JPH08232232A - Method for attaching cutoff wall to sluice - Google Patents

Method for attaching cutoff wall to sluice

Info

Publication number
JPH08232232A
JPH08232232A JP3578495A JP3578495A JPH08232232A JP H08232232 A JPH08232232 A JP H08232232A JP 3578495 A JP3578495 A JP 3578495A JP 3578495 A JP3578495 A JP 3578495A JP H08232232 A JPH08232232 A JP H08232232A
Authority
JP
Japan
Prior art keywords
hole
gutter pipe
peripheral surface
vertical hole
embankment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP3578495A
Other languages
Japanese (ja)
Inventor
Noriyuki Arakawa
範行 荒川
Hiroyasu Ohama
博保 大濱
Satoshi Kawahara
聡 川原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kubota Corp
Original Assignee
Kubota Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kubota Corp filed Critical Kubota Corp
Priority to JP3578495A priority Critical patent/JPH08232232A/en
Publication of JPH08232232A publication Critical patent/JPH08232232A/en
Pending legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Revetment (AREA)

Abstract

PURPOSE: To enable construction to be achieved with the use of a small vertical hole and to enable the range wherein an embankment is dug open to be reduced. CONSTITUTION: To attach a planar cutoff wall 5 to a sluice 1 buried in an embankment 2, a local part of the embankment 2 is dug to form a vertical hole 9, inside which the cutoff wall 5 with a through hole 6 formed in its center is installed. The sluice 1 is laid in the embankment 2 by propulsion method and passed through the through hole 6 in the cutoff wall 5, and a seepage- stopping ring 8 having elasticity and split into halves is fitted around the outer peripheral surface of the sluice 1 inside the vertical hole 9 and is pressed in between the inner peripheral surface of the through hole 6 and the outer peripheral surface of the sluice 1 by moving in the direction of the axis 10, after which the vertical hole 9 is backfilled. Since concrete is not placed as in conventional cases but the planar cutoff wall 5 is buried, a space to provide concrete forms and hence a space to remove the forms are not required.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、堤防などに埋設される
樋管の周囲に設けられる遮水壁の取付方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of mounting a water blocking wall around a gutter pipe buried in a bank or the like.

【0002】[0002]

【従来の技術】従来、この種の樋管への遮水壁の取付方
法としては例えば図6に示すように、先ず、推進工法に
より樋管24を堤防21に敷設し、その後、堤防21を堀り開
いてコンクリート22を厚く打設することにより、遮水壁
23を樋管24の所定位置に形成していた。
2. Description of the Related Art Conventionally, as a method of attaching a water blocking wall to a gutter pipe of this type, for example, as shown in FIG. 6, first, a gutter pipe 24 is laid on the embankment 21 by a propulsion method, and then the embankment 21 is installed. By digging open and placing concrete 22 thickly, impermeable walls
23 was formed at a predetermined position of the gutter pipe 24.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、上記の
従来形式では、コンクリート22を厚く打設することによ
り遮水壁23を形成しているため、コンクリート22を打設
するに際し、コンクリート用の型枠を設けるスペースが
必要となり、さらに打設後、この型枠を取り除くための
スペースが必要となる。したがって遮水壁23の取付部の
堤防21を図6の仮想線イで示した広範囲にわたり堀り開
かねばならないといった問題があった。
However, in the above-mentioned conventional type, since the water-impervious wall 23 is formed by casting the concrete 22 thickly, when the concrete 22 is cast, the formwork for concrete is used. A space for installing the mold is required, and a space for removing the formwork after the driving is required. Therefore, there is a problem in that the embankment 21 at the mounting portion of the impermeable wall 23 must be dug over a wide area shown by the phantom line A in FIG.

【0004】本発明は上記問題を解決するもので、遮水
壁を取付ける際、堤防を堀り開く範囲を狭くすることが
でき、遮水壁と樋管との間のシールが容易かつ確実に行
える樋管への遮水壁の取付方法を提供することを目的と
するものである。
The present invention solves the above-mentioned problems, and when installing the impermeable wall, it is possible to narrow the range in which the dike is dug and open, and the seal between the impermeable wall and the gutter pipe can be easily and reliably performed. The purpose of the present invention is to provide a method of attaching a water blocking wall to a gutter pipe that can be performed.

【0005】[0005]

【課題を解決するための手段】上記問題を解決するため
に本発明における樋管への遮水壁の取付方法は、堤防に
埋設される樋管の周囲に平板状の遮水壁を取付けるに際
し、上記堤防の遮水壁設置場所を局所堀りして竪穴を形
成し、この竪穴内に、中央部に貫通孔を形成した遮水壁
を設置し、推進工法により樋管を堤防に敷設して遮水壁
の貫通孔に貫通させ、弾性を有しかつ環状に形成された
止水用輪体を上記竪穴内で樋管の外周面に外嵌し、この
止水用輪体を樋管の軸心方向に移動させて上記貫通孔の
内周面と樋管の外周面との間に押し込み、その後、上記
竪穴を埋め戻すものである。
In order to solve the above problems, the method of mounting the impermeable wall to the gutter pipe according to the present invention is to install a flat impermeable wall around the gutter pipe embedded in the dike. The local location of the impermeable wall of the above levees is dug to form a pit, and the impermeable wall with a through hole in the center is installed in this pit, and a gutter pipe is laid on the levee by the propulsion method. The water-blocking ring, which has elasticity and is formed in an annular shape, is fitted onto the outer peripheral surface of the gutter pipe inside the vertical hole, and the water-blocking ring is inserted into the gutter pipe. Is pushed in between the inner peripheral surface of the through hole and the outer peripheral surface of the gutter tube, and then the vertical hole is backfilled.

【0006】[0006]

【作用】上記構成によると、従来のように樋管を敷設し
たのちコンクリートを打設するのではなく、平板状の遮
水壁を埋設したのち樋管を遮水壁に貫通させるため、コ
ンクリート用の型枠を設けるスペースやこの型枠を取り
除くためのスペースは不要となり、したがって小さな竪
穴で施工でき、堤防を堀り開く範囲を狭くすることがで
きる。
[Advantage] According to the above construction, instead of laying a gutter pipe and then placing concrete as in the conventional case, a flat water impervious wall is buried and then the gutter pipe is pierced through the impermeable wall. The space for installing the formwork and the space for removing this formwork are not required, and therefore it is possible to construct with a small vertical hole, and to narrow the range of excavating the embankment.

【0007】また、止水用輪体を樋管に装着する前に、
推進工法により樋管を遮水壁の貫通孔に貫通させるた
め、樋管を容易に遮水壁の貫通孔に貫通させることがで
きる。その後、止水用輪体を遮水壁の貫通孔の内周面と
樋管の外周面との間に押し込むことにより、止水用輪体
が樋管の外周面と貫通孔の内周面とに密着するため、樋
管と遮水壁との間は確実にシールされる。
Before mounting the water stop ring on the gutter pipe,
Since the gutter pipe is penetrated through the through hole of the water shield wall by the propulsion method, the gutter pipe can be easily penetrated through the through hole of the water shield wall. After that, by pushing the water-stop ring between the inner peripheral surface of the through hole of the impermeable wall and the outer peripheral surface of the gutter pipe, the water stop ring becomes the outer peripheral surface of the gutter pipe and the inner peripheral surface of the through hole. Since it closely adheres to and, the space between the gutter pipe and the impermeable wall is reliably sealed.

【0008】[0008]

【実施例】以下、本発明の一実施例を図1〜図5に基づ
いて説明する。図4に示すように、1は堤防2に埋設さ
れる樋管であり、この樋管1は河川が増水したとき堤防
2からの溢水や堤防2の決壊を防止するために、増水し
た水を別の河川や排水処理場へ排水するためのものであ
る。上記樋管1は多数の管体3が接続されて構成されて
いる。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to FIGS. As shown in FIG. 4, reference numeral 1 denotes a gutter pipe buried in the dike 2. This gutter pipe 1 is used to prevent the overflow of the dike 2 and the collapse of the dike 2 when the river increases. It is for draining to another river or wastewater treatment plant. The gutter pipe 1 is configured by connecting a large number of pipe bodies 3.

【0009】上記樋管1の所定位置には、この樋管1の
外面に沿って形成される恐れのある水抜け道4に対して
邪魔板として機能する遮水壁5が取付けられている。図
1,図5に示すように、上記遮水壁5は、鋼板製であ
り、正面視で四角形の平板状に形成され、中央部に貫通
孔6を有している。この貫通孔6の径Aは上記樋管1の
外径Bよりも大きく設定され、樋管1が貫通孔6に貫通
した際、貫通孔6の内周面と樋管1の外周面との間には
隙間7が形成される。
At a predetermined position of the gutter pipe 1, a water blocking wall 5 functioning as a baffle plate is attached to a water escape passage 4 which may be formed along the outer surface of the gutter pipe 1. As shown in FIGS. 1 and 5, the impermeable wall 5 is made of a steel plate, is formed in a rectangular flat plate shape in a front view, and has a through hole 6 in the central portion. The diameter A of the through hole 6 is set to be larger than the outer diameter B of the gutter tube 1, and when the gutter tube 1 penetrates the through hole 6, the inner peripheral surface of the through hole 6 and the outer peripheral surface of the gutter tube 1 are separated from each other. A gap 7 is formed between them.

【0010】上記隙間7は止水用輪体8によりシールさ
れている。この止水用輪体8は、図1および図3に示す
ように、弾性を有するゴム材で環状に製作され、かつ外
周面がテーパ状に形成され、さらに軸心方向に沿って2
分割された一方の輪体片8aと他方の輪体片8bとから
成る半割り構造になっている。尚、止水用輪体8の一端
の外径Cは上記貫通孔6の径Aよりも小さく、止水用輪
体8の他端の外径Dは上記貫通孔6の径Aよりも大きく
形成されている。
The gap 7 is sealed by a water stop ring 8. As shown in FIGS. 1 and 3, the water blocking wheel 8 is made of an elastic rubber material in an annular shape and has an outer peripheral surface formed in a tapered shape.
It has a half-split structure composed of one ring piece 8a and the other ring piece 8b that are divided. The outer diameter C at one end of the water stop ring 8 is smaller than the diameter A of the through hole 6, and the outer diameter D at the other end of the water stop ring 8 is larger than the diameter A of the through hole 6. Has been formed.

【0011】これによると、先ず、図1に示すように、
堤防2の遮水壁設置場所を局所堀りして竪穴9を形成す
る。そして、この竪穴9内に遮水壁5を設置する。その
後、推進工法により管体3を継ぎ足しながら水平方向に
一方から他方へ順次圧入して、樋管1を堤防2に敷設す
るとともに遮水壁5の貫通孔6に貫通させる。この際、
貫通孔6の内周面と樋管1の外周面との間には隙間7が
形成されているため、樋管1を容易に遮水壁5の貫通孔
6に貫通させることができる。
According to this, first, as shown in FIG.
A vertical hole 9 is formed by locally excavating the place where the impermeable wall of the embankment 2 is installed. Then, the impermeable wall 5 is installed in the vertical hole 9. After that, the pipes 3 are replenished by the propulsion method while being sequentially pressed horizontally from one to the other to lay the gutter pipe 1 on the dike 2 and to penetrate the through hole 6 of the impermeable wall 5. On this occasion,
Since the gap 7 is formed between the inner peripheral surface of the through hole 6 and the outer peripheral surface of the gutter pipe 1, the gutter pipe 1 can be easily penetrated into the through hole 6 of the impermeable wall 5.

【0012】次に、竪穴9内に作業者が入り、図3に示
すように一方の輪体片8aと他方の輪体片8bとを樋管
1の外周面に当て付けることにより止水用輪体8を樋管
1の外周面にセットし、この止水用輪体8を樋管1の軸
心方向10に移動させて貫通孔6の内周面と樋管1の外周
面との間に押し込む。これにより、図2に示すように、
止水用輪体8が樋管1の外周面と貫通孔6の内周面とに
密着するため、樋管1と遮水壁5との間は確実にシール
される。この際、止水用輪体8の外周面がテーパー状に
形成されているため、止水用輪体8の小径側端部から貫
通孔6に押し込むことにより、止水用輪体8を容易に遮
水壁5と樋管1との間に押し込むことができ、さらにく
さび作用によりしっかりと食い込ませることができる。
その後、竪穴9を埋め戻す。
Next, an operator enters the vertical hole 9 and puts one wheel piece 8a and the other wheel piece 8b on the outer peripheral surface of the gutter pipe 1 to stop water as shown in FIG. The ring body 8 is set on the outer peripheral surface of the gutter pipe 1, and the water blocking ring body 8 is moved in the axial direction 10 of the gutter pipe 1 so that the inner peripheral surface of the through hole 6 and the outer peripheral surface of the gutter pipe 1 are separated from each other. Push in between. As a result, as shown in FIG.
Since the water stop ring 8 is in close contact with the outer peripheral surface of the gutter pipe 1 and the inner peripheral surface of the through hole 6, the gutter pipe 1 and the water blocking wall 5 are reliably sealed. At this time, since the outer peripheral surface of the water blocking wheel 8 is formed in a tapered shape, the water blocking wheel 8 can be easily pushed by pushing it into the through hole 6 from the small-diameter side end of the water blocking wheel 8. In addition, it can be pushed between the impermeable wall 5 and the gutter pipe 1, and can be firmly bitten by the wedge action.
Then, the vertical hole 9 is backfilled.

【0013】上記の方法によると、従来のように樋管を
敷設したのちコンクリートを打設するのではなく、平板
状の遮水壁5を埋設したのち樋管1を遮水壁5に貫通さ
せるため、コンクリート用の型枠を設けるスペースやこ
の型枠を取り除くためのスペースは不要となり、したが
って小さな竪穴9で施工でき、堤防2を堀り開く範囲を
狭くすることができる。
According to the above-mentioned method, instead of laying a gutter pipe and then placing concrete as in the conventional method, a flat water shield wall 5 is buried and then the gutter pipe 1 is passed through the water shield wall 5. Therefore, a space for providing a formwork for concrete and a space for removing this formwork are not required, and therefore construction can be performed with a small vertical hole 9 and the range in which the bank 2 is dug can be narrowed.

【0014】上記実施例では図3に示すように止水用輪
体8を一方の輪体片8aと他方の輪体片8bとから成る
2つ割り構造(半割り構造)にしているが、3つ割り以
上あるいは1つ割り構造であってもよい。また、分割構
造ではなく連続した止水用輪体8を用い、竪穴9内に樋
管1の先端部が突出した際に、この樋管1の先端部から
止水用輪体8を外嵌してもよい。
In the above-mentioned embodiment, as shown in FIG. 3, the water blocking wheel 8 has a split structure (half-split structure) consisting of one wheel piece 8a and the other wheel piece 8b. The structure may be divided into three or more or one structure. Moreover, when the tip portion of the gutter pipe 1 is projected into the vertical hole 9 by using a continuous water stop ring body 8 instead of the divided structure, the water stop ring body 8 is externally fitted from the tip portion of the gutter pipe 1. You may.

【0015】[0015]

【発明の効果】以上のように本発明によれば、従来のよ
うに樋管を敷設したのちコンクリートを打設するのでは
なく、平板状の遮水壁を埋設したのち樋管を遮水壁に貫
通させるため、コンクリート用の型枠を設けるスペース
やこの型枠を取り除くためのスペースは不要となり、し
たがって小さな竪穴で施工でき、堤防を堀り開く範囲を
狭くすることができる。
As described above, according to the present invention, instead of laying a gutter pipe and then placing concrete as in the prior art, a flat water shield wall is buried and the gutter pipe is used as a water shield wall. Since there is no need to provide a space for a concrete formwork or a space for removing this formwork, the construction can be performed with a small vertical hole, and the range in which the embankment is dug can be narrowed.

【0016】また、止水用輪体を樋管に装着する前に、
推進工法により樋管を遮水壁の貫通孔に貫通させるた
め、樋管を容易に遮水壁の貫通孔に貫通させることがで
きる。その後、止水用輪体を遮水壁の貫通孔の内周面と
樋管の外周面との間に押し込むことにより、止水用輪体
が樋管の外周面と貫通孔の内周面とに密着するため、樋
管と遮水壁との間は確実にシールされる。
Also, before mounting the water stop ring to the gutter pipe,
Since the gutter pipe is penetrated through the through hole of the water shield wall by the propulsion method, the gutter pipe can be easily penetrated through the through hole of the water shield wall. After that, by pushing the water-stop ring between the inner peripheral surface of the through hole of the impermeable wall and the outer peripheral surface of the gutter pipe, the water stop ring becomes the outer peripheral surface of the gutter pipe and the inner peripheral surface of the through hole. Since it closely adheres to and, the space between the gutter pipe and the impermeable wall is reliably sealed.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施例における樋管への遮水壁の取
付方法を説明するための側面図である。
FIG. 1 is a side view for explaining a method of attaching an impermeable wall to a gutter pipe according to an embodiment of the present invention.

【図2】同樋管への遮水壁の取付方法を説明するための
側面図である。
FIG. 2 is a side view for explaining a method of attaching the water blocking wall to the gutter pipe.

【図3】止水用輪体の正面図である。FIG. 3 is a front view of a water blocking wheel.

【図4】樋管および遮水壁が埋設された堤防の断面図で
ある。
FIG. 4 is a cross-sectional view of an embankment in which a gutter pipe and an impermeable wall are buried.

【図5】図4におけるX−X矢視図である。5 is a view on arrow XX in FIG. 4. FIG.

【図6】従来例における樋管および遮水壁が埋設された
堤防の断面図である。
FIG. 6 is a cross-sectional view of an embankment in which a gutter pipe and an impervious wall are buried in a conventional example.

【符号の説明】[Explanation of symbols]

1 樋管 2 堤防 5 遮水壁 6 貫通孔 8 止水用輪体 9 竪穴 10 軸心方向 1 Gutter pipe 2 Levee 5 Impermeable wall 6 Through hole 8 Water stop ring 9 Vertical hole 10 Axial direction

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 堤防に埋設される樋管の周囲に平板状の
遮水壁を取付けるに際し、上記堤防の遮水壁設置場所を
局所堀りして竪穴を形成し、この竪穴内に、中央部に貫
通孔を形成した遮水壁を設置し、推進工法により樋管を
堤防に敷設して遮水壁の貫通孔に貫通させ、弾性を有し
かつ環状に形成された止水用輪体を上記竪穴内で樋管の
外周面に外嵌し、この止水用輪体を樋管の軸心方向に移
動させて上記貫通孔の内周面と樋管の外周面との間に押
し込み、その後、上記竪穴を埋め戻すことを特徴とする
樋管への遮水壁の取付方法。
1. When installing a plate-shaped impermeable wall around a gutter pipe to be buried in a levee, a vertical hole is formed by locally digging the location of the impermeable wall of the levee, and a central hole is formed in the vertical hole. An impermeable wall with an elastic ring formed by installing a water barrier with a through hole in the section and laying a gutter pipe on the embankment by the propulsion method to penetrate the through hole of the water barrier. Is fitted on the outer peripheral surface of the gutter pipe in the vertical hole, and the water blocking ring is moved in the axial direction of the gutter pipe to be pushed between the inner peripheral surface of the through hole and the outer peripheral surface of the gutter pipe. After that, a method of attaching the impermeable wall to the gutter pipe, which is characterized by backfilling the vertical hole.
JP3578495A 1995-02-24 1995-02-24 Method for attaching cutoff wall to sluice Pending JPH08232232A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3578495A JPH08232232A (en) 1995-02-24 1995-02-24 Method for attaching cutoff wall to sluice

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3578495A JPH08232232A (en) 1995-02-24 1995-02-24 Method for attaching cutoff wall to sluice

Publications (1)

Publication Number Publication Date
JPH08232232A true JPH08232232A (en) 1996-09-10

Family

ID=12451536

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3578495A Pending JPH08232232A (en) 1995-02-24 1995-02-24 Method for attaching cutoff wall to sluice

Country Status (1)

Country Link
JP (1) JPH08232232A (en)

Similar Documents

Publication Publication Date Title
JPH08232232A (en) Method for attaching cutoff wall to sluice
CN105970961B (en) A kind of bored concrete pile goes along with sb. to guard him deep pit monitor and cuts piling method
JP3128458B2 (en) How to attach impermeable walls to gutter pipes
JP3128456B2 (en) How to attach impermeable walls to gutter pipes
KR940007311A (en) Construction method of slope slope
JPH03244799A (en) Large sectional tunnel structure and constucting method thereof
JP3128457B2 (en) How to attach impermeable walls to gutter pipes
JPH03275812A (en) Foundation construction method for soft sea bottom ground
JP3464114B2 (en) Installation method of impermeable wall of gutter pipe
CN218911599U (en) Water supply pipe protection structure
JP3880403B2 (en) Method and structure for preventing the formation of water pipes
CN210049358U (en) A drainage structures for abandoning sediment field bottom
JP2873333B2 (en) Ground injection method
JP3872885B2 (en) Derating structure of underground piping with mounting pipe
JP3489964B2 (en) Installation method of impermeable wall of gutter pipe
JP2007231530A (en) Cut-off wall structure of sluice pipe
JP3240394B2 (en) Construction method of impermeable wall
JPH02240397A (en) Water stopper at entrance in shield construction work
JPH11107256A (en) Cut-off wall for sluice way
JPS584031A (en) Construction of artitificial body divertible vertical pile in iron moor process
JPH1121892A (en) Construction method for water passage of sheathing wall with steel pipe columns and structure
JPH083515Y2 (en) pipe
JP2000170158A (en) Recharging method for underground stream intercepted by construction of linear underground structure
JPS5923829Y2 (en) Groundwater outflow prevention device for direction adjustment pipes for underground pipe construction work
JP2556130Y2 (en) Construction structure of backfill drainage material