JPH08319689A - Concrete slab board having solid embedded material, construction method for concrete slab using the slab and structure thereof - Google Patents

Concrete slab board having solid embedded material, construction method for concrete slab using the slab and structure thereof

Info

Publication number
JPH08319689A
JPH08319689A JP12768995A JP12768995A JPH08319689A JP H08319689 A JPH08319689 A JP H08319689A JP 12768995 A JP12768995 A JP 12768995A JP 12768995 A JP12768995 A JP 12768995A JP H08319689 A JPH08319689 A JP H08319689A
Authority
JP
Japan
Prior art keywords
concrete slab
concrete
substrate
piping
embedding material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP12768995A
Other languages
Japanese (ja)
Other versions
JP3346948B2 (en
Inventor
Terumaro Nagai
照麿 永井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sekisui Kasei Co Ltd
Original Assignee
Sekisui Plastics Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sekisui Plastics Co Ltd filed Critical Sekisui Plastics Co Ltd
Priority to JP12768995A priority Critical patent/JP3346948B2/en
Publication of JPH08319689A publication Critical patent/JPH08319689A/en
Application granted granted Critical
Publication of JP3346948B2 publication Critical patent/JP3346948B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)

Abstract

PURPOSE: To facilitate the layout of utility piping. CONSTITUTION: When constructing a concrete slab by laying out a concrete slab board A between beams of a skeleton wherein an embedded material 1 made of synthetic resin expansion molded product is laid out with a specified spacing on a concrete board 3, it is necessary to use a concrete slab board A where a solid embedded material (u) is laid out as for a site scheduled for the layout of piping P at least during construction time. After a piping route is formed on the solid embedded material 1, piping work is executed and caste- in-place concrete is placed.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、構築物のコンクリート
スラブ内部へ、電気配線や電話配線等のシールドとして
用いられる合成樹脂製電線管(CD管)や給水、給湯用
管路等のためのさや管等の種々の設備用配管を容易に敷
設することを可能とするコンクリートスラブ用基板、該
基板を用いたコンクリートスラブの施工方法、及び該基
板を持つ構築物に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a sheath for a synthetic resin electric wire pipe (CD pipe) used as a shield for electric wiring, telephone wiring, etc., for water supply, hot water supply pipe, etc., inside a concrete slab of a structure. The present invention relates to a concrete slab substrate that enables easy laying of various equipment pipes such as pipes, a concrete slab construction method using the substrate, and a structure having the substrate.

【0002】[0002]

【従来の技術】最近のコンクリート系集合住宅の床構造
体は経済性等の観点から直床、直天井仕上げが一般的と
なっており、前記のような種々の配管はコンクリートス
ラブ内部に直接埋設されるようになっている。一方、コ
ンクリートスラブの施工法として、軽量化、遮音効果を
向上させる目的で、図5に示すように、例えば発泡ポリ
スチレンのような合成樹脂発泡成形品からなる内部に中
空部を持つ埋込材1を、トラス筋2を備えたコンクリー
ト基板3上に、所定の間隔で複数個、コンクリートが未
硬化の養生過程中に配設して係止具により係止し、コン
クリートの硬化により埋込材1をコンクリート基板3に
定着固定した中空コンクリートスラブ用基板Aを用い、
このコンクリートスラブ用基板Aを建築施工現場に搬入
して、図6に示すように必要個数、躯体の梁B、B間に
配置し、スラブ上端筋4等を取り付けた後、現場打ちコ
ンクリートCを打設していわゆる中空コンクリートスラ
ブCSを構築する施工法が広く行われている。図7、図
8は埋込材1の一例であり、天板部10と側壁部11と
中仕切り壁12とを持つ全体として箱状(矩形状)の形
状をなし、内部に一方側を解放した比較的大きな底面積
を持つ複数の中空部Sを有している(特公昭57−47
008号公報等参照)。この中空部Sは埋込材1の軽量
化及び材料節減の目的から設けられる。
2. Description of the Related Art In recent years, floor structures for concrete apartment houses are generally finished with a straight floor or a straight ceiling from the viewpoint of economy, and the various pipes described above are directly buried inside a concrete slab. It is supposed to be done. On the other hand, as a construction method for a concrete slab, as shown in FIG. 5, an embedding material 1 having a hollow portion inside made of a synthetic resin foam molded article such as expanded polystyrene, for the purpose of reducing the weight and improving the sound insulation effect. Are placed at a predetermined interval on the concrete substrate 3 having the truss streaks 2 during the curing process in which the concrete is uncured and locked by the locking tool, and the embedding material 1 is cured by hardening the concrete. Using a substrate A for hollow concrete slab, which is fixed and fixed to a concrete substrate 3,
This concrete slab substrate A is carried into the construction site, and as shown in FIG. 6, the required number of the slab substrates B and B are arranged between them and the slab upper end streak 4 and the like are attached, and then the cast-in-place concrete C is placed. A construction method in which a so-called hollow concrete slab CS is constructed by casting is widely used. 7 and 8 show an example of the embedding material 1, which has a box-shaped (rectangular) shape as a whole having a top plate portion 10, a side wall portion 11, and a partition wall 12, and one side is released inside. It has a plurality of hollow portions S having a relatively large bottom area (Japanese Patent Publication No. 57-47).
(See Japanese Patent Publication No. 008). The hollow portion S is provided for the purpose of reducing the weight of the embedding material 1 and saving the material.

【0003】そして、上記のような埋込材1を用いたコ
ンクリートスラブCSにおいて上記のような配管の埋設
工事を行うに当たっては、図9に示すように埋込材1と
埋込材1の間に形成される現場打ちコンクリート充填用
空間部SSに前記のような設備用配管Pを配置し、その
上から現場打ちコンクリートを打設する。そのために、
目標の2地点間に配管するのに迂回路を取ることが必然
となり、本来必要とされる距離以上の配管距離が必要と
なる。また、配管が占める容積だけ打設されるコンクリ
ート量が低減する。
Then, in performing the burying work of the pipe as described above in the concrete slab CS using the burying material 1 as described above, as shown in FIG. 9, between the burying material 1 and the burying material 1. The above-mentioned equipment pipe P is arranged in the space SS for filling the cast-in-place concrete formed in 1, and the cast-in-place concrete is poured from above. for that reason,
It is inevitable to take a detour for piping between the two target points, and a piping distance longer than originally necessary is required. In addition, the amount of concrete to be placed is reduced by the volume occupied by the pipes.

【0004】また、埋込材として上面に凹溝を持つもの
を配置したコンクリートスラブ用基板を用いてコンクリ
ートスラブを構築することも提案されており、現場打ち
コンクリートが該凹溝内に流入固化することによりコン
クリートスラブの防振効果が増大すると共に、該凹溝を
配管にも利用できるとしている(実公昭60−3224
8号公報参照)。
It has also been proposed to construct a concrete slab by using a concrete slab substrate in which an embedding material having a groove on the upper surface is arranged, and the cast-in-place concrete flows into the recess and solidifies. As a result, the anti-vibration effect of the concrete slab is increased and the concave groove can be used for piping (Jitsuko Sho 60-3224).
No. 8).

【0005】[0005]

【発明が解決しようとする課題】コンクリートスラブ中
に埋設すべき配管の本数が少ない場合には、配管距離の
増大が施工コストに与える影響は小さく格別の問題はな
い。また、埋込材と埋込材の間の現場打ちコンクリート
充填用空間部に配管を配置してその上から現場打ちコン
クリートを打設しても、打設コンクリートは該空間内に
密に行きわたることができ、打設コンクリートの量の減
少も少ないことから、コンクリートスラブに顕著な断面
欠損を引き起こすこともない。
When the number of pipes to be buried in the concrete slab is small, the increase in the pipe distance has a small effect on the construction cost, and there is no particular problem. Also, even if a pipe is placed in the space for filling the cast-in-place concrete between the potting material and the cast-in-place concrete is placed from above, the cast concrete will spread densely in the space. Since it is possible to reduce the amount of cast concrete, the concrete slab does not cause a significant cross-section loss.

【0006】しかしながら、近年施工されるコンクリー
ト系集合住宅においては従来の電気や電話線のための配
管に加えて、衛星放送や有線放送等の配線、ホームセキ
ュリティ設備用配線のための配管、さらには給水、給湯
用管路等のさや管としての配管等の種々の配管をコンク
リートスラブ中に埋設するようになってきており、さら
に、各部屋ごとにそれぞれのコンセントを配設する傾向
にあることから、電気、水等の分配のために配管の必要
分岐数も増大し配管距離も増大しつつある。
However, in concrete-type apartment houses constructed in recent years, in addition to the conventional piping for electricity and telephone lines, wiring for satellite broadcasting, cable broadcasting, etc., piping for wiring for home security equipment, and Various pipes such as pipes for water supply and hot water supply pipes are being buried in concrete slabs, and there is a tendency for each room to have its own outlet. , The number of branches required for distribution of electricity, water, etc. is increasing, and the piping distance is also increasing.

【0007】そのために、図9に示すように、コンクリ
ート充填用空間部SSには多数本の配管Pが配置される
こととなり、現場打ちコンクリートの打設時に十分な注
意を払わないと該空間部SS内においてコンクリートが
密に侵入せず配管Pと配管Pとの間に空隙が形成される
場合がある。また、打設されるコンクリートの量も低減
することから、この面からも十分な施工管理が必要とさ
れる。さらに、多数本の配管を枡目状に形成されるコン
クリート充填用空間部を迂回しながら配置していくこと
は多くの作業を必要とし、また、配管距離も増大する。
For this reason, as shown in FIG. 9, a large number of pipes P are arranged in the concrete filling space SS, and if sufficient attention is not paid at the time of pouring the cast-in-place concrete, the space P will be filled. In SS, concrete may not densely enter and a void may be formed between the pipe P and the pipe P. Also, since the amount of concrete to be placed is reduced, sufficient construction management is required from this aspect as well. Furthermore, arranging a large number of pipes while circumventing the concrete-filling space portion formed in a grid shape requires a lot of work, and also increases the pipe distance.

【0008】中空部を持つ埋込材を全面に配置したコン
クリートスラブ用基板を敷設した現場での配管作業にお
いて、該埋込材を部分的に切除あるいは溝切り加工して
配管用の通路を作り、その通路を通して配管を行うこと
により配管距離を短くすることも一部行われているが、
中空部を持つ埋込材を切除あるいは溝切り加工した場合
に、その加工面が前記中空部に連通してしまうことが生
じ得、そのままの状態で現場打ちコンクリートを打設す
ると、その加工面から中空部内に現場打ちコンクリート
が侵入してその部分の重量が過大化する恐れがある。そ
れにより、コンクリートスラブとしての空隙率が低下す
る。
In a piping work at a site where a concrete slab substrate having an embedding material having a hollow portion is laid on the entire surface, the embedding material is partially cut or grooved to form a passage for the piping. , It is partly done to shorten the piping distance by piping through the passage,
When cutting or grooving an embedding material with a hollow part, the processed surface may be connected to the hollow part. There is a risk that the cast-in-place concrete will enter the hollow part and the weight of that part will become excessive. This reduces the porosity of the concrete slab.

【0009】また、実公昭60−32248号公報に開
示されるコンクリートスラブ用基板においては、配置さ
れる埋込材はすべて表面に凹溝を持つものであり、該凹
溝を配管用に利用するとしても、コンクリートスラブの
全面積に占める配管面積の割合は少ないことから、コン
クリートスラブ全体としてみれば、結果として、凹溝分
だけ空隙率が減少するため、さらに高い空隙率を持つコ
ンクリートスラブが求められている。
Further, in the concrete slab substrate disclosed in Japanese Utility Model Publication No. 60-32248, all the embedding materials to be arranged have concave grooves on the surface, and the concave grooves are used for piping. Even so, since the proportion of the piping area in the total area of the concrete slab is small, when looking at the concrete slab as a whole, as a result, the porosity is reduced by the amount of the concave groove, so a concrete slab with a higher porosity is sought. Has been.

【0010】本発明の目的は、合成樹脂発泡成形品から
なる埋込材を内部に持つコンクリートスラブ中に多数本
の設備配管を埋設する際に生じている上記のような問題
点を解消することにあり、特に、多数の配管を確実かつ
容易に配置することが可能でありながら、同時に高い空
隙率を維持することを可能としたコンクリートスラブ用
基板及び該基板を用いたコンクリートスラブの施工方
法、そのようなコンクリートスラブ用基板を持つ構築物
を提供することにある。
An object of the present invention is to eliminate the above-mentioned problems that occur when a large number of equipment pipes are embedded in a concrete slab having an embedding material made of a synthetic resin foam molded product inside. In particular, in particular, it is possible to arrange a large number of pipes reliably and easily, at the same time, a concrete slab substrate capable of maintaining a high porosity and a method of constructing a concrete slab using the substrate, It is to provide a structure having such a concrete slab substrate.

【0011】[0011]

【課題を解決するための手段】上記の課題を解決するた
めの本発明によるコンクリートスラブ用基板の一つの態
様は、コンクリート基板上に合成樹脂発泡成形品からな
る中実の埋込材が所定の間隔で配置されてなることを特
徴とする。また、本発明によるコンクリートスラブ用基
板のもう一つの態様は、コンクリート基板上に合成樹脂
発泡成形品からなる埋込材が所定の間隔で配置されてな
るコンクリートスラブ用基板であって、該コンクリート
スラブ用基板を用いてのコンクリートスラブの構築時に
配管の敷設が予定される箇所の埋込材は中実のものとさ
れ、他の埋込材は中空部を持つもとされることを特徴と
する。
One embodiment of a concrete slab substrate according to the present invention for solving the above problems is that a solid embedding material made of a synthetic resin foam molded article is provided on a concrete substrate. It is characterized by being arranged at intervals. Another aspect of the concrete slab substrate according to the present invention is a concrete slab substrate in which embedding materials made of a synthetic resin foam molded product are arranged at a predetermined interval on the concrete substrate. It is characterized in that the embedding material at the place where the piping is to be laid when constructing the concrete slab using the circuit board is solid, and the other embedding materials have a hollow part. .

【0012】本発明は、上記のコンクリートスラブ用基
板を用いたコンクリートスラブの施工方法として、コン
クリートスラブの基板として前記いずれかの態様のコン
クリートスラブ用基板を必要に応じて敷設し、施工現場
において該コンクリートスラブ用基板の中実である埋込
材部分に配管部材を通過させるための通路を形成し、該
通路内を通過させて必要な配管作業を行い、しかる後、
その上から現場打ちコンクリートを打設することを特徴
とするコンクリートスラブの施工方法を開示する。
The present invention provides a method for constructing a concrete slab using the above concrete slab substrate, in which the concrete slab substrate according to any one of the above-described embodiments is laid as a substrate of the concrete slab, and the Forming a passage for passing a piping member in the embedding material portion which is solid for the concrete slab substrate, and performing the necessary piping work by passing through the passage, after that,
Disclosed is a method for constructing a concrete slab, which comprises pouring in-place concrete from above.

【0013】また、本発明は、コンクリートスラブの基
板として上記したコンクリートスラブ用基板を持つ構築
物をも開示する。
The present invention also discloses a structure having the above-mentioned concrete slab substrate as a substrate for the concrete slab.

【0014】[0014]

【作 用】本発明によるコンクリートスラブ用基板によ
れば、いずれの態様のコンクリートスラブ用基板であっ
ても、施工現場での埋込材への配管用通路あるいは凹溝
の形成は、中実である埋込材に対して行われる。それに
より、従来の中空部を持つ埋込材を切除する場合のよう
に、配管用通路あるいは凹溝の形成時に中空部への連通
孔が形成されて埋込材内部に現場打ちコンクリートが侵
入し、空隙率を低下させることは回避できる。また、中
実であることから作業者は凹溝あるいは通路を容易にか
つ任意の方向に形成することができ、特に、全ての埋込
材が中実のものにより構成されるコンクリートスラブ用
基板の場合には、施工現場での配管配置に変更が生じた
ような場合に、迅速に対応することが可能となる。
[Operation] According to the concrete slab substrate of the present invention, regardless of the aspect of the concrete slab substrate, the formation of the pipe passage or the concave groove in the embedding material at the construction site is solid. This is done for some embedding materials. As a result, as in the case of cutting an embedding material with a conventional hollow part, a communication hole to the hollow part is formed at the time of forming a passage for a pipe or a concave groove, and the cast-in-place concrete enters the embedding material inside. However, lowering the porosity can be avoided. Further, since it is solid, the operator can easily form the concave groove or the passage in any direction, and in particular, for the concrete slab substrate in which all the embedding materials are solid. In this case, it becomes possible to promptly respond to a case where the piping arrangement at the construction site is changed.

【0015】このようにして形成した通路あるいは凹溝
を通過させ配管作業を行うことにより、迂回させること
なく配管作業を終えることができる。また、複数本の配
管を平行して配置する場合には、それに必要な幅の通路
あるいは凹溝を確実にかつ容易に形成することもでき
る。必要な配管を終えた後、必要に応じてスラブ上端筋
の取り付け等の従来の工法と同様の作業を行い、現場打
ちコンクリートを打設する。配管は形成された通路ある
いは凹溝内に入り込んでいるために、配管の上方端の高
さは周囲の中空部を持つ埋込材の高さとほぼ同じ高さと
なっており、スラブ上端筋の取り付け等も従来のコンク
リートスラブ用基板の場合と同様に行うことができる。
By performing the piping work by passing through the passage or the concave groove formed in this way, the piping work can be completed without detouring. Further, when a plurality of pipes are arranged in parallel, it is possible to surely and easily form a passage or a groove having a width required for the pipes. After finishing the necessary piping, if necessary, perform the same work as the conventional method such as attaching the slab upper end streak, and pour in-place concrete. Since the pipe is inserted into the formed passage or groove, the height of the upper end of the pipe is almost the same as the height of the embedding material with the surrounding hollow part. The same can be performed as in the case of the conventional concrete slab substrate.

【0016】本発明によるコンクリートスラブ用基板を
敷設したコンクリートスラブにあっては、従来のよう
に、現場打ちコンクリート充填用空間部SSに多くの本
数の配管を集中配置することを避けることができ、現場
打ちコンクリートとコンクリート基板との一体化不足や
該空間部内での設備配管に起因する空隙の発生も回避で
きる。また、配管が上面に配置されない埋込材として従
来知られたコンクリートスラブ用基板に用いられている
埋込材と同じ中空部を持つものをそのまま配置する場合
には、コンクリートスラブ全体としての空隙率も高く維
持することができる。
In the concrete slab on which the substrate for concrete slab according to the present invention is laid, it is possible to avoid concentrating a large number of pipes in the space SS for in-place concrete filling as in the prior art. Insufficient integration of cast-in-place concrete and concrete substrate and generation of voids due to equipment piping in the space can be avoided. Also, when placing a pipe that has the same hollow part as the embedding material used for the conventionally known concrete slab substrate as the embedding material that is not placed on the top surface, the porosity of the entire concrete slab is Can also be kept high.

【0017】[0017]

【実施例】以下、実施例に基づき本発明をより詳細に説
明する。図1は、例えば図6に示されるように躯体の梁
B、B間にコンクリートスラブ用基板Aを配置した構築
物のコンクリートスラブCS部分の一例を模式的に示し
た平面図であり、この実施例においては、コンクリート
スラブ用基板Aが5枚(A1 〜A5 )配置されている。
そしてこのコンクリートスラブCSには、図示されるよ
うに配管用ボックスV1 が2番目のコンクリートスラブ
用基板A2 に取り付けられ、そこから3方の側壁に設け
たコンセント21、22、23に向けて、前記したよう
な電線用あるいは水用の種々の施設用配管P1、P2、
P3が配置されるような設計になっており、さらに4番
目のコンクリートスラブ用基板A4と5番目のコンクリ
ートスラブ用基板A5 にも配管用ボックスV2 、V3
取り付けられ、両配管用ボックスV2 とV3 とを配管P
4で接続するような設計となっている。以下、この設計
条件に従いコンクリートスラブを施工する場合を例にと
り本発明の一実施例を説明する。
The present invention will be described in more detail based on the following examples. FIG. 1 is a plan view schematically showing an example of a concrete slab CS portion of a structure in which a concrete slab substrate A is arranged between the beams B and B of a frame as shown in FIG. 6, for example. In FIG. 5, five concrete slab substrates A (A 1 to A 5 ) are arranged.
In this concrete slab CS, a pipe box V 1 is attached to a second concrete slab substrate A 2 as shown in the drawing, and from there, toward the outlets 21, 22, 23 provided on the three side walls. , Various facility pipes P1, P2 for electric wires or for water as described above,
It is designed so that P3 is placed, and the piping boxes V 2 and V 3 are also attached to the fourth concrete slab board A 4 and the fifth concrete slab board A 5 for both pipes. Piping P between boxes V 2 and V 3
It is designed to connect with 4. An embodiment of the present invention will be described below by taking the case of constructing a concrete slab according to these design conditions as an example.

【0018】この場合において、工場でコンクリートス
ラブ用基板A1 〜A5 を製造するに際して、以下の5種
類の異なった構造のものが用意される。この実施例にお
いては、図示されるように、施工現場での配管作業時
に、コンクリートスラブ用基板A1 においては、図1に
おいて右から3列目に位置する斜線で示される埋込材x
1〜x3部分を配管P2が通過する。従って、このコン
クリートスラブ用基板A1 の工場での製造に際しては、
斜線で示す埋込材x1〜x3の部分については、合成樹
脂発泡体からなる中実の埋込材1uを配置、固定し、他
の部分には例えば図6、図7に示したような標準化され
た中空部を持つ埋込材1・・を配置、固定する。
In this case, when manufacturing the concrete slab substrates A 1 to A 5 in the factory, the following five different structures are prepared. In this embodiment, as shown in the drawing, during the piping work at the construction site, in the concrete slab substrate A 1 , the embedding material x indicated by the diagonal lines located in the third column from the right in FIG.
The pipe P2 passes through the portions 1 to x3. Therefore, when manufacturing this concrete slab substrate A 1 in a factory,
Solid embedding materials 1u made of synthetic resin foam are arranged and fixed in the portions of the embedding materials x1 to x3 indicated by diagonal lines, and the other portions are standardized as shown in FIGS. 6 and 7, for example. The embedding material 1 having a hollow portion is arranged and fixed.

【0019】コンクリートスラブ用基板A2 において
は、図示されるように右から3列目に位置する斜線で示
される2個の埋込材x4、x5部分と、埋込材x5の左
右に位置する4個の埋込材x6〜x9部分を配管P1、
P2、P3が通過する。従って、コンクリートスラブ用
基板A2 の製造に際しては、斜線で示す5個の埋込材x
5〜x9の部分については中実の埋込材1uを配置固定
し、配管用ボックスV1が取り付けられる部分(x4部
分)には必要に応じて配管用ボックスV1 の形状に合わ
せて切削した形の埋込材1uを配置する。その他の部分
には例えば図6、図7に示したような標準化された中空
部を持つ埋込材1・・を配置固定する。
In the concrete slab substrate A 2 , as shown in the drawing, two embedding materials x4 and x5 shown in the third row from the right and shaded, and the embedding material x5 are located on the left and right sides. The four embedding materials x6 to x9 are connected to the pipe P1,
P2 and P3 pass. Therefore, when manufacturing the substrate A 2 for concrete slab, five embedding materials x indicated by diagonal lines are used.
The solid embedding material 1u was arranged and fixed in the portions 5 to x9, and the portion (x4 portion) to which the piping box V 1 was attached was cut according to the shape of the piping box V 1 if necessary. The embedding material 1u having a shape is arranged. The embedding material 1 having a standardized hollow portion as shown in FIGS. 6 and 7, for example, is arranged and fixed to the other portions.

【0020】コンクリートスラブ用基板A3 部分には、
図示されるように、配管が敷設される予定はない。従っ
て、コンクリートスラブ用基板A3 については、従来の
場合と同様、コンクリート基板の全面にわたって標準化
された中空部を持つ埋込材1・・を配置固定する。コン
クリートスラブ用基板A4 においては、図示されるよう
に、右から4列目の上から2個の斜線で示す埋込材x1
0、x11部分のみを配管P4が通過し、コンクリート
スラブ用基板A5 においては、右から3列目の最下位の
埋込材x12と右から2列目の中間の斜線で示す2個の
埋込材x13、x14部分のみを配管P4が通過する。
従って、コンクリートスラブ用基板A4 においては、埋
込材x10の部分には中実の埋込材1uを配置固定し、
またコンクリートスラブA5においては、埋込材x1
2、x14の部分には中実の埋込材1uを配置固定す
る。また、埋込材x11部分と埋込材x13部分には、
必要に応じて、配管用ボックスV4 及び配管用ボックス
5 の形状に合わせて切削した形の埋込材1uを配置す
る。そして、その他の部分には例えば図6、図7に示し
たような標準化された中空部を持つ埋込材1・・を配置
固定する。
In the concrete slab substrate A 3 part,
As shown, there are no plans to lay the plumbing. Therefore, as for the concrete slab substrate A 3 , the embedding material 1 having a standardized hollow portion is arranged and fixed over the entire surface of the concrete substrate, as in the conventional case. In the concrete slab substrate A 4 , as shown in the figure, an embedding material x1 indicated by two diagonal lines from the top in the fourth row from the right.
In the concrete slab substrate A 5 , the lowest embedding material x12 in the third column from the right and the two embeddings indicated by the diagonal lines in the middle from the right in the second row from the right in the concrete slab substrate A5. The pipe P4 passes only through the inserts x13 and x14.
Therefore, in the concrete slab substrate A 4 , the solid embedding material 1u is arranged and fixed in the embedding material x10 portion,
For concrete slab A 5 , embedding material x1
A solid embedding material 1u is arranged and fixed in the portions 2 and x14. In addition, the embedding material x11 portion and the embedding material x13 portion,
If necessary, place the implant member 1u form that was cut according to the shape of the piping boxes V 4 and piping box V 5. Then, the embedding materials 1 ... Having a standardized hollow portion as shown in FIGS. 6 and 7, for example, are arranged and fixed to the other portions.

【0021】なお、上記のコンクリートスラブ用基板A
1 〜A5 は、特定箇所に中実の埋込材1uを配置、固定
することを除いて、例えば特公昭57−47008号公
報等に開示される従来のコンクリートスラブ用基板の場
合と同様にして製造される。コンクリートスラブの施工
に際しては、各住戸あるいは各フロアーでのコンクリー
トスラブにおける配管設計状況に対応して上記のように
工場で製造された複数種類のコンクリートスラブ用基板
(A1 〜A5 )が、一括して構築物の施工現場に持ち込
まれる。施工現場では、形状の異なる各コンクリートス
ラブ用基板を設計図に従い躯体の梁B、B間に配置した
後、中実の埋込材1uに配管に必要な通路(この例では
凹溝U)を形成し、該凹溝U内を通過させながら所定の
配管P1〜P4の配設作業を行う。以下、従来工法と同
様にスラブ上端筋等の配筋を行い、現場打ちコンクリー
トを打設することによりコンクリートスラブの施工は終
了する。
The above-mentioned substrate A for concrete slab
1 to A 5 are the same as in the case of the conventional concrete slab substrate disclosed in, for example, Japanese Patent Publication No. 57-47008, except that the solid embedding material 1u is arranged and fixed at a specific position. Manufactured. When constructing concrete slabs, multiple types of concrete slab substrates (A 1 to A 5 ) manufactured at the factory as described above are batch-processed in accordance with the piping design situation in the concrete slab in each dwelling unit or each floor. Then it is brought to the construction site of the structure. At the construction site, after placing the boards for concrete slabs of different shapes between the beams B and B of the frame according to the design drawing, a passage (recessed groove U in this example) necessary for piping is provided in the solid embedding material 1u. The pipes are formed and the predetermined pipes P1 to P4 are arranged while passing through the recess U. The construction of the concrete slab is completed by arranging the upper slab reinforcements and the like in the same manner as in the conventional method, and then pouring in-place concrete.

【0022】図2は、上記した本発明によるコンクリー
トスラブ用基板Aの一例を示す斜視図であり、この例に
おいては、配管用ボックスVが取り付けられる位置には
配管用ボックスVの形状に合わせて切削した形の埋込材
1uが配置され、また、配管が予定される部分にも中実
の埋込材1u(図で、2点鎖線で示される)が配置さ
る。そして、残りの埋込材は中空部を持つ埋込材1が配
置されている。なお、この態様のコンクリートスラブ用
基板は配管を要しない部分に中空部を持つ埋込材を用い
てだけ軽量化することができ、好ましい態様である。
FIG. 2 is a perspective view showing an example of the concrete slab substrate A according to the present invention described above. In this example, the position where the piping box V is attached corresponds to the shape of the piping box V. The embedding material 1u in a cut form is arranged, and the solid embedding material 1u (indicated by a chain double-dashed line in the figure) is arranged also in a portion where piping is planned. Then, the remaining embedding material is the embedding material 1 having a hollow portion. The concrete slab substrate of this aspect is a preferable aspect because it can be made lighter only by using an embedding material having a hollow portion in a portion not requiring piping.

【0023】図3は、コンクリートスラブの施工時に、
躯体上に敷設されたこのような構造を持つコンクリート
スラブ用基板に作業者が配管用の凹溝Uを形成した状態
であり、配管の状況に応じて、1つの凹溝U、2つの凹
溝U、あるいは2本の配管分の幅を持つ凹溝U2 のよう
に種々の形の凹溝が形成される。凹溝Uは好ましくは配
管の管径程度の深さとされる。さらに、複数本の配管が
交叉して配置されることが予定される場合には、交叉可
能な深さを持つ凹溝を形成することにより、配管後にす
べての埋込材の上面をほぼ面一とすることができる。図
4は配管後の状態を示す図であり、凹溝U2 には2本の
配管が平行状態で通してある。
FIG. 3 shows that when the concrete slab is constructed,
It is a state in which an operator has formed a concave groove U for piping on a concrete slab substrate having such a structure laid on the frame, and one concave groove U and two concave grooves U are formed depending on the situation of the pipe. Various types of concave grooves are formed such as U or a concave groove U 2 having a width of two pipes. The concave groove U preferably has a depth of about the pipe diameter of the pipe. Further, when a plurality of pipes are planned to be arranged in an intersecting manner, by forming a groove having a depth capable of intersecting, the upper surfaces of all the embedding materials are made substantially flush with each other after the piping. Can be FIG. 4 is a view showing a state after piping, in which two pipes are passed in parallel in the concave groove U 2 .

【0024】特に図示しないが、コンクリート基板上に
配置する埋込材を全て中実の埋込材により構成する場合
であっても、本発明の初期の目的が達成可能であること
は理解されよう。この態様のコンクリートスラブ用基板
を用いる場合に、コンクリートスラブの軽量化は幾分阻
害されるが、埋込材に配管用の凹溝あるいは通路を形成
する自由度がより大きくなることから、施工現場で配管
状況を変更する必要が予想される場合などに柔軟に対応
することが可能となる。
Although not particularly shown, it will be understood that the initial object of the present invention can be achieved even when the embedding material to be placed on the concrete substrate is composed entirely of solid embedding material. . When the concrete slab substrate of this aspect is used, the weight reduction of the concrete slab is hindered to some extent, but since the degree of freedom for forming the recessed groove or passage for piping in the embedding material is increased, the construction site It is possible to flexibly cope with the case where it is expected that the piping situation needs to be changed.

【0025】以上の説明から分かるように、本発明によ
れば、従来は埋込材と埋込材との間に形成される現場打
ちコンクリート充填用空間部に配置せざるを得なかった
設備用配管の敷設を、本発明によるコンクリートスラブ
用基板を用いることにより、埋込材1uの上面を通して
短い配管距離で行うことが可能となる。また、現場で埋
込材に必要な配管用通路(凹溝等)を形成しながら配管
作業を行うにもかかわらず、現場で加工を受けるのは中
実の埋込材であるために、埋込材の破損は最小に保たれ
る。また、配管が予定される場所以外の埋込材を中空部
を持つ埋込材とする場合には、コンクリートスラブの空
隙率の低下を最小限とすることができ、コンクリートス
ラブの軽量化も十分に達成されるとともに、さらに、埋
込材の軽量化及び材料節減の目的も達成できる。また、
配管そのものが空隙形成材としての機能を果すことか
ら、凹溝が形成されているにもかかわらずコンクリート
スラブの中空率は十分平均化される。
As can be seen from the above description, according to the present invention, it is necessary for the equipment to be placed in the space for filling the cast-in-place concrete which is conventionally formed between the potting materials. By using the concrete slab substrate according to the present invention, it is possible to lay the pipe through the upper surface of the embedding material 1u with a short piping distance. In addition, even though the piping work is performed while forming the piping passages (concave grooves, etc.) necessary for the embedding material on-site, it is the solid embedding material that is processed on-site. Damage to the inserts is kept to a minimum. In addition, when the embedding material other than the place where piping is planned is an embedding material with a hollow part, the decrease in the porosity of the concrete slab can be minimized, and the weight reduction of the concrete slab is also sufficient. In addition to the above, the purpose of reducing the weight of the embedding material and saving the material can be achieved. Also,
Since the pipe itself functions as a void forming material, the hollow ratio of the concrete slab is sufficiently averaged even though the groove is formed.

【0026】配置される標準材としての埋込材1・・の
形状は任意であり、特に、中空部をもつ埋込材を用いる
場合には、コンクリート基板の養生時に発生する蒸気を
中空部Sから抜くための開口を形成した埋込材(特開平
5−208410号公報参照)等も有効に用いうる。さ
らに、埋込材のコンクリート基板への取り付けも、従来
のコンクリートが未硬化の状態で係止具により取り付け
るものに限らす、コンクリートが未硬化の状態でウレタ
ン系接着剤のような反応型の接着剤等を用いて接着固定
する方法、あるいは、コンクリートの硬化後にコンクリ
ート釘等の係止具や、接着剤、接着テープ等を用いて固
着する方法(特開平5−208411号公報参照)等も
用いることができる。
The shape of the embedding material 1 ... As a standard material to be arranged is arbitrary. In particular, when an embedding material having a hollow portion is used, the steam generated during curing of the concrete substrate is used for the hollow portion S. An embedding material (see Japanese Patent Laid-Open No. 5-208410) having an opening for pulling it out can also be effectively used. Furthermore, the mounting of the embedding material on the concrete substrate is also limited to the one that is attached by the locking tool in the state where the conventional concrete is uncured. In the state where the concrete is uncured, a reactive adhesive such as urethane adhesive is used. A method of adhering and fixing with an agent or the like, or a method of adhering with a fastener such as a concrete nail after hardening of concrete, an adhesive, an adhesive tape or the like (see Japanese Patent Laid-Open No. 5-208411) be able to.

【0027】[0027]

【発明の効果】上記の記載から明らかなように、本発明
によるコンクリートスラブ用基板を用いることにより、
コンクリートスラブ構築時の配管作業が容易となり、か
つ、その配管距離も短縮することができる。また、コン
クリートスラブとしても高い空隙率を維持することがで
きる。
As is apparent from the above description, by using the concrete slab substrate according to the present invention,
Piping work when constructing a concrete slab becomes easy and the piping distance can be shortened. In addition, a high porosity can be maintained even as a concrete slab.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明によるコンクリートスラブ用基板を用い
て施工されるコンクリートスラブを説明する図。
FIG. 1 is a diagram illustrating a concrete slab constructed using a concrete slab substrate according to the present invention.

【図2】本発明によるコンクリートスラブ用基板の一例
を示す斜視図。
FIG. 2 is a perspective view showing an example of a concrete slab substrate according to the present invention.

【図3】図2のコンクリートスラブ用基板に配管用凹溝
を加工した状態を示す斜視図。
FIG. 3 is a perspective view showing a state where a groove for piping is processed on the substrate for concrete slab of FIG.

【図4】図2のコンクリートスラブ用基板に配管を行っ
た状態を示す斜視図。
FIG. 4 is a perspective view showing a state where piping is performed on the concrete slab substrate of FIG.

【図5】従来のコンクリートスラブ用基板を示す鳥瞰
図。
FIG. 5 is a bird's-eye view showing a conventional concrete slab substrate.

【図6】従来のコンクリートスラブ用基板を用いてのコ
ンクリートスラブ及び構築物の一例を示す図。
FIG. 6 is a view showing an example of a concrete slab and a structure using a conventional substrate for concrete slab.

【図7】埋込材の一例を示す図。FIG. 7 is a diagram showing an example of an embedding material.

【図8】埋込材の一例を示す図。FIG. 8 is a diagram showing an example of an embedding material.

【図9】従来のコンクリートスラブ用基板を用いての配
管状態を説明する図。
FIG. 9 is a diagram illustrating a piping state using a conventional concrete slab substrate.

【符合の説明】[Description of sign]

A…コンクリートスラブ用基板、P…配管、V…配管用
ボックス、1…標準的な埋込材、1u…中実の埋込材、
u…凹溝、3…コンクリート基板
A ... Concrete slab substrate, P ... Piping, V ... Piping box, 1 ... Standard embedding material, 1u ... Solid embedding material,
u ... concave groove, 3 ... concrete substrate

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 コンクリート基板上に合成樹脂発泡成形
品からなる中実の埋込材が所定の間隔で配置されてなる
コンクリートスラブ用基板。
1. A substrate for a concrete slab, in which solid embedding materials made of a synthetic resin foam-molded product are arranged on a concrete substrate at predetermined intervals.
【請求項2】 コンクリート基板上に合成樹脂発泡成形
品からなる埋込材が所定の間隔で配置されてなるコンク
リートスラブ用基板であって、該コンクリートスラブ用
基板を用いてのコンクリートスラブの構築時に配管の敷
設が予定される箇所の埋込材は中実のものとされ、他の
埋込材は中空部を持つもとされることを特徴とするコン
クリートスラブ用基板。
2. A concrete slab substrate in which an embedding material made of a synthetic resin foam-molded product is arranged at a predetermined interval on a concrete substrate, which is used when constructing a concrete slab using the concrete slab substrate. Substrates for concrete slabs, characterized in that the embedding material at the place where the pipe is to be laid is solid, and the other embedding material is said to have a hollow portion.
【請求項3】 コンクリートスラブの基板として、請求
項1又は2に記載のコンクリートスラブ用基板を必要に
応じて敷設し、該コンクリートスラブ用基板の中実であ
る埋込材に配管部材を通過させるための通路を形成し、
該通路内を通過させて必要な配管作業を行い、しかる
後、その上から現場打ちコンクリートを打設することを
特徴とするコンクリートスラブの施工方法。
3. A concrete slab substrate, wherein the concrete slab substrate according to claim 1 or 2 is laid as required, and a pipe member is passed through a solid embedding material of the concrete slab substrate. To form a passage for
A method for constructing a concrete slab, which comprises passing the inside of the passage to perform a necessary piping work, and then pouring a cast-in-place concrete on the pipe.
【請求項4】 コンクリートスラブの基板として請求項
1又は2に記載のコンクリートスラブ用基板を持つ構築
物。
4. A structure having the concrete slab substrate according to claim 1 or 2 as a concrete slab substrate.
JP12768995A 1995-05-26 1995-05-26 Concrete slab substrate having solid embedded material, construction method of concrete slab using the substrate, and its structure Expired - Fee Related JP3346948B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12768995A JP3346948B2 (en) 1995-05-26 1995-05-26 Concrete slab substrate having solid embedded material, construction method of concrete slab using the substrate, and its structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12768995A JP3346948B2 (en) 1995-05-26 1995-05-26 Concrete slab substrate having solid embedded material, construction method of concrete slab using the substrate, and its structure

Publications (2)

Publication Number Publication Date
JPH08319689A true JPH08319689A (en) 1996-12-03
JP3346948B2 JP3346948B2 (en) 2002-11-18

Family

ID=14966277

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12768995A Expired - Fee Related JP3346948B2 (en) 1995-05-26 1995-05-26 Concrete slab substrate having solid embedded material, construction method of concrete slab using the substrate, and its structure

Country Status (1)

Country Link
JP (1) JP3346948B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1296580C (en) * 2003-09-15 2007-01-24 邱则有 Component of light stuffing mould for concrete poured-in-situ
CN100458047C (en) * 2003-09-15 2009-02-04 邱则有 Component of moulding bed in lightweight in use for pouring concrete in site

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1296580C (en) * 2003-09-15 2007-01-24 邱则有 Component of light stuffing mould for concrete poured-in-situ
CN100458047C (en) * 2003-09-15 2009-02-04 邱则有 Component of moulding bed in lightweight in use for pouring concrete in site

Also Published As

Publication number Publication date
JP3346948B2 (en) 2002-11-18

Similar Documents

Publication Publication Date Title
US5055252A (en) Method of constructing an integrated concrete wall structure
CN111424981A (en) Pre-embedding laying method for wires of fabricated building
JP3169818B2 (en) Substrate for concrete slab having concave grooves formed on the surface of some embedded materials, method of constructing concrete slab using the substrate, and its construction
JP3346948B2 (en) Concrete slab substrate having solid embedded material, construction method of concrete slab using the substrate, and its structure
US4250675A (en) Method for forming wiring channels in a concrete floor
JP3364051B2 (en) Substrate for concrete slab partially lacking embedding material, concrete slab construction method using the substrate, and its structure
JP3346947B2 (en) Substrate for concrete slab having embedded material with low height in part, construction method of concrete slab using the substrate, and its structure
JP3253487B2 (en) Substrate for concrete slab having embedded material partially open at the upper side, construction method of concrete slab using the substrate, and its structure
JP3253511B2 (en) Concrete slab substrate with pre-fixed piping, concrete slab construction method using the substrate, and its structure
JP3169801B2 (en) Concrete slab substrate having embedded material and concrete slab using the substrate
CN218117232U (en) Electric shaft preformed hole mould and equipotential connection integrated component
JP3071771B2 (en) How to build a void slab
CN216195868U (en) Line box embedded structure and coincide floor
JP3453322B2 (en) Embedded material for concrete slab and substrate for concrete slab having the embedded material
JP2698775B2 (en) How to build a void slab
JPH10245922A (en) Stepped floor execution method using perforated pc panel for composite floor
CA1070510A (en) Method for forming wiring channels in a concrete floor
CA1134638A (en) Method for forming wiring channels in a concrete floor
JP2928460B2 (en) Embedded material for concrete slab, substrate for concrete slab, and concrete slab using them
JP3364024B2 (en) Embedding material for concrete slab
JP2003096960A (en) Floor board block and floor slab using the same
JPH1084621A (en) Concrete box, supporting system and member
JP2002281639A (en) Embedding of wire conduit to sc structure, laying of electrical cable and unit metal plate thereof
JPH078676Y2 (en) Building floor structure
JPH0530122B2 (en)

Legal Events

Date Code Title Description
FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 6

Free format text: PAYMENT UNTIL: 20080906

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 7

Free format text: PAYMENT UNTIL: 20090906

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100906

Year of fee payment: 8

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100906

Year of fee payment: 8

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 9

Free format text: PAYMENT UNTIL: 20110906

LAPS Cancellation because of no payment of annual fees