JPH082651A - Controller for load transfer device - Google Patents

Controller for load transfer device

Info

Publication number
JPH082651A
JPH082651A JP13889394A JP13889394A JPH082651A JP H082651 A JPH082651 A JP H082651A JP 13889394 A JP13889394 A JP 13889394A JP 13889394 A JP13889394 A JP 13889394A JP H082651 A JPH082651 A JP H082651A
Authority
JP
Japan
Prior art keywords
load
sensor
transfer device
sensors
station
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP13889394A
Other languages
Japanese (ja)
Other versions
JP2729921B2 (en
Inventor
Hiroyuki Ueki
裕之 上木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Okamura Corp
Original Assignee
Okamura Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Okamura Corp filed Critical Okamura Corp
Priority to JP6138893A priority Critical patent/JP2729921B2/en
Publication of JPH082651A publication Critical patent/JPH082651A/en
Application granted granted Critical
Publication of JP2729921B2 publication Critical patent/JP2729921B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Special Conveying (AREA)
  • Control Of Conveyors (AREA)
  • Intermediate Stations On Conveyors (AREA)

Abstract

PURPOSE:To efficiently carry out the load transfer with high efficiency and place the load on a load carrying platform surely and safely, by controlling the operation of a transfer device according to the length of the load. CONSTITUTION:A load 1 is transferred on a load carrying plaform 3 side from a station 2 side, and when the load 1 passes through the first sensor 7 installed closely to the end part close to the station 2 on the load carrying platform 3, the operation of a transfer device 4 is suspended instantly by a control circuit 9 in the ordinary case, and the load l can be stopped at the position on the load carrying platform 3 which is most advantageous for the discharge to the station 2 side, independently of the length of the load 1.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、荷の受渡しを行なうス
テーションに対して、荷台を昇降しうるようにした荷移
載装置の制御装置、特に、荷台又はステーションに設け
られた荷の搬送装置の作動を停止させるための制御装置
に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a load transfer device control device capable of moving a load platform up and down with respect to a load delivery station, and more particularly to a load transfer device provided on the load carrier or station. The present invention relates to a control device for stopping the operation of the.

【0002】[0002]

【従来の技術】工場等においては、ステーションに運ば
れてきた被搬送物、例えば多数の部材を収容したコンテ
ナを、加工工程に供給したり、他のステーションに移載
する場合にしばしば吊下げ搬送装置が使用される。
2. Description of the Related Art In factories and the like, an object to be conveyed, for example, a container containing a large number of members, is often hung and conveyed when it is supplied to a processing step or transferred to another station. The device is used.

【0003】この吊下げ搬送装置には、ステーションに
対して昇降しうるようにした荷台に、荷を移載するため
の搬送装置と、荷が荷台上の所望の位置に到達したこと
を検知して、搬送装置の作動を停止させるセンサとを設
けたものがある。
[0003] This hanging transfer device detects a transfer device for transferring a load to a loading platform that can be moved up and down with respect to a station and that the load has reached a desired position on the loading platform. And a sensor for stopping the operation of the transport device.

【0004】[0004]

【発明が解決しようとする課題】上述した従来の搬送装
置は、荷台におけるステーションに遠い方の端部寄りに
設けた荷検知センサが、荷の到達したことを検知するこ
とにより、制御装置により、搬送装置を停止させるよう
にしている。この場合、荷が一定の長さの例えばコンテ
ナ類であるときには、荷台の搬送装置を常に一定の距離
だけ移動させればよい。
In the above-described conventional transport apparatus, the load detection sensor provided near the end of the carrier on the far side of the station detects the arrival of the load, so that the control device can The transport device is stopped. In this case, when the load is, for example, a container having a fixed length, the carrier device of the loading platform may always be moved by a fixed distance.

【0005】しかし、長さの異なる種々のコンテナや荷
を搬送しようとすると、荷の長さが短いときにも、荷が
荷検知センサに到達するまで、搬送装置が作動すること
となって、その分、荷台の荷の移載及び荷の後工程への
搬出に余計な時間がかかり、搬送効率が低下するという
問題がある。
However, when trying to convey various containers and loads having different lengths, even when the length of the load is short, the transport device operates until the load reaches the load detection sensor. As a result, it takes extra time to transfer the cargo on the loading platform and carry it out to the subsequent process, which causes a problem that the transportation efficiency is reduced.

【0006】逆に、荷が大きいと、荷検知センサが荷を
検知し搬送装置を直ちに停止させたとしても、荷台から
荷がはみ出したり、また落下したりする危険がある。
On the other hand, if the load is large, there is a risk that the load may overflow or drop from the bed even if the load detection sensor detects the load and immediately stops the transport device.

【0007】本発明は、上記問題点を解消すべくなされ
たもので、荷の長さに応じて、搬送装置の作動を制御す
ることができ、効率の良い荷の搬送を行なうとともに、
安全に、しかも確実に荷を荷台上に載置することができ
るようにした荷移載装置における制御装置を提供するこ
とを目的としている。
The present invention has been made to solve the above-mentioned problems, and it is possible to control the operation of the transfer device according to the length of the load, so that the load can be transferred efficiently.
An object of the present invention is to provide a control device in a load transfer device that can safely and reliably load a load on a loading platform.

【0008】[0008]

【課題を解決するための手段】本発明によると、上記課
題は、次のようにして解決される。 (1) 図1に示すように、荷(1)の受渡しを行なうステ
ーション(2)と、このステーション(2)に対して昇降し
うるようにした荷台(3)との少なくともいずれか一方
に、前記ステーション側から荷台(3)側に向けて荷を搬
送しうる搬送装置(4)を設けた荷移載装置(5)における
制御装置(6)であって、前記荷台(3)における前記ステ
ーション(2)に近い方の端部寄りに設けられ、かつ荷
(1)が通過したことを検知する第1センサ(7)と、この
第1センサ(7)が、荷(1)が通過したことを検知するこ
とにより、前記搬送装置(4)の作動を停止させる通常制
御回路(9)とを備えること。
According to the present invention, the above problems can be solved as follows. (1) As shown in FIG. 1, at least one of a station (2) for delivering and receiving a load (1) and a loading platform (3) capable of moving up and down with respect to the station (2), A control device (6) in a load transfer device (5) provided with a transfer device (4) capable of transferring a load from the station side to the load platform (3) side, wherein the station in the load platform (3) It is provided near the end closer to (2) and
The first sensor (7) for detecting the passage of (1) and the operation of the conveying device (4) by detecting the passage of the load (1) by the first sensor (7). A normal control circuit (9) for stopping should be provided.

【0009】(2) 図1に示すように、上記(1)項のも
のに、さらに、荷台(3)におけるステーション(2)から
遠い方の端部より若干内方寄りに設けられ、かつ荷(1)
の先端が到達したことを検知する第2センサ(8)と、こ
の第2センサ(8)が、荷(1)の先端が到達したことを検
知することにより、搬送装置(4)の作動を停止させる第
1安全回路(10)とを備える。
(2) As shown in FIG. 1, in addition to the above item (1), the loading platform (3) is provided slightly inward from the end of the loading platform (3) far from the station (2), and (1)
The second sensor (8) that detects the arrival of the tip of the load, and the second sensor (8) detects that the tip of the load (1) has reached the end of the transport device (4). A first safety circuit (10) for stopping.

【0010】(3) 図1に示すように、上記(1)又は
(2)項のものに、さらに、荷台(3)におけるステーショ
ン(2)から遠い方の端部寄りに設けられ、かつ荷の先端
が到達したことを検知する第3センサ(11)と、この第3
センサ(11)が、荷(1)の先端が到達したことを検知する
ことにより、搬送装置(4)の作動を停止させるととも
に、警報手段(12)を作動させる第2安全回路(13)とを備
える。
(3) As shown in FIG. 1, the above (1) or
In addition to the item (2), a third sensor (11) is provided near the end of the loading platform (3) farther from the station (2) and detects the arrival of the tip of the load. Third
The sensor (11) detects that the tip of the load (1) has arrived, and thereby stops the operation of the transfer device (4) and also activates the alarm means (12) and a second safety circuit (13). Equipped with.

【0011】(4) 図6に示すように、昇降しうる荷台
(3)の両側方に、荷(1)の受渡しを行なうステーション
(2)を配置し、かつ前記荷台(3)又はステーション(2)
に、荷(1)を各ステーション(2)側から荷台(3)側に向
けて搬送しうる搬送装置(4)を設けた荷移載装置(5)に
おける制御装置(6)であって、前記荷台(3)の両端部寄
りに設けられ、かつ荷(1)が通過したことを検知する1
対の第1センサ(7)(7)と、この第1センサ(7)が、荷
(1)が通過したことを検知することにより、前記搬送装
置(4)の作動を停止させる通常制御回路(14)とを備える
こと。
(4) As shown in FIG. 6, a loading platform that can move up and down.
Stations for delivering the load (1) to both sides of (3)
(2) is arranged, and the carrier (3) or station (2)
A control device (6) in a load transfer device (5) provided with a transfer device (4) capable of transferring the load (1) from each station (2) side toward the loading platform (3) side, It is provided near both ends of the loading platform (3) and detects that the loading (1) has passed 1
The pair of first sensors (7) (7) and this first sensor (7)
A normal control circuit (14) for stopping the operation of the transport device (4) by detecting that (1) has passed.

【0012】(5) 図8に示すように、昇降しうる荷台
(3)の両側方に、荷(1)の受渡しを行なうステーション
(2)を配置し、かつ前記荷台(3)又はステーション(2)
に、荷(1)を各ステーション(2)側から荷台(3)側に向
けて搬送しうる搬送装置(4)を設けた荷移載装置(5)に
おける制御装置(6)であって、前記荷台(3)の両端部寄
りに設けられ、かつ荷(1)が通過中であること、又は荷
(1)が通過したことを検知する1対の第1センサ(7)
(7)と、荷台(3)における前記1対の第1センサ(7)
(7)より若干内方寄りの部分に設けられ、かつ荷(1)が
到達したことを検知する1対の第2センサ(8)(8)と、
いずれか一方の第1センサ(7)が、荷(1)が通過中であ
ることを検出しているか、又は荷(1)が通過したことを
検知した後、前記一方の第1センサ(7)から遠い方の第
2センサ(8)が、荷(1)が到達したことを検知すること
により、前記搬送装置(4)の作動を停止させる通常制御
回路(15)とを備えること。
(5) As shown in FIG.
Stations for delivering the load (1) to both sides of (3)
(2) is arranged, and the carrier (3) or station (2)
A control device (6) in a load transfer device (5) provided with a transfer device (4) capable of transferring the load (1) from each station (2) side toward the loading platform (3) side, It is provided near both ends of the loading platform (3) and the loading (1) is passing, or
A pair of first sensors (7) for detecting the passage of (1)
(7) and the pair of first sensors (7) on the loading platform (3)
(7) A pair of second sensors (8) and (8), which are provided slightly inward of the load and detect that the load (1) has arrived,
Either one of the first sensors (7) detects that the load (1) is passing, or after detecting that the load (1) has passed, the one first sensor (7) is detected. The second sensor (8) farther from (1) is provided with a normal control circuit (15) for stopping the operation of the transfer device (4) by detecting that the load (1) has arrived.

【0013】(6) 図10に示すように、昇降しうる荷
台(3)の両側方に、荷(1)の受渡しを行なうステーショ
ン(2)を配置し、かつ前記荷台(3)又はステーション
(2)に、荷(1)を各ステーション(2)側から荷台(3)側
に向けて搬送しうる搬送装置(4)を設けた荷移載装置
(5)における制御装置(6)であって、前記荷台(3)の両
端部寄りに設けられ、かつ荷(1)が通過中であること、
及び荷(1)が通過したことを検知する1対の第1センサ
(7)(7)と、荷台(3)における前記1対の第1センサ
(7)(7)より若干内方寄りの部分に設けられ、かつ荷
(1)が到達したことを検知する1対の第2センサ(8)
(8)と、いずれか一方の第1センサ(7)が、荷(1)が通
過したことを検知することにより、前記搬送装置(4)の
作動を停止させる第1通常制御回路(16)と、いずれか一
方の第1センサ(7)が、荷(1)が通過中であることを検
知しているか、又は荷(1)が通過したことを検知した
後、前記一方の第1センサ(7)から遠い方の第2センサ
(8)が、荷(1)が到達したことを検知することにより、
前記搬送装置(4)の作動を停止させる第2通常制御回路
(17)とを備えること。
(6) As shown in FIG. 10, stations (2) for delivering and receiving the load (1) are arranged on both sides of the load platform (3) which can move up and down, and the load platform (3) or the station.
A load transfer device provided with a transfer device (4) capable of transferring the load (1) from each station (2) side toward the load platform (3) side in (2)
The control device (6) in (5), which is provided near both ends of the loading platform (3), and the load (1) is passing through,
And a pair of first sensors for detecting that the load (1) has passed
(7) (7) and the pair of first sensors on the platform (3)
(7) Provided in a part slightly inward of (7) and loaded
A pair of second sensors (8) that detect the arrival of (1)
(8) and either one of the first sensors (7) detects that the load (1) has passed, and thus the first normal control circuit (16) for stopping the operation of the conveying device (4). And either one of the first sensors (7) detects that the load (1) is passing, or after detecting that the load (1) has passed, the one first sensor Second sensor farther from (7)
By (8) detecting that the load (1) has arrived,
Second normal control circuit for stopping the operation of the transfer device (4)
(17) and must be provided.

【0014】(7) 図10に示すように、上記(6)項の
ものに、さらに、第1通常制御回路(16)の作動を、有効
としたり無効としたりしうる切換手段(18)を設ける。
(7) As shown in FIG. 10, in addition to the above item (6), a switching means (18) for enabling or disabling the operation of the first normal control circuit (16) is further provided. Set up.

【0015】(8) 図6、図8及び図10に示すよう
に、上記(4)〜(7)項のいずれかのものにおいて、各第
1センサ(7)を、荷(1)の少なくとも一部が到達したこ
と、及び荷(1)が通過中であることを検知する機能を有
するものとし、かついずれか一方の第1センサ(7)が、
荷(1)が通過中であることを検知しており、かつ他方の
第1センサ(7)が、荷(1)の少なくとも一部が到達した
ことを検知することにより、搬送装置(4)の作動を停止
させるとともに、警報手段(10)を作動させる安全回路を
設ける。
(8) As shown in FIGS. 6, 8 and 10, in any one of the above items (4) to (7), each first sensor (7) is connected to at least the load (1). It shall have a function of detecting that a part has arrived and that the load (1) is passing, and one of the first sensors (7) is
By detecting that the load (1) is passing and the first sensor (7) on the other side detects that at least a part of the load (1) has arrived, the transport device (4) A safety circuit for activating the alarm means (10) as well as stopping the operation of is provided.

【0016】(9) 図6、図8、図10及び図12に示
すように、上記(1)〜(8)項のいずれかのものにおい
て、各センサ(7)(8)を、荷(1)の搬送方向と直交する
荷台(3)の両側部に対向して設けられた発光素子と受光
素子とからなる光電センサとする。
(9) As shown in FIGS. 6, 8, 10 and 12, in each of the above items (1) to (8), each sensor (7) (8) is connected to a load ( The photoelectric sensor is composed of a light emitting element and a light receiving element which are provided so as to face each other on both sides of the loading platform (3) orthogonal to the carrying direction of (1).

【0017】(10) 図6、図8及び図10に示すよう
に、上記(1)〜(8)項のいずれかのものにおいて、搬送
装置(4)を、荷台(3)に設けられたベルトコンベヤとす
る。
(10) As shown in FIGS. 6, 8 and 10, in any one of the above items (1) to (8), the carrier device (4) is provided on the loading platform (3). Use a belt conveyor.

【0018】(11) 図12に示すように、上記(1)〜
(8)項のいずれかのものにおいて、搬送装置(4')を、ス
テーション(2)側に設けられた荷押出し装置とする。
(11) As shown in FIG. 12, the above (1)-
In any one of (8), the transfer device (4 ') is a load pushing device provided on the station (2) side.

【0019】[0019]

【作用】本発明によると、荷が、ステーション側から荷
台側に移載され、荷台におけるステーションに近い端部
寄りに設けられた第1センサを通過すると、通常制御回
路により、即座に搬送装置の作動が停止させられるの
で、荷の長さに関係なく、荷を、次にステーション側に
排出するときに最も便利な荷台上にの位置に停止させる
ことができる(請求項1、4)。
According to the present invention, when the load is transferred from the station side to the loading platform side and passes through the first sensor provided near the end of the loading platform near the station, the normal control circuit immediately causes the loading device to move. Since the operation is stopped, regardless of the length of the load, the load can be stopped at the most convenient position on the bed for the next discharge to the station side (claims 1 and 4).

【0020】また、第2センサ、第3センサ等を設け、
それらによっても、搬送装置の作動を停止させうるよう
にすると、安全性が向上する(請求項2、3、6、8)。
Further, a second sensor, a third sensor, etc. are provided,
Also by making them possible to stop the operation of the conveying device, the safety is improved (claims 2, 3, 6, 8).

【0021】[0021]

【実施例】次に、本発明の具体的な実施例を、図面を参
照して説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Next, specific embodiments of the present invention will be described with reference to the drawings.

【0022】図1〜図5は、請求項1〜3、9及び10
記載の発明の実施例(以下第1の実施例と呼ぶ)を示す。
1 to 5 show claims 1 to 3, 9 and 10.
An embodiment of the described invention (hereinafter referred to as a first embodiment) will be shown.

【0023】図2は、吊下げ搬送装置を示し、(21)は、
天井に架設したレール、(A)は、レール(21)に沿って自
走する台車、(2)は、走行台車(A)に吊支して昇降する
荷台である。
FIG. 2 shows a suspending and conveying device, (21) is
A rail erected on the ceiling, (A) is a trolley that travels along the rail (21), and (2) is a loading platform that is hung and supported by the traveling trolley (A).

【0024】走行台車(A)の水平をなす基板(22)の前部
と後部には、それぞれ前後に並んで左右方向を向く1対
ずつの支持板(23)が垂設され、対をなす両支持板(23)の
中央部には、左右1対の巻取りドラム(24)が枢設され、
同じく両端部には、それぞれフランジ付ローラ(25)と、
それに近接して平行に並ぶ押えローラ(26)とが枢設され
ている。
A pair of support plates (23), which are aligned in the front-rear direction and are oriented in the left-right direction, are vertically provided at the front and rear portions of the horizontal board (22) of the traveling carriage (A) to form a pair. A pair of left and right take-up drums (24) are pivotally installed at the center of both support plates (23),
Similarly, on both ends, with a flanged roller (25),
A pressing roller (26) arranged in parallel with and close to it is pivotally installed.

【0025】各巻取りドラム(24)に基端を止着した吊支
ベルト(27)の遊端は、フランジ付ローラ(25)と押えロー
ラ(26)の間を通過して、下方の荷台(2)の台枠(28)の4
角部に止着されている。
The free end of the suspension belt (27) having the base end fixed to each winding drum (24) passes between the flanged roller (25) and the pressing roller (26), and the lower bed ( 2) Underframe (28) 4
It is fastened to the corner.

【0026】対をなす両巻取りドラム(24)のドラム軸(2
4a)の内端には、同歯数のギヤ(29)が嵌設されて互いに
噛合し、一方のギヤ(29)には、基板(21)の中央部に左右
方向に向けて設けたモータ(30)の出力ギヤ(31)が噛合し
て、荷台(2)は、モータ(30)により水平を保持して昇降
する。
The drum shaft (2
Gears (29) with the same number of teeth are fitted and meshed with each other at the inner end of 4a), and one of the gears (29) is a motor provided in the center of the substrate (21) in the left-right direction. The output gear (31) of (30) meshes with each other, and the platform (2) moves up and down while being kept horizontal by the motor (30).

【0027】基板(22)の下方において水平をなす、基板
(22)より若干小形の押え板(35)の上面4角部には、下向
U字形の吊支具(36)が固着され、その上片が吊支杆(32)
に下方より遊嵌して、係止ピン(34)により吊支され、押
え板(35)は、吊支杆(32)に巻装した圧縮ばね(37)によ
り、下方に向けて付勢されている。
A substrate which is horizontal below the substrate (22)
A downward U-shaped hanging fixture (36) is fixed to the four corners of the upper surface of the holding plate (35) which is slightly smaller than (22), and the upper piece thereof is the hanging rod (32).
It is loosely fitted to the suspension from below and is suspended by the locking pin (34), and the pressing plate (35) is urged downward by the compression spring (37) wound around the suspension rod (32). ing.

【0028】各吊支具(36)の側面には、押え板(35)が圧
縮ばね(37)に抗して上昇すると、近接センサ(33)に近接
して、両軸モータ(30)を停止させる感知片(38)が添設さ
れている。
When the holding plate (35) rises against the compression spring (37) on the side surface of each suspension support (36), it comes close to the proximity sensor (33) and the double shaft motor (30) is installed. A sensing piece (38) for stopping is attached.

【0029】押え板(35)の下面全体(一部分でもよい)に
は、ゴムやウレタン等の弾性体からなるすべり止め高摩
擦層(39)が形成されている。
A non-slip high friction layer (39) made of an elastic material such as rubber or urethane is formed on the entire lower surface (or a part thereof) of the pressing plate (35).

【0030】図3に示すように、荷台(3)の台枠(28)に
は、プーリ(40)に掛け回された左右1対の無端ベルト(4
1)が、図1に示すモータ(42)によって図1における左右
方向へ回送させられるようにした、後述するステーショ
ン(30)からの荷の送り方向と同方向の荷を搬送する搬送
装置(4)であるベルトコンベヤ(43)が配設されている。
As shown in FIG. 3, a pair of left and right endless belts (4) wound around pulleys (40) are mounted on the underframe (28) of the loading platform (3).
1) is configured to be transported in the left-right direction in FIG. 1 by the motor (42) shown in FIG. ) Is a belt conveyor (43).

【0031】台枠(28)の上部におけるベルトコンベヤ(4
3)の両外側方には、ベルトコンベヤ(43)とほぼ等長かつ
平行をなす案内柵(44)が、側方位置調節可能に立設され
ている。
A belt conveyor (4
On both outer sides of 3), guide fences (44) that are approximately equal in length and parallel to the belt conveyor (43) are erected so that the lateral position can be adjusted.

【0032】図1、図3及び図4に示すように、各案内
棚(44)におけるステーション(2)に近い方の端部寄り
と、ステーション(2)から遠い方の端部より若干内方寄
りの部分と、ステーション(2)から遠い方の端部寄りと
には、ベルトコンベヤ(43)による荷(1)の搬送方向と直
交する方向に対向するように、発光素子(46a)受光素子
(46b)とからなる光電センサ(46)とした第1センサ(7)
と、第2センサ(8)と、第3センサ(11)とが設けられて
いる。
As shown in FIGS. 1, 3 and 4, each guide rack (44) is closer to the end closer to the station (2) and slightly inward than the end farther from the station (2). The light-emitting element (46a) and the light-receiving element (46a) are arranged so as to oppose in a direction orthogonal to the conveyance direction of the load (1) by the belt conveyor (43) in the portion near the end and the end near the station (2).
First sensor (7) which is photoelectric sensor (46) consisting of (46b)
And a second sensor (8) and a third sensor (11).

【0033】図1に示すように、荷台(3)には、第1セ
ンサ(7)が、荷(1)が通過したことを検知することによ
り、搬送装置(4)の作動を停止させる通常制御回路(9)
と、第2センサ(8)が、荷(1)の先端が到達したことを
検知することにより、搬送装置(4)の作動を停止させる
第1安全回路(10)と、第3センサ(11)が、荷(1)の先端
が到達したことを検知することにより、搬送装置(4)の
作動を停止させるとともに、警報ランプ又はブザー等の
警報手段(12)を作動させる第2安全回路(13)とを備える
制御装置(6)が設けられている。
As shown in FIG. 1, the first sensor (7) on the loading platform (3) normally detects the passage of the load (1) to stop the operation of the transfer device (4). Control circuit (9)
Then, the second sensor (8) detects the arrival of the tip of the load (1), and thereby stops the operation of the transfer device (4), and the third sensor (11). ) Detects that the tip of the load (1) has reached, stops the operation of the carrier device (4), and activates an alarm means (12) such as an alarm lamp or a buzzer (2). A control device (6) comprising 13) is provided.

【0034】図3に示すように、第1の実施例において
は、ステーション(2)は、常に荷台(3)の前端側(図3
の左方)に位置するものとし、かつ上下多段状に設置さ
れたモータ駆動式のローラコンベヤ(47)としてある。
As shown in FIG. 3, in the first embodiment, the station (2) always has the front end side (FIG. 3) of the loading platform (3).
It is located on the left side of the table) and is a motor-driven roller conveyor (47) installed in a multi-stage vertically.

【0035】次に、図5に示すフローチャートに基づい
て、第1の実施例の作用について説明する。
Next, the operation of the first embodiment will be described based on the flow chart shown in FIG.

【0036】荷台(3)を所望のローラコンベヤ(47)と等
高の位置まで昇降させた後、そのローラコンベヤ(47)と
荷台(3)上の搬送装置(4)とを作動させ(S1)、荷(1)
を、図1及び図3の右方に向けて移送させる。
After raising and lowering the loading platform (3) to a position at the same height as the desired roller conveyor (47), the roller conveyor (47) and the transport device (4) on the loading platform (3) are operated (S1 ), Load (1)
Are transferred to the right in FIGS. 1 and 3.

【0037】荷(1)が、第1センサ(7)の位置に到達
し、第1センサ(7)が荷(1)によって遮光されたときは
(S2)、搬送装置(4)は、そのまま作動状態を継続するが
(S3)、その後、荷(1)が第1センサ(7)の位置を完全に
通過し、第1センサ(7)の受光素子(46b)が発光素子(4
6a)からの光を受光すると(S4)、搬送装置(4)の作動が
即座に停止させられ(S5)、荷(1)は荷台(3)上の第1セ
ンサ(7)に近接した位置で停止させられる。
When the load (1) reaches the position of the first sensor (7) and the first sensor (7) is shielded by the load (1),
(S2) and the transport device (4) continue to operate,
(S3), after that, the load (1) completely passes the position of the first sensor (7), and the light receiving element (46b) of the first sensor (7) becomes the light emitting element (4).
When the light from 6a) is received (S4), the operation of the transport device (4) is immediately stopped (S5), and the load (1) is located at a position close to the first sensor (7) on the loading platform (3). Stopped at.

【0038】その後、荷台(3)が上昇させられ、吊下げ
搬送装置が他のステーション(2)まで走行した後、再度
荷台(3)が下降して、所望のローラコンベヤ(47)と等高
の位置で停止し、荷台(3)上の荷(1)をローラコンベヤ
(47)側へ移載する際、荷(1)がローラコンベヤ(47)に近
い方の荷台(3)の端部寄りに位置しているので、その移
載を迅速に行なうことができる。
After that, the loading platform (3) is lifted up, the suspending / conveying device travels to another station (2), and then the loading platform (3) is lowered again so as to have the same height as the desired roller conveyor (47). Stop at the position and load the load (1) on the loading platform (3) with the roller conveyor.
When transferring to the (47) side, since the load (1) is located near the end of the load platform (3) closer to the roller conveyor (47), the transfer can be carried out quickly.

【0039】また、ステップ(S4)において、例えば第1
センサ(7)が何らかの原因で故障するか、又は発光素子
(46a)と受光素子(46b)との間に何らかの遮光物が挾まる
等により、実際には荷(1)が第1センサ(7)を通過して
いるにも拘らず、第1センサ(7)が受光しない場合は、
荷(1)が第2センサ(8)に到達し、第2センサ(8)が荷
(1)によって遮光されることにより(S6)、搬送装置(4)
の作動が停止させられる(S5)。
In step (S4), for example, the first
The sensor (7) fails for some reason, or the light emitting element
Despite the fact that the load (1) actually passes through the first sensor (7) due to some kind of light blocking object between the (46a) and the light receiving element (46b), the first sensor ( If 7) does not receive light,
The load (1) reaches the second sensor (8) and the second sensor (8) loads
By being shielded from light by (1) (S6), the transport device (4)
Is stopped (S5).

【0040】さらに、万一第1センサ(7)と第2センサ
(8)がともに故障したり、又は誤って複数の荷(1)が隙
間なく連なって搬送されてきて、第2センサ(8)が作動
したにも拘らず、慣性で荷(1)がさらに進行してしまっ
たような場合には、荷(1)の先端が第3センサ(11)を遮
光した時点で、警報手段(12)が作動させられるとともに
(S8)、搬送装置(4)が緊急停止させられる(S5)。
Further, in the unlikely event that the first sensor (7) and the second sensor
(8) both failed, or a plurality of loads (1) were erroneously conveyed in a row without a gap, and the second sensor (8) was activated, but the load (1) was further moved due to inertia. In the case where it has proceeded, the alarm means (12) is activated at the time when the tip of the load (1) shields the third sensor (11).
(S8), the transport device (4) is stopped urgently (S5).

【0041】図6は、請求項4及び8〜10記載の発明
の実施例(以下第2の実施例と呼ぶ)を示す。なお、以下
における前記第1実施例のものと同一の部材には、同一
の符号を付して図示するに止め、それらについての詳細
な説明は省略する。
FIG. 6 shows an embodiment of the invention described in claims 4 and 8-10 (hereinafter referred to as a second embodiment). It should be noted that the same members as those in the first embodiment below are given the same reference numerals and are shown in the drawings, and detailed description thereof will be omitted.

【0042】この第2の実施例においては、図1〜図4
に示す吊下げ搬送装置におけるものと同様の荷台(3)の
両端部に、図3に示すステーション(2)と同様のステー
ション(2)が配置され、その両方から荷台(3)に荷(1)
が移載されることがあるものにおいて、荷台(3)上の搬
送装置(4)を、荷(1)を両方向に搬送しうるものとする
とともに、荷台(3)の両端部寄りに、図2に示すものと
同様の光電センサ(46)からなる第1センサ(7)を設けて
ある。
In this second embodiment, FIGS.
Stations (2) similar to the station (2) shown in FIG. 3 are arranged at both ends of a platform (3) similar to that in the suspension conveyance device shown in FIG. )
In some cases, the transfer device (4) on the loading platform (3) can transport the load (1) in both directions, and at the two sides of the loading platform (3), A first sensor (7) consisting of a photoelectric sensor (46) similar to that shown in 2 is provided.

【0043】すなわち、各第1センサ(7)は、荷(1)が
その位置まで到達して通過中であること(遮光)と、荷
(1)が通過したこと(遮光後の受光)とを検知することが
できる。
That is, each of the first sensors (7) has to check that the load (1) has reached its position and is passing (light blocking),
It is possible to detect that (1) has passed (light reception after light shielding).

【0044】(14)は、いずれかの第1センサ(7)が、荷
(1)が通過したことを検知することにより、搬送装置
(4)の作動を停止させるようにした通常制御回路であ
る。(19)は、いずれか一方のセンサ(7)が荷(1)によっ
て遮光されている状態で、他方のセンサ(7)にも荷(1)
の一部が到達して遮光されることにより、警報手段(12)
を作動させるとともに、搬送装置(4)を緊急停止させる
安全回路である。
(14) indicates that one of the first sensors (7)
By detecting that (1) has passed, the transfer device
This is a normal control circuit that stops the operation of (4). (19) is a state where one of the sensors (7) is shielded by the load (1) and the other sensor (7) also receives the load (1).
The alarm means (12)
It is a safety circuit that activates the device and stops the transport device (4) in an emergency.

【0045】次に、図7にフローチャートに基づいて、
図6に示す第2の実施例の作用について説明する。
Next, based on the flow chart in FIG.
The operation of the second embodiment shown in FIG. 6 will be described.

【0046】例えば、図6に左方のステーション(2)か
ら荷(1)を荷台(3)に移載する際には、そのステーショ
ン(2)のローラコンベヤ(図3参照)と、搬送装置(4)と
を、図6の右方に向かって荷送りすることにより作動さ
せる(S1)。
For example, when the load (1) is transferred from the station (2) on the left side in FIG. 6 to the loading platform (3), the roller conveyor (see FIG. 3) of the station (2) and the transfer device are used. (4) and (4) are actuated by sending the goods to the right in FIG. 6 (S1).

【0047】その後、ステップ(S2)〜(S5)は、図5に示
した第1の実施例のステップ(S2)〜(S5)と同様に作用す
る。
Thereafter, steps (S2) to (S5) operate in the same manner as steps (S2) to (S5) of the first embodiment shown in FIG.

【0048】ステップ(S4)において、第1センサ(7)が
遮光されたままの状態で、他方の第1センサ(7)が遮光
されると(S6)、警報手段(12)が作動させられるとともに
(S7)、搬送装置(4)が緊急停止させられる(S5)。
In step (S4), when the first sensor (7) is shielded while the other first sensor (7) is shielded (S6), the alarm means (12) is activated. With
(S7), the transport device (4) is stopped urgently (S5).

【0049】荷(1)が、図6の右方のステーション(2)
から送られてくるときは、左右の第1センサ(7)の作動
が逆になるだけで、図7に示すフローチャートと同様に
作動する。
The load (1) is on the right side station (2) in FIG.
When sent from, the operation of the left and right first sensors (7) is only reversed, and the operation is similar to the flowchart shown in FIG. 7.

【0050】したがって、前記第1の実施例のものと比
較すると、第2センサ(8)の作動により、搬送装置(4)
の作動が停止されることがないだけで、第1の実施例の
ものと同様の作用及び効果を奏することができる。しか
も、図6の実施例においては、荷(1)が左右いずれのス
テーション(2)から送られてきた場合でも、同様の働き
をすることができるという利点がある。
Therefore, as compared with the first embodiment, the operation of the second sensor (8) causes the transfer device (4) to move.
The same operation and effect as those of the first embodiment can be achieved only by not stopping the operation of. Moreover, the embodiment shown in FIG. 6 has the advantage that the same function can be achieved regardless of whether the load (1) is sent from the left or right station (2).

【0051】図8及び図9は、請求項5及び8〜10記
載の発明の実施例(以下第3の実施例と呼ぶ)を示す。
FIGS. 8 and 9 show an embodiment of the invention described in claims 5 and 8 to 10 (hereinafter referred to as a third embodiment).

【0052】第3の実施例においては、第2の実施例と
同様の構成のもの(通常制御回路(14)は除く)において、
荷台(3)における左右の第1センサ(7)(7)より若干内
方寄りの部分に、荷(1)が到達したこを検知する1対の
第2センサ(8)(8)を設けるとともに、いずれか一方の
第1センサ(7)が、荷(1)が通過中であることを検出し
ているか、又は荷(1)が通過したことを検知した後、一
方の第1センサ(7)から遠い方の第2センサ(8)が、荷
(1)が到達したことを検知することにより、搬送装置
(4)の作動を停止させる通常制御回路(14)といずれか一
方の第1センサ(7)が、荷(1)が通過中であることを検
知しており、かつ他方の第1センサ(7)が、荷(1)の少
なくとも一部が到達したことを検知することにより、搬
送装置(4)の作動を停止させるとともに、警報手段(12)
を作動させる安全回路(19)とを設けている。
In the third embodiment, in the same construction as the second embodiment (excluding the normal control circuit (14)),
A pair of second sensors (8) and (8) for detecting arrival of the load (1) are provided at portions of the loading platform (3) slightly inward of the left and right first sensors (7) and (7). At the same time, either one of the first sensors (7) detects that the load (1) is passing, or after detecting that the load (1) has passed, one of the first sensors (7) The second sensor (8) farther from 7)
By detecting that (1) has arrived, the transport device
The normal control circuit (14) for stopping the operation of (4) and one of the first sensors (7) detect that the load (1) is passing, and the other first sensor ( 7) detects that at least a part of the load (1) has arrived, thereby stopping the operation of the transfer device (4) and at the same time alarming means (12).
And a safety circuit (19) for operating the.

【0053】第3の実施例の装置は、図1に示すように
作用する。すなわち、ステップ(S1)〜(S4)までは、図7
に示す第2の実施例のステップ(S1)〜(S4)と同様に作用
する。
The device of the third embodiment operates as shown in FIG. That is, steps (S1) to (S4) are shown in FIG.
The same operation as steps (S1) to (S4) of the second embodiment shown in FIG.

【0054】しかし、ステップ(S4)において、荷(1)が
一方の第1センサ(7)を完全に通過し、第1センサ(7)
が受光しても、搬送装置(4)は作動を停止しないでその
まま作動し続け(S5)、一方の第1センサ(7)から遠い方
の第2センサ(8)が、遮光されることにより(S6)、初め
て作動が停止させられる(S7)。
However, in the step (S4), the load (1) completely passes through the one first sensor (7), and the first sensor (7)
Even when the light is received, the transport device (4) continues to operate without stopping the operation (S5), and the second sensor (8) far from the one first sensor (7) is shielded from light. (S6), the operation is stopped for the first time (S7).

【0055】また、ステップ(S4)において、一方の第1
センサ(7)がまだ遮光されていない場合でも、その第1
センサ(7)から遠い方の第2センサ(8)が遮光されると
(S8)、搬送装置(4)の作動は停止させられる(S7)。
In step (S4), the first one of the
Even if the sensor (7) is not shaded yet, its first
When the second sensor (8) farther from the sensor (7) is shielded from light
(S8), the operation of the transfer device (4) is stopped (S7).

【0056】さらに、ステップ(S8)において、その第2
センサ(8)が遮光されることなく、他方の第1センサ
(7)が先に遮光されると(S9)、警報手段(12)が作動させ
られるとともに(S10)、搬送装置(4)が緊急停止させら
れる(S7)。
Further, in step (S8), the second
The sensor (8) is not shielded from light, and the other first sensor
When (7) is shielded first (S9), the alarm means (12) is activated (S10), and the transport device (4) is stopped urgently (S7).

【0057】したがって、第3の実施例においては、荷
(1)は、荷台(3)上の最初の第1センサ(7)の通過後即
座に停止させられることはなく、その第1センサ(7)か
ら遠い方の第2センサ(8)に達した時点で停止させられ
るので、例えば、図8の左方のステーション(2)から荷
(1)を受取り、他のステーション(2)において、図8の
右方の荷(1)を排出したいような場合に、荷台(3)上の
右端を常に一定位置に整えることができ、便利である。
Therefore, in the third embodiment, the load
(1) is not immediately stopped after passing the first sensor (7) on the loading platform (3), and reaches the second sensor (8) farther from the first sensor (7). Since it will be stopped at the time of doing, for example, from the station (2) on the left side of FIG.
When receiving (1) and wanting to discharge the load (1) on the right side of FIG. 8 at another station (2), the right end on the loading platform (3) can be always adjusted to a fixed position, which is convenient. Is.

【0058】図10は、請求項6〜10記載の発明の実
施例(以下第4の実施例と呼ぶ)を示す。この第4の実施
例は、大まかには、第2の実施例と、第3の実施例とを
組合せたような構成となっている。
FIG. 10 shows an embodiment of the invention described in claims 6 to 10 (hereinafter referred to as a fourth embodiment). The fourth embodiment has a structure roughly combining the second embodiment and the third embodiment.

【0059】すなわち、機械的な構成は、第3の実施例
のものと同様に、荷台(3)に1対ずつの第1センサ(7)
(7)と第2センサ(8)(8)とを設け、電気的な制御回路
構成として、第2の実施例の通常制御回路(14)と同一の
第1通常制御回路(16)と、第3の実施例の通常制御回路
(15)と同一の第2通常制御回路(17)と、第1通常制御回
路(16)の作動を有効としたり無効としたりしうる切換手
段(18)と、第2の実施例及び第3の実施例におけるのと
同一の安全回路(19)及び警報手段(12)とを設けている。
That is, the mechanical structure is the same as that of the third embodiment, and the pair of first sensors (7) are arranged on the loading platform (3).
(7) and the second sensors (8) and (8) are provided, and as an electric control circuit configuration, a first normal control circuit (16) which is the same as the normal control circuit (14) of the second embodiment, Normal control circuit of the third embodiment
A second normal control circuit (17) identical to (15), a switching means (18) for enabling or disabling the operation of the first normal control circuit (16), the second embodiment and the third embodiment. The same safety circuit (19) and alarm means (12) as in the above embodiment are provided.

【0060】切換手段(18)としては、具体的には、第1
通常制御回路(16)と搬送装置(4)とを接続する信号線を
接続したり切断したりしうる単なるスイッチとすること
ができる。
The switching means (18) is specifically the first
It can be a mere switch that can connect and disconnect the signal line that normally connects the control circuit 16 and the transport device 4.

【0061】第4の実施例の作用を、図11に基づいて説
明すると次のとおりである。
The operation of the fourth embodiment will be described below with reference to FIG.

【0062】図11において、ステップ(S1)〜(S3)は、図
7及び図8のステップ(S1)〜(S3)と同一である。すなわ
ち、搬送装置(4)が所望の方向に作動させられ(S1)、荷
(1)が一方の第1センサ(7)を遮光した後も(S2)、搬送
装置(4)は作動し続ける(S3)。
In FIG. 11, steps (S1) to (S3) are the same as steps (S1) to (S3) in FIGS. 7 and 8. That is, the transport device (4) is operated in the desired direction (S1),
Even after (1) shields one of the first sensors (7) from light (S2), the transport device (4) continues to operate (S3).

【0063】ステップ(S4)において、切換手段(18)がオ
ン(ON)、すなわち第1通常制御回路(16)の作動が有効と
されていると、一方の第1センサ(7)を受光することに
より(S5)、すなわち荷(1)がその第1センサ(7)を通過
することにより、搬送装置(4)の作動は停止させられる
(S6)。
In step (S4), if the switching means (18) is on (ON), that is, the operation of the first normal control circuit (16) is valid, one of the first sensors (7) receives light. As a result (S5), that is, when the load (1) passes through the first sensor (7), the operation of the transfer device (4) is stopped.
(S6).

【0064】ステップ(S5)において、一方の第1センサ
(7)が受光せず、それより先に、一方の第1センサ(7)
から遠い方の第2センサ(8)が荷(1)によって遮光され
ると(S7)、それによっても搬送装置(4)の作動は停止さ
せられる(S6)。
In step (S5), one of the first sensors
(7) does not receive light, and first sensor (7) on one side
When the second sensor (8) farther from is shielded by the load (1) (S7), the operation of the transfer device (4) is also stopped (S6).

【0065】また、ステップ(S7)において、遠い方の第
2センサ(8)が遮光されることなく、他方の第1センサ
(7)が遮光されると(S8)、警報手段(12)が作動させられ
るとともに(S4)、搬送装置(4)の作動は停止させられる
(S6)。
In step (S7), the second sensor (8) on the far side is not shielded from light, and the other first sensor (8) is not shielded.
When (7) is shielded from light (S8), the alarm means (12) is activated (S4) and the transport device (4) is deactivated.
(S6).

【0066】ステップ(S4)において、切換手段(18)がオ
フ(OFF)側に切換えられており、第1通常制御回路(16)
の作動が無効とされているときは、その後、一方の第1
センサ(7)が受光しても(S10)、搬送装置(4)は作動し
続け(S11)、その後、荷(1)が一方の第1センサ(7)か
ら遠い方の第2センサ(8)に到達して、その第2センサ
(8)を遮光すると(S12)、搬送装置(4)の作動は停止さ
せられる(S6)。
In step (S4), the switching means (18) is switched to the OFF (OFF) side, and the first normal control circuit (16)
If the operation of the
Even if the sensor (7) receives light (S10), the transport device (4) continues to operate (S11), and then the load (1) is moved to the second sensor (8) farther from the one first sensor (7). ) To reach its second sensor
When (8) is shielded from light (S12), the operation of the transfer device (4) is stopped (S6).

【0067】ステップ(S10)において、一方の第1セン
サ(7)が受光することなく、その第1センサ(7)から遠
い方の第2センサ(8)に荷(1)が到達しても第2センサ
(8)を遮光した場合にも(S13)、搬送装置(4)の作動は
停止させられる(S6)。
In step (S10), even if the load (1) reaches the second sensor (8) farther from the first sensor (7) without receiving light from the one first sensor (7). Second sensor
Even when the light is blocked from (8) (S13), the operation of the transfer device (4) is stopped (S6).

【0068】ステップ(S13)において、遠い方の第2セ
ンサ(8)が遮光されることなく、他方の第1センサ(7)
が遮光されると(S13)、報手段(12)が作動させられると
ともに(S15)、搬送装置(4)が緊急停止させられる(S
6)。
In step (S13), the second sensor (8) on the far side is not shielded from light, and the first sensor (7) on the other side is not shielded.
When the light is blocked from light (S13), the reporting means (12) is activated (S15), and the transport device (4) is brought to an emergency stop (S).
6).

【0069】図12及び図13は、請求項1〜3、9及び11
記載の発明の実施例(以下第5の実施例と呼ぶ)を示す。
第5の実施例においては、ロータリラック(50)における
荷移載装置(51)に本発明を適用している。
12 and 13 show claims 1 to 3, 9 and 11.
An embodiment of the described invention (hereinafter referred to as a fifth embodiment) will be shown.
In the fifth embodiment, the present invention is applied to the load transfer device (51) in the rotary rack (50).

【0070】すなわち、ロータリラック(50)は、支持枠
(52)により上下多段状に支持した多数のパレット(53)
を、図13の左部の支柱(54)を中心として、平面視長円形
の軌跡に沿って、各段毎に独立して回走しうるようにし
たもので、(支柱(54)の左方は図示省略)、その長円形軌
跡の内側に配設された支柱(54)には、モータ駆動により
水平に伸縮するようにしたプッシャ(55)を備える荷押出
し装置(56)が昇降自在に装着されている。
That is, the rotary rack (50) is a support frame.
A large number of pallets (53) supported by the upper and lower stages (52)
The center of the column (54) on the left side of FIG. 13 is designed to be able to independently travel in each step along the trajectory of the oval in plan view. (The other side is not shown in the figure), but the column (54) arranged inside the elliptical locus has a load pushing device (56) equipped with a pusher (55) that can be horizontally expanded and contracted by a motor drive so that it can be moved up and down. It is installed.

【0071】またパレット(53)の回走軌跡の外側に、支
柱(54)と対向して立設された支柱(57)には、荷押出し装
置(56)によりパレット(53)から外側方に押出された荷
(1)を受ける荷台(3)が、荷押出し装置(56)と常に等高
をなして同期して昇降するように装着されている。
Further, on the pillar (57) which is erected on the outer side of the traveling locus of the pallet (53) so as to face the pillar (54), the load pushing device (56) moves the pallet (53) outward. Extruded load
The loading platform (3) for receiving (1) is mounted so as to always move at the same height as the loading push-out device (56) in synchronization with each other.

【0072】荷台(3)には、荷台(3)上に載置された荷
(1)を排出する排出装置(58)が設けられている。荷押出
し装置(56)と荷台(3)とにより、移載装置(51)が形成さ
れ、その間に挾まれたロータリラック(50)の一部がステ
ーション(2)をなしている。
The cargo bed (3) has a load placed on the cargo bed (3).
A discharge device (58) for discharging (1) is provided. A transfer device (51) is formed by the load push-out device (56) and the load platform (3), and a part of the rotary rack (50) sandwiched therebetween forms a station (2).

【0073】第5の実施例では、荷台(3)上に、図1〜
図5に示す実施例と同様の第1センサ(7)、第2センサ
(8)、及び第3センサ(11)が同様の配置で設けられてい
る。
In the fifth embodiment, as shown in FIG.
First sensor (7) and second sensor similar to those of the embodiment shown in FIG.
(8) and the third sensor (11) are provided in the same arrangement.

【0074】また、制御装置(6)は、第1の実施例と同
様の通常制御回路(9)と第1安全回路(10)と第2安全回
路(13)とを備えており、第1の実施例のものと同様に作
用する。
The control device (6) is provided with a normal control circuit (9), a first safety circuit (10) and a second safety circuit (13) similar to those of the first embodiment. The same operation as in the embodiment of

【0075】すなわち、第3の実施例は、適用対象をロ
ータリラック(50)の荷移載装置(51)としたことと、搬送
装置(4')を、ステーション(2)側に設けた荷押出し装置
(56)としたことを除いては、第1の実施例と同一であ
り、同一の作用及び効果を奏することができる。
That is, in the third embodiment, the object of application is the load transfer device (51) of the rotary rack (50), and the transfer device (4 ') is provided on the station (2) side. Extruder
Except that it is set to (56), it is the same as the first embodiment, and the same operation and effect can be obtained.

【0076】なお、上記の各実施例において、センサ
(7)(8)(11)は、透過型の光電センサとしたが、これら
を反射型の光電センサとしたり、近接センサ、リミット
スイッチその他のものとしてもよい。
In each of the above embodiments, the sensor
Although (7), (8) and (11) are transmission type photoelectric sensors, they may be reflection type photoelectric sensors, proximity sensors, limit switches and the like.

【0077】[0077]

【発明の効果】本発明によると、次のような効果を奏す
ることができる。 (1) 荷が第1センサを通過した後、即座に搬送装置が
停止させられるようにしたので、荷の長さに拘らず、荷
の一端を常にステーションに近い方の荷台の端部寄りの
一定の位置に整えて停止させることができ、その後の荷
の取扱いが便利であるとともに、荷の受取り時の移動量
を必要最小とし、移載時間を短縮でき、荷の搬入、搬出
作業を迅速に行なうことができる(請求項1、4及び
6)。
According to the present invention, the following effects can be obtained. (1) Since the transport device can be stopped immediately after the load passes through the first sensor, one end of the load is always near the end of the loading platform near the station regardless of the length of the load. It can be adjusted to a fixed position and stopped, and it is convenient to handle the load thereafter, and the transfer amount at the time of receiving the load can be minimized to shorten the transfer time and the load and unload operations can be done quickly. (Claims 1, 4 and 6).

【0078】(2) 第1センサの故障や誤作動により、
実際には荷が第1センサを通過しているのに、第1セン
サが作動しなかったり、又は複数の荷が誤って連なって
送られてきた時等は、荷の先端が第2センサに到達する
ことにより、搬送装置の作動が停止させれれるので、安
全である(請求項2及び6)。
(2) Due to the failure or malfunction of the first sensor,
When the load actually passes through the first sensor but the first sensor does not operate, or when a plurality of loads are erroneously sent in series, the tip of the load is transferred to the second sensor. It is safe because the operation of the transporting device is stopped by reaching it (claims 2 and 6).

【0079】(3) 第1センサ及び第2センサがともに
故障したり、誤作動を生じたり、又は第2センサが作動
したにも拘らず、荷及び搬送装置が慣性により進行して
しまったような場合には、荷の先端が第3センサ又は2
個設けた第1センサのうちの荷の進行方向の先方の第1
センサが作動することにより、搬送装置が緊急停止させ
られるとともに、警報手段が作動させられるので、さら
に安全であり、荷が荷台からはみ出した状態で荷台が昇
降したり、荷が荷台から落下したりするのを防止するこ
とができる(請求項3及び8)。
(3) It seems that both the first sensor and the second sensor are out of order, malfunction occurs, or the second sensor is activated, but the load and the conveyance device are advanced due to inertia. In this case, the tip of the load is the third sensor or 2
The first one of the provided first sensors in the traveling direction of the load
When the sensor is activated, the transport device is stopped in an emergency and the alarm means is activated, which is even safer, and the load platform moves up and down with the load protruding from the load platform, and the load drops from the load platform. This can be prevented (Claims 3 and 8).

【0080】(4) 荷台に対して荷を一方向に送り込む
場合だけでなく、その逆方向にも送り込むことができる
ようにした荷移載装置においては、そのいずれかの送り
込み方向に対しても同様に作動して、荷を荷台上の所定
の位置に停止させることができる(請求項4〜6及び
8)。
(4) In the load transfer device capable of sending the load not only in one direction to the loading platform but also in the opposite direction, the load is transferred in either of the feeding directions. It can be operated in the same manner to stop the load at a predetermined position on the bed (claims 4 to 6 and 8).

【0081】(5) 荷台の一端側から荷を荷台上に送り
込み、その荷を荷台の他側側からステーションに排出す
る場合に、荷の長短に関係なく、荷を常に荷台の排出側
の端部寄りに整えることができるので便利である(請求
項5)。
(5) When a load is sent from one end side of the loading platform to the loading platform and discharged from the other side of the loading platform to the station, the load is always discharged at the end of the loading platform regardless of the length of the loading platform. It is convenient because it can be arranged closer to the members (Claim 5).

【0082】(6) 切換手段を設けることにより、荷台
上に送られてきた荷を、進入側の第1センサの通過後即
座に停止させる態様と、進入側の第1センサから遠い方
の第2センサに達したときに停止させる態様とを選択す
ることができ、荷台に対する搬入時のステーションの配
置と、搬出時のステーションの配置によって、便利な方
の態様を選ぶことができる(請求項7)。
(6) By providing the switching means, the load sent to the loading platform is stopped immediately after passing through the first sensor on the approach side, and the load on the far side from the first sensor on the approach side is stopped. It is possible to select a mode of stopping when two sensors are reached, and a more convenient mode can be selected depending on the arrangement of the station at the time of loading and unloading with respect to the loading platform (claim 7). ).

【0083】(7) 荷が第1センサの作動による通常の
停止位置で停止しなかった場合でも、第2センサの作動
及び第3センサ又はその他の第1センサの作動により停
止させることができ、二重の安全策を講じているので万
全である(請求項1、2及び3の組合せ、並びに請求項
6及び8の組合せ)。
(7) Even when the load does not stop at the normal stop position due to the operation of the first sensor, it can be stopped by the operation of the second sensor and the operation of the third sensor or other first sensor, It is perfect because of the double safety measures (combination of claims 1, 2 and 3 and combination of claims 6 and 8).

【0084】(8) 荷移載装置を、荷台外に設けた荷の
押出し装置とすれば、荷台に特別な荷移載装置を設ける
必要がなく、その分荷台を簡単な構造とし、かつ軽量化
とすることができる(請求項11)。
(8) If the load transfer device is a load pushing device provided outside the load platform, it is not necessary to provide a special load transfer device on the load platform, and the load platform has a simple structure and is lightweight. (Claim 11).

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の第1の実施例の概要を示す概略構成図
である。
FIG. 1 is a schematic configuration diagram showing an outline of a first embodiment of the present invention.

【図2】第1の実施例に用いられる吊下げ搬送装置の側
面図である。
FIG. 2 is a side view of a suspension conveyance device used in the first embodiment.

【図3】同じく荷の移載時の状態を示す正面図である。FIG. 3 is a front view showing a state during transfer of a load.

【図4】同じく概略平面図である。FIG. 4 is a schematic plan view of the same.

【図5】第1の実施例の作動状態を示すフローチャート
である。
FIG. 5 is a flowchart showing an operating state of the first embodiment.

【図6】本発明の第2の実施例の概要を示す概略構成図
である。
FIG. 6 is a schematic configuration diagram showing an outline of a second embodiment of the present invention.

【図7】第2の実施例の作動状態を示すフローチャート
である。
FIG. 7 is a flow chart showing an operating state of the second embodiment.

【図8】本発明の第3の実施例の概要を示す概略構成図
である。
FIG. 8 is a schematic configuration diagram showing an outline of a third embodiment of the present invention.

【図9】第3の実施例の作動状態を示すフローチャート
である。
FIG. 9 is a flowchart showing an operating state of the third embodiment.

【図10】本発明の第4の実施例の概要を示す概略構成
図である。
FIG. 10 is a schematic configuration diagram showing an outline of a fourth embodiment of the present invention.

【図11】第4の実施例の作動状態を示すフローチャー
トである。
FIG. 11 is a flowchart showing an operating state of the fourth embodiment.

【図12】本発明の第5の実施例の概要を示す概略構成
図である。
FIG. 12 is a schematic configuration diagram showing an outline of a fifth embodiment of the present invention.

【図13】同じく要部の縦断正面図である。FIG. 13 is likewise a vertical sectional front view of a main part.

【符号の説明】[Explanation of symbols]

(1)荷 (2)ステーション (3)荷台 (4)搬送装置 (5)荷移載装置 (6)制御装置 (7)第1センサ (8)第2センサ (9)通常制御回路 (10)第1安全回路 (11)第3センサ (12)警報手段 (13)第2安全回路 (14)(15)通常制御回路 (16)第1通常制御回路 (17)第2通常制御回路 (18)切換手段 (19)安全回路 (21)レール (22)基板 (23)支持板 (24)巻取りドラム (24a)ドラム軸 (25)フランジ付ローラ (26)ローラ (27)吊支ベルト (28)台枠 (29)ギヤ (30)モータ (31)出力ギヤ (32)吊支杆 (33)近接センサ (34)係止ピン (35)押え板 (36)吊支具 (37)圧縮ばね (38)感知片 (39)高摩擦層 (40)プーリ(41)無端ベルト (42)モータ (43)ベルトコンベヤ (44)案内棚 (46)光電センサ (46a)発光素子 (46b)受光素子 (47)ローラコンベヤ (50)ロータリラック (51)荷移載装置 (52)支持枠 (53)パレット (54)支柱 (55)プッシャ (56)荷押出し装置 (57)支柱 (58)排出装置 (1) Load (2) Station (3) Loading platform (4) Transfer device (5) Load transfer device (6) Control device (7) First sensor (8) Second sensor (9) Normal control circuit (10) First safety circuit (11) Third sensor (12) Alarm means (13) Second safety circuit (14) (15) Normal control circuit (16) First normal control circuit (17) Second normal control circuit (18) Switching means (19) Safety circuit (21) Rail (22) Substrate (23) Support plate (24) Take-up drum (24a) Drum shaft (25) Flanged roller (26) Roller (27) Suspended belt (28) Underframe (29) Gear (30) Motor (31) Output gear (32) Suspension rod (33) Proximity sensor (34) Locking pin (35) Holding plate (36) Suspension support (37) Compression spring (38) ) Sensing piece (39) High friction layer (40) Pulley (41) Endless belt (42) Motor (43) Belt conveyor (44) Guide shelf (46) Photoelectric sensor (46a) Light emitting element (46b) Light receiving element (47) Roller conveyor (50) Rotary rack (51) Load transfer device (52) Support frame (53) Pallet (54) Post (55) Pusher (56) Load extrusion device (5 7) Support (58) Ejector

Claims (11)

【特許請求の範囲】[Claims] 【請求項1】 荷の受渡しを行なうステーションと、こ
のステーションに対して昇降しうるようにした荷台との
少なくともいずれか一方に、前記ステーション側から荷
台側に向けて荷を搬送しうる搬送装置を設けた荷移載装
置における制御装置であって、 前記荷台における前記ステーションに近い方の端部寄り
に設けられ、かつ荷が通過したことを検知する第1セン
サと、この第1センサが、荷が通過したことを検知する
ことにより、前記搬送装置の作動を停止させる通常制御
回路とを備えることを特徴とする荷移載装置における制
御装置。
1. A transfer device capable of transferring a load from the station side to the load side, to at least one of a station for delivering and receiving the load and a load platform that can be moved up and down with respect to the station. A control device in the provided load transfer device, wherein the first sensor is provided near the end of the loading platform near the station and detects that a load has passed; And a normal control circuit for stopping the operation of the conveying device by detecting that the carrier has passed.
【請求項2】 荷台におけるステーションから遠い方の
端部より若干内方寄りに設けられ、かつ荷の先端が到達
したことを検知する第2センサと、この第2センサが、
荷の先端が到達したことを検知することにより、搬送装
置の作動を停止させる第1安全回路とを備えることを特
徴とする請求項1記載の荷移載装置における制御装置。
2. A second sensor, which is provided slightly inward of the end of the loading platform farther from the station and detects when the tip of the load has reached, and the second sensor,
The control device in the load transfer device according to claim 1, further comprising: a first safety circuit that stops the operation of the transfer device by detecting that the front end of the load has arrived.
【請求項3】 荷台におけるステーションから遠い方の
端部寄りに設けられ、かつ荷の先端が到達したことを検
知する第3センサと、この第3センサが、荷の先端が到
達したことを検知することにより、搬送装置の作動を停
止させるとともに、警報手段を作動させる第2安全回路
とを備えることを特徴とする請求項1又は2記載の荷移
載装置の制御装置。
3. A third sensor provided near the end of the loading platform farther from the station and detecting the arrival of the tip of the load, and the third sensor detecting that the tip of the load has arrived. The control device for the load transfer device according to claim 1 or 2, further comprising: a second safety circuit that stops the operation of the transfer device and operates the alarm means.
【請求項4】 昇降しうる荷台の両側方に、荷の受渡し
を行なうステーションを配置し、かつ前記荷台又はステ
ーションに、荷を各ステーション側から荷台側に向けて
搬送しうる搬送装置を設けた荷移載装置における制御装
置であって、 前記荷台の両端部寄りに設けられ、かつ荷が通過したこ
とを検知する1対の第1センサと、該第1センサが、荷
が通過したことを検知することにより、前記搬送装置の
作動を停止させる通常制御回路とを備えることを特徴と
する荷移載装置における制御装置。
4. Stations for delivering loads are arranged on both sides of a load platform that can move up and down, and a transport device that can transport a load from each station side to the load platform side is provided on the load platform or the stations. A control device in a load transfer device, wherein a pair of first sensors, which are provided near both ends of the loading platform and detect that a load has passed, and the first sensor, A control device for a load transfer device, comprising: a normal control circuit for stopping the operation of the transfer device by detecting the operation.
【請求項5】 昇降しうる荷台の両側方に、荷の受渡し
を行なうステーションを配置し、かつ前記荷台又はステ
ーションに、荷を各ステーション側から荷台側に向けて
搬送しうる搬送装置を設けた荷移載装置における制御装
置であって、 前記荷台の両端部寄りに設けられ、かつ荷が通過中であ
ること、又は荷が通過したことを検知する1対の第1セ
ンサと、荷台における前記1対の第1センサより若干内
方寄りの部分に設けられ、かつ荷が到達したことを検知
する1対の第2センサと、いずれか一方の第1センサ
が、荷が通過中であることを検出しているか、又は荷が
通過したことを検知した後、前記一方の第1センサから
遠い方の第2センサが、荷が到達したことを検知するこ
とにより、前記搬送装置の作動を停止させる通常制御回
路とを備えることを特徴とする荷移載装置における制御
装置。
5. Stations for transferring loads are arranged on both sides of a load platform that can move up and down, and a carrier device that can transport a load from each station side to the load platform side is provided on the load platform or the stations. A control device in a load transfer device, comprising a pair of first sensors that are provided near both ends of the loading platform and that detect that a load is passing or that a load has passed, and the pair of first sensors in the loading platform. A pair of second sensors provided at a portion slightly inward of the pair of first sensors and detecting arrival of the load, and one of the first sensors is passing the load. Of the load is detected or the load has passed, and then the second sensor farther from the one first sensor detects that the load has arrived, thereby stopping the operation of the carrier device. Normal control circuit Controller in goods loader, characterized in that to obtain.
【請求項6】 昇降しうる荷台の両側方に、荷の受渡し
を行なうステーションを配置し、かつ前記荷台又はステ
ーションに、荷を各ステーション側から荷台側に向けて
搬送しうる搬送装置を設けた荷移載装置における制御装
置であって、 前記荷台の両端部寄りに設けられ、かつ荷が通過中であ
ること、及び荷が通過したことを検知する1対の第1セ
ンサと、荷台における前記1対の第1センサより若干内
方寄りの部分に設けられ、かつ荷が到達したことを検知
する1対の第2センサと、いずれか一方の第1センサ
が、荷が通過したことを検知することにより、前記搬送
装置の作動を停止させる第1通常制御回路と、いずれか
一方の第1センサが、荷が通過中であることを検知して
いるか、又は荷が通過したことを検知した後、前記一方
の第1センサから遠い方の第2センサが、荷が到達した
ことを検知することにより、前記搬送装置の作動を停止
させる第2通常制御回路とを備えることを特徴とする荷
移載装置における制御装置。
6. Stations for delivering a load are arranged on both sides of a load platform that can move up and down, and a transport device that can transport a load from each station side to the load platform side is provided on the load platform or the station. A control device in a load transfer device, comprising a pair of first sensors which are provided near both ends of the loading platform and which detect that a load is passing and that the load has passed; A pair of second sensors provided at a portion slightly inward of the pair of first sensors and detecting that the load has arrived, and one of the first sensors detects that the load has passed. By doing so, the first normal control circuit that stops the operation of the transport device and the first sensor of either one of them detect that the load is passing, or detect that the load has passed. After the first of the one Farther second sensor from capacitors is, by detecting that the load has reached, the control device in the goods loader, characterized in that it comprises a second usual control circuit for stopping the operation of the conveying device.
【請求項7】 第1通常制御回路の作動を、有効とした
り無効としたりしうる切換手段を設けてなる請求項6記
載の荷移載装置における制御装置。
7. The control device for a load transfer device according to claim 6, further comprising switching means for enabling or disabling the operation of the first normal control circuit.
【請求項8】 各第1センサを、荷の少なくとも一部が
到達したこと、及び荷が通過中であることを検知する機
能を有するものとし、かついずれか一方の第1センサ
が、荷が通過中であることを検知しており、かつ他方の
第1センサが、荷の少なくとも一部が到達したことを検
知することにより、搬送装置の作動を停止させるととも
に、警報手段を作動させる安全回路を設けたことを特徴
とする請求項4〜7のいずれかに記載の荷移載装置にお
ける制御装置。
8. Each of the first sensors has a function of detecting that at least a part of the load has arrived and that the load is passing, and one of the first sensors has a function of detecting the load. A safety circuit that detects the passage of the vehicle and detects that at least a part of the load has arrived by the other first sensor, thereby stopping the operation of the transport device and operating the alarm means. The control device in the load transfer device according to any one of claims 4 to 7, further comprising:
【請求項9】 各センサを、荷の搬送方向と直交する荷
台の両側部に対向して設けられた発光素子と受光素子と
からなる光電センサとした請求項1〜8のいずれかに記
載の荷移載装置における制御装置。
9. The photoelectric sensor according to claim 1, wherein each sensor is a photoelectric sensor composed of a light emitting element and a light receiving element which are provided so as to oppose each other on both sides of a bed which is orthogonal to the load carrying direction. Control device in load transfer device.
【請求項10】 搬送装置を、荷台に設けられたベルト
コンベヤとした請求項1〜9のいずれかに記載の荷移載
装置における制御装置。
10. The control device for a load transfer device according to claim 1, wherein the transfer device is a belt conveyor provided on a loading platform.
【請求項11】 搬送装置を、ステーション側に設けら
れた荷押出し装置とした請求項1〜9のいずれかに記載
の荷移載装置における制御装置。
11. The control device for a load transfer device according to claim 1, wherein the transport device is a load pushing device provided on the station side.
JP6138893A 1994-06-21 1994-06-21 Control device in load transfer device Expired - Fee Related JP2729921B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6138893A JP2729921B2 (en) 1994-06-21 1994-06-21 Control device in load transfer device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6138893A JP2729921B2 (en) 1994-06-21 1994-06-21 Control device in load transfer device

Publications (2)

Publication Number Publication Date
JPH082651A true JPH082651A (en) 1996-01-09
JP2729921B2 JP2729921B2 (en) 1998-03-18

Family

ID=15232589

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6138893A Expired - Fee Related JP2729921B2 (en) 1994-06-21 1994-06-21 Control device in load transfer device

Country Status (1)

Country Link
JP (1) JP2729921B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009113909A (en) * 2007-11-05 2009-05-28 Yamatake Corp Conveying device
US7540598B2 (en) 2003-06-25 2009-06-02 Ricoh Company, Ltd. Liquid container, sub tank, liquid discharge apparatus, liquid supply apparatus, and imaging apparatus

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS56170113U (en) * 1981-04-28 1981-12-16
JPH05124721A (en) * 1991-10-31 1993-05-21 Rengo Co Ltd Transport method with storage conveyor

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS56170113U (en) * 1981-04-28 1981-12-16
JPH05124721A (en) * 1991-10-31 1993-05-21 Rengo Co Ltd Transport method with storage conveyor

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7540598B2 (en) 2003-06-25 2009-06-02 Ricoh Company, Ltd. Liquid container, sub tank, liquid discharge apparatus, liquid supply apparatus, and imaging apparatus
JP2009113909A (en) * 2007-11-05 2009-05-28 Yamatake Corp Conveying device

Also Published As

Publication number Publication date
JP2729921B2 (en) 1998-03-18

Similar Documents

Publication Publication Date Title
JP2016121001A (en) Article conveyance container lifting and lowering device
CN111908097B (en) Control method of material feeding and discharging conveying equipment and material feeding and discharging conveying equipment
CN109264553B (en) Goods lift that can load and unload goods automatically
JPH082651A (en) Controller for load transfer device
JP2529523B2 (en) Transfer equipment
CN109795394A (en) Swing lift railway platform, swing lift system and handling method
JP2017030884A (en) Pallet separating facility
JPS6015302A (en) Detector for loading of goods and for abnormal condition such as slide-down of goods
JP2020121867A (en) Conveyance system
JP3568021B2 (en) Conveyor device
JPH11189305A (en) Article transferring device
JP3094840B2 (en) Sorting equipment
KR100581623B1 (en) Parking apparatus for solving a transfer failure of a pallet due to an elevation difference between a lift and a cart and method for controlling a pallet transfer
JPS6265823A (en) Storage device for article to be conveyed
JP3428911B2 (en) Article storage facility
JP2006213442A (en) Article conveying facility
JP2003089407A (en) Temporary storing device for articles
JP2514540B2 (en) Vertical conveyor system
JPS60137725A (en) Loaded pallet shipping installation
JP3622113B2 (en) Automatic warehouse
JPS6015306A (en) Conveying device
JP3489654B2 (en) Article transfer equipment
JP2003160226A (en) Cargo handling device
JP3287160B2 (en) Stacking device
JP2000272719A (en) Commodity storage facility

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19971118

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20071219

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081219

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091219

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091219

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101219

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101219

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111219

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111219

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121219

Year of fee payment: 15

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121219

Year of fee payment: 15

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131219

Year of fee payment: 16

LAPS Cancellation because of no payment of annual fees