
されるパネルP1から上方に向かって順番に行なわれ、
腹材3がK結構に形成されるパネルP6まで1パネルづ
つ組み立てられる。すなわち、設置されたパネルP1の
主柱材2に対して、クレーン等で吊り上げられた2段目
のパネルP2の主柱材2を連結することによってパネル
が積み上げられ、さらにパネルP3‥と続く。The rebuilding of the panel P is carried out in order from the panel P1 arranged at the lower end of the new steel tower T upward,
One panel is assembled up to the panel P6 in which the belly member 3 is formed in a K structure. That is, the panels are stacked by connecting the main columns 2 of the installed panel P1 to the main columns 2 of the second-stage panel P2 that has been lifted by a crane or the like, and then the panels P3.
【0026】新規パネルPをパネル6まで組み付けた
後、停電をし、既設鉄塔tに取りつけられている3組の
送電線体12を外して、新規に組み付けられたパネルP
6に仮取つけをする。なお、既設鉄塔tは、各パネルp
がダブルワーレン結構で、新規パネルTと同様に、各パ
ネル毎によって組み付けられているので、送電線体12
を新規鉄塔のパネルPに取りつけた後、上のパネル組か
ら順に分解し撤去することができる。そして、既設鉄塔
tを撤去した後、仮設材5、7を取り外し、主柱材2と
水平補助材4、第1斜材6と第2斜材8を直接結合す
る。After assembling the new panel P up to the panel 6, a power failure occurs, and the three sets of power transmission line bodies 12 attached to the existing steel tower t are removed to newly install the panel P.
Temporarily attach to 6. In addition, the existing steel tower t has each panel p
Is a double warren structure, and each panel is assembled in the same manner as the new panel T.
After being attached to the panel P of the new steel tower, they can be disassembled and removed in order from the upper panel set. Then, after removing the existing steel tower t, the temporary materials 5 and 7 are removed, and the main pillar material 2 and the horizontal auxiliary material 4, and the first diagonal material 6 and the second diagonal material 8 are directly coupled.
【0027】次に、パネルP7より上方のダブルワーレ
ン結構のパネルを、パネルP7より順に上方に向かって
組み付ける。そして、パネルP6に仮取り付けされた送
電線体12を取り外し、パネルPの正規な位置に3段に
送電線体12を取りつける。そして、停電を解除して、
新規鉄塔が完成される。Next, the panels of the double warren structure above the panel P7 are assembled upward from the panel P7 in order. Then, the power transmission line body 12 temporarily attached to the panel P6 is removed, and the power transmission line body 12 is attached to the regular position of the panel P in three stages. Then, cancel the power cut,
A new steel tower is completed.
【0028】なお、既設鉄塔tの分解撤去は、既設鉄塔
tに取りつけられている送電線体12を取り外し、新規
鉄塔TのパネルPに仮取り付けされる時点で行なわれる
が、組み付け途中の最上段のパネルに仮取付けできるも
のであれば、いずれの段のパネルであっても構わない。The dismantling and removal of the existing steel tower t is carried out when the power transmission line body 12 attached to the existing steel tower t is removed and temporarily attached to the panel P of the new steel tower T. Any panel may be used as long as it can be temporarily attached to the panel.
【0029】また、本実施形態においては、パネルP1
〜6までがK結構され、パネル7〜19までがダブルワ
ーレン結構されているように構成しているが、これに制
限されるものではなく、鉄塔の全長によって適宜変更で
きるものである。また、送電線体の数も同様である。た
だし、K結構されているパネルがクロスパネルと交差パ
ネルであり、ダブルワーレン結構されているパネルが上
部未交差パネルであることが望ましい。Further, in this embodiment, the panel P1
It is configured such that up to 6 are K-structured and panels 7 to 19 are double-waren structured, but the invention is not limited to this and can be appropriately changed depending on the total length of the steel tower. The same applies to the number of power transmission lines. However, it is desirable that the K-structured panel is a cross panel and a crossed panel, and the double warren-structured panel is an upper non-crossed panel.
【0030】[0030]
【発明の効果】本発明によれば、新規送電線鉄塔が既設
の送電線鉄塔に対して、45度、方向を変えるように建
設するので、増強工事を含む大規模な鉄塔の建替工事を
既設鉄塔の敷地範囲内で行うことができる。従って、近
年ますます困難になってきた敷地の買い増し等の問題を
解決することができるとともに、鉄塔の建替工事期間が
短縮される。また、仮工事を必要としないため、コスト
の低減が可能になる。According to the present invention, since a new transmission line tower is constructed so as to change its direction by 45 degrees with respect to the existing transmission line tower, large-scale tower rebuilding work including reinforcement work can be performed. It can be performed within the site area of the existing steel tower. Therefore, it is possible to solve the problems such as additional purchase of the site, which have become increasingly difficult in recent years, and shorten the period for rebuilding the steel tower. Further, since temporary work is not required, cost can be reduced.
【0031】そして、新規鉄塔のパネルPを既設鉄塔t
のパネルpの外側に配設するように仮設材を設けるの
で、45度、方向を変えることによって生じるパネル組
み付け時における既設鉄塔との干渉を防止することがで
きる。The panel P of the new steel tower is attached to the existing steel tower t.
Since the temporary material is provided so as to be disposed outside the panel p, it is possible to prevent interference with the existing steel tower at the time of assembling the panel, which is caused by changing the direction by 45 degrees.
【図1】本発明の一実施形態の新規鉄塔と既設鉄塔を示
す全体図FIG. 1 is an overall view showing a new steel tower and an existing steel tower according to an embodiment of the present invention.
【図2】本発明の一実施形態の新規鉄塔と既設鉄塔の基
礎を示す平面図FIG. 2 is a plan view showing the foundations of a new steel tower and an existing steel tower according to an embodiment of the present invention.
【図3】本発明による鉄塔建替工法のパネル区分を示す
図FIG. 3 is a diagram showing panel sections of a steel tower rebuilding method according to the present invention.
【図4】図1におけるK結構パネルの平面断面図FIG. 4 is a plan sectional view of the K-structure panel in FIG.
【図5】図1におけるK結構パネルの正面図FIG. 5 is a front view of the K structure panel in FIG.
【図6】図1におけるK結構パネルの一部側面断面図6 is a partial side sectional view of the K-structure panel in FIG.
【図7】従来の包込工法[Figure 7] Conventional wrapping method
1…新規基礎 2…主柱材 3…腹材 4…水平補助材 5…第1仮設材 6…第1斜材 7…第2仮設材 8…第2斜材 T…新規鉄塔 t…既設鉄塔 P…新規パネル p…既設パネル 1 ... New foundation 2 ... Main pillar material 3 ... Belly material 4 ... Horizontal auxiliary material 5 ... 1st temporary material 6 ... 1st diagonal material 7 ... 2nd temporary material 8 ... 2nd diagonal material T ... New steel tower t ... Existing steel tower P ... New panel p ... Existing panel
Claims (2)
体を備えてなる送電線鉄塔を建替する工法であって、既
設鉄塔の基礎間に新規鉄塔の基礎を建設し、前記既設の
鉄塔に対して前記新規の鉄塔が、平面視45度、方向を
変えて建設されることを特徴とする送電線鉄塔建替工
法。1. A method for rebuilding a transmission line tower comprising a plurality of stacked panels and a plurality of transmission line bodies, wherein a new steel tower foundation is constructed between existing steel tower foundations, The new steel tower is constructed by changing the direction of the steel tower at 45 degrees in a plan view with respect to the steel tower.
と、前記主柱材に対して横方向に配設される腹材を備え
て構成され、複数段の前記パネルの内、少なくとも一部
のパネルが、K字型部を含む腹材を備え、前記パネルを
組立てる際、K字型を構成する前記腹材に仮設材を設
け、前記腹材の一部を既設パネルの外側に一時的に配設
することを特徴とする請求項1記載の送電線鉄塔建替工
法。2. The panel comprises a main pillar member vertically arranged and a belly member horizontally arranged with respect to the main pillar member. At least a part of the panels is provided with a belly member including a K-shaped portion, and when the panels are assembled, a temporary member is provided on the belly member constituting the K-shape, and a part of the belly member is provided outside the existing panel. The method for constructing a transmission line tower as claimed in claim 1, wherein the construction is performed temporarily.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP29657595A JP3639999B2 (en) | 1995-11-15 | 1995-11-15 | Transmission line steel tower rebuilding method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP29657595A JP3639999B2 (en) | 1995-11-15 | 1995-11-15 | Transmission line steel tower rebuilding method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH09137633A true JPH09137633A (en) | 1997-05-27 |
JP3639999B2 JP3639999B2 (en) | 2005-04-20 |
Family
ID=17835322
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP29657595A Expired - Fee Related JP3639999B2 (en) | 1995-11-15 | 1995-11-15 | Transmission line steel tower rebuilding method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3639999B2 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2009156827A1 (en) * | 2008-06-24 | 2009-12-30 | Hedinger, Johan | Upgradeable lattice tower and components thereof |
CN102296871A (en) * | 2011-05-06 | 2011-12-28 | 山西省电力公司太原供电分公司 | High-voltage power transmission section length variable iron tower |
JP2012167459A (en) * | 2011-02-10 | 2012-09-06 | Tokyo Electric Power Co Inc:The | Steel tower rebuilding method |
-
1995
- 1995-11-15 JP JP29657595A patent/JP3639999B2/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2009156827A1 (en) * | 2008-06-24 | 2009-12-30 | Hedinger, Johan | Upgradeable lattice tower and components thereof |
JP2012167459A (en) * | 2011-02-10 | 2012-09-06 | Tokyo Electric Power Co Inc:The | Steel tower rebuilding method |
CN102296871A (en) * | 2011-05-06 | 2011-12-28 | 山西省电力公司太原供电分公司 | High-voltage power transmission section length variable iron tower |
Also Published As
Publication number | Publication date |
---|---|
JP3639999B2 (en) | 2005-04-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107419824A (en) | The full precast shear wall structural system of regenerative steel skeleton and construction method | |
JP5189546B2 (en) | Construction method of Nakaji arch bridge | |
CN109680835B (en) | Self-supporting precast concrete wallboard, concrete wall, structural system and construction method | |
CN207700746U (en) | The upper buttress of existing building base isolation reinforcement constructs | |
JP3333788B2 (en) | Prefabricated bridge pier | |
JP2903945B2 (en) | Large span structure and construction method thereof | |
US4743141A (en) | Offshore truss work type tower structure | |
JPH11200382A (en) | Reinforcing method for existing building foundation by diagonal pile | |
JPH09137633A (en) | Power-transmission line steel tower reconstruction method | |
JPH10152998A (en) | Earthquake-resistant reinforcing structure of existing building | |
AU679502B2 (en) | Method to construct the prestressed composite beam structure and the prestressed composite beam for a continuous beam thereof | |
JPH069170Y2 (en) | Beam structure | |
JP3999625B2 (en) | Bottom structure of steel tower | |
JP3593612B2 (en) | Method for removing residual stress from tower steel structure composed of angle iron | |
JP3265092B2 (en) | Construction method of tunnel with precast concrete slab | |
JPH07317194A (en) | Constructing method of large-sized building with doom roof | |
CN115478649A (en) | Large-span diagonal member truss and installation method thereof | |
JPH0518192A (en) | Construction method for tunnel and lining segment | |
JP3975401B2 (en) | Steel tower raising method | |
JP7548869B2 (en) | How to build structures | |
JP3721482B2 (en) | Seismic reinforcement method and structure for existing buildings | |
JPH0197744A (en) | Shearing reinforcing structure of shear head section in flat plate building | |
JPH0749684B2 (en) | Method of introducing tension in the string beam structure | |
JP2000110245A (en) | Column-omitted building unit, unit building, and its building method | |
JPH09310442A (en) | Roof structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Effective date: 20040120 Free format text: JAPANESE INTERMEDIATE CODE: A971007 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20040210 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20040407 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20040706 |
|
A521 | Written amendment |
Effective date: 20040825 Free format text: JAPANESE INTERMEDIATE CODE: A523 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Effective date: 20041207 Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20050106 |
|
R150 | Certificate of patent (=grant) or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110128 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 6 Free format text: PAYMENT UNTIL: 20110128 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 7 Free format text: PAYMENT UNTIL: 20120128 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 7 Free format text: PAYMENT UNTIL: 20120128 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 8 Free format text: PAYMENT UNTIL: 20130128 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130128 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140128 Year of fee payment: 9 |
|
LAPS | Cancellation because of no payment of annual fees |