JPH08290243A - Twin roll continuous casting method - Google Patents

Twin roll continuous casting method

Info

Publication number
JPH08290243A
JPH08290243A JP9378095A JP9378095A JPH08290243A JP H08290243 A JPH08290243 A JP H08290243A JP 9378095 A JP9378095 A JP 9378095A JP 9378095 A JP9378095 A JP 9378095A JP H08290243 A JPH08290243 A JP H08290243A
Authority
JP
Japan
Prior art keywords
casting
drum
speed
continuous casting
twin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP9378095A
Other languages
Japanese (ja)
Inventor
Akira Imamura
晃 今村
Masahiro Maeda
正浩 前田
Hideya Kuratani
秀也 藏谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Nippon Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Corp filed Critical Nippon Steel Corp
Priority to JP9378095A priority Critical patent/JPH08290243A/en
Publication of JPH08290243A publication Critical patent/JPH08290243A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Continuous Casting (AREA)

Abstract

PURPOSE: To make continuous casting feasible by casting while changing roll pushing force and casting speed based on the relationship between tundish molten steel temp. and roll pushing force/casting speed so as to maintain set casting thickness constant. CONSTITUTION: By detecting a rotating speed of cooling drums 1a, 1b with a speedometer 11 and controlling a rotating speed of the cooling drums 1a, 1b through a drive controller 10 so as to satisfy set condition, the pulling speed is controlled. Further, a molten metal surface S1, that is, arc angle is detected by a level meter 15, a sheet thickness by a gap meter 16, a drum cooling water inlet/outlet temp. difference is detected by a thermometer 12 and is converted to a heat transfer rate of roll by a computing element 13, also, a tundish temp. is detected by a molten metal thermometer 14. The roll pushing force control is executed so as to satisfy the set condition.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、双ドラム式連続鋳造機
を用いて薄板鋳片を製造する方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for producing a thin plate cast product using a twin-drum type continuous casting machine.

【0002】[0002]

【従来の技術】双ドラム式連続鋳造方法は鋳片板厚が所
定の厚みとなるように鋳造速度を制御し、必要に応じて
熱間圧延やインライン熱処理を実施する操業技術であ
る。このプロセスにおいて長時間安定な鋳造を行うに際
し重要なことは、精錬時間の変動や溶鋼温度バラツキ等
の操業条件変化に柔軟に対応すること、即ち、いかに鋳
造速度を任意に設定するかである。このような目的を達
成するため従来の鋳造技術では種々の対策を実施してい
るが、いずれも実効を上げるに至っていないのが実情で
ある。
2. Description of the Related Art The twin-drum type continuous casting method is an operating technique in which the casting speed is controlled so that the thickness of the slab becomes a predetermined thickness, and hot rolling or in-line heat treatment is carried out as necessary. What is important in carrying out stable casting for a long time in this process is to flexibly respond to changes in refining time and changes in operating conditions such as variations in molten steel temperature, that is, how to set the casting speed arbitrarily. In order to achieve such an object, various measures have been taken in the conventional casting technique, but in reality, none of them has been effective.

【0003】[0003]

【発明が解決しようとする課題】本発明は、上記に鑑み
なされたもので、薄板鋳片を製造するに当たり、ドラム
押し力の変更を行って鋳造速度を制御することを主眼と
する鋳造操業方法であって操業条件変化に柔軟に対応で
きる操業方法を提供するものである。なお、従来はこの
ようなドラム押し力制御による鋳造速度制御に関して
は、何らの提案もなされていなかった。
SUMMARY OF THE INVENTION The present invention has been made in view of the above circumstances, and in manufacturing a thin plate cast product, the casting operation method is mainly intended to change the drum pressing force to control the casting speed. In addition, it provides an operating method that can flexibly respond to changes in operating conditions. Incidentally, conventionally, no proposal has been made regarding the casting speed control by the drum pressing force control.

【0004】[0004]

【課題を解決するための手段】本発明の双ドラム式連続
鋳造方法は、連々鋳操業の際に、予め定めたタンディッ
シュ溶鋼温度とドラム押し力と鋳造速度の関係に基づき
ドラム押し力を変更し、当該チャージと次チャージのマ
ッチングに必要な鋳造速度となるように鋳造速度を遅く
することを可能とし、また、タンディッシュ溶鋼温度の
変化に応じて、予め定めたタンディッシュ溶鋼温度とド
ラム押し力と鋳造速度の関係に基づきタンディッシュ溶
鋼温度に見合ったドラム押し力を設定することにより、
鋳造速度の変化を小さく抑えることを可能とするもの
で、以下の4点を要旨とする。
In the twin-drum type continuous casting method of the present invention, the drum pushing force is changed on the basis of the relationship between the predetermined tundish molten steel temperature, the drum pushing force and the casting speed during the continuous casting operation. However, it is possible to slow down the casting speed so that the casting speed is the one required for matching the charge and the next charge, and according to the change in the tundish molten steel temperature, the tundish molten steel temperature and the drum pressing are set in advance. By setting the drum pushing force commensurate with the tundish molten steel temperature based on the relationship between force and casting speed,
It is possible to suppress the change in casting speed to a small level, and the following four points are the gist.

【0005】(1)鋳造幅w、鋳造厚dおよび鋳造速度
W(t/分)に基づいて引抜速度V(m/分)を(1)
式によって決定し、次いで一対の冷却ドラム間に形成さ
れる湯溜まりのなす弧角θ、冷却ドラム表面性状により
定まるドラムの熱伝達率Qおよびタンディッシュ溶鋼温
度Tsに基づき冷却ドラムが最も接近する点(ドラムキ
ス点)での中心固相率fsを(2)式によって決定し、
最後にドラム押し力Pを(3)式により決定して、これ
らの引抜速度V、中心固相率fsおよびドラム押し力P
の値を満足するように冷却ドラムの回転数および湯溜ま
り部への溶鋼供給量を設定し、設定した鋳造厚dを維持
しながら、連続鋳造操業を行う。
(1) Based on the casting width w, the casting thickness d, and the casting speed W (t / min), the drawing speed V (m / min) is set to (1).
The point at which the cooling drum is closest to each other based on the arc angle θ formed by the pool of water formed between the pair of cooling drums, the heat transfer coefficient Q of the drum determined by the surface properties of the cooling drum, and the tundish molten steel temperature Ts. The central solid fraction fs at (drum kiss point) is determined by the equation (2),
Finally, the drum pushing force P is determined by the equation (3), and the drawing speed V, the central solid fraction fs, and the drum pushing force P are determined.
The number of rotations of the cooling drum and the molten steel supply amount to the molten metal pool are set so as to satisfy the value of, and continuous casting operation is performed while maintaining the set casting thickness d.

【0006】(2)上記(1)に記載された双ドラム式
連続鋳造を行っている時に、同チャージ内かつ同キャス
ト内で鋳造速度Wを変更せずに、鋳造厚dのみを変更す
る場合に、変更後の鋳造厚dに基づいて、引抜速度Vを
(1)式によって決定し、次いで中心固相率fsおよび
ドラム押し力Pを(2)式および(3)式によって決定
して、これらの鋳造速度W、引抜速度V、中心固相率f
sおよびドラム押し力Pの値を満足するように、冷却ド
ラムの回転速度および湯溜まり部への溶鋼供給量を設定
して、変更後の鋳造厚dを維持しながら、連続鋳造操業
を行う。
(2) When the twin drum type continuous casting described in the above (1) is performed, only the casting thickness d is changed without changing the casting speed W in the same charge and in the same cast. Based on the changed casting thickness d, the drawing speed V is determined by the equation (1), and then the central solid fraction fs and the drum pushing force P are determined by the equations (2) and (3). These casting speed W, drawing speed V, central solid fraction f
The rotation speed of the cooling drum and the molten steel supply amount to the molten metal pool are set so as to satisfy the values of s and the drum pressing force P, and continuous casting operation is performed while maintaining the changed casting thickness d.

【0007】(3)上記(1)または(2)に記載され
た双ドラム式連続鋳造を行っている時に、同チャージ内
かつ同キャスト内で鋳造速度Wを変更する場合に、変更
後の鋳造速度Wに基づいて、引抜速度Vを(1)式によ
って決定し、次いで中心固相率fsおよびドラム押し力
Pを(2)式および(3)式によって決定して、これら
の鋳造速度W、引抜速度V、中心固相率fsおよびドラ
ム押し力Pの値を満足するように、冷却ドラムの回転速
度および湯溜まり部への溶鋼供給量を設定して、変更後
の鋳造速度Wを維持しながら、連続鋳造操業を行う。
(3) When the casting speed W is changed within the same charge and within the same cast during the twin drum type continuous casting described in the above (1) or (2), the changed casting Based on the speed W, the drawing speed V is determined by the equation (1), and then the central solid fraction fs and the drum pressing force P are determined by the equations (2) and (3) to determine the casting speed W, The rotation speed of the cooling drum and the amount of molten steel supplied to the molten metal pool are set so as to satisfy the values of the drawing speed V, the central solid fraction fs, and the drum pressing force P, and the changed casting speed W is maintained. While performing continuous casting operations.

【0008】(4)上記(2),(3),(4)のいず
れかに記載された双ドラム式連続鋳造を行っている時
に、決定したドラム押し力Pが設備能力を超える場合
に、鋳造速度Wを再設定し、(1),(2),(3)式
によって再度引抜速度V、中心固相率fsおよびドラム
押し力Pを決定し、ドラム押し力Pが設備能力範囲にあ
ってこれらの鋳造速度W、引抜速度V、中心固相率fs
およびドラム押し力Pの値を満足するように、冷却ドラ
ムの回転速度および湯溜まり部への溶鋼供給量を設定し
て、設定した鋳造厚dまたは鋳造速度Wを維持しなが
ら、連続鋳造操業を行う。
(4) When the twin drum type continuous casting described in any of (2), (3) and (4) above is performed and the determined drum pressing force P exceeds the facility capacity, The casting speed W is reset, and the drawing speed V, the central solid fraction fs, and the drum pushing force P are determined again by the equations (1), (2), and (3), and the drum pushing force P is within the equipment capacity range. Casting speed W, drawing speed V, central solid fraction fs
And the continuous casting operation is performed while setting the rotation speed of the cooling drum and the molten steel supply amount to the molten metal pool so as to satisfy the value of the drum pushing force P and maintaining the set casting thickness d or casting speed W. To do.

【0009】ここで、 V =(1000×W)/(d×w×γ) (1) fs=g(Q,Ts,θ,d)×10M (2) ただし、M=h(Q,Ts,θ,d)×Vで表される。 P =J(fs) (3) V :引抜速度(m/分) W :鋳造速度(t/
分) d :鋳造厚(mm) w :鋳造幅(mm) γ :鋳片の比重(t/m3 ) θ :弧角(度) fs:中心固相率(−) Ts:タンディッシュ
溶鋼温度(度) Q :ドラムの熱伝達係数(kcal/m2 /hr/℃) g,h,J,M:関数 P :ドラム押し力(t)
Here, V = (1000 × W) / (d × w × γ) (1) fs = g (Q, Ts, θ, d) × 10 M (2) where M = h (Q, It is represented by Ts, θ, d) × V. P = J (fs) (3) V: Drawing speed (m / min) W: Casting speed (t /
Min) d: Casting thickness (mm) w: Casting width (mm) γ: Specific gravity of slab (t / m 3 ) θ: Arc angle (degree) fs: Central solid fraction (-) Ts: Tundish molten steel temperature (Degree) Q: heat transfer coefficient of drum (kcal / m 2 / hr / ° C) g, h, J, M: function P: drum pressing force (t)

【0010】[0010]

【作用】本発明においては、双ドラム式連続鋳造方法に
おいて、鋳造厚と引抜速度とドラム押し力との相互関係
を設定し、この相互関係を満足させるように設定条件を
変更することによって、溶鋼供給量や供給タイミングが
ずれた場合あるいは鋳造厚を変更する場合も設定鋳造厚
を一定に維持しながら、連々鋳操業を円滑に実施でき、
連続鋳造の操業性、歩留りを向上することができる。
According to the present invention, in the twin-drum type continuous casting method, the relationship between the casting thickness, the drawing speed, and the drum pushing force is set, and the setting conditions are changed so as to satisfy the relationship. Even if the supply amount and supply timing are deviated or the casting thickness is changed, the casting operation can be smoothly performed continuously while maintaining the set casting thickness constant.
Operability and yield of continuous casting can be improved.

【0011】[0011]

【実施例】本発明においては、鋳造サイズおよび鋳造速
度が決められると次式により引抜速度が決定される。 V =(1000×W)/(d×w×γ) (1) V:引抜速度(m/分) W:鋳造速度(t/
分) d:鋳造厚(mm) w:鋳造幅(mm) γ:鋳片の比重(t/m3
EXAMPLES In the present invention, when the casting size and casting speed are determined, the drawing speed is determined by the following equation. V = (1000 × W) / (d × w × γ) (1) V: drawing speed (m / min) W: casting speed (t /
Min) d: casting thickness (mm) w: casting width (mm) γ: specific gravity of slab (t / m 3 )

【0012】また弧角θが設定されると中心固相率fs
は次式で設定される。 fs=g(Q,Ts,θ,d)×10M (2) ただし、M=h(Q,Ts,θ,d)×Vで表される。 fs:中心固相率(−) V :引抜速度(m/
分) θ :弧角(度) Ts:タンディッシュ溶
鋼温度(度) Q :ドラムの熱伝達率(kcal/m2 /hr/℃) g,h:θ,Q,Tsの関数 ここでgおよびhはドラムの冷却条件、鋳造板厚等で決
定される関数で、 g=a1 (θ,d)+a2 (θ,d)×Q+a3 (θ,d)×Ts h=b1 (θ,d)+b2 (θ,d)×Q+b3 (θ,d)×Ts と表される。係数は弧角θと板厚dによって変わるが、
1 は−105 〜0、a2 は0〜10、a3 は0.1〜
100の値、b1 は−100〜100、b2 は−10〜
10、b3 は−100〜100の値をとる。
When the arc angle θ is set, the central solid fraction fs
Is set by the following equation. fs = g (Q, Ts, θ, d) × 10 M (2) where M = h (Q, Ts, θ, d) × V. fs: central solid fraction (-) V: drawing speed (m /
Min) θ: Arc angle (degree) Ts: Tundish molten steel temperature (degree) Q: Heat transfer coefficient of drum (kcal / m 2 / hr / ° C) g, h: Function of θ, Q, Ts where g and h is a function determined by the drum cooling conditions, cast plate thickness, etc. g = a 1 (θ, d) + a 2 (θ, d) × Q + a 3 (θ, d) × Ts h = b 1 (θ , D) + b 2 (θ, d) × Q + b 3 (θ, d) × Ts. The coefficient changes depending on the arc angle θ and the plate thickness d,
a 1 is −10 5 to 0, a 2 is 0 to 10, and a 3 is 0.1.
A value of 100, b 1 is -100 to 100, and b 2 is -10.
10, b 3 takes a value of -100 to 100.

【0013】ドラム押し力Pは次式で表せる。 P=J(fs)=A×10N (4) ただし、N=B×fsで表される。ここで、Aは0.0
1〜100、Bは0.01〜10の値をとる。(4)式
より鋳造厚、引抜速度に対応するドラム押し力が求めら
れ、鋳造厚あるいは引抜速度の変化に連動してドラム押
し力の設定値を変更することが可能となる。
The drum pushing force P can be expressed by the following equation. P = J (fs) = A × 10 N (4) However, N = B × fs. Where A is 0.0
1-100 and B take the value of 0.01-10. The drum pushing force corresponding to the casting thickness and the drawing speed is obtained from the equation (4), and the set value of the drum pushing force can be changed in association with the change of the casting thickness or the drawing speed.

【0014】上記よりドラム押し力が設定変更される訳
であるが、中心固相率fsはドラム下での鋳片の復熱に
影響することから、当然適正な制御範囲を有する。この
範囲は鋳片強度により決定されるが、一般的にはfs=
0.2から0.8程度の範囲で設定される。
Although the setting of the drum pressing force is changed from the above, the central solid fraction fs affects the reheat of the slab under the drum, and thus has a proper control range. This range is determined by the slab strength, but generally fs =
It is set in the range of about 0.2 to 0.8.

【0015】従って、上記相互関係式より設定された中
心固相率が制御範囲を逸脱した値を示す場合は鋳造速度
を許容可能な範囲で再設定し、再度上記相互関係式に基
づき引抜速度および中心固相率を設定し中心固相率を制
御範囲に入れた上で操業を開始または継続しなければな
らない。
Therefore, when the central solid fraction set by the above relational expression shows a value outside the control range, the casting speed is reset within an allowable range, and the drawing speed and the drawing speed are again set based on the above relational expression. The central solid fraction should be set and the central solid fraction should be within the control range before starting or continuing the operation.

【0016】一例として、図2には引抜速度と中心固相
率との関係を、また図3には中心固相率とドラム押し力
の関係を示した。これらは、 鋳造量:W=1.5t/分 鋳造幅:w=1300mm ドラムの熱伝達率:Q=12,000kcal/m2 /hr/
℃ タンディッシュ溶鋼温度:Ts=1525℃,1510
℃,1495℃ 弧角 :θ=40° 板厚 :d=3mm 関数および係数: g=a1 +a2 ×Q+a3 ×Ts、h=b1 +b2 ×Q+b3 ×Ts a1 =−1307、a2 =2.8×10-3、a3 =0.
886、b1 =0.44、b2 =1.0×10-7、b3
=−3.0×10-4 P=J(fs)=A×10N ただし、N=B×fs、A=1.477、B=1.65
6 ドラム径:1200mm とした場合である。係数a1 〜a3 、b1 〜b3 、Aお
よびBは、予め実験、実績を通じて鋼種、操業条件毎に
求められており、これらの関係が前記(1)から(4)
式とともに、本発明を実施するための装置例を示す図1
における設定器8に設定されている。操業条件の設定お
よび変更に応じて演算器9で演算し、設定鋳造厚を一定
に維持するに必要な条件(鋳造厚、引抜速度、ドラム押
し力)の設定が行われる。
As an example, FIG. 2 shows the relationship between the drawing speed and the central solid fraction, and FIG. 3 shows the relationship between the central solid fraction and the drum pushing force. These are: casting amount: W = 1.5 t / min. Casting width: w = 1300 mm Drum heat transfer coefficient: Q = 12,000 kcal / m 2 / hr /
℃ Tundish molten steel temperature: Ts = 1525 ℃, 1510
° C, 1495 ° C Arc angle: θ = 40 ° Plate thickness: d = 3 mm Function and coefficient: g = a 1 + a 2 × Q + a 3 × Ts, h = b 1 + b 2 × Q + b 3 × Ts a 1 = −1307, a 2 = 2.8 × 10 −3 , a 3 = 0.
886, b 1 = 0.44, b 2 = 1.0 × 10 −7 , b 3
= −3.0 × 10 −4 P = J (fs) = A × 10 N However, N = B × fs, A = 1.477, B = 1.65
6 Drum diameter: 1200 mm. Coefficients a 1 ~a 3, b 1 ~b 3, A and B are preliminarily experiment, steels through experience, has been determined for each operating condition, these relationships from the (1) (4)
FIG. 1 shows an example apparatus for practicing the present invention with formulas
Is set in the setting device 8 in FIG. Calculation is performed by the calculator 9 according to the setting and change of the operating conditions, and the conditions (casting thickness, drawing speed, drum pushing force) necessary for maintaining the set casting thickness constant are set.

【0017】冷却ドラム1a,1bの回転速度は、速度
計11により検出され、上記設定条件を満足するよう
に、駆動制御装置10を介して冷却ドラム1a,1bの
回転速度の設定制御が行われ、引抜速度が制御される。
The rotation speeds of the cooling drums 1a and 1b are detected by the speedometer 11, and the rotation speeds of the cooling drums 1a and 1b are set and controlled by the drive control device 10 so as to satisfy the above setting conditions. , The withdrawal speed is controlled.

【0018】また湯面レベルS1即ち弧角θは、レベル
計15により、板厚はギャップ計16により、ドラムの
熱伝達率はドラム冷却水入り出温度差ΔTを温度計12
で検出し、これを演算器13で熱伝達率Qに変換し、ま
たタンディッシュ温度は溶鋼温度計14によりそれぞれ
検出され、上記設定条件を満足するように、ドラム押し
付けシリンダー17を介してドラム押し力制御が行われ
る。
The level S1 of the molten metal, that is, the arc angle θ is measured by the level meter 15, the plate thickness is measured by the gap meter 16, and the heat transfer coefficient of the drum is measured by the temperature difference ΔT between the drum cooling water and the thermometer 12.
And the tundish temperature is detected by the molten steel thermometer 14, respectively, and the drum pressing cylinder 17 presses the drum so as to satisfy the above set conditions. Force control is performed.

【0019】本発明では、このようにして溶鋼供給量、
供給タイミングがずれた場合も、同チャージ、同キャス
ト内で鋳造厚を変更する場合も、鋳造厚を一定にして、
連々鋳操業を開始あるいは継続できるようにしている。
In the present invention, the molten steel supply amount,
Even if the supply timing is deviated or the casting thickness is changed in the same charge or the same cast, the casting thickness is kept constant,
The casting operation can be started or continued one after another.

【0020】以下に、本発明を適用し、ドラム径120
0mmの双ドラム式連続鋳造装置を用いて、薄板の連続鋳
造を行った例について説明する。ここでは、鋳造条件と
してのドラムの熱伝達率Q=12,000kcal/m2
hr/℃、弧角θ=40°に対応して、引抜速度V(t/
分)と中心固相率fsおよび引抜速度V(m/分)との
関係式(2),(3)の関数g,hおよびA,Bを、 g=a1 +a2 ×Q+a3 ×Ts、h=b1 +b2 ×Q
+b3 ×Ts、 板厚3mmの時、 a1 =1307、a2 =2.8×10-3、a3 =0.8
86、b1 =0.44、b2 =1.0×10-7、b3
−3.0×10-4、 板厚4mmの時、 a1 =−2183、a2 =9.7×10-3、a3 =1.
450、b1 =0.61、b2 =9.1×10-7、b3
=−5.0×10-4、 板厚5mmの時、 a1 =−2193、a2 =8.4×10-3、a3 =1.
475、b1 =0.66、b2 =1.6×10-7、b3
=−5.0×10-4、 A=1.477、B=1.656 に設定している。この値は、操業実績から求められたも
のである。また、鋳片比重γは7.5t/m3 、中心固
相率の制御範囲は0.2から0.7に設定している。
The present invention is applied to the following, and the drum diameter 120
An example of continuously casting thin plates using a 0 mm twin-drum type continuous casting device will be described. Here, the heat transfer coefficient Q of the drum as the casting condition Q = 12,000 kcal / m 2 /
Corresponding to hr / ° C and arc angle θ = 40 °, pulling speed V (t /
Min) and the central solid fraction fs and the drawing speed V (m / min), the functions g, h and A and B of the relational expressions (2) and (3) are expressed by g = a 1 + a 2 × Q + a 3 × Ts , H = b 1 + b 2 × Q
+ B 3 × Ts, when the plate thickness is 3 mm, a 1 = 1307, a 2 = 2.8 × 10 −3 , a 3 = 0.8
86, b 1 = 0.44, b 2 = 1.0 × 10 −7 , b 3 =
When −3.0 × 10 −4 and plate thickness 4 mm, a 1 = −2183, a 2 = 9.7 × 10 −3 , a 3 = 1.
450, b 1 = 0.61, b 2 = 9.1 × 10 −7 , b 3
= −5.0 × 10 −4 , when the plate thickness is 5 mm, a 1 = −2193, a 2 = 8.4 × 10 −3 , a 3 = 1.
475, b 1 = 0.66, b 2 = 1.6 × 10 −7 , b 3
= −5.0 × 10 −4 , A = 1.477, B = 1.656. This value is obtained from the operation results. Further, the slab specific gravity γ is set to 7.5 t / m 3 , and the central solid fraction control range is set to 0.2 to 0.7.

【0021】(実施例1)1チャージ目の溶鋼量は60
tで精錬炉より40分間隔で、鋳造幅0.86m、鋳造
厚3mmの鋳片の連々鋳操業が計画された。この時、鋳造
速度は1.5t/分であるので、引抜速度は(1)式よ
り77.5m/分となる。弧角は40°に設定した。タ
ンディッシュ溶鋼温度は1495℃と低めであった。
(Example 1) The amount of molten steel at the first charge is 60
A continuous casting operation of a cast piece having a casting width of 0.86 m and a casting thickness of 3 mm was planned at an interval of 40 minutes from the refining furnace at t. At this time, since the casting speed is 1.5 t / min, the drawing speed is 77.5 m / min from the equation (1). The arc angle was set to 40 °. The temperature of the molten steel in the tundish was as low as 1495 ° C.

【0022】連々鋳の2チャージ目を30t鋳造したと
ころで、精錬炉の都合から3チャージ目の溶鋼到着時刻
が5分遅れることになり、直ちに時間調整に入った。残
り30tの溶鋼を1.5t/分、20分で鋳造する予定
を25分かけて鋳造する必要がある。このため鋳造速度
を1.2t/分にすべく引抜速度を62.0m/分に変
更、同時に鋳造厚が変化しないように(2)式から求め
た中心固相率0.67となるように、(4)式からドラ
ム押し力を求め19tに設定変更した。なお、3チャー
ジ目鋳造開始後は40分後の4チャージ目鍋到着に備え
るべく、再び引抜速度を77.5m/分、ドラム押し力
を4.5tに戻した。
When the second charge of continuous casting was cast for 30 tons, the arrival time of molten steel for the third charge was delayed by 5 minutes due to the circumstances of the refining furnace, and the time adjustment was immediately started. It is necessary to cast the remaining 30 t of molten steel at 1.5 t / min for 20 minutes, which is to be cast for 20 minutes. For this reason, the drawing speed was changed to 62.0 m / min in order to set the casting speed to 1.2 t / min, and at the same time, the central solid fraction was determined to be 0.67 so as not to change the casting thickness by the formula (2). , Drum pushing force was calculated from the equation (4) and the setting was changed to 19t. After the start of the third charge casting, the withdrawal speed was returned to 77.5 m / min and the drum pushing force was returned to 4.5 t to prepare for the arrival of the fourth charge pot 40 minutes later.

【0023】このようにして、溶鋼到着が3チャージ目
で5分遅れたにもかかわらず、引抜速度とドラム押し力
の設定変更を行うことにより、当初の設定鋳造厚3mmを
変更することなく、予定の鋳造時間内に、4チャージの
連々鋳操業で薄板を鋳造することができた。
In this way, even though the arrival of molten steel was delayed by 5 minutes at the third charge, by changing the setting of the drawing speed and the pushing force of the drum, the initial set casting thickness of 3 mm was not changed, It was possible to cast a thin plate in a continuous casting operation of 4 charges within the scheduled casting time.

【0024】(実施例2)1チャージ目の溶鋼量は60
tで、精錬炉より50分間隔で供給を受け、鋳造幅0.
8mの鋳片鋳造の連々鋳操業が計画された。この時、鋳
造速度は1.2t/分、最初の鋳造厚は4mmであったの
で(1)式から引抜速度は50.2m/分、ドラム押し
力は(4)式から4.6tに設定し、鋳造を開始した。
(Example 2) The amount of molten steel at the first charge is 60
At the same time, the casting width is 0.
Successive casting operations for casting 8 m slabs were planned. At this time, since the casting speed was 1.2 t / min and the initial casting thickness was 4 mm, the drawing speed was set to 50.2 m / min from the formula (1) and the drum pushing force was set to 4.6 t from the formula (4). And then started casting.

【0025】連々鋳の2チャージ目の30tの鋳造を終
えたところで鋳造厚を4mmから3mmに変更することによ
っていたため、厚み変更に入った。連々鋳における精錬
炉からの次チャージ溶鋼供給時間に当該チャージの鋳造
終了タイミングを合わせるため、同じ1.2t/分を維
持する必要がある。このため、(1)式から計算し、引
抜速度を66.7m/分に、ドラム押し力は(4)式よ
り10.7tに同時に変更し、鋳造を継続した。
Since the casting thickness had to be changed from 4 mm to 3 mm when 30 t of the second charge of the continuous casting had been completed, the thickness was changed. It is necessary to maintain the same 1.2 t / min in order to match the casting end timing of the next charge with the molten steel supply time from the refining furnace in continuous casting. Therefore, the drawing speed was calculated to be 66.7 m / min, and the drum pushing force was changed to 10.7 t from the expression (4) at the same time, which was calculated from the expression (1), and the casting was continued.

【0026】次に、連々鋳3チャージ目にチャージスタ
ートから鋳造厚を3mmから5mmに変更することになって
いたため、2回目の厚み変更に入った。3チャージ目の
タンディッシュ溶鋼温度は1525℃と高めとなってい
る。鋳造速度1.2t/分を維持すべく(1)式から引
抜速度を40.0m/分、(4)式よりドラム押し力は
1.93tとなり、この時(2)式より中心固相率は
0.07となった。
Next, since the casting thickness was to be changed from 3 mm to 5 mm from the charge start at the third charge of casting, the second thickness change was started. The molten steel temperature at the 3rd charge is as high as 1525 ° C. In order to maintain the casting speed of 1.2 t / min, the drawing speed is 40.0 m / min from the formula (1), and the drum pushing force is 1.93 t from the formula (4). At this time, the central solid fraction is calculated from the formula (2). Was 0.07.

【0027】この中心固相率は0.2から0.8の範囲
を外れているため採用することができない。このため精
錬炉からの溶鋼供給間隔を50分から60分に延ばすこ
ととし、鋳造速度を1.0t/分とし、(1)式より引
抜速度を求め33.3m/分、この時(2)式から再度
中心固相率を求め、0.29となった。
This central solid fraction cannot be adopted because it is outside the range of 0.2 to 0.8. Therefore, the molten steel supply interval from the refining furnace was extended from 50 minutes to 60 minutes, the casting speed was 1.0 t / min, and the drawing speed was calculated from equation (1) to 33.3 m / min. The central solid fraction was again determined from the above to be 0.29.

【0028】この中心固相率は制御範囲に入っているた
め今回の計算操業条件を採用、引抜速度33.3m/
分、ドラム押し力4.46t、この時の中心固相率0.
29で連々鋳操業を継続し、精錬炉も連絡し、溶鋼供給
間隔を60分に延ばす処置をとった。
Since the central solid fraction falls within the control range, the calculation operating conditions of this time are adopted, and the drawing speed is 33.3 m /
Min, drum pressing force 4.46 t, central solid fraction at this time 0.
At 29, the casting operation was continued, the refining furnace was also contacted, and the molten steel supply interval was extended to 60 minutes.

【0029】このようにして、途中で鋳造厚を変更した
場合にも、精錬炉からの溶鋼供給タイミングとチャージ
毎の鋳造終了タイミングとを調整しながら連々鋳操業を
実現することができた。
In this way, even when the casting thickness was changed in the middle, the continuous casting operation could be realized while adjusting the molten steel supply timing from the refining furnace and the casting end timing for each charge.

【0030】[0030]

【発明の効果】本発明により、双ドラム式薄板連続鋳造
法において、操業途中の条件変更、例えば溶鋼の供給
量、供給タイミングあるいは、同チャージ、同キャスト
内の鋳造厚の変更等がある場合にも、設定鋳造厚(サイ
ズ)を一定に維持して連々鋳操業の実現が可能となり、
操業性、歩留りを大幅に向上することができる。
EFFECTS OF THE INVENTION According to the present invention, in the twin drum type thin plate continuous casting method, when the conditions are changed during the operation, for example, the supply amount of molten steel, the supply timing, the charge, the casting thickness in the cast, etc. are changed. In addition, the set casting thickness (size) can be maintained constant and continuous casting operations can be realized.
Operability and yield can be greatly improved.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明を採用する双ドラム式薄板連続鋳造方法
を実施する装置例を示す一部切り欠き正面説明図。
FIG. 1 is a partially cutaway front view showing an example of an apparatus for carrying out a twin drum type thin plate continuous casting method adopting the present invention.

【図2】双ドラム式薄板連続鋳造方法での鋳造速度と中
心固相率の関係を示す説明図。
FIG. 2 is an explanatory view showing a relationship between a casting rate and a central solid fraction in a twin-drum type thin plate continuous casting method.

【図3】双ドラム式薄板連続鋳造方法での中心固相率と
ドラム押し力の関係を示す説明図。
FIG. 3 is an explanatory diagram showing a relationship between a central solid fraction and a drum pushing force in a twin drum type thin plate continuous casting method.

【符号の説明】[Explanation of symbols]

1a,1b 冷却ドラム 2a,2b サイド堰 3 湯溜まり部 4 タンディッシュ 5 ストッパー 6 ノズル 7 鋳片 8 設定器 9 演算器 10 駆動制御装置 11 速度計 12 冷却水温度計 13 熱伝達率演算器 14 溶鋼温度計 15 湯面レベル計 16 ドラムギャップ計 17 ドラム押し付けシリンダー S 溶鋼 S1 溶鋼湯面 1a, 1b Cooling drum 2a, 2b Side weir 3 Hot water pool 4 Tundish 5 Stopper 6 Nozzle 7 Cast slab 8 Setting device 9 Calculator 10 Drive controller 11 Speedometer 12 Cooling water thermometer 13 Heat transfer coefficient calculator 14 Molten steel Thermometer 15 Level gauge 16 Drum gap meter 17 Drum pressing cylinder S Molten steel S1 Molten steel level

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 双ドラム式連続鋳造機を用いて薄板鋳片
を製造するに当たり、予め定めたタンディッシュ溶鋼温
度とドラム押し力と鋳造速度の関係に基づき、ドラム押
し力および鋳造速度の変更を行って鋳造操業を行うこと
を特徴とする双ドラム式連続鋳造方法。
1. When manufacturing a thin plate slab using a twin-drum type continuous casting machine, the drum pressing force and the casting speed are changed based on a predetermined relationship between the tundish molten steel temperature, the drum pressing force and the casting speed. A twin-drum type continuous casting method characterized in that the casting operation is carried out.
【請求項2】 双ドラム式連続鋳造を行うに際し、製造
する鋳造幅w、鋳造厚dおよび鋳造速度W(t/分)に
基づいて引抜速度V(m/分)を(1)式により決定
し、次いで一対の冷却ドラム間に形成される湯溜まりの
なす弧角θ、冷却ドラム表面性状により定まるドラムの
熱伝達率Qおよびタンディッシュ溶鋼温度Tsに基づき
冷却ドラムが最も接近する点(ドラムキス点)での中心
固相率fsを(2)式により決定し、最後にドラム押し
力Pを(3)式により決定して、これらの引抜速度V、
中心固相率fsおよびドラム押し力Pの値を満足するよ
うに冷却ドラムの回転数および湯溜まり部への溶鋼供給
量を設定し、連続鋳造操業を行うことを特徴とする請求
項1記載の双ドラム式連続鋳造方法。ここで、 V =(1000×W)/(d×w×γ) (1) fs=g(Q,Ts,θ,d)×10M (2) ただし、M=h(Q,Ts,θ,d)×Vで表される。 P =J(fs) (3) V :引抜速度(m/分) W :鋳造速度(t/
分) d :鋳造厚(mm) w :鋳造幅(mm) γ :鋳片の比重(t/m3 ) θ :弧角(度) fs:中心固相率(−) Ts:タンディッシュ
溶鋼温度(度) Q :ドラムの熱伝達係数(kcal/m2 /hr/℃) g,h,J,M:関数 P :ドラム押し力(t)
2. When performing twin-drum type continuous casting, the drawing speed V (m / min) is determined by the formula (1) based on the casting width w, the casting thickness d and the casting speed W (t / min) to be produced. Then, based on the arc angle θ formed by the pool of water formed between the pair of cooling drums, the heat transfer coefficient Q of the drum determined by the surface properties of the cooling drum, and the tundish molten steel temperature Ts, the point where the cooling drum comes closest (drum kiss point). ), The central solid fraction fs is determined by the equation (2), and finally the drum pressing force P is determined by the equation (3).
2. The continuous casting operation according to claim 1, wherein the number of revolutions of the cooling drum and the amount of molten steel supplied to the molten metal pool are set so as to satisfy the values of the central solid fraction fs and the drum pressing force P. Twin drum type continuous casting method. Here, V = (1000 × W) / (d × w × γ) (1) fs = g (Q, Ts, θ, d) × 10 M (2) where M = h (Q, Ts, θ , D) × V. P = J (fs) (3) V: Drawing speed (m / min) W: Casting speed (t /
Min) d: Casting thickness (mm) w: Casting width (mm) γ: Specific gravity of slab (t / m 3 ) θ: Arc angle (degree) fs: Central solid fraction (-) Ts: Tundish molten steel temperature (Degree) Q: heat transfer coefficient of drum (kcal / m 2 / hr / ° C) g, h, J, M: function P: drum pressing force (t)
【請求項3】 請求項2に記載された双ドラム式連続鋳
造を行っている時に、同チャージ内かつ同キャスト内で
鋳造速度Wを変更せずに、鋳造厚dのみを変更する場合
に、変更後の鋳造厚dに基づいて、引抜速度Vを(1)
式によって決定し、次いで中心固相率fsおよびドラム
押し力Pを(2)式および(3)式によって決定して、
これらの鋳造速度W、引抜速度V、中心固相率fsおよ
びドラム押し力Pの値を満足するように、冷却ドラムの
回転速度および湯溜まり部への溶鋼供給量を設定して、
変更後の鋳造厚dを維持しながら、連続鋳造操業を行う
ことを特徴とする双ドラム式連続鋳造方法。 V =(1000×W)/(d×w×γ) (1) fs=g(Q,Ts,θ,d)×10M (2) ただし、M=h(Q,Ts,θ,d)×Vで表される。 P =J(fs) (3)
3. When performing twin-drum type continuous casting according to claim 2, when changing only the casting thickness d without changing the casting speed W within the same charge and within the same cast, Based on the changed casting thickness d, the drawing speed V is (1)
Then, the central solid fraction fs and the drum pressing force P are determined by the equations (2) and (3),
The rotation speed of the cooling drum and the amount of molten steel supplied to the molten metal pool are set so that the values of the casting speed W, the drawing speed V, the central solid fraction fs, and the drum pressing force P are satisfied.
A twin-drum type continuous casting method, characterized in that continuous casting operation is performed while maintaining the changed casting thickness d. V = (1000 × W) / (d × w × γ) (1) fs = g (Q, Ts, θ, d) × 10 M (2) where M = h (Q, Ts, θ, d) It is represented by × V. P = J (fs) (3)
【請求項4】 請求項2または3に記載された双ドラム
式連続鋳造を行っている時に、同チャージ内かつ同キャ
スト内で鋳造速度Wを変更する場合に、変更後の鋳造速
度Wに基づいて、引抜速度Vを(1)式によって決定
し、次いで中心固相率fsおよびドラム押し力Pを
(2)式および(3)式によって決定して、これらの鋳
造速度W、引抜速度V、中心固相率fsおよびドラム押
し力Pの値を満足するように、冷却ドラムの回転速度お
よび湯溜まり部への溶鋼供給量を設定して、変更後の鋳
造速度Wを維持しながら、連続鋳造操業を行うことを特
徴とする双ドラム式連続鋳造方法。 V =(1000×W)/(d×w×γ) (1) fs=g(Q,Ts,θ,d)×10M (2) ただし、M=h(Q,Ts,θ,d)×Vで表される。 P =J(fs) (3)
4. When the twin drum type continuous casting according to claim 2 or 3 is being performed, when the casting speed W is changed within the same charge and within the same cast, based on the changed casting speed W Then, the drawing speed V is determined by the equation (1), and then the central solid fraction fs and the drum pressing force P are determined by the equations (2) and (3). The continuous casting is performed while setting the rotation speed of the cooling drum and the molten steel supply amount to the molten metal pool so as to satisfy the values of the central solid fraction fs and the drum pressing force P, while maintaining the changed casting speed W. A twin-drum type continuous casting method characterized by performing operations. V = (1000 × W) / (d × w × γ) (1) fs = g (Q, Ts, θ, d) × 10 M (2) where M = h (Q, Ts, θ, d) It is represented by × V. P = J (fs) (3)
【請求項5】 請求項2,3,4のいずれか1項に記載
された双ドラム式連続鋳造を行っている時に、決定した
ドラム押し力Pが設備能力を超える場合に、鋳造速度W
を再設定し、(1),(2),(3)式によって再度引
抜速度V、中心固相率fsおよびドラム押し力Pを決定
し、ドラム押し力Pが設備能力範囲にあってこれらの鋳
造速度W、引抜速度V、中心固相率fsおよびドラム押
し力Pの値を満足するように、冷却ドラムの回転速度お
よび湯溜まり部への溶鋼供給量を設定して、設定した鋳
造厚dまたは鋳造速度Wを維持しながら、連続鋳造操業
を行うことを特徴とする双ドラム式連続鋳造方法。 V =(1000×W)/(d×w×γ) (1) fs=g(Q,Ts,θ,d)×10M (2) ただし、M=h(Q,Ts,θ,d)×Vで表される。 P =J(fs) (3)
5. When performing the twin-drum type continuous casting according to any one of claims 2, 3 and 4, when the determined drum pressing force P exceeds the facility capacity, the casting speed W
And the drawing speed V, the central solid fraction fs, and the drum pushing force P are determined again by the equations (1), (2), and (3), and the drum pushing force P is within the equipment capacity range. The rotation speed of the cooling drum and the molten steel supply amount to the molten metal pool are set so that the values of the casting speed W, the drawing speed V, the central solid fraction fs, and the drum pressing force P are satisfied, and the set casting thickness d is set. Alternatively, the twin-drum type continuous casting method is characterized in that the continuous casting operation is performed while maintaining the casting speed W. V = (1000 × W) / (d × w × γ) (1) fs = g (Q, Ts, θ, d) × 10 M (2) where M = h (Q, Ts, θ, d) It is represented by × V. P = J (fs) (3)
JP9378095A 1995-04-19 1995-04-19 Twin roll continuous casting method Withdrawn JPH08290243A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9378095A JPH08290243A (en) 1995-04-19 1995-04-19 Twin roll continuous casting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9378095A JPH08290243A (en) 1995-04-19 1995-04-19 Twin roll continuous casting method

Publications (1)

Publication Number Publication Date
JPH08290243A true JPH08290243A (en) 1996-11-05

Family

ID=14091940

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9378095A Withdrawn JPH08290243A (en) 1995-04-19 1995-04-19 Twin roll continuous casting method

Country Status (1)

Country Link
JP (1) JPH08290243A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1575723A1 (en) * 2002-12-23 2005-09-21 Posco Co., Ltd. A method of startup procedure of strip in the twin roll strip casting process
JP4734496B2 (en) * 1999-02-05 2011-07-27 キャストリップ・リミテッド・ライアビリティ・カンパニー Steel strip continuous casting method
JP2020168644A (en) * 2019-04-03 2020-10-15 日本製鉄株式会社 Method for producing thin slab
CN112222392A (en) * 2020-09-07 2021-01-15 东北大学 Cloth bag with continuous temperature measurement function
CN113953479A (en) * 2021-10-25 2022-01-21 江苏沙钢集团有限公司 Method for improving flanging of thin strip steel coil

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4734496B2 (en) * 1999-02-05 2011-07-27 キャストリップ・リミテッド・ライアビリティ・カンパニー Steel strip continuous casting method
EP1575723A1 (en) * 2002-12-23 2005-09-21 Posco Co., Ltd. A method of startup procedure of strip in the twin roll strip casting process
EP1575723A4 (en) * 2002-12-23 2006-08-16 Posco Co Ltd A method of startup procedure of strip in the twin roll strip casting process
JP2020168644A (en) * 2019-04-03 2020-10-15 日本製鉄株式会社 Method for producing thin slab
CN112222392A (en) * 2020-09-07 2021-01-15 东北大学 Cloth bag with continuous temperature measurement function
CN113953479A (en) * 2021-10-25 2022-01-21 江苏沙钢集团有限公司 Method for improving flanging of thin strip steel coil
CN113953479B (en) * 2021-10-25 2023-02-24 江苏沙钢集团有限公司 Method for improving flanging of thin strip steel coil

Similar Documents

Publication Publication Date Title
JPH08290243A (en) Twin roll continuous casting method
JP3095346B2 (en) Level control method in mold for continuous casting
JPH06264B2 (en) Level control method in continuous casting
KR101546266B1 (en) Control apparatus and method of accelerated cooling apparatus
JPS61232044A (en) Continuous casting method for thin sheet
JPH0460740B2 (en)
JPS62199253A (en) Constant width controlling method for continuous casting slab
JPH0929401A (en) Method for controlling temperature of molten steel in tundish for continuous casting
JPS5823543A (en) Controlling method for thickness in production of thin strip of quickly solidified metal by double roll method
JPH0561025B2 (en)
JPS5940539B2 (en) Continuous casting method
JP2952142B2 (en) Twin-drum continuous casting method
JPS60238001A (en) Continuous production of thin sheet
JPS6219935B2 (en)
JPS63313642A (en) Apparatus for controlling cutting weight of cast slab
JP3023877B2 (en) Prevention method of solidification cracking of stainless steel sheet in twin roll method.
RU2043835C1 (en) Method of the metal continuous casting
JPS62144808A (en) Method for controlling cooling water for work roll of hot rolling mill
JP2602368B2 (en) Method for controlling the temperature at the exit of a rolling mill for hot rolled material
RU2048963C1 (en) Method of continuous casting of metals
JPS6114049A (en) Production of quickly cooled thin strip having uniform thickness
JPH0673733B2 (en) Method of controlling molten steel temperature in tundish at the beginning of casting
RU2043834C1 (en) Method of the metal continuous casting
CN114559003A (en) Method for controlling thickness stability of casting strip in twin-roll thin strip continuous casting
JPH02147B2 (en)

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20020702