JPH0868039A - Concrete dam and construction method thereof - Google Patents

Concrete dam and construction method thereof

Info

Publication number
JPH0868039A
JPH0868039A JP20783394A JP20783394A JPH0868039A JP H0868039 A JPH0868039 A JP H0868039A JP 20783394 A JP20783394 A JP 20783394A JP 20783394 A JP20783394 A JP 20783394A JP H0868039 A JPH0868039 A JP H0868039A
Authority
JP
Japan
Prior art keywords
concrete
dam
precast
precast plate
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP20783394A
Other languages
Japanese (ja)
Inventor
Akiji Ogawa
朗二 小川
Masashi Funahashi
政司 舟橋
Yuji Akasaka
雄司 赤坂
Natsuo Hara
夏生 原
Hideaki Asai
秀明 浅井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Original Assignee
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp filed Critical Maeda Corp
Priority to JP20783394A priority Critical patent/JPH0868039A/en
Publication of JPH0868039A publication Critical patent/JPH0868039A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

PURPOSE: To rapidly and safely construct a dam and obtain a high quality dam, by erecting respective dam surface layers by use of a number of precast boards in both up and don stream sides in the construction area of the dam and placing concrete between the dam surface layers. CONSTITUTION: This construction method is constituted of a dam body 20 made of concrete 11 and dam surfaces 10 formed respectively by a number of precast boards 1 on the upstream side and the downstream side of the dam body 20. In this case, a space S1 for placing concrete is formed in the inside by precast boards 1. The space S1 is filled with left-in-place-concrete with the precast boards 1. Moreover, a plurality of precast boards 1 are laid on the concrete 11 already placed on respective upper end of precast boards 1 arranged on the up and don stream sides of the construction area Sd. And concrete 11 is placed in the next concrete space S1. In this way, such processes are repeated to construct a bank.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、主にコンクリートによ
り河川や渓谷を横断して形成され、上流部に河水或いは
流出土砂を貯留するコンクリートダム及びその施工方法
に係わり、特に、迅速、安全、且つ高品質な施工を可能
とするコンクリートダム及びその施工方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a concrete dam which is formed mainly of concrete across rivers and valleys and stores river water or runoff in the upstream, and a construction method thereof, and particularly to quick, safe, The present invention also relates to a concrete dam that enables high-quality construction and a construction method thereof.

【0002】[0002]

【従来の技術】従来、コンクリートダムの施工は、ダム
施工領域を左右岸方向に15m程度のブロックに区分け
し、そのブロックの上流側及び下流側に型枠を設置し、
その型枠内部にコンクリートを打設するようにして、各
ブロック毎にコンクリートを順次打設し、既打設のコン
クリートの上に更に上述同様にコンクリートを打設する
ようにして行なわれている。また、コンクリートダムの
施工の迅速化を可能としたRCD工法の場合には、図1
4に示すように、上流側及び下流側に設置された型枠1
01の間にセメント量を減じたノースランプの超硬練り
コンクリート102をダンプトラック103で運搬し、
ブルドーザー104で敷き均し、振動ローラー105、
バイブロドーザー106で締め固め、亀裂防止の横目地
107を振動式目地切機108で入れるようにして行な
われる。
2. Description of the Related Art Conventionally, in the construction of concrete dams, the dam construction area is divided into blocks of about 15 m in the left and right bank direction, and formworks are installed on the upstream and downstream sides of the blocks.
Concrete is poured into each of the blocks so that concrete is sequentially placed in each block, and concrete is placed in the same manner as above on the already placed concrete. In addition, in the case of the RCD method that enables speedy construction of concrete dams,
As shown in 4, the formwork 1 installed on the upstream side and the downstream side
During 01, the North Lamp super-hard concrete 102 with reduced cement content is transported by the dump truck 103,
Spread it with a bulldozer 104, level it with a vibrating roller 105,
The vibrodozer 106 is used for compaction, and the horizontal joint 107 for preventing cracks is inserted by the vibration jointing machine 108.

【0003】いずれにしても、従来のコンクリートダム
の施工では、ダム施工領域の上流側及び下流側に、コン
クリート打設空間S11を形成するように型枠101を
設置し、型枠101により形成されたコンクリート打設
空間S11にコンクリート102を打設し、そのコンク
リート102が硬化した後、型枠101を、上方に移動
し、その既打設のコンクリート102により形成された
堤体110の上流側及び下流側に取り付け、既打設のコ
ンクリート102の上に次なるコンクリート打設空間S
11を形成し、そのコンクリート打設空間S11にコン
クリート打設するようにしてコンクリート102を打ち
上げていき、ダムを施工する。この際に用いられる型枠
101には、幅50cm、長さ150cm程度の小さな
鋼製型枠を組み立てて形成される大型枠101が通常用
いられるが、近年は、図15に示すような、自らが堤体
110にアンカーを取りながら移動する型枠である、い
わゆる自動型枠120も用いられるようになっている。
In any case, in the conventional construction of a concrete dam, the formwork 101 is installed so as to form the concrete placing space S11 on the upstream side and the downstream side of the dam construction area, and the formwork 101 is formed. After the concrete 102 is poured into the concrete placing space S11 and the concrete 102 is hardened, the form 101 is moved upward and the upstream side of the bank 110 formed by the already placed concrete 102 and Installed on the downstream side, the next concrete placing space S is placed on the already placed concrete 102.
11 is formed, and the concrete 102 is launched in such a manner that the concrete is placed in the concrete placing space S11, and the dam is constructed. As the mold 101 used at this time, a large frame 101 formed by assembling a small steel mold having a width of 50 cm and a length of 150 cm is usually used, but in recent years, as shown in FIG. A so-called automatic formwork 120, which is a formwork that moves while anchoring the bank 110, is also used.

【0004】尚、自動型枠120の概略を説明すれば、
作業足場等が形成され、堤体110に着脱自在に設けら
れた自昇フレーム121を有しており、自昇フレーム1
21には、上下方向に伸縮自在なブーム122aを備え
た自昇装置122が設けられている。ブーム122aの
上端は、堤体110の上流側又は下流側に設けられた型
枠123の上端に着脱自在であり、型枠123には、左
右岸方向に沿う横行レール124が上下に複数設けられ
ている。また、自昇装置122には、横行レール124
に沿って移動自在な横行装置125が設けられている。
従って、ブーム122aの上端を型枠123に取り付け
ると共に、自昇フレーム121を堤体110に取り付
け、ブーム122aを伸ばすことにより、型枠123を
上方に移動させることが出来る。また、型枠123を堤
体110に取り付けた後に、自昇フレーム121を堤体
110から取り外し、ブーム122aを縮めることによ
り、自昇フレーム121を上方に引上げることが出来
る。よって、自動型枠120は、その型枠123と共に
上下方向に移動自在である。また、自動型枠120は、
自昇フレーム121を堤体110から取り外し、ブーム
122aの上端を型枠123から取り外し、横行装置1
25を型枠123に設けられた横行レール124に装着
すると、その横行装置125により横行レール124に
沿って左右岸方向に移動自在となる。よって、そのレー
ル124に沿って、左右岸方向に隣接する型枠123に
乗り移ることが出来るので、左右岸方向に連設される型
枠123を全て上方に移動させることが出来る。
The outline of the automatic form 120 will be described below.
A working scaffold or the like is formed, and a self-propelled frame 121 detachably provided on the bank 110 is provided.
21 is provided with a self-propelling device 122 having a boom 122a that is vertically expandable and contractible. The upper end of the boom 122a is attachable to and detachable from the upper end of the form 123 provided on the upstream side or the downstream side of the bank 110, and the form 123 is provided with a plurality of traverse rails 124 extending in the left-right bank direction. ing. Further, the self-propelling device 122 includes a traverse rail 124.
A traversing device 125 is provided which is movable along.
Therefore, by attaching the upper end of the boom 122a to the form 123, attaching the self-raising frame 121 to the bank 110, and extending the boom 122a, the form 123 can be moved upward. Moreover, after attaching the form 123 to the bank 110, the self-climbing frame 121 can be pulled upward by removing the self-climbing frame 121 from the dam 110 and retracting the boom 122a. Therefore, the automatic mold 120 is movable in the vertical direction together with the mold 123. In addition, the automatic form 120
The self-climbing frame 121 is removed from the bank 110, the upper end of the boom 122a is removed from the form 123, and the traverse device 1
When 25 is mounted on the traverse rail 124 provided on the form 123, the traverse device 125 allows the traverse rail 124 to move in the left and right bank directions. Therefore, along the rails 124, it is possible to transfer to the adjacent molds 123 in the left and right bank direction, and thus all the molds 123 that are continuously provided in the left and right bank direction can be moved upward.

【0005】[0005]

【発明が解決しようとする課題】しかし、従来のコンク
リートダムの施工では、以下に示す(イ)、(ロ)、
(ハ)のような問題を有している。 (イ)型枠の設置、取り外し、移動、解体等の大掛かり
な作業を要するため、更なる施工の迅速化を図ることが
難しい。 (ロ)既打設のコンクリートにより形成される堤体の上
流側及び下流側に型枠を取り付ける作業、及び、移動の
ために取り外す作業等の、高所での大掛かりな作業が必
要であるため、作業者の安全管理に多大な労力を要す
る。 (ハ)硬化したコンクリート表面に、ひび割れやジャン
カが生じ、表面の仕上り状態が見苦しくなる場合があ
る。
However, in the construction of a conventional concrete dam, the following (a), (b),
It has a problem like (C). (B) Since large-scale work such as installing, removing, moving, and dismantling the formwork is required, it is difficult to further speed up the construction. (B) Because large-scale work at high places is required, such as work for attaching the formwork to the upstream and downstream sides of the dam body formed of already cast concrete, and work for removing it for movement. However, it takes a lot of effort to manage the safety of workers. (C) Cracks and junkers may occur on the hardened concrete surface, and the finished state of the surface may be unsightly.

【0006】本発明は、上記事情に鑑み、迅速、安全に
施工することが出来、また、高品質化を図ることが出来
るコンクリートダム及びその施工方法を提供することを
目的としている。
In view of the above circumstances, it is an object of the present invention to provide a concrete dam that can be constructed quickly and safely, and that can achieve high quality, and a construction method thereof.

【0007】[0007]

【課題を解決するための手段】請求項1記載のコンクリ
ートダムは、コンクリートよりなるダム本体と、前記ダ
ム本体の上流側及び下流側に多数のプレキャスト板によ
りそれぞれ形成されたダム表層部とにより構成される。
A concrete dam according to claim 1 comprises a dam body made of concrete, and a dam surface layer portion formed by a number of precast plates on the upstream and downstream sides of the dam body. To be done.

【0008】請求項2記載のコンクリートダムの施工方
法は、ダム施工領域の上流側及び下流側にそれぞれ複数
のプレキャスト板を、内部にコンクリート打設空間を形
成するように設ける第一工程と、前記コンクリート打設
空間にコンクリートを、前記プレキャスト板を埋め殺し
とするように打設する第二工程と、前記ダム施工領域の
上流側に設けられたプレキャスト板の上端、及び前記ダ
ム施工領域の下流側に設けられたプレキャスト板の上端
に、それぞれ複数のプレキャスト板を、既打設の前記コ
ンクリートの上方に次なるコンクリート打設空間を形成
するように設ける第三工程と、前記次なるコンクリート
打設空間に、コンクリートを、前記プレキャスト板を埋
め殺しとするように打設する第四工程とを有し、前記第
三工程及び前記第四工程を繰り返すことによりコンクリ
ートを打ち上げるようにして堤体を築造することを特徴
とする。
According to a second aspect of the present invention, there is provided a method for constructing a concrete dam, comprising a first step of providing a plurality of precast plates on the upstream side and the downstream side of a dam construction area so as to form a concrete placing space therein. Concrete in the concrete placing space, the second step of placing so as to fill the precast plate, the upper end of the precast plate provided on the upstream side of the dam construction area, and the downstream side of the dam construction area A plurality of precast plates on the upper end of the precast plate provided in, respectively, so as to form the next concrete placing space above the already placed concrete, and the next concrete placing space A fourth step of placing concrete so as to bury the precast plate, and the third step and the fourth step. So as to launch a concrete, characterized in that construction the embankment by repeating the process.

【0009】請求項3記載のコンクリートダムの施工方
法は、請求項2記載のコンクリートダムの施工方法であ
って、前記既打設のコンクリートと前記次なるコンクリ
ート打設空間を形成するように設けられたプレキャスト
板との間に、アンカーを設けることを特徴とする。
The method for constructing a concrete dam according to claim 3 is the method for constructing a concrete dam according to claim 2, wherein the concrete dam is provided so as to form the already-exposed concrete and the next concrete placing space. An anchor is provided between the precast plate and the precast plate.

【0010】請求項4記載のコンクリートダムの施工方
法は、請求項2又は3記載のコンクリートダムの施工方
法であって、前記ダム施工領域の上流側のプレキャスト
板と前記ダム施工領域の下流側のプレキャスト板との間
に、連結材を設けることを特徴とする。
The construction method of the concrete dam according to claim 4 is the construction method of the concrete dam according to claim 2 or 3, wherein the precast plate on the upstream side of the dam construction area and the downstream side of the dam construction area. A feature is that a connecting material is provided between the precast plate and the precast plate.

【0011】[0011]

【作用】請求項1記載のコンクリートダムによれば、多
数のプレキャスト板によりダム表層部が形成されている
ので、表面仕上りを良好にすることが出来る。また、プ
レキャスト板を埋め殺し型枠とすることにより、そのプ
レキャスト板は断熱作用を果し、ダム本体を形成するた
めに打設されたコンクリートの硬化時の発熱、その後の
収縮による熱作用によるひび割れの発生を抑制すること
が出来る。
According to the concrete dam of the first aspect, since the dam surface layer portion is formed by a large number of precast plates, the surface finish can be improved. In addition, by filling the precast plate into a formwork, the precast plate performs a heat insulating function, and heat generated during hardening of the concrete cast to form the dam body, and cracking due to the heat effect due to subsequent contraction. Can be suppressed.

【0012】また、プレキャスト板を埋め殺し型枠とし
て用いることにより、従来のコンクリートダムの施工に
おける型枠の設置、取り外し、移動、解体等の大掛かり
な作業を省くことが出来る。
Further, by using the precast plate as a buried mold, it is possible to omit large-scale work such as installation, removal, movement and disassembly of the mold in the conventional construction of a concrete dam.

【0013】更に、プレキャスト板を埋め殺し型枠とし
て用いてコンクリートを打ち上げていく場合には、コン
クリートが打設されたプレキャスト板の上に、次なるコ
ンクリート打設空間を形成するプレキャスト板を設ける
ことにより、既打設のコンクリート上から埋め殺し型枠
としてのプレキャスト板の連結作業を行なうことが出来
る。よって、従来のように既打設のコンクリートにより
形成される堤体の上流側及び下流側に型枠を取り付ける
作業、及び、移動のために取り外す作業等の、高所での
大掛かりな作業を省くことが出来る。
Further, when the concrete is poured up by using the precast board as a burying mold, a precast board for forming the next concrete placing space is provided on the precast board on which the concrete is placed. By this, it is possible to perform the connecting work of the precast plates as the burying formwork from the already placed concrete. Therefore, large-scale work at high places, such as the work of attaching the formwork to the upstream side and the downstream side of the dam body formed by the already cast concrete and the work of removing it for movement, as in the past, is omitted. You can

【0014】請求項2記載のコンクリートダムの施工方
法によれば、プレキャスト板を埋め殺し型枠として用い
るので、従来のコンクリートダムの施工における型枠の
設置、取り外し、移動、解体等の大掛かりな作業を省く
ことが出来る。
According to the concrete dam construction method of the second aspect, since the precast plate is used as a buried formwork, large-scale work such as installation, removal, movement and dismantling of the formwork in the construction of conventional concrete dams is performed. Can be omitted.

【0015】また、プレキャスト板は、既設のプレキャ
スト板に設けられるので、既打設のコンクリート上から
その連結作業を行なうことが出来る。よって、従来のよ
うに既打設のコンクリートにより形成される堤体の上流
側及び下流側に型枠を取り付ける作業、及び、移動のた
めに取り外す作業等の、高所での大掛かりな作業を省く
ことが出来る。
Further, since the precast plate is provided on the existing precast plate, the connecting work can be performed from the already cast concrete. Therefore, large-scale work at high places, such as the work of attaching the formwork to the upstream side and the downstream side of the dam body formed by the already cast concrete and the work of removing it for movement, as in the past, is omitted. You can

【0016】更に、ダム表層部が多数のプレキャスト板
により形成されることとなるので、表面仕上りを良好に
することが出来る。また、埋め殺し型枠となるプレキャ
スト板は断熱作用を果すので、ダム本体を形成するため
に打設されたコンクリートの硬化時の発熱、その後の収
縮による熱作用によるひび割れの発生を抑制することが
出来る。
Further, since the dam surface layer portion is formed by a large number of precast plates, the surface finish can be improved. In addition, since the precast plate that serves as the buried mold has a heat insulating effect, it is possible to suppress the generation of heat during hardening of the concrete cast to form the dam body and subsequent cracking due to the heat effect due to contraction. I can.

【0017】請求項3記載のコンクリートダムの施工方
法によれば、アンカーによりプレキャスト板が支持され
るので、コンクリート打設時にコンクリートの圧力によ
りプレキャスト板が外方に変形することを防止すること
が出来る。
According to the method for constructing a concrete dam according to claim 3, since the precast plate is supported by the anchor, it is possible to prevent the precast plate from being deformed outward by the pressure of the concrete at the time of placing the concrete. .

【0018】請求項4記載のコンクリートダムの施工方
法によれば、連結材によりコンクリート打設時にコンク
リートの圧力によりプレキャスト板が外方に変形するこ
とを防止することが出来る。
According to the method for constructing a concrete dam of claim 4, the precast plate can be prevented from being deformed outward by the pressure of the concrete when the concrete is poured by the connecting material.

【0019】[0019]

【実施例】以下、本発明の一実施例を図面に基づき説明
する。図1は施工途中の本発明のコンクリートダム10
0の一実施例を示す図であり、コンクリートダム100
は、その上流側(図1左側)と下流側(図1右側)にそ
れぞれ、対向するように立設形成されたダム表層部1
0、10を有しており、ダム表層部10、10は、それ
ぞれ、上下方向及び左右岸方向(図1紙面に直角な方
向)に、連設された複数のプレキャスト板1により構成
されている。尚、下流側(図1右側)のダム表層部10
は、上流側に若干傾斜して設けられている。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to the drawings. FIG. 1 shows a concrete dam 10 of the present invention during construction.
It is a figure which shows one Example of 0, and concrete dam 100
Is a dam surface layer portion 1 which is vertically formed so as to face the upstream side (left side in FIG. 1) and the downstream side (right side in FIG. 1) of the dam.
The dam surface layers 10 and 10 are composed of a plurality of precast plates 1 that are continuously arranged in the up-down direction and the left-right bank direction (direction perpendicular to the plane of FIG. 1). . In addition, the dam surface layer portion 10 on the downstream side (right side in FIG. 1)
Are provided on the upstream side with a slight inclination.

【0020】各プレキャスト板1は、図6に示すよう
に、コンクリート等により予め長方形の板状に形成され
た部材であり、プレキャスト板1の内側の面は、打継処
理が施された打継処理面1aとなっている。プレキャス
ト板1の上端面1b及び下端面1cは、プレキャスト板
1の打継処理面1aに対して直角に形成されている。プ
レキャスト板1の左端面1d及び右端面1eは、打継処
理面1a側に狭まるようにテーパーしている。
As shown in FIG. 6, each precast plate 1 is a member formed in advance into a rectangular plate shape by concrete or the like, and the inner surface of the precast plate 1 has a spliced joint. It is the processing surface 1a. The upper end surface 1b and the lower end surface 1c of the precast plate 1 are formed at right angles to the splicing surface 1a of the precast plate 1. The left end surface 1d and the right end surface 1e of the precast plate 1 are tapered so as to narrow toward the piecing surface 1a.

【0021】また、プレキャスト板1の上端面1b、下
端面1c、左端面1d、右端面1eには、打継処理面1
a側に切り欠かれた溝2が、それぞれ複数形成されてお
り、溝2には、連結金具3が設けられており、連結金具
3は、上方又は下方又は左方又は右方に隣接するプレキ
ャスト板1に向けて貫通したピン孔3aを有している。
The precast plate 1 has an upper end surface 1b, a lower end surface 1c, a left end surface 1d, and a right end surface 1e, and a splicing surface 1
A plurality of grooves 2 cut out on the a side are formed respectively, and a connecting metal fitting 3 is provided in the groove 2, and the connecting metal fitting 3 is adjacent to an upper side, a lower side, a left side or a right side of the precast. It has a pin hole 3a penetrating toward the plate 1.

【0022】そして、図7に示すように、上下又は左右
に隣接するプレキャスト板1、1は、上端面1b、下端
面1c又は左端面1d、右端面1eに設けられた図6に
示す連結金具3のピン孔3aの位置を一致させ、その一
致したピン孔3a、3aに図示しないボルトを貫通し
て、図示しないナットを締着することにより連結され
る。
As shown in FIG. 7, the precast plates 1, 1 adjacent to each other in the vertical direction or the horizontal direction are connected to the upper end face 1b, the lower end face 1c or the left end face 1d, and the right end face 1e as shown in FIG. The pin holes 3a of 3 are aligned, the bolts (not shown) are passed through the pin holes 3a, 3a that are aligned, and the nuts (not shown) are tightened to connect them.

【0023】また、図8に示すように、上下に隣接する
プレキャスト板1、1の下端面1cと上端面1bとの間
の、プレキャスト板1の表面1f側の端には、ガスケッ
ト4が設けられており、上下に隣接するプレキャスト板
1、1の下端面1cと上端面1bとの間の、ガスケット
4より打継処理面1a側には、モルタル5が充填されて
いる。
Further, as shown in FIG. 8, a gasket 4 is provided at the end on the surface 1f side of the precast plate 1 between the lower end surface 1c and the upper end surface 1b of the vertically adjacent precast plates 1, 1. A mortar 5 is filled between the lower end surface 1c and the upper end surface 1b of the vertically adjacent precast plates 1, 1 on the side of the gasket 4 which is the splicing treated surface 1a.

【0024】図9に示すように、左右に隣接するプレキ
ャスト板1、1の左端面1dと右端面1eとの間の、プ
レキャスト板1の表面1f側の端には、ガスケット6が
設けられており、左右に隣接するプレキャスト板1、1
の左端面1dと右端面1eとの間の、ガスケット6より
打継処理面1a側には、シール材7が設けられている。
As shown in FIG. 9, a gasket 6 is provided at the end on the surface 1f side of the precast plate 1 between the left end face 1d and the right end face 1e of the left and right precast plates 1, 1. And precast plates 1 and 1 that are adjacent to each other
A sealing material 7 is provided between the left end surface 1d and the right end surface 1e on the splicing surface 1a side of the gasket 6.

【0025】図1に示すように、プレキャスト板1によ
り構成されたダム表層部10、10の間には、コンクリ
ート11が、下方から上方に向けて層状に打設されてお
り、このコンクリート11によりダム本体20が形成さ
れている。
As shown in FIG. 1, concrete 11 is cast between the dam surface layers 10 and 10 formed by the precast plate 1 in layers from the bottom to the top. The dam body 20 is formed.

【0026】また、ダム表層部10、10を形成してい
る各プレキャスト板1の打継処理面1a側には、コンク
リート11に埋設されたバックアンカー12が設けられ
ており、バックアンカー12の下端は、バックアンカー
12が設けられたプレキャスト板1より下方のコンクリ
ート11の層の上面に位置している。
A back anchor 12 embedded in concrete 11 is provided on the splicing surface 1a side of each precast plate 1 forming the dam surface layers 10 and 10, and the lower end of the back anchor 12 is provided. Is located on the upper surface of the layer of concrete 11 below the precast plate 1 provided with the back anchor 12.

【0027】即ち、図6に示すように、プレキャスト板
1の打継処理面1aには、上下に二列、複数の雌ねじ金
具8が埋設されており、雌ねじ金具8には、図10に示
すように、端部に環9aを有する雄ねじ9が螺着されて
いる。また、当該プレキャスト板1より下方のコンクリ
ート11の層の上面には、各雄ねじ9に対応するよう
に、雌ねじ金具13が埋設されており、雌ねじ金具13
には、端部に環14aを有する雄ねじ14が螺着されて
いる。そして、プレキャスト板1側の環9aとコンクリ
ート11側の環14aとの間に、前述のバックアンカー
12が設けられている。
That is, as shown in FIG. 6, a plurality of internal thread metal fittings 8 are embedded in the upper and lower rows on the connecting surface 1a of the precast plate 1, and the female thread metal fittings 8 are shown in FIG. As described above, the male screw 9 having the ring 9a at the end is screwed. Further, on the upper surface of the layer of concrete 11 below the precast plate 1, female screw metal fittings 13 are embedded so as to correspond to the respective male screws 9, and the female screw metal fittings 13 are embedded.
A male screw 14 having a ring 14a at its end is screwed onto the. The above-described back anchor 12 is provided between the ring 9a on the side of the precast plate 1 and the ring 14a on the side of the concrete 11.

【0028】バックアンカー12は、上部棒部材12a
と、下部棒部材12bと、上部棒部材12aと下部棒部
材12bを、バックアンカー12全体として伸縮自在な
るように接合するターンバックル12cよりなり、上部
棒部材12aの上端には、フック12dが設けられてい
る。そのフック12dは、プレキャスト板1側の環9a
に挿入され、掛着されており、下部棒部材12bの下端
にも、フック12eが設けられている。そのフック12
eは、コンクリート11側の環14aに挿入され、掛着
されている。また、フック12d、12eと環9a、1
4aは、略遊びの無い状態で掛着されている。
The back anchor 12 is an upper rod member 12a.
And a lower rod member 12b, and a turnbuckle 12c that joins the upper rod member 12a and the lower rod member 12b so that the entire back anchor 12 can expand and contract, and a hook 12d is provided at the upper end of the upper rod member 12a. Has been. The hook 12d is a ring 9a on the precast plate 1 side.
The lower rod member 12b is also provided with a hook 12e at the lower end thereof. That hook 12
e is inserted and hooked on the ring 14a on the concrete 11 side. Also, the hooks 12d and 12e and the rings 9a and 1
4a is hooked in a state with almost no play.

【0029】コンクリートダム100は、以上のような
構成を有するので、図1に示すように、多数のプレキャ
スト板1によりダム表層部10が形成されていることか
ら、表面仕上りを良好にすることが出来る。よって、コ
ンクリートダム100の高品質化を図ることが出来る。
Since the concrete dam 100 has the above-mentioned structure, as shown in FIG. 1, since the dam surface layer portion 10 is formed by a large number of precast plates 1, the surface finish can be improved. I can. Therefore, the quality of the concrete dam 100 can be improved.

【0030】また、コンクリートダム100は、図11
に示す施工工程を繰り返すようにして施工することが出
来る。即ち、まず、プレキャスト板吊り込み工程C1で
は、図2又は図4に示すように、ダム施工領域Sdの上
流側及び下流側に既設され、ダム表層部10、10の下
部を形成するプレキャスト板1の上端に、クレーン31
により、次なるプレキャスト板1を、それぞれ、プレキ
ャスト板1の打継処理面1aを内方に向けるようにして
吊り込む。クレーン31は、ダム施工領域Sdの上方に
架設されたケーブルクレーン、又は、コンクリート1に
より既設されたダム本体20上に運び込まれたクローラ
ークレーン等の吊り込み装置である。
The concrete dam 100 is shown in FIG.
The construction can be performed by repeating the construction process shown in. That is, first, in the precast plate suspending step C1, as shown in FIG. 2 or 4, the precast plate 1 that is already installed on the upstream side and the downstream side of the dam construction region Sd and forms the lower parts of the dam surface layer portions 10 and 10. At the top of the crane 31
Thus, the next precast plate 1 is hung so that the splicing surface 1a of the precast plate 1 faces inward. The crane 31 is a suspending device such as a cable crane installed above the dam construction area Sd or a crawler crane carried on the dam body 20 already installed by the concrete 1.

【0031】次に、図11に示す位置合わせ工程C2で
は、吊り込まれたプレキャスト板1は、図7に示すよう
に、既設のダム本体20下部上に待機した作業員によ
り、既設のプレキャスト板1の上端面1bの連結金具3
と、吊り込まれたプレキャスト板1の下端面1cの連結
金具3の位置が、一致するように誘導され、位置決めさ
れる。
Next, in the positioning step C2 shown in FIG. 11, the suspended precast plate 1 is moved to the existing precast plate 1 by an operator who stands by under the existing dam body 20 as shown in FIG. 1 upper end surface 1b of the connecting fitting 3
Then, the position of the connecting fitting 3 on the lower end surface 1c of the suspended precast plate 1 is guided and positioned so as to match.

【0032】次に、図11に示す連結金具締結工程C3
では、吊られた状態でまま、既設のプレキャスト板1の
上端面1bの連結金具3と、吊り込まれたプレキャスト
板1の下端面1cの連結金具3とをボルト及びナットに
より連結する。
Next, the connecting metal fitting step C3 shown in FIG.
Then, the connecting metal fitting 3 of the upper end surface 1b of the existing precast plate 1 and the connecting metal fitting 3 of the lower end surface 1c of the suspended precast plate 1 are connected by bolts and nuts in the suspended state.

【0033】また、図11に示す目地処理工程C4で
は、上記のように既設のプレキャスト板1と吊り込まれ
たプレキャスト板1とを連結する過程で、その既設のプ
レキャスト板1の上端面1bと吊り込まれたプレキャス
ト板1の下端面1cとの間に、図8に示すように、表面
1f側の端にガスケット4を設け、また、ガスケット4
より打継処理面1a側にモルタル5を設ける。これによ
り、上下に隣接するプレキャスト板1間の目地から水が
浸透することを防ぐことが出来る。
In the joint treatment step C4 shown in FIG. 11, in the process of connecting the existing precast plate 1 and the suspended precast plate 1 as described above, the upper surface 1b of the existing precast plate 1 is As shown in FIG. 8, a gasket 4 is provided between the lower end surface 1c of the suspended precast plate 1 and the end on the front surface 1f side.
The mortar 5 is provided closer to the splicing surface 1a. This makes it possible to prevent water from permeating through the joints between the vertically adjacent precast plates 1.

【0034】既設のプレキャスト板1と吊り込まれたプ
レキャスト板1との連結及び目地処理が完了したなら
ば、次に、図11に示すバックアンカー設置工程C5に
移る。バックアンカー設置工程C5では、図3及び図5
に示すように、吊り込まれたプレキャスト板1と既打設
のコンクリート11により形成されたダム本体20下部
との間に、バックアンカー12を取り付ける。
When the connection between the existing precast plate 1 and the suspended precast plate 1 and the joint treatment are completed, the process proceeds to the back anchor installation step C5 shown in FIG. In the back anchor installation step C5, as shown in FIGS.
As shown in, the back anchor 12 is attached between the suspended precast plate 1 and the lower part of the dam body 20 formed by the already cast concrete 11.

【0035】尚、ダム本体20下部を形成しているコン
クリート11の上面には、そのコンクリート11が硬化
する前に、図10に示すように、プレキャスト板1に設
けられた複数の雌ねじ金具8に対応する複数の雌ねじ金
具13が埋設されている。
On the upper surface of the concrete 11 forming the lower part of the dam body 20, before the concrete 11 hardens, a plurality of female screw fittings 8 provided on the precast plate 1 are provided as shown in FIG. A plurality of corresponding internal thread fittings 13 are embedded.

【0036】バックアンカー12の取り付けにおいて
は、まず、プレキャスト板1の打継処理面1aに上下に
二列設けられた各雌ねじ金具8に、それぞれ環9aを有
する雄ねじ9を螺着し、同様に、既打設のコンクリート
11に設けられた各雌ねじ金具13に環14aを有する
雄ねじ14を螺着する。次に、バックアンカー12の上
部棒部材12aのフック12dをプレキャスト板1の雄
ねじ9の環9aに挿入、掛着し、下部棒部材12bのフ
ック12eを、既打設のコンクリート11に設けられた
雄ねじ14の環14aに挿入、掛着する。そして、バッ
クアンカー12のターンバックル12cによりバックア
ンカー12を伸縮するすることにより、プレキャスト板
1の設置角度の調整を行なう。
In mounting the back anchor 12, first, the male screws 9 each having the ring 9a are screwed into the female screw fittings 8 provided in two rows above and below the joining surface 1a of the precast plate 1, and similarly. A male screw 14 having a ring 14a is screwed onto each female screw fitting 13 provided on the already-cast concrete 11. Next, the hook 12d of the upper rod member 12a of the back anchor 12 was inserted into and hooked on the ring 9a of the male screw 9 of the precast plate 1, and the hook 12e of the lower rod member 12b was provided on the already cast concrete 11. Insert and hook onto the ring 14a of the male screw 14. Then, the back anchor 12 is expanded and contracted by the turnbuckle 12c of the back anchor 12 to adjust the installation angle of the precast plate 1.

【0037】従って、吊り込まれたプレキャスト板1
は、バックアンカー12により所定の設置角度に精度良
く設置することが出来、また、既打設のコンクリート1
1に固定される。更に、バックアンカー12は、図7に
示すようにプレキャスト板1の上下にそれぞれ設けら
れ、また、左右岸方向に複数設けられるので、プレキャ
スト板1を既打設のコンクリート11に堅固に固定する
ことが出来る。
Therefore, the suspended precast plate 1
Can be accurately installed at a predetermined installation angle by the back anchor 12, and the existing concrete 1
Fixed to 1. Further, as shown in FIG. 7, the back anchors 12 are provided on the upper and lower sides of the precast plate 1, respectively, and a plurality of back anchors are provided in the left and right bank directions. Therefore, the precast plate 1 should be firmly fixed to the concrete 11 already placed. Can be done.

【0038】また、図1に示すように、ダム施工領域S
dの上流側及び下流側に既設され、ダム表層部10、1
0の下部を形成するプレキャスト板1は、図7に示すよ
うに、左右岸方向に多数連設されており、その各プレキ
ャスト板1上には、上述同様に、それぞれ、プレキャス
ト板1が吊り込まれ、連結され、また、バックアンカー
12により、既設のコンクリート11に固定される。
Further, as shown in FIG. 1, the dam construction area S
It is already installed on the upstream side and the downstream side of d, and the dam surface layers 10, 1
As shown in FIG. 7, a large number of precast plates 1 forming the lower part of 0 are continuously arranged in the left-right bank direction, and the precast plates 1 are suspended on each of the precast plates 1 in the same manner as described above. They are rarely connected and are fixed to the existing concrete 11 by the back anchor 12.

【0039】また、既設のプレキャスト板1上にそれぞ
れ設けられたプレキャスト板1は、それぞれ左右岸方向
に隣接するプレキャスト板1どうしが互いに連結され
る。その連結は、隣接するプレキャスト板1の左右端面
1d、1eに設けられた連結金具3、3をボルト、ナッ
トにより締結することにより行なわれる。
The precast plates 1 provided on the existing precast plates 1 are connected to each other so that the precast plates 1 adjacent to each other in the left and right bank direction are connected to each other. The connection is performed by fastening the connecting fittings 3 and 3 provided on the left and right end faces 1d and 1e of the adjacent precast plates 1 with bolts and nuts.

【0040】また、隣接するプレキャスト板1の連結の
過程では、その左右端面1d、1eには、図9に示すよ
うに、表面1f側の端にガスケット6を設け、また、ガ
スケット6より打継処理面1a側にはシール材7が設け
られる。これにより、左右に隣接するプレキャスト板1
間の目地から水が浸透することを防ぐことが出来る。
Further, in the process of connecting the adjacent precast plates 1, as shown in FIG. 9, the left and right end faces 1d and 1e are provided with gaskets 6 at the ends on the surface 1f side, and the gaskets 6 are joined together. A sealing material 7 is provided on the processing surface 1a side. As a result, the precast plates 1 adjacent to the left and right
Water can be prevented from penetrating from the joints between.

【0041】よって、図5に示すように、ダム施工領域
Sdの上流側及び下流側に既設され、ダム表層部10、
10の下部を形成するプレキャスト板1上に更に、プレ
キャスト板1を設けることが出来るので、その間、即
ち、既打設のコンクリート11上に更にコンクリート打
設空間S1を形成することが出来る。
Therefore, as shown in FIG. 5, the dam surface layer portion 10, which has already been installed upstream and downstream of the dam construction area Sd,
Since the precast plate 1 can be further provided on the precast plate 1 forming the lower part of 10, the concrete pouring space S1 can be further formed in the meantime, that is, on the already cast concrete 11.

【0042】また、既設のプレキャスト板1と、吊り込
まれたプレキャスト板1の連結及び吊り込まれたプレキ
ャスト板1どうしの連結は、連結金具3がプレキャスト
板1の打継処理面1c側に設けられた溝2に設けられて
いるので、既打設のコンクリート11上で行なうことが
出来る。更に、吊り込まれたプレキャスト板1の既設の
コンクリート11への固定も、上記のように既打設のコ
ンクリート11上から行なうことが出来る。従って、既
設のプレキャスト板1上へのプレキャスト板1の設置作
業は、既打設のコンクリート11より行なうことが出来
るので、従来のように、既打設のコンクリートにより形
成される堤体の上流側及び下流側に型枠を取り付ける作
業、及び、移動のために取り外す作業等の、高所での大
掛かりな作業を省くことが出来る。よって、施工の安全
性を向上することが出来る。
Further, the connection of the existing precast plate 1 and the suspended precast plate 1 and the connection of the suspended precast plates 1 are such that the connecting metal fitting 3 is provided on the side of the precast plate 1 where the splicing treatment surface 1c is formed. Since it is provided in the formed groove 2, it can be performed on the already cast concrete 11. Further, the suspended precast plate 1 can be fixed to the existing concrete 11 as described above from the already-cast concrete 11. Therefore, since the installation work of the precast plate 1 on the existing precast plate 1 can be performed from the already-cast concrete 11, the upstream side of the bank formed by the already-cast concrete as in the conventional art. Also, it is possible to omit large-scale work at a high place such as a work of mounting the formwork on the downstream side and a work of removing it for movement. Therefore, the safety of construction can be improved.

【0043】そして、図11のコンクリート打設工程C
6では、図5に示すコンクリート打設空間S1にコンク
リート11を打設する。この際、プレキャスト板1は、
バックアンカー12により既打設のコンクリート11に
固定されているので、コンクリート打設時にコンクリー
ト11の圧力によりプレキャスト板1が外方に変形する
ことを防止することが出来るので、一層の高品質化を図
ることが出来る。
Then, the concrete placing step C in FIG.
At 6, the concrete 11 is placed in the concrete placing space S1 shown in FIG. At this time, the precast plate 1 is
Since it is fixed to the already-cast concrete 11 by the back anchor 12, it is possible to prevent the precast plate 1 from being deformed outward by the pressure of the concrete 11 when the concrete is poured, thus further improving the quality. Can be planned.

【0044】プレキャスト板1のコンクリート打設空間
S1側の面は、打継処理の施された打継処理面1aとな
っており、また、プレキャスト板1に設けられたバック
アンカー12はコンクリート11に埋設されることとな
るので、プレキャスト板1とコンクリート11とを強力
に接合することが出来る。
The surface of the precast plate 1 on the concrete pouring space S1 side is a connecting surface 1a subjected to a connecting process, and the back anchor 12 provided on the precast plate 1 is made of concrete 11. Since it is buried, the precast plate 1 and the concrete 11 can be strongly bonded.

【0045】上記のように埋め殺し型枠となるプレキャ
スト板1は断熱作用を果すので、ダム本体20を形成す
るために打設されたコンクリート11の硬化時の発熱、
その後の収縮の際の熱作用によるひび割れの発生を抑制
することが出来る。よって、高品質化を図ることが出来
る。
As described above, the precast plate 1 serving as the buried mold has a heat insulating function, so that the heat generated when the concrete 11 cast to form the dam body 20 is hardened,
It is possible to suppress the occurrence of cracks due to the thermal action during the subsequent contraction. Therefore, high quality can be achieved.

【0046】また、プレキャスト板1を埋め殺し型枠と
して用いるので、従来のコンクリートダムの施工におけ
る型枠の設置、取り外し、移動、解体等の大掛かりな作
業を省くことが出来るので、施工の迅速化を図ることが
出来る。
Further, since the precast plate 1 is used as a buried formwork, large-scale work such as installation, removal, movement, and disassembly of the formwork in the construction of a conventional concrete dam can be omitted, so that the construction can be speeded up. Can be planned.

【0047】以上が本発明のコンクリートダム100の
施工工程の一サイクルであり、このサイクルを繰り返す
ことで、プレキャスト板1によりダム表層部10を形成
しつつ、コンクリート11によりダム本体20を形成す
ることが出来る。また、上述のように、高品質なコンク
リートダム100を、迅速、安全に施工することが出来
る。
The above is one cycle of the construction process of the concrete dam 100 of the present invention. By repeating this cycle, the dam surface layer portion 10 is formed by the precast plate 1 and the dam body 20 is formed by the concrete 11. Can be done. Further, as described above, the high-quality concrete dam 100 can be constructed quickly and safely.

【0048】また、コンクリートダム100の基礎にプ
レキャスト板1を設置する場合も、その基礎の上流側及
び下流側にプレキャスト板設置部を形成し、その設置部
の上端に、プレキャスト板1の連結金具3同様の連結金
具を設け、更に基礎上に既打設のコンクリート11に埋
設された雌ねじ金具13同様の雌ねじ金具を埋設してお
くことにより、上記同様に行なうことが出来る。
When the precast board 1 is installed on the foundation of the concrete dam 100, the precast board installation portions are formed on the upstream side and the downstream side of the foundation, and the connecting metal fittings of the precast board 1 are formed on the upper end of the installation portion. The same operation as described above can be performed by providing a connecting metal fitting similar to No. 3 and further embedding an internal thread metal fitting similar to the female thread metal fitting 13 embedded in the already cast concrete 11 on the foundation.

【0049】尚、上記実施例においては、バックアンカ
ー12をプレキャスト板1の上下に二列設けたが、必ず
しも二列である必要はなく、プレキャスト板1の大きさ
に応じて、一列でも、又、三列以上であってもよいこと
は勿論である。
In the above embodiment, the back anchors 12 are provided in two rows above and below the precast plate 1. However, the back anchors 12 do not necessarily have to be in two rows, and one row may be provided depending on the size of the precast board 1. Needless to say, the number of rows may be three or more.

【0050】また、上記実施例では、バックアンカー1
2により、コンクリート打設時におけるプレキャスト板
1の外方への変形を阻止するように設けたが、図12、
図13に示すように、バックアンカー12に加えて、上
流側に設けられたプレキャスト板1の上端と、下流側に
設けられたプレキャスト板1との上端に連結材31を架
設することにより、その変形を防止するようにしてもよ
い。これにより、変形に対する防止効果を高めることが
出来るので、更に一層の高品質化を図ることが出来る。
この場合、連結材31の両端は、図12に示すように、
プレキャスト板1の上端に設けられた連結金具3にボル
ト、ナットにより連結されるように形成されており、更
に、連結材31の両端部下面とプレキャスト板1の打継
処理面1aの上端部との間に、それぞれブラケット32
を設けることにより、連結材31とプレキャスト板1と
の連結力を高めることが出来る。また、図13に示すよ
うに、連結材31は、プレキャスト板1の上端に複数設
けられた連結金具3毎に設けられている。
Further, in the above embodiment, the back anchor 1
2, the precast plate 1 is provided so as to prevent the deformation of the precast plate 1 at the time of placing concrete.
As shown in FIG. 13, in addition to the back anchor 12, by installing a connecting member 31 on the upper ends of the precast plate 1 provided on the upstream side and the precast plate 1 provided on the downstream side, Deformation may be prevented. As a result, the effect of preventing deformation can be enhanced, so that the quality can be further improved.
In this case, both ends of the connecting member 31 are, as shown in FIG.
It is formed so as to be connected to a connecting fitting 3 provided on the upper end of the precast plate 1 by bolts and nuts, and further, on the lower surface of both end portions of the connecting member 31 and the upper end portion of the splicing surface 1a of the precast plate 1. Between the brackets 32
By providing, the connecting force between the connecting member 31 and the precast plate 1 can be increased. Further, as shown in FIG. 13, the connecting member 31 is provided for each of the connecting fittings 3 provided at the upper end of the precast plate 1.

【0051】また、上記実施例においては、一段のプレ
キャスト板1によりコンクリート打設空間S1を形成し
たが、図12に示すように、プレキャスト板1を複数段
上下方向に連結して、コンクリート打設空間S1を形成
するようにしてもよいことは勿論である。
Further, in the above embodiment, the concrete casting space S1 is formed by the one-stage precast plate 1. However, as shown in FIG. Of course, the space S1 may be formed.

【0052】また、上記実施例においては、図10に示
すように、プレキャスト板1の打継処理面1a側に環9
aを有する雄ねじ9を設け、既打設のコンクリート11
に環14aを有する雄ねじ14を設け、その間にバック
アンカー12を、その両端のフック12d、12eによ
り掛着するように設けたが、その雄ねじ9、14を溶接
板を有する雄ねじとし、バックアンカー12の両端も溶
接板として、バックアンカー12を、雄ねじ9、14に
対して、溶接するように設けてもよい。
Further, in the above-mentioned embodiment, as shown in FIG. 10, the ring 9 is provided on the side of the precast plate 1 which is the splicing surface 1a.
The male screw 9 having a is provided, and the already cast concrete 11
The male screw 14 having the ring 14a is provided on the back anchor 12, and the back anchor 12 is provided between the two so as to be hooked by the hooks 12d and 12e at both ends thereof. The male screw 9 and 14 are the male screw having the welding plate. Both ends may be welded plates, and the back anchor 12 may be provided so as to be welded to the male screws 9 and 14.

【0053】また、更に、棒状又は板状のバックアンカ
ーを既打設のコンクリート11に予めその上端がプレキ
ャスト板1の設置位置付近に位置するように埋設してお
くと共に、プレキャスト板1の打継処理面1a側に幅広
の溶接板を突設しておくことにより、プレキャスト板1
の設置角度を調整した後にそのバックアンカーを溶接す
るようにしてもよい。
Further, a rod-shaped or plate-shaped back anchor is embedded in the already cast concrete 11 so that its upper end is located near the installation position of the precast plate 1, and the precast plate 1 is spliced. By forming a wide welding plate on the processing surface 1a side, the precast plate 1
The back anchor may be welded after the installation angle is adjusted.

【0054】[0054]

【発明の効果】請求項1記載のコンクリートダムによれ
ば、表面仕上りを良好にすることが出来、ダム本体を形
成するために打設されたコンクリートの硬化時の発熱、
その後の収縮による熱作用によるひび割れの発生を抑制
することが出来るので、高品質化を図ることが出来る。
また、従来のコンクリートダムの施工における型枠の設
置、取り外し、移動、解体等の大掛かりな作業を省くこ
とが出来るので、施工の迅速化を図ることが出来る。更
に、従来の高所での大掛かりな作業を省くことが出来る
ので、施工の安全性を向上することが出来る。
According to the concrete dam of the first aspect, the surface finish can be improved, and the heat generated when the concrete cast to form the dam body is cured,
Since it is possible to suppress the occurrence of cracks due to the thermal action due to the subsequent contraction, it is possible to improve the quality.
Further, since it is possible to omit large-scale work such as installation, removal, movement, and disassembly of the formwork in the construction of the conventional concrete dam, the construction can be speeded up. Further, since it is possible to omit the conventional large-scale work at a high place, it is possible to improve construction safety.

【0055】請求項2記載のコンクリートダムの施工方
法によれば、請求項1記載のコンクリートダムにおける
効果と同様の効果を有する。
According to the concrete dam construction method of the second aspect, the same effects as those of the concrete dam of the first aspect can be obtained.

【0056】請求項3記載のコンクリートダムの施工方
法によれば、上記効果に加えて、アンカーによりコンク
リート打設時にコンクリートの圧力によりプレキャスト
板が外方に変形することを防止することが出来るので、
一層の高品質化を図ることが出来る。
According to the method for constructing a concrete dam according to claim 3, in addition to the above effects, it is possible to prevent the precast plate from being deformed outward by the pressure of the concrete when placing the concrete by the anchor.
It is possible to further improve the quality.

【0057】請求項4記載のコンクリートダムの施工方
法によれば、上記効果に加えて、連結材によりコンクリ
ート打設時にコンクリートの圧力によりプレキャスト板
が外方に変形することを防止することが出来るので、更
に一層の高品質化を図ることが出来る。
According to the method of constructing a concrete dam according to claim 4, in addition to the above effects, it is possible to prevent the precast plate from being deformed outward by the pressure of the concrete when the concrete is poured by the connecting material. It is possible to further improve the quality.

【図面の簡単な説明】[Brief description of drawings]

【図1】 施工途中の本発明のコンクリートダムの一実
施例を示す図である。
FIG. 1 is a diagram showing an example of a concrete dam of the present invention during construction.

【図2】 図1のコンクリートダムの施工過程を示す図
であって、上流側の既設のプレキャスト板に次なるプレ
キャスト板を吊り込んでいる状態を示す図である。
FIG. 2 is a diagram showing a construction process of the concrete dam shown in FIG. 1, and is a diagram showing a state in which a next precast plate is suspended from an existing precast plate on the upstream side.

【図3】 図1のコンクリートダムの施工過程を示す図
であって、上流側の既設のプレキャスト板上に次なるプ
レキャスト板を設置した状態を示す図である。
FIG. 3 is a view showing a construction process of the concrete dam shown in FIG. 1, and is a view showing a state in which a next precast plate is installed on an existing precast plate on the upstream side.

【図4】 図1のコンクリートダムの施工過程を示す図
であって、下流側の既設のプレキャスト板に次なるプレ
キャスト板を吊り込んでいる状態を示す図である。
FIG. 4 is a diagram showing a construction process of the concrete dam shown in FIG. 1, and is a diagram showing a state in which a next precast plate is suspended from an existing precast plate on the downstream side.

【図5】 図1のコンクリートダムの施工過程を示す図
であって、上下流側の既設のプレキャスト板上にそれぞ
れ次なるプレキャスト板を設置した状態を示す図であ
る。
FIG. 5 is a diagram showing a construction process of the concrete dam shown in FIG. 1, and is a diagram showing a state in which the following precast plates are respectively installed on the existing precast plates on the upstream and downstream sides.

【図6】 図1のプレキャスト板を示す図である。6 is a diagram showing the precast plate of FIG. 1. FIG.

【図7】 図5のプレキャスト板の設置状態を示す斜視
図である。
FIG. 7 is a perspective view showing an installed state of the precast plate of FIG.

【図8】 図7の上下に隣接したプレキャスト板間の目
地を示す図である。
8 is a diagram showing joints between vertically adjacent precast plates in FIG. 7. FIG.

【図9】 図7の左右に隣接したプレキャスト板間の目
地を示す図である。
FIG. 9 is a diagram showing joints between the precast plates adjacent to each other on the left and right sides of FIG. 7.

【図10】 図7のバックアンカーを示す図である。10 is a diagram showing the back anchor of FIG. 7. FIG.

【図11】 図1のコンクリートダムの施工工程を示す
フローチャートである。
11 is a flowchart showing a construction process of the concrete dam shown in FIG.

【図12】 本発明のコンクリートダムの別の実施例を
示す正面図である。
FIG. 12 is a front view showing another embodiment of the concrete dam of the present invention.

【図13】 図12のコンクリートダムを示す平面図で
ある。
FIG. 13 is a plan view showing the concrete dam of FIG.

【図14】 従来のコンクリートダムを示す図である。FIG. 14 is a diagram showing a conventional concrete dam.

【図15】 従来のコンクリートダムの施工に用いられ
る自動型枠を示す図である。
FIG. 15 is a view showing an automatic formwork used for construction of a conventional concrete dam.

【符号の説明】[Explanation of symbols]

1…プレキャスト板 11…コンクリート 12…バックアンカー(アンカー) 20…ダム本体 31…連結材 Sd…ダム施工領域 S1…コンクリート打設空間 1 ... Precast board 11 ... Concrete 12 ... Back anchor (anchor) 20 ... Dam body 31 ... Connection material Sd ... Dam construction area S1 ... Concrete placing space

───────────────────────────────────────────────────── フロントページの続き (72)発明者 原 夏生 東京都千代田区富士見二丁目10番26号 前 田建設工業株式会社内 (72)発明者 浅井 秀明 東京都千代田区富士見二丁目10番26号 前 田建設工業株式会社内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Natsuo Hara 2-1026 Fujimi, Chiyoda-ku, Tokyo Maeda Construction Industry Co., Ltd. (72) Hideaki Asai 2-1026 Fujimi, Chiyoda-ku, Tokyo Maeda Construction Industry Co., Ltd.

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 コンクリート(11)よりなるダム本体
(20)と、前記ダム本体(20)の上流側及び下流側
に多数のプレキャスト板(1)によりそれぞれ形成され
たダム表層部(10)とにより構成されるコンクリート
ダム。
1. A dam body (20) made of concrete (11), and a dam surface layer (10) formed by a number of precast plates (1) on the upstream side and the downstream side of the dam body (20), respectively. A concrete dam composed by.
【請求項2】 ダム施工領域(Sd)の上流側及び下流
側にそれぞれ複数のプレキャスト板(1)を、内部にコ
ンクリート打設空間(S1)を形成するように設ける第
一工程と、 前記コンクリート打設空間(S1)にコンクリート(1
1)を、前記プレキャスト板(1)を埋め殺しとするよ
うに打設する第二工程と、 前記ダム施工領域(Sd)の上流側に設けられたプレキ
ャスト板(1)の上端、及び前記ダム施工領域(Sd)
の下流側に設けられたプレキャスト板(1)の上端に、
それぞれ複数のプレキャスト板(1)を、既打設の前記
コンクリート(11)の上方に次なるコンクリート打設
空間(S1)を形成するように設ける第三工程と、 前記次なるコンクリート打設空間(S1)に、コンクリ
ート(11)を、前記プレキャスト板(1)を埋め殺し
とするように打設する第四工程とを有し、 前記第三工程及び前記第四工程を繰り返すことによりコ
ンクリート(11)を打ち上げるようにして堤体を築造
することを特徴とするコンクリートダムの施工方法。
2. A first step of providing a plurality of precast plates (1) on the upstream side and the downstream side of a dam construction area (Sd) so as to form a concrete placing space (S1) therein, and the concrete. In the pouring space (S1), concrete (1
The second step of placing 1) so that the precast plate (1) is buried and buried, the upper end of the precast plate (1) provided on the upstream side of the dam construction region (Sd), and the dam Construction area (Sd)
On the upper end of the precast plate (1) provided on the downstream side of
A third step of providing a plurality of precast plates (1) so as to form a next concrete placing space (S1) above the already placed concrete (11), and the following concrete placing space ( S1) has a fourth step of placing the concrete (11) so that the precast plate (1) is buried and buried, and the concrete (11) is obtained by repeating the third step and the fourth step. The concrete dam construction method is characterized in that the dam body is constructed so that
【請求項3】 請求項2記載のコンクリートダムの施工
方法であって、 前記既打設のコンクリート(11)と前記次なるコンク
リート打設空間(S1)を形成するように設けられたプ
レキャスト板(1)との間に、アンカー(12)を設け
ることを特徴とするコンクリートダムの施工方法。
3. The method for constructing a concrete dam according to claim 2, wherein the precast plate (11) is provided so as to form the already placed concrete (11) and the next concrete placing space (S1). A method for constructing a concrete dam, characterized in that an anchor (12) is provided between the anchor and (1).
【請求項4】 請求項2又は3記載のコンクリートダム
の施工方法であって、 前記ダム施工領域(Sd)の上流側のプレキャスト板
(1)と前記ダム施工領域(Sd)の下流側のプレキャ
スト板(1)との間に、連結材(31)を設けることを
特徴とするコンクリートダムの施工方法。
4. The method for constructing a concrete dam according to claim 2, wherein the precast plate (1) upstream of the dam construction area (Sd) and the precast downstream of the dam construction area (Sd). A method for constructing a concrete dam, characterized in that a connecting material (31) is provided between the board (1).
JP20783394A 1994-08-31 1994-08-31 Concrete dam and construction method thereof Withdrawn JPH0868039A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP20783394A JPH0868039A (en) 1994-08-31 1994-08-31 Concrete dam and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP20783394A JPH0868039A (en) 1994-08-31 1994-08-31 Concrete dam and construction method thereof

Publications (1)

Publication Number Publication Date
JPH0868039A true JPH0868039A (en) 1996-03-12

Family

ID=16546278

Family Applications (1)

Application Number Title Priority Date Filing Date
JP20783394A Withdrawn JPH0868039A (en) 1994-08-31 1994-08-31 Concrete dam and construction method thereof

Country Status (1)

Country Link
JP (1) JPH0868039A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001002650A1 (en) * 1999-06-30 2001-01-11 Changquan Jiang Method of horizontal spread with inclined layer for constructing a dam with rolling concrete
JP2015190138A (en) * 2014-03-27 2015-11-02 株式会社熊谷組 Concrete structure construction method and concrete form used with the same
JP2016151152A (en) * 2015-02-18 2016-08-22 Jfe建材株式会社 Weir construction method, and weir

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001002650A1 (en) * 1999-06-30 2001-01-11 Changquan Jiang Method of horizontal spread with inclined layer for constructing a dam with rolling concrete
JP2015190138A (en) * 2014-03-27 2015-11-02 株式会社熊谷組 Concrete structure construction method and concrete form used with the same
JP2016151152A (en) * 2015-02-18 2016-08-22 Jfe建材株式会社 Weir construction method, and weir

Similar Documents

Publication Publication Date Title
US4697955A (en) Method of constructing reinforced concrete works such as underground galleries, road tunnels, et cetera; pre-fabricated contrete elements for constructing such works
KR102061224B1 (en) Sectionally devided precast box culverts and the construction method thereof
CN203924116U (en) Portable side wall formwork jumbo
JPH0841826A (en) Erection method of bridge and equipment thereof and main girder unit
JPH0868039A (en) Concrete dam and construction method thereof
JP2023042601A (en) Construction device for concrete structure
CN214144646U (en) Laminated slab cantilever frame pre-embedding device, building component finished product and cantilever frame structure
CN212025812U (en) Concrete road surface pull rod false joint construction equipment
JP3584402B2 (en) Seawall and its construction method
JPH0868040A (en) Construction method of concrete dam
JP2864906B2 (en) Precast wall joining method
JP3311226B2 (en) Construction method of wave-break water-permeable breakwater
CN110055975A (en) A kind of large-span deep foundation pit basement stage construction method and temporary structure
JP2001164559A (en) Construction method of continuous underground wall guide wall making use of l-type precast member
CN113550572B (en) Basement outer wall post-cast strip structure and construction method thereof
JPH0724483Y2 (en) Soil concrete crack prevention device
SU1148925A1 (en) Method of constructing concrete structures
JP2811139B2 (en) Formwork for dam body and method of constructing dam body using this formwork
CN110725319B (en) Large-angle concrete pouring method
JP3290005B2 (en) Construction method of concrete joint between soil
JP2583058B2 (en) Basement method
JPH0531604B2 (en)
KR100507729B1 (en) Process for setting up structures for excavation of underground
JPH06257214A (en) Concrete casting method of uppermost floor having steer sloping roof
CN116905816A (en) Modularized steel mould for micro-drop plate construction and micro-drop plate construction method

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20011106