JPH09136245A - Evaluation method and evaluation device for production planning - Google Patents

Evaluation method and evaluation device for production planning

Info

Publication number
JPH09136245A
JPH09136245A JP24928896A JP24928896A JPH09136245A JP H09136245 A JPH09136245 A JP H09136245A JP 24928896 A JP24928896 A JP 24928896A JP 24928896 A JP24928896 A JP 24928896A JP H09136245 A JPH09136245 A JP H09136245A
Authority
JP
Japan
Prior art keywords
production
loss
production plan
amount
order
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP24928896A
Other languages
Japanese (ja)
Inventor
Hiroyoshi Suzuki
浩佳 鈴木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toyota Motor Corp
Original Assignee
Toyota Motor Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toyota Motor Corp filed Critical Toyota Motor Corp
Priority to JP24928896A priority Critical patent/JPH09136245A/en
Publication of JPH09136245A publication Critical patent/JPH09136245A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Abstract

PROBLEM TO BE SOLVED: To evaluate production planning quantitatively by recalculating a due data adherence rate and a stock quantity, which are characteristic values in the different dimensions, in the same dimension. SOLUTION: In an evaluation method for production planning, as to production plans S4, S5, S6 made on the basis of a given order data S2, a total loss of a production loss S8, which is generated because of a deviation between a product due date based on the order data and a product due date based on the production planning, and a stock loss S7 due to stock generated because of the production planning is calculated, and then, the production planning is evaluated on the basis of the calculated total loss.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、与えられた受注デ
ータに基づいて立案された生産計画を評価する方法及び
評価装置に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method and an evaluation device for evaluating a production plan designed based on given order data.

【0002】[0002]

【従来の技術】従来、与えられた受注データに基づいて
生産計画を立案する方法として、受注順に生産する方
法、納期順に生産する方法等種々の立案方法が使用され
ている。そして、これらのうち、どの生産計画を採用す
るかについては、従来作業者の経験と勘に依拠すること
が多かった。しかし、顧客の好みが多様化し、受注製品
の種類も多くなり、作業者の経験と勘に依拠していたの
では、満足な生産計画を得ることができなくなってい
た。そこで、立案された生産計画を評価する方法が、例
えば特開平4−364571号公報で提案されている。
すなわち、日毎の受注データに含まれる品種毎に、その
品種の中間仕掛かり品及び製品の発注在庫量及び補充量
とに基づいて、その品種の生産リードタイムを算出する
生産リードタイム算出部と、この生産リードタイムによ
って算出された各品種毎の生産リードタイムとその品種
の納期との比較から納期遵守率を求める納期遵守率出力
部を有している。また、在庫量推移表示部を有してい
る。
2. Description of the Related Art Conventionally, as a method of making a production plan based on given order data, various planning methods such as a method of producing in order and a method of producing in order of delivery date have been used. And among these, which production plan is adopted has often depended on the experience and intuition of a conventional worker. However, customer preferences have diversified, the types of products ordered have increased, and it has been impossible to obtain a satisfactory production plan based on the experience and intuition of workers. Therefore, a method for evaluating the planned production plan is proposed in, for example, Japanese Patent Laid-Open No. 4-364571.
That is, for each product type included in the daily order data, a production lead time calculation unit that calculates the production lead time of the product type based on the intermediate work-in-process product of the product type and the ordered stock amount and the replenishment amount of the product, It has a delivery date compliance rate output unit that obtains a delivery date compliance rate by comparing the production lead time for each product type calculated from the production lead time with the delivery time of the product type. It also has an inventory quantity transition display unit.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、従来の
評価方法には次のような問題点があった。すなわち、納
期遵守率と在庫量推移とを別々に求め各々表示している
のみで、立案された生産計画の良否を総合的に判断する
には、さらに両者をトータルして判断する必要がある。
しかし、両者を総合的に判断することに関しては、未だ
作業者の経験と勘とに依拠しており、同一の受注データ
に対して複数の生産計画が立案されたときに、各々の生
産計画を定量的に評価することができないため、最適な
生産計画を選択することが困難であった。
However, the conventional evaluation method has the following problems. That is, only the delivery date compliance rate and the inventory quantity transition are separately obtained and displayed, and in order to comprehensively determine the quality of the planned production plan, it is necessary to make a total determination of both.
However, regarding the comprehensive judgment of both, it still depends on the experience and intuition of the worker, and when multiple production plans are made for the same order data, each production plan is decided. It was difficult to select the optimal production plan because it could not be evaluated quantitatively.

【0004】本発明は、このような問題点を解決するた
めになされたものであり、納期遵守率と在庫量という次
元の異なる特性値を同一次元に計算し直して、生産計画
を定量的に評価する方法を提供することを目的とする。
The present invention has been made in order to solve such a problem, and the characteristic values having different dimensions such as the delivery date compliance rate and the stock amount are recalculated in the same dimension to quantitatively calculate the production plan. The purpose is to provide a method of evaluation.

【0005】[0005]

【課題を解決するための手段】本発明の生産計画の評価
方法は、コンピュータを用いて、与えられた受注データ
に基づいて立案された生産計画に対して、受注データの
製品納期と生産計画による生産納期とのずれから発生す
る生産損失、生産計画により発生する在庫による在庫損
失との合計損失を算出し、算出された合計損失に基づい
て、生産計画を評価する。また、本発明の生産計画の評
価方法は、上記方法において、生産計画において発生す
る部品の欠品による欠品損失を算出して、前記合計損失
に算入することを特徴とする。また、本発明の生産計画
の評価方法は、上記方法おいて、前記各損失の各々に所
定の係数を乗じて、前記合計損失を金額として換算する
ことを特徴とする。また、本発明の生産計画の評価方法
を実行するためのコンピュータ可読記録媒体には、上記
3つの評価方法のうち、少なくとも1つの評価方法を実
行するプログラムが記憶されている。
According to the method of evaluating a production plan of the present invention, a computer is used to prepare a production plan made on the basis of given order data, and the product delivery date of the order data and the production plan are used. A total loss including a production loss caused by a deviation from the production deadline and an inventory loss due to the inventory caused by the production plan is calculated, and the production plan is evaluated based on the calculated total loss. Further, the production planning evaluation method of the present invention is characterized in that, in the above method, a missing item loss due to a missing item of a component occurring in the production plan is calculated and included in the total loss. Further, the production plan evaluation method of the present invention is characterized in that, in the above method, each of the losses is multiplied by a predetermined coefficient to convert the total loss as a monetary amount. A computer-readable recording medium for executing the production plan evaluation method of the present invention stores a program for executing at least one of the above three evaluation methods.

【0006】また、本発明の生産計画の評価装置は、コ
ンピュータを用いて、与えられた受注データに基づいて
立案された生産計画に対して、受注データの製品納期と
生産計画による生産納期とのずれから発生する生産損失
を算出するための生産損失算出プログラムと、生産計画
により発生する在庫による在庫損失を算出するための在
庫損失算出プログラムと、生産損失と在庫損失との合計
損失を算出する合計損失算出プログラムと、算出された
合計損失を出力する出力手段とを有している。さらに、
評価装置は、生産計画において発生する部品の欠品によ
る欠品損失を算出する欠品損失算出プログラムを有して
いると良い。また、評価装置の合計損失算出プログラム
は、前記各損失の各々に所定の係数を乗じて、前記合計
損失を金額として換算する工程を有していると良い。
Further, the production plan evaluation apparatus of the present invention uses a computer to compare the product delivery date of the order data and the production delivery date of the production plan with respect to the production plan made based on the received order data. Production loss calculation program for calculating production loss caused by deviation, inventory loss calculation program for calculating inventory loss due to inventory caused by production plan, total for calculating total loss of production loss and inventory loss It has a loss calculation program and output means for outputting the calculated total loss. further,
It is preferable that the evaluation device has a stockout loss calculation program for calculating a stockout loss due to stockout of a part that occurs in a production plan. Further, the total loss calculation program of the evaluation device may include a step of multiplying each of the losses by a predetermined coefficient and converting the total loss as a monetary amount.

【0007】[0007]

【発明の実施の形態】以下に本発明の生産計画の評価方
法の一実施の形態を図面を参照して詳細に説明する。始
めに、生産計画の評価方法を実施するためのハードウェ
アについて説明する。図8にハードウェアの構成を示
す。本実施の形態の評価装置はパーソナルコンピュータ
11であり、演算手段であるCPU12とデータ記憶手
段であるディスク13より構成されている。CPU12
は、本発明に係る生産計画の評価方法を実施するための
プログラムを記憶するROM、一時的にデータを記憶す
るRAM等を含んでいる。また、CPU12には、キー
ボード、CRT、評価装置の出力手段であるプリンター
等の入出力端末装置14が接続されている。
BEST MODE FOR CARRYING OUT THE INVENTION An embodiment of the production plan evaluation method of the present invention will be described in detail below with reference to the drawings. First, the hardware for implementing the production plan evaluation method will be described. FIG. 8 shows the hardware configuration. The evaluation device of the present embodiment is a personal computer 11, which is composed of a CPU 12 which is a calculation means and a disk 13 which is a data storage means. CPU 12
Includes a ROM for storing a program for implementing the production planning evaluation method according to the present invention, a RAM for temporarily storing data, and the like. The CPU 12 is also connected with an input / output terminal device 14 such as a keyboard, a CRT, and a printer which is an output unit of the evaluation device.

【0008】図7に生産計画の評価方法を構成する具体
的手段の関係を示す。受注データを入力し記憶させるた
めの受注入力格納手段15、及び複数の生産計画立案プ
ログラムの中から評価対象としたい生産計画立案プログ
ラムを選択する順序計画方式選択手段16が、生産計画
評価プログラム17に接続している。また、複数の生産
計画立案プログラムを入力し記憶させるための順序計画
方式格納手段18、及び生産工程の各種パラメータを入
力し記憶させるための生産パターン入力格納手段19
が、生産計画評価プログラム17に接続している。ま
た、評価結果を出力するための評価結果出力手段20
が、生産計画評価プログラム17に接続している。生産
計画評価プログラム17には、コンピュータを用いて、
与えられた受注データに基づいて立案された生産計画に
対して、受注データの製品納期と生産計画による生産納
期とのずれから発生する生産損失を算出するための生産
損失算出プログラム171と、生産計画により発生する
在庫による在庫損失を算出するための在庫損失算出プロ
グラム172と、生産計画において発生する部品の欠品
による欠品損失を算出する欠品損失算出プログラム17
3と、それらの合計損失を算出する合計損失算出プログ
ラム174とが記憶されている。
FIG. 7 shows the relationship of concrete means constituting the production plan evaluation method. The order input storage means 15 for inputting and storing the order data, and the order planning method selecting means 16 for selecting a production planning program to be evaluated from a plurality of production planning programs are provided in the production planning evaluation program 17. Connected. Further, a sequence planning method storage means 18 for inputting and storing a plurality of production planning programs, and a production pattern input storage means 19 for inputting and storing various parameters of the production process.
Is connected to the production plan evaluation program 17. Further, the evaluation result output means 20 for outputting the evaluation result
Is connected to the production plan evaluation program 17. A computer is used for the production plan evaluation program 17,
A production loss calculation program 171 for calculating a production loss caused by a deviation between the product delivery date of the order data and the production delivery date according to the production plan for the production plan created based on the given order data, and the production plan Inventory loss calculation program 172 for calculating the inventory loss due to the inventory generated due to the inventory loss, and the missing item loss calculation program 17 for calculating the inventory loss due to the lack of parts that occur in the production plan.
3 and a total loss calculation program 174 for calculating the total loss thereof are stored.

【0009】次に、生産計画の評価方法について、図1
のフローチャートに基づいて詳細に説明する。 (1)基礎データの入力 S1に示す損失計算のための基礎データの入力について
説明する。基礎データとして入力が必要な情報は次のも
のである。 a)顧客からの受注オーダーを並べ換えるそれぞれの順
序計画の処理プログラム。 b)生産・部品調達モデルを規定する各種パラメータデ
ータ。 生産順序計画のプログラムは、順序計画方式格納手段1
8において入力し格納されるが、これは具体的には、入
出力端末装置14からCPU12を介してディスク13
に格納される。また、生産順序計画のプログラムの実行
もCPU12により行われる。この生産順序計画のプロ
グラムは任意に作成可能であるが、本実施の形態では先
着順方式、指定納期優先方式、部品使用頻度平準化方式
の3方式を例として説明する。この3方式の詳細内容は
後に説明する。
Next, the method of evaluating the production plan will be described with reference to FIG.
It will be described in detail based on the flowchart of FIG. (1) Input of Basic Data Input of basic data for the loss calculation shown in S1 will be described. The information that needs to be input as basic data is as follows. a) A processing program for each order plan for rearranging orders received from customers. b) Various parameter data that defines the production / parts procurement model. The production sequence planning program is the sequence planning method storage means 1.
8 is input and stored. Specifically, this is input from the input / output terminal device 14 via the CPU 12 to the disk 13
Is stored in The CPU 12 also executes the program of the production sequence plan. The program of the production order plan can be arbitrarily created, but in the present embodiment, three methods of the first-come-first-served method, the designated delivery date priority method, and the parts usage frequency leveling method will be described as an example. The details of these three methods will be described later.

【0010】次に生産計画が実施される生産工程の条件
等を規定するパラメータデータは、生産パターン入力格
納手段19に入力され記憶されるが、具体的手段は生産
順序計画のプログラムと同様である。生産・部品調達パ
ラメータデータとしては以下のものがある。 −生産パラメータデータ− a)生産計画立案タイミング:TO[時] (TO は今回の生産計画立案タイミングを示し、T-1
前回の生産計画立案タイミングを示し、T1 は次回の生
産計画立案タイミングを示す。) b)生産稼動パターン(生産工程の稼動時間と休止時間
の設定) c)生産能力:MAX[個/時間] d)生産計画の対象となる製品の種類数:P
Parameter data defining conditions of a production process for executing the next production plan are input and stored in the production pattern input storage means 19, and the specific means is the same as the program of the production sequence plan. . The following are production / parts procurement parameter data. -Production parameter data-a) Production plan drafting timing: T O [hours] (T O represents the current production plan drafting timing, T -1 represents the previous production plan drafting timing, and T 1 represents the next production plan It shows the planning timing.) B) Production operation pattern (setting of operation time and rest time of production process) c) Production capacity: MAX [pieces / hour] d) Number of types of products subject to production planning: P

【0011】−部品調達パラメータデータ− 部品調達は、部品使用量を所定納入便後に後補充する方
式を前提とする。ここで、実際の部品調達は1日数回の
トラック便により行われている。 a)部品の種類数:Q b)部品i(1,2,…i…Q)のTO後、初回の納入
タイミング:CO,i[時] (CO,i は今回の納入タイミングを示し、C-1,iは前回
の納入タイミングを示し、C1,iは次回の納入タイミン
グを示す。) c)部品i(1,2,…i…Q)の補充遅れ便数:Di
[回] d)製品種類ごとの構成部品表(図12参照)
-Parts Procurement Parameter Data-Parts procurement is premised on a method in which the amount of parts used is replenished after a predetermined delivery flight. Here, actual parts procurement is carried out several times a day by truck. a) the number of types of parts: Q b) parts i (1,2, ... i ... Q ) T O after, initial delivery timing: C O, i [time] (C O, i is the time the delivery timing , C -1, i indicates the previous delivery timing, and C 1, i indicates the next delivery timing.) C) Replenishment delay number of parts i (1, 2, ... i ... Q): D i
[Times] d) Component parts list for each product type (see Fig. 12)

【0012】また、在庫発生による損出計算用パラメー
タデータとしては以下のものがある。 −損失計算用パラメータデータ− a)部品i(1,2,…i…Q)の許容在庫量:LZi
[個] b)部品i(1,2,…i…Q)の許容在庫量を越えた
個数を損失に計算する係数:DZ(+,i)[円/個・時
間] c)部品i(1,2,…i…Q)の欠品個数を損失に計
算する係数:DZ(-,i)[円/個・時間] d)製品の、種類j(1,2,…j…P)毎の指定納期
からの遅れを損失に計算する係数:DN(+,j)[円/時
間] e)製品種類j(1,2,…j…P)毎の指定納期まで
の不足を損失に計算する係数:DN(-,j)[円/時間]
Further, the parameter data for calculating the loss due to the inventory occurrence is as follows. -Loss calculation parameter data-a) Allowable stock quantity of component i (1,2, ... i ... Q): LZ i
[Pieces] b) Coefficient for calculating loss as the number of parts i (1,2, ... i ... Q) exceeding the allowable inventory amount: DZ (+, i) [yen / piece / time] c) Parts i ( 1,2, ... i ... Q) Coefficient for calculating the number of missing items as loss: DZ (-, i) [yen / unit · time] d) Product type j (1,2, ... j ... P) Coefficient for calculating the delay from the specified delivery time for each loss: DN (+, j) [yen / hour] e) Loss due to lack of the specified delivery time for each product type j (1,2, ... j ... P) Coefficient to calculate: DN (-, j) [yen / hour]

【0013】ここで、LZi は、部品毎に、既存保管ス
ペースを目安に設定する。また、DZ(+,i )は、部品毎
に、在庫スペースを溢れた分が占めるスペースの地代の
利子分を目安に設定する。DZ(-,i )は、部品毎に、欠
品が生産を遅延する時間あたりの設備、作業者の損失金
額を目安に設定する。DN(+,j )は、納期遅れが機会損
失に及ぼす影響を販売の実体から判断し、製品種類毎の
売値を乗じた値を目安に設定する。DN(-,j )は、製品
毎に、製品在庫が及ぼす金利負担を目安に設定する。以
上が入力として必要とされるものであるが、前回生産計
画立案タイミングT-1以前に入力、あるいは計算された
結果のデータの中で、必要なものはCPU12によって
ディスク13に格納されている。
Here, LZ i is set for each part using the existing storage space as a guide. In addition, DZ (+, i) is set for each part by using the interest amount of the rent for the space occupied by the overflow of the stock space as a guide. DZ (-, i) is set for each part by using the amount of equipment lost by the equipment and the worker's loss per unit time as the production delays due to lack of parts. DN (+, j) is set based on the value obtained by multiplying the selling price for each product type by judging the effect of late delivery on opportunity loss from the sales entity. DN (-, j) is set for each product by using the interest rate burden on the product inventory as a guide. Although the above is required as an input, among the data of the results input or calculated before the previous production planning timing T −1 , the required data is stored in the disk 13 by the CPU 12.

【0014】それらのデータとしては以下のものがあ
る。 a)部品i(1,2,…i…Q)のTO以前の納入タイ
ミング:C-1,i,C-2,i,C-3,i,…[時] b)T-1の生産計画に則った最終製品生産後の部品i
(1,2,…i…Q)の在庫量:Z-1,L,i[個] c)T-1の生産計画に則った最終製品生産終了時間:S
-1,L[時]
The data are as follows. a) component i (1,2, ... i ... Q ) of T O previous delivery timing: C -1, i, C -2 , i, C -3, i, ... [ h] b) T -1 of Parts i after production of the final product according to the production plan
Inventory quantity of (1,2, ... i ... Q): Z -1, L, i [pieces] c) Final product production end time according to T -1 production plan: S
-1, L [hour]

【0015】(2)顧客受注オーダーの入力 次に、図1のS2に相当する、顧客受注オーダー入力に
ついて説明する。顧客受注オーダーは受注入力格納手段
15において入力され格納されるが、これは具体的に
は、入出力端末装置14からCPU12を介してディス
ク13に格納される。受注オーダーは生産計画立案タイ
ミング間で蓄積され、図9で示される形で格納される。
顧客受注オーダーの内容は、図9に示すように、オーダ
ーごとに割り当てる受注番号、製品種類、受注時期、顧
客の希望納入時期を明確化した指定納期である。指定納
期は本発明の損失評価において重要な役割を果す。
(2) Input of Customer Order Order Next, the customer order input corresponding to S2 of FIG. 1 will be described. The customer order is input and stored in the order input storage means 15, which is specifically stored in the disk 13 from the input / output terminal device 14 via the CPU 12. Orders are accumulated between production planning timings and stored in the form shown in FIG.
As shown in FIG. 9, the content of the customer order is a designated delivery date that clarifies the order number assigned to each order, the product type, the order reception time, and the customer desired delivery time. The designated delivery date plays an important role in the loss evaluation of the present invention.

【0016】顧客受注オーダーの内容について、後述の
損失計算に必要なパラメータデータを以下の通り定義す
る。 a)T-1〜TOの期間に蓄積された顧客受注オーダー
(以下TO受注オーダーと称す。)の数:R b)TO 受注オーダーの受注番号k(1,2,…k…
R)オーダーの受注時期:EO,k[時] c)TO 受注オーダーの受注番号k(1,2,…k…
R)オーダーの指定納期:NO.k[時]
Regarding the contents of the customer order, the parameter data necessary for the loss calculation described later are defined as follows. a) Number of customer order orders (hereinafter referred to as T O order orders) accumulated during the period of T −1 to T O : R b) Order number k (1, 2, ... K ...) of T O order orders.
R) Order acceptance time: E O, k [hours] c) T O Order acceptance order number k (1,2, ... k ...
R) Specified delivery date for order: N Ok [hours]

【0017】(3)生産順序計画立案 次に、図1のS3〜S6に相当する生産順序計画方式の
選択及び順序並び換えについて説明する。生産順序計画
方式の選択(S3)は順序計画方式選択手段16におい
て行うが、これは具体的には、入出力端末装置14の入
出力端末より、予め入力・格納されている順序計画のプ
ログラムのうち損失の評価を実施したい方式を複数選択
することである。選択された順序計画のプログラムは、
図1のS4〜S6に示すように、図9の顧客の受注オー
ダーを各々のプログラムにより順に並べ換える。順序計
画方式の例として以下の3方式を説明する。
(3) Formulation of Production Sequence Planning Next, selection and rearrangement of the production sequence planning method corresponding to S3 to S6 in FIG. 1 will be described. The selection of the production order planning method (S3) is performed by the order planning method selecting means 16. Specifically, this is performed by the input / output terminal of the input / output terminal device 14 of a program of the order planning which is previously input and stored. Of these, selecting multiple methods for which you want to evaluate loss. The selected sequence plan program is
As shown in S4 to S6 of FIG. 1, the customer order of FIG. 9 is rearranged in order by each program. The following three methods will be described as examples of the order planning method.

【0018】まず、先着順方式は、顧客からの受注時期
によって並べ換えを実施する。これは具体的には図9の
受注時期の昇順でソーディングを実施することである。
次に指定納期優先方式を説明する。ここでは顧客からの
受注時に、顧客の希望納入時期を明確にしてデータとし
て入力しておくことが前提となる。並べ替えは具体的に
は図9の指定納期の日付け順でソーティングを実施する
ことであり、図9を並び換えたものを図10に例として
示す。
First, in the first-come-first-served system, rearrangement is carried out according to the time of receiving an order from a customer. Specifically, this means that the sorting is performed in the ascending order of the order receiving time shown in FIG.
Next, the designated delivery date priority method will be described. Here, it is premised that the customer's desired delivery time is clarified and entered as data when an order is received from the customer. The rearrangement is specifically to carry out the sorting in the date order of the designated delivery date in FIG. 9, and FIG. 10 shows the rearranged one as an example.

【0019】最後に部品使用頻度平準化優先方式につい
て説明する。ここでは公知の技術である目標追跡法に基
づいた方法を示すこととする。図11〜図13におい
て、平準化が必要な部品を部品2、部品3であるとする
と、順番1の製品の種類はそれぞれの製品の比率×1−
0の最も大きいものを割り当てる。割り当った製品は順
番2の計算時に減ずる値を+1とする。順番2の製品種
類は、それぞれの製品の比率×2−0(順番1で割り当
った製品は1)の最も大きいものを割り当てる。以下最
後まで以上の方法で決めていく。図13を並び換える具
体的な計算の流れを図13に、並び換えた結果を図11
に示す。以上の3方式では、一般的に先着順方式は指定
納期と実納期のずれが大きくなる問題がある。また、指
定納期優先方式では指定納期と実納期のずれが少なくな
る反面、部品在庫ならびに部品欠品が増加する問題があ
る。また、部品平準化優先方式では部品在庫ならびに部
品欠品が減る反面、指定納期と実納期のずれが増加する
傾向となる。
Finally, the component usage frequency leveling priority method will be described. Here, a method based on a target tracking method which is a known technique will be shown. In FIGS. 11 to 13, assuming that the parts requiring leveling are the parts 2 and 3, the type of the product in the order 1 is the ratio of each product × 1−
Assign the largest of 0. For the assigned products, the value to be subtracted when calculating the order 2 is +1. For the product type of order 2, the largest product ratio x 2-0 (the product assigned in order 1 is 1) is assigned. Follow the steps above until the end. FIG. 13 shows a specific calculation flow for rearranging FIG. 13, and FIG. 11 shows the rearranged result.
Shown in In the above three methods, the first-come-first-served method generally has a problem that the difference between the designated delivery time and the actual delivery time becomes large. Further, in the designated delivery date priority method, the difference between the designated delivery date and the actual delivery date is reduced, but there is a problem that the parts inventory and the parts shortage increase. Further, in the parts leveling priority method, the parts inventory and the parts shortage decrease, but the gap between the designated delivery time and the actual delivery time tends to increase.

【0020】(4)在庫に関する損失計算 次に、図1のS7に相当する、在庫に関する損失計算方
法について説明する。本計算、及び次に述べる納期に関
する損失の計算は、生産計画評価プログラム17によっ
て実行される。これは具体的にはCPU12がディスク
13によって格納されたデータを使用して実施する。計
算方法の説明に先だって、説明の参考となる図4〜図6
の中で使用する記号や、損失計算に使用する記号、及び
関数の定義を行う。 a)TO 受注オーダーの生産順番m(1,2,…m…
R)ごとの部品i(1,2,…i…Q)の在庫量:Z
O,m,i[個]
(4) Loss Calculation for Inventory Next, a loss calculation method for inventory corresponding to S7 in FIG. 1 will be described. This calculation and the following calculation of the loss related to the delivery date are executed by the production plan evaluation program 17. This is specifically done by the CPU 12 using the data stored by the disk 13. Prior to the explanation of the calculation method, FIGS.
The symbols used in the above, symbols used for loss calculation, and functions are defined. a) T o Order-to-order production sequence m (1,2, ... m ...
Inventory quantity of parts i (1,2, ... i ... Q) for each R): Z
O, m, i [pieces]

【0021】[0021]

【式1】 ここで、関数f(x)は、プラス側のみを考慮するため
のものであり、関数g(x)は、マイナス側のみを考慮
するためのものであり、時間遅延または時間が早いこと
の一方のみを考慮するために用いる関数である。
(Equation 1) Here, the function f (x) is for considering only the plus side, and the function g (x) is for considering only the minus side. Is a function used to consider only

【0022】次に、それぞれの生産順序計画方式によっ
て実施された並べ換えごとに以下の損失を計算する。許
容在庫量オーバーによる損失合計の推定値V^[円]
は、次の式2のように示すことができる。
Next, the following losses are calculated for each sort performed by each production sequence planning method. Estimated total loss due to excess of allowable stock V ^ [yen]
Can be expressed as in Equation 2 below.

【式2】 ここで在庫ZO,m,iは ZO,m,i[個]=Z-1,L,i+(TOから生産順mの製品生
産までの時間内で納入される量)−(TOから生産順m
の製品生産までの時間内に使用する量) である。
(Equation 2) Here, the inventory Z O, m, i is Z O, m, i [pieces] = Z -1, L, i + (amount delivered in the time from T O to production of the product in the production order m) − ( Production order from T o m
The amount used in the time until the product is manufactured).

【0023】さらに、TO から生産順mの製品生産まで
の時間内で納入される量は、部品納入時期(…C-1,i
O,i,C1,i,…) 、T-1 の生産計画に則った最終製
品生産後の在庫量Z-1,L,i、補充遅れ便数Di[回]、
O以前の部品iの使用履歴から導かれる。また、TO
から生産順mの製品生産の時間内に使用する量は、生産
順m−1までの使用量に生産順mの製品の種類から引き
当てた部品iの使用量を加えることで導かれる。そし
て、部品欠品による損失合計の推定値W^[円]は、次
の式3のように示すことができる。
Further, the quantity delivered within the time from T O to the production of the product in the production order m is determined by the delivery time of the parts (... C -1, i ,
C O, i , C 1, i , ...), inventory quantity Z −1, L, i after final product production according to the production plan of T −1 , number of delayed delivery flights D i [times],
It is derived from the usage history of the part i before T o . Also, T O
The quantity used in the production time of the product in the production order m is derived by adding the usage amount of the part i assigned from the type of the product in the production order m to the usage amount up to the production order m-1. Then, the estimated value W ^ [yen] of the total loss due to the lack of parts can be expressed by the following Expression 3.

【式3】 (Equation 3)

【0024】(5)指定納期と実納期のずれによる損失
計算 次に、図1のS8に相当する、納期に関する損失計算に
ついて説明する。それぞれの生産順序計画方式によって
実施された並べ換えごとに以下の損失を計算する。指定
納期からの遅れ分による損失合計の推定値X^[円]
は、次の式4のように示すことができる。
(5) Loss Calculation Due to Deviation between Designated Delivery Date and Actual Delivery Date Next, the loss calculation regarding the delivery date, which corresponds to S8 in FIG. 1, will be described. The following losses are calculated for each sort performed by each production sequence planning method. Estimated total loss due to delay from designated delivery date X ^ [yen]
Can be expressed as in Equation 4 below.

【式4】 ここで、SO,k は受注番号k(1,2,…k…R)の製
品の生産終了時を表わし、SO,k はT-1の生産計画に則
った最終製品生産終了時間S-1,Lに、この製品の生産順
番に1個あたりの生産時間1/MAXを乗じたものを加
えることで導かれる。次に指定納期までの不足分による
損失合計の推定値Y^[円]は、次の式5のように示す
ことができる。
(Equation 4) Here, S O, k represents the production end time of the product of the order number k (1, 2, ... K ... R), and S O, k is the final product production end time S according to the production plan of T −1. It is derived by adding -1, L to the production order of this product multiplied by the production time 1 / MAX per piece. Next, the estimated value Y ^ [yen] of the total loss due to the shortfall until the designated delivery date can be expressed by the following Expression 5.

【式5】 (Equation 5)

【0025】(6)評価結果の出力 最後に図1のS9に相当する、評価結果の出力について
説明する。それぞれの生産順序計画方式によって実施さ
れた並べ換えごとに損失損失合計A^[円]は、次の式
6に示すように全ての損失の合計として計算できる。
(6) Output of Evaluation Result Finally, the output of the evaluation result corresponding to S9 in FIG. 1 will be described. The total loss loss A ^ [yen] for each rearrangement performed by each production sequence planning method can be calculated as the sum of all losses as shown in the following Expression 6.

【式6】 最終的には、A^が少ない順を、評価結果出力手段20
により出力する。これは具体的には入出力端末装置14
に表示する。以上のような作用により、あらかじめ入力
した生産順序計画方式のなかで、在庫および納期に関す
る損失が最も少ない方式を具体的に把握でき、最適な生
産順序計画方式にて生産を実施することができる。
(Equation 6) Finally, the evaluation result output means 20 is arranged in the order of smaller A ^.
Is output. This is specifically the input / output terminal device 14
To be displayed. With the above-described operation, it is possible to specifically grasp the method with the smallest loss regarding inventory and delivery among the preliminarily input production order planning methods, and it is possible to perform the production with the optimum production order planning method.

【0026】次に、以上説明した生産計画の評価方法を
具体例に適用した場合について詳細に説明する。図3に
詳細な前提条件である係数を表で示す。これらの係数
は、各損失を金額に換算するためのものである。次に、
図9に示した先着順方式で決定された生産計画を評価す
る例を図4に基づいて説明する。先に在庫に関する損出
計算を行う。式2により、部品1,2,3の在庫量が許
容在庫量LZi を越えた分に係数を乗じることにより、
許容在庫量オーバーにより発生する損出を金額換算した
値が求められる。すなわち、図中aで示す部分がLZi
を越えており、その部分を金額換算した値が求められ
る。図2に具体的な金額を算出した例を示す。係数とし
て図3に示すものを使用して求めたものである。これに
よると、許容在庫量のオーバーにより発生する損出金額
は、部品aによるものが0円、部品bによるものが14
0円、部品cによるものが0円であり、合計140円で
ある。
Next, the case where the above-described production plan evaluation method is applied to a specific example will be described in detail. FIG. 3 is a table showing the coefficients, which are detailed prerequisites. These coefficients are for converting each loss into a monetary amount. next,
An example of evaluating the production plan determined by the first-come-first-served method shown in FIG. 9 will be described with reference to FIG. Loss calculation for inventory is performed first. According to the equation 2, by multiplying the amount by which the inventory quantity of the parts 1, 2 and 3 exceeds the allowable inventory quantity LZ i by a coefficient,
A value obtained by converting the amount of loss caused by exceeding the allowable stock amount into an amount is obtained. That is, the portion indicated by a in the drawing is LZ i.
Is exceeded, and a value converted from that portion is calculated. FIG. 2 shows an example of calculating a specific amount of money. It is obtained by using the coefficient shown in FIG. According to this, the loss amount caused by exceeding the allowable stock amount is 0 yen for the part a and 14 for the part b.
0 yen, 0 yen for the part c, 140 yen in total.

【0027】また、式3により、部品1,2,3の在庫
量が欠品した分に係数を乗じることにより、部品欠品に
より発生する損出を金額換算した値が求められる。すな
わち、図中bで示す部分が0を下回っており、その部分
を金額換算した値が求められる。図2に示すように、具
体的金額を算出すると、部品欠品により発生する損出金
額は、部品aによるものが0円、部品bによるものが0
円、部品cによるものが50円であり、合計50円であ
る。
Further, according to the expression 3, a value obtained by converting the amount of loss caused by the lack of parts into a monetary amount is obtained by multiplying the stock amount of the parts 1, 2, 3 by the coefficient. That is, the portion indicated by b in the figure is less than 0, and a value obtained by converting the portion into a monetary amount is obtained. As shown in FIG. 2, when the specific amount of money is calculated, the loss amount caused by the part shortage is 0 yen for the part a and 0 for the part b.
A yen and a part c are 50 yen, which is 50 yen in total.

【0028】次に、指定納期からの遅れ分による損出を
式4により算出する。図4の上部に示すように、顧客指
定納入時間Nに対して、製品生産完了時間Sの遅れは、
図中プラスの時間として示されている。このプラスの時
間のみを累計して係数を乗じることにより、納期遅れに
より発生する損出を金額換算した値が求められる。図2
に示すように、具体的金額を算出すると、指定納期から
の遅れにより発生する損出金額は、生産順位1によるも
のが80円、生産順位2によるものが0円、生産順位3
によるものが360円、生産順位4によるものが0円、
生産順位5によるものが160円、生産順位6によるも
のが0円、生産順位7によるものが0円、生産順位8に
よるものが0円、生産順位9によるものが0円、生産順
位10によるものが160円であり、合計760円であ
る。
Next, the loss due to the delay from the designated delivery date is calculated by the equation (4). As shown in the upper part of FIG. 4, the delay of the product production completion time S with respect to the customer-specified delivery time N is
It is shown as plus time in the figure. By accumulating only this plus time and multiplying it by a coefficient, a value obtained by converting the amount of loss caused by delay in delivery into an amount can be obtained. FIG.
As shown in, when the specific amount of money is calculated, the loss amount due to the delay from the designated delivery date is 80 yen for the production order 1, 0 yen for the production order 2, and the production order 3
360 yen for production, 0 for production order 4,
160 yen for production rank 5, 0 yen for production rank 6, 0 yen for production rank 7, 0 yen for production rank 8, 0 yen for production rank 9, 0 yen for production rank 10. Is 160 yen, for a total of 760 yen.

【0029】次に、早く生産したことにより発生する指
定納期までの不足による損失を式5により算出する。図
4の上部に示すように、顧客指定納入時間Nに対して、
製品生産完了時間Sが早すぎることによる不足は、図中
マイナスの時間として示されている。このマイナスの時
間のみを累計して係数を乗じることにより、納期遅れに
より発生する損出を金額換算した値が求められる。図2
に示すように、具体的金額を算出すると、指定納期まで
の不足により発生する損出金額は、生産順位1によるも
のが0円、生産順位2によるものが400円、生産順位
3によるものが0円、生産順位4によるものが640
円、生産順位5によるものが0円、生産順位6によるも
のが0円、生産順位7によるものが0円、生産順位8に
よるものが120円、生産順位9によるものが40円、
生産順位10によるものが0円であり、合計1200円
である。従って、先着順方式により立案された生産計画
による損失金額の合計は、2150円である。
Next, the loss due to the shortage until the designated delivery date, which is caused by the early production, is calculated by the equation 5. As shown in the upper part of FIG. 4, for the customer-specified delivery time N,
The shortage due to the product production completion time S being too early is shown as a negative time in the figure. By accumulating only this minus time and multiplying it by a coefficient, a value obtained by converting the amount of loss caused by late delivery into an amount can be obtained. FIG.
As shown in, when calculating the concrete amount, the loss amount caused by the shortage by the designated delivery date is 0 yen for the production order 1, 400 yen for the production order 2, and 0 for the production order 3. Yen, 640 according to production ranking 4
Yen, production order 5 is 0 yen, production order 6 is 0 yen, production order 7 is 0 yen, production order 8 is 120 yen, production order 9 is 40 yen,
The production rank 10 is 0 yen, for a total of 1200 yen. Therefore, the total amount of loss due to the production plan designed by the first-come-first-served method is 2150 yen.

【0030】次に、図10示した納期優先方式で決定さ
れた生産計画を評価する例を図5に基づいて説明する。
先に在庫に関する損出計算を行う。式2により、部品
1,2,3の在庫量が許容在庫量LZi を越えた分に係
数を乗じることにより、許容在庫量オーバーにより発生
する損出を金額換算した値が求められる。すなわち、図
中cで示す部分がLZi を越えており、その部分を金額
換算した値が求められる。図2に具体的な金額を算出し
た例を示す。係数として図3に示すものを使用して求め
たものである。これによると、許容在庫量のオーバーに
より発生する損出金額は、140円である。また、式3
により、部品1,2,3の在庫量が欠品した分に係数を
乗じることにより、部品欠品により発生する損出を金額
換算した値が求められる。すなわち、図中dで示す部分
が0を下回っており、その部分を金額換算した値が求め
られる。図2に示すように、具体的金額を算出すると、
部品欠品により発生する損出金額は、250円である。
Next, an example of evaluating the production plan determined by the delivery date priority method shown in FIG. 10 will be described with reference to FIG.
Loss calculation for inventory is performed first. According to Equation 2, by multiplying the amount by which the inventory quantity of the parts 1, 2 and 3 exceeds the allowable inventory quantity LZ i by a coefficient, a value obtained by converting the amount of loss caused by the excess of the allowable inventory quantity into an amount is obtained. That is, the portion indicated by c in the figure exceeds LZ i , and a value obtained by converting the portion into a monetary amount is obtained. FIG. 2 shows an example of calculating a specific amount of money. It is obtained by using the coefficient shown in FIG. According to this, the loss amount generated due to the excess of the allowable stock amount is 140 yen. Also, Equation 3
Thus, by multiplying the stock quantity of the parts 1, 2, and 3 by the coefficient, a value obtained by converting the loss caused by the stock of the parts into a monetary amount is obtained. That is, the portion indicated by d in the figure is less than 0, and a value obtained by converting the portion into a monetary amount is obtained. As shown in FIG. 2, when the specific amount of money is calculated,
The amount of loss caused by missing parts is 250 yen.

【0031】次に、指定納期からの遅れ分による損出を
式4により算出する。図5の上部に示すように、顧客指
定納入時間Nに対して、製品生産完了時間Sの遅れは、
図中プラスの時間として示されている。このプラスの時
間のみを累計して係数を乗じることにより、納期遅れに
より発生する損出を金額換算した値が求められる。図2
に示すように、具体的金額を算出すると、指定納期から
の遅れにより発生する損出金額は、320円である。次
に、早く生産したことにより発生する指定納期までの不
足による損失を式5により算出する。図5の上部に示す
ように、顧客指定納入時間Nに対して、製品生産完了時
間Sが早すぎることによる不足は、図中マイナスの時間
として示されている。このマイナスの時間のみを累計し
て係数を乗じることにより、納期遅れにより発生する損
出を金額換算した値が求められる。図2に示すように、
具体的金額を算出すると、指定納期までの不足により発
生する損出金額は、400円である。従って、納期優先
方式により立案された生産計画における損失金額の合計
は、1110円である。
Next, the loss due to the delay from the designated delivery date is calculated by the equation 4. As shown in the upper part of FIG. 5, the delay of the product production completion time S with respect to the customer-specified delivery time N is
It is shown as plus time in the figure. By accumulating only this plus time and multiplying it by a coefficient, a value obtained by converting the amount of loss caused by delay in delivery into an amount can be obtained. FIG.
As shown in, when the specific amount of money is calculated, the loss amount caused by the delay from the designated delivery date is 320 yen. Next, the loss due to the shortage until the designated delivery date, which occurs due to the early production, is calculated by the formula 5. As shown in the upper part of FIG. 5, the shortage due to the product production completion time S being too early with respect to the customer-specified delivery time N is shown as a negative time in the figure. By accumulating only this minus time and multiplying it by a coefficient, a value obtained by converting the amount of loss caused by late delivery into an amount can be obtained. As shown in FIG.
When the specific amount of money is calculated, the loss amount caused by the shortage by the designated delivery date is 400 yen. Therefore, the total loss amount in the production plan designed by the delivery date priority method is 1110 yen.

【0032】次に、図11示した部品平準化優先方式で
決定された生産計画を評価する例を図6に基づいて説明
する。先に在庫に関する損出計算を行う。式2により、
部品1,2,3の在庫量が許容在庫量LZi を越えた分
に係数を乗じることにより、許容在庫量オーバーにより
発生する損出を金額換算した値が求められる。すなわ
ち、図中eで示す部分がLZi を越えており、その部分
を金額換算した値が求められる。図2に具体的な金額を
算出した例を示す。係数として図3に示すものを使用し
て求めたものである。これによると、許容在庫量のオー
バーにより発生する損出金額は、60円である。また、
式3により、部品1,2,3の在庫量が欠品した分に係
数を乗じることにより、部品欠品により発生する損出を
金額換算した値が求められる。すなわち、図中fで示す
部分が0を下回っており、その部分を金額換算した値が
求められる。図2に示すように、具体的金額を算出する
と、部品欠品により発生する損出金額は、50円であ
る。
Next, an example of evaluating the production plan determined by the parts leveling priority method shown in FIG. 11 will be described with reference to FIG. Loss calculation for inventory is performed first. According to Equation 2,
By multiplying the amount by which the inventory quantity of the parts 1, 2 and 3 exceeds the allowable inventory quantity LZ i by a coefficient, a value obtained by converting the loss caused by the excess of the allowable inventory quantity into an amount is obtained. That is, the portion indicated by e in the figure exceeds LZ i , and a value obtained by converting the portion into a monetary amount is obtained. FIG. 2 shows an example of calculating a specific amount of money. It is obtained by using the coefficient shown in FIG. According to this, the loss amount caused by the excess of the allowable stock amount is 60 yen. Also,
According to Equation 3, by multiplying the stock quantity of the parts 1, 2, and 3 by the coefficient, a value obtained by converting the loss caused by the stock of the parts into a monetary amount is obtained. That is, the portion indicated by f in the figure is less than 0, and a value obtained by converting the portion into a monetary amount is obtained. As shown in FIG. 2, when the specific amount of money is calculated, the loss amount caused by the lack of parts is 50 yen.

【0033】次に、指定納期からの遅れ分による損出を
式4により算出する。図6の上部に示すように、顧客指
定納入時間Nに対して、製品生産完了時間Sの遅れは、
図中プラスの時間として示されている。このプラスの時
間のみを累計して係数を乗じることにより、納期遅れに
より発生する損出を金額換算した値が求められる。図2
に示すように、具体的金額を算出すると、指定納期から
の遅れにより発生する損出金額は、920円である。次
に、早く生産したことにより発生する指定納期までの不
足による損失を式5により算出する。図6の上部に示す
ように、顧客指定納入時間Nに対して、製品生産完了時
間Sが早すぎることによる不足は、図中マイナスの時間
として示されている。このマイナスの時間のみを累計し
て係数を乗じることにより、納期遅れにより発生する損
出を金額換算した値が求められる。図2に示すように、
具体的金額を算出すると、指定納期までの不足により発
生する損出金額は、600円である。従って、納期優先
方式により立案された生産計画における損失金額の合計
は、1630円である。
Next, the loss due to the delay from the designated delivery date is calculated by the equation 4. As shown in the upper part of FIG. 6, the delay of the product production completion time S with respect to the customer-specified delivery time N is
It is shown as plus time in the figure. By accumulating only this plus time and multiplying it by a coefficient, a value obtained by converting the amount of loss caused by delay in delivery into an amount can be obtained. FIG.
As shown in, when the specific amount of money is calculated, the amount of loss that occurs due to the delay from the designated delivery date is 920 yen. Next, the loss due to the shortage until the designated delivery date, which occurs due to the early production, is calculated by the formula 5. As shown in the upper part of FIG. 6, the shortage due to the product production completion time S being too early with respect to the customer-specified delivery time N is shown as a negative time in the figure. By accumulating only this minus time and multiplying it by a coefficient, a value obtained by converting the amount of loss caused by late delivery into an amount can be obtained. As shown in FIG.
When the specific amount of money is calculated, the amount of loss that occurs due to a shortage by the designated delivery date is 600 yen. Therefore, the total loss amount in the production plan designed by the delivery date priority method is 1630 yen.

【0034】以上の評価結果を一覧表にしたのが図2で
ある。これによれば、先着順方式により立案された生産
計画の合計損失金額は、2150円であり、納期優先方
式により立案された生産計画の合計損失金額は、111
0円であり、部品平準化優先方式により立案された生産
計画の合計損失金額は、1630円である。従って、同
じ受注データにより立案された3つの生産計画の中で、
納期優先方式により立案された生産計画が最も優れてい
ると判断でき、これを採用することができる。
FIG. 2 shows a list of the above evaluation results. According to this, the total loss amount of the production plan made by the first-come-first-served method is 2150 yen, and the total loss amount of the production plan made by the delivery date priority method is 111
It is 0 yen, and the total loss amount of the production plan designed by the parts leveling priority method is 1630 yen. Therefore, in the three production plans that were planned with the same order data,
It can be judged that the production plan prepared by the delivery date priority method is the best, and it can be adopted.

【0035】以上詳細に説明したように、本実施の形態
の生産計画の評価方法及び費用か装置によれば、与えら
れた受注データに基づいて立案された生産計画に対し
て、受注データの製品納期と生産計画による生産納期と
のずれから発生する生産損失金額、生産計画により発生
する在庫による在庫損失金額、及び生産計画において発
生する部品の欠品による欠品損失金額とを各々算出し、
合計して合計損失を金額として比較しているので、複数
の生産計画の良否を容易に識別することができ、最適な
生産計画を採用することができる。また、本実施の形態
の生産計画の評価方法及び評価装置によれば、各損失の
各々に所定の係数を乗じて、合計損失を金額として換算
しているので、各工程のパラメータデータに合わせて適
切かつ容易に係数を選ぶことができ、各工程毎に最適な
評価方法及び評価装置を提供できる。
As described in detail above, according to the production plan evaluation method and cost or device of the present embodiment, the product of the order data is compared with the production plan made based on the received order data. Calculate the production loss amount due to the difference between the delivery date and the production delivery date according to the production plan, the inventory loss amount due to the inventory due to the production plan, and the out-of-stock loss amount due to the lack of parts in the production plan,
Since the total losses are compared as the amount of money, the quality of a plurality of production plans can be easily identified, and the optimum production plan can be adopted. Further, according to the production planning evaluation method and the evaluation device of the present embodiment, since each loss is multiplied by a predetermined coefficient and the total loss is converted as the amount of money, it is adjusted according to the parameter data of each process. A coefficient can be appropriately and easily selected, and an optimum evaluation method and evaluation apparatus can be provided for each process.

【0036】以上いくつかの実施の形態について説明し
たが、本発明は上記実施の形態に何ら限定されるもので
はなく、本発明の趣旨を逸脱しない範囲で種々の設計変
更が可能である。本実施の形態では生産計画として、先
着順方式により立案された計画、納期優先方式により立
案された計画、及び部品平準化方式により立案された計
画の3種類の生産計画について説明したが、他の方式に
より立案された計画に対しても本生産計画の評価方法が
適用できることは当然である。また、本実施の形態で
は、全てを金額として表示しているが、特定の単位によ
り次元を同一化して比較評価しても同様である。
Although several embodiments have been described above, the present invention is not limited to the above embodiments, and various design changes can be made without departing from the spirit of the present invention. In the present embodiment, as the production plan, three types of production plans, that is, a plan made by the first-come-first-served method, a plan made by the delivery date priority method, and a plan made by the parts leveling method have been described. It goes without saying that the evaluation method of this production plan can also be applied to plans drafted by the method. Further, in the present embodiment, all are displayed as the amount of money, but the same applies when the dimensions are made the same by a specific unit and comparative evaluation is performed.

【0037】[0037]

【発明の効果】本発明の生産計画の評価方法及び評価装
置によれば、与えられた受注データに基づいて立案され
た生産計画に対して、受注データの製品納期と生産計画
による生産納期とのずれから発生する生産損失、生産計
画により発生する在庫による在庫損失とを各々算出し、
合計して合計損失を比較しているので、複数の生産計画
の良否を容易に識別することができ、最適な生産計画を
採用することができる。
According to the method and apparatus for evaluating a production plan of the present invention, the product delivery date of the order data and the production delivery date according to the production plan are compared with the production plan planned based on the received order data. Calculate the production loss caused by the deviation and the inventory loss due to the inventory caused by the production plan,
Since the total losses are compared in total, the quality of a plurality of production plans can be easily identified, and the optimum production plan can be adopted.

【図面の簡単な説明】[Brief description of the drawings]

【図1】生産計画の評価方法のフローチャートである。FIG. 1 is a flowchart of a method for evaluating a production plan.

【図2】生産計画の評価方法により求めた損失金額の比
較表である。
FIG. 2 is a comparison table of loss amounts calculated by a production plan evaluation method.

【図3】前提条件となる係数の具体例を示す表である。FIG. 3 is a table showing a specific example of coefficients that are prerequisites.

【図4】先着順方式により立案された生産計画を評価す
る手順を説明する説明図である。
FIG. 4 is an explanatory diagram illustrating a procedure for evaluating a production plan that is planned by the first-come-first-served method.

【図5】納期優先方式により立案された生産計画を評価
する手順を説明する説明図である。
FIG. 5 is an explanatory diagram for explaining a procedure for evaluating a production plan designed by the delivery date priority method.

【図6】部品平準化優先方式により立案された生産計画
を評価する手順を説明する説明図である。
FIG. 6 is an explanatory diagram illustrating a procedure for evaluating a production plan designed by the component leveling priority method.

【図7】生産計画の評価方法を構成する手段の関係を示
す概念図である。
FIG. 7 is a conceptual diagram showing a relationship among means constituting a production plan evaluation method.

【図8】生産計画の評価方法を行うハードウェアの構成
を示すブロック図である。
FIG. 8 is a block diagram showing a hardware configuration for performing a production plan evaluation method.

【図9】先着順方式により立案された生産計画を示す表
である。
FIG. 9 is a table showing a production plan designed by the first-come-first-served method.

【図10】納期優先方式により立案された生産計画を示
す表である。
FIG. 10 is a table showing a production plan designed by the delivery date priority method.

【図11】部品平準化方式により立案された生産計画を
示す表である。
FIG. 11 is a table showing a production plan designed by the parts leveling method.

【図12】製品と部品との関係を示す表である。FIG. 12 is a table showing a relationship between products and parts.

【図13】部品平準化方式を説明するための説明図であ
る。
FIG. 13 is an explanatory diagram for explaining a component leveling system.

【符号の説明】[Explanation of symbols]

11 パーソナルコンピュータ 12 CPU 13 ディスク 14 入出力端末装置 15 受注入力格納手段 16 順序計画方式選択手段 17 生産計画評価プログラム 171 生産損失算出プログラム 172 在庫損失算出プログラム 173 欠品損失算出プログラム 174 合計損失算出プログラム 18 順序計画方式格納手段 19 生産パターン入力格納手段 20 評価結果出力手段 11 personal computer 12 CPU 13 disk 14 input / output terminal device 15 order input storage means 16 order planning method selection means 17 production plan evaluation program 171 production loss calculation program 172 inventory loss calculation program 173 missing item loss calculation program 174 total loss calculation program 18 Sequential planning method storage means 19 Production pattern input storage means 20 Evaluation result output means

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 コンピュータを用いて、与えられた受注
データに基づいて立案された生産計画に対して、 前記受注データの製品納期と前記生産計画による生産納
期とのずれから発生する生産損失、前記生産計画により
発生する在庫による在庫損失との合計損失を算出し、 前記算出された合計損失を出力する生産計画の評価方
法。
1. A production loss caused by a deviation between a product delivery date of the order data and a production delivery date of the production plan for a production plan made based on given order data using a computer, A method for evaluating a production plan, which calculates a total loss together with an inventory loss due to an inventory generated in the production plan, and outputs the calculated total loss.
【請求項2】 請求項1に記載する方法において、 前記生産計画において発生する部品の欠品による欠品損
失を算出して、前記合計損失に算入することを特徴とす
る生産計画の評価方法。
2. The method for evaluating a production plan according to claim 1, further comprising calculating a shortage loss due to a shortage of parts that occurs in the production plan and including the loss in the total loss.
【請求項3】 請求項1または請求項2に記載する方法
において、 前記各損失の各々に所定の係数を乗じて、前記合計損失
を金額として換算することを特徴とする生産計画の評価
方法。
3. The method for evaluating a production plan according to claim 1, wherein each of the losses is multiplied by a predetermined coefficient to convert the total loss as a monetary amount.
【請求項4】 請求項1乃至請求項3のうち、少なくと
も1つの評価方法を実行するプログラムが記憶されたコ
ンピュータ可読記録媒体。
4. A computer-readable recording medium in which a program for executing at least one evaluation method according to claim 1 is stored.
【請求項5】 コンピュータを用いて、与えられた受注
データに基づいて立案された生産計画に対して、 前記受注データの製品納期と前記生産計画による生産納
期とのずれから発生する生産損失を算出する生産損失算
出プログラムと、 前記生産計画により発生する在庫による在庫損失を算出
する在庫損失算出プログラムと、 前記生産損失と前記在庫損失との合計損失を算出する合
計損失算出プログラムと、 前記算出された合計損失を出力する出力手段とを有する
ことを特徴とする生産計画の評価装置。
5. A computer is used to calculate a production loss caused by a deviation between a product delivery date of the order data and a production delivery date of the production plan, for a production plan made based on given order data. A production loss calculation program, an inventory loss calculation program that calculates an inventory loss due to inventory generated by the production plan, a total loss calculation program that calculates a total loss of the production loss and the inventory loss, and the calculated An apparatus for evaluating a production plan, comprising: an output unit that outputs a total loss.
JP24928896A 1995-09-12 1996-08-30 Evaluation method and evaluation device for production planning Pending JPH09136245A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP24928896A JPH09136245A (en) 1995-09-12 1996-08-30 Evaluation method and evaluation device for production planning

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP26074195 1995-09-12
JP7-260741 1995-09-12
JP24928896A JPH09136245A (en) 1995-09-12 1996-08-30 Evaluation method and evaluation device for production planning

Publications (1)

Publication Number Publication Date
JPH09136245A true JPH09136245A (en) 1997-05-27

Family

ID=26539203

Family Applications (1)

Application Number Title Priority Date Filing Date
JP24928896A Pending JPH09136245A (en) 1995-09-12 1996-08-30 Evaluation method and evaluation device for production planning

Country Status (1)

Country Link
JP (1) JPH09136245A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003263217A (en) * 2002-03-11 2003-09-19 Toshiba Corp Production risk management method and its system, and method for producing products
JP2007310434A (en) * 2006-05-16 2007-11-29 Hitachi Ltd Evaluation system for procurement and production structure
JP2011150557A (en) * 2010-01-22 2011-08-04 Hitachi Ltd Forecast management system, its control method, and its program

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003263217A (en) * 2002-03-11 2003-09-19 Toshiba Corp Production risk management method and its system, and method for producing products
JP2007310434A (en) * 2006-05-16 2007-11-29 Hitachi Ltd Evaluation system for procurement and production structure
JP2011150557A (en) * 2010-01-22 2011-08-04 Hitachi Ltd Forecast management system, its control method, and its program

Similar Documents

Publication Publication Date Title
US5971585A (en) Best can do matching of assets with demand in microelectronics manufacturing
US7092929B1 (en) Method and apparatus for planning analysis
EP1107147A2 (en) Demand-production scheme planning apparatus and storage medium
CN108985527A (en) A kind of order delivery date appraisal procedure based on Dynamic Productivity Calculation
US7369910B2 (en) Method for the optimizing of a production process
JP2007140785A (en) Inventory management system
Tavaghof-Gigloo et al. Planning approaches for stochastic capacitated lot-sizing with service level constraints
US7123977B2 (en) Production planning system
US20090118854A1 (en) Production planning support method and its system
EP1701302A1 (en) Ordering/order receiving system
JP2002504726A (en) Process control method and system
US20020188529A1 (en) System and method for calculation of controlling parameters for a computer based inventory management
JP2006004414A (en) Production plan generation method, production plan generation device and program
JP2002541564A (en) System and method for scheduling manufacturing resources
JPH08212261A (en) Starting plan forming device
JPH09136245A (en) Evaluation method and evaluation device for production planning
JPH0798741A (en) Integrated management method for production sales article
JP3240237B2 (en) Production planning system
CN101111858A (en) Delivery date reply system, delivery date reply method, and delivery date reply program
JP3671809B2 (en) Inventory management support device
JP2006331459A (en) Integrated management method for production, sales and distribution
KR100780103B1 (en) Method for yieding material requirement and product planning requirement and record media recored program for realizing the same
JP3216578B2 (en) Appropriate stock quantity determining method, proper stock quantity determining device, and recording medium
JP2004292101A (en) System and method for supporting order processing
US20030204468A1 (en) Stock planning method