JPH08284194A - Repairing material for concrete structure under ground and repairing method therefor - Google Patents

Repairing material for concrete structure under ground and repairing method therefor

Info

Publication number
JPH08284194A
JPH08284194A JP11116995A JP11116995A JPH08284194A JP H08284194 A JPH08284194 A JP H08284194A JP 11116995 A JP11116995 A JP 11116995A JP 11116995 A JP11116995 A JP 11116995A JP H08284194 A JPH08284194 A JP H08284194A
Authority
JP
Japan
Prior art keywords
repair material
panel
fitting hole
reinforcing bars
concrete structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP11116995A
Other languages
Japanese (ja)
Other versions
JP2764252B2 (en
Inventor
Kosei Masaka
孝正 真坂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Seibu Polymer Corp
Original Assignee
Seibu Polymer Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Seibu Polymer Corp filed Critical Seibu Polymer Corp
Priority to JP11116995A priority Critical patent/JP2764252B2/en
Publication of JPH08284194A publication Critical patent/JPH08284194A/en
Application granted granted Critical
Publication of JP2764252B2 publication Critical patent/JP2764252B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

PURPOSE: To make unnecessary large-scale opencut construction, and to easily repair a damaged part in a short period, by arranging a plurality of reinforcing bars to be joined to reinforcing bars in a concrete structure under the ground at the periphery of a panel, at which the reinforcing bars protrude from the periphery of the panel at regular intervals ranging over the whole periphery of the panel. CONSTITUTION: A C-section steel bar unit is mounted on a square board member 3 with bolts, and reinforcing members 6 consisting of a pair of L-section steel bars are attached thereto so as to intersect each other parallel to diagonal lines, and thus a panel 2 is formed. A plurality of reinforcing bars 9 to be joined to reinforcing bars in a concrete structure under the ground are weld on the peripheral part of the outside of the C-section steel bar unit, ranging over the whole periphery, which bars 9 protrude from the periphery of the panel 2 toward the outside. A repairing material 1 composed of an above-mentioned way is put into a repairing material-fitting opening formed by opening the hole to be repaired on an underground structure, and the reinforcing bars 9 are welded to the reinforcing bar being left in the opening, and thus a concrete- placing framework is formed. After that, reinforcing bars are arranged in the opening and concrete is placed.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、建物の地下階、暗渠、
共同溝等の地下コンクリート構造物の破損箇所の補修材
および補修方法に関する。
BACKGROUND OF THE INVENTION The present invention relates to a basement floor of a building, an underdrain,
The present invention relates to a repair material and repair method for a damaged portion of an underground concrete structure such as a common ditch.

【0002】[0002]

【従来の技術】建物地下階、暗渠、共同溝等の地下コン
クリート構造物において、地震による衝撃や近接工事等
により局所的に穴があく等の破損が生じ、この穴等から
地下水が構造物内に浸入することがある。従来地下構造
物にこのような破損が生じた場合は、その修復のため建
造物の外側の地盤を開削し、構造物の外側から補修工事
を行っていた。
2. Description of the Related Art In an underground concrete structure such as a basement floor of a building, a culvert, a common ditch, etc., a damage such as a hole is locally caused by an impact from an earthquake or a nearby construction, and groundwater is discharged from the hole etc. May penetrate into. Conventionally, when such a damage occurs in an underground structure, the ground outside the building is excavated to repair the damage, and repair work is performed from the outside of the structure.

【0003】[0003]

【発明が解決しようとする課題】このような従来の補修
方法は、構造物の外側の地盤を大きく掘下げなければな
らないため大がかりな工事を必要とし、また地下水のた
め補修工事が困難であり、このため地下水を汲出すため
の工事も必要となり、建造物の修復までに多大の時間と
労力を要していた。
Such a conventional repair method requires large-scale work because the ground outside the structure must be dug deep, and the repair work is difficult because of groundwater. Therefore, the construction for extracting the groundwater was also necessary, and it took a lot of time and labor to restore the building.

【0004】本発明は、上記従来の方法の問題点にかん
がみなされたものであって、従来のように大がかりな工
事を必要とせず、また地下水が流れていても工事に支障
を来たすことがなく、短期間で容易に工事を完成するこ
とが可能な新規な地下構造物の補修方法およびこの補修
方法に使用する補修材を提供しようとするものである。
The present invention has been made in view of the problems of the above-mentioned conventional method, does not require a large-scale construction as in the conventional method, and does not hinder the construction even if groundwater flows. The present invention intends to provide a new method for repairing an underground structure that can be easily completed in a short period of time and a repair material used for this repair method.

【0005】[0005]

【課題を解決するための手段】上記本発明の目的を達成
する地下コンクリート構造物の補修材は、パネルの周縁
部に地下コンクリート構造物の鉄筋と接続するための複
数本の接続用鉄筋を該パネルの周縁から突出するように
して全周にわたって所定の間隔で配設してなるものであ
る。
A repairing material for an underground concrete structure which achieves the above-mentioned object of the present invention is to provide a plurality of connecting reinforcing bars for connecting with reinforcing bars of an underground concrete structure at a peripheral portion of a panel. It is arranged at a predetermined interval over the entire circumference so as to project from the peripheral edge of the panel.

【0006】また上記本発明の目的を達成するコンクリ
ート構造物の補修方法は、上記補修材を用意し、地下コ
ンクリート構造物の破損孔の周縁部を該補修材の接続用
鉄筋と接続すべき鉄筋部分を残して破砕して該補修材を
嵌装できる程度に拡開して補修材嵌装孔を形成し、該補
修材を該補修材嵌装孔に嵌装し、該補修材の接続用鉄筋
を該補修材嵌装孔の鉄筋部分に溶接するとともに、その
前後に締切板を該補修材嵌装孔の外側に配設することに
より該補修材の該パネルの周縁部と該補修材嵌装孔の周
縁部との間の空隙を閉ざし、該補修材の該パネルの周縁
部と該補修材嵌装孔の周縁部との間の空隙を急結モルタ
ル等の急結充填材で埋めた後、該補修材の内側の該補修
材嵌装孔内に鉄筋を配筋し、コンクリートを打設するこ
とを特徴とする。
Further, in the method for repairing a concrete structure which achieves the above object of the present invention, the above-mentioned repair material is prepared, and the peripheral portion of the damage hole of the underground concrete structure is to be connected to the connecting reinforcing bar of the repair material. For connecting the repair material by crushing leaving a part and expanding it to the extent that the repair material can be fitted to form a repair material fitting hole, and fitting the repair material into the repair material fitting hole A reinforcing bar is welded to a reinforcing bar portion of the repair material fitting hole, and a cut-off plate is provided outside the repair material fitting hole before and after the repair material fitting hole so that the peripheral edge portion of the panel of the repair material and the repair material fitting The gap between the peripheral portion of the mounting hole was closed, and the gap between the peripheral portion of the panel of the repair material and the peripheral portion of the repair material fitting hole was filled with a quick-setting filler such as quick-setting mortar. After that, reinforcing bars are arranged inside the repair material fitting hole inside the repair material, and concrete is poured.

【0007】また、本発明の一側面において、本発明の
補修方法は、上記の工程に加えて、該締切板の中該補修
材嵌装孔の下部に配設されたものに水抜きホースを挿通
し、この水抜きホースにより地下コンクリート構造物の
外部の地下水を抜き、次いでこの水抜きホースの内側か
ら止水剤を注入して該締切板外側に供給することにより
止水を行った後該水抜きホースを引抜く工程をさらに備
えることを特徴とするものである。
In addition, in one aspect of the present invention, in addition to the above steps, the repair method of the present invention includes a drainage hose provided in the shut-off plate below the repair material fitting hole. Through the drainage hose, drain the groundwater outside the underground concrete structure, then inject the waterproofing agent from the inside of the drainage hose and supply it to the outside of the shutoff plate to stop the water. The method further comprises the step of pulling out the water draining hose.

【0008】[0008]

【作用】本発明の補修材によれば、パネルの周縁部に、
地下構造物の鉄筋と接続するための複数本の接続用鉄筋
をパネルの周縁から突出するようにして全周にわたり所
定の間隔で配設したので、この補修材を地下構造物の補
修を要する穴を拡開して形成した補修材嵌装孔に嵌装
し、接続用鉄筋を該孔に残存する鉄筋に溶接することに
より、コンクリート打設用の枠組ができ上り、地下構造
物の内側から該孔内に鉄筋を配筋しコンクリートを打設
することができる。
According to the repair material of the present invention, in the peripheral portion of the panel,
Since a plurality of connecting reinforcing bars for connecting with the reinforcing bars of the underground structure are arranged at a predetermined interval over the entire circumference so as to project from the peripheral edge of the panel, this repair material is a hole requiring repair of the underground structure. Is fitted into a repair material fitting hole formed by expanding, and by welding the connecting reinforcing bar to the reinforcing bar remaining in the hole, a framework for concrete pouring is completed, and from the inside of the underground structure, Reinforcing bars can be arranged in the holes and concrete can be placed.

【0009】また本発明の補修方法によれば、破損孔の
拡開による補修材嵌装孔の形成、補修材の補修材嵌装孔
への嵌装、締切板による補修材のパネル周縁部と補修材
嵌装孔の周縁部との間の空隙の閉止、補修材の接続用鉄
筋と補修材嵌装孔の鉄筋部分との溶接、該空隙への急結
モルタル等の充填および補修材の内側の補修材嵌装孔内
への鉄筋の配筋、コンクリート打設をすべて地下構造物
の内側から行うことができる。
Further, according to the repair method of the present invention, the repair material fitting hole is formed by expanding the breakage hole, the repair material is fitted into the repair material fitting hole, and the panel peripheral portion of the repair material is provided by the shut-off plate. Closure of the gap between the peripheral edge of the repair material fitting hole, welding of the reinforcing bar for connecting the repair material and the reinforcing bar of the repair material fitting hole, filling of the quick-setting mortar, etc., and the inside of the repair material Reinforcing bar reinforcement and concrete pouring into the repair material fitting hole can be done from inside the underground structure.

【0010】また本発明の一側面においては、補修材嵌
装孔の下部に配設された締切板に水抜きホースを挿通し
たので、工事開始時にはこの水抜きホースにより地下水
を抜くことによって地下水があっても工事を支障なく行
うことができ、次いで該水抜きホースの内側から止水剤
を注入して締切板外側に供給することにより止水を行っ
た後水切りホースを引抜き、その後コンクリート打設を
行うことにより地下水の影響を受けることなく、補修工
事を行うことができる。
Further, according to one aspect of the present invention, the drainage hose is inserted through the shut-off plate provided in the lower portion of the repair material fitting hole, so that groundwater is drained by this drainage hose at the start of construction. Even if there is, the construction can be done without any problems. Then, after stopping the water by injecting the waterproofing agent from the inside of the water draining hose and supplying it to the outside of the shutoff plate, the draining hose is pulled out, and then the concrete is placed. By doing so, repair work can be performed without being affected by groundwater.

【0011】[0011]

【実施例】以下添付図面を参照して本発明の1実施例に
ついて説明する。図1は本発明の地下コンクリート構造
物補修材の正面図、図2はその側面図である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENT An embodiment of the present invention will be described below with reference to the accompanying drawings. FIG. 1 is a front view of an underground concrete structure repair material of the present invention, and FIG. 2 is a side view thereof.

【0012】補修材1はおおむね四角形のパネル2から
なり、パネル2は四角形に形成した合成樹脂製または鋼
製の板材3にC型鋼4をボルト5で取付けてなり、パネ
ル2の対角線に沿って1対のL型鋼からなる補強材6が
相互に交差するようにして各対角線上のパネルの角部に
溶接等の手段により取付けられている。なお、図2中7
は板材3とC型鋼4との間に介装されたゴムパッキンで
あり、8はゴムライニングした座金である。
The repair material 1 is composed of a panel 2 having a substantially rectangular shape. The panel 2 is formed by mounting a C-shaped steel 4 with bolts 5 on a plate material 3 made of a synthetic resin or steel formed in a rectangular shape, along a diagonal line of the panel 2. A pair of reinforcing members 6 made of L-shaped steel are attached to the corners of each diagonal panel by welding or the like so as to cross each other. In addition, 7 in FIG.
Is a rubber packing interposed between the plate member 3 and the C-shaped steel 4, and 8 is a rubber-lined washer.

【0013】パネル2のC型鋼4の外側周縁部には、地
下コンクリート構造物の鉄筋と接続するための複数本の
接続用鉄筋9がパネル2の周縁から外側に向けて突出す
るようにして全周にわたって溶接されている。鉄筋9の
間隔は補修しようとする構造物の鉄筋の間隔に合せて設
定されるかもしくは曲げて接続する。
A plurality of connecting reinforcing bars 9 for connecting to the reinforcing bars of the underground concrete structure are formed on the outer peripheral edge of the C-shaped steel 4 of the panel 2 so as to project outward from the peripheral edge of the panel 2. Welded all around. The distance between the reinforcing bars 9 is set according to the distance between the reinforcing bars of the structure to be repaired or is bent and connected.

【0014】パネル2の各辺の長さは、補修箇所の寸法
に対応して即時工事ができるように複数種類のものをあ
らかじめ用意しておく。
Plural kinds of lengths of the sides of the panel 2 are prepared in advance so that the construction can be carried out immediately depending on the size of the repaired portion.

【0015】次にこの補修材1を用いて地下コンクリー
ト構造物の破損孔を補修する方法について述べる。
Next, a method of repairing a damaged hole of an underground concrete structure using this repair material 1 will be described.

【0016】まず図3に示す地下構造物のコンクリート
壁10の破損孔11の周辺のコンクリート壁を複数種類
の寸法の補修材1の中サイズの近いものに合せて破砕
し、破損孔11を図3に点線Aで示す範囲まで拡開して
補修材嵌装孔12を形成する。その際コンクリート壁1
0中の鉄筋13は、補修材1の接続用鉄筋9と接続すべ
きものを残して余分な鉄筋を切断する。なお、図3
(a)中14はコンクリート壁10の外側の地盤を示
す。
First, the concrete wall around the damage hole 11 of the concrete wall 10 of the underground structure shown in FIG. 3 is crushed according to the medium size of the repair material 1 having a plurality of sizes, and the damage hole 11 is shown. A repair material fitting hole 12 is formed by expanding to a range indicated by a dotted line A in FIG. Then concrete wall 1
As for the reinforcing bar 13 in 0, the extra reinforcing bar is cut off, leaving the one to be connected to the connecting reinforcing bar 9 of the repair material 1. Note that FIG.
In (a), reference numeral 14 indicates the ground outside the concrete wall 10.

【0017】次に図4および図5に示すように複数の鋼
板または合成樹脂板からなる締切板15(図4中点線B
で示す)を補修材嵌装孔12の外側に配置する。
Next, as shown in FIGS. 4 and 5, a shut-off plate 15 made of a plurality of steel plates or synthetic resin plates (dotted line B in FIG. 4).
Are shown on the outside of the repair material fitting hole 12.

【0018】締切板15には、図6に示すように、複数
の針金挿通孔15aが開設されており、この針金挿通孔
15aには針金16が挿通されている。締切板15を設
置する際は、締切板を補修材嵌装孔12の外側に配置
し、針金16で各締切板15をコンクリート壁10の残
存鉄筋部分13に緩く結び着ける。また締切板15の長
手方向両側には止水用のパッキン18が貼着けられてい
る。
As shown in FIG. 6, the shut-off plate 15 is provided with a plurality of wire insertion holes 15a, and wires 16 are inserted into the wire insertion holes 15a. When installing the shut-off plate 15, the shut-off plate is arranged outside the repair material fitting hole 12, and each shut-off plate 15 is loosely tied to the residual reinforcing bar portion 13 of the concrete wall 10 by the wire 16. Further, water blocking packings 18 are attached to both sides of the shutoff plate 15 in the longitudinal direction.

【0019】地下水が補修材嵌装孔12の下部の外側か
ら構造物の内側に流入している場合は、あらかじめ水抜
きホース17を挿通させた締切板15′を1枚ないし数
枚用意しておき、補修材嵌装孔12の下部に配設する。
なお図中15a′は締切板15′の針金挿通孔である。
地下水はこの水抜きホース17を通って構造物内に流入
し排水される。
When groundwater flows into the inside of the structure from the outside of the lower part of the repair material fitting hole 12, one or several shutoff plates 15 'through which the drainage hose 17 is inserted are prepared in advance. The repair material fitting hole 12 is placed below the repair material fitting hole 12.
In the figure, 15a 'is a wire insertion hole of the shutoff plate 15'.
Groundwater flows into the structure through the drain hose 17 and is drained.

【0020】次に補修材1を図4,5に示すように補修
材嵌装孔12の外側寄りの位置に嵌装し、補修材1の接
続用鉄筋9を補修材嵌装孔12内に残存する鉄筋部分1
3に溶接することにより補修材1を固定する。溶接は地
下水の流出していない上部より行う。
Next, as shown in FIGS. 4 and 5, the repair material 1 is fitted to a position closer to the outer side of the repair material fitting hole 12, and the connecting reinforcing bar 9 of the repair material 1 is placed in the repair material fitting hole 12. Remaining rebar part 1
The repair material 1 is fixed by welding to No. 3. Welding is performed from the upper part where groundwater does not flow out.

【0021】その後締切板15,15′の針金16を内
側から引張り締切板15,15′をパネル2の周縁部外
側と補修材嵌装孔12の周縁部外側に圧接し、パネル2
の周縁部と補修材嵌装孔12の周縁部との間の空隙を閉
ざす。
After that, the wire 16 of the shut-off plates 15 and 15 'is pulled from the inside, and the shut-off plates 15 and 15' are pressed against the outside of the peripheral portion of the panel 2 and the outside of the peripheral portion of the repair material fitting hole 12 to make the panel 2
The gap between the peripheral edge of the above and the peripheral edge of the repair material fitting hole 12 is closed.

【0022】次に図7、図8に示すように、パネル2の
周縁部と補修材嵌装孔12の周縁部との間の空隙を急結
モルタル、急結セメント等の急速に乾燥固化する充填材
19で埋めて塞ぐ。
Next, as shown in FIGS. 7 and 8, the space between the peripheral edge of the panel 2 and the peripheral edge of the repair material fitting hole 12 is rapidly dried and solidified with quick-setting mortar, quick-setting cement or the like. It is filled with the filling material 19 and closed.

【0023】次に図9に示すように、水抜きホース17
の内側から止水剤20を注入して締切板15′の外側に
供給することにより、この止水剤20の固化により止水
が行われる。止水が完了したら水抜きホース17を引抜
く。水抜きホース17は短く切って後で打設する。コン
クリート中に埋設してもよい。
Next, as shown in FIG. 9, the drain hose 17
By injecting the water blocking agent 20 from the inside and supplying it to the outside of the shutoff plate 15 ′, the water blocking agent 20 is solidified to stop the water. When the water stop is completed, the drain hose 17 is pulled out. The water draining hose 17 is cut short and placed later. It may be embedded in concrete.

【0024】その後補修材1の内側の補修材嵌装孔12
内に補強用の鉄筋21を配筋し、生コンクリート22を
打設することにより補修を完了する。完成した補修部分
はコンクリート壁10と面一の平滑な内面を有し、鉄筋
21が配筋されているため強度も充分である。
After that, the repair material fitting hole 12 inside the repair material 1
Repair is completed by arranging reinforcing steel bars 21 inside and placing fresh concrete 22 therein. The completed repaired part has a smooth inner surface that is flush with the concrete wall 10 and the reinforcing bar 21 is reinforced, so that the repaired part has sufficient strength.

【0025】上記実施例においては、まず締切板15を
補修材嵌装孔12の外側に配置して針金16により鉄筋
13に結び着けた後補修材1を補修材嵌装孔12に嵌装
し鉄筋9,13を溶接するようにしているが、逆にまず
補修材1を補修材嵌装孔12に嵌装し鉄筋9,13を溶
接した後締切板15,15′を所定の位置に配置して針
金16により鉄筋13または9に結び着けるようにして
もよい。
In the above embodiment, first, the shut-off plate 15 is arranged outside the repair material fitting hole 12, the wire 16 is tied to the reinforcing bar 13, and then the repair material 1 is fitted into the repair material fitting hole 12. Although the reinforcing bars 9 and 13 are welded, conversely, first, the repair material 1 is fitted into the repair material fitting hole 12 and the reinforcing bars 9 and 13 are welded, and then the cutoff plates 15 and 15 'are arranged at predetermined positions. Alternatively, the wire 16 may be attached to the reinforcing bar 13 or 9.

【0026】また、図10に示すように、補修材1を補
修材嵌装孔12に嵌装する前に、地下水が流出している
補修嵌装孔12の下部12aを残して締切板15を補修
材嵌装孔12の周縁に配設し、次いで補修材1を補修材
嵌装孔12に嵌装し鉄筋9,13を溶接した後水抜きホ
ース17を挿通した締切板15′で下部12aを塞ぐよ
うにしてもよい。このようにすれば、締切板15′をパ
ネル2の下縁に支持させることができるので地下水が流
出している補修材嵌装孔下部においても工事が容易であ
る。
Further, as shown in FIG. 10, before the repair material 1 is fitted into the repair material fitting hole 12, the shut-off plate 15 is left with the lower part 12a of the repair fitting hole 12 into which ground water is flowing out. The lower part 12a is arranged at the periphery of the repair material fitting hole 12, then the repair material 1 is fitted in the repair material fitting hole 12, the reinforcing bars 9 and 13 are welded, and then the drainage hose 17 is inserted through the shut-off plate 15 '. May be closed. By doing so, since the shutoff plate 15 'can be supported on the lower edge of the panel 2, the work can be easily performed even in the lower portion of the repair material fitting hole where the groundwater flows out.

【0027】上記実施例においては、補修材は四角形に
形成されたものを示したが、補修材の形状は四角形に限
らず、円形、多角形等他の形状にしてもよい。また上記
実施例においては接続用鉄筋をC型鋼に溶接している
が、鉄筋のパネルへの取付方法はこの構造に限定される
ものではなく、種々の構造が可能である。
In the above embodiment, the repair material is shown to be formed in a quadrangle, but the shape of the repair material is not limited to a quadrangle, and may be another shape such as a circle or a polygon. Although the connecting rebar is welded to the C-shaped steel in the above embodiment, the method of attaching the rebar to the panel is not limited to this structure, and various structures are possible.

【0028】[0028]

【発明の効果】以上述べたように、本発明の補修材によ
れば、パネルの周縁部に、地下構造物の鉄筋と接続する
ための複数本の接続用鉄筋をパネルの周縁から突出する
ようにして全周にわたり所定の間隔で配設したので、こ
の補修材を地下構造物の補修を要する穴を拡開して形成
した補修材嵌装孔に嵌装し、接続用鉄筋を該孔に残存す
る鉄筋に溶接することにより、コンクリート打設用の枠
組ができ上り、地下構造物の内側から該孔内に鉄筋を配
筋しコンクリートを打設することができる。
As described above, according to the repair material of the present invention, a plurality of connecting reinforcing bars for connecting to the reinforcing bars of the underground structure are projected from the peripheral edge of the panel at the peripheral edge of the panel. Since it was arranged at a predetermined interval over the entire circumference, this repair material was fitted into the repair material fitting hole formed by expanding the hole requiring repair of the underground structure, and the connecting reinforcing bar was fitted in the hole. By welding to the remaining rebar, a framework for concrete pouring is completed, and the rebar can be laid in the hole from the inside of the underground structure to concrete.

【0029】また本発明の補修方法によれば、破損孔の
拡開による補修材嵌装孔の形成、補修材の補修材嵌装孔
への嵌装、締切板による補修材のパネル周縁部と補修材
嵌装孔の周縁部との間の空隙の閉止、補修材の接続用鉄
筋と補修材嵌装孔の鉄筋部分との溶接、該空隙への急結
モルタル等の充填および補修材の内側の補修材嵌装孔内
への鉄筋の配筋、コンクリート打設をすべて地下構造物
の内側から行うことができる。したがって、従来の方法
のように地下構造物の外側の地盤を開削する必要がな
く、短期間で容易に補修を行うことができる。
Further, according to the repair method of the present invention, the repair material fitting hole is formed by expanding the breakage hole, the repair material is fitted into the repair material fitting hole, and the panel peripheral edge portion of the repair material is provided by the shutoff plate. Closure of the gap between the peripheral edge of the repair material fitting hole, welding of the reinforcing bar for connecting the repair material and the reinforcing bar of the repair material fitting hole, filling of the quick-setting mortar, etc., and the inside of the repair material Reinforcing bar reinforcement and concrete pouring into the repair material fitting hole can be done from inside the underground structure. Therefore, unlike the conventional method, it is not necessary to excavate the ground outside the underground structure, and the repair can be easily performed in a short period of time.

【0030】また補修材嵌装孔内に配筋しコンクリート
を打設することにより補修完了後補修箇所は内面平滑と
なり必要な強度も充分確保することができる。
Further, by arranging the reinforcing material in the repair material fitting hole and placing concrete, the repaired portion has a smooth inner surface after the completion of repairing, and the necessary strength can be sufficiently secured.

【0031】また本発明の一側面においては、補修材嵌
装孔の下部に配設された締切板に水抜きホースを挿通し
たので、工事開始時にはこの水抜きホースにより地下水
を抜くことによって地下水があっても工事を支障なく行
うことができ、次いで該水抜きホースの内側から止水剤
を注入して締切板外側に供給することにより止水を行っ
た後水切りホースを引抜き、その後コンクリート打設を
行うことにより地下水の影響を受けることなく補修工事
を行うことができる。
Further, according to one aspect of the present invention, the drainage hose is inserted through the shut-off plate disposed below the repair material fitting hole, so that groundwater is drained by this drainage hose at the start of construction to remove groundwater. Even if there is, the construction can be done without any problems. Then, after stopping the water by injecting the waterproofing agent from the inside of the water draining hose and supplying it to the outside of the shutoff plate, the draining hose is pulled out, and then the concrete is placed. By doing so, repair work can be performed without being affected by groundwater.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の地下コンクリート構造物補修材の一実
施例を示す正面図である。
FIG. 1 is a front view showing an example of an underground concrete structure repair material of the present invention.

【図2】同実施例の側面図である。FIG. 2 is a side view of the embodiment.

【図3】地下コンクリート構造物の破損孔を示す図で
(a)は側面図、(b)は正面図である。
FIG. 3 is a view showing a damage hole of an underground concrete structure, (a) is a side view and (b) is a front view.

【図4】補修材嵌装孔に補修材を固定した状態を示す正
面図である。
FIG. 4 is a front view showing a state in which a repair material is fixed in a repair material fitting hole.

【図5】補修材嵌装孔に補修材を固定した状態を示す側
面図である。
FIG. 5 is a side view showing a state in which a repair material is fixed in a repair material fitting hole.

【図6】締切板を示す斜視図である。FIG. 6 is a perspective view showing a shutoff plate.

【図7】補修材と補修材嵌装孔との間の空隙を急結モル
タルで埋めた状態を示す正面図である。
FIG. 7 is a front view showing a state where a space between a repair material and a repair material fitting hole is filled with quick-setting mortar.

【図8】図7の状態の側面図である。FIG. 8 is a side view of the state shown in FIG.

【図9】補修材嵌装孔内に鉄筋を配筋し、生コンクリー
トを打設した状態を示す図である。
FIG. 9 is a view showing a state in which reinforcing bars are laid in repair material fitting holes and fresh concrete is placed.

【図10】締切板を設置する他の方法を示す正面図であ
る。
FIG. 10 is a front view showing another method of installing the shutoff plate.

【符号の説明】[Explanation of symbols]

1 補修材 2 パネル 9 接続用鉄筋 12 補修材嵌装孔 13 鉄筋部分 15,15′ 締切板 17 水抜きホース 19 急結充填材 21 鉄筋 22 生コンクリート 1 Repair Material 2 Panel 9 Reinforcing Bar for Connection 12 Repair Material Fitting Hole 13 Reinforcing Bar Part 15, 15 'Shutoff Plate 17 Drain Hose 19 Quick Filling Material 21 Reinforcing Bar 22 Raw Concrete

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 パネルの周縁部に地下コンクリート構造
物の鉄筋と接続するための複数本の接続用鉄筋を該パネ
ルの周縁から突出するようにして全周にわたって所定の
間隔で配設してなる地下コンクリート構造物補修材。
1. A plurality of connecting reinforcing bars for connecting to reinforcing bars of an underground concrete structure are arranged at a peripheral portion of the panel so as to project from the peripheral edge of the panel at predetermined intervals. Underground concrete structure repair material.
【請求項2】 パネルの周縁部に地下コンクリート構造
物の鉄筋と接続するための複数本の接続用鉄筋を該パネ
ルの周縁から突出するようにして全周にわたって所定の
間隔で配設してなる地下コンクリート構造物補修材を用
意し、 地下コンクリート構造物の破損孔の周縁部を該補修材の
接続用鉄筋と接続すべき鉄筋部分を残して破砕して該補
修材を嵌装できる程度に拡開して補修材嵌装孔を形成
し、 該補修材を該補修材嵌装孔に嵌装し、該補修材の接続用
鉄筋を該補修材嵌装孔の鉄筋部分に溶接するとともに、
その前後に締切板を該補修材嵌装孔の外側に配設するこ
とにより該補修材の該パネルの周縁部と該補修材嵌装孔
の周縁部との間の空隙を閉ざし、 該補修材の該パネルの周縁部と該補修材嵌装孔の周縁部
との間の空隙を急結モルタル等の急結充填材で埋めた
後、 該補修材の内側の該補修材嵌装孔内に鉄筋を配筋し、コ
ンクリートを打設することを特徴とする地下コンクリー
ト構造物の補修方法。
2. A plurality of connecting reinforcing bars for connecting to the reinforcing bars of an underground concrete structure are arranged on the peripheral edge of the panel at predetermined intervals over the entire circumference so as to project from the peripheral edge of the panel. Prepare a repair material for the underground concrete structure, and crush the peripheral edge of the damaged hole of the underground concrete structure to the extent that the repair material can be fitted by crushing it, leaving the reinforcing bar portion to be connected to the connecting reinforcing bar of the repair material. Open to form the repair material fitting hole, fit the repair material into the repair material fitting hole, and weld the connecting reinforcing bar of the repair material to the reinforcing bar portion of the repair material fitting hole,
By disposing a shut-off plate outside the repair material fitting hole before and after that, a gap between the peripheral edge portion of the panel of the repair material and the peripheral edge portion of the repair material fitting hole is closed, and the repair material After filling the gap between the peripheral edge of the panel and the peripheral edge of the repair material fitting hole with a quick-setting filler such as quick-setting mortar, inside the repair material fitting hole inside the repair material A method for repairing an underground concrete structure, which comprises arranging reinforcing bars and placing concrete.
【請求項3】 該締切板の中該補修材嵌装孔の下部に配
設されたものに水抜きホースを挿通し、この水抜きホー
スにより地下コンクリート構造物の外部の地下水を抜
き、次いでこの水抜きホースの内側から止水剤を注入し
て該締切板外側に供給することにより止水を行った後該
水抜きホースを引抜く工程をさらに備えることを特徴と
する請求項2記載の地下コンクリート構造物の補修方
法。
3. A drainage hose is inserted through one of the cut-off plates arranged below the repair material fitting hole, and the groundwater outside the underground concrete structure is drained by the drainage hose, and then this 3. The underground according to claim 2, further comprising a step of injecting a waterproofing agent from the inside of the drainage hose and supplying it to the outside of the shutoff plate to stop the water, and then pulling out the drainage hose. How to repair concrete structures.
JP11116995A 1995-04-11 1995-04-11 Underground concrete structure repair material and repair method Expired - Lifetime JP2764252B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11116995A JP2764252B2 (en) 1995-04-11 1995-04-11 Underground concrete structure repair material and repair method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11116995A JP2764252B2 (en) 1995-04-11 1995-04-11 Underground concrete structure repair material and repair method

Publications (2)

Publication Number Publication Date
JPH08284194A true JPH08284194A (en) 1996-10-29
JP2764252B2 JP2764252B2 (en) 1998-06-11

Family

ID=14554235

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11116995A Expired - Lifetime JP2764252B2 (en) 1995-04-11 1995-04-11 Underground concrete structure repair material and repair method

Country Status (1)

Country Link
JP (1) JP2764252B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102434008A (en) * 2010-09-29 2012-05-02 贵阳铝镁设计研究院有限公司 Opening reinforcing method implemented after punching hole on cast-in-place concrete plate
CN104420487A (en) * 2013-08-21 2015-03-18 贵阳铝镁设计研究院有限公司 Strengthening method and structure of basic short column
CN109944256A (en) * 2019-04-02 2019-06-28 中铁二十三局集团第四工程有限公司 A kind of underground engineering vertical lift well restoring and fastening method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102434008A (en) * 2010-09-29 2012-05-02 贵阳铝镁设计研究院有限公司 Opening reinforcing method implemented after punching hole on cast-in-place concrete plate
CN104420487A (en) * 2013-08-21 2015-03-18 贵阳铝镁设计研究院有限公司 Strengthening method and structure of basic short column
CN109944256A (en) * 2019-04-02 2019-06-28 中铁二十三局集团第四工程有限公司 A kind of underground engineering vertical lift well restoring and fastening method

Also Published As

Publication number Publication date
JP2764252B2 (en) 1998-06-11

Similar Documents

Publication Publication Date Title
JP6636773B2 (en) Construction structure and construction method of tunnel lining body
RU2568668C2 (en) Formwork element for trench wall and trench wall erection method
CN106812131B (en) A kind of permanent sheet pile underground structure and its construction method
CN110952995A (en) Construction method for external tunnel door post-cast ring beam
KR101599403B1 (en) Method for constructing clean sewer pipe
WO2009005244A2 (en) Method for burying hume pipes and support block used in the method
JP3893056B2 (en) Construction method of underground structure
JP2764252B2 (en) Underground concrete structure repair material and repair method
CN109680722A (en) The construction method for setting external building access port is directly stayed on outer wall of basement body
KR101545713B1 (en) Composite type cutoff wall of steel temporary facility and construction method of the same
JPS6354093B2 (en)
KR100310457B1 (en) Waterproofing method of concrete structure
JP4387919B2 (en) Seismic countermeasures for tunnels using seismic isolation materials, construction methods for seismic isolation walls, and construction structures
JP7094717B2 (en) Press-fit method
JP3225818B2 (en) How to repair crack-inducing joints
KR102526362B1 (en) Apparatus for constructing downward vertical structure
JPH084033A (en) Structure method of building underground outer periphery pressure bulkhead
JPH0546427B2 (en)
JPH06980B2 (en) How to place steel sheet pile concrete
KR200417474Y1 (en) Support pipe
JP2583058B2 (en) Basement method
JP2693028B2 (en) Construction method of human hole in middle of pipeline
JP2003041549A (en) Joint repair construction method for caisson
JPH0517955A (en) Execution method for direct foundation and form panel for direct foundation
JP2022158643A (en) Repair construction method and repair structure using stainless steel repair panel for wall of expressway tunnel watchman passage