JPH0860654A - Construction method of pile with bag - Google Patents
Construction method of pile with bagInfo
- Publication number
- JPH0860654A JPH0860654A JP19148294A JP19148294A JPH0860654A JP H0860654 A JPH0860654 A JP H0860654A JP 19148294 A JP19148294 A JP 19148294A JP 19148294 A JP19148294 A JP 19148294A JP H0860654 A JPH0860654 A JP H0860654A
- Authority
- JP
- Japan
- Prior art keywords
- pile
- auger bit
- excavated
- ground
- bag
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、杭先端に取り付けられ
た袋体の中にセメントミルクやコンクリートを注入して
根固め球根を造成させる袋付杭の施工方法に関するもの
である。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a pile with a bag, in which cement milk or concrete is injected into a bag attached to the tip of the pile to form a rooted bulb.
【0002】[0002]
【従来の技術】従来より、既製杭の先端に袋体を取り付
け、その杭をプレボーリング工法によって拡大掘削した
地盤中に沈設し、しかる後に袋体内に固結性流動物を注
入して根固め球根を造成する工法が知られている。この
工法は、例えば特開昭62−215719号公報や特開
昭62−63721号公報等に示されているものであ
る。従来工法は、図2に示すようにオーガービット21
により地盤を拡大掘削した後、直ちに該拡大掘削孔22
に袋付杭23を沈設し、該袋体24内に固結性流動物2
9を注入して所定径まで膨張させ、杭先端付近に根固め
球根25を造成させるものである。この根固め球根25
の造成によって、大きな支持力が発現できるものであ
る。2. Description of the Related Art Conventionally, a bag is attached to the end of a ready-made pile, and the pile is sunk in the ground that has been enlarged and excavated by the pre-boring method. A method of forming a bulb is known. This construction method is disclosed, for example, in JP-A-62-215719 and JP-A-62-63721. The conventional method is the auger bit 21 as shown in FIG.
Immediately after the ground is expanded and excavated by the
A pile 23 with a bag is sunk in the bag, and the solidified fluid 2
9 is injected and inflated to a predetermined diameter, and a root-fixing bulb 25 is formed near the tip of the pile. This rooting bulb 25
With the creation of, a large supporting force can be expressed.
【0003】[0003]
【発明が解決しようとする課題】しかしながら従来工法
では、地盤を拡大掘削した後、袋付杭23を沈設するま
での間に掘削孔壁26が崩壊して、土砂が掘削孔底部2
7に厚く堆積することがあった。特に標準貫入試験にお
けるN値の低い砂地盤や礫が混入した地盤が崩壊し易
く、この堆積した土砂のために、袋体の膨張が阻害され
て袋体が所定の形状まで膨張できないといった問題があ
った。従って、このような場合には杭の支持力が設計ど
おり発現できないといった現象が発生していた。このた
め、このような場合には、掘削孔28内にベントナイト
等を投入して掘削孔壁26の安定を保つことが行われて
いたが、確実なものではなかった。However, in the conventional method, the excavation hole wall 26 collapses after the ground is enlarged and excavated until the bagged piles 23 are sunk, and the earth and sand are removed by the excavation hole bottom portion 2.
It was sometimes thickly deposited on 7. In particular, in the standard penetration test, the sand with a low N value or the ground mixed with gravel tends to collapse, and the accumulated soil prevents the bag from expanding and the bag cannot expand to a predetermined shape. there were. Therefore, in such a case, there was a phenomenon that the bearing capacity of the pile could not be achieved as designed. Therefore, in such a case, it has been attempted to maintain the stability of the excavation hole wall 26 by introducing bentonite or the like into the excavation hole 28, but this is not reliable.
【0004】本発明は前述したような課題の解決を目的
としたもので、崩壊性の高い地盤において袋付杭を施工
する場合でも、オーガービットでプレボーリングした
後、掘削孔壁の崩壊を生じることがなく、袋体の膨張が
確実に行うことができ、設計通りの安定した支持力が発
揮できる工法を提供するものである。The present invention is intended to solve the above-mentioned problems, and even when a pile with a bag is constructed on a highly collapsible ground, the borehole wall collapses after preboring with an auger bit. It is intended to provide a construction method in which the bag body can be surely inflated without causing the occurrence of a stable supporting force as designed.
【0005】[0005]
【課題を解決するための手段】本発明は、オーガービッ
トにより杭埋設位置を支持地盤まで掘削した後、該オー
ガービットの先端から固結性流動物を吐出させて掘削土
と混合しながら該オーガービットを回収し、その後固結
性流動物が凝結するまで放置し、改めて該杭埋設位置に
おいて、オーガービットにより支持地盤を拡大掘削した
後、先端部外周面に袋体を装着した既製杭を支持地盤ま
で沈設し、しかる後に該袋体内に固結性流動物を注入し
て杭先端部に根固め球根を造成することを特徴とする袋
付杭の施工方法である。According to the present invention, after excavating a pile burying position to a support ground with an auger bit, a solidifying fluid is discharged from the tip of the auger bit to mix the excavated soil with the auger bit. After recovering the bit, it is left to stand until the solidifying fluid is solidified, and at the pile burying position, the support ground is expanded and excavated again, and the ready-made pile with the bag body attached to the outer peripheral surface of the tip is supported. It is a construction method of a pile with a bag, which is characterized by sinking to the ground, and then injecting a solidifying fluid into the bag body to solidify a root at the tip of the pile to form a bulb.
【0006】[0006]
【作用】本発明によれば、オーガービットにより掘削
し、固結性流動物を吐出させて掘削土と混合して凝結さ
せ、改めてオーガービットで掘削し、杭沈設先端を拡大
掘削するので、N値が低く緩い地盤に対しても掘削壁の
崩壊が生じることがなく、掘削孔壁を安定に保つことが
できる。そのため沈設した袋付杭の袋体を確実に膨張さ
せることができる。According to the present invention, since the excavation is carried out by the auger bit, the solidified fluid is discharged and mixed with the excavated soil to be solidified, the auger bit is excavated again, and the pile sunk tip is enlarged and excavated. The excavation wall does not collapse even on low-grade loose ground, and the excavation hole wall can be kept stable. Therefore, it is possible to surely inflate the bag body of the pile with the bag that is sunk.
【0007】[0007]
【実施例】以下、図面に基づいて説明する。図1は本発
明の施工方法の概念図である。先ず、(a)のようにオ
ーガービット1の先端から水等を吐出しながら地盤をス
トレートに掘削するか、或いは先端のみ拡大掘削し、支
持層まで到達させる。次に(b)のようにオーガービッ
ト先端から固結性流動物9を吐出し、掘削土と混合させ
ながらオーガービットを回収する。その後(c)のよう
に固結性流動物9が凝結するまで放置する。次に(d)
のように改めてオーガービットにより支持地盤まで掘削
し、先端部分を拡大掘削する。そしてオーガービットを
回収した後、(e)のように袋付杭3を沈設する。最後
に(f)のように袋体内に固結性流動物9を注入し、根
固め球根5を造成する。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A description will be given below with reference to the drawings. FIG. 1 is a conceptual diagram of the construction method of the present invention. First, as shown in (a), the ground is excavated straight while discharging water or the like from the tip of the auger bit 1, or only the tip is enlarged and excavated to reach the support layer. Next, as shown in (b), the solidifying fluid 9 is discharged from the tip of the auger bit, and the auger bit is collected while mixing with the excavated soil. Then, as in (c), the solidifying fluid 9 is allowed to stand until it is solidified. Then (d)
As described above, the auger bit is used to excavate to the supporting ground, and the tip is enlarged. After collecting the auger bit, the bagged pile 3 is sunk as shown in (e). Finally, as in (f), the solidifying fluid 9 is injected into the bag to form the root-hardening bulb 5.
【0008】本発明に用いる杭は、鋼管杭、コンクリー
ト杭、鋼管コンクリート複合杭である。この杭の先端部
外周面に、袋体がバンドによって装着されている。また
杭には、袋体内に固結性流動物を注入するための注入管
が杭の肉厚部、若くは中空部に設けられている。本発明
に使用する袋体の材質は、ナイロン、ポリエステル、ビ
ニロン、ポリプロピレン等の合成繊維である。このよう
に合成繊維を用いると固結性流動物を注入した際に、固
結性流動物中の水が外へ排出できるため、出来上がった
根固め球根の強度が増加できる。The piles used in the present invention are steel pipe piles, concrete piles and steel pipe concrete composite piles. A bag is attached to the outer peripheral surface of the tip of the pile by a band. In addition, an injection pipe for injecting the solidifying fluid into the bag body is provided in the pile in the thick portion, that is, in the hollow portion of the pile. The material of the bag used in the present invention is synthetic fiber such as nylon, polyester, vinylon, polypropylene and the like. In this way, when the synthetic fluid is used, the water in the solidifying fluid can be discharged to the outside when the solidifying fluid is injected, so that the strength of the completed root-hardening bulb can be increased.
【0009】本発明でいう凝結とは、固結性流動物と土
を混ぜた地盤改良土の強度が、一軸圧縮強度で2〜30
kg/cm2 である。特に土の崩壊に対する抵抗性と掘
削時のオーガービットの貫入性の面から5〜10kg/
cm2 が好ましい。(a)で行う掘削の掘削径dおよび
Dは、(d)で行う掘削の掘削径d’およびD’と同等
か、或いは10cm程度大きいものが好ましい。即ち、
(d)で行う拡大掘削によって、掘削孔壁6が崩壊しな
いように、掘削孔壁6の周面10に十分に固結性流動物
9が行き渡るようにする必要があるからである。また、
該オーガービット1は先端のみ拡大掘削できる構造のも
の(例えば拡大掘削刃14等が付いているもの)を使用
した方が、排出する土砂が少なくなり、また(b)で使
用する固結性流動物9が少なくなるので好ましい。更に
また、該オーガービット1上方のロッド11は、投入し
た固結性流動物9と掘削した土が混合し易いように、ス
クリュー状のものか、或いは撹拌アーム12の付いたも
の等が好ましい。(b)において地盤中に吐出させる固
結性流動物9は、一般的にはセメントミルクであるが、
地盤条件によっては珪酸塩ソーダを基材とするグラウト
材等を用いても良い。The setting in the present invention means that the strength of the ground-improved soil obtained by mixing the solidifying fluid and the soil is 2 to 30 in uniaxial compressive strength.
It is kg / cm 2 . 5-10 kg / from the viewpoint of resistance to soil collapse and penetration of auger bit during excavation
cm 2 is preferred. The excavation diameters d and D of the excavation performed in (a) are preferably equal to or larger than the excavation diameters d ′ and D ′ of the excavation performed in (d), or about 10 cm. That is,
This is because it is necessary to sufficiently spread the caking fluid 9 on the peripheral surface 10 of the drill hole wall 6 so as not to collapse the drill hole wall 6 by the expanded drilling performed in (d). Also,
The auger bit 1 has a structure in which only the tip can be expanded and excavated (for example, one with an expanded excavation blade 14 etc.), which reduces the amount of earth and sand discharged, and the solidifying flow used in (b). This is preferable because it reduces the number of animals 9. Furthermore, the rod 11 above the auger bit 1 is preferably a screw-shaped one or one with a stirring arm 12 so that the injected solidifying fluid 9 and the excavated soil can be easily mixed. Although the solidifying fluid 9 discharged into the ground in (b) is generally cement milk,
Depending on the ground conditions, a grout material having silicate soda as a base material may be used.
【0010】固結性流動物の使用量は、地盤条件によっ
て異なるが、水セメント比60〜70%のセメントミル
クの場合は、掘削ボリュームに対して体積比で5〜20
%程度が好ましい。固結性流動物は、最低限、崩壊性の
高い地層の上面以上まで充填する必要がある。(c)に
おいては、固結性流動物が十分凝結するまで放置するこ
とが必要である。固結性流動物としてセメントミルクを
用いる場合、放置する時間は約2時間以上である。The amount of the solidifying fluid used depends on the ground conditions, but in the case of cement milk having a water-cement ratio of 60 to 70%, the volume ratio is 5 to 20 with respect to the excavation volume.
% Is preferable. It is necessary to fill the solidified fluid to at least the upper surface of the highly collapsible formation. In (c), it is necessary to leave it until the caking fluid is sufficiently set. When cement milk is used as the caking fluid, it is left for about 2 hours or longer.
【0011】その後、従来工法と同様の施工方法を行
う。(d)で行う掘削では、掘削能率を上げるために、
オーガービット1先端から水等の掘削液を吐出した方が
良い。また、掘削孔の底部7には、根固め球根5との空
隙を埋める目的で、若干のセメントミルク等の硬化材1
3を投入したほうが良い。このようにして造成された拡
大掘削孔2は、掘削孔壁6が固結性流動物9によって、
強固な地盤に改良されているために、崩壊する恐れが全
くないのである。After that, a construction method similar to the conventional construction method is performed. In the excavation performed in (d), in order to increase the excavation efficiency,
It is better to discharge the drilling fluid such as water from the tip of the auger bit 1. Further, at the bottom portion 7 of the excavation hole, some hardening material 1 such as cement milk is used for the purpose of filling a gap with the root consolidation bulb 5.
It is better to throw in 3. In the expanded excavation hole 2 thus formed, the excavation hole wall 6 is formed by the solidifying fluid 9.
Since it has been improved to a solid ground, there is no danger of it collapsing.
【0012】従って、その後の(e)、(f)の工程が
極めてスムーズに、しかも確実に行うことができるので
ある。つまり、根固め球根9が所定の形状まで確実に造
成できるため、大きな支持力が安定的に確保できるので
ある。Therefore, the subsequent steps (e) and (f) can be performed extremely smoothly and reliably. That is, since the rooting bulb 9 can be reliably formed into a predetermined shape, a large supporting force can be stably ensured.
【0013】[0013]
【実施例】以下、実施例により本発明を詳細に説明す
る。本発明の工法によって袋付杭3を5本施工した。支
持層はGL−20m〜25mに分布する砂礫層である
が、GL−13m〜16mに崩壊性の高い砂礫層が存在
する地盤であった。本発明の工法には、図1の(a)に
示す構造の掘削治具を用いた。即ち、外径200mmの
ロッド11に外径600mm、拡大掘削時の外径が95
0mmになるようなオーガービット1を設置した。この
オーガービット1により、GL−23mまで掘削し、先
端3mの範囲を拡大掘削した。その後、水セメント比7
0%のセメントミルクを掘削ボリュームに対して体積比
10%の割合で掘削孔8内に投入し、ロッド11の撹拌
アーム12によって掘削土と混合させた後にオーガービ
ット1を回収し、セメントミルクが凝結するまで約2時
間放置した。次に外径200mmのロッドに外径530
mm、拡大掘削時の外径が860mmになるようなオー
ガービット1を設置して、再掘削を行った。掘削長は同
じくGL−23mで、先端3mの範囲を拡大掘削した。
この掘削孔内に、外径500mm、長さ23mのSC杭
で、先端に外径900mm、長さ3mのナイロン製の袋
体を取り付けたものをGL−23mまで沈設した。地上
より、この袋体内に水セメント比60%のセメントミル
クを注入した結果、5本全て設計通りの大きさの根固め
球根5、即ち外径800mm〜860mmの根固め球根
5を造成することができた。The present invention will be described in detail below with reference to examples. Five piles 3 with bags were constructed by the construction method of the present invention. The support layer was a gravel layer distributed in GL-20m to 25m, but was a ground in which a highly collapsible gravel layer was present in GL-13m to 16m. For the construction method of the present invention, an excavating jig having a structure shown in FIG. That is, the outer diameter of the rod 11 having an outer diameter of 200 mm is 600 mm, and the outer diameter at the time of enlarged excavation is 95 mm.
An auger bit 1 having a size of 0 mm was installed. The auger bit 1 was used to excavate up to GL-23m and expand the range of the tip 3m. Then water cement ratio 7
0% cement milk was introduced into the excavation hole 8 at a volume ratio of 10% with respect to the excavation volume, mixed with excavated soil by the stirring arm 12 of the rod 11, and then the auger bit 1 was recovered. It was left for about 2 hours until it set. Next, an outer diameter of 530 is attached to a rod with an outer diameter of 200 mm.
mm, and the auger bit 1 having an outer diameter of 860 mm when expanded and excavated was installed, and re-excavation was performed. The excavation length was also GL-23m, and the range of the tip 3m was enlarged and excavated.
An SC pile having an outer diameter of 500 mm and a length of 23 m with a nylon bag having an outer diameter of 900 mm and a length of 3 m attached to the tip was sunk to the GL-23 m in the excavated hole. As a result of injecting cement milk with a water-cement ratio of 60% into the bag from the ground, it is possible to create 5 root-fixing bulbs 5 of the size as designed, that is, root-fixing bulbs 5 having an outer diameter of 800 mm to 860 mm. did it.
【0014】[0014]
【比較例】実施例と同じ仕様の杭を5本、図2のような
従来工法によって同一地盤に施工した。その結果、5本
共、所定形状に対して約5〜7割の大きさの根固め球
根、即ち外径650mm〜700mmの根固め球根しか
造成できなかった。掘り出し調査を行った結果、掘削孔
壁が崩壊して礫が掘削孔底面に堆積したため、袋体膨張
が阻害されたことが判明した。[Comparative Example] Five piles having the same specifications as those of the example were constructed on the same ground by the conventional method as shown in FIG. As a result, it was possible to produce only 5 to 70% of the root-consolidating bulbs having a predetermined shape, that is, the root-consolidating bulbs having an outer diameter of 650 mm to 700 mm. As a result of the excavation investigation, it was found that the bag body expansion was hindered because the hole wall collapsed and gravel accumulated on the bottom surface of the hole.
【0015】[0015]
【発明の効果】本発明の工法によれば、崩壊性の高い地
盤において袋付杭を施工する場合でも、オーガービット
でプレボーリングした際、掘削孔に固結性流動物を吐出
させて掘削土と混合して凝結させ、改めてオーガービッ
トで掘削したので、掘削孔壁の崩壊を生じることがな
く、袋体の膨張が確実に行うことができる。従って設計
通りの大きな支持力を発現させ得る。EFFECTS OF THE INVENTION According to the method of the present invention, even when a pile with a bag is constructed on a highly collapsible ground, when preboring with an auger bit, the solidified fluid is discharged into the excavation hole to excavate the excavated soil. Since the mixture is mixed with and coagulated and excavated again with the auger bit, the bag wall can be surely inflated without collapsing the hole wall. Therefore, a large supporting force as designed can be expressed.
【図1】本発明の工法の概念図である。FIG. 1 is a conceptual diagram of a construction method of the present invention.
【図2】従来工法の概念図である。FIG. 2 is a conceptual diagram of a conventional method.
1 オーガービット 2 拡大掘削孔 3 袋付杭 4 袋体 5 根固め球根 6 掘削孔壁 7 掘削孔底部 8 掘削孔 9 固結性流動物 10 掘削孔壁の周面 11 ロッド 12 撹拌アーム 13 セメントミルク等の硬化材 14 拡大掘削刃 21 オーガービット 22 拡大掘削孔 23 袋付杭 24 袋体 25 根固め球根 26 掘削孔壁 27 掘削孔底部 28 掘削孔 1 Auger Bit 2 Expanded Drilling Hole 3 Bag Pile 4 Bag Body 5 Rooting Bulb 6 Drilling Hole Wall 7 Drilling Hole Bottom 8 Drilling Hole 9 Solidifying Fluid 10 Circumferential Surface of Drilling Hole Wall 11 Rod 12 Stirring Arm 13 Cement Milk Hardened materials such as 14 Expanded drilling blade 21 Auger bit 22 Expanded drilled hole 23 Bagged pile 24 Bag body 25 Rooting bulb 26 Drilled hole wall 27 Drilled hole bottom 28 Drilled hole
Claims (1)
地盤まで掘削した後、該オーガービットの先端から固結
性流動物を吐出させて掘削土と混合しながら該オーガー
ビットを回収し、その後固結性流動物が凝結するまで放
置し、改めて該杭埋設位置において、オーガービットに
より支持地盤を拡大掘削した後、先端部外周面に袋体を
装着した既製杭を支持地盤まで沈設し、しかる後に該袋
体内に固結性流動物を注入して杭先端部に根固め球根を
造成することを特徴とする袋付杭の施工方法。1. After excavating a pile burying position to a support ground with an auger bit, a solidifying fluid is discharged from a tip of the auger bit to collect the auger bit while mixing with excavated soil, and then solidified. After leaving the fluidized material to solidify, at the pile burying position again, after enlarging and excavating the support ground with an auger bit, the ready-made pile with the bag body attached to the tip outer peripheral surface is sunk to the support ground, and then the A method for constructing a pile with a bag, comprising injecting a solidifying fluid into a bag body to solidify a root at a tip of the pile to form a bulb.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP19148294A JPH0860654A (en) | 1994-08-15 | 1994-08-15 | Construction method of pile with bag |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP19148294A JPH0860654A (en) | 1994-08-15 | 1994-08-15 | Construction method of pile with bag |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH0860654A true JPH0860654A (en) | 1996-03-05 |
Family
ID=16275386
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP19148294A Pending JPH0860654A (en) | 1994-08-15 | 1994-08-15 | Construction method of pile with bag |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0860654A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101838987A (en) * | 2010-04-21 | 2010-09-22 | 东南大学 | Operation method of piles with variable cross section for reinforcing shield end soil body |
-
1994
- 1994-08-15 JP JP19148294A patent/JPH0860654A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101838987A (en) * | 2010-04-21 | 2010-09-22 | 东南大学 | Operation method of piles with variable cross section for reinforcing shield end soil body |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2008088746A (en) | Replacing construction method of column | |
JP4154487B2 (en) | Foundation pile construction method, foundation pile | |
JP2005282063A (en) | Composite field preparation pile, its construction method and device for preparing composite field preparation pile | |
JPH0860654A (en) | Construction method of pile with bag | |
JPH08199566A (en) | Construction method of pile | |
JPH10237866A (en) | Method for constructing foundation of building | |
JPS5817849B2 (en) | Foundation pile construction method | |
JP3200240B2 (en) | Filling method of self-hardening material in ground reinforcement method | |
JPH0280710A (en) | Preparing cast-in-place concrete pile | |
JPH08199567A (en) | Construction method of pile | |
JP4200237B2 (en) | Construction method of foundation pile | |
JP2575139B2 (en) | Burying method of ready-made pile | |
JP4475845B2 (en) | Pile construction method | |
JPH0627405B2 (en) | Ready-made pile burying method | |
CN212772407U (en) | Grouting device | |
JPH0240151Y2 (en) | ||
JP2589672B2 (en) | Construction method of ready-made pile | |
JP3182585B2 (en) | Construction method of composite pile for supporting column | |
KR900005913B1 (en) | Base stake inflated in bump state at lower end there of and its construction | |
JPH0325121A (en) | Sinking of pile in inner drilling pile method | |
JPH0656017B2 (en) | Construction method for ready-made piles | |
JPH0718157B2 (en) | Piling method | |
JPH0442493B2 (en) | ||
JPS61113924A (en) | Method of forming pileform body | |
JPH09125389A (en) | Pile construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20040106 |
|
A02 | Decision of refusal |
Effective date: 20040406 Free format text: JAPANESE INTERMEDIATE CODE: A02 |